Rate Analysis for Hume Pipes

Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP2 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 900.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
e) Labour charges for sand filling Rmt 26.67
Sub Total 1169.17
f) VAT @ 12.5% on (a) & (b) 120.63
g) Service Tax @ 12.24% on (d) & (e) 15.20
h) Transportation @ 10% on (a) & (b) 96.50
Sub Total 1401.49
i) Add 15% for Overheads & Profit 210.22
Grand Total for 3.00 M Rs. 1611.71
Cost for 1.00 Rmt Rs. 537.24
Say Rs. 540.00
Say Rs. 540.00 / Rmt

2 Providing & laying NP2 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 1620.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 177.00
e) Labour charges for sand filling Rmt 43.00
Sub Total 2089.00
f) VAT @ 12.5% on (a) & (b) 217.50
g) Service Tax @ 12.24% on (d) & (e) 26.93
h) Transportation @ 10% on (a) & (b) 174.00
Sub Total 2507.43
i) Add 15% for Overheads & Profit 376.11
Grand Total for 3.00 M Rs. 2883.54
Cost for 1.00 Rmt Rs. 961.18
Say Rs. 960.00
Say Rs. 960.00 / Rmt

3 Providing & laying NP2 Class 600mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 3000.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 229.50
e) Labour charges for sand filling Rmt 61.67
Sub Total 3656.17

Page 1
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate


f) VAT @ 12.5% on (a) & (b) 397.50
g) Service Tax @ 12.24% on (d) & (e) 35.64
h) Transportation @ 10% on (a) & (b) 318.00
Sub Total 4407.31
i) Add 15% for Overheads & Profit 661.10
Grand Total for 3.00 M Rs. 5068.40
Cost for 1.00 Rmt Rs. 1689.47
Say Rs. 1690.00
Say Rs. 1,690.00 / Rmt

4 Providing & laying NP2 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 4380.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 375.00
e) Labour charges for sand filling Rmt 108.33
Sub Total 5368.33
f) VAT @ 12.5% on (a) & (b) 570.00
g) Service Tax @ 12.24% on (d) & (e) 59.16
h) Transportation @ 10% on (a) & (b) 456.00
Sub Total 6453.49
i) Add 15% for Overheads & Profit 968.02
Grand Total for 3.00 M Rs. 7421.52
Cost for 1.00 Rmt Rs. 2473.84
Say Rs. 2475.00
Say Rs. 2,475.00 / Rmt

5 Providing & laying NP2 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 487.50
e) Labour charges for sand filling Rmt 250.00
Sub Total 8387.50
f) VAT @ 12.5% on (a) & (b) 862.50
g) Service Tax @ 12.24% on (d) & (e) 90.27
h) Transportation @ 10% on (a) & (b) 690.00
Sub Total 10030.27
i) Add 15% for Overheads & Profit 1504.54
Grand Total for 3.00 M Rs. 11534.81
Cost for 1.00 Rmt Rs. 3844.94
Say Rs. 3845.00
Say Rs. 3,845.00 / Rmt

Page 2
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate

Lowering, laying and jointing true to line and level RCC Hume pipes (NP-3
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP3 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 1320.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 180.00
e) Labour charges for sand filling Rmt 26.67
Sub Total 1671.67
f) VAT @ 12.5% on (a) & (b) 173.13
g) Service Tax @ 12.24% on (d) & (e) 25.30
h) Transportation @ 10% on (a) & (b) 138.50
Sub Total 2008.59
i) Add 15% for Overheads & Profit 301.29
Grand Total for 3.00 M Rs. 2309.88
Cost for 1.00 Rmt Rs. 769.96
Say Rs. 770.00
Say Rs. 770.00 / Rmt

2 Providing & laying NP3 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 2940.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 225.00
e) Labour charges for sand filling Rmt 43.00
Sub Total 3457.00
f) VAT @ 12.5% on (a) & (b) 382.50
g) Service Tax @ 12.24% on (d) & (e) 32.80
h) Transportation @ 10% on (a) & (b) 306.00
Sub Total 4178.30
i) Add 15% for Overheads & Profit 626.75
Grand Total for 3.00 M Rs. 4805.05
Cost for 1.00 Rmt Rs. 1601.68
Say Rs. 1600.00
Say Rs. 1,600.00 / Rmt

Page 3
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate

3 Providing & laying NP3 Class 600mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 3720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 292.50
e) Labour charges for sand filling Rmt 61.67
Sub Total 4439.17
f) VAT @ 12.5% on (a) & (b) 487.50
g) Service Tax @ 12.24% on (d) & (e) 43.35
h) Transportation @ 10% on (a) & (b) 390.00
Sub Total 5360.02
i) Add 15% for Overheads & Profit 804.00
Grand Total for 3.00 M Rs. 6164.02
Cost for 1.00 Rmt Rs. 2054.67
Say Rs. 2055.00
Say Rs. 2,055.00 / Rmt

