You are on page 1of 26

FIRST DIVISION The SOB required the contractors to submit (1) a performance bond

[G.R. No. 140047. July 13, 2004] of ID271,808/610 representing 5% of the total contract price and (2) an
PHILIPPINE EXPORT AND FOREIGN LOAN GUARANTEE advance payment bond of ID541,608/901 representing 10% of the
CORPORATION, petitioner, vs. V.P. EUSEBIO CONSTRUCTION, INC.; advance payment to be released upon signing of the contract.[6] To
3-PLEX INTERNATIONAL, INC.; VICENTE P. EUSEBIO; SOLEDAD C. comply with these requirements, respondents 3-Plex and VPECI applied for
EUSEBIO; EDUARDO E. SANTOS; ILUMINADA SANTOS; AND FIRST the issuance of a guarantee with petitioner Philguarantee, a government
INTEGRATED BONDING AND INSURANCE COMPANY, financial institution empowered to issue guarantees for qualified Filipino
INC., respondents. contractors to secure the performance of approved service contracts
DECISION abroad.[7]
DAVIDE, JR., C.J.: Petitioner Philguarantee approved respondents
This case is an offshoot of a service contract entered into by a Filipino application. Subsequently, letters of guarantee[8] were issued by
construction firm with the Iraqi Government for the construction of the Philguarantee to the Rafidain Bank of Baghdad covering 100% of the
Institute of Physical Therapy-Medical Center, Phase II, in Baghdad, Iraq, at performance and advance payment bonds, but they were not accepted
a time when the Iran-Iraq war was ongoing. by SOB. What SOB required was a letter-guarantee from Rafidain Bank, the
In a complaint filed with the Regional Trial Court of Makati City, government bank of Iraq. Rafidain Bank then issued a performance bond
docketed as Civil Case No. 91-1906 and assigned to Branch 58, in favor of SOB on the condition that another foreign bank, not
petitioner Philippine Export and Foreign Loan Guarantee Philguarantee, would issue a counter-guarantee to cover its exposure. Al
Corporation[1] (hereinafter Philguarantee) sought reimbursement from the Ahli Bank of Kuwait was, therefore, engaged to provide a counter-
respondents of the sum of money it paid to Al Ahli Bank of Kuwait pursuant guarantee to Rafidain Bank, but it required a similar counter-guarantee in
to a guarantee it issued for respondent V.P. Eusebio Construction, Inc. its favor from the petitioner. Thus, three layers of guarantees had to be
(VPECI). arranged.[9]
The factual and procedural antecedents in this case are as follows: Upon the application of respondents 3-Plex and VPECI, petitioner
On 8 November 1980, the State Organization of Buildings (SOB), Philguarantee issued in favor of Al Ahli Bank of Kuwait Letter of Guarantee
Ministry of Housing and Construction, Baghdad, Iraq, awarded the No. 81-194-F [10] (Performance Bond Guarantee) in the amount of
construction of the Institute of Physical TherapyMedical Rehabilitation ID271,808/610 and Letter of Guarantee No. 81-195-F[11] (Advance Payment
Center, Phase II, in Baghdad, Iraq, (hereinafter the Project) to Ajyal Trading Guarantee) in the amount of ID541,608/901, both for a term of eighteen
and Contracting Company (hereinafter Ajyal), a firm duly licensed with the months from 25 May 1981. These letters of guarantee were secured by (1)
Kuwait Chamber of Commerce for a total contract price of ID5,416,089/046 a Deed of Undertaking[12]executed by respondents VPECI, Spouses Vicente
(or about US$18,739,668).[2] P. Eusebio and Soledad C. Eusebio, 3-Plex, and Spouses Eduardo E. Santos
On 7 March 1981, respondent spouses Eduardo and Iluminada Santos, and Iluminada Santos; and (2) a surety bond[13] issued by respondent First
in behalf of respondent 3-Plex International, Inc. (hereinafter 3-Plex), a local Integrated Bonding and Insurance Company, Inc. (FIBICI). The Surety Bond
contractor engaged in construction business, entered into a joint venture was later amended on 23 June 1981 to increase the amount of coverage
agreement with Ajyal wherein the former undertook the execution of the from P6.4 million to P6.967 million and to change the bank in whose favor
entire Project, while the latter would be entitled to a commission of 4% of the petitioners guarantee was issued, from Rafidain Bank to Al Ahli Bank
the contract price.[3] Later, or on 8 April 1981, respondent 3-Plex, not being of Kuwait.[14]
accredited by or registered with the Philippine Overseas Construction On 11 June 1981, SOB and the joint venture VPECI and Ajyal executed
Board (POCB), assigned and transferred all its rights and interests under the the service contract[15] for the construction of the Institute of Physical
joint venture agreement to VPECI, a construction and engineering firm duly Therapy Medical Rehabilitation Center, Phase II, in Baghdad, Iraq, wherein
registered with the POCB.[4] However, on 2 May 1981, 3-Plex and VPECI the joint venture contractor undertook to complete the Project within a
entered into an agreement that the execution of the Project would be period of 547 days or 18 months. Under the Contract, the Joint Venture
under their joint management.[5] would supply manpower and materials, and SOB would refund to the
former 25% of the project cost in Iraqi Dinar and the 75% in US dollars at the On 14 April 1987, the petitioner received another telex message from
exchange rate of 1 Dinar to 3.37777 US Dollars.[16] Al Ahli Bank stating that it had already paid to Rafidain Bank the sum of
The construction, which was supposed to start on 2 June 1981, US$876,564 under its letter of guarantee, and demanding reimbursement
commenced only on the last week of August 1981. Because of this delay by the petitioner of what it paid to the latter bank plus interest thereon and
and the slow progress of the construction work due to some setbacks and related expenses.[26]
difficulties, the Project was not completed on 15 November 1982 as Both petitioner Philguarantee and respondent VPECI sought the
scheduled. But in October 1982, upon foreseeing the impossibility of assistance of some government agencies of the Philippines. On 10 August
meeting the deadline and upon the request of Al Ahli Bank, the joint 1987, VPECI requested the Central Bank to hold in abeyance the payment
venture contractor worked for the renewal or extension of the Performance by the petitioner to allow the diplomatic machinery to take its course, for
Bond and Advance Payment Guarantee. Petitioners Letters of Guarantee otherwise, the Philippine government , through the Philguarantee and the
Nos. 81-194-F (Performance Bond) and 81-195-F (Advance Payment Bond) Central Bank, would become instruments of the Iraqi Government in
with expiry date of 25 November 1982 were then renewed or extended to 9 consummating a clear act of injustice and inequity committed against a
February 1983 and 9 March 1983, respectively.[17] The surety bond was also Filipino contractor.[27]
extended for another period of one year, from 12 May 1982 to 12 May On 27 August 1987, the Central Bank authorized the remittance for its
1983.[18] The Performance Bond was further extended twelve times with account of the amount of US$876,564 (equivalent to ID271, 808/610) to Al
validity of up to 8 December 1986,[19] while the Advance Payment Ahli Bank representing full payment of the performance counter-guarantee
Guarantee was extended three times more up to 24 May 1984 when the for VPECIs project in Iraq. [28]
latter was cancelled after full refund or reimbursement by the joint venture On 6 November 1987, Philguarantee informed VPECI that it would
contractor.[20] The surety bond was likewise extended to 8 May 1987.[21] remit US$876,564 to Al Ahli Bank, and reiterated the joint and solidary
As of March 1986, the status of the Project was 51% accomplished, obligation of the respondents to reimburse the petitioner for the advances
meaning the structures were already finished. The remaining 47% consisted made on its counter-guarantee.[29]
in electro-mechanical works and the 2%, sanitary works, which both The petitioner thus paid the amount of US$876,564 to Al Ahli Bank
required importation of equipment and materials.[22] of Kuwait on 21 January 1988.[30] Then, on 6 May 1988, the petitioner paid
On 26 October 1986, Al Ahli Bank of Kuwait sent a telex call to the to Al Ahli Bank of Kuwait US$59,129.83 representing interest and penalty
petitioner demanding full payment of its performance bond counter- charges demanded by the latter bank.[31]
guarantee. On 19 June 1991, the petitioner sent to the respondents separate
Upon receiving a copy of that telex message on 27 October 1986, letters demanding full payment of the amount of P47,872,373.98 plus
respondent VPECI requested Iraq Trade and Economic Development accruing interest, penalty charges, and 10% attorneys fees pursuant to their
Minister Mohammad Fadhi Hussein to recall the telex call on the joint and solidary obligations under the deed of undertaking and surety
performance guarantee for being a drastic action in contravention of its bond.[32] When the respondents failed to pay, the petitioner filed on 9 July
mutual agreement with the latter that (1) the imposition of penalty would 1991 a civil case for collection of a sum of money against the respondents
be held in abeyance until the completion of the project; and (2) the time before the RTC of Makati City.
extension would be open, depending on the developments on the After due trial, the trial court ruled against Philguarantee and held that
negotiations for a foreign loan to finance the completion of the the latter had no valid cause of action against the respondents. It opined
project.[23] It also wrote SOB protesting the call for lack of factual or legal that at the time the call was made on the guarantee which was executed
basis, since the failure to complete the Project was due to (1) the Iraqi for a specific period, the guarantee had already lapsed or expired. There
governments lack of foreign exchange with which to pay its (VPECIs) was no valid renewal or extension of the guarantee for failure of the
accomplishments and (2) SOBs noncompliance for the past several years petitioner to secure respondents express consent thereto. The trial court
with the provision in the contract that 75% of the billings would be paid in also found that the joint venture contractor incurred no delay in the
US dollars.[24]Subsequently, or on 19 November 1986, respondent VPECI execution of the Project. Considering the Project owners violations of the
advised the petitioner not to pay yet Al Ahli Bank because efforts were contract which rendered impossible the joint venture contractors
being exerted for the amicable settlement of the Project.[25] performance of its undertaking, no valid call on the guarantee could be
made. Furthermore, the trial court held that no valid notice was first made PETITIONER CANNOT CLAIM SUBROGATION.
by the Project owner SOB to the joint venture contractor before the call on III
the guarantee. Accordingly, it dismissed the complaint, as well as the IT IS INIQUITOUS AND UNJUST FOR PETITIONER TO HOLD RESPONDENTS
counterclaims and cross-claim, and ordered the petitioner to pay attorneys LIABLE UNDER THEIR DEED OF UNDERTAKING.[36]
fees of P100,000 to respondents VPECI and Eusebio Spouses and P100,000 The main issue in this case is whether the petitioner is entitled to
to 3-Plex and the Santos Spouses, plus costs. [33] reimbursement of what it paid under Letter of Guarantee No. 81-194-F it
In its 14 June 1999 Decision,[34] the Court of Appeals affirmed the trial issued to Al Ahli Bank of Kuwait based on the deed of undertaking and
courts decision, ratiocinating as follows: surety bond from the respondents.
First, appellant cannot deny the fact that it was fully aware of the status of The petitioner asserts that since the guarantee it issued was absolute,
project implementation as well as the problems besetting the contractors, unconditional, and irrevocable the nature and extent of its liability are
between 1982 to 1985, having sent some of its people to Baghdad during analogous to those of suretyship. Its liability accrued upon the failure of the
that period. The successive renewals/extensions of the guarantees in fact, respondents to finish the construction of the Institute of Physical Therapy
was prompted by delays, not solely attributable to the contractors, and Buildings in Baghdad.
such extension understandably allowed by the SOB (project owner) which By guaranty a person, called the guarantor, binds himself to the
had not anyway complied with its contractual commitment to tender 75% creditor to fulfill the obligation of the principal debtor in case the latter
