PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.

JOB ACTIVITY
HIRARC NO: 011 DATE: 22nd Nov 2017
Falsework (EFCO) lifting OSD
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Minor Injury
Wrong
 Back pain 2 4 8  Apply correct posture. 1 2 2
posture
Sharp edges Minor Injury 2 2 4  Mandatory PPE, gloves 1 2 2
of the will be applied for this
material activity.
Working at  Safety harness will be used
Major Injury,
height 4 4 16 and anchored at rigid 1 4 4
death
(2 meter above) place.
 Hand tools will be secured
using tools bag / bucket
1. Falsework  Assign experienced
dismantling at workers for falsework
the top. activity
 During installation,
scaffolding supervisor will
 Major
monitor concern activities.
Falling Object Injury 4 4 16 2 4 8
 Concern area will be
 Death
secured & prohibited for
others except concern
workers.
 Scaffolding to be inspected
by EFCO supervisor &
safety personnel before
casting.

1|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 011 DATE: 22nd Nov 2017
Falsework (EFCO) lifting OSD
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Minor Injury
Wrong
 Back pain 2 2 4  Apply correct posture. 1 2 2
Falsework posture
mobilization to
Sharp edges Minor Injury 2 2 4  Mandatory PPE, gloves 1 2 2
2. the loading
of the will be applied for this
platform using
material activity
castor wheel
 Protruding rebar will be
cover.
Falsework  Major  Mobilize path will be clear
toppled Injury from any obstruction
during  Death before proceed.
mobilize 4 4 16  Using 2 manpower to 1 4 4
push & 1 spotter to
control the movement, to
the loading platform.

2|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 011 DATE: 22nd Nov 2017
Falsework (EFCO) lifting OSD
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Assign competent crane
operator with signalman.
 The crane ground surface will
be compacted and stable
area.
 4 lifting point using web sling
will be applied.
 Major
 Crane and lifting gear will be
Falling Object Injury 4 4 16 2 4 8
inspected for safe to use.
Loading &  Death  Crane load chart will be
Unloading the applied for the load &
3. falsework unloading activity.
using mobile  Lifting radius will be isolated
crane with warning tape to prevent
workers into the lifting area.

 Assign competent crane to


check the surface of the
Crane toppled crane.
Major Injury
due to uneven 4 4 16  The crane ground surface will 2 4 8
Death be compacted and park at
ground
stable area.

3|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 011 DATE: 22nd Nov 2017
Falsework (EFCO) lifting OSD
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Assign competent crane
operator with signalman.
 The signalman will apply
orange vest.
Movement of  Major
 Efficient communication
lifting Injury
4 5 20 between crane operator & 2 3 6
material.  Death signalman.
Loading &  Tagline will be applied.
Unloading the  Lifting radius will be isolated
3. with warning tape to prevent
falsework using
mobile crane workers into the lifting area.

 Workers to wear glove


when performing activity
Sharp edges Minor Injury 2 2 4 1 2 2

4|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 011 DATE: 22nd Nov 2017
Falsework (EFCO) lifting OSD
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS

 Edge protection will install


when working at edges.
Loading &  Safety harness will be used
Unloading the Open edges at and anchored.
Major Injury,
3 falsework loading 4 4 16  Ladder will be used as 1 4 4
death
using mobile platform access.
crane  Scaffolding will be used as
access or working
platform.
4 Housekeeping  Sharp edges Minor Injury 2 2 4  Mandatory PPE, gloves 1 2 2
activity of the will be applied for this
material activity
 Wrong body  Correct body posture
posture

Prepared by: Review by (HSSE Department): Approved by (Project Manager):

…………………………………………………………… ………………………………………………………………. …………………………………………………….


Name: TENGKU AHMAD WILDAN BIN TENGKU AZAN Name: MOHD RAMDHAN BIN MOHD SAID Name: YAP KOK YAW
Date: 22nd November 2017 Date: 22nd November 2017 Date: 22nd November 2017