Professional Documents
Culture Documents
2-MARKS
3. How will you assess the safe stress for a high tensile steel tendon?
Tensile stresses in steel at the time of tension behind the anchorages and after
allowing for all possible losses are generally expressed as a fraction of the ultimate
tensile strength or proof stress.
At the time of initial tensioning = Initial pre stress not to exceed 80% of the
characteristic tensile strength of tendons.
Final stress after allowing for all losses of Pre stress = Not less than 45% of the
characteristic tensile strength of tendons.
2
5. Why high strength materials are essential for Pre stressed concrete?
(Jun 2009, Dec 2012, Dec 2015, May 2016)
Shrinkage cracks will be very little when high strength materials are used.
Bursting stresses are not be resisted by low strength material
When the stress transfer the material should have a high bond stress.
It will reduce the losses of Pre stress.
8. What is Anchorage?
A device generally used to enable the tendon to impart and maintain pre stress
in concrete. The commonly used anchorages are the Freyssinet, MagnelBalton,
Gifford Udal, Lee- Mccal etc.,
3
11. What are the various methods/systems of Pre stressing?
(May 2010, May 2013)
Pre stressing
Unbonded tendon:
When there is no bond between the pre stressing tendon and concrete, it is
called un bonded tendon. Un grouted post tensioned tendons are examples of
unbounded tendons.
4
15. What are the stages of loading in pre stressing?
The analysis of pre stressed members can be different for the different stages of
loading. The stages of loading are as follows.
Initial : It can be subdivided into two stages.
17. Write down the factors influencing deflections. (May 2011, Dec 2011, Dec
2015, May 2016)
The deflection of the pre stressed concrete members is influenced by the
following salient factors
1. Imposed load and self- weight.
2. Magnitude of the pre stressing force
3. Cable Profile
4. Second moment of area of cross section
5. Modulus of elasticity of concrete
6. Shrinkage, creep and relaxation of steel stress.
7. Span of the member
5
8. Fixity condition.
6
23. What are the losses encountered in pre tensioned and post tensioned
members? (May2008, Jun 2009, Jun2012, Dec2013)
7
28. What is loss due to anchorage slip?
In post-tensioned members, when the pre stress is transferred to the concrete,
the wedges slip through a little distance before they get properly seated in conical
shape. The anchorage block also moves before it settles on the concrete. There is loss
of pre stress due to the consequent reduction in the length of the tendon.
31. What are the advantages of PSC construction? (Dec 2012, May 2013)
In case of fully pre stressed member, which are free from tensile stresses
under working loads, the cross section is more efficiently utilized when
compared with a reinforced concrete section which is cracked under
working loads.
The flexural member is stiffer under working loads than a reinforced
concrete member of the same length.
8
32. What are the materials used for Pre stressed concrete?
The materials used in pre stressed concrete are
1. High strength concrete and 2. High tensile steel
Disadvantages:
9
37.What are the classifications of pre stressed concrete structures. (Dec 2013)
1. Class I structure
2. Class II structure
3. Class III structure
10
40. List the types of losses in pre stress in pre tensioned system.
(May 2008, Jun 2012, Dec 2013)
1. Elastic deformation of concrete
2. Relaxation of stress in steel
3. Shrinkage of concrete
4. Creep of concrete
42. What are the types of devices used for tensioning. (May 2014)
Jacks, Hydraulic jack.
11
46. What is Self-stressing or chemical pre stressing? (Dec 2014)
Self-stressing or chemical prestressing of concrete was made possible by the
development of expanding cements. Generally, expanding cements consist and 75 %
Portland cement, 15 % high alumina cement and 10 % gypsum, which results in the
formation of calcium sulphoaluminate.
Since the expansion of concrete is restrained by high tensile steel wires, the
compressive stresses that develop in concrete and steel wires are subjected to tensile
stresses. Tensile stresses up to 850 N/mm2 were developed in steel by the expansion
of concrete.
47. Explain why steel with a low yield stress is not used in pre stressed
construction. (May 2015)
Mild steel has working stress of 120 N/mm2 which is completely lost
due to shrinkage, creep and elastic deformation. Normal loss of stress in steel is 100 –
240 N/mm2. Hence high initial stress of about 1200-2000 N/mm2 is required to make
up for the losses. Therefore steelwith a low yield stress is not used in pre stressed
construction.
48. Why loss due to creep is more for pretensioned beam compared to that of
post tensioned member?
Pre-tensioned members have large magnitude of loss due to creep then post
tensioned over, as transfer of prestress usually takes place earlier in pretensioned
member.
50. What are the three forms in which high tensile steel is used in the prestressed
concrete?
High tensile steel wire
Cables
Strands
12
CE 6702 -Prestressed concrete structures
16 Marks
1. Briefly explain various systems and methods of pre stressing with neat sketch
(May 2015, Dec 2015, May 2016)
Pre stressing
PRE-TENSIONING SYSTEM:
In the pre-tensioning system, the tendons are first tensioned between rigid
anchor-blocks cast on the ground or in a column or unit-mould pre stressing bed, prior
to the casting of concrete in the moulds.
The tendons comprising individual wires or strands are stretched with constant
eccentricity is shown in Figure (a).
13
b. Beam with Variable Tendon:
Figure (b) shows the tendons of variable eccentricity with tendon anchorage at
one end and jacks at the other. The tendons are harped using special hold down
devices.
For mass production of pre tensioned elements, the long line process developed
by Hoyer is generally used. Strands of 18mmØ and high tensile wires of 7mmØ are
used. Ends are clipped using Weinberg anchor clip or Donald clip which is close to
the end diaphragms of the units before concreting operation.
14
Fig d. Supplementary anchoring devices
2. POST-TENSIONING SYSTEM:
High tension wires 5- 8mmø of 12 nos are formed into a cable with a
spiral spring inside.Spring gives the clearance between wires and enhances
grouting.The whole is enclosed in sheet metal .Anchorage has cylinder of concrete
with corrugations outside, central conical hole and hoop reinforcement.Conical
pugs are pushed inside after tendons are tightened. The space is grouted.
15
b. MagnelBalton system:
Cables are of rectangular section. Layers of wires 5-8mmø (up to 16 layers for
64 wires) layer clearance is 4mm. Spacers or grills are provided to maintain clearance.
Anchoring by sandwich plates 25mm thick. 2 wires in each- wedge shaped groove-
steel wedge is driven to tighten the wires. 8 plates can be used – each plate can have 8
wires. Sandwich plates are arranged against a distribution plate.
B.MagnelBalton system
c. Gifford Udall system:
Consist of steel split cone and cylindrical female cone to house the HT
wires bearing against the steel plates. Each wire is tensioned separately and
anchored using wedge in bearing plate. The ducts are formed using metal sheaths
cast into the concrete member.
16
d. CCL standard system:
Wires are tensioned individually. 12 nos of wires are used in circular cable.
Size of duct is 40mmø for 8 wire cable, 50mmø for 12 wire cable. Spacers are
provided at 60mm interval. CCL anchor grip is used for anchorage which consists of
steel wedges which fit over the wire and are accommodated in a steel barrel having a
tapered hole. These wedges bear against a drilled anchored plate. The anchor plates
bears against a thrust ring which is cast into the concrete. Thrust ring is of mild steel
6mm thick having rectangular central hole. Bearing plate 18mm thick and has9mm
ø@25mmc/c holes to accommodate the wires
High tensile alloy steel bars (silico manganese steel) are used as tendons. Bars
of ø 22,25,28, & 30mm, length is of 20m. Bars threaded at ends. Anchoring is done by
screwing special threaded nuts. Nuts bear against the distribution plate at the end of
the beam. Forces are transmitted by bearing at the end blocks.
17
2. Explain the classification of pre stressed concrete.
Pre stressing of concrete can be classified in several ways. The following
classifications are discussed.
i. Based on Source of Pre stressing Force
ii. Based on Location of the pre stressing tendon
iii. Based on sequence of casting the concrete and applying tension to the
tendons.
iv. Based on the shape of the member pre stressed.
v. Based on the amount of pre stressing force
vi. Based on the directions of pre stressing a member.
i. Based on Source of Pre stressing Force:
This classification is based on the method by which the pre stressing force is
generated. There are four sources of pre stressing force:
This is the simplest type of pre stressing, producing large pre stressing
forces. The hydraulic jack used for the tensioning of tendons, comprises of calibrated
pressure gauges which directly indicate the magnitude of force developed during the
tensioning.
