Professional Documents
Culture Documents
GENERAL QA Programme
for
Projects
1
DD/MM/YY
0 Initial Release
YY
Approve
Index Date Revisions Prepared Reviewed
d
QA Programme – Construction of Transportation Engineering Projects
Table of Contents
This general QA Plan represents quality assurance policy and requirements for the
construction of Transportation Engineering projects .
The QA Programme is to provide objective evidence that the project’s mission will be
effectively completed. This will be accomplished by an integrated systems approach to
quality assurance and quality control, based on ISO 9001 quality management system.
The ultimate goal is to achieve project’s successful completion with quality engineering,
procurement, construction, commissioning and all of which is adequately documented. In
this respect, this QA Plan is to be used as a standard and this policy shall be understood,
implemented, and maintained at all levels in the organizations engaged in or concerned with
the project execution in accordance with the requirements of the contract documents.
For the overall implementation of the QA Programme, it also defines the fundamental
organizational structure and aims to complete the project work to the Engineer’s
satisfaction.
All personnel including subcontractors shall faithfully observe all plans, specification,
schedules, instructions and recommendations provided or made by Contractor, for carrying
out the project work.
The Project Manager has the primary responsibility for project quality as delegated by the
Employer organisation.
-----------------------------------------
Director
Employer
QA Programme – Construction of Transportation Engineering Projects
1.2 SCOPE
All activities of the project
1.3 PROCEDURE
Corresponding
Activity R A D
Document
Overall Target
1 Define targets and make known to all staff PM
Schedule
Work Schedule per
2 Define sub targets All Staff
Department
3 Strive to achieve targets All Staff
Compare Planned/
4 Evaluate target achievement All Staff
Actual schedule
5 Corrective action (continue with Chapter 7) All Staff PM
6 Revise targets (continue with 1) PM
1.4 ORGANISATION
The Site Management shall act in accordance with the contract Agreement and the Contract
Documents.
The Site Management shall be responsible for the due execution of the works as defined by the
contract.
The following descriptions are the main tasks and responsibilities of the Site Management.
The Project Manager is the leading authority on site and responsible for all activities on site. He is
responsible for ensuring the execution and the maintenance of the works according to contractual
specifications, drawings and programme of work. He is responsible for the proper execution of the
following:
- Approve QA Programme, Method Statement and Inspection & Test Plan (ITP),
- Define and document quality policy,
- Take corrective action on the finding of internal quality audit,
- General technical administration,
- Define the structure of his team and control its composition,
- Manage relations with the Engineer / Employer,
- Select subcontractors and suppliers and sign subcontracts and purchase orders (or authorise
signature),
- Manage subcontractors and suppliers,
- Implement a management system for costs, time, technics, safety and quality,
- Supervise administrative and financial management of the project,
- Supervise the management of the personnel placed under his control.
1.4.3.3 QA Manager
has the responsibility to
- Manage Quality Assurance and Quality Control activities, Prepare and control the QA
Programme and Inspection & Test Plan (ITP),
- Manage submission of QA documents to the Engineer,
QA Programme – Construction of Transportation Engineering Project
- Planning,
- Review of QA Programme, Method Statement and Inspection & Test Plan (ITP),
- Preparation of Project Construction Schedule Updates,
- Monitoring of Progress against Construction Schedule and Clause 14 Programmes,
- Claim Preparation,
- Assistance to Administration Manager in Cash Flow Forecast Preparation.
1 Section-1
2 Section-2
3 Section-3
4 Section-4
5 Section-5
QA Programme – Construction of Transportation Engineering Project
2. QUALITY SYSTEM
2.1 QA DOCUMENTATION
- QA Programme
- Method Statements
- Quality Procedure / Work Procedure
- Inspection & Test Plan
Inspection & Test Plans shall be provided according to the chapter 5 (Inspection and Testing) for at
least every title where quality tests are required by the contractual specifications. The Inspection and
Test Plan has to be set up by the QA Manager with support of organization who is in charge of the
work (i.e. Construction Manager, Works Manager, subcontractor).
Quality Control has to ensure that all works are carried out according to
If a product does not meet the contractual specifications, (also called ”Nonconforming Product”) it
must be guaranteed, that the product will meet the requirements by repairing or similar. The manner
is ruled by the chapter 6 (Control of Nonconforming Products).