of payment in US Dollars, and which still retained overdue amounts should fail to do so. If a person binds himself solidarily with the principal
collectible by VPECI. debtor, the contract is called suretyship. [37]
Second, appellant was very much aware of the violations committed by Strictly speaking, guaranty and surety are nearly related, and many of
the SOB of its contractual undertakings with VPECI, principally, the the principles are common to both. In both contracts, there is a promise to
payment of foreign currency (US$) for 75% of the total contract price, as answer for the debt or default of another. However, in this jurisdiction, they
well as of the complications and injustice that will result from its payment may be distinguished thus:
of the full amount of the performance guarantee, as evident in 1. A surety is usually bound with his principal by the same
PHILGUARANTEEs letter dated 13 May 1987 . instrument executed at the same time and on the same
Third, appellant was fully aware that SOB was in fact still obligated to the consideration. On the other hand, the contract of guaranty is
Joint Venture and there was still an amount collectible from and still being the guarantor's own separate undertaking often supported by
retained by the project owner, which amount can be set-off with the sum a consideration separate from that supporting the contract of
covered by the performance guarantee. the principal; the original contract of his principal is not his
Fourth, well-apprised of the above conditions obtaining at the Project site contract.
and cognizant of the war situation at the time in Iraq, appellant, though 2. A surety assumes liability as a regular party to the undertaking;
earlier has made representations with the SOB regarding a possible while the liability of a guarantor is conditional depending on
amicable termination of the Project as suggested by VPECI, made a the failure of the primary debtor to pay the obligation.
complete turn-around and insisted on acting in favor of the unjustified call 3. The obligation of a surety is primary, while that of a guarantor
by the foreign banks.[35] is secondary.
The petitioner then came to this Court via Rule 45 of the Rules of Court 4. A surety is an original promissor and debtor from the beginning,
claiming that the Court of Appeals erred in affirming the trial courts ruling while a guarantor is charged on his own undertaking.
that 5. A surety is, ordinarily, held to know every default of his principal;
I whereas a guarantor is not bound to take notice of the non-
RESPONDENTS ARE NOT LIABLE UNDER THE DEED OF UNDERTAKING THEY performance of his principal.
EXECUTED IN FAVOR OF PETITIONER IN CONSIDERATION FOR THE ISSUANCE 6. Usually, a surety will not be discharged either by the mere
OF ITS COUNTER-GUARANTEE AND THAT PETITIONER CANNOT PASS ON TO indulgence of the creditor to the principal or by want of
RESPONDENTS WHAT IT HAD PAID UNDER THE SAID COUNTER-GUARANTEE. notice of the default of the principal, no matter how much he
II may be injured thereby. A guarantor is often discharged by
the mere indulgence of the creditor to the principal, and is Having determined petitioners liability as guarantor, the next question
usually not liable unless notified of the default of the we have to grapple with is whether the respondent contractor
principal. [38] has defaulted in its obligations that would justify resort to the guaranty. This
In determining petitioners status, it is necessary to read Letter of is a mixed question of fact and law that is better addressed by the lower
Guarantee No. 81-194-F, which provides in part as follows: courts, since this Court is not a trier of facts.
In consideration of your issuing the above performance It is a fundamental and settled rule that the findings of fact of the trial
guarantee/counter-guarantee, we hereby unconditionally and court and the Court of Appeals are binding or conclusive upon this Court
irrevocably guarantee, under our Ref. No. LG-81-194 F to pay you on your unless they are not supported by the evidence or unless strong and cogent
first written or telex demand Iraq Dinars Two Hundred Seventy One reasons dictate otherwise.[43] The factual findings of the Court of Appeals
Thousand Eight Hundred Eight and fils six hundred ten (ID271,808/610) are normally not reviewable by us under Rule 45 of the Rules of Court
representing 100% of the performance bond required of V.P. EUSEBIO for except when they are at variance with those of the trial court. [44] The trial
the construction of the Physical Therapy Institute, Phase II, Baghdad, Iraq, court and the Court of Appeals were in unison that the respondent
plus interest and other incidental expenses related thereto. contractor cannot be considered to have defaulted in its obligations
In the event of default by V.P. EUSEBIO, we shall pay you 100% of the because the cause of the delay was not primarily attributable to it.
obligation unpaid but in no case shall such amount exceed Iraq Dinars A corollary issue is what law should be applied in determining whether
(ID) 271,808/610 plus interest and other incidental expenses. (Emphasis the respondent contractor has defaulted in the performance of its
supplied)[39] obligations under the service contract. The question of whether there is a
Guided by the abovementioned distinctions between a surety and a breach of an agreement, which includes default or mora,[45] pertains to the
guaranty, as well as the factual milieu of this case, we find that the Court essential or intrinsic validity of a contract. [46]
of Appeals and the trial court were correct in ruling that the petitioner is a No conflicts rule on essential validity of contracts is expressly provided
guarantor and not a surety. That the guarantee issued by the petitioner is for in our laws. The rule followed by most legal systems, however, is that the
unconditional and irrevocable does not make the petitioner a surety. As a intrinsic validity of a contract must be governed by the lex
guaranty, it is still characterized by its subsidiary and conditional quality contractus or proper law of the contract. This is the law voluntarily agreed
because it does not take effect until the fulfillment of the condition, namely, upon by the parties (the lex loci voluntatis) or the law intended by them
that the principal obligor should fail in his obligation at the time and in the either expressly or implicitly (the lex loci intentionis). The law selected may
form he bound himself.[40] In other words, an unconditional guarantee is still be implied from such factors as substantial connection with the transaction,
subject to the condition that the principal debtor should default in his or the nationality or domicile of the parties.[47] Philippine courts would do
obligation first before resort to the guarantor could be had. A conditional well to adopt the first and most basic rule in most legal systems, namely, to
guaranty, as opposed to an unconditional guaranty, is one which depends allow the parties to select the law applicable to their contract, subject to
upon some extraneous event, beyond the mere default of the principal, the limitation that it is not against the law, morals, or public policy of the
and generally upon notice of the principals default and reasonable forum and that the chosen law must bear a substantive relationship to the
diligence in exhausting proper remedies against the principal.[41] transaction. [48]
It appearing that Letter of Guarantee No. 81-194-F merely stated that It must be noted that the service contract between SOB and VPECI
in the event of default by respondent VPECI the petitioner shall pay, the contains no express choice of the law that would govern it. In the United
obligation assumed by the petitioner was simply that of an unconditional States and Europe, the two rules that now seem to have emerged as kings
guaranty, not conditional guaranty. But as earlier ruled the fact that of the hill are (1) the parties may choose the governing law; and (2) in the
petitioners guaranty is unconditional does not make it a surety. Besides, absence of such a choice, the applicable law is that of the State that has
surety is never presumed. A party should not be considered a surety where the most significant relationship to the transaction and the
the contract itself stipulates that he is acting only as a guarantor. It is only parties.[49] Another authority proposed that all matters relating to the time,
when the guarantor binds himself solidarily with the principal debtor that place, and manner of performance and valid excuses for non-
the contract becomes one of suretyship.[42] performance are determined by the law of the place of performance or lex
loci solutionis, which is useful because it is undoubtedly always connected 5.3 That the Ministry of Labor and Employment of the Philippines requires
to the contract in a significant way.[50] the remittance into the Philippines of 70% of the salaries of Filipino workers
In this case, the laws of Iraq bear substantial connection to the working abroad in US Dollars;
transaction, since one of the parties is the Iraqi Government and the place 5.5 That the Iraqi Dinar is not a freely convertible currency such that the
of performance is in Iraq. Hence, the issue of whether respondent VPECI same cannot be used to purchase equipment, materials, supplies, etc.
defaulted in its obligations may be determined by the laws outside of Iraq;
of Iraq. However, since that foreign law was not properly pleaded or 5.6 That most of the materials specified by SOB in the CONTRACT are not
proved, the presumption of identity or similarity, otherwise known as available in Iraq and therefore have to be imported;
the processual presumption, comes into play. Where foreign law is not 5.7 That the government of Iraq prohibits the bringing of local currency
pleaded or, even if pleaded, is not proved, the presumption is that foreign (Iraqui Dinars) out of Iraq and hence, imported materials, equipment, etc.,
law is the same as ours.[51] cannot be purchased or obtained using Iraqui Dinars as medium of
Our law, specifically Article 1169, last paragraph, of the Civil Code, acquisition.
provides: In reciprocal obligations, neither party incurs in delay if the other 8. Following the approved construction program of the CONTRACT, upon
party does not comply or is not ready to comply in a proper manner with completion of the civil works portion of the installation of equipment for
what is incumbent upon him. the building, should immediately follow, however, the CONTRACT
Default or mora on the part of the debtor is the delay in the fulfillment specified that these equipment which are to be installed and to form part
of the prestation by reason of a cause imputable to the former. [52] It is the of the PROJECT have to be procured outside Iraq since these are not
non-fulfillment of an obligation with respect to time.[53] being locally manufactured. Copy f the relevant portion of the Technical
It is undisputed that only 51.7% of the total work had been Specification is hereto attached as Annex C and made an integral part
accomplished. The 48.3% unfinished portion consisted in the purchase and hereof;
installation of electro-mechanical equipment and materials, which were 10. Due to the lack of Foreign currency in Iraq for this purpose, and if only
available from foreign suppliers, thus requiring US Dollars for their to assist the Iraqi government in completing the PROJECT, the Contractor
importation. The monthly billings and payments made by SOB[54] reveal that without any obligation on its part to do so but with the knowledge and
the agreement between the parties was a periodic payment by the Project consent of SOB and the Ministry of Housing & Construction of Iraq, offered
owner to the contractor depending on the percentage of to arrange on behalf of SOB, a foreign currency loan, through the facilities
accomplishment within the period. [55] The payments were, in turn, to be of Circle International S.A., the Contractors Sub-contractor and SACE
used by the contractor to finance the subsequent phase of the MEDIO CREDITO which will act as the guarantor for this foreign currency
work. [56] However, as explained by VPECI in its letter to the Department of loan.
Foreign Affairs (DFA), the payment by SOB purely in Dinars adversely Arrangements were first made with Banco di Roma. Negotiation started in
affected the completion of the project; thus: June 1985. SOB is informed of the developments of this negotiation,
