PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 2 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
QUALITY OBJECTIVES
Page 3 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Therefore and in full respect with the industry professional code and
• Implement the Project Quality Plan and Quality Control Procedures and
objectives.
Page 4 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Table of Contents
SECTION-1 ........................................................................................................................................11
1-PQP DOCUMENT REVIEW .............................................................................................................11
1.1 DOCUMENT REVISION................................................................................................................12
1.1.1 REVISION TABLE ......................................................................................................................12
SECTION - 2.......................................................................................................................................13
2-SCOPE & DEFINITIONS ..................................................................................................................13
2.1 SCOPE .........................................................................................................................................14
2.2 DEFINITION AND INTERPRETATION ...........................................................................................14
2.2.1 INTERPRETATION ....................................................................................................................14
2.2.2 DEFINITIONS ............................................................................................................................17
SECTION 3 ...................................................................................................................................25
3-QA/QC ORGANIZATION & JOB DESCRIPTIONS..............................................................................25
3.1 JOB DESCRIPTION FOR QA/QC PERSONNEL ...............................................................................27
3.1.1 JOB DESCRIPTION FOR QA MANAGER ....................................................................................27
3.1.2 JOB DESCRIPTION FOR QC MANAGER.....................................................................................28
3.1.3 JOB DESCRIPTION FOR QA COORDINATOR .............................................................................30
3.1.4 JOB DESCRIPTION FOR QC SUPERVISOR .................................................................................31
3.1.5 JOB DESCRIPTION FOR QC INSPECTOR ...................................................................................33
3.1.6 JOB DESCRIPTION FOR QC TECHNICIAN ..................................................................................35
SECTION 4.........................................................................................................................................37
4-OVERVIEW OF THE PROJECT QUALITY MANAGEMENT SYSTEM (ISO 9001:2008 VERSION) ........37
4.1 COMPLIANCE ..............................................................................................................................38
4.1.1 NORMATIVE REFERENCE .........................................................................................................38
4.2 MANAGEMENT REVIEW .............................................................................................................38
4.3 MANAGEMENT COMMITMENT .................................................................................................40
4.4 RESPONSIBILITIES AND AUTHORITY ...........................................................................................40
4.5 PROJECT OBJECTIVES AND CONTINUAL IMPROVEMENT ...........................................................42
4.5.1 TOOLS TO MONITOR SMART...................................................................................................42
Page 5 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 9 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 10 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
SECTION-1
Page 11 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
2 1 12/04/10 Owner/Consultant
comments are
incorporated
Page 12 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
SECTION - 2
Page 13 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
2.1 SCOPE
The intent of this Project Quality Plan is to construct the Holy Mosque
Extension of King Abdullah Project in Shamiyah, Makkah in accordance
with the established International and Saudi Arabian Standards,
procedures, approved drawings, specifications and all applicable
regulatory requirements. This Project Quality Plan deals with the
procurement, field engineering, construction and commissioning phases
of the Project.
The purpose of PQP is to provide a simple but effective system for
controlling the quality of the works on this Project. Its basis is the
planning in advance of all QC activities and records to be kept and agreed
with all concerned parties before commencement of associated activities.
This PQP is applicable to all QA/QC items related to this Project.
SBG-ABCD has established and maintains this Project Quality Plan. It
identifies the scope of the Quality Management System and any exclusion
to the requirements of ISO 9001:2008. It includes procedures and
documents covering work activities as well as the sequences and
interactions of processes that fall under the scope of the Quality
Management System
It will be adopted by SBG-ABCD and all contractors/sub-contractors.
Exclusions are made for the clause “Design and Development” as Design
activities are being performed by the Consultant “Dar Al Handasah” and
by a subcontractor “FOCUS”.
2.2.1 INTERPRETATION
In this document, the following words and expressions could have the
following meaning as applicable and should be adapted to the words of
the Contract.
Page 14 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 15 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 16 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
2.2.2 DEFINITIONS
1. “Works”
“Works” means the obligations undertaken by the Contractor for all the
components of the Project pursuant to the Contract Documents. Works
shall include both Permanent Works and Temporary Works
3. “Drawings”
“Drawings” means, collectively, all the drawings listed in the Contract and
any modification of such drawings by the Architect and/or Interior
Designer and such supplementary drawings as from time may be
furnished or approved in writing by the Architect. The word Drawings
shall also be understood to include documents such as procedures,
calculations, manuals etc.
Page 17 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
5. “Contractor’s Schedule”
6. “Approved” or “Approval”
7. “Key Personnel”
8. “Bill of Quantities”
9. “Cost”
“Quality Control Procedures” are work guidelines that define how the
work should be carried out under different circumstances and by whom.
In addition, it explains the allocated responsibilities, authorities, inputs to
be used, and outputs aimed to be generated. Quality Control Procedure
also provides instructions related to control the specifications and
standards to ensure that specific quality requirements are actually being
Page 18 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
met on the Project and it also helps in the prevention of errors as well as
in the detection and correction of errors.
22. “Correspondence”
27. “Voucher”
“Full Traceability” means that the material or product is traceable from its
certification through records and material markings to its final location in
Page 21 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
the works.
“No Traceability” means that the material received in the Stores complies
with the Purchase Order, but neither test certificates nor letters of
conformity are supplied or required. The installation inspection record is
used as a proof that the material has been used for the intended purpose.
37. “Materials”
38. “Non-Conformance”
requirements.
40. “Dispositions”
Page 23 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
“Audit Report” means the summary of the findings and the conclusions of
the Audit, which include the Corrective and/ or Preventive Actions.
Page 24 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
SECTION 3
Page 25 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 26 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Main Responsibilities:
Note: These are main responsibilities & tasks; more will be added
during the execution of the Project as deemed necessary.
MAIN RESPONSIBILITIES:
problems on Site.
8 To ensure all testing and inspection are carried out and
approved prior to covering up.
9 To issue Non Conformance Report when necessary and to
follow-up for its agreed disposition in order to close out the NCR.