18
c. Electrical Pre stressing:
This classification is based on the location of the pre stressing tendon with
respect to the concrete section.
When external steel wires known as tendons are placed on the outer section of
the region being stressed, then the technique is called external pre stressing.
iii.Based on the sequence of casting the concrete and applying tension to the
tendons.
a. Pre- tensioning
b. Post – tensioning
19
a. Pre-tensioning:
The tension is applied to the tendons before casting of the concrete. The pre-
compression is transmitted from steel to concrete through bond over the transmission
length near the ends. Post-tensioning:
The tension is applied to the tendons (located in a duct) after hardening of the
concrete. The pre-compression is transmitted from steel to concrete by the anchorage
device (at the end blocks).
b. Circular Prestressing:
When the prestressed members are curved, in the direction of prestressing, the
prestressing is called circular prestressing. For example, circumferential prestressing
of tanks, silos, pipes and similar structures. The following figure shows the
containment structure for a nuclear reactor which is circularly prestressed.
a. Fully prestressing
b. Limited prestressing
c. Partial prestressing
a. Full Pre stressing:
20
b. Limited Pre stressing:
When the level of prestressing is such that the tensile stress under service loads
is within the cracking stress of concrete, it is called Limited Prestressing (Type 2).
c. Partial Prestressing:
When the level of prestressing is such that under tensile stresses due to service
loads, the crack width is within the allowable limit, it is called Partial Prestressing
(Type 3).
a. Uniaxial prestressing
b. Biaxial prestressing
c. Multi-axial prestressing
a. Uniaxial Prestressing:
When the prestressing tendons are parallel to one axis,it is called Uniaxial
Prestressing.For example: longitudinal pre stressing of beams.
b. Biaxial Prestressing:
When there are prestressing tendons parallel to two axes, it is called Biaxial
Prestressing. For example: biaxial prestressing of slabs.
c. MultiaxialPrestressing:
When the prestressing tendons are parallel to more than two axes, it is called
Multiaxial Pre stressing. E.g: pre stressing of domes.
21
3. Discuss about the importance of control of deflections and factors influencing
the deflection of PSC beams. (May 2013)
22
a. Loss due to elastic deformation of concrete:
The loss of pre stress due to elastic deformation of concrete depends on the
modular ratio and the average stress in concrete at the level of steel.
Loss of stress in steel = c x fc
Es
c = modular ratio.
Ec
fc
Strain in concrete at the level of steel =
Ec
fc
Stress in steel corresponding to this strain = x Es
Ec
Loss of stress in steel = c x fc
If the initial stress in steel is known, the percentage loss of stress due to the
elastic deformation of concrete can be computed.
b. Loss due to relaxation of stress in steel:
Most of the code provides for the loss of stress due to relaxation of steel as a
percentage of the initial stress in steel. The Indian standard code recommends a value
varying from 5 to 10% initial stress in steel.
23
200 x106
cs for post tensioning and
log10 t 2
Where,
t = age of concrete at transfer in days.
The loss of stress in steel due to the shrinkage of concrete is estimated
as, Loss due to shrinkage of concrete = cs xEs
Creep coefficient( ) = c
e
Loss of stress in steel = f c c
24
e. Loss due to anchorage slip:
In most post-tensioned system, when the cable is tensioned and the jack is
released to transfer pre stress to concrete, the friction wedges, employed to grip the
wires, slip over a small distance before the wires are firmly housed between the
wedges. The magnitude of slip depends upon the type of wedge and the stress in the
wire.
Loss = ( E s Δ/L)
Where Δ = slip of anchorage, mm
L = length of the cable, mm
A = cross sectional area of the cable, mm2
E s = modulus of elasticity of steel.
P = Pre stressed force in the cable
f. Loss of stress due to friction:
On tensioning the curved tendons, loss of stress occurs in the post tensioned
members due to friction between the tendons and the surrounding concrete ducts. The
magnitude of this loss is of the following types:
(a) Loss of stress due to the curvature effects, which depends upon the
tendon from or alignment which generally follows a curved profile along
the length of the beam.
(b) Loss of stress due to the wobble effect, which depends upon the local
deviation in the alignment of the cable. The wobble or wave effect is the
result of accidental or unavoidable misalignment, since ducts or sheaths
cannot beperfectly located to follow predetermined profile throughout the
length of thebeam.
Px Poe
kx
= Po 1 Kx
25
Stress Concept
5. A rectangular concrete beam 100 mm wide by 250 mm deep spanning over 8
m is prestressed by a straight cable carrying an effective prestressing force of
250 kN located at an eccentricity of 40 mm. The beam supports a live load of
1.2 kN/m.
(a) Calculate the resultant stress distribution for the centre of span cross
section of the beam assuming the density of concrete as 24 kN/m3
(b) Find the magnitude of prestressing force with an eccentricity of 40 mm
which can balance the stresses due to dead and live loads at the soffit of the
centre span section.
Given Data:
P Pe M g M q
f top = - + +
A c Zt Zt Zt
P Pe M g M q
f bot = + - -
A c Z b Z b Zb
26
Step 1: Direct stress due to pre stress:
P 250 x 103 2
= = +10 N/mm
Ac 100 x 250
P x e
Bending stress due to Prestress =
Z
i. Section Modulus:
bD2 100 x 2502 6 3
Z=Zt =Zb =
6 = 1.041 x 10 mm
=
6
Note: Given section is symmetric section so Z=Z t =Zb
ii. Bending stress due to Prestress
P x e 250 x 103 x 40 2
= = 9.615 N/mm
Z 1.04 x 10
6
Mg
Bending Stress due to self-weight of beam =
Z
w g = b x D x Dc
wg = 0.1 x 0.25 x 24 = 0.6 kN/m
ii. Bending moment due to Self-weight of beam :(Mg)
w g L2 0 . 6 x 82
Mg = = = 4 . 8 kN m
8 8
27
Step 4: Bending Stress due to live load of beam at centre (Mq):
i. Bending Moment due to Live load at centre
wq = 1.2 kN/m
w q L2 1. 2 x 8 2
M q= = = 9 . 6 kN m
8 8
P Pe M g M q
f top = - + +
Ac Zt Zt Zt
P Pe M g Mq
f bot = + - -
c
A Z b Zb Zb
P Pe M g M q
+ - -
c
A Z b b Zb
Z
M g M q P Pe
+ = +
b b c Zb
Z Z A
28
1 e 1 40
4.615 + 9.23 = P + ; 13.845 = P +
100 x 250 1.04 x 10
6
A c Zb
Results:
Given Data:
29
Solution:
Resultant stress distribution top and bottom for centre span section
P Pe M g M q
f top = - + +
A c Z t Z t Zt
P Pe M g M q
f bot = + - -
A c Z b Z b Zb
P = No's of wires x f pi x As
P = (18 x 840 x 19.63) = 296.80 x 103 N
30
Step 5: Bending Stress due to Prestress:
P x e
Bending stress due to Prestress =
Z
i. Section Modulus:
bD2 200 x 3002 6 3
Z=Zt =Zb =
6 = 3 x 10 mm
=
6
Note: Given section is symmetric section so Z=Z t =Zb
w g L2 1. 44 x 62
Mg = = = 6 . 48 kN m
8 8
wq = 6 kN/m
w q L2 6 x 6 2
Mq = = = 27 kN m
8 8
31
ii. Bending stress due to live load
Mq 27 x 106 2
= 6 = ±9 N/mm
Z 3 x 10
Step 8: Resultant stress for centre span section:
R.S at top = 4.95 – 4.95 + 2.16 + 9.0 = 11.16 N/mm2
R.S at bottom = 4.95 + 4.95 - 2.16 - 9.0 = -1.26 N/mm2
The resultant stresses due to (self-weight + prestress + Live load) are shown in fig.1.