- In case of technical problems: Corrective actions have to be carried out by alteration of the
regarding Method Statement and / or
- In case of organizational problems: Corrective actions have to be carried out by alteration of
the regarding chapters.
Besides the issuing of corrective action requests upon detected nonconformance there is the
preventive possibility for detected improvements
- In technical
- Organizational regulations, where also corrective action requests can be issued.
The issuing and introduction of corrective actions is described in the chapter 7 (Cor-rective Actions).
The quality system document hierarchy is same as below. In document structure of quality system,
the items of low level documents shall be consistent with requirements of high level documents.
QA Plan
Level I
Method Statements
3.1 PURPOSE
To define a system for the control of document approval, issue and changes / modification.
3.2 SCOPE
This chapter applies to all documents used in Transportation Engineering Project. such as Quality
Programme, Quality Procedure, Method Statement, Inspection & Test Plan and Engineering and
Technical Documents.
3.3 REFERENCE
Chapter 12 - Standard Forms Indexing System
3.4 DEFINITIONS
3.4.1 Documents
Any written information describing requirements of activities affecting quality.
Documents shall include QA Programme, Method Statement, Inspection & Test Plan and
Engineering and Technical Documents. If correspondence (e.g. letter, memo etc.) mentioned serious
subject about Quality or Technical data, it shall be maintained as document.
A document that specifies or describes how an activity is to be performed for quality / work.
Working Method for Tradesman and Workers to follow when they perform a specific job.
As a minimum, the following points shall be included:
1. Scope of Work
2. References
3. Description of the Work
4. Responsibility
5. Plant and Equipment
6. Inspection, Testing and Survey
7. Safety
8. Appendices
3.4.5 Inspection & Test Plan
Documents which contain hold point, witness point, acceptance criteria and document required
according to sequence of inspection to ascertain quality.
An identifiable copy of the QA Programme or its supporting Quality procedures and ITP which is
distributed, revised or replaced through a written Document Control Procedure that assures the
document reflects all current requirements.
An identifiable copy of the QA Programme or document that is distributed through a Document and
Data Control Procedure with no assurance that later, the document reflects all current requirements.
These shall be for information only and shall not be used as reference to perform work.
3.5 RESPONSIBILITY
1. The Project Management shall be overall responsible for the control of Documents. (i.e., QA
PLAN, Quality Procedure / Work Procedure, Method Statement, Inspection & Test Plan,
Drawings and Calculations)
2. The responsibility for each stage of the control of documents are defined in Annex 1.
3. QA Manager is responsible for taking out a unique document number of QA documents
except drawing, and Design Manager is responsible for taking out unique drawing number.
3.6 PROCEDURE
3.6.1 Internal Documents
Prepared documents by subcontractor may be indexed according to its own indexing system.
TEQA-XXX
QP-XXX / WP-XXX
CPS-X-MSP-YYY
.
CPS = Construction Plan and Specification
X = Module Number (‘0’ for two or more modules)
MSP = Method Statement
YYY = 3 Digit Running Method Statement Number
ITP-XXX
.
ITP = Inspection & Test Plan
XXX = 3 Digit Running ITP Number
TE-SX-YY-ZZZ
TE = Transportation Engineering
SX = section 0
YY = TD : Temporary Drawing
SK : Sketch
CS : Construction Drawing
AB : As-Built Drawing
ZZZ = 3 Digit Running Drawing Number
CPS-X-CLC-YYY
10. The document indexing system for standard forms shall be followed in accordance with
chapter 12 (Standard forms indexing system).
3.6.1.2 List Indexing System
TE-DML-MX-YYY-ZZZ
TE = Transportation Engineering
DML = Document Master List
MX = Module Number (‘0’ for two or more modules)
YYY = Document Type (as QAP, QPS, MSP, TCR, ITP, Etc.)
