SHABAN BOOLKET
SHABAN
CIVIL
ENGINEERS
BOOKLET
Prepared by Consultant Civil
Engineer:
Majed A. Shaban Akree
Mobile No. for Viber and WhatsApp:
+964 770 446 1234
2
SHABAN BOOLKET
INDEX
Subject Page
1- GENERAL 5
2- STEEL 20
3- BUILDINGS 40
4- ROADS 65
5- SANITARY 100
6- CONCRETE 114
7- ESTIMATION 131
8- Electrical & 142
Mechanical
9- Miscellaneous 153
3
SHABAN BOOLKET
4
SHABAN BOOLKET
GENERAL
5
SHABAN BOOLKET
Conversions
1 mile 1.609 km
1 barrel 210 Liter
1 Inch 2.5 cm
1 kg. 2.204 lb.
1 hp 745.7 watt.
1 hector 10000 m2
1 acre 4046.86 m2
1 donam 2500 m2
1 Olk 100 m2
1 bar 1.019 kg/cm2
1 kg. 9.81 Newton
1 bar 105 Pascal
1 gallon 3.785 Liter
1 Psi 6.89 N/m2
1 Mpa 145 Psi
1 Mpa 10.197 kg/cm2
6
SHABAN BOOLKET
Densities
MATERIAL kg/m3
Concrete 2300
Asphalt Conc. 2400
Bricks 1900
Cement 1400
Clay(wet) 2080
Cement mortar 1440
Concrete 2400
(Reinforced )
Gypsum 1200
Sand 1650
Concrete Blocks 1400
Gravel 1800
Steel 7850
Wood (average) 400-700
Water 1000
Lead 11370
7
SHABAN BOOLKET
8
SHABAN BOOLKET
Rock 10 - 20
Loose rock 8 -12
Gravel & 6 –10
sand
Coarse 3-5
sand
Hard dry 2-3
clay
Clay & 1.5 - 2
sand
Fine sand 1-2
Loose clay 0.5-0.75
Filling soils 0.25- 0.50
9
SHABAN BOOLKET
Materials Tests -1
10
SHABAN BOOLKET
Materials Tests – 2
11
SHABAN BOOLKET
Materials Tests – 3
Item Important tests
Paints Mineral content , coloring
material , oil and Resin ,
one gallon as sample
every 100 gallon .
Stinger Modulus of Rupture , % of
Tiles absorption , 6 samples for
each 5000 unit .
Concrete Nominal Internal Diameter
Pipes with tolerance of + , - 10 %
, Crushing test , absorption
one sample for each 50
units
Damp Flexibility , Heat resistant ,
proofing and Tensile resistant , one
bitumen sample for each source .
Water for % of So4 , % of salt ,
concrete Alkalinity or acidity , one
sample for each source .
12
SHABAN BOOLKET
Timber size for
FORM WORKS
Timber
Part of form work thickness or
size in mm
Sheeting’s 25 to 50
Beam& column
25 to 50
side
Beam bottom 50
50 x 100 to
Ledgers
75 x 200
50 x 100 to
Posts
75 x 200
75 x 100 to
Joists
150 x 150
50 x 100 to
Column Yoke
100 x 100
50 x 150 to
Studs and walling
150 x 150
13
SHABAN BOOLKET
Expansion joints
T = C x L x Co
T = Total expansion joint width in (mm)
C = coefficient of linear expansion
L = length of structure in mm
Co= change of temperature in centigrade.
Material C mm/mm/co
Structural steel 0.0000017
Concrete Masonry 0.0000094
14
SHABAN BOOLKET
LEVEL CHECKING
a1 b1 Level Instr.
A p B Fig : 1
d1 d2
a2 b2 Fig : 2
A B Q
d1+d2 d3
Error(e) =
( a2 - b2 ) - ( a1 - b1 ) / ( d1 + d2)
1-At Fig 1 , Put level at point P and
Take levels at A & B , read a1,b1
2-At Fig 2 , Take levels at A & B ,
while the level is at Q point, read
a2 , b2
3-Calculate e, allowable error is equal
+,- 0.5 mm per each 10 m length.
4- d1,d2,& d3 are about 25 m.l each .
5- C= 0.0675 k2
C= Leveling curvature correction
in meters
K= Leveled Distance in Kilometers
15
SHABAN BOOLKET
Piles foundations
Types of piles:
1- Timber piles , 2- Steel H-piles ,
3- Steel pipe piles , 4- Precast concrete
piles , 5- Concrete piles , 6- Composite
piles of different materials .
Main Purpose of using Piles:
1- High Structural Load compression or
uplift pressure.
2- Weak Bearing of upper layer of soil .
3- High Lateral Pressure .
For piles Load Carrying Capacity (Q)
Q = Q1 + 2 * π * r * f * D
where :
Q1 = Base Resistance in Ton
r = Circular Pile Radius in Meters
f = skin Friction between Pile and soil
which vary from 500-2000 ton/m2
D = Depth of the Foundation in meters .
16
SHABAN BOOLKET
17
SHABAN BOOLKET
18
Certificate to the Authorities or owners .
SHABAN BOOLKET
19
SHABAN BOOLKET
STEEL
20
SHABAN BOOLKET
21
SHABAN BOOLKET
22
SHABAN BOOLKET
BRC Reinforcing
Bar
Gage Dia. Section Net weight
61 7.62 2.99 4.69
62 7.01 2.53 3.97
63 6.4 2.11 3.31
64 5.89 1.79 2.8
65 5.38 1.49 2.34
66 4.88 1.23 1.92
67 3.25 0.54 0.86
1- All bars spacing are 15.2X15.2 cm
2-Normally BRC nets are of 2X6 m
diameter.
3- Bar Dia. In mm, section is steel
bars cross section is in cm2 per
meter length.
4 - weight of the Net is in kg / m2.
23
SHABAN BOOLKET
NOTES:
1- All weights in kg / m2
1- 2 - 1 / 24 inch means gage.