4 Providing & laying NP3 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6600.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 472.50
e) Labour charges for sand filling Rmt 108.33
Sub Total 7685.83
f) VAT @ 12.5% on (a) & (b) 847.50
g) Service Tax @ 12.24% on (d) & (e) 71.09
h) Transportation @ 10% on (a) & (b) 678.00
Sub Total 9282.43
i) Add 15% for Overheads & Profit 1392.36
Grand Total for 3.00 M Rs. 10674.79
Cost for 1.00 Rmt Rs. 3558.26
Say Rs. 3560.00
Say Rs. 3,560.00 / Rmt

5 Providing & laying NP3 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 10800.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 645.00
e) Labour charges for sand filling Rmt 250.00

Page 4
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own
arrangements for procuring water for testing).

Sl. No. Item Unit Rate


Sub Total 12625.00
f) VAT @ 12.5% on (a) & (b) 1372.50
g) Service Tax @ 12.24% on (d) & (e) 109.55
h) Transportation @ 10% on (a) & (b) 1098.00
Sub Total 15205.05
i) Add 15% for Overheads & Profit 2280.76
Grand Total for 3.00 M Rs. 17485.81
Cost for 1.00 Rmt Rs. 5828.60
Say Rs. 5830.00
Say Rs. 5,830.00 / Rmt

Note : Labour cost for laying & jointing


adopted from KUWSDB 1999-2000 as basis.

Page 5
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own arrangements
for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP2 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 900.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
e) Labour charges for sand filling Rmt 53.33
Sub Total 1195.83
g) Transportation @ 10% on (a) & (b) 96.50
Sub Total 1292.33
f) WCT @ 4% on sub total 51.69
Sub Total 1344.03
h) Add 15% for Overheads & Profit 201.60
Grand Total for 3.00 M Rs. 1545.63
Cost for 1.00 Rmt Rs. 515.21
Say Rs. 515.00
Say Rs. 515.00 / Rmt

2 Providing & laying NP2 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 1620.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 177.00
e) Labour charges for sand filling Rmt 86.00
Sub Total 2132.00
g) Transportation @ 10% on (a) & (b) 174.00
Sub Total 2306.00
f) WCT @ 4% on sub total 92.24
Sub Total 2398.24
h) Add 15% for Overheads & Profit 359.74
Grand Total for 3.00 M Rs. 2757.98
Cost for 1.00 Rmt Rs. 919.33
Say Rs. 920.00
Say Rs. 920.00 / Rmt

3 Providing & laying NP2 Class 600mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 3000.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 229.50
e) Labour charges for sand filling Rmt 123.33
Sub Total 3717.83
g) Transportation @ 10% on (a) & (b) 318.00
Sub Total 4035.83
f) WCT @ 4% on sub total 161.43
Sub Total 4197.27
h) Add 15% for Overheads & Profit 629.59
Grand Total for 3.00 M Rs. 4826.86
Cost for 1.00 Rmt Rs. 1608.95
Say Rs. 1610.00
Say Rs. 1,610.00 / Rmt

4 Providing & laying NP2 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 4380.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 375.00
e) Labour charges for sand filling Rmt 216.67
Sub Total 5476.67
g) Transportation @ 10% on (a) & (b) 456.00
Sub Total 5932.67
f) WCT @ 4% on sub total 237.31
Sub Total 6169.97
h) Add 15% for Overheads & Profit 925.50
Grand Total for 3.00 M Rs. 7095.47
Cost for 1.00 Rmt Rs. 2365.16
Say Rs. 2365.00
Say Rs. 2,365.00 / Rmt

5 Providing & laying NP2 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 487.50
e) Labour charges for sand filling Rmt 500.00
Sub Total 8637.50
g) Transportation @ 10% on (a) & (b) 690.00
Sub Total 9327.50
f) WCT @ 4% on sub total 373.10
Sub Total 9700.60
h) Add 15% for Overheads & Profit 1455.09
Grand Total for 3.00 M Rs. 11155.69
Cost for 1.00 Rmt Rs. 3718.56
Say Rs. 3720.00
Say Rs. 3,720.00 / Rmt
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-3
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test to the required pressure equal
to 2.10 times the working pressure (Contractor will make his own arrangements
for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP3 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 1320.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 180.00
e) Labour charges for sand filling Rmt 53.33
Sub Total 1698.33
g) Transportation @ 10% on (a) & (b) 138.50
Sub Total 1836.83
f) WCT @ 4% on sub total 73.47
Sub Total 1910.31
h) Add 15% for Overheads & Profit 286.55
Grand Total for 3.00 M Rs. 2196.85
Cost for 1.00 Rmt Rs. 732.28
Say Rs. 735.00
Say Rs. 735.00 / Rmt

