By present the results achieved during the month of December 2017 is reported.
During 15 work filled, making a total volume of 9,436.85m³ having operated a total of
252.50 hours. 22 partitions prepared whose total area was 267.22m2.
Datos Enero Febrero Marzo Abril Mayo Junio Julio Agosto Setiembre Octubre Noviembre Diciembre Total general
Volumen Mensual Operativo mᶟ 5,781.04 6,831.77 8,541.55 8,154.98 5,838.05 7,244.70 9,272.71 5,351.39 7,752.92 5,995.64 3,985.42 7,745.39 82,495.56
Volumen Mensual Pasivo mᶟ 6,866.71 2,972.55 3,605.75 5,956.10 7,961.48 6,513.63 4,892.14 3,128.91 2,286.69 3,690.80 3,727.28 1,691.46 53,293.50
Volumen Mensual Total mᶟ 12,647.75 9,804.32 12,147.30 14,111.08 13,799.53 13,758.33 14,164.85 8,480.30 10,039.61 9,686.44 7,712.70 9,436.85 135,789.06
Tiempo Relleno Hrs 339.58 263.50 325.08 377.92 370.08 368.00 379.83 227.08 268.58 259.33 204.25 252.50 3635.74
Volumen Acumulado Explotado mᶟ 1,312,833 1,305,242 1,569,232 1,790,006 2,015,798 1,848,124 1,817,637.64 1,588,224.34 1,373,772.60 1,385,991.59 1,474,083.57 1,481,591.40 ##########
Volumen Acumulado Relleno mᶟ 1,283,954.57 1,258,486.69 1,526,110.79 1,601,266.14 1,828,250.85 1,665,309.44 1,642,873.98 1,258,718.73 1,143,350.13 1,149,416.13 1,140,707.00 1,149,956.63 ##########
Volumen Acumulado Detritico mᶟ 17,997.28 18,941.07 19,994.48 152,153.32 153,301.41 154,179.24 155,143.46 154,978.90 105,456.53 106,303.94 113,370.30 114,189.33 1,266,009.26
Volumen Pasivo a Rellenar mᶟ 28,878.09 46,754.86 43,121.09 188,739.72 187,546.78 182,814.39 174,763.66 329,505.60 230,422.46 236,575.46 333,376.57 331,634.77 2,314,133.45
Volumen Purgado Aire Comprimido
Pulmón de Aire N° 05 11,744 11,529 10,493 3,093 25,989 30,186 31,837 37,348 33,099 30,415 20,147 27,616 273,497
Purgadores Pique Andres 3,134 2,840 3,106 18,795 22,618 16,968 13,318 13,888 12,775 15,550 14,572 16,742 154,306
Purgadores Pique Marsa 0 0 0 2,542 7,248 5,184 5,903 5,314 4,584 6,819 7,832 12,845 58,271
Total Litros de Agua Purgados 14,878 14,369 13,599 24,430 55,855 52,338 51,058 56,550 50,458 52,784 42,551 52,220 481,091
Volumen Reportado por Mes
Volumen Mensual 12,647.75 9,804.32 12,147.30 14,111.08 13,799.53 13,758.33 14,164.75 8,480.30 10,039.61 9,686.44 7,712.70 9,436.85 135,788.96
Tiempo Relleno 339.58 263.50 325.08 377.92 370.08 368.00 379.83 227.08 268.58 259.33 204.25 252.50 3,635.75
Num. Labores Mes
Total 19 19 18 26 20 21 16 13 16 20 11 15 214
Preparacion de Tabiques por Mes
Area Total 286.48 200.42 256.37 214.23 197.67 441.29 214.87 119.57 217.57 242.28 175.56 267.22 2833.53
Area Promedio 8.19 10.02 7.12 7.93 8.99 10.76 7.96 5.98 5.58 9.32 13.50 12.15 8.64
Numero de Tabiques 35 20 36 27 22 41 27 20 39 26 13 22 328
Distribucion de Tareas Relleno Hidraulico
Transporte de Materiales 100% Relave 13 15 3 14 16 11 5 13 3 19 2 2 116
Jefe de Guardia Comiluz 62 56 61 47 57 60 57 61 56 56 57 59 689
Tareas Total 2,138 1,908 2,165 1,988 2,173 2,060 2,008 2,134 1,992 1,873 1,138 1,488 23,065
Ratios Enero Febrero Marzo Total General
Volumen de Relleno m3 / Area de Tabique m2 44.15 48.92 47.38 65.87 69.81 31.18 65.92 70.92 46.14 39.98 43.93 35.31 47.92
Volumen de Relleno m3 / Tarea Directa 8.43 8.13 8.88 11.17 11.14 10.29 10.83 7.26 7.62 7.41 5.90 9.46 9.29