2- 3- mm & Inch are Thicknesses
24
SHABAN BOOLKET
Span in (cm) / 20
25
SHABAN BOOLKET
L/7
L/5 Span = L
L/4 L/5
Wall
l/4
l/3
Span = l
26
SHABAN BOOLKET
TYPICAL REINFORCEMENT
needed For ordinary works
TYPE Kg /m3
1 -Slabs and stair cases
70
(Tension loads)
2 -Beams (stirrups,
Transverse, & Shear 120
Reinforcement.)
3- Columns and
150
concrete walls.
4 -Concrete Foundations 130
5- Doors and windows
50
lintels
NOTE:
For (12- 18) cm thick slabs
assume approx. (10) kg/m2
27
SHABAN BOOLKET
28
SHABAN BOOLKET
29
SHABAN BOOLKET
30
SHABAN BOOLKET
31
Groups of steel bars area (mm2 ) Part -1
6
No 471 679 1207 1527 2281 2946 3696 4826 6108 6805
5
No. 393 566 1006 1273 1901 2455 3080 4021 5090 5671
4
32
No. 314 453 805 1018 1520 1964 2464 3217 4072 4536
SHABAN BOOLKET
3
No. 236 340 604 764 1140 1473 1848 2413 3054 3402
2
No. 157 226 402 509 760 982 1232 1609 2036 2268
1
No. 79 113 201 255 380 491 616 805 1018 1134
Dia.
mm 10 12 16 18 22 25 28 32 36 38
Groups of steel bars area (mm2 ) Part - 2
12
No. 942 1357 2413 3054 4561 5892 7392 9651 12216 13609
11
No. 864 1244 2212 2800 4181 5401 6776 8847 11198 12475
10
33
No. 785 1131 2011 2545 3801 4910 6160 8043 10180 11341
SHABAN BOOLKET
9
No. 707 1018 1810 2291 3421 4419 5544 7238 9162 10207
8
No. 628 905 1609 2036 3041 3928 4928 6434 8144 9073
7 22
No. 550 792 1408 1782 2661 3437 4312 5630 7126 7939
Dia.
mm 10 12 16 18 22 25 28 32 36 38
Groups of steel bars area (cm2 /m. length spacing) part - 1
20 3.93 5.65 10.05 12.70 19.00 24.54 30.80 40.21 50.90 56.71
cm
17.5
4.49 6.46 11.49 14.51 21.71 28.05 35.20 45.96 58.17 64.81
cm
15c 5.24 7.54 13.40 16.93 25.33 32.72 41.07 53.62 67.87 75.61
34
m
SHABAN BOOLKET
12.5
6.28 9.05 16.08 20.32 30.40 38.27 44.26 64.34 81.44 90.73
cm
10 7.85 11.31 20.17 25.40 38.00 49.09 61.60 80.43 101.8 113.4
cm
7.5
10.47 15.08 26.81 33.87 50.67 65.45 82.13 107.2 135.7 151.2
cm
Dia. 10 12 16 18 22 25 28 32 36 38
Groups of steel bars area (cm2 /m. length Spacing part – 2
40
cm 1.95 2.83 5.03 6.35 9.50 12.28 15.40 20.11 25.45 28.36
35
cm 2.23 3.23 5.74 7.26 10.86 14.03 17.60 22.98 29.09 32.41
30
cm 2.62 3.77 6.70 8.47 12.67 16.36 20.54 26.81 33.44 37.81
35
SHABAN BOOLKET
27.5
cm 2.86 4.11 7.31 9.24 13.82 17.85 22.40 29.25 37.02 41.24
25
cm 3.14 4.52 8.04 10.16 15.20 19.63 24.64 32.17 40.72 45.73
22.5
cm 3.49 5.03 8.94 11.29 16.89 21.82 27.38 35.75 45.25 50.41
dia 10 12 16 18 22 25 28 32 36 38
SHABAN BOOLKET
I-Beams Sections
Designation h b tr Kg/m
mm mm mm
IPE 100 100 55 5.7 8.10
IPE 140 140 73 6.9 12.9
IPE 200 200 100 8.5 22.4
IPE 240 240 120 9.8 29.4
IPE 300 300 150 10.7 41.4
IPE 360 360 170 12.7 56.0
IPE 400 400 180 13.5 63.6
IPE 500 500 200 16.0 90.7
36
Typical Steel Frames Sections
S H Column Girder
D
span height
H
37
S
SHABAN BOOLKET
IPE- 240
15 - 20 6–8 2 – 2.5 IPE- 300
IPE- 300
IPE- 300
20 – 30 8 – 10 2.5 – 3 IPE- 360
IPE- 360
IPE- 360
30 – 40 10 –12 2.5 – 3.5 IPE- 400
IPE- 400
SHABAN BOOLKET
Hollow
Section in Thickness Weight
H x W mm WT mm kg /ml
20 x 20 1 0.46
25 x 25 1.2 0.88
50 x 50 1.5 2.30
75 x 75 2.3 5.14
100 x 100 2.3 6.95
40 x 20 1 0.86
50 x 25 1.2 1.36
75 x 40 1.5 2.57
100 x 25 1.9 4.29
100 x 75 3.0 7.78
Note : According to ASTM
Standards A 500 Grade A & B.
38
SHABAN BOOLKET
39
SHABAN BOOLKET
3
___________
BUILDINGS
40
SHABAN BOOLKET
Buildings Requirements-1
Designing Buildings Requirements
used normally in IRAQ :
Application of Loading: IBC
Code 2006 or newest.
Concrete Structure: ACI Code
318-08 Metric version or newest.
Seismicity: IRAQI seismic Code
for buildings Code2/1997(English
version) It can be designed in
accordance to the ACI code by
applying this requirement
Wind Load: Applying 160 km/hr ,
Consider IBC code for the rest of
the regulation.
Designing Methods: Allowable
Stress Design Method for steel
structure and Ultimate Strength
Design for Concrete structures.
Reinforcement details: Should
be according to ACI Detailing
Manual, New Version.
41
SHABAN BOOLKET
Buildings Requirements-2
Steel Structure: AISC Code.