10 To manage QC staff and issues efficiently and effectively
wherever Quality matters are concerned.
11 To develop mutual understanding related to the QA/QC system,
QC inspections, administration of the system etc. with the
Construction and Consultant.
12 To coordinate with the Consultant in order to resolve Quality
related problems on Site.
13 To ensure proper coordination with approved Independent
Testing Laboratories to carry out the tests and proper reporting
of the same.
14 To ensure all tests / inspection reports are submitted to the
Consultant in time as per the specifications / ITP.
15 Daily meetings with the QA Manager to discuss QA / QC related
matters.
16 Weekly meetings with QC supervisor, QC staff related to QC
matters and problems to be resolved. And review the
effectiveness and improvement in Quality Control of the activity.
17 To review quality control report on a weekly basis and distribute
it to all concerned.
18 To ensure healthy and productive environment is developed
during interaction with other departments / SBG-ABCD.
19 To conduct training sessions / meetings regarding Quality
system and documents implementation on this Project, such as
PQP, ITP, NCR, Quality Procedures etc.
Page 29 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Main Responsibilities:
Note: These are main responsibilities & tasks; more will be added
during the execution of the Project as deemed necessary.
Main Responsibilities:
Note: These are main responsibilities & tasks; more will be added
during the execution of the Project as deemed necessary.
Page 32 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Main Responsibilities:
Note: These are main responsibilities & tasks; more will be added
during the execution of the Project as deemed necessary
Page 34 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Main Responsibilities:
Note: These are main responsibilities & tasks; more will be added
during the execution of the Project as deemed necessary.
Page 36 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
SECTION 4
Page 37 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.1 COMPLIANCE
B. Review Input
Page 39 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 40 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
F. Project Director
Establish the Site Organization.
Assign detailed work assignment to the Site personnel.
Control overall construction work including all support
functions related to Design, engineering, Project controls,
procurement, construction, Project interface, safety and
security. Overview the performance of the organization to
ensure it meets with the schedule requirements for the
Project.
Represent SBG-ABCD to the Client.
G. Construction Manager
Construction of the Project in conformance with the detailed
drawings and Contract Specification within the overall
schedule and cost parameters set for the Project.
Maintenance of all construction records.
Management of all personnel assigned to work under him.
Management and coordination of all subcontractors work at
the Site.
Responsible for schedule , quality and safety conformance.
H. Engineering Manager
Responsible to ensure that the Site construction has all the
technical information required to construct the Project such
as “approved” construction drawings, technical data as per
the established schedule.
Engineering Coordination.
Responsible for the development of requisitions related to
Design, & Engineering.
Ensure that all contract close-out submittals are made to the
Owner such as as-built, warranties, spare parts, maintenance
manuals, etc.
Page 42 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.5.1.2 MEASURABLE
The planning as detailed above in 4.3.1.1 will be measurable in line with
the Site progress and the overall Project planning. This also includes the
quality of the work, which is measured on the basis of number of NCR
issued, number of rejections, remedial works, abortive works, number of
rejected RFI returned back with ‘C’ status, Trend analysis of reasons for a
RFI rejections. etc.
The trends of such events will be discussed in weekly QA/QC meeting and
weekly meeting for NCR log in order to achieve improvement in that area.
4.5.1.3 ACHIEVABLE
This is more or less related to planning on basis of the available resources
and means in order to analyse the target considering all possible negative
effects / hindrances to achieve the goal.
4.5.1.4 REALISTIC
This is related to implementation and actual action by each department
This again refer to weekly meeting as detailed above in 4.3.1.1, where
the Project Director review and approves the monthly target for each
department. He may amend if the monthly planning / schedule is not
realistic.
Page 44 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
The overall planning and the actual progress is monitored by the planning
department which leads to the trend and highlights the area needs
improvement in order to complete the Project in time.
Data review and the analysis of possible problems are carried out as a
rule by the various departments in SBG-ABCD organization.
Page 45 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
The above data will be analyzed and submitted to Owner with a monthly
Quality Management Report.
4.7 IMPROVEMENT
1. Data analysis
2. Corrective action
3. Preventive action
Page 46 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4. Management review
5. Lessons learned
6. Process performance measures
7. Repeated violations
8. Internal and external Non conformities
9. Internal and external audits
10. Customer satisfaction
11. FIR rejection rate by Consultant compared to quality objective of less
than 3%
Page 47 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Risks to
Quality Internal
Objectives achieve Controls
Processes Measurements
Objectives
Contract Understand Inexperienced Internal Were contract
Review the Personnel Procedures requirements
requirement of Review, Failure List of met?
the Project and to understand Reference –
the Owner requirements appropriate
QMS Manual
Section
Mobilization Prepare for Subcontractors Internal Was Project
Design, and staff not Procedures schedule met?
Procurement, hired; Processes List of
Construction not controlled, Reference –
inexperienced appropriate
personnel, lack QMS Manual
of proper Section
resources
Design Progress Design Poor customer Internal Where
to appropriate information, Procedures technical
levels for review Inexperienced List of requirements of
personnel, Reference – the Contract
Failure to appropriate met and
understand QMS Manual submitted to
requirements Section the SBG-ABCD
for review on
time?
Page 48 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Risks to
Quality Internal
Objectives achieve Controls
Processes Measurements
Objectives
Procurement Procure Poorly defined Internal Was material
materials that requisitions, Procedures delivered on
meet customer Unqualified List of time? Was
requirements, supplier, poor Reference – material
budget and expediting, appropriate defective?
on-time poor inspection QMS Manual
delivery Section
Construction Meet the Incompetent Visual Was overall
customer’s workers; Inspection; non-conforman
stated inexperienced Non- ce percentage
expectations construction destructive acceptable?
with regard to supervisors; examination,
quality, cost, inappropriate Proper testing
aesthetics and working procedures
time. Internal conditions;
measurement abnormally
for the rejected stringent
RFI are minimize requirements;
(<3%) Lack of
accountability;
unclear HR
policies
4.10.1 GENERAL
A. SBG-ABCD has established the following documentation for its quality
management system:
1. Quality policy and quality objectives
2. This Project Quality Plan
3. Documented procedures
Page 50 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 52 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 53 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
appropriate records.