4. Despite protests from the plaintiff, SOB continued paying the attached is a copy of the draft of the loan Agreement between SOB as
accomplishment billings of the Contractor purely in Iraqi Dinars and which the Borrower and Agent. The Several Banks, as Lender, and counter-
payment came only after some delays. guaranteed by Istituto Centrale Per II Credito A Medio Termine
5. SOB is fully aware of the following: (Mediocredito) Sezione Speciale Per LAssicurazione Del Credito
5.2 That Plaintiff is a foreign contractor in Iraq and as such, would need AllExportazione (Sace). Negotiations went on and continued until it
foreign currency (US$), to finance the purchase of various equipment, suddenly collapsed due to the reported default by Iraq in the payment of
materials, supplies, tools and to pay for the cost of project management, its obligations with Italian government, copy of the news clipping dated
supervision and skilled labor not available in Iraq and therefore have to be June 18, 1986 is hereto attached as Annex D to form an integral part
imported and or obtained from the Philippines and other sources outside hereof;
Iraq. 15. On September 15, 1986, Contractor received information from Circle
International S.A. that because of the news report that Iraq defaulted in its
obligations with European banks, the approval by Banco di Roma of the
loan to SOB shall be deferred indefinitely, a copy of the letter of Circle creditor, SOB, which could be implied when the latter granted several
International together with the news clippings are hereto attached as extensions of time to the former. [60] Besides, no demand has yet been
Annexes F and F-1, respectively.[57] made by SOB against the respondent contractor. Demand is generally
As found by both the Court of Appeals and the trial court, the delay necessary even if a period has been fixed in the obligation. And default
or the non-completion of the Project was caused by factors not imputable generally begins from the moment the creditor demands judicially or extra-
to the respondent contractor. It was rather due mainly to the persistent judicially the performance of the obligation. Without such demand, the
violations by SOB of the terms and conditions of the contract, particularly effects of default will not arise.[61]
its failure to pay 75% of the accomplished work in US Dollars. Indeed, where Moreover, the petitioner as a guarantor is entitled to the benefit of
one of the parties to a contract does not perform in a proper manner the excussion, that is, it cannot be compelled to pay the creditor SOB unless
prestation which he is bound to perform under the contract, he is not the property of the debtor VPECI has been exhausted and all legal
entitled to demand the performance of the other party. A party does not remedies against the said debtor have been resorted to by the
incur in delay if the other party fails to perform the obligation incumbent creditor.[62] It could also set up compensation as regards what the creditor
upon him. SOB may owe the principal debtor VPECI.[63] In this case, however, the
The petitioner, however, maintains that the payments by SOB of the petitioner has clearly waived these rights and remedies by making the
monthly billings in purely Iraqi Dinars did not render impossible the payment of an obligation that was yet to be shown to be rightfully due the
performance of the Project by VPECI. Such posture is quite contrary to its creditor and demandable of the principal debtor.
previous representations. In his 26 March 1987 letter to the Office of the As found by the Court of Appeals, the petitioner fully knew that the
Middle Eastern and African Affairs (OMEAA), DFA, Manila, petitioners joint venture contractor had collectibles from SOB which could be set off
Executive Vice-President Jesus M. Taedo stated that while VPECI had taken with the amount covered by the performance guarantee. In February 1987,
every possible measure to complete the Project, the war situation in Iraq, the OMEAA transmitted to the petitioner a copy of a telex dated 10
particularly the lack of foreign exchange, was proving to be a great February 1987 of the Philippine Ambassador in Baghdad, Iraq, informing it
obstacle; thus: of the note verbale sent by the Iraqi Ministry of Foreign Affairs stating that
VPECI has taken every possible measure for the completion of the project the past due obligations of the joint venture contractor from the petitioner
but the war situation in Iraq particularly the lack of foreign exchange is would be deducted from the dues of the two contractors.[64]
proving to be a great obstacle. Our performance counterguarantee was Also, in the project situationer attached to the letter to the OMEAA
called last 26 October 1986 when the negotiations for a foreign currency dated 26 March 1987, the petitioner raised as among the arguments to be
loan with the Italian government through Banco de Roma bogged down presented in support of the cancellation of the counter-guarantee the fact
following news report that Iraq has defaulted in its obligation with major that the amount of ID281,414/066 retained by SOB from the Project was
European banks. Unless the situation in Iraq is improved as to allay the more than enough to cover the counter-guarantee of ID271,808/610; thus:
banks apprehension, there is no assurance that the project will ever be 6.1 Present the following arguments in cancelling the counterguarantee:
completed. [58] The Iraqi Government does not have the foreign
In order that the debtor may be in default it is necessary that the exchange to fulfill its contractual obligations of paying
following requisites be present: (1) that the obligation be demandable and 75% of progress billings in US dollars.
already liquidated; (2) that the debtor delays performance; and (3) that It could also be argued that the amount of
the creditor requires the performance because it must appear that the ID281,414/066 retained by SOB from the proposed
tolerance or benevolence of the creditor must have ended. [59] project is more than the amount of the outstanding
As stated earlier, SOB cannot yet demand complete performance counterguarantee.[65]
from VPECI because it has not yet itself performed its obligation in a proper In a nutshell, since the petitioner was aware of the contractors
manner, particularly the payment of the 75% of the cost of the Project in US outstanding receivables from SOB, it should have set up compensation as
Dollars. The VPECI cannot yet be said to have incurred in delay. Even was proposed in its project situationer.
assuming that there was delay and that the delay was attributable to
VPECI, still the effects of that delay ceased upon the renunciation by the
Moreover, the petitioner was very much aware of the predicament of undue payment on the guaranty. Rights under the deed of undertaking
the respondents. In fact, in its 13 May 1987 letter to the OMEAA, and the surety bond do not arise because these contracts depend on the
DFA, Manila, it stated: validity of the enforcement of the guaranty.
VPECI also maintains that the delay in the completion of the project was The petitioner guarantor should have waited for the natural course of
mainly due to SOBs violation of contract terms and as such, call on the guaranty: the debtor VPECI should have, in the first place, defaulted in its
guarantee has no basis. obligation and that the creditor SOB should have first made a demand from
While PHILGUARANTEE is prepared to honor its commitment under the the principal debtor. It is only when the debtor does not or cannot pay, in
guarantee, PHILGUARANTEE does not want to be an instrument in any whole or in part, that the guarantor should pay.[71] When the petitioner
case of inequity committed against a Filipino contractor. It is for this guarantor in this case paid against the will of the debtor VPECI, the debtor
reason that we are constrained to seek your assistance not only in VPECI may set up against it defenses available against the creditor SOB at
ascertaining the veracity of Al Ahli Banks claim that it has paid Rafidain the time of payment. This is the hard lesson that the petitioner must learn.
Bank but possibly averting such an event. As any payment effected by As the government arm in pursuing its objective of providing the
the banks will complicate matters, we cannot help underscore the necessary support and assistance in order to enable [Filipino exporters and
urgency of VPECIs bid for government intervention for the amicable contractors to operate viably under the prevailing economic and business
termination of the contract and release of the performance conditions,[72] the petitioner should have exercised prudence and caution
guarantee. [66] under the circumstances. As aptly put by the Court of Appeals, it would be
But surprisingly, though fully cognizant of SOBs violations of the service the height of inequity to allow the petitioner to pass on its losses to the
contract and VPECIs outstanding receivables from SOB, as well as the Filipino contractor VPECI which had sternly warned against paying the Al
situation obtaining in the Project site compounded by the Iran-Iraq war, the Ahli Bank and constantly apprised it of the developments in the Project
petitioner opted to pay the second layer guarantor not only the full amount implementation.
of the performance bond counter-guarantee but also interests and penalty WHEREFORE, the petition for review on certiorari is hereby DENIED for
charges. lack of merit, and the decision of the Court of appeals in CA-G.R. CV No.
This brings us to the next question: May the petitioner as a guarantor 39302 is AFFIRMED.
secure reimbursement from the respondents for what it has paid under No pronouncement as to costs.
Letter of Guarantee No. 81-194-F? SO ORDERED.
As a rule, a guarantor who pays for a debtor should be indemnified by
the latter[67] and would be legally subrogated to the rights which the
creditor has against the debtor.[68] However, a person who makes payment
without the knowledge or against the will of the debtor has the right to
recover only insofar as the payment has been beneficial to the debtor.[69] If
the obligation was subject to defenses on the part of the debtor, the same
defenses which could have been set up against the creditor can be set up
against the paying guarantor.[70]
From the findings of the Court of Appeals and the trial court, it is clear
that the payment made by the petitioner guarantor did not in any way
benefit the principal debtor, given the project status and the conditions
obtaining at the Project site at that time. Moreover, the respondent
contractor was found to have valid defenses against SOB, which are fully
supported by evidence and which have been meritoriously set up against
the paying guarantor, the petitioner in this case. And even if the deed of
undertaking and the surety bond secured petitioners guaranty, the
petitioner is precluded from enforcing the same by reason of the petitioners
KOREA TECHNOLOGIES CO., G.R. No. 143581 Carmona, Cavite. The contract was executed in the Philippines. On April
LTD., 7, 1997, the parties executed, in Korea, an Amendment for Contract No.
Petitioner, KLP-970301 dated March 5, 1997[2] amending the terms of payment. The
Present: contract and its amendment stipulated that KOGIES will ship the
- versus - QUISUMBING, J., Chairperson, machinery and facilities necessary for manufacturing LPG cylinders for
CARPIO, which PGSMC would pay USD 1,224,000. KOGIES would install and initiate
CARPIO MORALES, the operation of the plant for which PGSMC bound itself to pay USD
HON. ALBERTO A. LERMA, in TINGA, and 306,000 upon the plants production of the 11-kg. LPG cylinder
his capacity as Presiding Judge of VELASCO, JR., JJ. samples. Thus, the total contract price amounted to USD 1,530,000.
Branch 256 of Regional Trial
Court of Muntinlupa City, and On October 14, 1997, PGSMC entered into a Contract of Lease [3] with
PACIFIC GENERAL STEEL Promulgated: Worth Properties, Inc. (Worth) for use of Worths 5,079-square meter
MANUFACTURING property with a 4,032-square meter warehouse building to house the LPG
CORPORATION, manufacturing plant. The monthly rental was PhP 322,560 commencing
Respondents. January 7, 2008 on January 1, 1998 with a 10% annual increment clause. Subsequently, the
x-----------------------------------------------------------------------------------------x machineries, equipment, and facilities for the manufacture of LPG
cylinders were shipped, delivered, and installed in the Carmona
DECISION plant. PGSMC paid KOGIES USD 1,224,000.