Reinforced Bars: Required
strength is 420 Mpa.(Grade 60)
Dia. Ø16 mm dia. Or more, and
350 Mpa (Grade 50) for others.
Steel Material: Strength of steel
materials used in IRAQ: apply the
criteria according to AISC Code
( A36 , A50).
Soil Investigation: soil
investigation is required for Soil
capacity, Soil layer and
Underground Water Level test
data on soil conditions of the site
Footings: Between pile-footing
and soil strengthening, pile-
footing is mostly used in IRAQ.
Structural Analysis Software:
ETABS and STAAD programs are
usually used in IRAQ.
42
Type Min. Min.
2
area m width
m
Living room. 9.50 2.40
Bed Room. 3.50m2 2.50
per bed
SHABAN BOOLKET
43
Kitchen. 6.00 2.00
Kitchen + dining. 10.00 2.50
Bath room. 1.80 1.50
W.C. 1.10 0.80
BUILDINGS BYELAWS
Buildings Allowed
Tolerances
1- Max.
decreasing in
footing Thick for 5%
concrete casting
2- Footing
displacement or
eccentricity of 2%
footing width
3- Variations for
stairs RISE + or - 3 mm
4 - For stair
TREAD + or - 6.5 mm
5 - For Lintels,
parapets,
Horizontal 6.5 mm
grooves, etc..
6 - Variations in
column and
Walls shuttering 12.5 mm
of total length
7 -Variations for
Slabs, beams
Shuttering for 3 6.5 mm
Meters length
45
SHABAN BOOLKET
46
SHABAN BOOLKET
LINTLELS
d Surrounded wall
b L b
Lintel Concrete Lintel
Bottom
Span Beam Bearing
Reinforce
(L) m Depth(d) walls =
ment
cm (b) cm
Up - 1.2 15 3 - 8 mm 20
1. 2 -2.0 25 3 - 10 mm 25
3 – 12
2.0 -3.0 30 30
mm
NOTES :
1- Use 8 mm stirrups @ 20 cm.
2- For top bars reinforcing use 2 of 8
mm. diameter .
3-Minimum overlap = 40 bar diameter
4-Beam width is same wall width .
47
SHABAN BOOLKET
48
SHABAN BOOLKET
Slabs on walls 15 cm
Lintels 20 cm
Beams
Spans up to 3.5 m 20 cm
Spans up to 5.5 m 30 cm
Spans up to 7.5 m 40 cm
Slab or beam
D span b
49
SHABAN BOOLKET
PLASTERING
Plastering material required on
masonry , blocks walls , (2)cm
thickness , and per (100)m2 area .
TYPE M3 Mix
1-Cement
Mortar= 3.00 1:3
(Cement +Sand)
2-White Lime
(Gypsum)= 6.00 With water
(Loose powder)
3-Pointing =
(Cement+ 0.35 1:3
Sand).
4- Rendering =
(white cement 0.25 1:2
+filler)
NOTE: (220kg)of cement to be
added for 100m2 plastering if
smooth surfaces are required.
50
SHABAN BOOLKET
WALLS SMALL
FOUNDATION
wall
2T
////////////// ////////////////Ground level
T
D
d = Depth of
Plain Conc.
45 o Inclined I I p= Clear leave
D= Depth of back distance
Foundation
Plain concrete Foundations.
1:2:4 with Masonry walls For
Normal houses and buildings.
NOTES:
1- Minim d = 20 cm , OR 3P/2
minim p = 15 cm .
minim D = 60 cm
2 -Load angle projection is 45
Degree in both sides.
3- T = Building wall Thickness .
51
SHABAN BOOLKET
52
SHABAN BOOLKET
STAIRS
T
R H= Stair Height
w = Stair Width
q = Stair slope angle
W = width H = height
T = Tread R= Rise
RULES :
1- 2R + T = 584 to 610 mm
2- H / R = No. of stairs.
3- W = (T x No. of stairs )
4- Min m T = 216 mm
Max m R = 203 mm
Max m q = 42 o
Min m q = 20 o
53
SHABAN BOOLKET
Step Foundations
Z – shape reinforcing
Recommendations:
1- Continuous Foundation thickness = T
2- Minim Y = T , No. of steps not limited .
3- Minim X= 2Y but not less than 30 cm
4- Use inclined Z – shape steel
connection between the foundation
levels A & B and use the same
reinforcement type used in the
foundation Bottom Mesh .
5- Min overlap of z-shape with original
foundation reinforcement is 40
reinforcing bar diameter .
54
SHABAN BOOLKET
Typical Basement
Drainage
This for Typical Basement excavated in soil
30 cm Min . Filter
12 cm Min.
Reinforced concrete
Wall , 2500 psi min. water proofing
;;;;;;;;;;;;;;;;;;; layer.
;;;;;;;;;;;;;;;;;;;;;
;;;; Natural ;;;; Proofed Flooring
Non excavated;
;;;;;; soil ;;;;;;;;;;;;;
;;;;;;;;;;;;;;;;;;;;;;;;;;;,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, NGL
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;
Footing
Tamped Earth
Back filling
15 – 20 cm Diameter
Filter layer from Slotted pipe on hard
Coarse graded agg. Base , with slope
Or stone backfilling For draining seepage
For water draining water outside plot .
55
SHABAN BOOLKET
FORMS OPENING
TYPE DAYS
( Beams +
Lintels
+Footing ) 2
Sides.
Column
without 3
loads.
(Slabs +
Lintels +
2 X small dimension
Under.
(m) +2 days
Beams
base ).
m = meter
NOTE:
This recommendation are for
ordinary concrete works, with air
temperature above 5o C.
56
SHABAN BOOLKET
57
SHABAN BOOLKET
58
SHABAN BOOLKET
Paints
Paint type Quantity Area
Oil on plastered 30-35
surfaces and 1 gallon m2
iron.
Emulation on 20-25
1 gallon
walls and roofs. m2
Varnish on 30
1 gallon
Wood surface . m2
Bitumen for 5
10 kg
Roofs isolation . m2
Snowcem on 100
50 kg
walls. (powder ) m2
Distemper for 100
12 kg
external surface. m2
Notes :
1- The covered area is changed
according to surface smoothness.
2- Painter can cover (45-65) m2/day.
