Barricading to Sri Kurumurthy Swamy Udhaalothsavam 2017

BLD- Fixing steel barricading with MS Angle Iron Pegs and GI Pipes
CSTN17-7 with nuts & bolts duly excavating pits and its removal after the
function is over including transporting of the entire barricading
materials from the Divisional stores to the barricading site duly
engaging labour to load, transport and unload the materials at
barricading site & as per the schedule given by the
departmental authorities and loading back into the trucks,
unloading at Divisional stores, accounting for the received
materials, labour for loading, unloading, fixing, handling etc,
complete for finished item of work

a. MS Iron Angle Posts using ISA 65x65x6


mm - 1.5 M long - 329 Nos in 1000 RM
length - 3015 Kgs

b. GI Pipes of 32 mm dia Nominal Bore


medium grade 2000 RM in 1000 RM
length - 6300 Kgs

c. Nuts & Bolts - 329 posts x 4 Nos = 1316


Nos in a length of 1000 RM - 130 Kgs
Total Barricading Weight - Appx 9445 Kgs
(if departmental material is used no
hire charges shall be calculated)
LABOUR Charges
Loading and unloading
a. for materials loading & carriage to
work spot
1 Day ( 8 Hrs) - Men Mazdoor 16
Numbers
1 Night - (2 Days - 16 Hrs) 16 + 16
Numbers

b. for removal, unloading & return to


stores back Total 64 No's for loading unloading and
1 Day ( 8 Hrs) - Men Mazdoor 16 dismantling
Numbers

FIXATION CHARGES
c. for fixing the barricading materials
1 Day ( 8 Hrs) - Men Mazdoor 16
Numbers ½ Night - (1 Day - 8 Hrs)
Total 32 Numbers day 32.00 32 No's for fixation
BLD-CSTN17-7
325 Fixing steel barricading with MS Angle Iron Pegs and GI Pipes with nuts & bolts duly excavating pits and its removal after th

A) MATERIAL REQUIREMENT a. MS Iron Angle Posts using ISA 65x65x6 mm - 1.5 M long - 329 Nos in 1000 RM length
ating pits and its removal after the function is over including transporting of the entire barricading materials from the Divisional stores to th

ong - 329 Nos in 1000 RM length - 3015 Kgs b. GI Pipes of 32 mm dia Nominal Bore medium grade 2000 RM in 1000 RM length - 630
s from the Divisional stores to the barricading site duly engaging labour to load, transport and unload the materials at barricading site & as

2000 RM in 1000 RM length - 6300 Kgs c. Nuts & Bolts - 329 posts x 4 Nos = 1316 Nos in a length of 1000 RM - 130 Kgs Tota
materials at barricading site & as per the schedule given by the departmental authorities and loading back into the trucks, unloading at Div

1000 RM - 130 Kgs Total Barricading Weight - Appx 9445 Kgs (if departmental material is used no hire charges shall be calcula
into the trucks, unloading at Divisional stores, accounting for the received materials, labour for loading, unloading, fixing, handling etc, com

d no hire charges shall be calculated) B) LABOUR CHARGES a. for materials loading & carriage to work spot 1 Day (
loading, fixing, handling etc, complete for finished item of work

ge to work spot 1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers 1 Night - (2 Days - 16 Hrs) 16 + 16 Numbers b. for remo
16 Numbers b. for removal, unloading & return to stores back 1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers Total 64
or 16 Numbers Total 64 Numbers day 64.00 c. for fixing the barricading materials 1 Day ( 8 Hrs) - Men Mazdoor 16
Day ( 8 Hrs) - Men Mazdoor 16 Numbers ½ Night - (1 Day - 8 Hrs) 16 Numbers Total 32 Numbers day 32.00 BASIC CO
mbers day 32.00 BASIC COST per 1000 RM