Professional Documents
Culture Documents
ENGINEERING ECONOMY
Case Study
Case Study Teams: You can work on this case by yourself, or you can partner with another
classmate. If you work as a team, you need to submit a single report.
Deliverables: A case report should be uploaded to the MOODLE. In the report you have to cover
the following areas:
Your report should be original, and it should reflect your own efforts. Any cheating will
be graded as zero.
CASE:
A new boring machine costs 40 million Euro. For operation costs, an hourly rate of 7000 Euro is a
reasonable assumption based on 24-hour per day operation. Anatolia construction will be paid
20 thousand Euro per meter of tunnel completed. The company is expecting to have solid work
for the next 5 to 10 years, as the government is planning to expand high-speed rail network to
1
entire Turkey. However, the company has a signed contract for 2 years only, and the company
has to bid for new contracts after that.
The company already has 5 million Euro in cash, and they hope to secure a private loan of 10
million Euro from an investor. This investor is not expecting any return in the first five years.
However, he wants 15 million Euro back at the end of year 5.
Option 1.
Option 2
An adjustable rate loan. The interest is %0.4 per month for the first 5 years. The company must
pay at least the interest as a minimum monthly payment. After the fifth year, the interest
readjusts to 0.9 percent per month. The loan should be paid off within 10 years. There is no
early payment penalty. The company can pay off the outstanding balance at any time they
choose.
Option 3
An adjustable rate loan. The interest is 0.1 % per month for the first 3 years. The interest
readjusts to 1.5% per month from year 4 to 10.
Develop a financing strategy for Anatolia Engineering Company. Assume that the company can
earn 0.75 percent interest on his unused cash reserves. The company can payback any loan early
without any termination fee.
The hourly rate for the boring machine is 7000 Euro per hour. When machine remains idle, it still
cost the company 1000 Euro per hour to keep the machine operation ready. There is also
monthly fixed cost of 1 million Euro.
When developing strategies consider the cases where the machine is not operational for 24
hours.