59
SHABAN BOOLKET
Column Requirements - 1
1- Columns are considered short or
small when the ratio of column
effective Length (L) to its least
lateral dimension(d) exceed (15)
Slenderness ratio SR = L / d
60
SHABAN BOOLKET
Column Requirements- 2
1- Un supported column length
should not be greater than (10)
times of the least lateral dimension
or Diameter of the cross section,
other wise it should be considered
as long column and braced for
lateral support.
2- Minim column dimension, diameter
or thickness, should not be less
than (15) cm , and maxim length to
width percentage should not
exceed 3:1 for the rectangular
cross sections.
3- Maxim steel reinforcement for a
column cross section is 8% and
minim is 1% as percentage of the
total column cross section area.
4- Minim steel bars used ½ inch, and
maxim 2 inch, for stirrups minim is ¼
inch and maxim spacing is(25) cm.
61
SHABAN BOOLKET
62
SHABAN BOOLKET
63
SHABAN BOOLKET
64
SHABAN BOOLKET
ROADS
65
SHABAN BOOLKET
GENERAL ROADS -1
1- For small blasting in rocks , (1.0)
kg of explosive materials is needed
for every (4.0) m 3 , and in huge
blasting, half of this quantity is
required.
2-Soils expand after excavation
about 25% of its original
volume , subbase 10%,sand
20%, and chalk soils 30% .
3- Max. Allowable Soluble salts in
road embankments is 10 % ,
and Max allowable organic
materials is 5 - 10 % .
One test sample required for every
3000 m 3 of soil.
4- Maximum allowable longitudinal
grade is (6-9%) for a (50km/hr)
design speed road , and (3-5%) for
a (110 km/hr) design speed .
66
SHABAN BOOLKET
GENERAL ROADS - 2
1-Standard roads lane width is
(3.7m) but not less than 5.5 m for
2 lanes , with median width from
( 1 to 4) m between lanes .
2- Roads Shoulder Minimum width
is 1.25 m and Max. 3.6 m ,
with transverse slope between 2%
and 5 % for water draining.
3-Absolute Maxm grades for
highways is 12% , and for urban
streets is 30 %
4-Required Widening width ( w )
for horizontal curves up to
Radius ( R ) = 60 m is 1.2 m ,
for R= 150 m , w = 0.9 m and
for R = 300 m , w = 0.3 m , No
(w) widening is required for more
than R = 900 m .
67
SHABAN BOOLKET
68
SHABAN BOOLKET
Airports
1- Airports are classified according to
its usage , aircraft type and Runway
code letter from ( A to F ) according
to ICAO international standards.
2- Airports are Mainly composed of
Main Runway, taxiways, aprons ,
terminal building for passengers, VIP ,
tower , cargo , and other service
buildings, communications and roads.
3-Main Runway rigid pavements typical
layers are Concrete 40 cm thickness
+ 15 cm Dry lean concrete + 35cm
stone base + 30 cm sub base ).
4-Flexibale pavement is consist of 4 cm
wearing + 6 cm Binder + 15cm MBC
Macadam base course + 50 cm stone
base + 30cm subcase).
5-Minm clear distance between runway
and any parallel taxiway is 200 m , for
safety issues .
69
SHABAN BOOLKET
Airports Classification
Airports are classified according to its
runway characteristics as below :
Type Runway Runway Max.
Length width Grade
Secondary 500-900 25 2.0%
Domestic 1250 30 1.5%
Sub-maim 1800 45 1.5%
Main 2250 45 1.5%
International 3150 & 45 & 1.25%
More 60
Airports also are classified with its
annual passenger capacity ( Mppa) , for
example 2.5 Million passenger (Arrivals
+ Departures) per year.
Notes :
1- All dimensions are in meters
2- Maximum grade is for runway
centerline profile.
3- These physical characteristics are
according to FAA standards.
70
SHABAN BOOLKET
71
SHABAN BOOLKET
Rolling 4% 5% 7%
Mountain 6% 7% 9%
NOTES:
1- Min longitudinal grade 0.5% in
snowy countries, and 0.3% at
other locations.
2- Max. Ramp grades 8 %.
3- Level longitudinal grade is
accepted in flat only where side fill
slope 1:4 or flatter .
72
SHABAN BOOLKET
73
SHABAN BOOLKET
74
SHABAN BOOLKET
Asphalt layesTolerances
75
2:3
1.0
1.5
3.0
A
B
R
SHABAN BOOLKET
76
R = Right of the road is all width of the
allocated land for constructing the road
structures and safety area on both sides ,
and it is equal to :
Right Of the Road
77
SHABAN BOOLKET
Asphalt Pavement
Deviations Part-2
B- Deviations in Stability and Flow :
1-Deviations from vMin required limit
of stability by (68 to 100)Kg for
wearing course, and ( 100 to 150) kg
for Binder course , and also deviation
from Min and Max required limits of
Flow by 7.62 mm , should be treated
by increasing the next layer by 3 cm
2-But if Deviations are more than
upper mentioned limits for stability or
flow limits by more than 7.62 mm,
should be treated according to item
(A-2 ) in part 1
3 - Any deviations more than above
limits , the complete layer should be
removed and replaced by new one
without any compensations and
according to required specifications.
78
SHABAN BOOLKET
79
SHABAN BOOLKET
ASPHALT LAYERS
GRADING
Sieve Stabilizer Binder Wearing
1.5" 100
1.0" 90-100 100
3/4" 75-91 90-100 100
1/2" 56-80 70-90 90-100
3/8" 50-74 56-80 77-93
No. 4 29-59 35-65 44-74
No. 8 19-45 23-49 28-58
No. 50 5-17 5-19 5-21
No. 200 2-8 3-10 3-10
% of
bitumen. 3.0- 5.5 3.5-6.0 4.0-6.0
Marshal >= 5 KN >=7 KN >= 8 KN
Notes:
1- Required Flow is from (2 - 4mm)
2- Required air voids (>=70%) for all
asphalt types as Typical.
3- Bitumen Grade 40/50 to used for
upper layers Binder and Wearing
4- Bitumen Grade 60/70 to used for
lower layer Stabilizer .