Maximum working stress in concrete = 11.16 N/mm2 (Compression)
1. Diagram:
4.95 4.95 2.16 9.0 11.16
Result:
Maximum working stress in concrete = +11.16 N/mm2
Given Data:
Wide (b) = 250 mm
Deep (D) = 600 mm
4 wires of 14 mm diameter located 200 from the bottom (soffit)
Effective stress in wire (fpe) = 700 N/mm2
32
To calculate:
1. To determine the maximum bending moment
Solution:
M
= Total stresses at soffit
Z
i. Centroidal distance
x142
153.93mm
2
Area of wire =
4
4 x 153.93 x 200
y= =200 mm
(4 x 153.93)
P = No's of wires x f pi x As
P = (4 x 700 x 153.93) = 431.00 x 103 N
Ac = b x D
P 431.0x 103
= 3
= +2.87 N/mm2
c
A 150 x 10
33
i. Section modulus:
Step 6: Maximum moment on the section for zero tension at the soffit:
M
= Total stresses at soffit
Z
M
= Total stresses at soffit
Z
M
= 5.74
Z
M = 5.74 x (15 x 106 )
M = 86.1 x 106 N mm
Result:
Maximum bending moment at soffit of the beam without causing
tension M = 86.1 x 106 N mm
34
8. An unsymmetrical I-section beam is used to support an imposed load of 2
kN/m over a span of 8m. The sectional details are top flanges, 300 mm wide and
60 mm thick; bottom flange, 100 mm wide and 60 mm thick; thickness of web =
80 mm; overall depth of the beam is 400 mm. At the centre of the span, the
effective prestressing force of 100 kN is located at 50 mm from the soffit of the
beam. Estimate the pre stress at the centre of span section of the beam for the
following load condition:
a. Prestress + self-weight
b. Prestress + self-weight + live load
Given Data:
Top Flange:
Wide = 300 mm
Thickness = 60 mm
Bottom Flange:
Wide = 100 mm
Thickness = 60 mm
Thickness of web = 80 mm
Span (L) = 8m
35
Solution:
P Pe Mg
Extreme stresses for (Prestress + Self weight) =
Ac Z Z
P Pe Mg Mq
Extreme stresses for (Prestress + Self weight + live load) =
Ac Z Z Z
Say e = 194 mm
b d3 b 2d 32 b3d33
I xx = 1 1 +(A1 (y t - y1 )) 2 +
2
+(A 2 (y t - y 2 )) + +(A 3 (y t - y3 ))
2
12
12 12
300x603 2 80x280
3
= +(22400(156-200) 2
12
+(18000(156-30) +
Ixx 12
100x603
+ +(6000(156-370)2
12
I xx = 75.745 x 107 mm 4
Step 4: Section modulus
Ixx 75.745 x 107 6 3
Zt = = = 4.854 x 10 mm
yt 156.03
I xx 75.745 x 107 6 3
Zb = = = 3.104 x 10 mm
yb 243.97
36
Step 5: Direct Stress:
P 100 x 103 2
= = +2.155 N/mm
Ac (18000)+(22400)+(6000)
Step 6: Bending Stress due to Prestress:
i. For top fibre:
P x e 100 x 103 x 194 2
= 6 = -3.996 N/mm
Zt 4.854 x 10
ii. For bottom fibre:
P x e 100 x 103 x 194 2
= 6 = +6.250 N/mm
Zb 3.104 x 10
Step 7: Bending Stress due to self-weight at centre:
i. Self-weight of beam (Wg):
w g = (Area of section )x (Dc )
= ( (18000)+(22400)+(6000) /106 ) x 24
= 1.113 kN/m
w q L2 2x 8 2
Mq = = = 16 kN m
8 8
37
ii. Bending stress due to live load:
For top fibre:
Mq 16 x 106 2
= 6 = +3.296 N/mm
Zt 4.854 x 10
For bottom fibre:
Mq 16 x 106 2
= 6 = -5.154 N/mm
Zt 3.104 x 10
Step 9: Resultant stress for the given Conditions:
Condition: 1 (Prestress + self-weight
Top fibre = (Prestress + self-weight)
= (-3.996+2.155+1.838)
= -0.003 N/mm2
Bottom fibre = (Prestress + self-weight)
= (6.250+2.155-2.867)
= +5.538 N/mm2
Result:
Resultant Stress forCondition: 1 (Prestress + self-weight)
i. R.S attop fibre = -0.008 N/mm2
ii. R.S at bottom fibre = +5.538 N/mm2
38
9. A prestressed concrete beam of section 200 mm wide by 300 mm deep is used
over an effective span of 6 m to supports an imposed load of 4 kN/m. The density
of concrete is 24 kN/m3.
At the centre of span section of the beam, find the magnitude of
(a) The concentric prestressing force necessary for zero fibre stress at the
soffit when the beam is fully loaded; and
(b) The eccentric prestressing force located 100 mm from the bottom of the
beam which would nullify the bottom fibre stresses due to loading.
Given Data:
Wide (b) = 200 mm
Deep (D) = 300 mm
Effective span (L) = 6m
Imposed load (wq) = 4 kN/m
Density of concrete (Dc) = 24 kN/m3
Steel wires location (ye) = 100 mm from soffit
To calculate:
1. To determine the concentric prestressing force (if e = 0; P =?)
2. To determine the eccentric prestressing force (if e = 50; P =?)
Solution:
P Pe M g M q
Resul tan t stress at soffit of the beam 0
A C Zb Zb Zb
Ac = b x D
39
ii. Self-weight moment (Mg):
w g L2 1. 44 x 62
Mg = = = 6 . 48 kN m
8 8
iii. Section modulus:
bD2 200 x 3002 6 3
Z=Zt =Zb =
6 = 3 x 10 mm
=
6
Note: Given section is symmetric section so Z=Z t =Zb
w q L2 4 x 6 2
Mq = = = 18 kN m
8 8
Mq 18 x 106 2
= 6 = ±6 N/mm
Z 3 x 10
Step 4: Concentric Prestressing force:
= - 8.16 N/mm2
If P = concentric prestressing force, for zero stresses at the soffit of the beam under
loads
P Pe M g M q
0
C
A Z b Z b Z b
40
P
A 8.16 N/mm
2
c
P = (8.16 x 60000)
P = 489.60 kN
Step 5: Eccentric Prestressing force:
If P = eccentric prestressing force, for zero stresses at the soffit of the beam
under loads
P Pe M g M q
0
C
A Z b Z b Z b
P P x e
8.16 N/mm
2
Ac Zb
i. Eccentricity (e):
e = ((D/2)-ye) = (150-100) = 50 mm
P P x 50
8.16
60000 3 x 106
1 50
P 8.16
60000 3 x 106
P(1.666 x 10-5 +1.666 x 10-5 ) 8.16
P = 244.80 kN
Result:
41
10. A Prestressed concrete beam of rectangular section 300 mm wide and 600
mm deep has a span of 12 m. The effective prestressing force is 980 kN, at an
eccentricity of 120 mm. The dead load of the beam is 4.5kN/m and the beam has
to carry a live load of 7.5 kN/m. Find the extreme stresses for the following
conditions:
Solution:
P Pe P Pe
R.S at top and R.S at bottom
A C Z t A C Zt
ii. Extreme stresses at mid span section without the action of Live load
P Pe M g P Pe M g
R.S at top and R.S at bot
AC Zt Zt AC Zt Zt
42
iii. Extreme stresses at mid span section with the action of Live load
P Pe M g M q
R.S at top and
AC Zt Zt Zt
P Pe M g M q
R.S at bot
A C Zb Zb Zb
Ac = b x D
bD 2 300 x 6002 6 3
Z=Zt =Zb = = = 18 x 10 mm
6 6
Note: Given section is symmetric section so Z=Z t =Zb
P 980 x 103 2
= 3 = + 5.44 N/mm
Ac 180 x 10
w g L2 4.5 x 12 2
Mg = = = 81 kN m
8 8
43
Mg 81 x 106 2
= 6 = ± 4.5 N/mm
Z 18 x 10
wq = 7.5 kN/m
44
Condition 2 : Extreme stresses at mid-span without the action of live load
Resultant stress at mid-section without the action of Live load
P Pe M
= g
AC Z Z
P Pe Mg 980 x103 980 x103 x120 81x106
R.S at top 3
AC Zt Zt 180 x10 18x106 18x106
= 5.44 – 6.53 + 4.5 = 3.41 N/mm2
P Pe M g M q
R.S at top
AC Zt Zt Zt
P Pe Mg Mq
R.S at bottom
A C Zb Zb Zb
Result:
45
ii. Extreme stresses at mid span section without the action of Live load
Resultant stress at top = + 3.41 N/mm2
Resultant stress at bottom = + 7.47 N/mm2
iii. Extreme stresses at mid span section with the action of Live load
Resultant stress at top = + 10.91 N/mm2
Resultant stress at bottom = - 0.03 N/mm2
11. A prestressed concrete beam of section 120 mm wide by 300 mm deep is used
an effective span of 6 m to support a uniformly distributed load 4kN/m, which
includes the self-weight of the beam. The effective span of the beam is 6 m. The
beam is concentrically prestressed by a cable carrying a force of 180 kN. Locate
the position of the pressure line (or) thrust line in beam.
