Oman Oman

OMAN PROJECTS AT A GLANCE


Package name Owner Status** $ million* Consultant Contractor Start date End date
2,600 MW IPPS in the Main Interconnected System (MIS) – Ibri IPP Oman Power & Water Procurement Company (OPWP) Engineering & Procurement 1,000 - ACWA Power-Dhofar International Development and Investment Holding Company 2014-Q1 2018-Q2
2,600 MW IPPS in the Main Interconnected System (MIS) – Sohar Three IPP OPWP Engineering & Procurement 1,000 - Mitsui-ACWA Power-Dhofar International Development and Investment Holding Company 2014-Q1 2018-Q2
Acetic Acid Manufacturing Plant Oman Oil Company (OOC) FEED 600 - - 2014-Q1 2019-Q2
Al Irfan Urban Development Oman Tourism And Development Company (Omran) Design 2,000 - - 2014-Q1 2020-Q2
Barka IWP OPWP EPC ITB 600 - Itochu Corporation-Degremont-Engie-WJ Towell 2014-Q4 2018-Q2
Batinah Expressway – Overview Ministry of Transport and Communications (MOTC) Construction 3,500 Driver Consult Galfar Engineering & Contracting-Oman Roads Engineering Company 2012-Q1 2017-Q4
Batinah Expressway – Package 11 MOTC EPC ITB 300 - - 2008-Q2 2017-Q4
Batinah Expressway – Package Eight MOTC EPC ITB 300 - - 2012-Q1 2017-Q4
Batinah Expressway – Package Five MOTC Engineering & Procurement 330 Botek Bosphorus Federici Stirling and Batco JV 2008-Q2 2016-Q3
Batinah Expressway – Package Four MOTC Construction 350 - Larsen & Toubro 2008-Q3 2017-Q4
Batinah Expressway – Package Nine MOTC EPC ITB 300 - - 2012-Q1 2017-Q4
Batinah Expressway – Package One MOTC Construction 350 Driver Consult Galfar Engineering & Contracting 2008-Q2 2016-Q4
Batinah Expressway – Package Seven MOTC EPC ITB 300 - - 2012-Q1 2018-Q4
Batinah Expressway – Package Six MOTC Engineering & Procurement 320 Botek Bosphorus Consolidated Contracting Company (CCC) 2008-Q2 2016-Q3
Batinah Expressway – Package Three MOTC Construction 350 WorleyParsons Simplex Infrastructure 2008-Q2 2017-Q2
Batinah Expressway – Package Two MOTC Construction 330 Driver Consult Nagarjuna Construction Company 2008-Q2 2017-Q3
Diba-Lima-Khasab Road – Section Two MOTC EPC ITB 1,000 - - 2013-Q1 2018-Q2
Dualisation of Adam-Thumrait Road – Part Two MOTC Construction 250 Parsons CCC 2012-Q1 2018-Q2
Dualisation of Bidbid-Sur Road – Section Two MOTC Engineering & Procurement 390 Hill International-Cowi and Partners Khalid Bin Ahmed and Sons 2008-Q3 2017-Q1
Dualisation of Adam-Thumrait Road – Part One MOTC Construction 300 - Ghantoot Transport & General Contracting 2012-Q1 2018-Q2
Duqm Beach Touristic Resort Duqm Beach Resort Design 500 - - 2014-Q4 2020-Q4
Duqm Fishery Harbours Ministry of Agriculture and Fisheries EPC ITB 259 - - 2012-Q3 2017-Q1
Duqm Special Economic Zone Duqm Special Economic Zone Authority (Sezad) Design 500 KEO International Consultants - 2015-Q1 2022-Q2
Freezone Sohar Sohar International Development & Investment (SIDI)-SKIL Infrastructure Construction 2,000 - Al Naboodah Contracting-Premier International Projects 2010-Q1 2016-Q4
Kempinski The Wave Muscat The Omani Hospitality Company Construction 300 Confluence Project Management Carillion Alawi 2008-Q3 2016-Q4
Mall of Oman Majid Al Futtaim EPC ITB 400 Aecom - 2012-Q4 2020-Q2
Masirah Island Causeway MOTC Feasibility Study 600 - - 2013-Q1 2019-Q4
Miraah Solar Thermal Power Plant Petroleum Development Oman (PDO ) Engineering & Procurement 600 - Glass Point 2014-Q2 2017-Q4