ZZZ = 3 Digit Running Documents Master List Number
TE-DWL-MX-YY-ZZZ
TE = Transportation Engineering
DWL = Drawing Master List
MX = Module Number (‘0’ for two or more modules)
YY = TD : Temporary Drawing
SK : Sketch
CS : Construction Drawing
AB : As-Built Drawing
ZZZ = 3 Digit Running Drawing Master List Number
1. All Documents must be reviewed and approved by the respective department prior to issue.
2. QA Programme must be prepared by QA Manager, reviewed by Planning Manager and
approved by Project Manager.
3. Quality Procedures must be prepared by QA Manager, reviewed by Planning Manager and
approved by Project Manager.
4. Method Statement / Work Procedure must be prepared by Construction Manager or Works
Manager, reviewed by Planning Manager and approved by Project Manager .
5. Inspection & Test Plan must be prepared by QA Manager (or QC Engineer for HCC’s
independent work), reviewed by Planning Manager and approved by Project Manager.
a. Drawings must be prepared by Design Manager, reviewed by Planning Manager and
approved by Project Manager.
6. As built drawing control procedure (work procedure) must be prepared by design
manager reviewed by planning manager and approved by project manager.
7. Calculations must be prepared by Design Engineer, reviewed by Design Manager and
approed by Planning Manager.
3.6.1.4 Distribution
1. The Project Manager shall mark the “Document Distribution Sheet” for distribution.
2. After approval of Document Distribution Sheet with documents by the Project Manager,
full set of documents are filed in Master File Shelf.
3. All following process shall be done in accordance with Annex 1 .
1. All internal and external document except drawings shall be listed up in the form of
“Documents Master List” for identification of latest status of documents.
- - Documents as mentioned above definition No. 4.2, 4.3, 4.4, 4.5 & 4.8
(except drawing)
- Appointed by Planning Manager
3. The “Documents Master List” may be prepared for each type of documents.
4. The “Documents Master List” shall be submitted to the Engineer 2 days before each Site
Meeting at least.
1. Change to documents shall be performed by department that carried out original preparation
unless specifically designated otherwise.
2. Revised portion shall be marked by typing them in bold and Italic letters. Cloud mark with
revision number shall be used for revised portion of drawing, and cloud mark shall be
used for revised portion of form.
3. The approved revised documents shall be controlled in accordance with above paragraph
6.1.3, 6.1.4, & 6.1.5.
3.6.2.1 Receipt
1. Upon receipt of document, the Document Controller shall check the following :
2. All documents received shall be controlled in accordance with ANNEX 1 of this chapter.
3.6.2.2 Review
1. Project Manager shall review the incoming document and comments at remark on the
column.
2. Document reviewed will be distributed to various department as per ANNEX 1 attached.
3. Person who received the copied incoming document shall take an action according to the
comments by Project Manager.
3.6.2.3 Distribution
All documents received shall be distributed in accordance with ANNEX 1 of this chapter.
1. All documents received shall be filed at Master File Shelf according to Master Filing System
in Annex 2 of this chapter.
2. The list-up of external documents shall be done in accordance with above paragraph 3. 6.1.5
3.6.3.1 Receipt
1. Upon receipt of drawing, Document Controller shall perform the following :
1. After checking and stamping of received drawings, the Design Engineer shall list-up the
received drawings in “Drawing Master List”.
2. The information of registration of drawing are as follows
- Drawing No.
- Drawing Title
- Revision No.
- Revision Date
- Issued Date
3. Drawing Master List shall be distributed periodically by Design Engineer to the
relevant departments for cross checking the latest status.
3.6.3.3 Distribution
1. The received drawings are distributed to Construction Manager / Works Manager by the
Design Manager.
2. A Master Set of Drawings of this Project shall be kept by Design Manager.
3. The Construction Manager / Works Manager shall make the copies for subcontractor. (if
there)
4. When receive the Master Drawing List from Design Manager, this lists shall be copied by
Construction Manager / Works Manager and distributed to subcontractor for cross checking
the latest status.
5. The “Drawing Master List” shall be submitted to the Engineer 2 days before each Site
Meeting at least.
1. When receive the revised drawings, the Design Engineer shall check the revision status.
2. If there are revised drawing , the obsolete drawings in Master Drawings shall be stamped
"Void" and separate storage.
3. When receive the revised drawings from Design Manager, the Construction Manager / Works
Manager promptly destroy the obsolete drawings after replacing them with revised ones to
assure the latest drawings are used.
4. Where the Construction Manager / Works Manager require obsolete drawings for their
retention, this may be permitted but it shall be clearly identified with the “Void” stamp.
5. The Construction Manager / Works Manager shall perform the checking at all times that
subcontractors are using latest drawing.
3.6.3.5 Control of Internal Drawings
INTERNAL DOCUMENTS
1.
2.
AAA - XXX - YY / ZZ
Type of Documents
COR = General Correspondence (Letter)
DWG = Drawing
CLC = Calculation
IND = The Engineer’s Instruction / Direction
COV = Confirmation of Verbal Instruction / Direction
DML = Document Master List
DWL = Drawing Master List
QAP = QA Programme
MSP = Method Statements
QPS = Quality Procedure
ITP = Inspection and Test Plan
TCR = Test Certificate Report
CLC = Calculations
NCR = Nonconformance Report
WPS = Work Procedure
I & TP = Inspection & Test Procedure
(Stamp of document)
QA Programme – Construction of Transportation Engineering project
4.1 PURPOSE
To define a system for the identification and traceability of materials during all stages of
construction.
4.2 SCOPE
This chapter applies to the Identification and traceability of materials.
4.3 REFERENCE
Table 1 - Material Identification & traceability Requirement
4.4 RESPONSIBILITY
The Planning Manager and / or Construction Manager / Works Manager are responsible for the
identification and traceability of materials.
4.5 PROCEDURE :
1. When the Traceability is a specified requirements for specific materials, following activities
should be done by QA Manager.
2. The Inspection & Test Reports for required traceability shall include the following
informations for traceability :
3. Working daily reports and other type of construction reports are used for trace the history
and location of materials or activities.
5.1 PURPOSE
To define the system for the inspection and testing of materials / works to specify requirements and
the necessary controls to achieve and maintain the required standard.
5.2 SCOPE
This chapter applies to the Transportation Engineering project for Inspection & Test activities.
5.3 REFERENCE
chapter 4 - Material Identification and traceability
chapter 6 - Control of nonconforming Products
chapter 7 - Corrective Action.
Applicable Method statement.
5.4 RESPONSIBILITY
1. The QA Manager is responsible to ensure that materials / works are duly inspected and
tested to specified requirements, and necessary controls are taken to achieve and maintain
the required standard as per contractual specification.
2. The QC Engineer is responsible for the proper identification of inspection and test status
and ensuring that only materials that has passed the required inspection and test are
dispatched or used.
3. The QC Engineer who manage the respective inspection and test of incoming materials,
intermediary and completed works shall ensure that the following identification
requirements are met.
4. The QC Engineer holds the responsibility and authority for the release of conforming
materials / works.
5. QA Manager is responsible to prepare the ITP before start of Inspection & Test.
6. In case the work involve subcontractors, Contractor programme will be issued to the
subcontractor. Construction Manager / Works Manager will request the subcontractor to
comply with the QA programme and:
a. Subcontractor should be responsible for their own testing and inspection. Report and
findings of the inspection should be submitted to contractor for record and
monitoring purpose.
b. QA Manager will conduct a periodic check on subcontractor’s site work to ensure
that subcontractor is complying with the quality requirement.
5.5 PROCEDURE :
QA Programme – Construction of Transportation Engineering Project
The followings shall be apply to both Contractor ITP and subcontractors ITP:
1. The QA Manager shall ensure that Inspections & Tests, including those submitted by
subcontractors, are carried out in accordance with the Inspection & Test Plan [ITP].
2. The QA Manager shall ensure that all relevant contractual specifications and method
statement are clearly stated when preparing the Inspection & Test Plan.
3. All construction materials that will affect the work quality shall be performed with the
receiving inspection.
4. The Project Manager shall check the above prior to approving the Inspection & Test Plan.
Reference should be made with the Inspection & Test Plan for Works and Material.
(a). QC Engineer shall ensure that the material / supplies are inspected and tested as planned and
in accordance with the Inspection & Test Plan. He shall also ensure that the specified
records are maintained.
(b).For subcontractor, subcontractor is responsible for their own material inspection & testing.
