You are on page 1of 7

BILL OF QUANTITIES

ITEM UNIT LABOR


DESCRIPTION UNIT QTY. PRICE
NO.: COST COST
1. GROUND FLOOR

- EARTH WORKS

Excavation for column footings 21.6 5,076.00 5,076.00


Excavation for septic tank 4.48 1,052.00 1,052.00
Excavation for tie-beams 49.9 11,726.50 11,726.50
Excavation for stair footings 0.35 122.50 122.50
Tampering of soil 52.2 9,187.50 9,187.50
100 mm thk. gravel bedding 5.22 11,353.50 11,353.50
Back filling of soil 63.78 9,567.00 9,567.00
48,084.50
- STEEL WORKS

Column & Column footing rebars Lot 10 46,431.56 19,898.93 66,330.49


Septic tank rebars Lot 1 1,398.60 599.40 1,998.00
Stair & Stair footing rebars Lot 1 3,885.00 1,665.00 5,550.00
Tie Beam rebars Lm 59.95 28,106.00 11,474.00 39,580.00
Slab on grade rebars 58.36 9,790.20 4,195.80 13,986.00
Ground floor beam rebars Lm 45.9 27,202.14 11,658.06 38,860.20
166,286.69
- FORMWORKS

Columns and column footings Lm 236 53,100.00


Tie beams Lm 95.4 21,465.00
Stairs and stair footing Lm 7 1,575.00
Ground floor beams Lm 86.5 19,462.50
95,602.50
- CONCRETE/MASONRY WORKS

Pouring of column and column footings 10.64 58,786.00


Pouring of stairs and stair footings 2.18 12,044.50
Pouring of tie beams 3.82 21,105.50
Pouring of slab on grade 7.86 43,426.50
Pouring of ground floor beams 2.71 14,972.75
CHB layering and plaster both sides
6" 119.88 47,532.42
4" 75.24 28,215.00
226,082.67
- FINISHING WORKS

Tile works

Toilet and ext. spaces 30cm x 30cm 17.00 10,350.00


Commercial space int. 60cm x 30cm 41.76 17,940.00
28,290.00
Painting works

Exterior (2 coats) 53.75 29,562.50


Interior (2 coats) 26.20 14,410.00
43,972.50
Ceiling works 44.12 43,017.00
43,017.00
Toilet door and door jamb installation

PVC door and door jamb Lot 1 5,850.00

Doors and Windows installation

Powder coated aluminum frame 12mm Lot 1 12,350.00


thk. clear glass doors
ITEM UNIT LABOR
DESCRIPTION UNIT QTY. PRICE
NO.: COST COST

Powder coated aluminum frame 12mm Lot 10 46,410.00


thk. clear glass windows 64,610.00

- ELECTRICAL WORKS

Service entrance & feeders Lot 1 18,547.00


Chipping & roughing ins of outlets and auxiliary Lm 67.73 17,271.15
Chipping & roughing ins of lighting switches Lm 36.74 9,368.70
Roughing ins of lightings Lm 58.38 14,886.90
Wiring of outlets and auxiliary Lm 169.33 7,704.28
Wiring of lightings and lighting switches Lm 237.80 10,816.90
Toilet exhaust fan No. 1 3,250.00
Panel board & circuit breaker installation Lot 1 10,205.00

Installation of electrical fixtures

Outlets and auxiliary No. 9 1,775.00


Switches No. 4 780.00
Lighting fixtures No. 10 7,540.00

Testing

Meager test 3,500.00


105,644.93
- PLUMBING WORKS

Sanitary pipe installation @ septic tank to


toilets Lm 9.68 3,872.00
Toilet water line installation Lm 14.52 4,598.00
Gate valve installation No. 2 910.00
Exhaust Lm 9.20 3,680.00

Toilet fixture installation

Lavatory No. 1 780.00


Floor drain No. 1 325.00
Water Closet No. 1 4,550.00
Faucet No. 1 416.00
19,131.00
2. SECOND FLOOR