Given Data:
Span (L) = 6m
To calculate:
(1) Locate the position of pressure line (or) thrust line
Solution:
M
i. Lever arm distance „a‟ =
P
ii. Shift of pressure line e‟ = a-e
46
wl2
iii. B.M at centre span = (for udl)
8
w g q = 4 kN/m
w 2
4x62
g q L
Mq = = = 18 kN m
8 8
M 18 x106
a 100mm
P 180 x103
c
A Z t 36 x10 1.8x10
47
P Pe ' 180x103 180x103 x100
ii. R.S at top = = 3
6 =-5 N/mm
2
c
A Z t 36 x10 1.8x10
Result:
i. Lever arm distance „a‟ (shift from tendon line) at mid span = 100 mm
ii. Shift of pressure line e‟(shift from neutral axis) at mid span =+100 mm
iii. Extreme stress at mid-span section
a. R.S at top fibre = + 15 N/mm2
b. R.S at top fibre = -5 N/mm2
12. A prestressed concrete beam of section 120 mm wide by 300 mm deep is used
over an effective span of 6 m to support a uniformly distributed load 4kN/m,
which includes the self-weight of the beam. The beam is prestressed by a straight
cable carrying a force of 180kN and located at an eccentricity of 50 mm.
Determine the location of the thrust line (or) pressure line in the beam and plot
its position at quarter and central span section. And also find the extreme fibre
stress at mid-span and quarter span section.
Given Data:
Wide (b) = 120 mm
Overall depth (D) = 300 mm
Span (L) = 6m
Dead load & Live load = 4 kN/m
Prestressing force (P) = 180 kN
Eccentricity (e) = 50 mm
To calculate:
Locate the position of pressure line (or) thrust line at quarter and central span
section
Solution:
M
i. Lever arm distance „a‟ =
P
ii. Shift of pressure line e‟ = a-e
48
wl2
iii. B.M at centre span = (for udl)
8
3wl2
iv. B.M at quarter span = (for udl)
32
P Pe'
v. Extreme stresses at mid span = mid
A Z
P Pe 'quarter
vi. Extreme stresses at quarter span =
A Z
wl2 4x62
i. Bending moment at centre span = = 18kN.m
8 8
3wl2 3x4x62
ii. Bending moment at quarter span = = 13.5kN.m
32 32
Step 2: Lever arm ‘a’ (shift from tendon line)at central and quarter span section:
M centre 18 x106
i. a mid 100mm
P 180 x103
49
Step 4: Section Modulus:
bD 2 120 x 3002 6 3
Z=Zt =Zb = = = 1.8 x 10 mm
6 6
Note: Given section is symmetric section so Z=Z t =Zb
Step 5: Extreme fibre stress for mid-span section and quarter span section:
a.Extremefibre stress at mid-span section:
P Pe'mid 180 x103 180 x103 x50
i. R.S at top fibre= = 6 = +10 N/mm
2
Result:
i. Lever arm distance „a‟ (shift from tendon line) at mid span = 100mm
ii. Lever arm distance „a‟ (shift from tendon line) at quarter span = 75mm
iii. Shift of pressure line e‟(shift from neutral axis) at mid span = + 50mm
iv. Shift of pressure line e‟(shift from neutral axis) at quarter span = +25 mm
v. Extreme stress at mid-span section
a. R.S at top fibre = + 10N/mm2
b. R.S at top fibre = 0 N/mm2
vi. Extreme stress at quarter span section
a. R.S at top fibre = + 7.5 N/mm2
b. R.S at top fibre = + 2.5 N/mm2
50
13. A rectangular concrete beam 250 mm wide by 300 mm deep is prestressed by
a force of 540 kN at a constant eccentricity of 60 mm. The beam supports a
concentrated load of 68 kN at the centre of span of 3 m. Determine the location of
the pressure line at the centre, quarter span and support section of the beam,
Neglect the self-weight of the beam. And also find the extreme stress at centre
and quarter span section.
Given Data:
Wide (b) = 250 mm
Overall depth (D) = 300 mm
Span (L) = 3m
Concentrated load = 68 kN
Prestressing force (P) = 540 kN
Eccentricity (e) = 60 mm
To calculate:
i. Locate the position of pressure line (or) thrust line at quarter and central span
section
ii. Extreme stress at centre and quarter span section
Solution:
M
i. Lever arm distance „a‟ =
P
ii. Shift of pressure line e‟ = a-e
wl
iii. B.M at centre span = (for point load)
4
wl
iv. B.M at quarter span = (for point load)
8
P Pe'
v. Extreme stresses at mid span = mid
A Z
P Pe 'quarter
vi. Extreme stresses at quarter span =
A Z
51
Step 1: Bending moment at central and quarter span section:
wl 68x3
i. Bending moment at centre span = = 51kN.m
4 4
wl 68x3
ii. Bending moment at quarter span = = 25.5 kN.m
8 8
Step 2: Lever arm ‘a’ (shift from tendon line)at central and quarter span section:
M centre 51x106
i. a mid 94.4mm
P 540 x103
Note: e‟ is +ve means lies above Neutral axis and e‟ is -ve means lies below
Neutral axis
bD 2 250 x 3002 6 3
Z=Zt =Zb = = = 3.75 x 10 mm
6 6
Note: Given section is symmetric section so Z=Z t =Zb
52
Step 5: Extreme fibre stress for mid-span section and quarter span section:
a. Extreme fibre stress at mid-span section:
Result:
vii. Lever arm distance „a‟ (shift from tendon line) at mid span = 94.4 mm
viii. Lever arm distance „a‟ (shift from tendon line) at quarter span = 47.2 mm
ix. Shift of pressure line e‟(shift from neutral axis) at mid span = + 34.4 mm
x. Shift of pressure line e‟(shift from neutral axis) at quarter span = - 12.8 mm
xi. Extreme stress at mid-span section
a. R.S at top fibre = + 12.15 N/mm2
b. R.S at top fibre = + 2.25 N/mm2
xii. Extreme stress at quarter span section
a. R.S at top fibre = + 9.04 N/mm2
b. R.S at top fibre = + 5.36 N/mm2
53
14. A box girder of prestressed concrete bridge of span 40 m has overall
dimensions of 1200 mm by 1800 mm. The uniform thickness of the wall is 200
mm. The live load analysis indicates a maximum live load moment of 2000 kNm
at the centre of the span. The beam is prestressed by parabolic cables with an
effective force of 7000 kN. The cables which are concentric at supports have an
eccentricity of 800 mm at the centre of span section. Compute the resultant
stresses at the centre of span section using the internal resisting couple method.
The longitudinal elevation and C/S of the girder is shown in figure.
Given Data:
Span (L) = 40 m
Solution:
P Pe'
Resultant stress =
Ac Z
54
Step 1: Cross sectional area of Girder:
I 400.26x109 6 3
Z=Zt =Zb = = = 444x10 mm
yt 900
Note: Given section is symmetric section so Z=Z t =Zb
w g L2 26 x 402
Mg = = = 5200kNm
8 8
Step 4: Total bending moment (M):
M = Mg Mq
Where
Mg = Bending moment due to self-weight = 5200 kNm
55
Step 5: Lever arm ‘a’ (Shift from tendon line):
M 7200x106
a 1028mm
P 7000 x103
Result:
i. Lever arm distance „a‟ (shift from tendon line) at mid span = 1028 mm
ii. Shift of pressure line e‟(shift from neutral axis) at mid span = + 228
mm
iii. Extreme stress at mid-span section
a. R.S at top fibre = + 10.32 N/mm2
b. R.S at top fibre = + 3.14 N/mm2
56
Concept of Load Balancing:
15. A Prestressed concrete beam is prestressed with a tendon bent as shown. The
external load of the beam consists of a concentrated load of 180 kN at mid-span.
If the effective prestressing force is 1200 kN. Find the extreme stresses at
midspan section, using load balancing method.