However, gleaned from the Certificate[4] executed by the parties on


VELASCO, JR., J.: January 22, 1998, after the installation of the plant, the initial operation
could not be conducted as PGSMC encountered financial difficulties
In our jurisdiction, the policy is to favor alternative methods of resolving affecting the supply of materials, thus forcing the parties to agree that
disputes, particularly in civil and commercial disputes. Arbitration along KOGIES would be deemed to have completely complied with the terms
with mediation, conciliation, and negotiation, being inexpensive, speedy and conditions of the March 5, 1997 contract.
and less hostile methods have long been favored by this Court. The
petition before us puts at issue an arbitration clause in a contract mutually For the remaining balance of USD306,000 for the installation and initial
agreed upon by the parties stipulating that they would submit themselves operation of the plant, PGSMC issued two postdated checks: (1) BPI
to arbitration in a foreign country. Regrettably, instead of hastening the Check No. 0316412 dated January 30, 1998 for PhP 4,500,000; and (2)BPI
resolution of their dispute, the parties wittingly or unwittingly prolonged the Check No. 0316413 dated March 30, 1998 for PhP 4,500,000.[5]
controversy.
When KOGIES deposited the checks, these were dishonored for the
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a Korean corporation reason PAYMENT STOPPED. Thus, on May 8, 1998, KOGIES sent a demand
which is engaged in the supply and installation of Liquefied Petroleum letter[6] to PGSMC threatening criminal action for violation of Batas
Gas (LPG) Cylinder manufacturing plants, while private respondent Pacific Pambansa Blg. 22 in case of nonpayment. On the same date, the wife of
General Steel Manufacturing Corp. (PGSMC) is a domestic corporation. PGSMCs President faxed a letter dated May 7, 1998 to KOGIES President
who was then staying at a Makati City hotel. She complained that not
On March 5, 1997, PGSMC and KOGIES executed a Contract[1] whereby only did KOGIES deliver a different brand of hydraulic press from that
KOGIES would set up an LPG Cylinder Manufacturing Plant in
agreed upon but it had not delivered several equipment parts already plant operational although it earlier certified to the contrary as shown in a
paid for. January 22, 1998 Certificate. Likewise, KOGIES averred that PGSMC
violated Art. 15 of their Contract, as amended, by unilaterally rescinding
On May 14, 1998, PGSMC replied that the two checks it issued KOGIES the contract without resorting to arbitration. KOGIES also asked that
were fully funded but the payments were stopped for reasons previously PGSMC be restrained from dismantling and transferring the machinery
made known to KOGIES.[7] and equipment installed in the plant which the latter threatened to do
on July 4, 1998.
On June 1, 1998, PGSMC informed KOGIES that PGSMC was canceling
their Contract dated March 5, 1997 on the ground that KOGIES had On July 9, 1998, PGSMC filed an opposition to the TRO arguing that
altered the quantity and lowered the quality of the machineries and KOGIES was not entitled to the TRO since Art. 15, the arbitration clause,
equipment it delivered to PGSMC, and that PGSMC would dismantle and was null and void for being against public policy as it ousts the local courts
transfer the machineries, equipment, and facilities installed in the of jurisdiction over the instant controversy.
Carmona plant. Five days later, PGSMC filed before the Office of the
Public Prosecutor an Affidavit-Complaint for Estafa docketed as I.S. No. On July 17, 1998, PGSMC filed its Answer with Compulsory
98-03813 against Mr. Dae Hyun Kang, President of KOGIES. Counterclaim[9] asserting that it had the full right to dismantle and transfer
the machineries and equipment because it had paid for them in full as
On June 15, 1998, KOGIES wrote PGSMC informing the latter that PGSMC stipulated in the contract; that KOGIES was not entitled to the PhP
could not unilaterally rescind their contract nor dismantle and transfer the 9,000,000 covered by the checks for failing to completely install and make
machineries and equipment on mere imagined violations by KOGIES. It the plant operational; and that KOGIES was liable for damages
also insisted that their disputes should be settled by arbitration as agreed amounting to PhP 4,500,000 for altering the quantity and lowering the
upon in Article 15, the arbitration clause of their contract. quality of the machineries and equipment. Moreover, PGSMC averred
that it has already paid PhP 2,257,920 in rent (covering January to July
On June 23, 1998, PGSMC again wrote KOGIES reiterating the contents of 1998) to Worth and it was not willing to further shoulder the cost of renting
its June 1, 1998 letter threatening that the machineries, equipment, and the premises of the plant considering that the LPG cylinder manufacturing
facilities installed in the plant would be dismantled and transferred on July plant never became operational.
4, 1998. Thus, on July 1, 1998, KOGIES instituted an Application for
Arbitration before the Korean Commercial Arbitration Board (KCAB) After the parties submitted their Memoranda, on July 23, 1998, the RTC
in Seoul, Korea pursuant to Art. 15 of the Contract as amended. issued an Order denying the application for a writ of preliminary
injunction, reasoning that PGSMC had paid KOGIES USD 1,224,000, the
On July 3, 1998, KOGIES filed a Complaint for Specific Performance, value of the machineries and equipment as shown in the contract such
docketed as Civil Case No. 98-117[8] against PGSMC before the that KOGIES no longer had proprietary rights over them. And finally, the
Muntinlupa City Regional Trial Court (RTC). The RTC granted a temporary RTC held that Art. 15 of the Contract as amended was invalid as it tended
restraining order (TRO) on July 4, 1998, which was subsequently extended to oust the trial court or any other court jurisdiction over any dispute that
until July 22, 1998. In its complaint, KOGIES alleged that PGSMC had may arise between the parties. KOGIES prayer for an injunctive writ was
initially admitted that the checks that were stopped were not funded but denied.[10] The dispositive portion of the Order stated:
later on claimed that it stopped payment of the checks for the reason
that their value was not received as the former allegedly breached their
contract by altering the quantity and lowering the quality of the WHEREFORE, in view of the foregoing consideration, this Court believes
machinery and equipment installed in the plant and failed to make the and so holds that no cogent reason exists for this Court to grant the writ of
preliminary injunction to restrain and refrain defendant from dismantling queries and issues raised in the motion for inspection fell under the
the machineries and facilities at the lot and building of Worth Properties, coverage of the arbitration clause in their contract.
Incorporated at Carmona, Cavite and transfer the same to another site:
and therefore denies plaintiffs application for a writ of preliminary On September 21, 1998, the trial court issued an Order (1) granting
injunction. PGSMCs motion for inspection; (2) denying KOGIES motion for
reconsideration of the July 23, 1998 RTC Order; and (3) denying KOGIES
motion to dismiss PGSMCs compulsory counterclaims as these
counterclaims fell within the requisites of compulsory counterclaims.
On July 29, 1998, KOGIES filed its Reply to Answer and Answer to
Counterclaim.[11] KOGIES denied it had altered the quantity and lowered On October 2, 1998, KOGIES filed an Urgent Motion for
the quality of the machinery, equipment, and facilities it delivered to the Reconsideration[17] of the September 21, 1998 RTC Order granting
plant. It claimed that it had performed all the undertakings under the inspection of the plant and denying dismissal of PGSMCs compulsory
contract and had already produced certified samples of LPG cylinders. It counterclaims.
averred that whatever was unfinished was PGSMCs fault since it failed to
procure raw materials due to lack of funds. KOGIES, relying on Chung Fu Ten days after, on October 12, 1998, without waiting for the resolution of its
Industries (Phils.), Inc. v. Court of Appeals,[12] insisted that the arbitration October 2, 1998 urgent motion for reconsideration, KOGIES filed before
clause was without question valid. the Court of Appeals (CA) a petition for certiorari [18] docketed as CA-G.R.
SP No. 49249, seeking annulment of the July 23, 1998 and September 21,
After KOGIES filed a Supplemental Memorandum with Motion to 1998 RTC Orders and praying for the issuance of writs of prohibition,
Dismiss[13] answering PGSMCs memorandum of July 22, 1998 and seeking mandamus, and preliminary injunction to enjoin the RTC and PGSMC from
dismissal of PGSMCs counterclaims, KOGIES, on August 4, 1998,filed its inspecting, dismantling, and transferring the machineries and equipment
Motion for Reconsideration[14] of the July 23, 1998 Order denying its in the Carmona plant, and to direct the RTC to enforce the specific
application for an injunctive writ claiming that the contract was not agreement on arbitration to resolve the dispute.
merely for machinery and facilities worth USD 1,224,000 but was for the
sale of an LPG manufacturing plant consisting of supply of all the In the meantime, on October 19, 1998, the RTC denied KOGIES urgent
machinery and facilities and transfer of technology for a total contract motion for reconsideration and directed the Branch Sheriff to proceed
price of USD 1,530,000 such that the dismantling and transfer of the with the inspection of the machineries and equipment in the plant
machinery and facilities would result in the dismantling and transfer of the on October 28, 1998.[19]
very plant itself to the great prejudice of KOGIES as the still unpaid
owner/seller of the plant. Moreover, KOGIES points out that the arbitration Thereafter, KOGIES filed a Supplement to the Petition[20] in CA-G.R. SP No.
clause under Art. 15 of the Contract as amended was a valid arbitration 49249 informing the CA about the October 19, 1998 RTC Order. It also
stipulation under Art. 2044 of the Civil Code and as held by this Court reiterated its prayer for the issuance of the writs of prohibition, mandamus
in Chung Fu Industries (Phils.), Inc.[15] and preliminary injunction which was not acted upon by the CA. KOGIES
asserted that the Branch Sheriff did not have the technical expertise to
In the meantime, PGSMC filed a Motion for Inspection of Things [16] to ascertain whether or not the machineries and equipment conformed to
determine whether there was indeed alteration of the quantity and the specifications in the contract and were properly installed.
lowering of quality of the machineries and equipment, and whether these
were properly installed. KOGIES opposed the motion positing that the
On November 11, 1998, the Branch Sheriff filed his Sheriffs Report [21] finding Hence, we have this Petition for Review on Certiorari under Rule 45.
that the enumerated machineries and equipment were not fully and
properly installed. The Issues

The Court of Appeals affirmed the trial court and declared Petitioner posits that the appellate court committed the following errors:
the arbitration clause against public policy a. PRONOUNCING THE QUESTION OF OWNERSHIP OVER THE MACHINERY
AND FACILITIES AS A QUESTION OF FACT BEYOND THE AMBIT OF A PETITION
FOR CERTIORARI INTENDED ONLY FOR CORRECTION OF ERRORS OF
On May 30, 2000, the CA rendered the assailed Decision[22] affirming the JURISDICTION OR GRAVE ABUSE OF DISCRETION AMOUNTING TO LACK OF
RTC Orders and dismissing the petition for certiorari filed by KOGIES. The (SIC) EXCESS OF JURISDICTION, AND CONCLUDING THAT THE TRIAL COURTS
CA found that the RTC did not gravely abuse its discretion in issuing the FINDING ON THE SAME QUESTION WAS IMPROPERLY RAISED IN THE PETITION
assailed July 23, 1998 and September 21, 1998 Orders. Moreover, the CA BELOW;
reasoned that KOGIES contention that the total contract price for USD
1,530,000 was for the whole plant and had not been fully paid was b. DECLARING AS NULL AND VOID THE ARBITRATION CLAUSE IN ARTICLE 15
contrary to the finding of the RTC that PGSMC fully paid the price of USD OF THE CONTRACT BETWEEN THE PARTIES FOR BEING CONTRARY TO PUBLIC
1,224,000, which was for all the machineries and equipment. According to POLICY AND FOR OUSTING THE COURTS OF JURISDICTION;
the CA, this determination by the RTC was a factual finding beyond the
ambit of a petition for certiorari. c. DECREEING PRIVATE RESPONDENTS COUNTERCLAIMS TO BE
ALL COMPULSORY NOT NECESSITATING PAYMENT OF DOCKET FEES AND
On the issue of the validity of the arbitration clause, the CA agreed with CERTIFICATION OF NON-FORUM SHOPPING;
the lower court that an arbitration clause which provided for a final
determination of the legal rights of the parties to the contract by d. RULING THAT THE PETITION WAS FILED PREMATURELY WITHOUT
arbitration was against public policy. WAITING FOR THE RESOLUTION OF THE MOTION FOR RECONSIDERATION OF
THE ORDER DATED SEPTEMBER 21, 1998 OR WITHOUT GIVING THE TRIAL
On the issue of nonpayment of docket fees and non-attachment of a COURT AN OPPORTUNITY TO CORRECT ITSELF;
certificate of non-forum shopping by PGSMC, the CA held that the
counterclaims of PGSMC were compulsory ones and payment of docket e. PROCLAIMING THE TWO ORDERS DATED JULY 23
fees was not required since the Answer with counterclaim was not an AND SEPTEMBER 21, 1998 NOT TO BE PROPER SUBJECTS OF CERTIORARI
initiatory pleading. For the same reason, the CA said a certificate of non- AND PROHIBITION FOR BEING INTERLOCUTORY IN NATURE;
forum shopping was also not required.
f. NOT GRANTING THE RELIEFS AND REMEDIES PRAYED FOR IN HE
Furthermore, the CA held that the petition for certiorari had been filed (SIC) PETITION AND, INSTEAD, DISMISSING THE SAME FOR ALLEGEDLY
prematurely since KOGIES did not wait for the resolution of its urgent WITHOUT MERIT.[23]
motion for reconsideration of the September 21, 1998 RTC Order which
was the plain, speedy, and adequate remedy available. According to
the CA, the RTC must be given the opportunity to correct any alleged The Courts Ruling
error it has committed, and that since the assailed orders were
interlocutory, these cannot be the subject of a petition for certiorari. The petition is partly meritorious.
Before we delve into the substantive issues, we shall first tackle the Citing Gamboa v. Cruz,[25] the CA also pronounced that certiorari and
procedural issues. Prohibition are neither the remedies to question the propriety of an
interlocutory order of the trial court.[26] The CA erred on its reliance
The rules on the payment of docket fees for counterclaims on Gamboa. Gamboa involved the denial of a motion to acquit in a
and cross claims were amended effective August 16, 2004 criminal case which was not assailable in an action for certiorari since the
denial of a motion to quash required the accused to plead and to
KOGIES strongly argues that when PGSMC filed the counterclaims, it continue with the trial, and whatever objections the accused had in his
should have paid docket fees and filed a certificate of non-forum motion to quash can then be used as part of his defense and
shopping, and that its failure to do so was a fatal defect. subsequently can be raised as errors on his appeal if the judgment of the
trial court is adverse to him. The general rule is that interlocutory orders
We disagree with KOGIES. cannot be challenged by an appeal.[27] Thus, in Yamaoka v. Pescarich
Manufacturing Corporation, we held:
As aptly ruled by the CA, the counterclaims of PGSMC were incorporated
in its Answer with Compulsory Counterclaim dated July 17, 1998 in The proper remedy in such cases is an ordinary appeal from an adverse
accordance with Section 8 of Rule 11, 1997 Revised Rules of Civil judgment on the merits, incorporating in said appeal the grounds for
Procedure, the rule that was effective at the time the Answer with assailing the interlocutory orders. Allowing appeals from interlocutory
Counterclaim was filed. Sec. 8 on existing counterclaim or cross- orders would result in the sorry spectacle of a case being subject of a
claim states, A compulsory counterclaim or a cross-claim that a counterproductive ping-pong to and from the appellate court as often as
defending party has at the time he files his answer shall be contained a trial court is perceived to have made an error in any of its interlocutory
therein. rulings. However, where the assailed interlocutory order was issued with
grave abuse of discretion or patently erroneous and the remedy of
appeal would not afford adequate and expeditious relief, the Court
On July 17, 1998, at the time PGSMC filed its Answer incorporating its allows certiorari as a mode of redress.[28]
counterclaims against KOGIES, it was not liable to pay filing fees for said
counterclaims being compulsory in nature. We stress, however, that
effective August 16, 2004 under Sec. 7, Rule 141, as amended by A.M. No. Also, appeals from interlocutory orders would open the floodgates to
04-2-04-SC, docket fees are now required to be paid in compulsory endless occasions for dilatory motions. Thus, where the interlocutory order
counterclaim or cross-claims. was issued without or in excess of jurisdiction or with grave abuse of
discretion, the remedy is certiorari.[29]
As to the failure to submit a certificate of forum shopping, PGSMCs Answer
is not an initiatory pleading which requires a certification against forum The alleged grave abuse of discretion of the respondent court equivalent
shopping under Sec. 5[24] of Rule 7, 1997 Revised Rules of Civil Procedure. It to lack of jurisdiction in the issuance of the two assailed orders coupled
is a responsive pleading, hence, the courts a quo did not commit with the fact that there is no plain, speedy, and adequate remedy in the
reversible error in denying KOGIES motion to dismiss PGSMCs compulsory ordinary course of law amply provides the basis for allowing the resort to a
counterclaims. petition for certiorari under Rule 65.