E. SBG-ABCD’s records that provide evidence of conformance to
requirements and of the effective operation of SBG-ABCD's quality
management system shall be identified, stored, protected, and
retained. Retrieval shall be controlled. The QCM along with the EM
is responsible for identifying the records to be retained, retention
time, disposal method, and for arranging for their protection and
controlled retrieval.
F. Electronic data will be controlled in accordance with the SBG-ABCD
relevant procedure.
G. Quality Records will be controlled, maintained, and filed in accordance
with the steps defined in the SBG-ABCD procedure “Control of
Quality Records”. The Project will file all documents as detailed in
the Project Filing System. Archiving of documents and retrieval
of the same has been specified in the SBG-ABCD procedures.
Archiving will be done once every 12 months. All Project records
will be maintained as per the contract requirement / Consultant
instructions
• RFI
• Calibration Certificates
• Standards being used on Site / Project
Page 55 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
L. When a file is complete, it will be removed from the working files and
stored in a Site archive. Access to completed files will only be by
permission of the QC Manager.
M. No original documents will be removed from the files. Photocopies
may be made by the office boy for reference.
N. If required infrastructure is available on the Project Site, all the
records can also be maintained on CIS (Construction Information
Systems) software system.
Page 56 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
The files will be held within the Project in order to prevent deterioration
due to effects of the environment, vermin or fire damage. The condition
of the files will be monitored continuously by the Store Keeper in order to
detect the onset of any potential deterioration at an early stage.
The original documents will be stored at the Site office under safe and
acceptable condition for ready reference and finally handed over to the
OWNER as per the agreed procedure.
4.10.4 CORRESPONDENCE
A. The Project will ensure effective control over incoming and outgoing
correspondence in accordance to SBG-ABCD procedures (see 4.6.2
above) Incoming documents will be date stamped and forwarded to
the Project Director for action/distribution as relevant. Outgoing
correspondence will be signed by the Project Director. Incoming
and outgoing correspondence logs will be maintained. All outgoing
correspondence, whether letters or faxes will be identified.
B. The document numbering and registration will be unique for the whole
Project and as such will be centralized in one computerized
Document Control System.
Page 58 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.11.2 RESPONSIBILITIES
A. The Store Keeper is responsible to inform the QA/QC Department of
the Al Haram Expansion Project for the arrival of any material to the
store or at any other location on Site and to complete the inspection
request fully and actually.
B. The Store Keeper is responsible for maintaining records of goods
arriving and leaving the Stores including damage report and
incomplete orders.
C. The Procurement Manager will inform the Stores of arrival of materials
from abroad, check for storage conditions and arrange
transportation to the Stores.
D. The QC Inspector (materials) will check the material prior to it is used
in the permanent works.
B) Conditions of Store
1 The Storekeeper will enter details of the goods received into the
appropriate register in the computer, indicating quantity, unit price, total
value, and date of receipt.
2 A Store Receipt Printout will be prepared for all items entering the
store.
3 A copy of the Store Receipt Printout together with a copy of the
Delivery Order or Invoice (original) will be forwarded to the concern
department as per SBG-ABCD procedure
4 All Store Receipt computer entries must clearly describe the goods
involved and include the arrival date of goods, suppliers name, invoice or
delivery order n°, details description, quantity, unit price etc.
Page 60 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
1 Where bulk materials such as road gravels, sand, sweet soil etc. are
delivered directly to Site for inclusion in the works, the Site Engineer will
obtain the Delivery Note from the driver and copy immediately to the
QA/QC department along with the material inspection form duly filled for
receipt inspection in accordance with Project Inspection and Testing
Procedures.
2 Following receipt of inspection the Delivery Note will be copied to
the Procurement Manager and Stores with the result of the inspection
accepted or rejected with reason.
3 Where rejected the signature of the driver should be obtained if
possible.
4 The use of such bulk material, time, location, levels etc.; will be
recorded in the daily Inspection Reports of the Works.
E) Rejected Materials
F) Issuing Goods
Page 61 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 62 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 65 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
• The “Submittal Log Sheet” that contains the submittal status per
type of document and requires approval (listing of transmitted
documents, date of expected/received approval).
• Analysis of the return times of documents from the
Consultant/supplier/etc to highlight any delays in returning documents
back to SBG-ABCD.
Page 67 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
A procedure is developed for ITP preparation and function. The ITP will be
developed for major activities on Site by the QA/QC Managers reviewed
and approved by the Consultant prior to implementation on this Project.
The list of the major activities is highlighted here after.
The ITP according to the list will be prepared along with the checklist and
formats (provided by the Consultant) and submitted to the Consultant for
approval prior to the commencement of activity on Site.
ITP and related completed forms are the quality records of the works and
are numbered and filed in accordance with the agreed index.
Training session will be held before the activity starts to all concern
specially the Construction by the QA/QC Managers, to introduce
thoroughly ITP functions, stages, requirements, formats, activities
involved in process, inspections, Hold points, witnessing, testing, role of
QC, coordination, planning works for inspection, Daily Inspection and
Testing program, submission, QA/QC requirements, Consultant
inspections, rectification of defects, re-inspection etc.
Page 69 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Sub Rev.
ITP No. Discipline Activity Description Status
Con No.
1 ITP-C-001 CIVIL Excavation
Cutting piles to cut-off
2 ITP-C-002 CIVIL
level
3 ITP-C-003 CIVIL Earthwork / Backfilling.
Cast –in –place concrete
4 ITP-C-004 CIVIL
for substructure
Installation of sub
5 ITP-C-005 CIVIL
structure waterproofing
Cast –in –place concrete
6 ITP-C-006 CIVIL
for superstructure
Fabrication of Curtain
7 ITP-A-007 Arch.
walls.