80
SHABAN BOOLKET
81
SHABAN BOOLKET
BRIDGES JOINTS
Total Maximum
Longitudinal Acceptable
Movement Vertical
Joint Movement
Type Between
Min. Max. Two Sides
mm mm of Joint
mm
Buried joint
under
1. continuous 5 20 0· 5
surfacing
Gap joint with
2.
poured sealant 5 12 3
Gap joint with
3. flexible 5 50 3
membrane
4. Open gap joint 5 60 3
Fully
5. cantilevered 50 - 3
toothed
speciallyplates
6.
designed joints 100 - 3
82
SHABAN BOOLKET
Asphalt Properties
Marshall Stability
5 7 8
(KN), min
Marshall Flow
(mm) 2-4 2-4 2-4
Voids in Marshall
3-6 3-5 3-5
specimen (%)
Voids in mineral
aggregate (%), 12 13 14
mm.
Immersion-
Compression
Index of
70 70 70
Retained
Strength (%),
min.
83
SHABAN BOOLKET
86
SHABAN BOOLKET
shoulders slope 4 %
Pavement slope 2 %
Each side
/////////////////////////////////////
Note :
Minim Excavation for Removing
Top-soil under pavement ,“Original sub
soil” , is (15)cm, with Minim required
CBR = 5 %.
87
SHABAN BOOLKET
88
SHABAN BOOLKET
Notes:
1- Liquid limit = (25) % as upper limit for
Materials Passing sieve No. 4 .
2- plasticity Index= (4) % as upper limit
for Materials Passing sieve No. 4 .
3- Abrasion loss is 45 % as upper limit .
4- Soaked CBR = or more than 80%
at 95% modified maxim density.
5 – All material should be crushed
with Aggregate crushing value of less
than 30 , BS 812 .
89
SHABAN BOOLKET
SUB-BASE GRADING
As % Passing
Grade Grade
Sieve A B Grade C
2.0" 100 100
1.0" 60-90 75-95 100
3/8" 30-65 40-75 50-85
No. 4 25-55 30-60 35-65
No.10 15-40 20-45 25-50
No.40 8-20 15-30 15-30
No.200 2- 8 5 - 15 5 -15
Notes:
1-Liquid limit not more than (35)
2- required plasticity Index not
more than (6).
3- Soaked CBR = or more than
60 % at 95% modified maxim
density.
90
F
F’
DB .
E’
E
C
DC , EF are
perpendicula
DE = (0.5) DB
AC = (0.5) AB
r on AB , AD ,
R
SHABAN BOOLKET
91
R=Radius, EF = DC/4, DC= (AB)2 /8R
1 –Information; points A, B and R.
2 -Draw line AB.
3- Find DC and EF, EF equation same as DC
4- Locate points (E,F,D).
5-Draw curve (A,F,D,F’ and B)
Small horizontal curve Setting
SHABAN BOOLKET
SIGHT DISTANCE
E .
A B CL
Q
R
S = 2R Arc Cos. (R - E ) / R
92
SHABAN BOOLKET
Culverts Length
Min. culvert length L is calculated
as :
L= SW + 2*SH + 4*FH
SW =sub base width
SH = shoulder width
FH = filling height on top of
The culvert slab to the
bottom of the pavement
NOTES :
1- The Culverts side slopes are
assumed 1:2 for fill.
9- Min. Culvert bed slope for suitable
flow is 0.5% and max. is 5% .
3- For low water discharges, use pipe
culverts till 1.0 meter diameter size ,
for 3.0 meter river water flow span ,
Box culverts preferable .
4- Bridges are recommended for
bigger Discharges, and rivers with
more higher spans .
93
SHABAN BOOLKET
Culverts Size
94
SHABAN BOOLKET
RETAINING WALLS
Masonry wall with plain Concrete
Footing , the section is Economical up
to (3)m (H) = Height .
H/7
.
/////////// H/3
H H/3
H/5
f H/3
D //////////// H/3
d
7 / 16 H
NOTES :
1- Min m Footings Excavation,
D = 80 cm ,
2- Min m Footing Thickness,
d = 50 cm .
3- Min m f = 20 cm .
4-Inside Wall casting Concrete can
be filled with 30 % stones.
5-Drain PVC (4)” pipes to be
inserted each 1 by 1 m .
95
SHABAN BOOLKET
D= 3WC/S
96
SHABAN BOOLKET
groove= T/4
T Crack
////////////////////////////
T=thickness
b- Expansion joint :
Isolation filter
////////////////////////////
concrete
c- Construction joint:
formed edge
with key
1st cast 2nd cast
////////////////////////////
Treated Ground
97
Internal City Roads Layers
98
Base A Thick A Thick A Thick
SHABAN BOOLKET
20 cm 30 cm 40 cm
Crushed lime
Crushed Lime Crushed lime
Stone thick
Base Stone Thick stone Thick
30 cm (2) layers
20Cm 25 cm
Binder
Binder Binder
Asphalt 6 Cm +
6 7
Wearing
Cm Cm
5 cm
SHABAN BOOLKET
99
SHABAN BOOLKET
SANITARY
100
SHABAN BOOLKET
SANITARY CONSTANTS
1- Water supply Consumption
requirements as liter /capita /day
a- For Each Person at Home as
average is about (200) L / C / D
b- For Schools (100) per Student
c- For Hospitals (400) per Bed
d- For Offices (80) per Employer
e- For hotels (500) per person
f- For Restaurants (5) per Meal
2- Recommended water supplying
pipe size for ordinary house is ½
inch , and for distributing net from
tank and ventilation pips is ¾ inch
3- Min. water velocity in pipes (0.7)
m /sec. and max. is ( 3.0 ) m /sec.
4- For sewerage flow, best design
Velocity between ( 0.4 - 0.9) m/sec ,
which provide best self-cleaning
without erosion or sedimentation.
5- Minimum Longitudinal slope for
sanitary pipes ( 4 to 6)” is (1.0) cm/
per meter length of the pipe .