- STEEL WORKS

Column rebars Lot 12 13,042.54 5,589.66 18,632.20


Second floor slab rebars 74.46 11,683.36 5,007.15 16,690.51
Second floor stair rebars Lot 1 3,106.20 931.86 4,038.06
Second floor beam rebars Lm 59.95 35,528.72 8,889.58 44,418.31
83,779.07
- CONCRETE & MASONRY WORKS

Pouring of column 4.032 22,276.80


Pouring of Stairs 1.08 5,967.00
Pouring of second floor slab 9.30 51,382.50
Pouring of second floor beam 5.24 28,951.00
CHB layering with plaster both sides

6" 92.96 36,858.64


4" 60.20 22,575.00
168,010.94
ITEM UNIT LABOR
DESCRIPTION UNIT QTY. PRICE
NO.: COST COST

- FORMWORKS

Columns Lm 53.76 12,096.00


Second floor stairs Lm 5 1,125.00
Second floor slab 74.46 16,753.50
Second floor beams Lm 56.95 12,813.75
42,788.25
- FINISHING WORKS

Tile works

Toilet and ext. spaces 30cm x 30cm 25.48 15,521.82


Commercial spaces int. 60cm x 30cm 32,483.73
48,005.55
Painting works

Exterior (2 coats) 76.58 42,119.00


Interior (2 coats) 72,226.00
114,345.00
Ceiling works

Commercial space 2 18.40 17,940.00


Commercial space 3 28.57 27,855.75
45,795.75
Toilet doors and door jambs installation

PVC flush door and door jamb Lot 1 5,850.00

Doors and Windows installation

Powder coated aluminum frame 12mm


thk. clear glass doors Lot 5 61,750.00
Powder coated aluminum frame 12mm
thk. clear glass windows Lot 4 18,564.00
86,164.00
- ELECTRICAL WORKS

Feeders Lot 2 7,000.00


Chipping & roughing ins of outlets and auxiliary Lm 116.26 29,646.30
Chipping & roughing ins of lighting switches Lm 53.16 13,555.80
Roughing ins of lightings Lm 95.24 24,286.20
Wiring of outlets and auxiliary Lm 290.65 13,224.57
Wiring of lightings and lighting switches Lm 371 16,880.00
Toilet exhaust fan No. 1 3,250.00
Panel board and circuit breaker installation Lot 2 20,410.00

Installation of electrical fixtures

Outlets and auxiliary No. 16 3,155.55


Switches No. 8 1,560.00
Lighting fixtures No. 18 13,572.00

Testing

Meager test 3,500.00


150,040.42
ITEM UNIT LABOR
DESCRIPTION UNIT QTY. PRICE
NO.: COST COST

- PLUMBING WORKS

Sanitary pipe installation @ septic tank to


toilet Lm 13.28 5,312.00
Toilet water line installation and hose bib Lm 24.71 7,824.83
Exhaust Lm 5.6 2,240.00
Toilet water proofing and leak test 2.50 2,600.00

Toilet fixture installation

Lavatory No. 1 780.00


Floor drain No. 1 325.00
Water Closet No. 1 4,550.00
Faucet No. 1 416.00
Urinal No. 1 3,250.00
27,297.83
3. THIRD FLOOR

- STEEL WORKS

Column rebars Lot 10 14,011.06 4,203.31 18,214.37


Third floor slab rebars 62.38 10,266.73 3,080.02 13,346.75
Roof beam rebars Lm 31.60 11,130.63 3,339.19 14,469.82

Roof framing works

Commercial space 4 63.72 57,348.00 17,204.74 74,609.74


Stair roofing 8.94 8,046.00 2,413.80 10,459.80
131,100.48
- CONCRETE & MASONRY WORKS

Pouring of column 3.36 18,564.00


Pouring of third floor slab 7.80 43,095.00
Pouring of roof beam 1.90 10,497.50
CHB layering with plaster both sides