Installation of Curtain
8 ITP-A-008 Arch.
walls.
Delivery, storage,
9 ITP-A-009 Arch. handling and installation
of Pre-cast Panels.
Fabrication of structural
10 ITP-C-010 CIVIL
steel
Handling, Storage,
11 ITP-C-011 CIVIL Delivery and Installation
of Structural steel.
12 ITP-C-012 CIVIL Grouting
Fabrication and
13 ITP-C-013 CIVIL
Installation of Steel Deck
Construction and
14 ITP-A-014 Arch.
Installation of cladding
Page 70 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Sub Rev.
ITP No. Discipline Activity Description Status
Con No.
15 ITP-A-015 Arch. Masonry works
16 ITP-A-016 Arch. Plaster works
17 ITP-A-017 Arch. Ceramic Floor tiles
18 ITP-A-018 Arch. Ceramic wall tiles
19 ITP-A-019 Arch. Epoxy Flooring
20 ITP-A-020 Arch. Mosaic Tiles
21 ITP-A-021 Arch. False Ceiling
Supply and installation of
22 ITP-A-022 Arch. fabricated metalwork
e.g. handrails,
Supply and installation of
23 ITP-A-023 Arch.
fabricated wood decking
Supply and installation of
24 ITP-A-024 Arch.
building insulation
Supply and installation of
25 ITP-A-025 Arch.
fireproofing
Supply and installation of
26 ITP-A-026 Arch.
fire stopping material
Supply and installation of
27 ITP-A-027 Arch.
Gypsum Board Walls
Supply and installation of
28 ITP-A-028 Arch.
Gypsum Board Bulkheads
Installation of water
29 ITP-A-029 Arch. proofing to internal wet
areas and Plant room
30 ITP-A-030 Arch. Installation of carpets
Page 71 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Sub Rev.
ITP No. Discipline Activity Description Status
Con No.
31 ITP-A-031 Arch. Joinery Works
32 ITP-A-032 Arch. Hardware
33 ITP-A-033 Arch. Ironmongery
Supply and Application of
34 ITP-A-034 Arch.
External Painting
Supply and installation of
35 ITP-A-035 Arch.
internal Painting
Supply and installation of
36 ITP-A-036 Arch. roofing membrane. (
roofing works )
Supply and installation of
37 ITP-A-037 Arch.
sheet Metal roofing.
Supply and installation of
38 ITP-A-038 Arch.
Traffic coating.
Supply and installation of
39 ITP-C-039 CIVIL
Curbstone.
Interlock walkway /
40 ITP-A-040 Arch.
footpath.
Guniting / shotcreting
41 ITP-C-041 CIVIL
works.
42 ITP-A-042 Arch. Soft landscaping
43 ITP-A-043 Arch. Hard landscaping.
44 ITP-A-044 Arch. Traffic signs and markings
45 ITP-A-045 Arch. Lake works
Road paving / asphalt
46 ITP-C-046 CIVIL
works
Internal drainage
47 ITP-M-047 MEP
/waste/Vent System
Page 72 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Sub Rev.
ITP No. Discipline Activity Description Status
Con No.
External drainage/waste
48 ITP-M-048 MEP
/Vent System
Internal water supply
49 ITP-M-049 MEP
system
External water supply
50 ITP-M-050 MEP
system
Automatic Sprinkler
51 ITP-M-051 MEP
system
52 ITP-M-052 MEP Compressed air system
53 ITP-M-053 MEP LPG systems
54 ITP-M-054 MEP HVAC Duct system
HVAC chilled water
55 ITP-M-055 MEP
system
56 ITP-M-056 MEP Electrical lighting System
57 ITP-M-057 MEP Electrical power system
Building grounding
58 ITP-M-058 MEP
system
59 ITP-M-059 MEP Electrical Trunking System
60 ITP-M-060 MEP Telephone System
61 ITP-M-061 MEP Fire Alarm System
62 ITP-M-062 MEP Video System
63 ITP-M-063 MEP TV System
64 ITP-M-064 MEP Queuing System
Page 73 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
NOTE: Detailed Inspection & Test plan schedule will be developed and
maintained separately for all activities including those for
subcontractor. It will closely follow the Project specs requirements.
The QA/QC department will collect all the inspections and tests RFI from
the Construction and the sub-contractors and develop the “DAILY
INSPECTIONS AND TESTS PROGRAM”. Copy of the same will be sent to
the Consultant, construction managers, Engineering and Planning
department, Concrete Engineer, Independent testing lab, QA/QC
Supervisor, QC Inspectors, QC Technicians etc. as a minimum. The
“DAILY INSPECTIONS AND TESTS PROGRAM” will be submitted to the
Consultant not later than 14:30 hours for the next day inspections /
testing.
Mean while the construction will complete the work in accordance to the
inspection time on the RFI.
All RFI as received by the QA/QC department will be reviewed by the QC
Manager and marked to the relevant QC Inspector responsible for the
area of that RFI. The QA/QC Supervisor will immediately collect the RFI
from the QA/QC department after the review of QC Manager and
distributes the RFI to the relevant QA/QC inspection team.
progress. The Construction will advise the time, when the work will be
ready for QC inspections. Any deficiency / defect found will be
immediately notified to the concern personal (Site Engineer / Supervisor)
on Site for prompt action. The RFI attached sheet will be filled by the QC
Inspector, recording all the findings, deficiencies and handover the copy
of the same to the relevant responsible Site personal ( Site Engineer /
Supervisor ) for action. The deficiencies / comments pointed out by the
QC Inspector (in the presence of Construction) will be acknowledged by
the relevant responsible Site personal (Site Engineer / Supervisor) on the
original by signing and date / time written on the same.
The Construction will inform the QC Inspector when the work is ready for
re-inspections after attending all QC comments, the QC Inspector will
re-inspect the work, if the work is satisfactory, the QC Inspector will sign
off the RFI and inform accordingly to the QA/QC Supervisor to collect the
same for further action.
The QA/QC Supervisor will bring the RFI to the QA/QC department, where
the QC Manager will review the RFI and comments accordingly. The RFI
will then pass to QA/QC document controller, where he / she will register
the RFI and the reference number of the RFI will be allotted in accordance
to the building / area (separate RFI numbering system will be developed).
The RFI will then be submitted to the Consultant for formal inspection.
Copy of the same will be acknowledged by the Consultant and will be filed
in the relevant file by the QA/QC document controller.
the Consultant.
In case, if the work is not ready for inspection on the day scheduled, then
the Construction will inform QA/QC department, just revising the RFI
(cover sheet only) duly filled along with the new inspection time
(Submitted in the QA/QC department not later than 10: 00 hours). The
QA/QC department will send this new revised RFI to the relevant
Inspector after passing through the above procedure.
The QC Inspector will attach the revised RFI to the previous RFI
attachment and perform the inspections accordingly.
After the comments on the RFI by the Consultant, the original RFI will be
sent to the QA/QC department directly and the QA/QC document
controller will acknowledge the same and endorse the status or the RFI
received from the Consultant in the RFI register.
All RFI received will be given to the QC Manager for review and further
action. The QC Manager will mark the distribution of the commented RFI
to all concerned. A database (in excel/access) will be maintained by
QA/QC documents controller for the statistical analysis. At the end of the
month the QA Coordinator will prepare the statistical analysis of the
rejected RFI/Area/Inspector.
All original RFI will be retained by the QA/QC department. Only QA/QC
document controller and authorized personnel have access to the QA/QC
department files.
Page 76 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
The SBG-ABCD has a data bank system where all the evaluation sheets
are grouped together for consultation of a particular
supplier/subcontractor.
Local Purchase Orders (LPO) generated will ensure the following (with
particular emphasis on permanent work items)
The relevant ITP and formats approved for this Project will be used by all
suppliers and sub-contractors where applicable.
Page 78 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
The suppliers and the sub-contractor will have there own QA/QC team,
but, they will follow strictly all QC procedures and ITP (approved for this
Project) and will work under the direction of QC Manager where any
work / product / material involves quality issues.
4.20 PURCHASING
Page 79 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
procedures.
E. Project Vendor List for permanent works.
F. SBG-ABCD may purchase material, equipment and services only from
suppliers that are approved by the Owner as per the acceptable
procedures.
• They also list the Quality records and the material certifications to
be issued by the supplier. The supplier prepares the Inspection and
Test Plans (ITP) for approval by SBG-ABCD. The implementation
methods for the ITP are documented in the Project procedure titled
“Project Inspection Procedure”.
Page 80 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 81 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 83 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.21.3 INFRASTRUCTURE
The details of the temporary offices and facilities including software and
hardware requirements of the Project are addressed in the Project
Execution Plan.
To meet Quality Objectives and Project requirements, SBG-ABCD has
developed buildings, offices and space facilities. SBG-ABCD’s
infrastructure includes resources such as plant, workspace, tools and
equipment, support services, information and communication
technology, and transport facilities.
C. If any non-compliance found, the material will be sent back along with
the findings / comments or will be quarantined with HOLD tag for
further action.
D. Note: A separate procedure will be developed for “Concrete” supplied
by Ready mix concrete supplier.
Page 86 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
A. The Project Director will seek all the additional information required
when the characteristics of products supplied by the Client not
adequately specified in the Contract. In order to prevent any
subsequent dispute, deadlines of delivery, maintenance, and
storage terms will be defined in agreement with the Client to ensure
that they are in line with the conditions of execution of the Project
(as referred in QMSP-GEN-07).
4.23.1 PURPOSE
To describe the method used to ensure the following:
• The risks, consequences, and importance of non-conformities are
appropriately identified and recorded.
• The most appropriate disposition is proposed, agreed with the
Consultant and implemented accordingly.
• The results of such disposition are verified and recorded.
• To close all NCR promptly and in agreement with the Consultant.
4.23.2 SCOPE
A. This procedure applies to all non-conformities observed during the
Project processing up to the provisional acceptance.
B. This procedure describes the responsibilities in respect of the
identification, the documentation, the evaluation, the segregation
(where practical) and the disposition of non-conforming products,
and for notification to the affected parties.
C. NCR is equally valid for suppliers and sub-contractors also.
D. Individual procedures (e.g. ITP) will describe the responsibilities for
inspection, checking and testing activities, which mainly relates to
received material and to construction and installation processes.
During inspection / testing, the non-conforming product (if any) is
detected and identified / recorded.
E. Non-conformity with respect to specification, drawings, procedures,
submittals etc. related to the Project.
C. The QC Manager will review the report and coordinate with the concern
Construction Engineer and discuss the content of the
Non-conformity. Accordingly a QA/QC memo will be issued along
with the report to the concern Engineer for prompt action within
maximum 2 working days time.
D. IF the QC Manager finds the seriousness in the report. He will
immediately issue the NCR (form attached) along with the
complete report attached to the concern department. Copy of the
same to all concerned. A copy of the NCR will also be given to the
Consultant/Owner Representative (for information).
E. NCR-s shall be logged sequentially. The NCR shall specify the date,
time, building location, disciplines (Civil, Mechanical, Electrical and
etc.), the originator name and signature, type of the non
conformance, etc.
F. If the QC Manager finds the memo issued for the rectification of the
deficiencies / non-conformity within the time frame is not acted
upon, NCR will be raised for the same as detailed above.
G. NCR issued by the QA/QC department will have a unique reference
number registered with the QA/QC document controller.
H. Where practicable, the QC Inspector will arrange to have the affected
item(s) or Work clearly identified to prevent inadvertent work arise.
The means of identification will vary from situation to situation but
will involve the use of “HOLD” tags, paint, tape, segregation etc. or
any other method providing that the message is clear. The removal
of such marking by any person other than the QA/QC Department is
strictly prohibited.
I. Such segregation or marking, and the entry in the “Non Conformance
Log”, shall not be removed until formal disposition has been agreed
with the Consultant.
Page 89 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 90 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
Page 91 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.25.1 PURPOSE
To define the method used to:-
A. Determine the products which have to be identified or whose
traceability must be ensured in the Project
B. Define and implement the most appropriate Product Identification
Page 92 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.25.2 SCOPE
This procedure applies to all materials used in the permanent
works of the construction.
4.25.4 RESPONSIBILITIES
A. The QA/QC department will prepare the Identification and Traceability
Plan.
B. The QA/QC department is responsible for the maintenance of the
quality records relating to traceability (where required) of materials
incorporated into the works (including concrete test cubes, in-situ
compaction testing of soil reinforcement, concrete masonry blocks
testing etc.) Work inspection records as per the relevant ITP,
calibration certificate for testing and measuring equipments being
used on Site etc.
C. The Storekeeper will maintain the identification system within the
Stores together with the associated records. The Storekeeper will
maintain the identification records of materials from receipt,
delivery notes, vouchers etc. into the Stores until issue for
construction.
Page 93 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.25.5 METHODS
be quickly located.
B. Note ! The individual items will hold physical identification marking,
such as etching, stamping, labeling, painting etc., or any form of
indelible and permanent marking which can be traced back to the
installation / testing records and hence back to its certification.
C. On receipt, material requiring full traceability will have its unique
identification marking, verified by the QC Inspector against its
certificates of conformity or test certificates.
D. Whenever the material concerned can be subdivided, such as pressure
pipe work, structural steel plate, etc. for installation, fabrication,
any transfer of identification to the subdivided material will,
wherever possible, be performed prior to the subdivision. The Store
Keeper or Foreman in charge will ensure that all such transfers are
properly made.
E. The QC Inspector will record on the Material Inspection form the
unique identification number of the materials concerned.
4.25.5.4 NO TRACEABILITY
A. Where no traceability is required the Storekeeper will ensure that the
Page 95 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.26.1 PURPOSE
To define the methods used to ensure that measuring and test
equipment are:-
1. Identified.
2. Capable of reaching the required precision and are functionally
adequate.
3. Regularly and appropriately verified and maintained in good
working order.
4.26.2 SCOPE
This procedure applies to all inspection, measuring, and testing
equipment including the requirements of ISO/IEC 17025 for validation
and proficiency testing when and where required.
Page 96 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.27.2 CALIBRATION
Page 98 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.28.1.1 OBJECTIVE
To define the methods used so that:
A. Drawings and / or shop drawing as well as verification activities are
defined and appropriately assigned.
Page 99 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
B. The design and verification methods are carefully chosen and models
of output documents are adequately defined.
C. The design and / or shop drawings comply with the requirement of the
contract specifications and standards.
D. Subsequent modifications are appropriately controlled.
The present note deals with specific data for the Construction of the
design and / or shop drawings (structural and / or architectural), for this
Project. This is controlled by the Engineering and Planning department in
line with the contract. and should be part of this Project Quality Plan.
Specific procedure will be developed for the designers in order to have
same system and consistency in their performance.
4.28.3.2 REFERENCES
This paragraph must summarize all related references to be followed
4.28.3.3 DEFINITIONS
This paragraph must describe the measures to be taken
A. Calculation note
B. Request for information
Page 101 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
C. Technical note
D. Design Input
E. Design Output
4.28.3.4 RESPONSIBILITIES
Indicate the Design Manager when applicable.
4.28.3.5 ACTIONS
This paragraph must describe the measures to be taken
A. Language
B. Contents of a calculation note
C. Title block of a calculation note
D. Modifications in a calculation note
E. Request for information
F. Technical note
To be listed when all data are available. Following items will have to be
covered:-
A. Design Output data
B. Design Input data
C. List of reference documents
D. Elaboration of the drawings
E. Schedule of design deliverable documents
F. As-built drawings
A. Standards
B. Dimensions and scale
C. CAD layer system
D. Title block
Page 102 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.29.1 PURPOSE
A. Evaluation of the conformity or non-conformity of the Quality
Management System against the specified requirements
B. Evaluation of the effective implementation of the Quality System on
the Site
C. Collecting of all relevant information in order to impose the existing
Quality Management System.
4.29.2 SCOPE
This procedure details the method and means for carrying out an Internal
Quality Audit in line with the requirements of ISO 9001:2008 version (as
referred in QMSP-GEN-05).
4.29.3 PROCEDURE
4.29.3.5 REPORTING
A. The Audit will be summarized by the Internal Quality Auditor on an
Audit Report, which will be issued to the Auditee and the Project
Director. The report will contain the conclusion of the Audit, refer to
any findings, and identify any observations made during the audit.
Reports will be controlled and filed by the Internal Quality Auditor.
B. CARs will be recorded by the Internal Quality Auditor in the CAR log
together with the details of the response and close out times, etc.
Page 105 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.30.1 PURPOSE
The execution of a Project relies on the implementation of many
processes. Therefore, it is necessary to define the activities essential
for:-
4.30.2 SCOPE
This procedure applies to all processes implemented to carry out the
works.
form
ACTIVITY DESCRIPTION ITP FORM
no.
form
ACTIVITY DESCRIPTION ITP FORM
no.
form
ACTIVITY DESCRIPTION ITP FORM
no.
permission to pour 9
concrete
material receiving 22
daily report
SURVEYING 4
(SETTTING OUT)
NON-CONFORMANCE 27
REPORT
test confirmation 20
request for technical 1
approval
A treatment able to limit, in ITP-BA-CW advice of starting 3
some conditions that it is new activity
peculiar, the penetration of waterproofing test 17
rainwater (possibly other
test confirmation 20
liquids) into the supports on
which it is applied. test status list 21
waterproofing
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
request for technical 1
approval
The application of a bitumen ITP-AW-CW advice of starting 3
coating. Syn. With TARRING new activity
material receiving 22
daily report
road work 19
earth work 5
asphalt works
NON-CONFORMANCE 27
REPORT
material receiving 22
daily report
SURVEYING 4
(SETTTING OUT)
installation of curb stones ITP-IK-AW NON-CONFORMANCE 27
installation blocks to transfer level REPORT
Page 110 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
form
ACTIVITY DESCRIPTION ITP FORM
no.