101
SHABAN BOOLKET
1.0 m graded
Boulders max. size 3”
60 – 80 cm width
Slotted drain pipe
NOTE :
This typical deep filter can be used
for Both Roads and buildings
Surroundings .
102
SHABAN BOOLKET
Domestic septic
Tanks
Number of
users Length(m) x width(m)
x Depth (m) .
5 2.0x1.0x1.0
10 2.5X1.3x1.0
15 2.5x1.5x1.3
20 2.8x1.5x1.3
50 4.5x2.0x1.4
Notes:
1- Use ventilation pipe( 2.0") diameter
for the septic tank .
2- Use Manhole cover (50x50)cm.
3- A wall to be constructed for dividing
the septic tank to two parts with one
small opening on the top of wall .
4-Free board 30cm required over
depth.
103
SHABAN BOOLKET
Galvanized pipes
Normally used in water and gas
supply installations .
Pipe Pipe weight Thick-
Dia. Dia. mm kg/m.l ness
inch mm
1/ 2 12 1.26 2.76
3/4 19 1.68 2.87
1.0 25 2.50 3.37
2.0 50 5.43 3.91
2.5 65 6.49 3.65
3.0 75 8.00 3.80
4.0 100 12.00 4.50
Note :
The Tolerance is = +,- 10 % in
Pipe weight, for testing purpose
104
SHABAN BOOLKET
G. L///////////////// /////////////////////////////
------------------------------------------------------
……..
H ……..
…….. R
depression cone
R= \ 2Q / π
R= radius of depression cone in ft
Q = discharge in galloons / day
h = depression of water in well
during pumping in ( ft )
105
SHABAN BOOLKET
Types:
Ductile, Galvanized, Steel,
plastic (PVC) , high pressure pipes ,
and High Density pipes
106
SHABAN BOOLKET
Note :
1-Pipes type are Series 3 and
6 atmosphere water pressure.
1- Tolerance is = +,- 10 % in
Pipe weight for lab. Testing .
107
SHABAN BOOLKET
Typical Cesspool
sewerage Brick
Masonry
Surrounding (1m )
Gravel (15) Humus height
Cm thick
( ½ to 1” )
grading open
joint
( 30 ) cm Masonry
crushed stone layer
Notes:
1- Min. cesspool total Depth 7.0 m
2- Min cesspool Diameter clear 90 cm
3- Usage for normal houses , buildings
and industries.
108
SHABAN BOOLKET
NGL
///////////////;;;;;;;;;;;;;///////////////////////////////
;;;;;;;;;;;;; Compacted back
filing soil Min.
…… depth 50 cm
sewer .…
pipe ;;;;;;;;;;;;; surrounding
0000000 concrete 1:2:4
Min. 15 cm
lean concrete
Base 20 cm Crushed stone 10 cm
109
SHABAN BOOLKET
Weirs
H Q
Q
////////////////////////////
////////////////////////
4H
Q = 1. 84 B H 3/2
Q = discharge in m3 /sec.
B = weir width in (m)
H = height of water flow in (m)
Notes: 1 -Basin formula is
recommended for
rectangular weirs.
2 - Above formula is useful
for water, c = 0.62
and g = 9.81.
110
SHABAN BOOLKET
111
SHABAN BOOLKET
Pipe diameter :
D= 7.45 Q2 C / S
112
SHABAN BOOLKET
113
SHABAN BOOLKET
CONCRETE
114
.
SHABAN BOOLKET
SAFE LOADS
Materials Kg/cm2
Concrete. 1:1:2
320
(Cubes)
Concrete 1:2:4
210
(Cubes)
Concrete 1:3:6
110
(Cubes)
Brick work in
20
cement Mortar 1:3
Stone masonry in
15
cement mortar 1:3
Concrete Blocks
in cement Mortar 12
1:3
Note : 1- Above safe loads used for
designing Purpose, but suitable factor of
safety should be calculated.
2- Min. structural concrete strength should
not be less than about( 175 ) Kg/cm2
115
SHABAN BOOLKET
Recommended Slump
slump cm
Concrete construction
Max. Min.
Reinforce. Foundations
footings and walls 7.5 2.5
Plain footings and
sub-walls . 7.5 2.5
Beams and
reinforced slabs 10 2.5
building columns 10 2.5
Pavements and
slabs 7.5 2.5
5 2.5
Mass concrete
116
For (ONE) M3 CONCRETE
Dry
MIX Cement Gravel
sand
C/S/G C/ kg. 3 G/ M3
S/ M
1:1:2 570 0.4 0.8
SHABAN BOOLKET
117
1:2:4 300 0.45 0.9
Concrete Mix
Concrete Strength
Age % of Max m strength
3 days 40 %
7 days 65 %
14 days 90 %
28 days 99 %
Notes :
1-Maxm Air Temperature allowed
For concreting casting is in
Hot weather is 40o,Minim is
Freezing water degree, (0o c)
without any precautions. And
Maxm is 32o for the concrete mix .
2-Recommended Slump test for
plain concrete is (25 -75) mm
and for Reinforced concrete is
( 50-100) mm , depending on
structure type and location .
118
SHABAN BOOLKET
CEMENT MORTARS
Mix
(Cemen Cement
Sand m3
t+ kg
sand)
1:1 1020 0.71
1:3 510 1.05
1:5 310 1.05
119
SHABAN BOOLKET
NOTES :
1-This table for dry materials
2-This quantities per (50kg)
1- one bag cement.
3-For wet sand and gravel
2- use less water quantities.
4-Use mechanical vibrators.
121
SHABAN BOOLKET
Flooring Expansion
Joints and Reinforcing
Flooring
Weight Maxim
Concrete
of BRC spacing
slab
Reinfor- between 2
Thickness
cement joints
2.7
10 cm 12.5 m
kg/m2
3.8
15 cm 25 m
kg/m2
5.5
20 cm 37 m
kg/m2
Notes:
1- Normally Width of expansion joint is
between (1 – 2) cm.
2- Reinforcement to be placed at top 1/3
of the concrete slab Thickness.
3- Typical Crack control joints each 3 M.
