You are on page 1of 12

TECBAR Review

Issue Spring 2011

The Newsletter of the Technology and Construction Bar Association


in association with

From the Chairman On a more somber note I was sad to hear of the passing of
His Honour Esyr Lewis QC, a former Official Referee. The next
I am delighted to announce that Informa Law & Finance has
edition of the Review will contain an obituary. A Memorial
agreed to publish and distribute the TECBAR Review. TECBAR
Service, to which all are welcome, will be held in Gray’s Inn
looks forward to this relationship and the opportunities it offers.
Chapel at 5.00pm on Wednesday 15 June. A reception will fol-
In addition to publishing the Review, Informa Law & Finance will
low in the Large Pension Room.
provide members with access to a limited number of Informa
Law CPD Podcasts each year. The next edition of the Review will
explain how TECBAR and SCL members will be able to access Chantal-Aimée Doerries QC, Chairman
these. I would also like to thank Sweet and Maxwell, the former
publisher of the TECBAR Review, for many years of support.
From the Editor
On 11 February many judges and users of the TCC gathered In this first issue of the TECBAR Review to be published by our
in the Lord Chief Justice’s Court for the valedictory of HH new partners at Informa, Mr Justice Ramsey considers claims
Judge John Toulmin C.M.G. Q.C. This was very well attended. for delay and disruption and the decision in City Inn, a case
The Lord Chief noted “it is a lovely turn-out, to pay a tribute that will unfortunately (from the perspective of construction
to a wonderful Judge and actually a lovely man … This is the lawyers, if not the parties) not now come before the Supreme
only court that would have been big enough to find a place Court, following its compromise. Steven Walker’s article
for all the many people who want to join in the tribute that addresses Part 8 claims in the context of adjudication, a topic
is going to be paid to John Toulmin … It is not merely because of considerable importance given the amount of adjudica-
it is John, but it is, in a strange way, symbolic of something tion-related actions coming before the TCC.
that has been happening over the years which those of us
who are older than some of you will remember as the old Both articles are based upon talks given at the TECBAR
Official Referees’ corridor tucked away in an out of the way Annual Conference. Correspondence on the articles as well
bit of the building unknown, unheard of, where very strange as contributions to the next edition of the Review would, as
people used to work! I did a couple of cases there myself, so always, be very welcome indeed.
I can speak with confidence. It shows a move from there by
what is now the Technology and Construction Court right into Mark Chennells, Editor
the heart of the administration of civil justice. I think, there-
fore, it is salutary to just bear that in mind when we consider
all the many wonderful things that can be said about John.”
List of Contents
We had a packed out TECBAR Annual Conference on 29
Claims for Delay & Disruption: the decision in City Inn 2
January 2011. We also held, for the first time in a number of
years, our adjudication training course in May. Thanks go to
Part 8 Claims and adjudication business 8
Lynne McCafferty for organising two such good events.

Spring 2011
TECBAR Issue Spring 2011

Claims for Delay & Disruption: the decision in City Inn


Introduction notice, particulars and estimate under clauses 25.2.1.1
1. One of the risks in contracting is delay and disruption on and 25.2.2
projects and also the way in which this is dealt with under 1.1 any of the events which are stated by the Contrac-
standard forms of contract. Claims based on either delay or tor to be the cause of the delay is a Relevant Event, and
disruption are notoriously complex and difficult to establish
both as to liability and quantum. The mechanisms adopted 1.2 the completion of the Works is likely to be delayed
by many standard forms of contract provide for the con- thereby beyond the Completion Date the Architect shall
tractor to give notices and provide particulars, and for the in writing to the Contractor give an extension of time
architect or engineer to carry out an assessment and grant by fixing such later date as the Completion Date as he
an extension of time and certify a sum to be paid. Those then estimates to be fair and reasonable.”
mechanisms often lead to disputes and, when they do, an (3) In relation to loss and expense, Clause 26 makes provi-
arbitrator or the court is faced with the task of carrying out sion for loss and expense caused to the contractor by matters
an assessment based on the factual and expert evidence materially affecting regular progress of the works. Clause 26.1
produced in an adversarial contest. is in the following terms:
2. Over the years arbitrators and the courts have attempt- “26.1 If the Contractor makes written application to the
ed to analyse the basis upon which such claims are assessed Architect stating that he has incurred or is likely to incur
but this has normally focused on the facts and arguments direct loss and/or expense in the execution of this Con-
in those particular cases and has not led to a consistent or tract for which he would not be reimbursed by a payment
well-established set of rules to be applied. under any other provision in this Contract ... because the
3. In this paper, I shall consider the extent to which any regular progress of the Works or of any part thereof has
helpful guidance can be derived from case law including the been or is likely to be materially affected by any one or
recent Scottish appeal decision in City Inn v Shepherd Con- more of the matters referred to in clause 26.2; and if and
struction [2010] CSIH 68, [2010] BLR 473, where the possible as soon as the Architect is of the opinion .... that the regu-
appeal to the Supreme Court has now been settled. lar progress of the Works or of any part thereof has been
or is likely to be so materially affected as set out in the
Claims under the Contract or for breach application of the Contractor, then the Architect from time
4. Where contracts contain express provisions for extension to time thereafter shall ascertain, .... the amount of such
of time and for payment of loss caused by delay and disrup- loss and/or expense which has been or is being incurred
tion the starting point must of course be the relevant terms by the Contractor; provided always that...”
of the contract. Where those express terms do not contain a
sufficient description of the way in which extensions of time
and loss are to be assessed and where the claims for delay 6. It can be seen from the emphasised parts of those clauses
and disruption are based on a breach of contract, resort has that they leave much to the discretion of the architect (as do
to be had to general principles of law applicable to breach, other forms of contract to the discretion of the engineer or
causation and assessment of loss. the project manager) and do not assist in defining the way
in which the assessment of extension of time or loss and
5. Examples of contractual provisions which deal with
expense is to be made.
these matters can be found in the standard forms. It is
convenient to consider the UK JCT standard form of contract 7. When there is a gap in the contractual mechanism then
considered in City Inn: the courts will look to general principles of law in an attempt
to define some rules to fill that gap and in doing so the
(1) Clause 25.2.1.1 provides the starting point for the proce- tendency is for the principles applicable to claims under the
dure to grant an extension of time as follows: contract to be elided with claims for breach of contract.
“If and whenever it becomes reasonably apparent that 8. The principles of the common law which often apply in
the progress of the Works is being or is likely to be de- such circumstances are that:
layed the Contractor shall forthwith give written notice to
(1) The breach of contract must be proved.
the Architect of the material circumstances including the
cause or causes of the delay and identify in such notice (2) A causative link between the breach and the loss must
any event which in his opinion is a Relevant Event.” be established.
(2) Clause 25.3.1 then deals with the role of the architect (3) Damages will be assessed on the basis, generally, that
and provides: the party is put in the position that they would have
“If, in the opinion of the Architect, upon receipt of any been in had the contract been performed.

