Professional Documents
Culture Documents
Received 12 November 2002; received in revised form 10 March 2004; accepted 10 March 2004
Abstract
This paper is aimed at emphasising the advantages of structural steel in general and composite floor construction in particular.
It is typical of engineers in developing countries, such as those in the Middle East, Gulf and Far East, to look at the cost of
materials on a one to one basis. That is to say, compare a concrete beam with a steel beam. However, often what really matter
are the overall project cost and the lifetime cost of structures. The two case studies included from United Arab Emirates (UAE)
provide some facts about advantages and economies of using the composite floor construction. Also, it shows that the initial cost
of individual material or elements of a structure is not the best way in determining the overall life-time cost of structures.
䊚 2004 Elsevier Ltd. All rights reserved.
Keywords: Composite floor; Steel decking; Case study; Steel beams; Pre-cast slabs; Post-tensioned
0950-0618/04/$ - see front matter 䊚 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.conbuildmat.2004.03.001
384 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390
Fig. 5. Mezzanine floor framing plan—built up sections and local decking are used.
structures allowing reductions in member sizes. This 5.1. Case study 1: new factory building project G174-
means lower dead load and reduction in the size of industrial building with a mezzanine floor
foundations.
c Requires minimum site storage, allows easy fixing Emirates Building Systems (EBS) are a predominant-
to the soffits, handling on site is simple and it can ly pre-engineered company. They do not use steel
easily be cut and fitted to awkward shapes. In most decking as part of a composite floor; instead they use it
circumstances there is no need for temporary prop- as a permanent shutter. One of the objectives of this
ping during the placing and curing of the concrete. study is to prove that the use of composite floor with
Therefore, all together simplifies and speeds up the RLSD will provide considerable savings to EBS in the
construction. long run.
d It can be used with lightweight or dense concrete. The project considered is a new pre-engineered fac-
Up to 4 h fire resistance with exposed soffit can be tory building in Dubai. In UAE, it is typical of such
designed. During construction it provides a safe buildings to have mezzanine floors used as offices.
working platform and cover for the site staff. These are the areas where steel deck is used as perma-
nent shuttering. Fig. 5 shows the mezzanine floor layout
with built-up beam sections. The built-up beam section
5. Case studies sizes, e.g. BU 500=250=16=10 represents a beam
with a 500 mm overall depth, 250 mm flange width,
16-mm web thickness and 10-mm flange thickness. The
Two case studies are considered to compare the two material of these fabricated built-up sections is out of
possible uses of steel decking; firstly as a composite ASTM A572 grade 50 steel w10x. The loads on the
floor and secondly as a permanent shuttering. Steel mezzanine floor are as follows:
decking, in particular locally manufactured steel decking Gridline G-Jy7-9.
(Fig. 1), are often used as permanent shuttering for Dead loads5 kNym2 and live loads7.9 kNym2
industrial, commercial, and residential structures in UAE (including 0.4 kNym2 for services).
Due to its profile and properties the locally produced Gridline J-Ly7a-9.
steel deck is generally not capable of achieving long Dead loads2.5 kNym2 and live loads2.4 kNym2
spans to enable more effective steel floor beam design. (including partitions and services).
These case studies are carried out to prove that compos- The Emirates Buildings Systems steel decking EBS
ite floor construction using steel decking, such as 45 (Fig. 1), which is used as a permanent shutter for
Richard Lees Steel Decking (RLSD) w9x (Figs. 2 and this project, is only capable of spanning approximately
3), leads to a more economical design that achieves 1 m. An alternative floor layout with same column
long clear spans. positions and floor loading can be seen in Fig. 6. BS
¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390 387
Fig. 6. Mezzanine floor framing plan—hot rolled sections and 0.9 mm Ribdeck AL Z35 are used.
5950: Part 1, Part 3 and Part 4 w11–13x were used to are involved in construction market and should be taken
design this composite floor. Corus (formerly British very seriously.
Steel) hot rolled steel beams w14x of grades S275 (pys
275 Nymm2) and S355 (pys355 Nymm2) complying 5.2. Case study 2: Children’s City-Commercial Build-
with British Standards BS 4 and BS 4848 w15,16x were ing—suspended floors
used together with the in-situ reinforced concrete slab
and 0.9-mm thick Richard Lees Ribdeck AL Z35 w9x This particular project worth nearly $20 million pro-
for this floor layout (Fig. 2). The 135-mm thick com- vided with the opportunity to compare the unit prices
posite slab (self weight of slab 2.96 kNym2) had A193 of floors using RLSD w9x with those using several
top mesh and was capable of resisting 1.5-h fire. It is locally manufactured steel decking.
clear from the floor layouts that composite slabs with Children’s City is now built in a prestigious location
RLSD option can span longer and aesthetically the at Creek Park of Dubai, UAE. This complex is a kind
ceiling would look nicer with less number of beams. of museum for children having three main buildings in
Steel beams that are designed composite with the slab red, blue and yellow. Fig. 7 shows a sketch plan layout
also enable shallower floor construction. of the complex. These buildings contain resources and
Table 3 compares the cost of the two options. Two inter-active equipment to help children learn by seeing,
main elements, which are structural steel and decking feeling and touching. Yellow building is an atrium in
prices, are compared. Tonnage of steel required, its between the other two buildings. The main aim of this
fabrication, erection and fire proofing prices are calcu- complex is to help local children learn more about the
lated on a per square meter basis. Prices of steel deck past and the present of UAE; including the way of
as per square meter added to obtain the cost of the living, importance of trade, banks and souks (market
composite floor system. Findings indicate that RLSD places), effects of the environment on people and
option uses less tonnages of steel, therefore, leading to economy, etc.
lower fabrication, erection and fire proofing costs. How- Buildings have two floor levels. Since the Children’s
ever, RLSD is almost three times more expensive than City complex was so important due to its intended
the EBS decking, however, overall the option with built- function and prestigious location then the consultant,
up beams and EBS 45 decking costs 65.6% more than Schuster Pechtold and Partners, was looking for provid-
the RLSD. option with hot rolled beams. This is a ing a strikingly different structure to become a landmark
saving due to the composite floor alone. It should also in that area. The structure was located in a park,
be kept in mind that less tonnage of steel means lower therefore the structural height had to be limited. Also,
foundation loads with further savings on foundation the building was expected to have reasonably high live
construction. Furthermore, lighter structures are also loads. Therefore, the building’s construction depth had
preferred for construction in earthquake regions. All the to be shallow with beams capable of carrying heavy
above mentioned are considerable savings for those who live loads and bridging long spans. All these require-
388 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390
Table 3
Comparison of Richard Lees Ribdeck AL Z35 and EBS 45 per square meter floor area
ments strongly suggested the use of a steel framed layout options was Westok cellular beams w17x used
building. However, engineer’s general lack of knowl- with RLSD or pre-cast slabs. However, for better com-
edge and experience in steel design and application in parison hot rolled I-beams were used for both floor
Gulf region was clearly reflected on the preliminary layout options. The alternative layout option had 0.9
design of the structure. Originally the floor layout was mm HOLORIB Z28 Richard Lees Steel Decking that
arranged as such to use local galvanized steel decking spans 2.67 m between beams giving clearer ceiling for
with in-situ concrete. 5 kNym2 live load and 6 kNym2 aesthetics and allows more space for services and
dead load plus self-weight were assumed for the struc- shallower floor construction. For this study, RLSD was
tural analysis and design. Fig. 8 shows a typical bay compared with four other locally manufactured steel
from the preliminary floor layout where local deck is decking considering the cost of structural steel material,
spanning up to 2 m. fabrication, erection, fire proofing and the cost of shear
There were several options to replace this layout, one studs and steel decking (Table 4) it is found that savings
of which was the layout using hot rolled I beams w14x between 11.5 and 15.2% can be achieved by using
and RLSD w9x as shown in Fig. 9. Among other floor RLSD option.
Fig. 9. First floor framing plan—hot rolled sections and 0.9 mm Holo-
rib Z28 are used.
Fig. 8. First floor framing plan—hot rolled sections and local decking the locally available decking material. This means that
are used.
engineers at UAE should consider the imported decking
material for composite construction. They are reluctant
6. Conclusions to do so since the purchase cost of the imported steel
deck is very high, as much as 200% higher than the
Budget rates of floor construction given in Table 2 local decking (Tables 3 and 4). However, these case
indicate that composite steel floor construction rates are studies show that the initial cost of a specific material
heavily dependent on the availability of material, expe- or method should not be such a big concern for
rienced professionals and skilled laborer. It is clear from engineers. One should always look at the overall costs
the case studies in Section 5 that when steel decking, and long-term advantages while deciding on which
such as Richard Lees Steel Decking, is used composite material and systems to use for construction in general.
with slab and beams then it could provide considerable All the costs provided in this paper relate to the floor
savings for steel framed structures. There is a lack of construction and this alone is not enough to judge the
technical details regarding the composite behavior of overall cost of a building with different floor systems.
Table 4
Comparison of Richard Lees Holorib Z28 and various local decking per square meter floor area
Before deciding on which framing system to use it is w4x West Bay and Salam Twin Towers, Doha, Qatar. British steel.
highly advisable to consider the numerous advantages British steel sections plates and commercial steels, March
1997.
mentioned in Section 2 of this paper in addition to the w5x Prebble A, A decade of export achievement. Building with
floor cost. Besides cost, it should be kept in mind that steel, Vol. 8, No. 1, Westerham Press, May 1980; pp. 21–24.
sometimes aesthetics may be equally important to the w6x UAE Interact, The official website for the Ministry of Infor-
client. All these factors should finally be balanced to mation and Culture in the UAE, http:yywww.uaeinteract.comy
achieve an acceptable design. cultureyarchitectureyasp.
w7x Gauliard JL, Plank R, Wyss U, editors. Merits of steel construc-
tion, European convention for constructional steelwork, 1998;
Acknowledgments pp. 1–24.
w8x Trebilcock P, Lawson M, Smart C, Adaptability in steel,
Gratitude is extended to Corus Middle East Dubai concepts in steel 1, British steel. British steel sections plates
(formerly British Steel Middle East Dubai), Richard and commercial steels, April 1995; pp. 1–24.
Lees Steel Decking of UK for allowing and encouraging w9x Richard Lees Steel Decking of UK Product Technical Detail
me to develop this study. Sincere thanks to the staff of Catalogue, Richard Lees Steel Decking is part of the Kvaerner
group companies, 1999.
Emirates Building Systems, Cleveland Bridge Engineer- w10x ASTM A572M-94c High strength low alloy columbium–
ing Middle East, Schuster Pechtold and Partners and vanadium structural steel.
Tuleila Heat Insulation in UAE for all the technical w11x BS 5950: Part 1: Structural use of steelwork in building. Code
support which helped greatly in building up the cost of practice for design in simple and continuous construction:
comparisons for the case studies. hot rolled sections, 1990.
w12x BS 5950: Part 3: Section 3.1: Design of composite construction.
References Code of practice for design of simple and continuous composite
beams, 1990.
w1x Todd A., Steel or concrete, the economics of commercial w13x BS 5950: Part 4: Code of practice for design of floors with
buildings, British steel structural advisory service: British steel profiled steel sheeting, 1982.
sections plates and commercial steels, February 1996. pp. 2– w14x Corus (formerly British Steel) Structural Sections to BS4: Part
15. 1 and BS 4848: Part 4. British steel sections plates and
w2x Hart A. Multi-storey buildings. In: Owens G, Knowles P, commercial steels, December 1998; pp. 2–5.
editors. 5th ed. Steel designers manual, the steel construction w15x BS 4: Part 1: Specification for hot rolled sections, 1993.
institute. Blackwell Science, 1992. p. 36 –80. w16x BS 4848: Part 4: Hot rolled structural steel sections, equal and
w3x Gray BA, Walker HB. Steel framed multi-storey buildings the unequal angles, 1986.
economics of construction in the UK, Constrado. London: w17x Westok Cellular Beams, Westok Structural Services Limited,
Grove Colour prints Limited, September 1982. p. 3 –37. England. July 1997; pp. 3–14.