All inspection and testing record and findings to be submitted to the contractor for record
and monitoring. QA Manager will carry out periodic check to ensure all materials of the
subcontractor are comply to standard.
a) QC Engineer shall ensure the intermediary and completed works are Inspected and
tested as planned and in accordance with the Inspection & Test Plan. He shall also
ensure that the specified records are maintained.
b) Subcontractor’s own QC will carry out their own inspection and testing
according to their own ITP. QA Manager will carry out periodic check to
ensure work quality.
b) No works shall be released until all the activities specified in the Inspection & Test
Plan for Materials and Works have been satisfactorily completed and the associated
records are available and authorized by Construction Manager and Works Manager.
1. The QA Manager / QC Engineer is responsible to review and interpret the test reports for all
materials and completed works, including those of the subcontractors.
2. The test reports shall be reviewed based on the acceptance criteria set in the Inspection &
Test Plan.
3. The QA Manager / QC Engineer shall endorse on all test reports, including those of the
subcontractors, that have been reviewed.
4. If the materials / works fail to meet the criteria, chapter 6 shall apply.
1. In the event, materials are not inspected due to urgent production purposes, the Project
Manager shall authorize the QA Manager to draw samples and the lots shall be positively
identified. The location where the materials are used shall be recordedin the Remarks
column of the “Store Record Sheet”. The samples shall be inspected at a later stage and in
the case when materials failed, the affected works shall be put on hold pending decision by
Material Review Meeting. Reference shall be made to according the chapter 6 – control of
nonconforming Product.
R. I = Receiving Inspection
QA Programme – Construction of Transportation Engineering Project
I. I = In-process Inspection
F. I = Final Inspection
The results of each stage of Inspection & Tests are identified as follows
6.1 PURPOSE
To define a control and review system to prevent the inadvertent use or release of nonconforming
materials / works and to reach a consensus on the disposition of them.
6.2 SCOPE
This chapter applies to the Transportation Engineering Project to the materials, intermediary and
final works.
6.3 REFERENCE
chapter 5 - Inspection & Testing
6.4 RESPONSIBILITY
1. The QC Engineer shall be responsible for the control of nonconforming materials / works and
preventing the inadvertent use or release of nonconforming materials / works.
2. The QA Manager that manages the respective inspection and test of materials, intermediary
and final works shall ensure that the identification, segregation and documentation of
nonconforming materials / works are properly made.
3. The Project Manager shall be responsible for decision on disposition of nonconforming
materials / works.
6.5 PROCEDURE :
6.5.1.2 Documentation
The descriptions and data of the nonconforming materials / works shall be
recorded in the “Nonconformance Report”.
6.5.1.3 Notification
Recommended corrective action will be initiated by the QA Manager and taken
by the organisation responsible for the nonconforming materials / works.
6.5.2.1 When the nature of nonconformity is beyond the decision of Project Manager, he
should open a Review Meeting. The meeting shall be delegated by the respective
organisation.
(e) Scrap
To dispose the materials which are not consumable. The members must give
accurate and practical advice. A group consensus on the disposition and
corrective action shall be reached. In the event of any dispute, the matter
shall be referred to the Project Manager.
6.5.2.4 Documentation
The "Nonconformance Report" shall be prepared by personnel who found
nonconformance. The Project Manager shall ensure that reason to justify
the group decision on the disposition to "use as it is" is documented in the
report. The nonconformance report shall be submitted to the Engineer for
approval of proposed disposition immediately.
7. CORRECTIVE ACTION
7.1 PURPOSE
To define a Corrective Action System to ensure that the root cause of nonconformance is promptly
analyzed and effective corrective actions are taken to prevent recurrence.
7.2 SCOPE
This chapter applies to all organizations.
7.3 REFERENCE :
chapter 3 - Document & Data Control
chapter 6 - Nonconforming Product Control
chapter 10 - Internal Quality Audit
7.4 PROCEDURE
7.4.1 Responsibility
1. The responsible department manager for the nonconforming product shall ensure that
root cause of nonconforming product is promptly analyzed and effective corrective
actions are taken to prevent recurrence.
2. All staff has the responsibility to identify any potential product quality problem and
initiate preventive actions to prevent its occurrence.
1. The Project Manager shall be responsible to take the appropriate action upon receipt of
complaint / feedback from the Engineer either in writing or verbal. In case of verbal
compliant from the Engineer, the “The Engineer Complaint Report” to be initiated by who
received complaint from the Engineer. Either way, the complaints shall be reported to the
responsible department manager.
2. Responsible department manager shall report to Project Manager or his related and hold the
meeting with related functional Department Manager, if required.
3. Responsible department manager shall participate jointly with other related functional
departments in identifying the root cause to the complaint and initiating corrective actions of
the problem.
QA Programme – Construction of Concrete Cable Stayed Bridge across River
Yamuna at Allahabad/Naini
4. If the root cause of the nonconformity shows that it was originated from the supplied
material, clause 4.3 of this chapter shall follow.
5. The responsible department manager shall take necessary actions promptly and ensure
that the corrective actions are effective to prevent recurrence of the problem.
6. The Project Manager or his delegate shall follow-up on the corrective action
commitment, verify the implementation.
7. The responsible department manager shall feedback to the Engineer, the corrective
action taken if requested by the Engineer.
8. Upon receipt of the Engineer positive reaction to the feedback given, the Project
Manager or his delegate shall close the case. For verbal complaint, Project Manager
or his delegate shall complete the “The Engineer Complaint Report”. For written
complaint, Project Manager or his delegate shall write back to the Engineer to report
completion of rectification works.
1. Project corrective action may be issued by any department whose function is affected by the
nonconforming product, practices or services of another Department. This shall be documented
in an “Nonconformance Report” Form in the chapter 6 (Control of nonconforming products).
2. The responsible Department for action to correct the nonconformity shall reply within one week
unless it is justifiable that more time is needed due to complexity of the problem.
Nonconformity detected during Internal Quality Audits should be recorded and closed-out by the
QA Manager.
7.4.7 The responsible Department Manager shall implement and record any change in chapter
resulting from corrective actions. This shall be carried out in accordance with the chapter 3 -
Document & Data Control.
8.1 PURPOSE
To define methods or system for handling, storage and preservation of products to prevent damage,
deterioration, or loss and final inspection and hand over of completed project.
8.2 SCOPE :
This chapter applies to Transportation Engineering Project.
8.3 REFERENCE
Applicable method statement.
8.4 RESPONSIBILITY
1. The Construction Manager / Works Manager is responsible for the proper handling and protection of
materials / works at all stages.
2. The Field Engineer is responsible to ensure material in such a way that they do not suffer damage,
deterioration or loss.
3. The Project Manager is responsible for the planing and coordination of final inspection and hand over of
the completed project to the Employer after final inspection and test.
8.5 PROCEDURE :
8.5.1 Handling
1. All operators of handling equipment, that is, excavator/crane, etc. shall be experienced in
the proper use of the equipment. Field Engineer shall ensure that workers involved in
handling and transportation activities observe the applicable method statement.
2. The following table shows the Handling Precautions (Do’s & Don’t):
QA Programme – Construction of Transportation Engineering Project
8.5.2 Storage
3. The QC Engineer shall conduct a monthly assessment of the stock condition. He shall
use the “Stock Condition Assessment Checklist / Report” to perform the assessment
The following table shows the Storage Precautions (Do’s & Don’t) :
Material / Storage
Precautions (Do’s & Don’t)
Product
Location Method
1. The Construction Manager / Works Manager or his delegate (e.g. Field Engineer, or
subcontractor) shall ensure that the completed project / works and completed works by
subcontractors are protected to ensure conformance to customer.
2. All internal areas and facilities within the building and all external areas and facilities shall
be cleaned, locked or barricaded and / or cleared of debris and prevented from
unauthorized use, damage and deterioration.
3. Additional protection measures arising from or required to meet contractual requirements
shall be observed.
4. In General
- Patch up chipped surface and touch-up using similar paint color.
- Barricade and lock up all the access to prevent unauthorized entry for internal
area.
QA Programme – Construction of Transportation Engineering Project
8.5.4 Delivery
1. The Project Manager or his delegate shall plan and coordinate the final inspection / testing of all
services and facilities by relevant authorities.
