Project: Construction of KH APOLLO HOSPITAL TOILET BLOCK @ TERRACE FLOOR

Architect : M/s.Mustaq Ahmed, Chennai


Quantity Surveyor : Alagu.C, Karaikudi
Points observed over Topline reply for Toilet block bill
Top line Difference
S.NO DESCRIPTION UNIT RATE QUANTITY AMOUNT Remarks
Quoted Amount in Amount
1 Parapet wall demolition & new wall construction Item covered in measurement
2 Scaffolding work Sft 7 2125 14875 21250 -6375 We can give INR.7.00/- Sft
3 Floor was raised 7" thick Already discussed.
4 Weathering course over new RCC slab Item covered in measurement
5 Wooden frame with flush door for outer side Item covered in measurement
6 Sanitary & CP Fittings
i EWC Nos 9400.00 4 37,600
ii IWC Nos 3770.00 1 3,770
iii Long body tap Nos 740.00 3 2,220
iv Short body tap Nos 600.00 1 600
v Bib cock - 2 way Nos 1275.00 4 5,100
vi Angle cock with connecting hose Nos 755.00 6 4,530
vi Wash basin with Pillar cock inc. fittings Nos 3370.00 2 6,740
vii Cockroach trap Nos 260.00 7 1,820
Total Amount of Sanitary items 62,380 64,500 (2,120) There is no major difference , Hence it is OK
7 Wates supply & Drainage work
i 50 mm Water supply pipe Mt 120.00 250 30,000 96,000
ii 140 mm dia drainage pipe Mt 180.00 624 1,12,320 80,000
iii Construction of manhole champer Nos 5.00 7000 35,000
iv 90 mm dia drainage pipe Mt 140.00 305 42,700
It seems less than the actual, hence we can agree
Total Amount of Sanitary items 2,20,020 1,76,000 44,020 their quoted rates.

Still, together we can ask contractor some


Plumbing and sanitary works 2,82,400 2,40,500 percentage of discout.

8 Electircal works LS 13000 15000 (2,000) There is no major difference , Hence it is OK

9 Staircase room sheet removal & ramp area sheet fixing work Contractos to be submitted the actual cost

NOTES: The rates are worked out from provided rates including labour for installations and 18% GST.