2 Providing & laying NP3 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 2940.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 225.00
e) Labour charges for sand filling Rmt 86.00
Sub Total 3500.00
g) Transportation @ 10% on (a) & (b) 306.00
Sub Total 3806.00
f) WCT @ 4% on sub total 152.24
Sub Total 3958.24
h) Add 15% for Overheads & Profit 593.74
Grand Total for 3.00 M Rs. 4551.98
Cost for 1.00 Rmt Rs. 1517.33
Say Rs. 1520.00
Say Rs. 1,520.00 / Rmt

3 Providing & laying NP3 Class 600mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 3720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 292.50
e) Labour charges for sand filling Rmt 123.33
Sub Total 4500.83
g) Transportation @ 10% on (a) & (b) 390.00
Sub Total 4890.83
f) WCT @ 4% on sub total 195.63
Sub Total 5086.47
h) Add 15% for Overheads & Profit 762.97
Grand Total for 3.00 M Rs. 5849.44
Cost for 1.00 Rmt Rs. 1949.81
Say Rs. 1950.00
Say Rs. 1,950.00 / Rmt

4 Providing & laying NP3 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6600.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 472.50
e) Labour charges for sand filling Rmt 216.67
Sub Total 7794.17
g) Transportation @ 10% on (a) & (b) 678.00
Sub Total 8472.17
f) WCT @ 4% on sub total 338.89
Sub Total 8811.05
h) Add 15% for Overheads & Profit 1321.66
Grand Total for 3.00 M Rs. 10132.71
Cost for 1.00 Rmt Rs. 3377.57
Say Rs. 3380.00
Say Rs. 3,380.00 / Rmt

5 Providing & laying NP3 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 10800.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 645.00
e) Labour charges for sand filling Rmt 500.00
Sub Total 12875.00
g) Transportation @ 10% on (a) & (b) 1098.00
Sub Total 13973.00
f) WCT @ 4% on sub total 558.92
Sub Total 14531.92
h) Add 15% for Overheads & Profit 2179.79
Grand Total for 3.00 M Rs. 16711.71
Cost for 1.00 Rmt Rs. 5570.57
Say Rs. 5570.00
Say Rs. 5,570.00 / Rmt

Note : 1) Labour cost for laying & jointing


adopted from KUWSDB 1999-2000 as basis.
2) Collar joints considered one in every 3 M.
Rate Analysis for Hume Pipes
Lowering, laying and jointing true to line and level RCC Hume pipes (NP-2
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test for water tightness
(Contractor will make his own arrangements for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP2 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 900.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
e) Labour charges for sand filling Rmt 53.33
Sub Total 1195.83
f) VAT @ 12.5% on (a) & (b) 120.63
g) Service Tax @ 12.24% on (d) & (e) 18.46
h) Transportation @ 10% on (a) & (b) 96.50
Sub Total 1431.42
i) Add 15% for Overheads & Profit 214.71
Grand Total for 3.00 M Rs. 1646.13
Cost for 1.00 Rmt Rs. 548.71
Say Rs. 550.00
Say Rs. 550.00 / Rmt

2 Providing & laying NP2 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 1620.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 177.00
e) Labour charges for sand filling Rmt 86.00
Sub Total 2132.00
f) VAT @ 12.5% on (a) & (b) 217.50
g) Service Tax @ 12.24% on (d) & (e) 32.19
h) Transportation @ 10% on (a) & (b) 174.00
Sub Total 2555.69
i) Add 15% for Overheads & Profit 383.35
Grand Total for 3.00 M Rs. 2939.04
Cost for 1.00 Rmt Rs. 979.68
Say Rs. 980.00
Say Rs. 980.00 / Rmt

3 Providing & laying NP2 Class 600mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 3000.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 229.50
e) Labour charges for sand filling Rmt 123.33
Sub Total 3717.83
f) VAT @ 12.5% on (a) & (b) 397.50
g) Service Tax @ 12.24% on (d) & (e) 43.19
h) Transportation @ 10% on (a) & (b) 318.00
Sub Total 4476.52
i) Add 15% for Overheads & Profit 671.48
Grand Total for 3.00 M Rs. 5148.00
Cost for 1.00 Rmt Rs. 1716.00
Say Rs. 1720.00
Say Rs. 1,720.00 / Rmt

4 Providing & laying NP2 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 4380.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 375.00
e) Labour charges for sand filling Rmt 216.67
Sub Total 5476.67
f) VAT @ 12.5% on (a) & (b) 570.00
g) Service Tax @ 12.24% on (d) & (e) 72.42
h) Transportation @ 10% on (a) & (b) 456.00
Sub Total 6575.09
i) Add 15% for Overheads & Profit 986.26
Grand Total for 3.00 M Rs. 7561.35
Cost for 1.00 Rmt Rs. 2520.45
Say Rs. 2520.00
Say Rs. 2,520.00 / Rmt