Volumen de Relleno m3 / Tarea Total 5.92 5.14 5.61 7.10 6.35 6.68 7.05 3.97 5.04 5.17 6.78 6.34 5.89
Volumen de Relleno m3 / Tabique 361.36 490.22 337.43 522.63 627.25 335.57 524.62 424.02 257.43 372.56 593.28 428.95 413.99
Volumen de Relleno m3 / Labor 665.67 516.02 674.85 542.73 689.98 655.16 885.30 652.33 627.48 484.32 701.15 629.12 634.53
Tarea Directa / Area de Tabiques m2 5.24 6.02 5.34 5.90 6.27 3.03 6.09 9.77 6.05 5.39 7.44 3.73 5.16
Tarea Directa / Tabique 42.89 60.30 38.00 46.78 56.32 32.61 48.44 58.40 33.77 50.27 100.54 45.36 44.57
Tarea Directa / Labor 79.00 63.47 76.00 48.58 61.95 63.67 81.75 89.85 82.31 65.35 118.82 66.53 68.32
Area de Tabiques m2 / Labor 15.08 10.55 14.24 8.24 9.88 21.01 13.43 9.20 13.60 12.11 15.96 17.81 13.24
Area de Tabiques m2 / Tabique 8.19 10.02 7.12 7.93 8.99 10.76 7.96 5.98 5.58 9.32 13.50 12.15 8.64
Tabiques / Labor 1.84 1.05 2.00 1.04 1.10 1.95 1.69 1.54 2.44 1.30 1.18 1.47 1.53
____________________________
Ing. Alberto Vargas Ramirez
Chief General Services - Mina
DC: Superintendent / Superintendent Mine / Mine Planning / Engineering / File.
1. SECURITY:
2. FILLING HYDRAULIC
Page 2 of 10
Tie m po Caudal De ns idad Volum e n
Fecha Labores Observacion Hr m 3/Hr Kg/l m3
01/12/2017 Tj. 464 El tajo se relleno conforme.Quedo Topeado 1.50 74.30 1.832 56.56
Tj. 862 Daniela El tajo se relleno conforme 3.33 73.80 1.836 125.32
Xc 10089 Se corto por falta de Carga 3.50 73.50 1.836 131.18
02/12/2017 Tj. 554 El tajo se relleno conforme 1.50 73.70 1.813 54.82
Se inició tarde por instalacion de tuberia RH. 2.00 73.50 1.830 74.43
Tj. 765 Daniela El tajo se relleno conforme 1.67 73.70 1.829 61.87
Xc 10089 El crucero se relleno conforme. Quedo Topeado 1.50 74.00 1.813 55.04
03/12/2017 Tj. 554 El tajo se relleno conforme 2.50 73.80 1.830 93.55
Tj. 465 El tajo se relleno conforme 1.17 73.20 1.804 41.89
Tj. 765 Daniela El tajo se relleno conforme 1.50 73.70 1.826 55.76
04/12/2017 Tj. 554 El tajo se relleno conforme 1.83 75.00 1.817 69.04
06/12/2017 Tj. 11 El tajo se relleno conforme 6.83 73.00 1.844 256.69
5.50 73.20 1.841 206.54
Tj. 554 El tajo se relleno conforme 1.67 73.70 1.825 61.57
07/12/2017 Tj. 11 El tajo se relleno conforme 1.50 74.60 1.813 55.49
Tj. 10 El tajo se relleno conforme 3.00 73.00 1.828 110.61
2.33 73.80 1.834 87.48
08/12/2017 Tj. 11 El tajo se relleno conforme 3.00 73.70 1.830 111.94
Tj. 554 El tajo se relleno conforme 1.83 73.70 1.825 67.92
Tj. 10 El tajo se relleno conforme 2.17 73.50 1.834 80.77
09/12/2017 Tj. 554 El tajo se relleno conforme 2.00 73.30 1.828 74.04
Tj. 868 El tajo se relleno conforme 3.50 74.00 1.838 132.40
10/12/2017 Tj. 11 El tajo se relleno conforme.Quedo Topeado 1.50 73.50 1.815 54.81
Tj. 661 Se incio tarde por trabajos en el tajo 6.83 73.70 1.848 260.38
Tj. 10 El tajo se relleno conforme 2.33 72.60 1.825 85.12
11/12/2017 Tj. 661 El tajo se relleno confome 8.33 73.50 1.846 315.96
Tj. 868 El tajo se relleno confome 6.50 73.10 1.842 244.04
12/12/2017 Tj. 465 El tajo se relleno confome 1.00 73.70 1.821 36.91
Tj. 661 El tajo se relleno confome 2.67 73.80 1.836 100.11
Tj. 10 El tajo se relleno confome 2.00 73.00 1.820 73.02
Tj. 868 El tajo se relleno confome.Quedo Topeado 2.00 74.00 1.821 74.11
13/12/2017 Tj. 10 El tajo se relleno confome 1.83 73.70 1.825 67.87