form
ACTIVITY DESCRIPTION ITP FORM
no.
application for epoxy mortar ITP-EF-AW NON-CONFORMANCE 27
and painting according to REPORT
approved materials,
material receiving 22
documents & method
daily report
statement
epoxy flooring SURVEYING 4
(SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
installation and providing for ITP-FC-CW NON-CONFORMANCE 27
false ceiling tiles, Armstrong & REPORT
wire mesh according to material receiving
approved materials, 22
daily report
documents & method SURVEYING
false ceiling statement 4
(SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
installation and providing for ITP-IGBW-AW NON-CONFORMANCE 27
gypsum board partitions REPORT
according to approved material receiving
materials, documents &
22
installation of daily report
method statement SURVEYING
gypsum board 4
(SETTTING OUT)
walls request for technical 1
approval
advice of starting new 3
activity
fabrication and erection for ITP-IFMW-AW NON-CONFORMANCE 27
artificial windows and screens REPORT
metal works
material receiving 22
installation of daily report
fabricated SURVEYING 4
metal work (SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
Page 112 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
form
ACTIVITY DESCRIPTION ITP FORM
no.
fabrication and erection for ITP-PC-AW NON-CONFORMANCE 27
precast artificial stones, arch, REPORT
soffa and bodes according to
approved materials,
documents & method
material receiving 22
statement
daily report
precast SURVEYING
elements 4
(SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
factory inspection test 26
erection for raised floor over ITP-RF-AW NON-CONFORMANCE 27
MEP ducts according to REPORT
approved materials,
documents & method material receiving
statement 22
daily report
SURVEYING 4
raised floor (SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
factory inspection test 26
application for specified ITP-IPW-AW NON-CONFORMANCE 27
internal and external painting ITP-EPW-AW REPORT
according to approved
materials, documents & inspection request
method statement
material receiving 22
painting daily report
SURVEYING 4
(SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
form
ACTIVITY DESCRIPTION ITP FORM
no.
fabrication and erection of ITP-JW-AW NON-CONFORMANCE 27
wooden doors and joinery REPORT
according to approved
materials, documents & material receiving
method statement 22
daily report
wooden doors SURVEYING 4
and joinery (SETTTING OUT)
request for technical 1
approval
advice of starting new 3
activity
factory inspection test 26
form
ACTIVITY DESCRIPTION ITP FORM
no.
providing and erection for ITP-WDPS-MW request for technical 1
distribution water piping approval
system according to
approved materials, advice of starting
documents & method 3
new activity
statement
SURVEYING 4
water (SETTTING OUT)
distribution earth work 5
piping system utilities 18
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
fabrication and erection for ITP-MDS-MW request for technical 1
HVAC duct system according approval
to approved materials,
documents & method advice of starting
statement 3
new activity
SURVEYING 4
(SETTTING OUT)
HVAC duct earth work
system
5
utilities 18
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide and installation for ITP-CTFA-EW request for technical 1
cable trays and accessories approval
according to approved
materials, documents & advice of starting
cable tray method statement 3
new activity
fittings and SURVEYING
accessories 4
(SETTTING OUT)
earth work 5
utilities 18
Page 115 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
form
ACTIVITY DESCRIPTION ITP FORM
no.
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide and erection of ITP-BSSS-MW request for technical 1
building and standpipe approval
system according to
approved materials, advice of starting
documents & method 3
new activity
statement
SURVEYING 4
building (SETTTING OUT)
sprinkler and earth work
standpipe
5
utilities 18
system
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide and erection of low ITP-LVSSB-EW request for technical 1
voltage switchgear and approval
switchboards according to
approved materials,
documents & method
advice of starting 3
statement
new activity
SURVEYING 4
low voltage (SETTTING OUT)
switchgear and earth work
switchboards
5
utilities 18
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide roof drain and ITP-RDDP-MW request for technical 1
roof drain and drainage piping according approval
drainage piping to approved materials,
form
ACTIVITY DESCRIPTION ITP FORM
no.
documents & method advice of starting 3
statement new activity
SURVEYING 4
(SETTTING OUT)
earth work 5
utilities 18
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide above grade ITP-AGGFA-EW request for technical 1
conduit, fittings and approval
accessories according to
approved materials, advice of starting
documents & method 3
new activity
above grade statement
SURVEYING 4
conduit, fittings (SETTTING OUT)
and earth work 5
accessories test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
provide storm water ITP-SWDS-MW request for technical 1
drainage system according approval
to approved materials,
documents & method advice of starting
statement 3
new activity
storm water SURVEYING 4
(SETTTING OUT)
drainage earth work
system 5
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
form
ACTIVITY DESCRIPTION ITP FORM
no.
providing and installation of ITP-EBWEE-EW request for technical 1
electrical boxes and wire approval
ways according to
approved materials,
documents & method
advice of starting 3
statement
electrical boxes new activity
and wire ways SURVEYING 4
(SETTTING OUT)
(electrical earth work
enclosures) 5
test confirmation 20
material receiving 22
daily report
NON-CONFORMANCE 27
REPORT
4.30.4.5 Attachments:
G. Appendices
1. This will list and contain copies of any related forms etc. referred to in
the procedure.
2. The QA Manager and / or the submittal Engineer will liaise with all
relevant parties involved to establish how the work is to be done.
3. The QA Manager and / or the submittal Engineer will establish that the
current method of working is in compliant with the requirements of
ISO 9001 and the Contract.
