You are on page 1of 1

China Harbour Engineering Co.L.L.C.

PRE-CONCRETE CHECKLIST

CONTRACTOR: China Harhour Engineering co. L.L.C DATE: _______________


CHECKLIST #: __________

AREA / STRUCTURE / LOCATION: __________________________________________________


___________________________________________________________________________
REFERENCE DRAWING#: _______________________________________________________
Activities / Items / to be Inspected CHEC DORSCH CONSULT

1 Eraction of formwork (location, size, shape and level)


2 Support of formwork (Adequate bracing)
3 Cleaning of formwork
4 Installation of reinforcement (grade, size, splices and spacing)
5 Embedded items (pipes, conduits, etc.)
6 MEP provisions (sleeves, blockouts, shaft openings)

INTERFACE RELEASE NAME POSITION DATE


Electrical items verified by
Electrical QA/QC
Mechanical items verified by
Mechanical QA/QC

COMMENTS: _____________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
_________________________________________________________________________________
Accepted Accepted with comments Rejected
SIGN AS ACCEPTED / ACCEPTED WITH COMMENTS / REJECTED
CHEC DORSCH COSULT
Name
Position
Signature
Date

You might also like