122
SHABAN BOOLKET
Typical Concrete
Retaining Wall
20
//////////////////////////// TOP FILL
Notes :
1- This section is suitable for Maxm 4.0
m wall height .
2- Distribution steel 12 mm @ 30 cm
for all layers A , B , C , D & dowels .
3- All dimensions are in centimeters .
123
SHABAN BOOLKET
12.5 or ¾-1½
less
¾
28 to 74 ½-3 3–6
74 or
more 1½-3 6
Minimum Concrete cover:
1- For slabs & walls = 1.5 cm
2- Beams & T-beams = 2.5 cm
3- 3- foundations & columns = 4.0 cm
4-
124
SHABAN BOOLKET
Concrete Admixtures
Formulated products Usually in liquid form
Added to concrete at a dosage of less than
5% by weight of cement content to modify
and improve the properties of concrete in
the wet and/or hardened state.
Main Types of Concrete Admixtures:
ASTM C 494 ( B.S 5075 )
1-Waterproofing& Water Reducing
(Type A)
2-Retarding) Type B )
3-Accelerator (Type C )
4-Water Reducing And Retarding
(Type D )
5-Water Reducing And Accelerator
(Type E)
6-High Range Water Reducing (Type F)
7-High Range Water Reducing and
Regarding (Type G).
8-Self Compacting (Type G & F)
9-Corrosion protection.
125
SHABAN BOOLKET
Member d
Roof and floor slabs L /25
126
SHABAN BOOLKET
Concrete Grades
fc` = 0.85 ( F cu )
127
SHABAN BOOLKET
Cement Types
The ASTM has designated five types
of Portland cement :
Type Applications
General General construction
purpose (most buildings, bridges,
pavements, precast
units, etc)
Moderate Structures exposed to
sulfate soil or water containing
resistance sulfate ions
High early Rapid construction, cold
strength weather concreting
Low heat of Massive structures such
hydration (slow as dams. Now rare.
reacting)
High sulfate Structures exposed to
resistance high levels of sulfate
ions
White color Decorative (properties
similar to First Type )
128
SHABAN BOOLKET
130
SHABAN BOOLKET
ESTIMATION
131
SHABAN BOOLKET
132
SHABAN BOOLKET
AREAS
1-Sector of Circle :
q
A= (q / 360) x π R2
q = Angle in degree q
R = radius R
2- Ellipse :
A=1/4 x D x d x π
D , d = The two
diameters .
3- Parabola :
A = 2/3 x B x H H
B = base
H= Height.
A= area.
4-Tripozoidal: B
A= (L1 +L2) /2 H
L= Bases width
5- Circle :
A = π r2
r = Radius
133
SHABAN BOOLKET
VOLUMES
1-Cone ,and Pyramid.
V = 1/3 (H) (A)
V= Volume , A = Base area
H = Height
2-Frusta of Pyramid.
V= H / 3 ( A1 +A2 + A1 A2 )
A2 H
A1
3-Spherical segment:
V= ╥ h2 (r-h/3)
r = radius
h=height of segment.
╥ = 3.14 h
r
4- Ball:Volume = 4/3 ╥ r3
134
SHABAN BOOLKET
EQUATIONS
1-TEMP:
Co = 5 / 9 (F o – 32 )
C = centigrade = Fahrenheit.
3- ESTIMATION:
Concrete works V= 0.67 * (C+S +G)
Cement Mortar works = 0. 75 (C+S)
Stone Masonry Vm = 0.30( V ).
Bricks Mortar Vm = 0.23 (V )
Concrete Blocks Vm = 0.13 (V )
V =Total Volume, Vm= Mortar vol.
C,S,G = cement ,sand & gravel vol.
4- SIMPSON RULE :
135
SHABAN BOOLKET
136
SHABAN BOOLKET
137
SHABAN BOOLKET
MATERIALS NEEDED
MATERIAL No. / M 3 No. / M 2
1- Bricks
(7x11x23)cm
with 450 -
cement
mortar1:3
2- Concrete.
Blocks 73 -
(15x20x40) cm.
3- Sand bricks
(20x10x5)cm. 410 -
4- Concrete.
Blocks
(20)cm. Wall - 16
thick
5- Tiles (25 x
25)cm - 16
6- Tiles (15 x
15)cm - 45
7- Tiles (20 x
20)cm - 25
8- Tiles (30 x
30)cm - 12
138
SHABAN BOOLKET
139
SHABAN BOOLKET
140
SHABAN BOOLKET
141
SHABAN BOOLKET
8
_____________________________________
Electrical &
Mechanical
142
SHABAN BOOLKET
Water Pumps Power
Q H
P = -------- x ----------
102 q
P = Power in ( kw )
H = Head in meter ( Total )
Q = discharge in Liter/sec.
q = efficiency ( output ) factor for
piston pumps between (0.8 – 0.95)
centrifugal pumps from (0.4 – 0.75)
H= Hw + Hst .(in m)
Hw=Total suction and pushing head
Hst= Extra head losses in ( m )Due
to pipes friction and values
according to pipe diameter, length
and discharge in side it , which
calculated from special Empirical
tables.
143
SHABAN BOOLKET
Electrical Information-1
1-Required cross section for
Installation wires is :
a = ( 2 K L I ) / Vd
a is in mm2
K= 0.02 for copper , & 0.03 for
Aluminum wires , I = amperes .
L = wire length in meter
Vd= voltage drop from 3 – 5 %.
2- One KVA = 4.5 Amperes for
220-volt system generators.
3- Every 1000 current amp.
Needs 1.0 in2 bus – bar
Connection for Main Boards .
4- E= I * R
E= Volts , I = Current in Amperes
R= Resistance in Ohms
5- P= I * E OR P = I2 * R ,
P= power in watts
144
SHABAN BOOLKET
Electrical Information-2
1-All (13 ) Amp Switched Plug
Socket should be placed at height
of (40-50) cm from house floor
level , but for bath rooms and
kitchens on (120 ) cm level .
2-For (15-20) Amp. All should be
on (120) cm Height from floor.
3-All electrical installations should
be extended above false ceiling
level and then dropped directly to
the points.
4-All electrical installations levels
should be above sanitary
installations levels .