Interlocutory orders proper subject of certiorari Prematurity of the petition before the CA
Neither do we think that KOGIES was guilty of forum shopping in filing the
petition for certiorari. Note that KOGIES motion for reconsideration of the
July 23, 1998 RTC Order which denied the issuance of the injunctive writ Petitioner claims the RTC and the CA erred in ruling that the arbitration
had already been denied. Thus, KOGIES only remedy was to assail the clause is null and void.
RTCs interlocutory order via a petition for certiorari under Rule 65.
Petitioner is correct.
While the October 2, 1998 motion for reconsideration of KOGIES of the
September 21, 1998 RTC Order relating to the inspection of things, and the Established in this jurisdiction is the rule that the law of the place where the
allowance of the compulsory counterclaims has not yet been resolved, contract is made governs. Lex loci contractus. The contract in this case
the circumstances in this case would allow an exception to the rule that was perfected here in the Philippines. Therefore, our laws ought to
before certiorari may be availed of, the petitioner must have filed a govern. Nonetheless, Art. 2044 of the Civil Code sanctions the validity of
motion for reconsideration and said motion should have been first mutually agreed arbitral clause or the finality and binding effect of an
resolved by the court a quo. The reason behind the rule is to enable the arbitral award. Art. 2044 provides, Any stipulation that the arbitrators
lower court, in the first instance, to pass upon and correct its mistakes award or decision shall be final, is valid, without prejudice to Articles 2038,
without the intervention of the higher court.[30] 2039 and 2040. (Emphasis supplied.)

The September 21, 1998 RTC Order directing the branch sheriff to inspect Arts. 2038,[31] 2039,[32] and 2040[33] abovecited refer to instances where a
the plant, equipment, and facilities when he is not competent and compromise or an arbitral award, as applied to Art. 2044 pursuant to Art.
knowledgeable on said matters is evidently flawed and devoid of any 2043,[34] may be voided, rescinded, or annulled, but these would not
legal support. Moreover, there is an urgent necessity to resolve the issue denigrate the finality of the arbitral award.
on the dismantling of the facilities and any further delay would prejudice
the interests of KOGIES. Indeed, there is real and imminent threat of The arbitration clause was mutually and voluntarily agreed upon by the
irreparable destruction or substantial damage to KOGIES equipment and parties. It has not been shown to be contrary to any law, or against
machineries. We find the resort to certiorari based on the gravely abusive morals, good customs, public order, or public policy. There has been no
orders of the trial court sans the ruling on the October 2, 1998 motion for showing that the parties have not dealt with each other on equal
reconsideration to be proper. footing. We find no reason why the arbitration clause should not be
respected and complied with by both parties. In Gonzales v. Climax
The Core Issue: Article 15 of the Contract Mining Ltd.,[35] we held that submission to arbitration is a contract and that
a clause in a contract providing that all matters in dispute between the
We now go to the core issue of the validity of Art. 15 of the Contract, the parties shall be referred to arbitration is a contract.[36] Again in Del Monte
arbitration clause. It provides: Corporation-USA v. Court of Appeals, we likewise ruled that [t]he provision
to submit to arbitration any dispute arising therefrom and the relationship
Article 15. Arbitration.All disputes, controversies, or differences which may of the parties is part of that contract and is itself a contract.[37]
arise between the parties, out of or in relation to or in connection with this
Contract or for the breach thereof, shall finally be settled by arbitration in Arbitration clause not contrary to public policy
Seoul, Korea in accordance with the Commercial Arbitration Rules of the
Korean Commercial Arbitration Board. The award rendered by the The arbitration clause which stipulates that the arbitration must be done
arbitration(s) shall be final and binding upon both parties in Seoul, Korea in accordance with the Commercial Arbitration Rules of
concerned. (Emphasis supplied.) the KCAB, and that the arbitral award is final and binding, is not contrary
to public policy. This Court has sanctioned the validity of arbitration For domestic arbitration proceedings, we have particular agencies to
clauses in a catena of cases. In the 1957 case of Eastboard Navigation arbitrate disputes arising from contractual relations. In case a foreign
Ltd. v. Juan Ysmael and Co., Inc.,[38] this Court had occasion to rule that arbitral body is chosen by the parties, the arbitration rules of our domestic
an arbitration clause to resolve differences and breaches of mutually arbitration bodies would not be applied. As signatory to the Arbitration
agreed contractual terms is valid. In BF Corporation v. Court of Appeals, Rules of the UNCITRAL Model Law on International Commercial
we held that [i]n this jurisdiction, arbitration has been held valid and Arbitration[41] of the United Nations Commission on International Trade Law
constitutional. Even before the approval on June 19, 1953 of Republic Act (UNCITRAL) in the New York Convention on June 21, 1985,
No. 876, this Court has countenanced the settlement of disputes through the Philippines committed itself to be bound by the Model Law. We have
arbitration. Republic Act No. 876 was adopted to supplement the New even incorporated the Model Law in Republic Act No. (RA) 9285,
Civil Codes provisions on arbitration.[39] And in LM Power Engineering otherwise known as the Alternative Dispute Resolution Act of
Corporation v. Capitol Industrial Construction Groups, Inc., we declared 2004 entitled An Act to Institutionalize the Use of an Alternative Dispute
that: Resolution System in the Philippines and to Establish the Office for
Alternative Dispute Resolution, and for Other Purposes, promulgated on
Being an inexpensive, speedy and amicable method of settling April 2, 2004. Secs. 19 and 20 of Chapter 4 of the Model Law are the
disputes, arbitrationalong with mediation, conciliation and negotiationis pertinent provisions:
encouraged by the Supreme Court. Aside from unclogging judicial
dockets, arbitration also hastens the resolution of disputes, especially of CHAPTER 4 - INTERNATIONAL COMMERCIAL ARBITRATION
the commercial kind. It is thus regarded as the wave of the future in
international civil and commercial disputes. Brushing aside a contractual SEC. 19. Adoption of the Model Law on International Commercial
agreement calling for arbitration between the parties would be a step Arbitration.International commercial arbitration shall be governed by the
backward. Model Law on International Commercial Arbitration (the Model Law)
adopted by the United Nations Commission on International Trade Law on
Consistent with the above-mentioned policy of encouraging alternative June 21, 1985 (United Nations Document A/40/17) and recommended for
dispute resolution methods, courts should liberally construe arbitration enactment by the General Assembly in Resolution No. 40/72 approved on
clauses. Provided such clause is susceptible of an interpretation that December 11, 1985, copy of which is hereto attached as Appendix A.
covers the asserted dispute, an order to arbitrate should be granted. Any
doubt should be resolved in favor of arbitration.[40] SEC. 20. Interpretation of Model Law.In interpreting the Model Law, regard
shall be had to its international origin and to the need for uniformity in its
interpretation and resort may be made to the travaux preparatories and
Having said that the instant arbitration clause is not against public policy, the report of the Secretary General of the United Nations Commission on
we come to the question on what governs an arbitration clause International Trade Law dated March 25, 1985 entitled, International
specifying that in case of any dispute arising from the contract, an arbitral Commercial Arbitration: Analytical Commentary on Draft Trade identified
panel will be constituted in a foreign country and the arbitration rules of by reference number A/CN. 9/264.
the foreign country would govern and its award shall be final and binding.

RA 9285 incorporated the UNCITRAL Model law


to which we are a signatory While RA 9285 was passed only in 2004, it nonetheless applies in the instant
case since it is a procedural law which has a retroactive effect. Likewise,
KOGIES filed its application for arbitration before the KCAB on July 1,
1998 and it is still pending because no arbitral award has yet been SEC. 42. Application of the New York Convention.The New York
rendered. Thus, RA 9285 is applicable to the instant case. Well-settled is Convention shall govern the recognition and enforcement of arbitral
the rule that procedural laws are construed to be applicable to actions awards covered by said Convention.
pending and undetermined at the time of their passage, and are
deemed retroactive in that sense and to that extent. As a general rule, The recognition and enforcement of such arbitral awards shall be filed
the retroactive application of procedural laws does not violate any with the Regional Trial Court in accordance with the rules of procedure to
personal rights because no vested right has yet attached nor arisen from be promulgated by the Supreme Court. Said procedural rules shall
them.[42] provide that the party relying on the award or applying for its
enforcement shall file with the court the original or authenticated copy of
Among the pertinent features of RA 9285 applying and incorporating the the award and the arbitration agreement. If the award or agreement is
UNCITRAL Model Law are the following: not made in any of the official languages, the party shall supply a duly
certified translation thereof into any of such languages.
(1) The RTC must refer to arbitration in proper cases
The applicant shall establish that the country in which foreign arbitration
Under Sec. 24, the RTC does not have jurisdiction over disputes that are award was made in party to the New York Convention.
properly the subject of arbitration pursuant to an arbitration clause, and
mandates the referral to arbitration in such cases, thus: xxxx

SEC. 24. Referral to Arbitration.A court before which an action is brought in SEC. 43. Recognition and Enforcement of Foreign Arbitral Awards Not
a matter which is the subject matter of an arbitration agreement shall, if Covered by the New York Convention.The recognition and enforcement
at least one party so requests not later than the pre-trial conference, or of foreign arbitral awards not covered by the New York Convention shall
upon the request of both parties thereafter, refer the parties to arbitration be done in accordance with procedural rules to be promulgated by the
unless it finds that the arbitration agreement is null and void, inoperative or Supreme Court. The Court may, on grounds of comity and reciprocity,
incapable of being performed. recognize and enforce a non-convention award as a convention award.

SEC. 44. Foreign Arbitral Award Not Foreign Judgment.A foreign arbitral
award when confirmed by a court of a foreign country, shall be
recognized and enforced as a foreign arbitral award and not as a
(2) Foreign arbitral awards must be confirmed by the RTC judgment of a foreign court.

Foreign arbitral awards while mutually stipulated by the parties in the A foreign arbitral award, when confirmed by the Regional Trial Court, shall
arbitration clause to be final and binding are not immediately be enforced in the same manner as final and executory decisions of
enforceable or cannot be implemented immediately. Sec. 35[43] of the courts of law of the Philippines
UNCITRAL Model Law stipulates the requirement for the arbitral award to
be recognized by a competent court for enforcement, which court under xxxx
Sec. 36 of the UNCITRAL Model Law may refuse recognition or
enforcement on the grounds provided for. RA 9285 incorporated these SEC. 47. Venue and Jurisdiction.Proceedings for recognition and
provisos to Secs. 42, 43, and 44 relative to Secs. 47 and 48, thus: enforcement of an arbitration agreement or for vacations, setting aside,
correction or modification of an arbitral award, and any application with
a court for arbitration assistance and supervision shall be deemed as
special proceedings and shall be filed with the Regional Trial Court (i) The recognition and enforcement of such arbitral awards shall be filed
where arbitration proceedings are conducted; (ii) where the asset to be with the Regional Trial Court in accordance with the rules of procedure to
attached or levied upon, or the act to be enjoined is located; (iii) where be promulgated by the Supreme Court. Said procedural rules shall
any of the parties to the dispute resides or has his place of business; or (iv) provide that the party relying on the award or applying for its
in the National Judicial Capital Region, at the option of the applicant. enforcement shall file with the court the original or authenticated copy of
the award and the arbitration agreement. If the award or agreement is
SEC. 48. Notice of Proceeding to Parties.In a special proceeding for not made in any of the official languages, the party shall supply a duly
recognition and enforcement of an arbitral award, the Court shall send certified translation thereof into any of such languages.
notice to the parties at their address of record in the arbitration, or if any
part cannot be served notice at such address, at such partys last known The applicant shall establish that the country in which foreign arbitration
address. The notice shall be sent al least fifteen (15) days before the date award was made is party to the New York Convention.
set for the initial hearing of the application.
If the application for rejection or suspension of enforcement of an award
has been made, the Regional Trial Court may, if it considers it proper,
It is now clear that foreign arbitral awards when confirmed by the RTC are vacate its decision and may also, on the application of the party claiming
deemed not as a judgment of a foreign court but as a foreign arbitral recognition or enforcement of the award, order the party to provide
award, and when confirmed, are enforced as final and executory appropriate security.
decisions of our courts of law.
xxxx
Thus, it can be gleaned that the concept of a final and binding arbitral
award is similar to judgments or awards given by some of our quasi- SEC. 45. Rejection of a Foreign Arbitral Award.A party to a foreign
judicial bodies, like the National Labor Relations Commission and Mines arbitration proceeding may oppose an application for recognition and
Adjudication Board, whose final judgments are stipulated to be final and enforcement of the arbitral award in accordance with the procedures
binding, but not immediately executory in the sense that they may still be and rules to be promulgated by the Supreme Court only on those grounds
judicially reviewed, upon the instance of any party. Therefore, the final enumerated under Article V of the New York Convention. Any other
foreign arbitral awards are similarly situated in that they need first to be ground raised shall be disregarded by the Regional Trial Court.
confirmed by the RTC.