5 Providing & laying NP2 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 487.50
e) Labour charges for sand filling Rmt 500.00
Sub Total 8637.50
f) VAT @ 12.5% on (a) & (b) 862.50
g) Service Tax @ 12.24% on (d) & (e) 120.87
h) Transportation @ 10% on (a) & (b) 690.00
Sub Total 10310.87
i) Add 15% for Overheads & Profit 1546.63
Grand Total for 3.00 M Rs. 11857.50
Cost for 1.00 Rmt Rs. 3952.50
Say Rs. 3955.00
Say Rs. 3,955.00 / Rmt

Lowering, laying and jointing true to line and level RCC Hume pipes (NP-3
class) with specials including collars and perfect linking of joints with jack to
correct position including cost of pipes & collars, jointing materials i.e. C:M 1:3
proportion and tar dipped hemp, including filling the excavated trench with
approved quality saturated sand on sides, bottom and top surface of pipe with
all leads and lifts, including giving hydraulic test for water tightness
(Contractor will make his own arrangements for procuring water for testing).

Sl. No. Item Unit Rate


1 Providing & laying NP3 Class 300mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 1320.00
b) Cost of Collar Each 65.00
c) Sand filling around pipes Rmt 80.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 180.00
e) Labour charges for sand filling Rmt 53.33
Sub Total 1698.33
f) VAT @ 12.5% on (a) & (b) 173.13
g) Service Tax @ 12.24% on (d) & (e) 28.56
h) Transportation @ 10% on (a) & (b) 138.50
Sub Total 2038.52
i) Add 15% for Overheads & Profit 305.78
Grand Total for 3.00 M Rs. 2344.30
Cost for 1.00 Rmt Rs. 781.43
Say Rs. 785.00
Say Rs. 785.00 / Rmt

2 Providing & laying NP3 Class 450mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 2940.00
b) Cost of Collar Each 120.00
c) Sand filling around pipes Rmt 129.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 225.00
e) Labour charges for sand filling Rmt 86.00
Sub Total 3500.00
f) VAT @ 12.5% on (a) & (b) 382.50
g) Service Tax @ 12.24% on (d) & (e) 38.07
h) Transportation @ 10% on (a) & (b) 306.00
Sub Total 4226.57
i) Add 15% for Overheads & Profit 633.98
Grand Total for 3.00 M Rs. 4860.55
Cost for 1.00 Rmt Rs. 1620.18
Say Rs. 1620.00
Say Rs. 1,620.00 / Rmt
3 Providing & laying NP3 Class 600mm Hume
pipes (for 3 M length).
a) Cost of Pipe Rmt 3720.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 185.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 292.50
e) Labour charges for sand filling Rmt 123.33
Sub Total 4500.83
f) VAT @ 12.5% on (a) & (b) 487.50
g) Service Tax @ 12.24% on (d) & (e) 50.90
h) Transportation @ 10% on (a) & (b) 390.00
Sub Total 5429.23
i) Add 15% for Overheads & Profit 814.38
Grand Total for 3.00 M Rs. 6243.62
Cost for 1.00 Rmt Rs. 2081.21
Say Rs. 2085.00
Say Rs. 2,085.00 / Rmt

4 Providing & laying NP3 Class 900mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 6600.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 325.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 472.50
e) Labour charges for sand filling Rmt 216.67
Sub Total 7794.17
f) VAT @ 12.5% on (a) & (b) 847.50
g) Service Tax @ 12.24% on (d) & (e) 84.35
h) Transportation @ 10% on (a) & (b) 678.00
Sub Total 9404.02
i) Add 15% for Overheads & Profit 1410.60
Grand Total for 3.00 M Rs. 10814.62
Cost for 1.00 Rmt Rs. 3604.87
Say Rs. 3605.00
Say Rs. 3,605.00 / Rmt

5 Providing & laying NP3 Class 1200mm Hume


pipes (for 3 M length).
a) Cost of Pipe Rmt 10800.00
b) Cost of Collar Each 180.00
c) Sand filling around pipes Rmt 750.00
d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 645.00
e) Labour charges for sand filling Rmt 500.00
Sub Total 12875.00
f) VAT @ 12.5% on (a) & (b) 1372.50
g) Service Tax @ 12.24% on (d) & (e) 140.15
h) Transportation @ 10% on (a) & (b) 1098.00
Sub Total 15485.65
i) Add 15% for Overheads & Profit 2322.85
Grand Total for 3.00 M Rs. 17808.50
Cost for 1.00 Rmt Rs. 5936.17
Say Rs. 5940.00
Say Rs. 5,940.00 / Rmt

Note : Labour cost for laying & jointing


adopted from KUWSDB 1999-2000 as basis.