2 Informa Law & Finance


Issue Spring 2011 TECBAR

Background to extension of time claims are difficulties when a claiming party fails to establish li-
9. It is worth considering two matters by way of background. ability for particular events, particular effects alleged to have
First, there is a link between extension of time and the recov- been caused by events or elements of loss which the party
ery of damages, often liquidated and ascertained damages attributes to certain causes. This is compounded by posi-
for delay. The purpose of the extension of time clause is tive assertions that there were other operative events which
therefore to relieve the contractor from liquidated damages caused effects and loss.
and also to provide the contractor with more time to carry 14. That complexity is frequently defined as being concur-
out the work. rent events or concurrent causes or concurrent delay or dis-
10. The common law, particularly in England and Wales ruption. The use of the word “concurrent” particularly in the
has generally approached the question of extensions of time context of delay has become a useful term to conceal rather
from the impact of liquidated damages. The underlying pre- than to deal with the problem.
vention principle, as set out in Holme v Guppy (1838) 3 M & Concurrent delay
W 387 is that: “if the party be prevented, by the refusal of the 15. The problem of defining concurrent delay was dealt with
other contracting party, from completing the contract within in the opinion of Lord Osborne in City Inn at [49],
the time limited, he is not liable in law for the default … It
“One of the problems in using such expressions as ‘con-
is clear, therefore, that the plaintiffs were excused from per-
current delay’ or ‘concurrent delaying events’ is that they
forming the agreement contained in the original contract...
may refer to a number of different situations. Confining
The plaintiffs were therefore left at large; and consequently
attention for a moment to concurrent delaying events,
they are not to forfeit anything for the delay.” This principle
which may be taken to mean relevant events and other
was developed in Dodd v Churton [1897] 1 QB 562 .
events, or causes of delay, which are not relevant events,
11. In Peak Construction (Liverpool) Ltd v McKinney Foun- there would seem to be several possibilities. Such events
dations Ltd [1970] 1 BLR 111, Salmon LJ said this: “If the fail- may be described as being concurrent if they occur in time
ure to complete on time is due to the fault of both the em- in a way in which they have common features. One might
ployer and the contractor, in my view, the clause does not describe events as concurrent on a strict approach only if
bite. I cannot see how, in the ordinary course, the employer they were contemporaneous or co-extensive, in the sense
can insist on compliance with a condition if it is partly his that they shared a starting point and an end point in time.
own fault that it cannot be fulfilled: Wells v Army and Navy Alternatively, events might be said to be concurrent only
Co-operative Society Ltd (1902) 86 LTR 764; Amalgamated in the sense that for some part of their duration they
Building Contractors Ltd v Waltham Holy Cross Urban District overlapped in time. Yet again, events might be said to be
Council [1952] 2 All ER 452 ; and Holme v Guppy 3 M & W 387. concurrent if they possessed a common starting point or
I consider that unless the contract expresses a contrary in- a common end point. It might also be possible to describe
tention, the employer, in the circumstances postulated, is events as concurrent in the broad sense that they both
left to his ordinary remedy; that is to say, to recover such possessed a causative influence upon some subsequent
damages as he can prove flow from the contractor’s breach. event, such as the completion of works, even though they
No doubt if the extension of time clause provided for a post- did not overlap in time. In other words, they might also
ponement of the completion date on account of delay caused be said to be contributory to or co-operative in bringing
by some breach or fault on the part of the employer, the posi- about some subsequent event. It is in this sense that the
tion would be different.” use of the term concurrent is perhaps most likely to be of
12. Secondly, there is a timing aspect to extension of time relevance in the application of clause 25.3 of the Standard
clauses. Most contracts expect extensions of time to be given Form conditions ... It appears to me that one of the prob-
soon after the relevant delaying event has occurred with a lems in the present case is that language such as that un-
review of the situation at a later date. That gives rise to der consideration here has been used in different senses
problems of timing. Generally architects and engineers have at different times. It therefore becomes important in the
been reluctant to give large prospective extensions of time interests of clarity, to try to disentangle this confusion.”
at any early stage. 16. In reality the first question is whether there is true concur-
Complexity of claims for delay and disruption rency. In City Inn Lord Drummond Young dealt with the ques-
tion as follows: “Where there is true concurrency between a
13. Those contractual provisions and the principles of law
relevant event and a contractor default, in the sense that both
to be applied can be stated and are tolerably easy to apply
existed simultaneously, regardless of which started first…”.
where there is one event which causes an obvious effect
which, in turn, can be easily assessed. The real problem is 17. In many cases the definition of concurrency falls short
that claims for delay and disruption are based on a num- of true concurrency where no cause is dominant and where
ber of events, with difficulty in establishing which event has there are two or more dominant causes of a delay. Equally
caused what and a global loss which cannot be traced to any when fully analysed the facts often do not establish true
particular cause. In the course of establishing the claim there concurrency.