(3) The RTC has jurisdiction to review foreign arbitral awards


Thus, while the RTC does not have jurisdiction over disputes governed by
Sec. 42 in relation to Sec. 45 of RA 9285 designated and vested the RTC arbitration mutually agreed upon by the parties, still the foreign arbitral
with specific authority and jurisdiction to set aside, reject, or vacate a award is subject to judicial review by the RTC which can set aside, reject,
foreign arbitral award on grounds provided under Art. 34(2) of the or vacate it. In this sense, what this Court held in Chung Fu Industries
UNCITRAL Model Law. Secs. 42 and 45 provide: (Phils.), Inc. relied upon by KOGIES is applicable insofar as the foreign
arbitral awards, while final and binding, do not oust courts of jurisdiction
SEC. 42. Application of the New York Convention.The New York since these arbitral awards are not absolute and without exceptions as
Convention shall govern the recognition and enforcement of arbitral they are still judicially reviewable. Chapter 7 of RA 9285 has made it clear
awards covered by said Convention.
that all arbitral awards, whether domestic or foreign, are subject to Thereafter, the CA decision may further be appealed or reviewed before
judicial review on specific grounds provided for. this Court through a petition for review under Rule 45 of the Rules of Court.
(4) Grounds for judicial review different in domestic and foreign arbitral PGSMC has remedies to protect its interests
awards
Thus, based on the foregoing features of RA 9285, PGSMC must submit to
The differences between a final arbitral award from an international or the foreign arbitration as it bound itself through the subject
foreign arbitral tribunal and an award given by a local arbitral tribunal are contract. While it may have misgivings on the foreign arbitration done
the specific grounds or conditions that vest jurisdiction over our courts to in Koreaby the KCAB, it has available remedies under RA 9285. Its interests
review the awards. are duly protected by the law which requires that the arbitral award that
may be rendered by KCAB must be confirmed here by the RTC before it
For foreign or international arbitral awards which must first be confirmed can be enforced.
by the RTC, the grounds for setting aside, rejecting or vacating the award
by the RTC are provided under Art. 34(2) of the UNCITRAL Model Law. With our disquisition above, petitioner is correct in its contention that an
arbitration clause, stipulating that the arbitral award is final and binding,
For final domestic arbitral awards, which also need confirmation by the does not oust our courts of jurisdiction as the international arbitral award,
RTC pursuant to Sec. 23 of RA 876[44] and shall be recognized as final and the award of which is not absolute and without exceptions, is still judicially
executory decisions of the RTC,[45] they may only be assailed before the reviewable under certain conditions provided for by the UNCITRAL Model
RTC and vacated on the grounds provided under Sec. 25 of RA 876.[46] Law on ICA as applied and incorporated in RA 9285.

(5) RTC decision of assailed foreign arbitral award appealable Finally, it must be noted that there is nothing in the subject Contract which
provides that the parties may dispense with the arbitration clause.
Sec. 46 of RA 9285 provides for an appeal before the CA as the remedy of
an aggrieved party in cases where the RTC sets aside, rejects, vacates, Unilateral rescission improper and illegal
modifies, or corrects an arbitral award, thus:
Having ruled that the arbitration clause of the subject contract is valid
and binding on the parties, and not contrary to public policy;
SEC. 46. Appeal from Court Decision or Arbitral Awards.A decision of the consequently, being bound to the contract of arbitration, a party may not
Regional Trial Court confirming, vacating, setting aside, modifying or unilaterally rescind or terminate the contract for whatever cause without
correcting an arbitral award may be appealed to the Court of Appeals in first resorting to arbitration.
accordance with the rules and procedure to be promulgated by the What this Court held in University of the Philippines v. De Los
Supreme Court. Angeles[47] and reiterated in succeeding cases,[48] that the act of treating
a contract as rescinded on account of infractions by the other
The losing party who appeals from the judgment of the court confirming contracting party is valid albeit provisional as it can be judicially assailed,
an arbitral award shall be required by the appellate court to post a is not applicable to the instant case on account of a valid stipulation on
counterbond executed in favor of the prevailing party equal to the arbitration. Where an arbitration clause in a contract is availing, neither of
amount of the award in accordance with the rules to be promulgated by the parties can unilaterally treat the contract as rescinded since whatever
the Supreme Court. infractions or breaches by a party or differences arising from the contract
must be brought first and resolved by arbitration, and not through an
extrajudicial rescission or judicial action.
The issues arising from the contract between PGSMC and KOGIES on However, what appears to constitute a grave abuse of discretion is the
whether the equipment and machineries delivered and installed were order of the RTC in resolving the issue on the ownership of the plant when
properly installed and operational in the plant in Carmona, Cavite; the it is the arbitral body (KCAB) and not the RTC which has jurisdiction and
ownership of equipment and payment of the contract price; and whether authority over the said issue. The RTCs determination of such factual issue
there was substantial compliance by KOGIES in the production of the constitutes grave abuse of discretion and must be reversed and set aside.
samples, given the alleged fact that PGSMC could not supply the raw
materials required to produce the sample LPG cylinders, are matters
proper for arbitration. Indeed, we note that on July 1, 1998, KOGIES
instituted an Application for Arbitration before the KCAB RTC has interim jurisdiction to protect the rights of the parties
in Seoul, Korea pursuant to Art. 15 of the Contract as amended. Thus, it is
incumbent upon PGSMC to abide by its commitment to arbitrate. Anent the July 23, 1998 Order denying the issuance of the injunctive writ
paving the way for PGSMC to dismantle and transfer the equipment and
Corollarily, the trial court gravely abused its discretion in granting PGSMCs machineries, we find it to be in order considering the factual milieu of the
Motion for Inspection of Things on September 21, 1998, as the subject instant case.
matter of the motion is under the primary jurisdiction of the mutually
agreed arbitral body, the KCAB in Korea. Firstly, while the issue of the proper installation of the equipment and
In addition, whatever findings and conclusions made by the RTC Branch machineries might well be under the primary jurisdiction of the arbitral
Sheriff from the inspection made on October 28, 1998, as ordered by the body to decide, yet the RTC under Sec. 28 of RA 9285 has jurisdiction to
trial court on October 19, 1998, is of no worth as said Sheriff is not hear and grant interim measures to protect vested rights of the
technically competent to ascertain the actual status of the equipment parties. Sec. 28 pertinently provides:
and machineries as installed in the plant.
SEC. 28. Grant of interim Measure of Protection.(a) It is not incompatible
For these reasons, the September 21, 1998 and October 19, 1998 RTC with an arbitration agreement for a party to request, before constitution of
Orders pertaining to the grant of the inspection of the equipment and the tribunal, from a Court to grant such measure. After constitution of the
machineries have to be recalled and nullified. arbitral tribunal and during arbitral proceedings, a request for an interim
measure of protection, or modification thereof, may be made with the
Issue on ownership of plant proper for arbitration arbitral or to the extent that the arbitral tribunal has no power to act or is
unable to act effectivity, the request may be made with the Court. The
Petitioner assails the CA ruling that the issue petitioner raised on whether arbitral tribunal is deemed constituted when the sole arbitrator or the third
the total contract price of USD 1,530,000 was for the whole plant and its arbitrator, who has been nominated, has accepted the nomination and
installation is beyond the ambit of a Petition for Certiorari. written communication of said nomination and acceptance has been
received by the party making the request.
Petitioners position is untenable.
(b) The following rules on interim or provisional relief shall be observed:
It is settled that questions of fact cannot be raised in an original action for
certiorari.[49] Whether or not there was full payment for the machineries Any party may request that provisional relief be granted against the
and equipment and installation is indeed a factual issue prohibited by adverse party.
Rule 65.
Such relief may be granted:
(a) Maintain or restore the status quo pending determination of the
(i) to prevent irreparable loss or injury; dispute;
(ii) to provide security for the performance of any obligation;
(iii) to produce or preserve any evidence; or (b) Take action that would prevent, or refrain from taking action that is
(iv) to compel any other appropriate act or omission. likely to cause, current or imminent harm or prejudice to the arbitral
process itself;
(c) The order granting provisional relief may be conditioned upon the
provision of security or any act or omission specified in the order. (c) Provide a means of preserving assets out of which a subsequent
award may be satisfied; or
(d) Interim or provisional relief is requested by written application
transmitted by reasonable means to the Court or arbitral tribunal as the (d) Preserve evidence that may be relevant and material to the resolution
case may be and the party against whom the relief is sought, describing of the dispute.
in appropriate detail the precise relief, the party against whom the relief is
requested, the grounds for the relief, and the evidence supporting the
request. Art. 17 J of UNCITRAL Model Law on ICA also grants courts power and
jurisdiction to issue interim measures:
(e) The order shall be binding upon the parties.
Article 17 J. Court-ordered interim measures
(f) Either party may apply with the Court for assistance in implementing or
enforcing an interim measure ordered by an arbitral tribunal. A court shall have the same power of issuing an interim measure in
relation to arbitration proceedings, irrespective of whether their place is in
(g) A party who does not comply with the order shall be liable for all the territory of this State, as it has in relation to proceedings in courts. The
damages resulting from noncompliance, including all expenses, and court shall exercise such power in accordance with its own procedures in
reasonable attorney's fees, paid in obtaining the orders judicial consideration of the specific features of international arbitration.
enforcement. (Emphasis ours.)