Tj. 2005 El tajo se relleno confome 4.17 73.30 1.843 158.94
14/12/2017 Tj. 465 El tajo se relleno confome 1.00 74.00 1.815 36.78
Tj. 661 El tajo se relleno confome 2.67 73.50 1.828 98.74
Tj. 10 El tajo se relleno confome 1.83 73.70 1.828 68.12
Tj. 2005 El tajo se relleno confome 4.50 74.20 1.844 171.91
15/12/2017 Tj. 465 El tajo se relleno confome 1.50 74.00 1.821 55.58
Tj. 661 El tajo se relleno confome 2.00 73.60 1.827 74.25
Tj. 10 El tajo se relleno confome 1.67 73.70 1.825 61.85
Tj. 2005 El tajo se relleno confome 4.33 74.40 1.843 165.66
16/12/2017 Tj. 465 El tajo se relleno confome 2.00 74.00 1.826 74.57
Tj. 661 El tajo se relleno confome 2.50 73.50 1.833 93.36
Tj. 10 El tajo se relleno confome 1.83 73.80 1.829 68.30
Tj. 2005 El tajo se relleno confome 4.50 74.00 1.844 171.44
17/12/2017 Tj. 465 El tajo se relleno confome 1.50 74.60 1.821 56.04
Tj. 661 El tajo se relleno confome 1.50 73.60 1.820 55.22
Tj. 152 Se incio tarde por trabajos en el tajo 1.33 74.70 1.826 50.06
Tj. 2005 El tajo se relleno conforme 3.00 74.00 1.840 113.75
18/12/2017 Tj. 465 Se corto antes por fuga por la Ch. 13 1.33 74.00 1.808 48.50
Tj. 661 El tajo se relleno conforme 1.67 73.60 1.825 61.48
Tj. 10 El tajo se relleno conforme 1.17 73.70 1.819 42.72
Tj. 152 El tajo se relleno conforme 1.67 74.30 1.834 62.75
19/12/2017 Tj. 10 Se corto por fuga de fino 1.00 73.70 1.820 36.86
Tj. 152 Se corto por fuga de fino por el drenaje 1.33 74.60 1.826 49.99
Tj. 2005 El tajo se relleno conforme 2.50 73.60 1.825 92.59
20/12/2017 Tj. 554 El tajo se relleno conforme 1.50 73.70 1.826 55.70
Tj. 661 Se corto por fuga de fino 1.50 73.50 1.830 55.81
Tj. 10 El tajo se relleno conforme.Quedo Topeado 1.00 74.00 1.821 37.05
21/12/2017 Tj. 152 El tajo se relleno conforme 1.33 74.30 1.827 49.85
22/12/2017 Tj. 465 Se corto por picadura en el desviador (Nv.2950) 1.00 74.00 1.806 36.38
Tj. 661 El tajo se relleno conforme 1.50 73.50 1.815 54.81
23/12/2017 Tj. 554 El tajo se relleno conforme 4.00 73.40 1.836 149.72
Tj. 465 El tajo se relleno conforme 1.00 74.00 1.808 36.47
Tj. 661 El tajo se relleno conforme 1.17 73.00 1.804 41.53
Tj. 152 El tajo se relleno conforme 1.50 74.00 1.815 55.18
Tj. 2005 El tajo se relleno conforme.Quedo Topeado 1.00 74.00 1.821 37.05
24/12/2017 Tj. 554 El tajo se relleno conforme 3.50 73.70 1.835 131.38
Tj. 465 El tajo se relleno conforme 1.50 74.00 1.816 55.25
Tj. 661 El tajo se relleno conforme 1.50 73.50 1.815 54.81
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme 2.00 74.00 1.820 74.02
25/12/2017 Tj. 554 El tajo se relleno conforme 3.00 73.70 1.832 112.21
Tj. 661 Se corto por falta de agua (3715) 1.50 73.00 1.815 54.43
Tj. 1161 El tajo se relleno conforme 2.50 74.20 1.830 93.91
26/12/2017 Tj. 465 El tajo se relleno conforme 1.50 73.40 1.815 54.81
Tj. 1161 El tajo se relleno conforme.Quedo Topeado 2.50 74.00 1.828 93.43
27/12/2017 Tj. 554 El tajo se relleno conforme 7.17 73.70 1.834 268.75
Tj. 465 El tajo se relleno conforme 2.17 74.00 1.826 80.79
Tj. 661 El tajo se relleno conforme 2.50 73.50 1.810 90.79
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme. 3.00 74.00 1.815 110.37
28/12/2017 Tj. 554 El tajo se relleno conforme 2.67 73.70 1.828 99.01
Tj. 465 El tajo se relleno conforme 4.00 73.80 1.840 151.26