2. The Project Manager or his delegate shall assign the Engineer / QC Engineer to carry out final
defect checking with respective subcontractors. The “Punch List” shall be prepared. The Project
Manager or his delegate shall verify and carry out random check on the inspected units.
3. Punch list shall be rectified by the responsible organisation. All defects due to subcontractors
shall be rectified by the respective subcontractors.
4. The defective areas shall be re-checked by the Field Engineer and subcontractor to ensure the
defect has been rectified.
5. The QA Manager or his delegate for the Engineer’s representative to inspect the works, it shall
be done after defective areas have been rectified.
6. The Project Manager or his delegate shall prepare and compile the necessary documents such as
Warranty Certificate / Test Certificates for the Engineer.
7. Any defects found by the Engineer’s representative shall be rectified and recorded.
QA Programme – Construction of Transportation Engineering Project
9.1 PURPOSE
To define controls for the identification, collection, indexing, filing, storage, maintenance and disposition of
quality records.
9.2 SCOPE
This chapter applies to the Project.
9.3 REFERENCE
chapter 3 - Document & Data Control
9.4 RESPONSIBILITY
1. The Managers (See table 1) are responsible to provide instruction for the completion and storage
of quality records that must be kept for historical purposes. He is to ensure quality records are
legible and identifiable to the products and every alteration made on the quality record is to be
counter signed by the Originator or by his immediate Superior.
2. The Managers (See table 1) are responsible for the identification, collection, indexing, filing,
accessing storage, maintenance and disposition of quality records. Refer to Table 1 - List of
Quality Records.
9.5 PROCEDURE
9.5.1 Accessing, Storage, Maintenance and Disposition of Records (Active & Inactive)
Index of Form Description of Quality Records / Form Retention Time Location & Responsible manager of
File
Number
- QA Programme
- Quality / Work Procedure
Until finish the
- Method Statement QA
Project
- Calculation
- Test Certificate Report
10.1 PURPOSE
To define a system for the conduct of Internal Quality Audit to verify whether quality activities and
related results comply with planned arrangements and to evaluate the
effectiveness of the implementation of the Quality System.
10.2 SCOPE
This chapter applies to the Transportation Project.
10.3 REFERENCE :
Nil
10.4 DEFINITIONS
1. Audit Team Member is a person who has the qualification and is authorized to perform a
Quality System audit.
2. Audit Team Leader is a person who has the qualification and is authorized to manage a team
of Auditors.
3. Auditee is the person being audited.
10.5 RESPONSIBILITY
1. The Internal Quality Audit shall be performed by qualified auditor in Head Office. If the
Head Office Audit Team is not available for the site, the Project Manager shall appoint
Planning Manager (for QA Department) and QA Manager (for the other organization) as
Auditor. In this case, forms for audit may be used standard forms in Transportation
Engineering Project procedure (Standerd forms for QA procedure : QP-009).
2. The QA Manager
4. The Audit Team Leader shall oversee the internal quality audit activities and enforce the
implementation of outstanding corrective actions. He shall report to the Project Manager on
the findings of each auditing cycle.
5. The Audit Team Member is to carry out the instructions as layout by the Audit Team Leader.
6. The individual Department Manager responsible for the area audited shall review, agree and
correct the Audit Finding items. He shall ensure the effectiveness of the corrective actions.
QA Programme – Construction of Transportation Engineering Project
10.6 PROCEDURE :
1. The detail procedure of Internal Quality Audits shall be done in accordance with latest
version of Head office Internal quality audit procedure.
2. The Department Manager shall take action on the “Audit Finding Report” until the
recommended date in those request sheet.
3. After completion of “Audit Finding Report”, the Project Manager shall review and signed on
those report and this report sent to Head Office.
4. The QA Manager is responsible to ensure that the Quality System of the Project is
implemented and maintained.
5. All copy of reports related to the Internal Quality Audit shall kept (filing) by QA Manager
for using the back-data of Coordinate Committee Review.
QA Programme – Construction of Transportation Engineering Project
11. TRAINING
11.1 PURPOSE
To define the system for identifying the training needs and providing for the training of all personnel
performing activities affecting quality.
11.2 SCOPE
This chapter applies to the Transportation Engineering Project overseeing the training need of staff
performing activities affecting quality.