In the recent 2006 case of Transfield Philippines, Inc. v. Luzon Hydro


Art. 17(2) of the UNCITRAL Model Law on ICA defines an interim measure Corporation, we were explicit that even the pendency of an arbitral
of protection as: proceeding does not foreclose resort to the courts for provisional reliefs.
We explicated this way:
Article 17. Power of arbitral tribunal to order interim measures
As a fundamental point, the pendency of arbitral proceedings does not
xxx xxx xxx foreclose resort to the courts for provisional reliefs. The Rules of the ICC,
which governs the parties arbitral dispute, allows the application of a
(2) An interim measure is any temporary measure, whether in the form of party to a judicial authority for interim or conservatory measures. Likewise,
an award or in another form, by which, at any time prior to the issuance of Section 14 of Republic Act (R.A.) No. 876 (The Arbitration Law) recognizes
the award by which the dispute is finally decided, the arbitral tribunal the rights of any party to petition the court to take measures to safeguard
orders a party to: and/or conserve any matter which is the subject of the dispute in
arbitration. In addition, R.A. 9285, otherwise known as the Alternative PGSMC to preserve the subject equipment and machineries
Dispute Resolution Act of 2004, allows the filing of provisional or interim
measures with the regular courts whenever the arbitral tribunal has no Finally, while PGSMC may have been granted the right to dismantle and
power to act or to act effectively.[50] transfer the subject equipment and machineries, it does not have the right
to convey or dispose of the same considering the pending arbitral
proceedings to settle the differences of the parties. PGSMC therefore must
It is thus beyond cavil that the RTC has authority and jurisdiction to grant preserve and maintain the subject equipment and machineries with the
interim measures of protection. diligence of a good father of a family[51] until final resolution of the arbitral
proceedings and enforcement of the award, if any.
Secondly, considering that the equipment and machineries are in the
possession of PGSMC, it has the right to protect and preserve the
equipment and machineries in the best way it can. Considering that the
LPG plant was non-operational, PGSMC has the right to dismantle and WHEREFORE, this petition is PARTLY GRANTED, in that:
transfer the equipment and machineries either for their protection and
preservation or for the better way to make good use of them which is (1) The May 30, 2000 CA Decision in CA-G.R. SP No. 49249
ineluctably within the management discretion of PGSMC. is REVERSED and SET ASIDE;

Thirdly, and of greater import is the reason that maintaining the (2) The September 21, 1998 and October 19, 1998 RTC Orders in Civil Case
equipment and machineries in Worths property is not to the best interest No. 98-117 are REVERSED and SET ASIDE;
of PGSMC due to the prohibitive rent while the LPG plant as set-up is not
operational. PGSMC was losing PhP322,560 as monthly rentals or PhP3.87M (3) The parties are hereby ORDERED to submit themselves to the arbitration
for 1998 alone without considering the 10% annual rent increment in of their dispute and differences arising from the subject Contract before
maintaining the plant. the KCAB; and

Fourthly, and corollarily, while the KCAB can rule on motions or petitions (4) PGSMC is hereby ALLOWED to dismantle and transfer the equipment
relating to the preservation or transfer of the equipment and machineries and machineries, if it had not done so, and ORDERED to preserve and
as an interim measure, yet on hindsight, the July 23, 1998 Order of the RTC maintain them until the finality of whatever arbitral award is given in the
allowing the transfer of the equipment and machineries given the non- arbitration proceedings.
recognition by the lower courts of the arbitral clause, has accorded an
interim measure of protection to PGSMC which would otherwise been No pronouncement as to costs.SO ORDERED.
irreparably damaged.

Fifth, KOGIES is not unjustly prejudiced as it has already been


paid a substantial amount based on the contract. Moreover, KOGIES is
amply protected by the arbitral action it has instituted before the KCAB,
the award of which can be enforced in our jurisdiction through the
RTC. Besides, by our decision, PGSMC is compelled to submit to arbitration
pursuant to the valid arbitration clause of its contract with KOGIES.
DIVISION under the Amended BOT Agreement dated April 5, 2002 by approving the
site of the Central Facility at the Star Mall Complex in Shaw Boulevard,
[ GR No. 225051, Jul 19, 2017 ] Mandaluyong City, within five days from receipt of the Arbitral Award; (c)
a judgment ordering the DFA to pay damages to BCA, reasonably
estimated at P100,000,000.00 as of this date, representing lost business
DEPARTMENT OF FOREIGN AFFAIRS v. BCA INTERNATIONAL CORPORATION +
opportunities; financing fees, costs and commissions; travel expenses;
legal fees and expenses; and cost of arbitration, including the fees of the
DECISION members of the Arbitral Tribunal; and (d) other just or equitable relief.

On October 5, 2013, respondent manifested that it shall file an Amended


Statement of Claims so that its claim may conform to the evidence they
have presented.[4]

PERALTA, J.:
Petitioner opposed respondent's manifestation, arguing that such
This is a petition for certiorari under Rule 65 of the Rules of Court, seeking to amendment at the very late stage of the proceedings will cause undue
annul and set aside Procedural Order No. 11 dated February 15, 2016 and prejudice to its interests. However, the Arbitral Tribunal gave respondent a
Procedural Order No. 12 dated June 8, 2016, both issued by the period of time within which to file its Amended Statement of Claims and
UNCITRAL Ad Hoc Arbitral Tribunal in the arbitration proceedings between gave petitioner time to formally interpose its objections.[5]
petitioner Department of Foreign Affairs (DFA) and respondent BCA
International Corporation. In the Amended Statement of Claims[6] dated October 25, 2013,
respondent interposed the alternative relief that, in the event specific
The facts are as follows: performance by petitioner was no longer possible, petitioner prayed that
the Arbitral Tribunal shall render judgment ordering petitioner to pay
In an Amended Build-Operate-Transfer (BOT) Agreement[1] dated April 5, respondent P1,648,611,531.00, representing the net income respondent is
2002 (Agreement), petitioner DFA awarded the Machine Readable expected to earn under the Agreement, and P100,000,000.00 as
Passport and Visa Project (MRP/V Project) to respondent BCA exemplary, temperate or nominal damages.[7]
International Corporation. In the course of implementing the MRPN
Project, conflict arose and petitioner sought to terminate the Agreement. In an Opposition dated December 19, 2013, petitioner objected to
respondent's Amended Statement of Claims, averring that its belated
Respondent opposed the termination and filed a Request for Arbitration filing violates its right to due process and will prejudice its interest and that
on April 20, 2006. The Arbitral Tribunal was constituted on June 29, 2009. [2] the Tribunal has no jurisdiction over the alternative reliefs sought by
respondent.[8]
In its Statement of Claims[3] dated August 24, 2009, respondent sought the
following reliefs against petitioner: (a) a judgment nullifying and setting On August 6, 2014, respondent filed a Motion to Withdraw Amended
aside the Notice of Termination dated December 9, 2005 of the DFA, Statement of Claims[9] in the light of petitioner's opposition to the
including its demand to BCA to pay liquidated damages equivalent to admission of the Amended Statement of Claims and to avoid further
the corresponding performance security bond posted by BCA; (b) a delay in the arbitration of its claims, without prejudice to the filing of such
judgment confirming the Notice of Default dated December 22, 2005 claims for liquidated and other damages at the appropriate time and
issued by BCA to the DFA and ordering the DFA to perform its obligation proceeding. Thereafter, respondent filed a motion to resume
proceedings. balance of 3 million pesos shall be payable upon submission of this case
for resolution. No award shall be issued and promulgated by the Tribunal
However, on May 4, 2015, respondent filed anew a Motion to Admit unless the balance of 40% in the Arbitrators' fees for the original Claim and
Attache,d Amended Statement of Claims dated April 30, 2015, increasing Counterclaim, respectively, and the balance of 3 million for the Amended
the actual damages sought to P390,000,000.00, plus an additional Claim, are all fully paid by the parties.
P10,000,000.00 for exemplary, temperate or nominal damages.[10]
DFA is hereby given the period of 20 days from receipt of this Order to file
On November 6, 2015, petitioner filed an Opposition to the Motion to its Answer to the Amended Statement of Complaint, and to manifest
Admit Attached Amended Statement of Claims. before this Tribunal if it will present additional evidence in support of its
Amended Answer in order for the Tribunal to act accordingly.[12]
In Procedural Order No. 11[11] dated F bruary 15, 2016, the Arbitral Tribunal
granted respondent's Motion to Admit Attached Amended Statement of On February 18, 2016, respondent filed a Motion for Partial
Claims dated April 30, 2015 on the premise that respondent would no Reconsideration[13] of Procedural Order No. 11 and prayed for the
longer present any additional evidence in-chietPetitioner was given a admission of its Amended Statement of Claims by the Arbitral Tribunal
period of 20 days from receipt of the Order to file its Answer to the without denying respondent's right to present evidence on the actual
Amended Statement of Claims and to manifest before the Tribunal if it will damages, such as attorney's fees and legal cost that it continued to incur.
present additional evidence in support of its Amended Answer in order for
the Tribunal to act accordingly. On February 19, 2016, petitioner filed a Motion for Reconsideration of
Procedural Order No. 11 and, likewise, filed a Motion to Suspend
Procedural Order No. 11 reads: Proceedings dated February 19, 2016. Further, on February 29, 2016,
petitioner filed its Comment/Opposition to respondent's Motion for Partial
Reconsideration of Procedural Order No. 11.
For resolution by the Tribunal is BCA's Motion to Admit the Amended
Statement of Claim dated 30 April2015 objected to by DFA in its The Arbitral Tribunal, thereafter, issued Procedural Order No. 12 dated
Opposition dated 6 November 2015. June 8, 2016, which resolved respondent's Motion for Partial
Reconsideration of Procedural Order No. 11, disallowing the presentation
BCA's Counsel made representations during the hearings that the of additional evidence-in-chief by respondent to prove the increase in the
Amendment is for the simple purpose of making the Statement of Claim amount of its claim as a limitation to the Tribunals' decision granting
conform with what BCA believes it was able to prove in the course of the respondent's Motion to Amend its Statement of Claims. In Procedural
proceedings and that the Amendment will no longer require the Order No. 12, the Tribunal directed the parties to submit additional
presentation of any additional evidence-in-chief. documentary evidence in support of their respective positions in relation
to the Amended Statement of Claims and to which the other party may
Without ruling on what BCA was able to prove, the Tribunal hereby grants submit its comment or objections.
the Motion to Admit on the premise that BCA will no longer present any
additional evidence-in-chief to prove the bigger claim in the Amended Procedural Order No. 12 reads:
Statement.

For the additional claim of 300 million pesos, BCA should pay the For resolution is the partial Motion for Reconsideration of the Tribunal's
additional fee of 5% or 15 million pesos. Having paid 12 million pesos, the Procedural Order No. 11 disallowing the presentation of additional
evidence-in-chief by Claimant to prove the increase in the amount of its
Claim as a limitation to this Tribunal's decision granting Claimant's Motion As Procedural Order No. 12 denied petitioner's motion for reconsideration
to Amend its Statement of Claims. of Procedural Order No. 11, petitioner filed this petition for certiorari under
Rule 65 of the Rules of Court with application for issuance of a temporary
After a careful consideration of all the arguments presented by the Parties restraining order and/or writ of preliminary injunction, seeking to annul and
in their pleadings, the Tribunal hereby decides to allow the submission of set aside Procedural Order No. 11 dated February 15, 2016 and
additional documentary evidence by any Party in support of its position in Procedural Order No. 12 dated June 8, 2016.
relation to the Amended Statement of Claims and to which the other may
submit its comments or objections. The Tribunal, however, will still not allow Petitioner stated that it opted to file the petition directly with this court in
the taking of testimonial evidence from any witness by any Party. The view of the immensity of the claim concerned, significance of the public
Tribunal allowed the amendment of the Statement of Claims but only for interest involved in this case, and the circumvention of the temporary
the purpose of making the Statement of Claims conform with the restraining order issued by this Court in Department of Foreign Affairs v.
evidence that had already been presented, assuming that, indeed, it was BCA International Corporation, docketed as G.R. No. 210858. It
the case. In resting its case, Respondent must have already dealt with cited Department of Foreign Affairs, et al. v. Hon. Judge
and addressed the evidence that had already been presented by Falcon,[15] wherein the Court overlooked the rule on hierarchy of courts
Claimant and that allegedly supports the amended Claim. However, in and took cognizance of the petition for certiorari.
order to give the Parties more opportunity to prove their respective
positions, additional evidence shall be accepted by the Tribunal, but only Petitioner raised these issues:
documentary evidence.