4. Where it is compliant, the QA Manager and / or the submittal Engineer
will draft the procedure to reflect the existing practices.
5. Where it is not compliant the QA Manager and / or the submittal
Engineer will review the existing arrangements and in co-ordination
with the relevant parties involved will propose and develop measures
to bring the activity into compliance.
6. Once agreed with the personnel involved, the QA Manager and / or
submittal Engineer will draft the procedure to reflect the agreed
methods.
7. On completion of the draft Project Procedure, the submittal Engineer
will circulate it for comments to the managers concerned.
8. The submittal Engineer will review all comments received, with the
personnel involved, and agree to incorporate them or not.
9. Following incorporation of comments, the method submittal Engineer
will submit the Project Procedure to the Project Director for review and
approval.
10. Following the approval from PD, the submittal Engineer will
submit the procedure to the Consultant for review and formal approval
as per the approved transmittal system
11. The Consultant comments will be reviewed by the QA Manager and
concerned Managers and, when agreed, will be incorporated into the
procedure and resubmitted to the Consultant.
12. In case of any disagreement meeting will be called with the
Consultant to seek out the matter / issue.
13. When “approved with comments” status is obtained, the procedure
shall be formally issued for use by the authority of the Project Director
, together with details of the comments to be incorporated.
14. The registration and distribution control of Project Procedures will
be in accordance with the Document Control System.
4.32 TRAINING
B. Where agreed, the Project Director could enter the training into the
Project’s training program. The training program shall give the
following details:
1 Subjects
2 Instructors
3 Attendees
4 Date
5 Time
6 and will ensure that training is programmed to take place for the
particular skill
7 Knowledge required
C. The Project Director shall circulate the training program to the relevant
Managers.
D. Each manager will ensure that the person(s) assigned to attain the
training are instructed to attend as required.
D. Senior Staff
1 All senior staff will be assessed initially by the Project Director.
2 The relevant manager will carry out reassessment at the end of
each year. The report will be submitted to the Project Director for his
Page 125 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
comments and the final copy will be sent to the Administration Manager
for filing with the employee’s personal records.
3 If it is found necessary for the individual to attend courses to learn
any special skills, the type of training required will be identified on the
personal records. The Project Director will arrange the training if
required.
4 Records of training will be also filed with the personal records.
C. One of the tools for the assessment and training requirement is the
number of RFI rejection and repeated defects.
4.33.1 ENGINEERING
4.22.1.1 Procedure approval requirements
4.22.1.2 Management Review
4.22.1.3 Design Input and design basis control
4.22.1.4 Technical Interface control
4.22.1.5 Control of design output
Page 126 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
4.33.2 PROCUREMENT
4.22.2.1 Project organization end interfaces
4.22.2.2 Procedure approval requirements
4.22.2.3 Management Review
4.22.2.4 Technical interface control
4.22.2.5 Review of purchase requisitions
4.22.2.6 Approval / Appraiser of Sub-suppliers
4.22.2.7 Supplier Inspection & Test Plan review/approval
4.22.2.8 Review/Approval of Supplier
4.22.2.9 Waiver requests
4.22.2.10 Change Control
4.22.2.11 Controlling documents including customer supplied
drawings and documents
4.22.2.12 Testing and inspection Witness/release
4.22.2.13 Quality surveillance
4.22.2.14 Inspection/monitoring/reporting
4.22.2.15 Control and disposition of non-conformities
4.33.3 CONSTRUCTION
4.22.3.1 Mobilization
Construction
Tendering
Cost Value Reconciliation (CVR)
Purchase
Supplier-Subcontractor Approval Statement
Supplier-Subcontractor Evaluation Questionnaire
Subcontractor Performance Monitor
Supplier Performance Monitor
Quantity Surveying
Day work Sheet
Variation Schedule
Disruption Schedule
Certificate Status Report
Subcontractor Bid Summary
Variation Order
Subcontractor’s Final Statement of Account
Final Account Letter
Page 129 of 136
PROJECTQUALITY PLAN
HOLY MOSQUE EXTENSION OF KING ABDULLAH PROJECT Revision # 6
SHAMIYAH - MAKKAH Feb., 2011
I.T.
Records of Data Backed Up
I.T. Service Requisition
Admin
Request for Archiving / Retrieval of Documents
Request for Disposal of Documents
Contractors All Risks Insurance – Questionnaire & Proposal
Finance
Request for arranging Letter of Guarantee
Form of Performance Bond
Form of Retention Guarantee
Form of Advance Payment Guarantee
Request for arranging Letter of Credit
Marine Insurance – Import/Export Details
Project Cash Flow Projection
Staff Sharing Plan
Quality
Non Conformance Report Log
Internal Quality Audit Summary Report
Internal Quality Audit Checklist
Corrective Action Request
Corrective Action Request Log
Client Complaint Report
Client Complaint Log
Investigation Report
Application for External Training
Quality System Monitoring Checks
Internal Audit Schedule
Client Satisfaction Questionnaire
Internal Training Schedule
Internal Training Record
Training Proposal for the Year
Training Evaluation
Review for Training Effectiveness
Project Management
Site Instruction
Field Adjustment Form (FAF)
Field Adjustment Form Log
Request for Inspection (RFI) Log
Method Statement Cover Sheet
Method Statement Schedule
As Built Drawings Register
Document Approval Sheet
Daily Planning & Achievement Report
Weekly Planning & Achievement Report
Incoming Correspondence Register
Outgoing Correspondence Register
Project Monthly Report
Project Closeout Checklist
Plant
Plant Hire & Off-hire Request
Equipment Control Card
Breakdown Report
Personnel / Human Resources
Staff Joining Report
Leave Application Form
Passport Requisition Form
Asset Issue Form
Asset Return Form
Clearance for Staff
Personnel Requisition
Personnel Transfer Confirmation
Personnel Transfer Memo
Leave / Final Clearance for Workers
Worker’s Statement of Personal Belongings
Liaison Officer Services
The End
Page 136 of 136