Given Data:
Span (L) = 6m
Dead load = 6 kN /m
Live load = 180 kN
Prestressing force (P) = 1200 kN
Eccentricity (e) = 140 mm
To calculate:
Extreme stresses at mid-span section using load balancing method
Solution:
P M
i. Resultant stress =
Ac Z
57
Step 1: Upward load for bent tendon:
4Ph 4x1200x140
Upward load = = 112kN
L 6000
=180 – 112 = 68 kN
Wg 6kN / m
Wg L2 6 x 62
Mg 27 kNm
8 8
W
q net L
M q net for point load
4
68 x 6
102 kNm
4
M = M g M q(net)
Where
Mg = Bending moment due to self-weight = 27 kNm
58
Step 6: Section Modulus of the section:
Section Modulus:
bD 2 400x6002 6 3
Z=Zt =Zb = = = 24x10 mm
6 6
Note: Given section is symmetric section so Z=Z t =Zb
= - 0.375 N/mm2
Results:
i. Resultant stress at top = + 10.375 N/mm2
ii. Resultant stress at bottom = - 0.375 N/mm2
16. The figure shows a prestressed concrete beam provided with a tendon having
a parabolic profile.If the external load on the beam is 35kN/m on the whole span.
Find the extreme fibre stresses at mid-span section by load balancing method.
The tendon carries a prestressing force of 1000kN.
59
Given Data:
Span (L) = 6m
Solution:
P M
i. Resultant stress =
Ac Z
8Ph 8x1000x0.1
Upward load = 2 = 22.22kN / m
L 62
60
Wg L2 6 x 62
Mg 27 kNm
8 8
W 2
q net L
M q net for udl
8
12.78 x 62
57.51kNm
8
M = M g M q(net)
Where
Mg = Bending moment due to self-weight = 27 kNm
M 27 57.51 84.51kNm
bD 2 400x6002 6 3
Z=Zt =Zb = = = 24x10 mm
6 6
Note: Given section is symmetric section so Z=Z t =Zb
= + 7.68 N/mm2
61
P M P M 1000 x103 84.51x106
ii. R.S at top fibre = =
c b
24 x106
A Z c
A Z b 600 x 400
= 0.64 N/mm2
Results:
iii. Resultant stress at top = + 7.68 N/mm2
iv. Resultant stress at bottom = 0.64 N/mm2
17. A prestressed concrete beam 500 mm x 800 mm deep has simply supported
span of 10 m. It is prestressed with a linearly bent tendon with zero eccentricity
at end and an eccentricity of 200 mm below the axis at mid-span. The beam
carries a concentrated load of 150 kN at centre besides its self -weight. Compute
the extreme fibre stresses at mid-span using the stress concept, Strength concept
and load balancing concept. The prestressing force in the beam is 1000 kN.
Given Data:
Span (L) = 10 m
i. Stress Concept
62
Solution:
i. Stress Concept
P Pe M g M q
R.S at top
AC Zt Zt Zt
P Pe M g M q
R.S at bottom
C
A Z b Z b Zb
ii. Strength Concept
P Pe '
R.S
A C Zt
M
Lever arm distance „a‟ =
P
Shift of pressure line e‟ = a-e
iii. Load balancing Concept
P M
Resultant stress =
Ac Z
4Ph
For bent tendon, upward load =
L
wx L
B.M due to point load =
4
I. Stress Concept
Ac = b x D
63
Step 2: Section Modulus:
P 1000 x 103 2
= 3 = + 2.5 N/mm
Ac 400 x 10
w g L2 10x 10 2
Mg = = = 125 kN m
8 8
Mg 125 x 106 2
= 6 = ± 2.34 N/mm
Z 53.33 x 10
wq = 150 kN
64
Mq 375 x 106
= 6
= ± 7.03 N/mm2
Z 53.33 x 10
P Pe M g M q
R.S at top
AC Zt Zt Zt
M = Mg + M q
M 500 x10
6
a = 500mm
P 1000 x103
65
Step 4: Extreme stresses at mid-span section:
Since e‟ is +ve,
= +8.12 N/mm2
= - 3.12 N/mm2
=150 – 80 = 70 kN
Wg (0.5x0.8x25) 10kN / m
Wg L2 10 x102
Mg 125kNm
8 8
W
q net L
Mq net for point load 70 x10 175kNm
4 4
66
Step 5: Total bending moment at centre (M):
M = M g M q(net)
Where
Mg = Bending moment due to self-weight =125kNm
67
LOSSES OF PRESTRESS:
18. A pre-tensioned concrete beam of rectangular cross section 150 mm wide and
300 mm deep is pre-stressed by eight high tensile wire of 7 mm diameter located
at 100 mm from the soffit of the beam. If the wires are tensioned to a stress of
1100 N/mm2, calculate the percentage loss of stress due to elastic deformation
assuming the modulus of elasticity of concrete and steel as 31.5 kN/ mm2 and 210
kN/mm2 and also find strain in concrete at the level of wire.
Given Data:
Wide (b) = 150 mm
Deep (D) = 300 mm
Pre-tensioned stress of wires (fpi) = 1100 N/mm2
Modulus of elasticity of concrete (EC) = 31.5 kN/mm2
Modulus of elasticity of steel (ES) = 210 kN/mm2
8 No‟s of high tensile wire of 7 mm diameter located at 100 mm from the soffit
To Calculate:
To calculate the percentage loss of stress due to elastic deformation
Solution:
= x 8 = 307.87 mm
2
4
P = (1100 x 307.87) = 338.65 x 10 N 3
P = 338.65 kN
68
Step 2: Cross section Area:
Ac = b x D
bD3 150x3003
I xx 337.5x106 mm4
12 12
Es 210
c 6.667
E c 31.5
Step 5: Stress in concrete at level of steel (wire)
P Pe
2
fc
A I
333.65x103 333.65x103 x50 2
45000 337.5x106
10.03N / mm 2
Step 6: Strain concrete at the level of steel (wire):
f 10.03
c 0.00031
E c 31.5
69
19. A prestressed concrete pile, 250 mm square, contains 60 pre-tensioned wires,
each of 2 mm diameters, uniformly distributed over the section. The wires are
initially tensioned on the prestressing bed with a total force of 300 kN. Calculate
the final stress in concrete and the percentage loss of stress is steel after all losses,
gives the following data:
Es = 210 kN/mm2
Ec = 32 kN/mm2
Shortening due to creep = 30 x 10-6 mm/mm per N/mm2
Total shrinkage = 2 x 10-4 per unit length
Relaxation of steel stress = 5 % of initial stress
Given Data:
Prestressed concrete pile (Square)= 250 x 250 mm
60 wires of 2 mm diameter
Es = 210 kN/mm2
Ec = 32 kN/mm2
fcu = 42 N/mm2
Total shrinkage ( εcs ) = 2 x 10-4 per unit length
Relaxation loss = 5%
To Calculate:
To calculate the final stress in concrete and the percentage loss of stress is steel
after all losses
Solution:
Effective prestress x Totalloss
a. Final stress in concrete =
Area of c / s
b. Effective pre stress = (Initial pre stress – Total loss)
c. For Pre tensioned Total loss
Lossdue toelasticdeformation Lossdue to Relaxation of steelstress
=
Lossdue toShrinkage Lossdue tocreep
Totalloss
4. % Loss of stress in steel = x100
Initialstress
70
Step 1:Area of concrete (Ac):
Ac = (b x D)
Ac = (250 x250) = 62500 mm2
Step 2: AverageInitial stress in concrete:
P 300 x 103 2
fc = = = 4.8 N/mm
Ac 62500
Step 3: Initial stress in wire (fpi)
πd 2
As = No's of wires x
4
π(2)2
As = 60 x = 188.49 mm2
4
P 300 x 103 2
f pi = = = 1591 N/mm
As 188.49
Step 4:Modular Ratio:
Es 210
c 6.58
c
E 32
Step 5: Losses of pre stress (Pre-tensioned member):
i. Loss of stress due to elastic deformation of concrete:
= (α c x f c )
= (6.58 x 4.8)
= 31.5 N/mm 2
71
d. Loss of stress due to creep:
loss of stress in steel = ε cc x Es
where ε cc 30x106 mm / m per N / mm 2 of stress (given)
= (30 x 10-6 )(4.8) = 144x106
= (144x106 )(210 x 103 )
= 30 N/mm 2
Step 6: Total loss: (Pre-tensioned beam)
1408 x183.05
=
250x250
= 4.12 N/mm2
183.05
% loss of stress = x 100 = 11.5 %
1591
Result:
Percentage loss of stress in wires = 11.51 %
72
20. A prestressed concrete beam, 200 mm wide and 300 mm deep, is prestressed
with wires (area = 320 mm2) located at a constant eccentricity of 50 mm and
carrying an initial stress of 1000 N/mm2. The span of the beam is 10 m. calculated
the percentage loss of stress in wires if (a) the beam is pre-tensioned, and (b) the