6" 45.50 18,040.75


4" 48.30 18,112.50
108,309.75
- FORMWORKS

Columns Lm 44.80 10,080.00


Third floor slab 62.40 14,040.00
Roof beams Lm 25.28 5,688.00
29,808.00
- FINISHING WORKS

Tile works

Toilet and ext. spaces 30cm x 30cm 18.20 11,087.00


Commercial spaces int. 60cm x 30cm 42.68 29,224.40
40,311.40
Painting works

Exterior (2 coats) 44.10 24,255.00


Interior (2 coats) 76.16 41,888.00
66,143.00
Ceiling works

Commercial space 4 45.51 44,372.25


44,372.25
ITEM UNIT LABOR
DESCRIPTION UNIT QTY. PRICE
NO.: COST COST

Toilet doors and door jambs installation

PVC flush door and door jamb Lot 1 5,850.00

Doors and Windows installation

Powder coated aluminum frame 12mm


thk. clear glass doors Lot 2 24,700.00
Powder coated aluminum frame 12mm
thk. clear glass windows Lot 7 32,487.00
63,037.00
- ELECTRICAL WORKS

Feeders Lot 1 3,500.00


Chipping & roughing ins of outlets and auxiliary Lm 73.36 18,706.00
Chipping & roughing ins of lighting switches Lm 26.16 6,670.80
Roughing ins of lightings Lm 93.58 23,862.90
Wiring of outlets and auxiliary Lm 183.40 8,344.70
Wiring of lightings and lighting switches Lm 260.11 11,835.00
Toilet exhaust fan No. 1 3,250.00
Panel board and circuit breaker installation Lot 1 10,205.00

Installation of electrical fixtures

Outlets and auxiliary No. 9 1,775.00


Switches No. 4 780.00
Lighting fixtures No. 16 12,064.00

Testing

Meager test 3,500.00


104,493.40
- PLUMBING WORKS

Sanitary pipe installation @ septic tank to


toilets Lm 16.08 6,432.00
Toilet water line installation and hose bib Lm 25.56 8,094.00
Gate valve installation No. 1 455.00
Exhaust Lm 3 1,200.00
Toilet water proofing and leak test 25 2,600.00

Toilet fixture installation

Lavatory No. 1 780.00


Floor drain No. 1 325.00
Water Closet No. 1 4,550.00
Faucet No. 1 416.00
Urinal No. 1 3,250.00
28,102.00
4. OTHERS

- ROOFING

Installation of long span G.I. Sheet


Installation of PVC composite roof eaves Lot 1 50139.60 21,488.40 71,628.00
Down spouts from roof gutters 71,628.00
Roof sealant and paintings
ITEM UNIT LABOR
DESCRIPTION UNIT QTY. PRICE
NO.: COST COST

- EXTERIOR FINISHES

PVC composite panel for wall accent 30.26 9,683.20

Stair and ramp railings

Stainless steel railings Lm 17.1 5,557.50

Balcony and open deck railings

12mm thk. clear glass, stainless Lot 14 36,400.00


steel frame railings

Skylight

12mm thk. frosted tempered


glass
2" x 4" steel tubular connected Lm 8.05 14,087.50
to concrete by expansion bolt 65,728.20

NOTE:

ALL THE FOLLOWING ITEMS SHALL BE COMPLETED ACCORDING TO DRAWINGS, SPECIFICATIONS,


CONDITIONS AND DIRECTED INSTRUCTIONS BY THE ARCHITECT/ENGINEER OR THEIR REPRESENTATIVES.
BILL
DESCRIPTION TOTAL AMOUNT
NO.:

1. GROUND FLOOR WORKS 812,431.79

2. SECOND FLOOR WORKS 766,226.81

3. THIRD FLOOR WORKS 615,677.28

4. OTHERS 137,356.20
Total 2,331,692.08

5. SUPERVISION AND PROFIT 93,267.62

PROJECT TOTAL PRICE 2,424959.70

PREPARED BY:

JEFFREY M. RAMA
PROJECT ARCHITECT

You might also like