e Informa Law & Finance 3


TECBAR Issue Spring 2011

18. If there is concurrency then in tort because there are occurs (no matter when), the fact that the Works would
competing causes, a claimant can recover in full under Eng- have been delayed, in any event, because of a contractor
lish law if he establishes that the cause for which the de- default remains irrelevant.”
fendant is liable caused or materially contributed to his loss. 23. The main problem is the question of overlap between de-
Any cause for which the claimant is liable will be taken into lay caused by matters for which the contractor is responsible
account under the statutory provisions for contributory negli- (“culpable delay”) and matters which may give rise to an
gence. Prior to the Law Reform (Contributory Negligence) Act extension of time (“relevant events”). It is convenient to look
1945 which allowed contribution, the position was that the at some of the cases which have dealt with this problem.
fault of the other party acted as a complete defence: But- In Balfour Beatty Building Limited v Chestermount Properties
terfield v Forrester (1809) 11 East 60 per Lord Ellenborough. Limited (1993) 62 BLR 1 Coleman J dealt with the issue of
19. In contract, the general approach to causation is to look whether the extension of time had to be based on the net or
for the effective, dominant cause. If there is no single domi- the gross period of delay. At 34 he said:
nant cause the position is unclear. The authors of Keating “In each case it is for the architect exercising his powers
on Construction Contracts (8th Edition) suggest three possible under clause 25.3.3 to decide whether an adjustment of
approaches: The approach of Devlin J in Heskell v Continental the completion date is fair and reasonable having regard
Express Ltd [1950] 1 All ER 1033 at 1048 for the loss to be to the incidence of relevant events.
recoverable if one of the causes is a breach; the approach
...
of being unable to show a dominant cause and therefore not
recovering and the approach in tort of allowing recovery if Fundamental to this exercise is an assessment of whether
the cause has caused or materially contributed to the loss. the relevant event occurring during a period of culpable
delay has caused delay to the completion of the works
Previous English decisions on principles of
and, if so, how much delay. There may well be circum-
extension of time stances where a relevant event has an impact on the prog-
20. The questions which have to be answered are: ress of the works during a period of culpable delay but
(1) Has delay been caused by a Relevant Event? where that event would have been wholly avoided had the
contractor completed the works by the previously-fixed
(2) Is completion of the Works likely to be delayed by the completion date. For example, a storm which floods the
Relevant Event beyond the Completion Date? site during a period of culpable delay and interrupts the
(3) What is a fair and reasonable extension of time? progress of the works would have been avoided altogether
21. The first two questions raise issues of causation on which if the contractor had not overrun the completion date.
the decisions appear to have concentrated, rather than on In such a case it is hard to see that it would be fair and
the third question of what is a fair and reasonable extension reasonable to postpone the completion date to extend
of time. In City Inn Lord Carloway took an interesting view of the contractor’s time. Indeed, where the relevant event
the way in which the issues should be considered when he would not be an act of prevention, it is hard to envisage
said at [103] that: any extension of time being fair and reasonable unless
the contractor was able to establish that, even if he had
“[I]t is important to note that the contract is not expressed
not been in breach of overshooting the completion date,
in a manner whereby the contractor is entitled to an ex-
the particular relevant event would still have delayed the
tension of time in the event of a Relevant Event occurring.
progress of the works at an earlier date.”
Were that to be the case, all the esoteric nuances of a
lawyer’s approach to causation, including issues such as 24. In Henry Boot Construction (UK) Limited v Malmaison Ho-
‘dominant’ or ‘operative’ causes etc, might have a more tel (Manchester) Limited (1999) 70 ConLR 32 at [13] Dyson J
prominent part to play. Rather clause 25.3.1 provides that noted with approval an agreement between the parties that:
it is in the power of the architect to form an opinion on “... if there are two concurrent causes of delay, one of
whether a matter complained of is a ‘Relevant Event’ and which is a relevant event, and the other is not, then the
whether ‘the completion of the Works is likely to be de- contractor is entitled to an extension of time for the peri-
layed thereby beyond the Completion Date’. If he does so od of delay caused by the relevant event notwithstanding
determine, then he will fix a later date ‘as he then esti- the concurrent effect of the other event.”
mates to be fair and reasonable’. On one view, the matter 25. The question was whether, in determining whether a rel-
ought to be approached as an architect would assess the evant event is likely to cause delay to the works beyond the
situation at the time and not by a judge using his percep- completion date, the architect was permitted by clause 25 to
tion of legal causation.” consider the effect of other events. At [15] Dyson J said that
22. At [110] he said: the architect could consider the effect of other events and
“But the exercise remains one of looking at the Relevant added:
Event and the effect it would have had on the original “It seems to me that it is a question of fact in any given
(or already altered) Completion Date. If a Relevant Event case whether a relevant event has caused or is likely to

4 Informa Law & Finance


Issue Spring 2011 TECBAR

cause delay to the works beyond the completion date in (3) Liquidated and ascertained damages: £30,000 per week;
the sense described by Coleman J in the Balfour Beatty
(4) The original Architect was dismissed in December 1998
case.”
and new architects appointed.
26. In Royal Brompton Hospital NHS Trust v Hammond and
others (No 7) (2001) 76 ConLR 148 Judge Seymour QC con- (5) Practical completion took place on 29 March 1999 but
sidered the circumstances in which it was proper to grant work continued until April 1999.
an extension of time under clause 25 of the Standard Form (6) In June 1999 the Architect granted a four-week exten-
conditions. He was referred to Balfour Beatty Building Ltd sion of time to 22 February 1999. This meant that Liqui-
v Chestermount Properties Ltd and Henry Boot Construction dated damages of £150,000 for the five-week period to
(UK) Ltd v Malmaison Hotel (Manchester) Ltd in relation to 29 March 1999 could be deducted and the contractor was
cases where relevant and non-relevant events operate con- entitled to four weeks of loss and expense.
currently and said at [31]:
(7) In an adjudication, the Adjudicator awarded a further
“However, it is, I think, necessary to be clear what one
extension of five weeks so that the employer had to
means by events operating concurrently. It does not
repay £150,000 and pay five weeks additional loss and
mean, in my judgment, a situation in which, work al-
expense.
ready being delayed, let it be supposed, because the
contractor has had difficulty in obtaining sufficient la- (8) In the court proceedings the employer contended that
bour, an event occurs which is a relevant event and the contractor was entitled to no extension of time be-
which, had the contractor not been delayed, would have yond 25 January 1999: any delays were concurrent with
caused him to be delayed, but which in fact by reason of contractor’s delays caused to the lifts and stair balus-
the existing delay, made no difference. In such a situa- trades. The contractor sought an extension of time of 11
tion although there is a relevant event, ‘the completion weeks up to 12 April 1999. This was based on three-and-
of the Works is [not] likely to be delayed thereby beyond a-half weeks caused by the late issue of an architect’s in-
the Completion Date’. struction varying the gas membrane in the substructure;
5 weeks (concurrent with the three-and-a-half weeks) for
The relevant event simply has no effect upon the com-
a delay caused by a late architect’s instruction varying
pletion date. This situation obviously needs to be distin-
the roof cladding and six weeks caused by late issue of
guished from a situation in which, as it were, the works
instructions following the dismissal of the original archi-
are proceeding in a regular fashion and on programme,
tects. The contractor also claimed loss and expense for
when two things happen, either of which, had it happened
11 weeks.
on its own, would have caused delay, and one is a rel-
evant event, while the other is not. In such circumstances (9) At first instance Lord Drummond Young held that there
there is a real concurrency of causes of the delay. It was were causes of delay which were relevant events and
circumstances such as these that Dyson J was concerned also delay to the lift installation and the construction of
with in the passage from his judgment in Henry Boot Con- the stair balustrades which were the fault of the contrac-
struction (UK) Ltd v Malmaison Hotel (Manchester) Ltd tor. Both caused delay to 12 April. He decided to appor-
(1999) 70 ConLR 32 at 37 at [13].” tion the delay so that he granted an extension of time
27. The Court of Appeal refused leave to appeal against the of 9 weeks to 29 March 1999. The employer was there-
decision of Judge Seymour. Sir Anthony Evans did not enter fore not entitled to liquidated damages. The contractor
upon a consideration of the proper approach as regards cau- awarded loss and expense for nine weeks. This was all
sation required by clause 25 other than to say at [11] that no as the Adjudicator had decided.
criticism was made of the judge’s approach and that both 30. The main issue of general interest considered on appeal
parties accepted that his analysis of the legal position was was whether, in circumstances of concurrency, it was appro-
entirely correct. priate for there to be an apportionment.
28. The overall conclusion of those decisions is that the
Malmaison principle applies, that is, if there are two concur- Apportionment
rent causes of delay, one of which is a relevant event, and the 31. Apportionment has not generally found favour except
other is not, then the contractor is entitled to an extension where introduced by statute. In the Law Commission working
of time for the period of delay caused by the relevant event paper on contributory negligence as a defence in contract,
notwithstanding the concurrent effect of the other event. produced in 1990, they proceeded on the basis that, broadly
The City Inn case speaking, the law did not currently permit apportionment
29. The facts of the case may be summarised as follows: where the defendant is liable only in contract. The Law Com-
mission’s provisional conclusion was that where the loss or
(1) Date for possession: 26 January 1998;
damage suffered by the claimant results partly from his own
(2) Completion Date: 25 January 1999; conduct and partly from the defendant’s breach of contract,