5-All electrical installations for
sockets should be connected to
house Earthing system .
145
SHABAN BOOLKET
Air conditioning
1- For Cooling: chiller used , and split
units , every 35 m3 of the room
space volume required 1 R-Ton
, which is equal to 12000 BTU
(BTU = British thermal unit )
1 R-Ton / hr cooling = 0.293 Watt
Every Kw = TON * 3. 5
2- For Heating: boiler used .
1 Ton heating = 3050 kcal / h
Every Kw = 870 kcal / h
3- Air coolers use CFM = cubic foot
per minute, 2500,3500,….
4- Pumps discharge unit m3 / hr
usually use the units of ;
1 Kw = 1.33 hp ( Normal head )
1 hp = 2. 25 – 3 m3 / hr discharge
1 hp = Horse power unit .
146
SHABAN BOOLKET
5 – 10 6000
10 - 15 8000
15 - 25 12000
32 – 40 18000
40 – 50 24000
65 - 90 34000
147
SHABAN BOOLKET
148
SHABAN BOOLKET
149
SHABAN BOOLKET
Sound Levels in dB
Source Decibel dB
Wisper 30
Rain fall 50
Conservation 60 – Normal Level
Factory 80
Jet Engine 130
150
SHABAN BOOLKET
Thermal Conductivity
__________________________________________________________
H = K*A *(T1-T2) / t
H= Thermal conductivity in watt .
K= The material thermal conductivity
A= Total cross section area of
conducting surface in m2
T1 & T2 = Outside and inside
temperatures in centigrade cº
t = Thickness of the conducting
surface in meters
Material K in Watt / m cº
Bricks 1
Concrete 2
Plastering 0.5
Glass 1
Stone 1.7
Wood 0.04 – 0.4
Polystyrene 0.05
Air 0.025
Soil 1.5
151
SHABAN BOOLKET
152
SHABAN BOOLKET
9
_____________________________________
Miscellaneous
153
SHABAN BOOLKET
154
SHABAN BOOLKET
Investigation Boreholes
The Spacing and Depth of Boreholes for
any structures may viried cosiderably in
the light of local foundation conditions and
the size and loads of the structure .
The grid of Borehles location is usually
decided by the Geologistik Engineer
according to his accumilated Experience .
And Depth is :
1- 1.5 x Foundatioin depth , below
foundation depth + one or two contrle
hole to Min. (10) m depth , unless
rock ahead found .
2- Then (3)m. below Roackhead to prove
sound rock .
3- Probes to 3 -10 m to locate rock
cavities as rough estimation.
155
SHABAN BOOLKET
156
Electronics Engineers .
SHABAN BOOLKET
A- Architectural :
1- Buildings Plot with infrastructure
services & Site Plan Drawing.
2- Foundations , Basement and all
Floors plans with penthouse
details furniture and Dimensions .
3- Two Horizontal and vertical
Sections for complete structure.
4- All required Elevations.
5- Details for Main and Emergency
Stair case and other structures .
6- 3D Views of the Buildings and
may be also animation.
7- Doors and windows Details .
8- Legend For all Parts& finishing’s.
157
9-
SHABAN BOOLKET
158
SHABAN BOOLKET
159
SHABAN BOOLKET
Engineering Design Elements-4
G- ROADS: For Roads and highway
projects below typical elements are
required for complete Design Set.
1- General Road site plan and
alignment on digitized satellite
map with kilometer stations.
2- Typical road cross section and
material layers with slopes details
3- Road alignment plan each
certain stations and profile
section with Natural ground ,
Subgrade and final road levels.
4- All road structures like culverts,
bridges , over & underpasses ,
intersections , parking ,Guard
rails, Signs …etc should be
shown on alignment and profile.
5- Complete BOQ for all cut and fill
quantities, materials used with
total lengths of culverts & Bridges
160
SHABAN BOOLKET
161
SHABAN BOOLKET
PHYSICS CONSTANTS
1- Light Velocity in Space (c) =
299,000 km/s
2- One light year = 9.5x1012 km .
3- Gravity acceleration=9.81 m/s2
4- Avogadro No.(NA)=
6.x1023 mol-1
5- Plank constant (h)=6.6x10-34 j.s
6- Gravity Constant (G)=
6.7x10-11 m2/kg2
7- Earth Radius = 6,370,000 km .
8- Average distance between
earth and sun = 1.5x108 km.
9- Sun Radius = 7x105 km .
10- Sound velocity = 343 m/s
11- Standard. Air Pressure =
100,000 Pascal OR N/m2
12- Uniform Atomic Mass Unit
( u) = 1.66x10-27 kg.
162
SHABAN BOOLKET
SOME REFFERENCES
1- Standard Hand book for civil
engineers , Merritt , 2002 .
2- Highway Design manual – State
organization of roads and bridge ,
Baghdad , Iraq , SORB-2003 .
3- A Dictionary of civil engineering,
GHOSE, Delhi , 2004 .
4- Waste water engineering,
METCALF & EDDY, 1991
5- Indian Practical civil engineers
Hand book , KHANA , 1985 .
6- Buildings Construction, Principles’ ,
and practice , Denis Walton , 1995 .
7- Iraqi Technical Specifications For
buildings, Baghdad, 1993.
8- Al - MANSOOR company practical
handbook ( IRAQ).
9- Building Materials , 2009,Jordan
10- ACI code , AASHTO 2010,etc …
163
SHABAN BOOLKET
NOTES:
1-Please Inform me for any Mistakes
modifications, suggestions or
corrections on below Addresses.
so that to be edited in next edition.
2-All information here are practical
, empirical enough for ordinary,
and collected from general
resources of civil engineering.
3-Please Note that for structures
Which may you need more and
accurate details you are strongly
advised to review basic & detailed
Civil engineering standards & not
depending on this booklet only.
E-mail : Serwang60@gmail.com
Mobile No. for Viber and WhatsApp:
+964 770 446 1234
164
SHABAN BOOLKET
Face Book : @SadaEngineering
www.sadaconsult.com
165
SHABAN BOOLKET
166
SHABAN BOOLKET
167