Wherefore, Procedural Order No. 11 is modified accordingly. The Claimant THE AD HOC ARBITRAL TRIBUNAL COMMITTED GRAVE ABUSE OF
is given until 25 June 2016 to submit its additional documentary evidence DISCRETION AMOUNTING TO LACK OR EXCESS OF JURISDICTION WHEN IT
in support of the Amended Statement of Claims. Respondent is given until ADMITTED THE AMENDED STATEMENT OF CLAIMS DATED 30 APRIL 2015
15 July 2016 to file its Answer to the Amended Statement of Claims, NOTWITHSTANDING THAT:
together with all the documentary evidence in support of its position.
Claimant is given until 30 July 2016 to comment or oppose the Answer and
the supporting documentary evidence, while Respondent is given until 14 I. THE AMENDMENT CAUSES UNDUE DELAY AND PREJUDICE TO
August 2016 to file its comment or opposition to the Claimant's submission, PETITIONER DFA;
together with any supporting documentary evidence. Thereafter, hearing
II. THE ALTERNATIVE RELIEF IN THE AMENDED STATEMENT OF CLAIMS
of the case shall be deemed terminated. The periods allowed herein are
FALLS OUTSIDE THE SCOPE OF THE ARBITRATION CLAUSE; HENCE,
non-extendible and the Tribunal will not act on any motion for extension of
OUTSIDE THE JURISDICTION OF THE AD HOC ARBITRAL TRIBUNAL;
time to comply.
III. THE AMENDMENT CIRCUMVENTS THE TEMPORARY RESTRAINING
The Parties shall submit their Formal Offer of Evidence, in the manner ORDER DATED 02 APRIL 2014 ISSUED BY THIS HONORABLE COURT IN
previously agreed upon, on 20 September 2016 while their respective G.R. NO. 210858; AND
Memorandum shall be filed on 20 October 2016. The Reply Memoranda of
the Parties shall be filed on 20 November 2016. Thereafter, with or without IV. PROCEDURAL ORDER NO. 12 DATED 8 JUNE 2016 VIOLATES
the foregoing submissions, the case shall be deemed submitted for PETITIONER DFA'S RIGHT TO DUE PROCESS.[16]
Resolution.[14]
Petitioner states that Article 20 of the 1976 UNCITRAL Arbitration Rules by the ADR Act of 2004, its Implementing Rules and Regulations (IRR) and
grants a tribunal the discretion to deny a motion to amend where the the Special Rules of Court on Alternative Dispute Resolution (Special ADR
tribunal "considers it inappropriate to allow such amendment having Rules).
regard to the delay in making it or prejudice to the other party or any
other circumstances." It further proscribes an amendment where "the Respondent avers that petitioner's objections to the admission of its
amended claim falls outside the scope of the arbitral clause or separate Amended Statement of Claims by the Arbitral Tribunal, through the
arbitration agreement." assailed Procedural Order Nos. 11 and 12, are properly within the
competence and jurisdiction of the Arbitral Tribunal to resolve. The Arbitral
Petitioner contends that respondent's Motion to Admit Attached Tribunal derives their authority to hear and resolve the parties' dispute from
Amended Statement of Claims dated April 30, 2015 should have been the contractual consent of the parties expressed in Section 19.02 of the
denied by the Arbitral Tribunal as there has been delay and prejudice to Agreement.
it. Moreover, other circumstances such as fair and efficient administration
of the proceedings should have warranted the denial of the motion to In a Resolution dated July 25, 2016, the Court resolved to note the Office
amend. Finally, the Arbitral Tribunal did not have jurisdiction over the of the Solicitor General's Very Urgent Motion for the Issuance of a
amended claims. Temporary Restraining Order and/or Writ of Preliminary Injunction dated
July 5, 2016.
Petitioner prays that a temporary restraining order and/or writ of
preliminary injunction be issued enjoining the Arbitral Tribunal from In regard to the allegation that the Amended Statement of Claims
implementing Procedural Order No. 11 dated February 15, 2016 and circumvents the temporary restraining order dated April 2, 2014 issued by
Procedural Order No. 12 dated June 8, 2016; that the said Procedural the Court in DFA v. BCA International Corporation, docketed as G.R. No.
Orders be nullified for having been rendered in violation of the 1976 210858, it should be pointed out that the said temporary restraining order
UNCITRAL Arbitration Rules and this Court's Resolution dated April 2, 2014 has been superseded by the Court's Decision promulgated on June 29,
rendered in G.R. No. 210858; that respondent's Amended Statement of 2016, wherein the Court resolved to partially grant the petition and
Claims dated April 30, 2015 be denied admission; and, if this Court affirms remand the case to the RTC of Makati City, Branch 146, to determine
the admission of respondent's Amended Statement of Claims, petitioner whether the documents and records sought to be subpoenaed are
be allowed to present testimonial evidence to refute the allegations and protected by the deliberative process privilege as explained in the
reliefs in the Amended Statement of Claims and to prove its additional Decision.
defenses or claims in its Answer to the Amended Statement of Claims or
Amended Statement of Defense with Counterclaims. The issues to be resolved at the outset are which laws apply to the
arbitration proceedings and whether the petition filed before the Court is
Petitioner contends that the parties in this case have agreed to refer any proper.
dispute to arbitration under the 1976 UNCITRAL Arbitration Rules and to
compel a party to be bound by the application of a different rule on The Agreement provides for the resolution of dispute between the parties
arbitration such as the Alternative Dispute Resolution (ADR) Act of 2004 or in Section 19.02 thereof, thus:
Republic Act (RA) No. 9285 transgresses such vested right and amounts to
vitiation of consent to participate in the arbitration proceedings. If the Dispute cannot be settled amicably within ninety (90) days by
mutual discussion as contemplated under Section 19.01 herein, the
In its Comment, respondent contends that this Court has no jurisdiction to Dispute shall be settled with finality by an arbitrage tribunal operating
intervene in a private arbitration, which is a special proceeding governed under International Law, hereinafter referred to as the "Tribunal," under the
UNCITRAL Arbitration Rules contained in Resolution 31/98 adopted by the 2046 of the Civil Code, the Special ADR Rules were formulated and were
United Nations General Assembly on December 15, 1976, and entitled also applied to all pending arbitration proceedings covered by RA 9285,
"Arbitration Rules on the United Nations Commission on the International provided no vested rights are impaired. Thus, contrary to DFA's contention,
Trade Law." The DFA and BCA undertake to abide by and implement the RA 9285, its IRR, and the Special ADR Rules are applicable to the present
arbitration award. The place of arbitration shall be Pasay City, Philippines, arbitration proceedings. The arbitration between the OFA and BCA is still
or such other place as may mutually be agreed upon by both parties. The pending, since no arbitral award has yet been rendered. Moreover, DFA
Arbitration proceeding shall be conducted in the English language. did not allege any vested rights impaired by the application of those
procedural rules.
Under Article 33 of the UNCITRAL Arbitration Rules governing the parties,
"the arbitral tribunal shall apply the law designated by the parties as RA No. 9285 declares the policy of the State to actively promote party
applicable to the substance of the dispute." "Failing such designation by autonomy in the resolution of disputes or the freedom of the parties to
the parties, the arbitral tribunal shall apply the law determined by the make their own arrangements to resolve their disputes.[23] Towards this
conflict of laws rules which it considers applicable." Established in this end, the State shall encourage and actively promote the use of
jurisdiction is the rule that the law of the place where the contract is made Alternative Dispute Resolution as an important means to achieve speedy
governs, or lex loci contractus.[17] As the parties did not designate the and impartial justice and declog court docl[24]
applicable law and the Agreement was perfected in the Philippines, our
Arbitration laws, particularly, RA No. 876,[18] RA No. 9285[19] and its IRR, and Court intervention is allowed under RA No. 9285 in the following instances:
the Special ADR Rules apply.[20] The IRR of RA No. 9285 provides that "[t]he (1) when a party in the arbitration proceedings requests for an interim
arbitral tribunal shall decide the dispute in accordance with such law as is measure of protection;[25] (2) judicial review of arbitral awards[26] by the
chosen by the parties. In the absence of such agreement, Philippine law Regional Trial Court (RTC); and (3) appeal from the RTC decisions on
shall apply."[21] arbitral awards to the Court of Appeals.[27]

In another earlier case filed by petitioner entitled Department of Foreign The extent of court intervention in domestic arbitration is specified in the
Affairs v. BCA International Corporation,[22] docketed as G.R. No. 210858, IRR ofRA No. 9285, thus:
petitioner also raised as one of its issues that the 1976 UNCITRAL Arbitration
Rules and the Rules of Court apply to the present arbitration proceedings,
not RA No. 9285 and the Special ADR Rules. We ruled therein thus: Art. 5.4. Extent of Court Intervention. In matters governed by this Chapter,
no court shall intervene except in accordance with the Special ADR Rules.

Arbitration is deemed a special proceeding and governed by the special Court intervention in the Special ADR Rules is allowed through these
provisions of RA 9285, its IRR, and the Special ADR Rules. RA 9285 is the remedies: (1) Specific Court Relief, which includes Judicial Relief Involving
general law applicable to all matters and controversies to be resolved the Issue of Existence, Validity and Enforceability of the Arbitral
through alternative dispute resolution methods. While enacted only in Agreement,[28] Interim Measures of Protection,[29] Challenge to the
2004, we held that RA 9285 applies to pending arbitration proceedings Appointment of Arbitrator,[30] Termination of Mandate of
since it is a procedural law, which has retroactive effect. Arbitrator,[31] Assistance in Taking Evidence,[32]Confidentiality/Protective
Orders,[33] Confirmation, Correction or Vacation of Award in Domestic
xxxx Arbitration,[34] all to be filed with the RTC; (2) a motion for reconsideration
may be filed by a party with the RTC on the grounds specified in Rule 19.1;
The IRR of RA 9285 reiterate that RA 9285 is procedural in character and (3) an appeal to the Court of Appeals through a petition for review under
applicable to all pending arbitration proceedings. Consistent with Article Rule 19.2 or through a special civil action for certiorari under Rule 19.26;
and (4) a petition for certiorari with the Supreme Court from a judgment or discretion resulting in substantial prejudice to the petitioner without
final order or resolution of the Court of Appeals, raising only questions of indicating with specificity the nature of such error or abuse of discretion
law. and the serious prejudice suffered by the petitioner on account thereof,
shall constitute sufficient ground for the Supreme Court to dismiss outright
Under the Special ADR Rules, review by the Supreme Court of an appeal the petition.
by certiorari is not a matter of right, thus:
RULE 19.37. Filing of Petition with Supreme Court. - A party desiring to
appeal by certiorari from a judgment or final order or resolution of the
RULE 19.36. Review Discretionary. - A review by the Supreme Court is not a Court of Appeals issued pursuant to these Special ADR Rules may file with
matter of right, but of sound judicial discretion, which will be granted only the Supreme Court a verified petition for review on certiorari. The petition
for serious and compelling reasons resulting in grave prejudice to the shall raise only questions of law, which must be distinctly set forth.
aggrieved party. The following, while neither controlling nor fully
measuring the court's discretion, indicate the serious and compelling, and It is clear that an appeal by certiorari to the Supreme Court is from a
necessarily, restrictive nature of the grounds that will warrant the exercise judgment or final order or resolution of the Court of Appeals and only
of the Supreme Court's discretionary powers, when the Court of Appeals: questions of law may be raised. There have been instances when we
overlooked the rule on hierarchy of courts and took cognizance of a
petition for certiorari alleging grave abuse of discretion by the Regional
a. Failed to apply the applicable standard or test for judicial review Trial Court when it granted interim relief to a party and issued an Order
prescribed in these Special ADR Rules in arriving at its decision resulting in assailed by the petitioner, considering the transcendental importance of
substantial prejudice to the aggrieved party; the issue involved therein[35] or to better serve the ends of justice when the
case is determined on the merits rather on technicality.[36] However, in this
b. Erred in upholding a final order or decision despite the lack of case, the appeal by certiorari is not from a final Order of the Court of
jurisdiction of the court that rendered such final order or decision; Appeals or the Regional Trial Court, but from an interlocutory order of the
Arbitral Tribunal; hence, the petition must be dismissed.
c. Failed to apply any provision, principle, policy or rule contained in these
Special ADR Rules resulting in substantial prejudice to the aggrieved party; WHEREFORE, the Court resolves to DISMISS the pet1t1on for failure to
and observe the rules on court intervention allowed by RA No. 9285 and the
Special ADR Rules, specifically Rule 19.36 and Rule 19.37 of the latter, in
d. Committed an error so egregious and harmful to a party as to amount the pending arbitration proceedings of the parties to this case.
to an undeniable excess of jurisdiction.

The mere fact that the petitioner disagrees with the Court of Appeals' SO ORDERED.
determination of questions of fact, of law or both questions of fact and
law, shall not warrant the exercise of the Supreme Court's discretionary Carpio, (Chairperson), Mendoza, and Martires, JJ., concur.
power. The error imputed to the Court of Appeals must be grounded Leonen, J., on wellness leave.
upon any of the above prescribed grounds for review or be closely
analogous thereto.

A mere general allegation that the Court of Appeals has committed


serious and substantial error or that it has acted with grave abuse of

You might also like