Muscat International Airport MOTC Construction 2,500 Hill International Bechtel Corporation-Enka-Bahwan Engineering Company (BEC)-Consolidated Contracting 2007-Q1 2016-Q4
Company (CCC)-Carillion Alawi-TAV Construction
Muscat International Airport and Salalah Airport – MOTC Construction 530 Ghafari Associates Joannou & Paraskevaides 2009-Q1 2016-Q2
Cargo and MRO Facilities (MC12)
Muttrah Redevelopment Muscat Municipality Design 1,240 - - 2011-Q1 2020-Q1
National Railway Network – Overview Oman Railway Company (ORC) EPC ITB 15,000 Tecnicas Reunidas - 2008-Q2 2018-Q4
National Railway Network – Sohar-Al Buraimi MOTC EPC ITB 1,500 Tecnicas Reunidas-Dar Al Handasah - - 2008-Q2 2018-Q4
Ingenieria & Consultoria de Transporte (Ineco)
New Musandam Airport MOTC Design 250 - - 2010-Q1 2019-Q1
New Residential Area in Liwa – Infrastructure Package Ministry of Housing Construction 250 AAW & Partners Consulting Engineers Towell Infrastructure Projects Company 2013-Q4 2017-Q4
Omagine Project Omagine Engineering & Procurement 1,600 - CCC 2005-Q3 2020-Q4
Oman Convention & Exhibition Centre – Package Three Omran Construction 250 - Oman Shapoorji Construction Company-Shapoorji Pallonji & Company 2013-Q2 2017-Q4
Port of Salalah – Phase Three MOTC Design 260 - - 2012-Q2 2018-Q3
Port of Sohar – Phase Two (Terminal D) Oman International Container Terminal (OICT) Design 350 - - 2013-Q1 2019-Q1
Qurayat IWP OPWP Engineering & Procurement 350 - National Power & Water Company-Hyflux 2011-Q1 2017-Q2
Ras Al-Hadd Airport MOTC Construction 300 Indra-Airport Architects and Engineers (ADPI)-Thales Group Galfar Engineering & Contracting-Desert Line Projects 2009-Q4 2017-Q4
Royal Oman Police Hospital Royal Oman Police Construction 570 Al Manara Engineering Consultancy-Option One Galfar Engineering & Contracting 2011-Q3 2018-Q1
Salalah Two IPP OPWP Engineering & Procurement 600 - Mitsui-ACWA Power-Sepco III-Dhofar International Development and Investment Holding 2011-Q1 2018-Q3
Salalah Airport MOTC Construction 750 Hill International Larsen & Toubro-Galfar Engineering & Contracting 2005-Q1 2016-Q4
Salalah IWP OPWP EPC ITB 300 - - 2015-Q1 2019-Q1
Shadeed Iron Expansion Jindal Steel and Power Limited (JSPL) EPC ITB 2,000 - - 2014-Q4 2018-Q4
Sohar IWP OPWP Engineering & Procurement 600 - Sogex-Valoriza Agua 2014-Q4 2018-Q2
Solar Power Plant Occidental Feasibility Study 300 - - 2015-Q3 2018-Q2
South Batinah Logistics Area Supreme Council for Planning Engineering & Procurement 467 - Alisco Strong Plant Trading & Contracting 2013-Q4 2030-Q4
Steel Mill Plant Sun Metals Engineering & Procurement 500 Steelworks Engineering Systems Posco Engineering & Construction 2013-Q1 2018-Q1
Sultan Qaboos Medical City Ministry of Health Design 1,000 - - 2013-Q2 2017-Q2
Sultan Qaboos Port Expansion MOTC Design 360 - - 2007-Q3 2020-Q2
Sur Gate The Public Establishment for Industrial Estates (PEIE) Construction 312 Abdulla Mukadam & Partners Al Sharqiya for Real Estate Development & Investment 2012-Q2 2016-Q4
The Wave Muscat – Mixed-use Development The Wave, Muscat Construction 1,100 Turner Construction International Carillion Alawi-Al Turki-SNE 2006-Q1 2016-Q4
**ITB = invitation to bid; EPC = engineering, procurement and construction; FEED = front end engineering design *List includes projects worth over $250 million only.