11.3 REFERENCE :
Nil
11.4 RESPONSIBILITY
1. The Project Manager is responsible for approving of yearly training schedule.
2. QA Manager is responsible for the execution of the training and maintain the training
records.
12.1 PURPOSE :
To define the system for identifying the indexing system for standard forms.
12.2 SCOPE :
This chapter applies to the Transportation Engineering Project.
12.3 REFERENCE :
QP-009 – Standard forms for QA (Quality Assurance)
12.4 RESPONSIBILITY
PNC-MX-YYY
3. Nonconformance Report
CPS-X –NCR-YY
ECR-MX-YYY
ICAR-XXX
SCAR-XXX
7. Audit Plan
AP-XX
ACAR-XX
9. Memo
TERF – X / YYY
13.1 PURPOSE
To define a system for the calibration of inspection, measuring and test equipment.
13.2 SCOPE
This chapter applies to the inspection, measuring and test equipment used by TE Project. The applicable
equipment are those listed in the "Master list of Inspection / Measuring / Test
Equipment" (see Attachment 6.1).
13.3 REFERENCE
Not Applicable
13.4 RESPONSIBILITY
The QC Engineer shall have the main responsibility to supervise and co-ordinate all calibration services
of all inspection, measuring and test equipment.
13.5 PROCEDURE :
1. The QC Engineer or his delegates shall check the new equipment prior to use to assure that each
equipment meets the specification and performance test.
2. He shall ensure that the equipment is logged in the “Master list of Inspection / Measuring / Test
Equipment” and arrange for external calibration as appropriate.
1. The QC Engineer shall ensure that the “Master list of Inspection / Measuring / Test Equipment” is
generated for review monthly (on the first week of each month) and each item on the list shall be
physically identified and traceable to the list.
2. He shall decide the frequency of calibration, review the master list for any equipment currently in use
which is due for calibration and arrange for external or internal calibration as appropriate.
The calibration standards shall be traceable to national metrology laboratories in developed industrialised
countries such as USA, UK, Australia, Japan, West Germany, India and France.
Equipment manufacturer's serial number or identification number is used for identification purposes.
Equipment that does not bear a serial number is assigned a identification number.
The calibration schedule in the “Master list of Inspection / Measuring / Test Equipment” is updated,
immediately, whenever there is a change.
QA Programme – Construction of Transportation Engineering Project
For routine measuring equipment, such as steel rulers and measuring tapes, are exempted from calibration.
1. For task identified in the QA Plan as requiring controlled measuring or test equipment, the QC Engineer
shall ensure that only properly controlled inspection or measuring equipment is used.
2. The QC Engineer shall show that all controlled equipment is in an acceptable state of calibration. All
such equipment shall be labelled, marked or engraved. Non-controlled equipment is identified by the
absence or such label, mark or engraving.
The QC Engineer shall ensure the external and internal calibration reports / certificates are reviewed. The
equipment is released to the User only if the result is in order.
The equipment are calibrated, used, handled and stored in suitable environmental condition, in accordance with
manufacturer's recommendation (if any) and where necessary in a dry, clean and cool place free from
mechanical damage, impact and shock. User shall not adjust or temper with the calibrated equipment to
invalidate the calibration settings.
The user and / or his superior shall ensure that the inspection / measuring / test
equipment used for a verification activity is suitable for the necessary accuracy and
precision.
When a measuring equipment is found to be out of calibration, the User shall report the fault to the QC
Engineer. The QC Engineer shall investigate and confirm the fault. Once the fault is confirmed, he shall stop
the measurement task.
The faulty equipment usage shall be prohibited immediately and an "Out of Service" label shall be affixed to it
by QC Engineer. He shall ensure that the faulty equipment is completely repaired / calibrated prior to further
use. He shall review the need to revise the frequency of calibration of such equipment and ensure that the
calibration is carried out on prescribed intervals.
The QC Engineer shall ensure that the following are carried out :
(b) Their parameters shall be re-validated starting from the latest by another piece of
equipment certified to be of good condition. The re-validation will stop at the
works that show satisfactory results.
(c) If necessary, a meeting shall be held amongst the QC Engineer, to discuss the
disposition of the non-conforming works.