beam is post-tensioned, using the following data:
Es = 210 kN/mm2
Ec = 35 kN/mm2
Creep co-efficient = 1.6
Total shrinkage = 3 x 10-4 for pre-tensioning
Total shrinkage = 2 x 10-4 for post-tensioning
Relaxation of steel stress = 5 % of initial stress
Slip at anchorage = 1 mm
Frictional co-efficient for wave effect = 0.0015 per m
Given Data:
Wide (b) = 200 mm
Deep (D) = 300 mm
Span (L) = 10 m
Initial stress in wire (fpi) = 1000 N/mm2
Eccentricity (e) = 50 mm
Relaxation loss = 5%
Es = 210 kN/mm2
Ec = 35 kN/mm2
Creep co-efficient ( ) = 1.6
Total residual shrinkage ( εcs )=3 x 10-4 for pre-tensioning
73
Step 1:Prestressing force (P):
P = As x f pi
P = (320 x 1000) = 320 x 103 N
74
Loss of stress = (ε cs x Es )
= (300 x 10-6) x (210 x 103)
= 63.0 N/mm2
222.20
% loss of stress = x 100 = 22.22 %
1000
75
Loss of stress = (ε cs x Es )
= (200 x 10-6) x (210 x 103)
= 42.0 N/mm2
76
Totalloss
% loss of stress = x100
Initialstress
237.20
% loss of stress = x 100 = 23.7 %
1000
Result:
Given Data:
Eccentricity (e) = 200 mm (at 1/3 of span)
Span (L) = 12 m
Area of cable (As) = 800 mm2
Initial stress in wires (Px) = 1000 N/mm2 (At un-jacked end B)
μ = 0.55 and k = 0.0015 per m
To Calculate:
To determine the stress in the wires at the jacking end
Solution:
Step 1:Slope of cable:
e
Slope at A ( ) =
L/3
200
= = 0.05
12000/3
Total change of slope of cable from A to B = (2 x 0.05) = 0.1
If Po is the stress in the wires at jacking end A, the loss of stress in the wires
from A to B is
77
Loss of stress = Po (μα + kx)
= Po (0.55 x 0.1 + 0.0015 x 12) Step 2:Prestress in jacking end
= 0.073 Po
at A:
Px = Po (1-(μα + kx))
1000 = Po (1-(0.55 x 0.1 + 0.0015 x 12))
1000 = 0.927 Po
1000 2
Po = = 1078.74 N/mm
0.927
Result:
The stress in the wires at the jacking end (Po) = 1078.74 N/mm2
Deflection
22. The deck of prestressed concrete culvert is made up of a slab 500 mm thick.
The slab is spanning over 10.4 m and supports a total uniformly load comprising
the dead load and live loads of 33.5 kN/m. The modulus of elasticity of concrete is
38kN/mm2. The concrete slab is prestressed by straight cables each containing 12
high-tensile wire of 7 mm diameter stressed to 1200 N/mm2 at a constant
eccentricity of 195 mm. The cables are placed at 328 mm intervals in the
transverse direction. Estimate the instantaneous deflection of the slab at centre of
span under prestress and the imposed loads.
Given Data:
Deep (D) = 500 mm
Span (L) = 10.4 m
Dead and Live load (wq) = 33.5 kN/m
Modulus elasticity of concrete (Ec) = 38 kN/mm2
12-high-tensile wires of 7 mm diameter
Initial stress of wires = 1200 N/mm2
Constant eccentricity (e) = 195 mm
Spacing of cables = 328 mm (transverse direction)
To Calculate:
78
To estimate the instantaneous deflection of the slab at centre of span section
under prestress and imposed load
Solution:
Considering 1 m width of the slab, the properties of the cross section are computed.
PeL2
Upward deflection due to prestress
8EI
5gL4
Downward deflection due to D.L & L.L
384EI
PeL2
Upward deflection due to prestress(PS )
8EI
1689.54x195x 10.4x1000 2
8x38x10416.67x10 6
79
= -11.25 mm (Upwards)
23. A concrete beam with a rectangular section 300mm wide and 500mm deep is
prestressed by 2 post-tensioned cables of area 600mm2each.Initially stressed to
1600N/mm2.The cables are located at a constant eccentricity of 100mm
throughout the length of the beam having a span of 10m. The modulus of
elasticity of steel and concrete is 210 and 38kN/mm2 respectively.
a. Neglecting all losses, find the deflection at the centre of span when it is
supporting its own weight.
b. Allowing for 20% loss in prestress, find the final deflection at the centre of
when it carries an imposed load of 18kN/m. Dc = 25kN/m3.
Given Data:
Beam size = 300 x 500 mm
Span (L) = 10 m
Area of prestressing cable = 2x600mm2
Eccentricity e = 100mm
Modulus elasticity of concrete (Ec) = 38 kN/mm2
Modulus elasticity of steel (Es) = 210kN/mm2
Density of concrete Dc = 25kN/m3
80
Live load = 18 kN/m
Loss = 20%
Type of cable = Straight cable at uniform eccentricity.
To Calculate:
Solution:
PeL2
i. Upward deflection due tostraight tendon
8EI
5gL4
ii. Downward deflection due to D.L
384EI
5qL4
iii. Downward deflection due to L.L iv. Final deflection PS DL LL
384EI
81
Step 4: Upward deflection due to pre stress:
PeL2
Upward deflection due to prestress(PS )
8EI
1920x100x100002
8x38x3125x106
= -20.20 mm (Upwards)
5x0.0037x10000 4
DL
384x38x3125x106
DL 4.05mm(downward)
5x0.018x100004
DL
384x38x3125x106
DL 19.73mm(downward)
Step 7: Deflection at the centre of the span when it supports its own weight:
Final PS DL
82
Step 9: Final Deflection at the centre of the span after loss in prestress when it
carries an udl of 18kN/m:
Final PS DL LL
= -16.16+ 4.05+19.73
= +7.62mm(downward)
Result:
1. Final at the centre of span when it is supporting its own weight = -16.15 mm
2. Final at the centre of span when it carries an udl of 18kN/m and allowing for
20% loss = +7.62 mm
24. A concrete beam with a cross sectional area of 32 x 103 mm2 and radius of
gyration of 72mm is prestressed by a parabolic cable carrying an effective
prestress of 1000 N/mm2.The span of the beam is 8m.The cable composed of 6
wires of 7mm diameter has an eccentricity of 50mm at the centre and zero at
supports. Neglecting all losses, Find the central deflection of the beam as follows.
a. Self-weight + Prestress
Given Data:
c/s area of beam = 32x103 mm2
Radius of gyration rxx = 72 mm
Span (L) = 8m
Prestress = 1000N/mm2
Eccentricity e = 50 mm @ centre and zero @ supports
Modulus elasticity of concrete (Ec) = 38 kN/mm2
Live load = 2kN/m
Type of cable = Parabolic cable (central Anchors)
To Calculate:
83
a. Self-weight + Prestress
Solution:
PeL2
i. Upward deflection due to parabolic tendon centralanchors 5
48EI
5gL4
ii. Downward deflection due to D.L
384EI
5qL4
iii. Downward deflection due to L.L
384EI
32x103
x25
10002
0.8kN / m 0.0008kN / mm
Step 2: Moment of inertia:
x72
Area of tendon = x6 = 231 mm2
4
84
PeL2
Upward deflection due to prestress(PS ) 5
48EI
231x150x80002
5
48x38x165.88x106
= -12.22 mm (Upwards)
5x0.0008x8000 4
DL
384x38x165.8x106
DL 6.76mm(downward)
5x0.002x80004
DL
384x38x165.88x106
DL 16.92mm(downward)
Condition 1: PS DL
25. A rectangular concrete beam of cross section 150 mm wide and 300 mm deep
is simply supported over a span of 8 m and is prestressed by means of a
85
symmetric parabolic cable, at a distance of 75 mm from the bottom of the beam
at mid span and 125 mm from the top of the beam at support sections. If the
force in the cable is 350 kN and the modulus of elasticity of concrete is 38
kN/m2calculate
(a) The deflection at mid-span when the beam is supporting its own weight, and
(b) The concentrated load which must be applied at mid-span to restore it to the
level of supports.
