EXCEPTION REPORT DATED 12-01-2010

SR ACTIVITY SCHEDULED DATE EXPECTED DATE REMARKS

1 - Charging of CWPH Board 08.01.10

2 - Charging of Station LT Switch gear 10.01.10

3 - Charging of LT Switch gear of DM/PT Plant 10.01.10

4 - CT Make up system Readiness 07.01.10

5 - Hotwell Make up system 10.01.10

6 - Instrument air FOR Unit 1 & 2 10.01.10

7 - Trial run of CT make up pumps 28.12.09

8 - DMCW Motor trial run 10.01.10

9 - Pump trial run 11.01.10

10 - Compressor Motor trial run 12.01.10

11 - Charging of LDO Pump house MCC 10.01.10

12 - LDO unloading pump Motor trial run 10.01.10

18 - Completion of LDO supply & return line up to & from boiler 10.01.10

19 - LDO line flushing 11.01.10

20 - Availability of EDTA and other chemicals 07.01.10

21 - Completion of Burner control station 10.01.10

22 - Trial run of jockey pump 10.01.10