e Informa Law & Finance 5


TECBAR Issue Spring 2011

it is correct in principle for the damages to be apportioned. decision-maker, requires to be the cause for the delay
This has not been implemented. in the completion of the works, upon a fair and reason-
32. There have been cases where there has been an at- able view. Thus, it may not be of importance to identify
tempt to apportion liability. In the landlord and tenant case whether some delaying event or events was or was not
of Tennant Radiant Heat v Warrington Development Cor- concurrent with another, in any of the possible narrow
poration [1988] 1 EGLR 41, the tenant was responsible for senses described, but rather to consider the effect upon
one rainwater outlet and the council for the other 23 out- the completion date of relevant events and events not
lets. When a roof collapsed under the rainwater because of relevant events. For that reason, discussion of whether
blocked outlets the Court of Appeal made an apportionment or not there is true concurrency, in my opinion, does not
of the two concurrent causes one against the landlord in assist in the essential process to be followed under clause
tort and the other a claim in contract under the tenant’s 25. Having said that, however, I would endorse the view
repairing covenant. The apportionment of 90% landlord and of the Lord Ordinary that where two causes, neither of
10% tenant was made “as a matter of causation”. That case which is dominant, are under consideration, a relevant
was followed in W Lamb Ltd v J Jarvis & Sons plc (1998) 60 event and a non-relevant event, it may be appropriate for
ConLR 1 to apportion liability between a contractor and sub- the architect or decision-maker to apportion responsibility
contractor where both were equally responsible for defective for the delay between the two causes.”
work. However the principle of apportionment was criticised 36. Lord Kingarth agreed with Lord Osborne but Lord Carloway
in Bank of Nova Scotia v Hellenic Mutual Risks Association took a different view. He commented at [112] on the passage
(Bermuda) Ltd [1990] 1 QB 818 at 904 where it was said “we in the judgment of Lord Drummond Young where he said
merely add respectfully our view that the scope and extent there should be apportionment and said that it was not an
of this last mentioned case would have to be a matter of exercise warranted by any term of the contract.
substantial argument if the principle there applied were to 37. There are also problems with the practical application
arise for consideration in another case.” of the principle of apportionment. The way in which the Lord
33. It is important to distinguish between apportionment Ordinary approached the matter was similar to that under the
of the type set out above and apportionment of damages Civil Liability (Contribution) Act 1978 and was set out at [159]
which is based upon the principle that each party is liable of his judgment:
for the damage which it has caused. In the United States, for “That leads on to the question of how the exercise of ap-
instance, the Federal Court of Appeals said in Blinderman portionment is carried out. That exercise is broadly similar
Construction Inc v US 695 F2d 552 (1983) that “Where both to the apportionment of liability on account of contributo-
parties contribute to the delay neither can recover damage ry negligence or contribution among joint wrongdoers. In
unless there is in the proof a clear apportionment of the my opinion two main elements are important: the degree
delay and expense attributable to each party.” of culpability involved in each of the causes of the delay
34. It has been suggested that some support for apportion- and the significance of each of the factors in causing the
ment can be derived from the decision in Peak Construction delay. In practice culpability is likely to be the less impor-
(Liverpool) Ltd v McKinney Foundations Ltd [1970] 1 BLR 111 tant of these two factors. Nevertheless, I think that in ap-
where Salmon LJ referred to apportionment in the context of propriate cases it is important to recognize that the seri-
a claim by the main contractor for damages for delay caused ousness of the architect’s failure to issue instructions or of
by defects in the sub-contractor’s piling. The overall delay the contractor’s default may be a relevant consideration.
was 58 weeks but some of the delay had been caused by The causative significance of each of the factors is like-
the Employer’s delay in approving the remedial works. The ly to be more important. In this respect, two matters
Contractor was not liable to the Employer for liquidated dam- appear to me to be potentially important. The first of
ages because the Employer had contributed to the delay and these is the length of the delay caused by each of the
there was no provision for granting an extension of time for causative events; that will usually be a relatively straight-
that delay. On the appeal Salmon  LJ said at 119 that some forward factor. The second is the significance of each of
judges might say that the major part of the 58 week delay the causative events for the Works as a whole. Thus an
was caused by the sub-contractor’s breach; some might say event that only affects a small part of the building may
less and that “this court would not interfere, because such be of lesser importance than an event whose effects run
an apportionment is a matter on which opinions may reason- throughout the building or which has a significant effect
ably differ”. That seems to be saying that the apportionment on other operations. Ultimately, however, the question is
of the 58 weeks delay has to be made on the basis of cau- one of judgment.”
sation but does not deal with concurrent causes or general 38. In relation to loss and expense under clause 26 he re-
principles of apportionment. ferred to John Doyle v Laing Management [2004] BLR 295 at
35. In City Inn, in dismissing the appeal, Lord Osborne said: [16] to [18] where Lord Macfadyen had said this:
“the focus for consideration by the architect, or other “[16] … even if it cannot be said that events for which the

6 Informa Law & Finance


Issue Spring 2011 TECBAR

employer is responsible are the dominant cause of the “Taking all these circumstances into account, I am of
loss, it may be possible to apportion the loss between the opinion that the part of the total delay apportioned to
causes for which the employer is responsible and other Relevant Events should be substantially greater than that
causes. In such a case it is obviously necessary that the apportioned to the two items for which the defenders are
event or events for which the employer is responsible responsible. I consider that a fair and reasonable result
should be a material cause of the loss. Provided that con- would be that the defenders are entitled to an extension
dition is met, however, we are of opinion that apportion- of time of nine weeks from the original Completion Date.
ment of loss between the different causes is possible in On that basis I conclude that completion has been de-
an appropriate case. … layed beyond the completion Date by Relevant Events for
a period of nine weeks, or until 29 March 1999.”
Where the consequence is delay as against disruption,
that can be done fairly readily on the basis of the time 41. On analysis, the way in which apportionment worked
during which each of the causes was operative. During was to consider what was “fair and reasonable” and it is dif-
the period when both operated, we are of opinion that ficult to see how the concept of “apportionment” assisted in
each should normally be treated as contributing to the coming to the conclusion that the contractor was entitled to
loss, with the result that the employer is responsible for an extension of time of nine weeks until the date of Practical
only part of the delay during that period. Unless there are Completion. That result, it may be thought, could have been
special reasons to the contrary, responsibility during that achieved without using “apportionment”.
period should probably be divided on an equal basis, at Conclusion
least where the concurrent cause is not the contractor’s
42. The basis for assessing extension of time starts with a
responsibility. Where it is his responsibility, however, it
breach or event which causes delay. It is that delay which
may be appropriate to deny him any recovery for the
has to be assessed to give a “fair and reasonable” exten-
period of delay during which he is in default.
sion of time. That process is not prescribed and leaves the
[17] Apportionment in this way, on a time basis, is rela- person making the assessment of the appropriate extension
tively straightforward in cases that involve only delay. of time a wide area of discretion in which to act. Similarly
Where disruption to the contractor’s work is involved, when assessing loss there is a wide range of assessment in
matters become more complex. Nevertheless, we are of which the appropriate figure may fall. If in the end there is a
opinion that apportionment will frequently be possible in delay or a loss which is concurrent then an approach which
such cases, according to the relative importance of the moves towards apportionment based on statutory principles
various causative events in producing the loss ...” of joint liability does not seem to provide a necessary solu-
39. Lord Drummond Young said this as to John Doyle v Laing tion to the problem or one which is consistent with English
Management at [166]: law. It causes difficulties when it is laid against the principle
that in cases where there is no extension of time provision
“In that case it is recognized at paragraphs [16]–[18] that
the party cannot recover damages. The concept of a “fair
in an appropriate case where loss is caused both by
and reasonable” extension of time must be based on delay
events for which the employer is responsible and events
caused by a relevant event and complex analysis in an at-
for which the contractor is responsible it is possible to
tempt to apply apportionment may hide rather than prove
apportion the loss between the two causes. In my opinion
the true cause of delay.
that should be done in the present case. This is a case
where delay has been caused by a number of different 43. The decision in City Inn was not, on analysis, a com-
causes, most of which were the responsibility of the em- plex case and the ultimate decision on extension of time
ployer, through the architect, but two of which were the and loss does not seem to have depended on a result which
responsibility of the contractor. It is accordingly necessary required the concept of apportionment. It had been hoped
to apportion the defenders’ prolongation costs between that this important aspect might be considered by the Su-
these two categories of caused. I consider that the same preme Court under the easier route of a case on appeal from
general considerations, the causative significance of each Scotland or Northern Ireland. By settling the appeal, the par-
of the sources of delay and the degree of culpability in ties have evidently come to an sensible decision but have
respect of each of those sources, must be balanced. On left the law in an unsatisfactory state. One day a decision
this basis, I am of opinion that the result of the exercise of the TCC may be found which merits consideration by the
should be the same; I am unable to discover any reason Supreme Court so as to provide much needed guidance.
for treating the two exercises under clause 25 and clause
26 on a different basis. I accordingly conclude that the
defenders are entitled to their prolongation costs for nine
Mr Justice Ramsey
weeks.”
40. In coming to the conclusion at [161] on the exercise of
apportionment Lord Drummond Young said:

e Informa Law & Finance 7


TECBAR Issue Spring 2011

Part 8 Claims and adjudication business


1. Adjudication business has been a significant part of the 7. The circumstances where a Part 8 claim will often arise
TCC’s case load for the last decade or so and, if 2010 is any for consideration in relation to adjudication may be catego-
guide to the future, the stream of work shows little sign of rised as follows:
abating. Most of the work relates to actions for summary (i) A claim to establish or to refute the existence of a right
enforcement of adjudicator’s decisions for payment; such to adjudicate or to ascertain the terms governing any
actions are typically begun under Part 7 of the CPR1 with adjudication.
an application for directions following the procedure set out (ii) A claim alleging a breach of natural justice.
in the TCC Guide. However, there is an established steadily
(iii) A claim that seeks a final decision from the Court.
growing number of Part 8 claims being issued and decided in
the TCC which concern adjudication. (i) A claim to establish or to refute the existence of a
2. CPR 8.1(2) provides that a claimant may use the Part 8 right to adjudicate or ascertain the applicable terms
procedure where he seeks the court’s decision on a question 8. Disputes as to the contract terms or whether a contract
which is unlikely to involve a “substantial dispute of fact”. falls within the scope of the HGCRA are questions that tend
3. CPR 8.2 provides that the claimant who uses Part 8 must not to involve a “substantial dispute of fact”. Issues may
state, inter alia, the question which he wants the court to include the following3:
decide. This reflects the principal use for which the Part 8 (i) Questions of contract formation tend to be capable
procedure is used, namely the determination of questions of resolution by reference to the documents passing
of law including issues as to the proper construction of con- between the parties.
tracts. The relief sought will normally be declaratory relief,
(ii) Issues as to the nature of the works to be carried out
which is a discretionary remedy.
can be resolved by reference to the description of the
4. Part 8 does not provide for statements of case, disclo- work in the parties’ contract together with where nec-
sure or a CMC. Any evidence the claimant wishes to adduce essary some evidence to explain what the work entails.
should be provided with the Claim Form and any evidence Issues as to the principal activity undertaken on the site
from the defendant should be filed with his acknowledge- may require some evidence of fact but this is unlikely
ment of service. The Part 8 procedure is expected to be docu- to be the subject of a substantial dispute. Such disputes
ment light. As a result, the Part 8 procedure can be speedy will often be suitable for a Part 8 claim.
and relatively inexpensive but it is not suitable for determi- (iii) The question whether there is a dispute capable of giv-
nation of complex issues of fact. ing rise to an adjudication is normally one where the
Issues of fact result will be apparent from documents.
5. Most construction disputes concern issues of fact that will 9. Recent examples of cases in category (i) above include
not be capable of being tried quickly under Part 8. Forest Yuanda (UK) v WW Gear Construction4 and Banner Holdings
Heath District Council v ISG Jackson2 was such a case. An v Colchester Borough Council5. In Yuanda the claimant ob-
adjudicator had awarded Jackson an extension of time. One tained a declaration in Part 8 proceedings that an adjudica-
of his findings was that Jackson had decided to paint steel tion clause was incompatible with the HGCRA because it fet-
on site due to the late finalisation of the steelwork design (a tered the right to adjudicate. In Banner Holdings the claimant
matter for which the council was responsible). The claimant sought a declaration as to the adjudicator’s jurisdiction.
sought a declaration that the decision to paint steelwork on 10. A recent example of type (ii) above is provided by
site was not taken due to late finalisation of the steelwork North Midland Construction v AE  &  E Lentjes6. North Mid-
design. The claimant did not suggest that such a declaration land sought declarations that its works were “construction
would render the adjudicator’s decision null and void and operations” within the meaning of section 105 of the HGCRA
this was not a case where the claimant was seeking to use and did not fall within one of the exceptions described in
Part 8 to avoid enforcement. section 105(2)(c) (“the assembly, installation or demolition
6. The Court declined to grant relief because there were of plant or machinery, or erection or demolition of steelwork
issues of fact that the Court could not determine on the doc- for the purposes of supporting or providing access to plant
uments alone: see para [36]. or machinery”). Ramsey J granted the declarations sought in
relation to those issues. However, the Court declined to grant
1 Para. 9.2.1 of the TCC Guide states that if the enforcement proceed-
ings are known to raise a question which is unlikely to involve a sub- 3 See TCC Guide para. 9.4.1.
stantial dispute of fact and no monetary judgment is sought, CPR Part 8 4 [2010] EWHC 720 (TCC), [2010] BLR 435.
proceedings may be used instead. 5 [2010] EWHC 139 (TCC).
2 [2010] EWHC 322 (TCC). 6 [2009] EWHC 1371 (TCC), [2009] BLR 574.

8 Informa Law & Finance


Issue Spring 2011 TECBAR

declarations relating to responsibility for the design of the 17. In between these two extremes come the cases where
foundation earth bonding and whether the defendant had it is said the timetable was too tight for there to be a fair and
instructed a change to the works when issuing plans giving impartial determination of the issues. The use of adjudica-
details of the foundation earth bonding. These were issues tion to decide a multitude of issues, e.g. final account type
that required more detailed investigation in order for the claims, is commonplace. Many such claims are seasonal with
Court to determine them. the largest emerging bi-annually in the months of December
11. The Part 8 claim may be made before, during or after and July. The result, intended for or not, is that the Refer-
adjudication. Applications under Part 8 during an adjudication ral and the associated boxes arrive during the respondent’s
are common: see, for example, ABB Zantingh v Zedal Build- Christmas party, or just as his QS starts a summer vacation.
ing Services7; Dalkia Energy and Technical Services Ltd v Bell 18. In Enterprise Managed Services v Tony McFadden Utili-
Group UK Ltd8 and Rok Building v Bestwood Carpentry9. In the ties11, Coulson J observed that “the adjudicator has to decide
last mentioned case Akenhead J noted that the parties had at the outset whether or not he can discharge his duty to
sensibly agreed that the Court should rule on the jurisdictional reach a decision impartially and fairly within the time limits
issues before the adjudication proceeded to any conclusion. prescribed by the Act. If he cannot he ought to resign” (para
12. Where there is a genuine issue as to whether the con- [93]). In paragraph [97] Coulson J suggested the enthusiasm
tract contains an adjudication agreement or is subject to the of some adjudicators to grant piecemeal extensions and per-
provisions of the HGCRA, it will often be convenient to ask the mit “creep” in large and paper-heavy final account disputes
Court to decide the question before an adjudication is start- should be curbed. However, the Court will not readily inter-
ed. This avoids the risk that much time and money is spent vene where an adjudicator has decided that he can fairly
on what might turn out to be a futile adjudication: see the reach a decision.
comments of Coulson J in Vitpol Building Service v Samen10. 19. In Dorchester Hotel v Vivid Interiors12 the responding
(ii) A claim alleging a breach of natural justice party to a final account claim issued a Part 8 claim for decla-
rations that there was a serious risk of a breach of the rules
13. Allegations of a breach of natural justice may involve
of natural justice unless the current timetable for the adjudi-
allegations of actual or apparent bias on the part of the ad-
cation was revised to allow it more time. Whilst recognising
judicator or, more commonly, an allegation that a party (nor-
the jurisdiction to grant such relief in an ongoing adjudica-
mally the respondent) has been denied a proper opportunity
tion, the Court declined to grant the relief sought: see the
to respond to the referral, or that the adjudicator failed or
following passages in Coulson J’s judgment.
refused to consider a defence or a submission that was put
to him. It is only in a clear case that such arguments will “such a jurisdiction will be exercised very sparingly. It will
achieve the aim of avoiding enforcement. only be appropriate in rare cases for the TCC to intervene in
an ongoing adjudication. It is important that, wherever possi-
14. It might be thought that a party which perceived itself ble, the adjudication process is allowed to operate free from
to be the victim of a breach of the rules of natural justice the intervention of the court. Applications of this sort will be
should seek relief immediately before the adjudication goes very much the exception rather than the rule.” (para [18])
any further and results in potentially wasted cost, rather than
awaiting an enforcement application to pursue the complaint. “The concepts of natural justice which are so familiar to
Whether or not such a course is appropriate will depend on lawyers are not always easy to reconcile with the swift and
the complaint that is being made. summary nature of the adjudication process; and in the
event of a clash between the two, the starting point must
15. For example, in a case where apparent bias is alleged
be to give priority to the rough and ready adjudication pro-
eg, the adjudicator is a solicitor, expert or barrister who hap-
cess. It seems to me that such an approach is even more
pens to be instructed by one of the parties in relation to an-
necessary in circumstances where, as here, it may be said
other matter, the directions and decision that the adjudicator
that the breaches of natural justice have not yet occurred
makes would seem to be immaterial to the question whether
and, depending on what happens, may never in fact arise.”
the test for apparent bias is met. In such a case an applica-
tion for removal could be made promptly. 20. The Court’s reasons for rejecting the application may be
summarised as follows.
16. However, in the case where the complaint is that the (i) The adjudicator was to be accorded a wide discretion to
adjudicator failed or refused to take account of a defence, it fix the timetable so the Court would rarely intervene.
will be difficult if not impossible to prove a breach of natural
(ii) The adjudicator had a continuing duty to act fairly. The
justice before the decision is published.
Judge referred to the possibility that the adjudicator might
have to extend the timetable (see para [27] of the judg-
ment). This provided some protection to the claimant.
7 [2001] BLR 66.
8 [2009] EWHC 73 (TCC).
9 [2010] EWHC 1409 (TCC). 11 [2009] EWHC 3222 (TCC), [2010] BLR 89.
10 [2008] EWHC 2283 (TCC) at para [16]. 12 [2009] EWHC 70 (TCC), [2009] BLR 135.

e Informa Law & Finance 9


TECBAR Issue Spring 2011

(iii) The time allowed for the claimant’s response although 26. Where a dispute can be finally determined before or at
short could not be said to be incapable of permitting a the same time as the enforcement hearing that will normally
fair result. The claimant would have the last word in its be in the best interests of the parties and consistent with the
rejoinder. overriding objective: see the reasons given in Alstom Signal-
(iv) The Court could not form a view on the significance ling v Jarvis Facilities13. In the Alstom case the Adjudicator de-
of the new material identified by the claimant, or the cided that Alstom should pay approximately £1.3m to Jarvis
amended figures in the final account. based on his interpretation of the payment terms. Alstom
issued a claim for various declarations including declarations
(v) As a matter of discretion the Court also took into
to the effect that the Adjudicator was wrong to decide that
account the ability of the claimant to resist enforcement
payment was due from Alstom to Jarvis. A week later Jarvis
later on should it wish to do so.
issued a claim and an application for summary judgment.
21. The making of an application, even if unsuccessful, may The actions were listed to be heard together. The Court found
result in the adjudication timetable being revised to the ben- that the Adjudicator had erred in deciding that the sum due
efit of the applicant. The Dorchester case suggests that the to Jarvis was the sum it had applied for and that he had
scope for obtaining relief before the adjudication is complete thereby failed to decide the sum due to Alstom14.
will be limited to cases of bias and extreme irregularity in the
conduct of the adjudication. 27. Supposing that the Adjudicator’s error of law in Alstom
had not been interpreted as one which meant that he had
(iii) A claim that seeks a final decision from the failed to decide the dispute referred to him, would relief have
Court been granted then? Having regard to section 108 (3) it is
22. The parties must comply with the adjudicator’s decision submitted that the decision would have been enforced. The
until the dispute is finally determined. Section 108(3) of the Court would not have been able to finally decide the dispute
HGCRA provides: because the Court could not ascertain the amount due15. The
Court might have decided to give declarations as to the true
“The contract shall provide that the decision of the adjudi-
construction of the contract but the decision would have re-
cator is binding until the dispute is finally determined by
mained enforceable.
legal proceedings, by arbitration (if the contract provides for
arbitration or the parties otherwise agree to arbitration) or 28. In Geoffrey Osborne v Atkins Rail16 Atkins obtained
by agreement. The parties may agree to accept the decision declaratory relief to the effect that the Adjudicator’s decision
of the adjudicator as finally determining the dispute.” was in error in ordering a payment to be made to Osborne.
The dispute concerned the valuation of two items of work
23. In the absence of an applicable arbitration clause, the
and Osborne’s Notice sought an order for payment of such
Court will normally be the final arbiter of the dispute. The
sum as the Adjudicator thought fit. No issue of fact arose be-
obligation to comply with the decision of the adjudicator is
fore the Court because it was common ground that an error
not affected by the commencement of a Part 8 claim.
had been made in that the Adjudicator did not give credit for
sums paid or allowed to Osborne when arriving at his deci-
(a) Seeking a final decision to avoid enforcement
sion. The Court gave a declaration that the Adjudicator was in
24. There have been cases in which the Court has listed en-
error and declined to enforce that part of the decision.
forcement applications to be heard at the same time as Part
8 claims seeking a final decision in respect of the same dis- Continues on page 12
pute. In this way the losing party in the adjudication has
been able to avoid enforcement by getting in first and obtain-
ing a different outcome from the Court.
25. The TCC Guide provides for the possibility that 2 claims
13 [2004] EWHC 1285 (TCC) at para [20].
may be issued in respect of a single dispute. Paragraph 9.4.3
14 See para [35]. It may be debatable whether the adjudicator’s mistaken
provides as follows.
interpretation of the contract rendered his decision a nullity. In Carillion
“It sometimes happens that one party to an adjudication Construction v Devonport Royal Dockyard [2005] EWHC 778 (TCC) Jackson
commences enforcement proceedings, whilst the other
J (as he then was) noted that “In borderline cases what one judge may
commences proceedings under Part 8, in order to challenge
regard as a permissible error of law or procedure on the part of an ad-
the validity of the adjudicator’s award. This duplication of
judicator, another judge may characterise as excess of jurisdiction or a
effort is unnecessary and it involves the parties in extra
substantial breach of the rules of natural justice” (para [79]). He went
costs, especially if the two actions are commenced at dif-
on to identify five propositions (see para [81]) which the Court of Appeal
ferent court centres. Accordingly there should be sensible
expressed broad agreement with (see [2005] EWCA Civ 1358, [2006] BLR
discussions between the parties or their lawyers, in order to
15 at para [84]).
agree the appropriate venue and also to agree who shall be
claimant and who defendant. All the issues raised by each 15 See para [35] of the judgment: “Entitlement, one way or the other,

party can and should be raised in a single action.” requires further investigation”.
16 [2009] EWHC 2425, [2010] BLR 363.

10 Informa Law & Finance


Issue Spring 2011 TECBAR

Is your Construction Law library complete?


Informa Law’s construction and building law publications bring you a wide
assortment of informative books, in-depth articles and verbatim law reports,
providing you with the tools you need to stay up-to-date with the latest
developments in the construction industry.

Our Construction Law publications include:

• Building Law Reports – providing comprehensive coverage of the latest


decisions, with approved verbatim judgments that can be cited in court

• International Construction Law Review – with established and


authoritative articles, offering insightful articles, comprising quarterly issues
and an annual bound volume

• Building Law Monthly and Construction Industry Law Letter –


providing you with expert guidance on the latest legal developments,
available 10 times a year in hard copy and PDF

• Books – offering leading industry standard guides and readable analysis,


covering the entire spectrum of construction law

• Online access – all of our subscription products include online access, with
a searchable archive providing you with instant access

Visit our website for more information

www.informaprofessional.com

Special reader offer

We are offering a 15% discount to TECBAR Review


readers on all new orders placed by 31 July 2011.

Just use the promo code TECBAR01


when you check out.

All subscription products and a selection of books are available on Construction Law on i-law.
The unrivalled breadth and depth of content, complemented with practical information and impressive search
functionality provides you with a single platform for all of your research needs.

Sign up for your free demonstration and trial at:


www.i-law.com/trial
NH1339CON

NH1339CON.indd 1 12/05/2011 16:37

e Informa Law & Finance 11


TECBAR Issue Spring 2011

Continued from page 10


29. The difficult issue that arises from the decision in “I accept Mr Stansfield’s submission that a useful analo-
Osborne is that a valid decision was not enforced in circum- gy is to be found in the approach of the Court in ordering
stances where the Court could not finally decide the dispute the trial of preliminary issues. This is a case where there
which had been referred to the Adjudicator. The Court could was a dispute between the parties related to the overall
not decide the value of the two items of work (see para [25] extension of time. In such circumstances the court would
of the judgment) and therefore it could not finally decide the be unwilling, in my judgment, to order a preliminary is-
dispute which the adjudicator had decided. The BLR com- sue of the cause of the decision to paint steelwork on site
mentary suggests that the decision should be construed as a where that opened up an area of factual investigation and
final determination under Part 8 of the outstanding balance where the ultimate outcome in terms of extension of time
due to Osborne which was part of the dispute referred to would be unclear. I consider that similar considerations
the Adjudicator. It is respectfully suggested that so construed apply to the declaration sought in this case.” (para [45]).
the decision would still be at odds with section 108(3). Fur- 32. The considerations that apply in deciding whether to or-
thermore, the determination would not be “final” given that der a preliminary issue are set out in section 8 of the TCC
the Adjudicator’s value of the two items of work might be Guide. The threshold test is whether the issue meets the
later revised and this would be likely to result in an adjusted significance criteria described in paragraph 8.2.1 as follows.
balance. In Pilon v Breyer17 Coulson J distinguished Osborne
“The court would expect that any issue proposed as a
and suggested that Osborne is a case on its own particular
suitable PI would, if decided in a particular way, be ca-
facts. The fact that the parties in Osborne agreed what the
pable of:
Adjudicator’s decision was intended to mean was plainly a
significant, if not decisive, factor in the decision. • resolving the whole proceedings or a significant
element of the proceedings; or
(b) Seeking a final decision on part of a dispute post • significantly reducing the scope, and therefore the
adjudication costs, of the main trial; or
30. A claimant may seek a final declaration in relation to part
• significantly improving the possibility of a settlement of
of a dispute referred to an adjudicator. As noted above and
the whole proceedings.”
save in exceptional cases, the decision of the adjudicator
should stand by virtue of section 108(3). This is so even if 33. In a case where the adjudicator has made an error of law
one of the reasons for the decision, or one part of the deci- that undermines his conclusions in relation to a significant
sion itself, has been found to be in error by the Court. The part of the dispute Part 8 relief may offer a possible route to
decision remains enforceable pending resolution of all issues the final resolution of the dispute.
decided by the adjudicator. If, however, there is a discrete is- Other grounds on which relief may be refused
sue that is central to the decision and which the adjudicator
34. The Court may refuse to entertain a Part 8 claim where
may have wrongly decided18, a Part 8 claim offers a relatively
the contract provides that adjudication is mandatory and no
inexpensive and speedy means of obtaining a final decision
adjudication has been completed: DGT Steel v Cubitt.19
which can be used to facilitate settlement without the need
for the whole of the dispute to be litigated. 35. The existence of an arbitration agreement would pre-
clude a final determination by the Court since only the arbi-
31. In Forest Heath the Court indicated that even if it had
trator could make a final decision (assuming the defendant
been able to decide the issues of fact it would have refused
sought a stay): see Pilon v Breyer.
declaratory relief because it would not lead to a final deter-
mination of the dispute that had been referred to adjudica-
tion. Ramsey J’s judgment provides the following guidance. Steven Walker
17 [2010] EWHC 837 (TCC), [2010] BLR 452. See paras [33] and [34]. 25 March 2011
18 The Alstom v Jarvis case is a good example of the sort of issue in this
category. 19 [2007] EWHC 1584 (TCC), [2007] BLR 371.

Readers are invited to submit material by email to be considered for Correspondence should be addressed to: mchennells@atkinchambers.com
possible publication. This may consist of correspondence, short articles or Mark Chennells, TECBAR Review Editor, Atkin Chambers,
or case notes, news of forthcoming cases or events, book reviews, or 1 Atkin Building, Gray’s Inn, London, WC1R 5AT. DX 1033 Chancery Lane.
other matters of interest to members of TECBAR or SCL. Tel 020 7404 0102. Fax 020 7404 7456.
If you do not wish to receive the TECBAR Review
ISSN 1472 0078 please notify the Editor.
© Informa UK Limited and TECBAR 2011 Published by Informa UK Limited.
Editor: Mark Chennells Production Editor: Frida Fischer.

12 Informa Law & Finance

You might also like