Given Data:
Beam size = 150 x 300 mm
Span (L) = 8m
Prestressing force = 350 kN
Eccentricity e 1 = 75 mm; e2 = 25mm
Modulus elasticity of concrete (Ec) = 38 kN/mm2
Type of cable = Parabolic cable with eccentric anchors.
To Calculate:
Solution:
PL2
48EI
i. Upward deflection due toparabolic with eccentricanchors 5e1 e2
5gL4
ii. Downward deflection due to D.L
384EI
5qL4
iii. Downward deflection due to L.L
384EI
86
g = (Area of c/s x unit weight of concrete)
g = (0.15x 0.3 x 25)
g = 1.125 kN/m = 0.00125 kN/mm
Step 2: Moment of inertia:
PL2
48EI
Upward deflection due to prestress(PS ) 5e1 e2
350x80002
5x75 25
48x38x337.5x106
= -12.70 mm (Upwards)
5x0.00125x8000 4
DL
384x38x337.5x106
DL 5.19mm(downward)
Step 5: Deflection at the centre of the span when it supports its own weight:
Final PS DL
87
If „Q‟ = Concentrated load required at the centre of span,
wl 3
For concentrated load ,
48EI
Ql3
Then, 7.51 =
48EI
Qx80003
d. =
48x38x337.5x106
Q = 9.02kN
Result:
1. Final at the centre of span when it is supporting its own weight = -12.70 mm
2. Concentrated load Q = 9.02kN
26. A concrete beam having a rectangular section 100mm wide and 300mm deep
is prestressed by a parabolic cable carrying an initial force of 240kN. The cable
has an eccentricity of 50mm at the centre of span at the supports. If the span of
the beam is 10m wide and the live load is 2kN/m.Estimate the short time
deflection at the centre of span.Assuming Ec= 38kN/mm2 and creep co-efficient
Ф = 2.0. Loss of pre stress = 20% of initial stress after 6 months. Estimate the
long time deflection at the centre of span at this stage, assuming the dead and live
loads are simultaneously applied after the release of pre stress.
Given Data:
Beam size = 100 x 300 mm
Span (L) = 10 m
Initial Prestressing force = 240 kN
Eccentricity e = 50mm @ centre and zero @ supports
Modulus elasticity of concrete (Ec) = 38 kN/mm2
Creep co-efficient = 2.0
Live load = 2 kN/m
Loss = 20% of initial stress
Type of cable = Parabolic cable with central anchors
88
To Calculate:
Solution:
PieL2
i. Upward deflection due to parabolic tendon with centralanchors 5
48EI
5gL4
ii. Downward deflection due to D.L
384EI
5qL4
iii. Downward deflection due to L.L
384EI
L p Lp
Long time deflection i1 1 ip 1 1
Pi 2Pi
89
5P eL2
Upward deflection due to prestress(PS ) i
48EI
5x240x50x100002
14.61mm
48x38x225x106
= -14.61 mm (Upwards)
5x0.00075x100004
DL
384x38x225x106
DL 11.42mm(downward)
5x0.002x100004
DL
384x38x225x106
DL 30.45mm(downward)
Final PS DL LL
90
i. Initial deflection due to transverse loads( i1 )
i1 LL DL = 11.42 + 30.45 = 41.87 mm
ii. Initial deflection due to pre stress = 14.61 mm
iii. Final deflection ( f )
L L
f i1 1 ip 1 p 1 p (Note: L = 20% of initial stress)
Pi 2Pi p
0.2Pi 0.2 Pi
f 41.87 1 2 14.61 1 1 2
Pi 2Pi
f + 89.11 mm (downward)
Result:
1. Short time deflection = + 27.26 mm (downward)
2. Long time deflection = + 89.1 mm (downward)
27. Explain in detail about the basic concepts, advantages, materials required
and methods of prestressing. (April / May - 2015)
A prestressed concrete structure is different from a conventional reinforced
concrete structure due to the application of an initial load on the structure
prior to its use. The initial load or „pre stress‟ is applied to enable the structure
to counteract the stresses arising during its service period.
The prestressing of a structure is not the only instance of prestressing. The
concept of prestressing existed before the applications in concrete. Two
examples of prestressing before the development of prestressed concrete are
provided.
91
Fig 1 Force-fitting of metal bands on wooden barrels
For concrete, internal stresses are induced (usually, by means of tensioned steel) for
the following reasons.
The tensile strength of concrete is only about 8% to 14% of its compressive
strength.
Cracks tend to develop at early stages of loading in flexural members such
as beams and slabs.
To prevent such cracks, compressive force can be suitably applied in the
perpendicular direction.
Prestressing enhances the bending, shear and torsional capacities of the
flexural members.
In pipes and liquid storage tanks, the hoop tensile stresses can be effectively
counteracted by circular prestressing.
92
Advantages of prestressing:
The prestressing of concrete has several advantages as compared to traditional
reinforced concrete (RC) without prestressing. A fully prestressed concrete member is
usually subjected to compression during service life. This rectifies several deficiencies
of concrete.
In case of fully prestressed member, which are free from tensile stresses under
working loads
The cross section is more effectively utilized when compared with a reinforced
concrete section which is cracked under working loads.
Within certain limits, a permanent dead load may be counteracted by
increasing the eccentricity of the prestressing force in a prestressed structural
elements, thus effecting saving in the use of materials.
Prestressed concrete members possess improved resistance to shearing forces,
due to the effect of compressive prestress, which reduces the principle tensile
stress.
The use of high strength concrete and steel in prestressed members results in
lighter and slender members than is possible with reinforced concrete.
It is free from cracks, contributes to the improved durability of the structure
under aggressive environmental conditions.
The economy of prestressed concrete is well established for long span
structures.
A prestressed concrete flexural member is stiffer under working loads than a
reinforced concrete member of the same depth.
1) Section remains un-cracked under service loads:
Reduction of steel corrosion
• Increase in durability.
Full section is utilized
• Higher moment of inertia (higher stiffness)
• Less deformations (improved serviceability)of
Increase in shear capacity.
Suitable for use in pressure vessels, liquid retaining structures.
Improved performance (resilience) under dynamic and fatigue loading.
93
2) High span-to-depth ratios:
Larger spans possible with prestressing (bridges, buildings with
large column-free spaces)
Typical values of span-to-depth ratios in slabs are given below.
94
High strength concrete:
Prestressed concrete requires concrete which has a high
compressive strength at a reasonably early age, with comparatively higher
tensile strength than the ordinary concrete. Low shrinkage, minimum creep
characteristic and a high valve of Young‟s modulus are deemed necessary for
concrete used for prestressed members.
High strength concrete is necessary in prestressed concrete, as the
materials offers high resistance in tension, shear, bond and bearing. In the zone
of anchorages, the bearing stresses being higher, high strength concrete is
invariably preferred to minimize costs. The use of high strength concrete
results in a reduction in the cross sectional dimensions of prestressed concrete
structural elements. With a reduced deadweight of the material, longer spans
become technically and economically practicable.
High tensile steel:
For prestressed concrete members, the high-tensile steel used
generally consists of wires, bars, or strands. The higher tensile strength is
generally achieved by marginally increasing the carbon content in comparison
mild steel.
The steel used in prestress shall be any one of the following:-
(a) Plain hard-drawn steel wire conforming to IS1785(Part-I & Part-III)
(b) Cold drawn indented wire conforming to IS6003
(c) High tensile steel wire bar conforming to IS2090
(d) Uncoated stress relived strand conforming to IS6006
High strength steel contains:
0.7 to 0.8% carbons,
0.6% manganese,
0.1% silica
Necessity of high grade of concrete & steel:
Higher the grade of concrete higher the bond strength which is vital in
pretensioned concrete, Also higher bearing strength which is vital in post-
tensioned concrete. Further creep & shrinkage losses are minimum with high-
95
grade concrete. Generally minimum M30 grade concrete is used for post-
tensioned & M40 grade concrete is used for pretensioned members.
The normal loss of stress in steel is generally about 100 to 240 N/mm2
and it is apparent that if this loss of stress is to be a small portion of the initial
stress, the stress in steel in the initial stages must be very high, about 1200 to
2000 N/mm2 . These high stress ranges are possible only with the use of high
strength steel.
96
Anna university Two marks Questions
1. Explain why steel with a low yield stress is not used in pre-stressed construction.
(April-May 2015)
2. List the loss of pre-stress. (April-May 2015)
3. What is the principle of post-tensioning? (April-May 2015)
4.What are the advantages of PSC construction? (Nov / Dec 2014)
5. Define Pre tensioning and Post tensioning. (Nov / Dec 2014)
6. Define Basic Concept. (Nov / Dec 2013)
7. What is Relaxation of steel? (April-May 2014)
8. Define chemical pre-stressing (or) self -stressing (Nov / Dec 2014)
9. Define bonded and non -bonded pre-stressing concrete (Nov / Dec 2014)
10. Why high tensile steel is essential for pre-stressed concrete (Nov / Dec 2012, Nov
/ Dec 2015, May / June 2016)(Pg. no:3, Q.no:5)
11. List down the factors that influence the deflection of prestressed concrete
members.(Nov / Dec 2015, May / June 2016)(Pg. no:5, Q.no:17)
97
Anna University Sixteen Marks Questions
(NOV-DEC 2014)
Es = 210 kN/mm2
Ec = 5700 x (fcu)1/2
fcu = 45 N/mm2
Creep co-efficient ( ) = 1.6 and Total residual shrinkage = (3 x 10-4)
3. A rectangular concrete beam of cross section 150 mm wide and 300 mm deep
is prestressed by a parabolic cable having an eccentricity of 75 mm at mid span
towards the soffit and an eccentricity 25 mm towards the top at support
sections. The effective force in the cable is 350 kN. The beam supports a
concentrated load of 20kN at the centre of span in addition to the self-weight. If
the modulus of elasticity of concrete is 38 kN/m2 and span is 8 m. calculate
(a) Short term deflection at centre of span under prestress, self-weight and live
load.
98
(b) Long term deflection assuming the loss ratio as 0.8 and creep co-efficient as
1.6 (APRIL-MAY 2015)
4. Rectangular beam 180 mm wide and 400 mm deep is simply supported over a
span of 8 m and is reinforced with 3 wires of 8 mm diameter. The wires are
located at a constant eccentricity of 80 mm and are subjected to an initial stress
of 1200 N/mm2. Calculate the percentage loss of stress in wires if the beam is
(a) Pre-tensioned and
(b) Post-tensioned Es = 210 kN/mm2, modular ratio is 6, slip at anchorage is 0.8
mm, friction co-efficient = 0.002/m, relaxation of steel stress = 6%. Adopt
creep and shrinkage co-efficient as per IS 1343 (APRIL-MAY
2015)
6. Explain in detail about the basic concepts, advantages, materials required and
methods of prestressing. (April / May - 2015)
99
Ec = 35 kN/mm2
Creep co-efficient = 1.6
Total shrinkage = 3 x 10-4 for pre-tensioning
Total shrinkage = 2 x 10-4 for post-tensioning
Relaxation of steel stress = 5 % of initial stress
Slip at anchorage = 1 mm
Frictional co-efficient for wave effect = 0.0015 per m
10. A pre-tensioned concrete beam of rectangular cross section 150 mm wide and
300 mm deep is pre-stressed by eight high tensile wire of 7 mm diameter
located at 100 mm from the soffit of the beam. If the wires are tensioned to a
stress of 1100 N/mm2, calculate the percentage loss of stress due to elastic
deformation assuming the modulus of elasticity of concrete and steel as 31.5
kN/mm2 and 210 kN/mm2.and also find strain in concrete at the level of wire.
(Nov / Dec 2012)
100
11. Explain the systems and methods of prestressing with neat sketches.(Nov / Dec
2015, May / June 2016)(Pg.No:13, Q.No:1)
101
Important Two marks Questions
1. What are the advantages of PSC construction?
2. Define Pre tensioning and Post tensioning.
3. Define Basic Concept.
4. What is the need for the use of high strength concrete and tensile steel in Pre-
stressed concrete?
5. Define Kern Distance.
6. What is Relaxation of steel?
7. What is concordant prestressing?
8. Define bonded and non-bonded prestressing concrete.
9.Define axial prestressing
10. Define prestressed concrete.
11. State any four losses that can take place in prestressed concrete.
12. State the advantages of prestressed concrete over reinforced concrete.
13. Write any four system of prestressing?
14. Define anchorage.
15. Explain why steel with a low yield stress is not used in prestressed construction.
(April-may 2015)
16. List the loss of prestress. (April-may 2015)
17. What is the principle of post-tensioning? (April-may 2015)
18. What is mean by load balancing method of design in prestressed concrete?
19. Why loss due to creep is more for pre-tensioned beam compared to that of post
tensioned member?
20. Why is smaller diameter wires used in pre-tensioning works?
21. What are the three forms in which high tensile steel is used in the pre stressed
concrete?
22. Why high tensile steel is essential for prestressed concrete?
23. Briefly explain thermo electric prestressing.
24. Define chemical prestressing (or) self-stressing.
102
Important Sixteen marks Questions
1. A post tensioned cable of beam 10 m long is initially tensioned to a stress of
1200 N/mm2 at one end. If the tendons are curved so that the slope is 1 in 24 at
each end, with an area of 600 mm2, calculate the loss of prestress due to
friction given the following data
Co-efficient of friction b/w duct and cable = 0.55; friction co-efficient
for „wave‟ effect = 0.0015 per m. During anchoring, if the there is slip of 3 mm
at the jacking end, calculate the final force in the cable and the percentage loss
of prestress due to friction and slip. Es = 210 kN/mm2. (NOV-DEC 2014)
(NOV-DEC 2014)
Es = 210 kN/mm2
Ec = 5700 x (fcu)1/2
fcu = 45 N/mm2
Creep co-efficient ( ) = 1.6 and Total residual shrinkage = (3 x 10-4)
3. A rectangular concrete beam of cross section 150 mm wide and 300 mm deep
is prestressed by a parabolic cable having an eccentricity of 75 mm at mid span
towards the soffit and an eccentricity 25 mm towards the top at support
sections. The effective force in the cable is 350 kN. The beam supports a
concentrated load of 20kN at the centre of span in addition to the self-weight. If
the modulus of elasticity of concrete is 38 kN/m2 and span is 8 m. calculate
(a) Short term deflection at centre of span under prestress, self weight and live
load.
103
(b) Long term deflection assuming the loss ratio as 0.8 and creep co-efficient as
1.6 (APRIL-MAY 2015)
4. Rectangular beam 180 mm wide and 400 mm deep is simply supported over a
span of 8 m and is reinforced with 3 wires of 8 mm diameter. The wires are
located at a constant eccentricity of 80 mm and are subjected to an initial stress
of 1200 N/mm2. Calculate the percentage loss of stress in wires if the beam is
(a) Pre-tensioned and
(b) Post-tensioned Es = 210 kN/mm2, modular ratio is 6, slip at anchorage is 0.8
mm, friction co-efficient = 0.002/m, relaxation of steel stress = 6%. Adopt
creep and shrinkage co-efficient as per IS 1343 (APRIL-MAY
2015)
6. a. Explain in detail about the basic concepts, advantages, materials required and
methods of prestressing. (April / May - 2015)
b. Explain the systems and methods of prestressing with neat sketches.(Nov /
Dec 2015, May / June 2016)( Pg. No : 13, Q. No :1)
104
7. A prestressed concrete beam, 200 mm wide and 300 mm deep, is prestressed
with wires (area = 320 mm2) located at a constant eccentricity of 50 mm and
carrying an initial stress of 1000 N/mm2. The span of the beam is 10 m.
calculated the percentage loss of stress in wires if (a) the beam is pre-tensioned,
and (b) the beam is post-tensioned, using the following data: (Nov / Dec 2012)
Es = 210 kN/mm2
Ec = 35 kN/mm2
Creep co-efficient = 1.6
Total shrinkage = 3 x 10-4 for pre-tensioning
Total shrinkage = 2 x 10-4 for post-tensioning
Relaxation of steel stress = 5 % of initial stress
Slip at anchorage = 1 mm
Frictional co-efficient for wave effect = 0.0015 per m
105
10. A pre-tensioned concrete beam of rectangular cross section 150 mm wide and
300 mm deep is pre-stressed by eight high tensile wire of 7 mm diameter
located at 100 mm from the soffit of the beam. If the wires are tensioned to a
stress of 1100 N/mm2, calculate the percentage loss of stress due to elastic
deformation assuming the modulus of elasticity of concrete and steel as 31.5
kN/mm2 and 210 kN/mm2.and also find strain in concrete at the level of wire.
(Nov / Dec 2012).
106