4.00 74.30 1.827 149.93
Tj. 661 El tajo se relleno conforme 1.67 73.50 1.815 60.97
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme. 3.50 73.60 1.838 131.68
29/12/2017 Tj. 554 El tajo se relleno conforme 5.00 74.00 1.821 185.30
Tj. 465 El tajo se relleno conforme 3.00 73.80 1.833 112.50
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme 3.50 73.70 1.837 131.70
30/12/2017 Tj. 465 El tajo se relleno conforme 3.00 74.00 1.830 112.40
Tj. 202 El tajo se relleno conforme 5.50 73.70 1.834 206.22
Tj. 661 El tajo se relleno conforme 5.50 73.90 1.835 207.02
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme 4.50 74.30 1.832 169.69
31/12/2017 Tj. 202 El tajo se relleno conforme 3.50 73.50 1.834 130.87
Tj. 661 El tajo se relleno conforme 5.50 74.00 1.840 208.45
Tj. 1160 CHI 10138-4AS El tajo se relleno conforme . Queda topeado 4.00 73.40 1.830 148.65
Total 252.50 73.73 1.831 9436.85
m3/Hr 37.37
Q agua 25.81
%Sv 50.99%
%Sp 73.24%
Q pulpa 48.77
Page 3 of 10
2.3 Filling volume sections:
3
Seccion Tiempo Densidad Caudal Volumen (m ) Cumplimiento
Programado Ejecutado
Chilcas Bajo 73.50 1.834 73.60 2,600 2,753.67 105.91%
Valeria I 39.33 1.825 74.04 3,010 1,464.45 48.65%
Valeria II 53.67 1.833 73.63 2,107 2,005.75 95.18%
Valeria III 55.50 1.831 73.70 2,517 2,073.31 82.36%
Valeria IV 30.50 1.830 73.84 850 1,139.67 134.08%
Total 252.50 1.831 73.73 11,085 9,436.85 85.13%
Datos Enero Febrero Marzo Abril Mayo Junio Julio Agosto Setiembre Octubre NoviembreDiciembre Total
Pulmón de Aire N° 05 11,744 11,529 10,493 3,093 25,989 30,186 31,837 37,348 33,099 30,415 20,147 27,616 273,497
Purgadores Pique Andres 3,134 2,840 3,106 18,795 22,618 16,968 13,318 13,888 12,775 15,550 14,572 16,742 154,306
Purgadores Pique Marsa 0 0 0 2,542 7,248 5,184 5,903 5,314 4,584 6,819 7,832 12,845 58,271
Total Litros de Agua Purgados 14,878 14,369 13,599 24,430 55,855 52,338 51,058 56,550 50,458 52,784 42,551 52,220 481,091
Page 6 of 10
3.3 Material consumption by Labor.
Acoplamient Alambre Alambre Cemento Mangas de P.Rielero Puntal 8" Puntal 8" Saco Metalero Tablas de 2" Tubería de Tuberia Tuberia
Clavo de Clavo de Pita Rafia Pita Yute Tela Rafia Puntal 8" x
Seccion Nivel Labor o 995 Ф 4" Negro N°16 Negro N°8 Norte tela Rafia de 1/2"x3" x 3.0 m x 4.0 m de 20" x 30" x 8" x 10' Polietileno de drenaje 3" drenaje 4" Yeso (Klo)
4" (Klo) 5" (Klo) (Mto) (Mto) (Mto) 2.4 m (pza)
(pza) (Klo) (Klo) (bls) (Mto) (pza) (pza) (pza) (pza) (pza) 4" (Mto) (pza) (pza)
Page 7 of 10
3.4 Material consumption:
Acoplamiento 995
Acoplamiento 997
Acoplamiento 2"a
Acoplamiento 4"a
Acoplamiento 4"a
Niple o Empalme
Niple o Empalme
Grampas Grosby
Cable de acero
Mullembach 1"
Mullembach 2"
Total general
x 2½" (pza)
1/4" (pza)
1/4" (mto)
2" (pza)
2" (pza)
4" (pza)
2" (pza)
4" (pza)
4" (pza)
1" (pza)
2" (pza)
(pza)
(pza)
(pza)
Nivel
Chilcas 1 3 3 4 4 10 6 31
Chilcas Bajo 7 1 1 15 10 2 88 88 18 1 9 240
Valeria I 2 3 2 8 8 20 20 2 18 83
Valeria II 4 6 5 3 45 45 20 1 129
Valeria III 2 2 4 2 20 25 5 1 30 7 98
Taller Soldadura RH
Valeria IV
Valeria V 3 3 5 3 1 4 20 20 60 9 128
Total general 17 10 1 30 28 21 6 193 198 5 6 1 4 156 8 25 709
Page 8 of 10
4. Distribution of tasks
4.4 Others
Page 9 of 10
5. Hydraulic Fill indicators: