You are on page 1of 8

Construction and Building Materials 18 (2004) 383–390

Economic aspects of using steel framed buildings with composite floors:


case studies from United Arab Emirates
¨ ¨ Celikag*
Murude ¸
Civil Engineering Department, Eastern Mediterranean University, Gazimagusa, T.R.N.C., Via Mersin 10, Turkey

Received 12 November 2002; received in revised form 10 March 2004; accepted 10 March 2004

Abstract

This paper is aimed at emphasising the advantages of structural steel in general and composite floor construction in particular.
It is typical of engineers in developing countries, such as those in the Middle East, Gulf and Far East, to look at the cost of
materials on a one to one basis. That is to say, compare a concrete beam with a steel beam. However, often what really matter
are the overall project cost and the lifetime cost of structures. The two case studies included from United Arab Emirates (UAE)
provide some facts about advantages and economies of using the composite floor construction. Also, it shows that the initial cost
of individual material or elements of a structure is not the best way in determining the overall life-time cost of structures.
䊚 2004 Elsevier Ltd. All rights reserved.

Keywords: Composite floor; Steel decking; Case study; Steel beams; Pre-cast slabs; Post-tensioned

1. Introduction It is a fact that steel framed buildings are not so


common in the Middle East. However, ‘Buildings’ do
During the concept design stage of projects, steel vs. not necessarily mean residential or commercial build-
concrete w1x is becoming a more frequent argument. The ings. In reality, 95% of the ‘Industrial buildings’ in UAE
steel framed buildings with composite floor construction and other Middle Eastern and Gulf countries are steel
are now very popular due to the numerous advantages framed w5x.
they provide throughout construction projects. During As we all know, customs, traditions, natural resources
the late 1980s there was a notable increase in the use and environmental factors in specific countries have a
of structural steel with composite floor construction in lot to do with the architecture of the buildings and
the United Kingdom w2,3x. The trend in the Middle East various materials and methods used for the construction.
and Far East also indicates that clients and consultants Often these factors lead to a more practical and econom-
are becoming more aware of the advantages of using ical building structure. Due to traditions in design and
structural steel with composite floor construction. One construction in the area, engineers and public alike
good example from Gulf region is the West Bay and naturally accept that steel is a must for industrial
Salam Twin Towers in Doha, Qatar w4x. These twin buildings and somehow they do not ask the question
towers were originally planned to have a reinforced ‘why’? There are many reasons why steel should be
concrete frame. However, detailed work carried out used more often for residential and commercial buildings
during the concept design stage of the project revealed too. At this stage one should admire those individuals
that a steel framed structure with a concrete shear core who continuously work hard to find answers to such
and composite floors built with steel decking would questions and make our lives better by developing new
bring considerable economies to the overall cost of the techniques, materials and methods in diverse disciplines.
project during its lifetime. The Client was convinced Nowadays, people travel a lot and, therefore they
with the results and the twin towers were built using
become multi-cultural. Ease of transportation for goods
the steel frame option.
also means that the one who has the right finance can
*Tel.: q90-392-6301159; fax: q90-392-6302869. buy anything he wants and have it delivered to any
E-mail address: murude.celikag@emu.edu.tr (M. Celikag).
¸ location. It is time for all of us to think globally in

0950-0618/04/$ - see front matter 䊚 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.conbuildmat.2004.03.001
384 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390

Table 1 commercial buildings. However, often there is fierce


Cost differentials for floor construction competition between the post-tensioned and steel com-
Floor construction options Cost US$ym2 posite steel systems, particularly for buildings requiring
long clear spans and shallow depth of construction.
Option 1 Datum
Depending on the project, often, the steel option is not
Waffle slab
Option 2 y5.3 preferred due to the need for longer procurement time.
Precast planks on in-situ beams A variety of cladding and glass systems are used to
Option 3 Same as Option 1 cover the external surfaces of buildings, as in the case
Post-tensioned of Emirates Towers and Jumairah Beach Hotel. Fabric
Option 4 42.3
Composite steel
is also a very favorable material that is generally used
to cover roof areas. However, it is used for the facade¸
of the seven-star Bur Jul Arab Hotel. Good quality
order to take more advantage of what is on offer to us marble and ceramic are used as floor and wall finishes
or for our customers. whereas stainless steel balustrades decorate the staircases
In recent years, structural steel is one of the products and balcony areas. Stainless steel truss systems also
that is being manufactured and more frequently used in appear in atriums as part of the structural system holding
developing countries. There is no doubt that it is the the glass walls. Paving stones are extensively used for
right product for many construction projects and that is gardens, garage driveways, pavements, private roads,
why it should be taken more seriously. Those who are and so on.
not familiar with structural steel, its ancillary products Table 1 details the cost differentials for a hypermarket
and the design and construction of steel framed struc- type retail development where retail area is a suspended
tures, should make an effort to learn more about its first floor with car parking at ground level below.
applications in the construction industry. Structural solutions have been investigated based on an
Two case studies were carried out in the UAE to 8.4=8.4 m grid over a total area of 36 200 m2. Cost
establish the advantages of using steel decking for differentials indicate that the pre-cast planks on in-situ
composite floor construction. Details of these case stud- beams are the most economical type of floor construc-
ies are given in Section 5 of this paper. tion followed by waffle slab and post-tensioned slab.
Therefore, option 2 was selected for the floor construc-
2. Modern building materials in the UAE and Middle tion. Composite steel appears as the most onerous
East Region solution in this particular case.
Table 2 gives the indicative rates provided by two
In previous times, building materials were simple but international contractors for different types of floor
were superbly adapted to the demands of lifestyle and construction. The building is a 15-storey tower in the
climate. Portable tents provided shelter during tribal
form of a rectangular arch. Structural solutions have
wanderings in the winter season. Summer months were
been investigated based on a 9=9 m grid over a total
spent in the date-palm plantations, where home was an
area of 4356 m2. Option 1 is the most economical floor
airy ‘arish made of palm fronds’. Arish were also
construction system offered by the Contractor 1 whilst
common in the coastal fishing, pearling and trading
Option 2 is the most economical one that is offered by
settlements. Inland more permanent houses were built
the Contractor 2. Option 2 was favorable due to the
of stone guss (mud mixture made into blocks) and were
availability of post-tensioning materials and the presence
roofed with palm trees leaves. Fossilized coral, cut in
blocks, bonded with Sarooj (a blend of Iranian red clay
and manure), or a lime mixture derived from seashells, Table 2
and plastered with chalk and water paste, was used Budget rates per square meter construction of the floor area
extensively in coastal regions. These materials have very Floor construction options Indicative rates US$ym2
low thermal conductivity and were therefore ideally
suited for the hot and humid coastal environment w6x. Contractor 1 Contractor 2
After the establishment of the UAE in 1971 there was Option 1 52.7 61.5
a rapid development in the construction industry. This Reinforced concrete flat slab
brought along the need to use modern materials and 350-mm thick
methods to be innovative and fast in construction. Option 2 53.3 53.3
Currently, UAE has some of the most interesting and Post-tensioned concrete flat slab
275-mm thick
unique structures in the world, such as, Emirates Towers,
Bur Jul Arab and Jumairah Beach Hotel. In-situ rein- Option 3 81.7 58.2
forced concrete is one of the most widely used materials Precast concrete slab with structural
topping on structural steel beams
for the construction of residential houses, industrial and
¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390 385

The case studies in Section 5 clearly presents the


reduction in the cost of steel framed buildings when
proper systems and methods are used.

3. Why structural steel?

There are few advantages of structural steel that are


widely known, such as: column free clear spans provid-
Fig. 1. EBS 45 Galvanized decking profile. ing flexible space, freedom for fixing services and more
natural lighting; short construction period due to fast
erection and the use of composite floors; lower foun-
dation costs due to excellent strength to weight ratio
w7x. Steel is a homogeneous and quality controlled
material that has additional safety. It has the ability to
accommodate exceptional loads, such as, earthquake and
explosion and it is a recyclable structural material. All
these are important advantages of steel and they help
Fig. 2. RLSD 0.9-mm thick Ribdeck AL Z35.
all parties involved in construction to achieve the best
of everything.
Architects get more freedom for expression, creativity
in design resulting in elegant simplicity, allows trans-
parency, slenderness with no limits for architectural
design.
Civil Engineers can achieve simple functional designs
with relatively low material cost over time, easy fixing
¸
for facade and other components, integration of services,
Fig. 3. RLSD 0.9-mm thick Holorib Z28. effective solutions for acoustic and thermal insulation,
efficient surface and fire protection systems, easy com-
bination with other materials.
Contractors achieve lower site costs during construc-
tion, weather independent construction due to prefabri-
cation, construction site with less noise, dust and
spillage, visible connections that enable easy checking
that provides extra safety.
Owner achieves durability, long life, calculated main-
tenance, easy future extension, modification and refur-
bishment w8x, energy efficient design.

4. Composite floor construction is the way forward

Significant developments have taken place in the


Fig. 4. Composite floor with steel decking and shear studs. structural design of multi-storey buildings in recent
years. These developments have generally been based
of a number of capable post-tensioning specialist sub- on the principles of composite construction. However,
contractors in the local market. recent studies in the UAE and other Gulf countries, such
Floor construction option 4 (Table 1) and option 3 of as Qatar, Bahrain and Saudi Arabia, had proved that
contractor 1 (Table 2) indicates that the steel option is mezzanine floors in single storey industrial buildings
continuing to be relatively more expensive than the could also benefit from composite floor construction
other options. However, the budget rates of contractor 2 using steel decking (Figs. 1–3). Some of the advantages
for option 3 (Table 2) are more competitive than that of steel floor decking w9x can be summarized as follows:
of contractor 1. These notable differences in rates can
be due to a It acts as permanent shuttering for suspended in-situ
concrete floor or roof slabs, stiffens supporting
● Contractor’s ability for speedy procurement of steel steelwork frame and acts as all or part of the tensile
from the local market. bottom reinforcement for the concrete slabs.
● Contractor’s knowledge and experience about the b In conjunction with decking system, shear studs
proper usage of steel for buildings. (Fig. 4) can enhance the performance of steel framed
386 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390

Fig. 5. Mezzanine floor framing plan—built up sections and local decking are used.

structures allowing reductions in member sizes. This 5.1. Case study 1: new factory building project G174-
means lower dead load and reduction in the size of industrial building with a mezzanine floor
foundations.
c Requires minimum site storage, allows easy fixing Emirates Building Systems (EBS) are a predominant-
to the soffits, handling on site is simple and it can ly pre-engineered company. They do not use steel
easily be cut and fitted to awkward shapes. In most decking as part of a composite floor; instead they use it
circumstances there is no need for temporary prop- as a permanent shutter. One of the objectives of this
ping during the placing and curing of the concrete. study is to prove that the use of composite floor with
Therefore, all together simplifies and speeds up the RLSD will provide considerable savings to EBS in the
construction. long run.
d It can be used with lightweight or dense concrete. The project considered is a new pre-engineered fac-
Up to 4 h fire resistance with exposed soffit can be tory building in Dubai. In UAE, it is typical of such
designed. During construction it provides a safe buildings to have mezzanine floors used as offices.
working platform and cover for the site staff. These are the areas where steel deck is used as perma-
nent shuttering. Fig. 5 shows the mezzanine floor layout
with built-up beam sections. The built-up beam section
5. Case studies sizes, e.g. BU 500=250=16=10 represents a beam
with a 500 mm overall depth, 250 mm flange width,
16-mm web thickness and 10-mm flange thickness. The
Two case studies are considered to compare the two material of these fabricated built-up sections is out of
possible uses of steel decking; firstly as a composite ASTM A572 grade 50 steel w10x. The loads on the
floor and secondly as a permanent shuttering. Steel mezzanine floor are as follows:
decking, in particular locally manufactured steel decking Gridline G-Jy7-9.
(Fig. 1), are often used as permanent shuttering for Dead loads5 kNym2 and live loads7.9 kNym2
industrial, commercial, and residential structures in UAE (including 0.4 kNym2 for services).
Due to its profile and properties the locally produced Gridline J-Ly7a-9.
steel deck is generally not capable of achieving long Dead loads2.5 kNym2 and live loads2.4 kNym2
spans to enable more effective steel floor beam design. (including partitions and services).
These case studies are carried out to prove that compos- The Emirates Buildings Systems steel decking EBS
ite floor construction using steel decking, such as 45 (Fig. 1), which is used as a permanent shutter for
Richard Lees Steel Decking (RLSD) w9x (Figs. 2 and this project, is only capable of spanning approximately
3), leads to a more economical design that achieves 1 m. An alternative floor layout with same column
long clear spans. positions and floor loading can be seen in Fig. 6. BS
¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390 387

Fig. 6. Mezzanine floor framing plan—hot rolled sections and 0.9 mm Ribdeck AL Z35 are used.

5950: Part 1, Part 3 and Part 4 w11–13x were used to are involved in construction market and should be taken
design this composite floor. Corus (formerly British very seriously.
Steel) hot rolled steel beams w14x of grades S275 (pys
275 Nymm2) and S355 (pys355 Nymm2) complying 5.2. Case study 2: Children’s City-Commercial Build-
with British Standards BS 4 and BS 4848 w15,16x were ing—suspended floors
used together with the in-situ reinforced concrete slab
and 0.9-mm thick Richard Lees Ribdeck AL Z35 w9x This particular project worth nearly $20 million pro-
for this floor layout (Fig. 2). The 135-mm thick com- vided with the opportunity to compare the unit prices
posite slab (self weight of slab 2.96 kNym2) had A193 of floors using RLSD w9x with those using several
top mesh and was capable of resisting 1.5-h fire. It is locally manufactured steel decking.
clear from the floor layouts that composite slabs with Children’s City is now built in a prestigious location
RLSD option can span longer and aesthetically the at Creek Park of Dubai, UAE. This complex is a kind
ceiling would look nicer with less number of beams. of museum for children having three main buildings in
Steel beams that are designed composite with the slab red, blue and yellow. Fig. 7 shows a sketch plan layout
also enable shallower floor construction. of the complex. These buildings contain resources and
Table 3 compares the cost of the two options. Two inter-active equipment to help children learn by seeing,
main elements, which are structural steel and decking feeling and touching. Yellow building is an atrium in
prices, are compared. Tonnage of steel required, its between the other two buildings. The main aim of this
fabrication, erection and fire proofing prices are calcu- complex is to help local children learn more about the
lated on a per square meter basis. Prices of steel deck past and the present of UAE; including the way of
as per square meter added to obtain the cost of the living, importance of trade, banks and souks (market
composite floor system. Findings indicate that RLSD places), effects of the environment on people and
option uses less tonnages of steel, therefore, leading to economy, etc.
lower fabrication, erection and fire proofing costs. How- Buildings have two floor levels. Since the Children’s
ever, RLSD is almost three times more expensive than City complex was so important due to its intended
the EBS decking, however, overall the option with built- function and prestigious location then the consultant,
up beams and EBS 45 decking costs 65.6% more than Schuster Pechtold and Partners, was looking for provid-
the RLSD. option with hot rolled beams. This is a ing a strikingly different structure to become a landmark
saving due to the composite floor alone. It should also in that area. The structure was located in a park,
be kept in mind that less tonnage of steel means lower therefore the structural height had to be limited. Also,
foundation loads with further savings on foundation the building was expected to have reasonably high live
construction. Furthermore, lighter structures are also loads. Therefore, the building’s construction depth had
preferred for construction in earthquake regions. All the to be shallow with beams capable of carrying heavy
above mentioned are considerable savings for those who live loads and bridging long spans. All these require-
388 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390

Table 3
Comparison of Richard Lees Ribdeck AL Z35 and EBS 45 per square meter floor area

Types of decking Structural steel Decking details Total cost


a b
(US$ym2)
Tonnage of Fabrication Erection Beam fire 1.0 h fire Fire rating Mesh Price
steel (US$ym2) (US$ym2) proof area proofingc (h) (US$ym2)
(tonnesym2) (m2) (US$ym2)
RLSD 0.9 mm 0.0308 29.32 6.70 209 5.08 1.5 A142 14.2 55.30
RIBDECK AL
EBS 45 0.0518 66.20 12.68 322 7.82 None A142 4.75 91.45
(0.456 mm)
a
Fabricationqsupply of materialqpainting, etc. U$ 1278ytonne for EBS option and US$ 952ytonne for Ribdeck option.
b
Erection only: US$ 244.8ytonne for prefabricated sections and US$ 217.6ytonne for hot rolled sections.
c
Fire proofing: Tuleila heat insulation—1 h fire proofing US$ 6.12ym2.

ments strongly suggested the use of a steel framed layout options was Westok cellular beams w17x used
building. However, engineer’s general lack of knowl- with RLSD or pre-cast slabs. However, for better com-
edge and experience in steel design and application in parison hot rolled I-beams were used for both floor
Gulf region was clearly reflected on the preliminary layout options. The alternative layout option had 0.9
design of the structure. Originally the floor layout was mm HOLORIB Z28 Richard Lees Steel Decking that
arranged as such to use local galvanized steel decking spans 2.67 m between beams giving clearer ceiling for
with in-situ concrete. 5 kNym2 live load and 6 kNym2 aesthetics and allows more space for services and
dead load plus self-weight were assumed for the struc- shallower floor construction. For this study, RLSD was
tural analysis and design. Fig. 8 shows a typical bay compared with four other locally manufactured steel
from the preliminary floor layout where local deck is decking considering the cost of structural steel material,
spanning up to 2 m. fabrication, erection, fire proofing and the cost of shear
There were several options to replace this layout, one studs and steel decking (Table 4) it is found that savings
of which was the layout using hot rolled I beams w14x between 11.5 and 15.2% can be achieved by using
and RLSD w9x as shown in Fig. 9. Among other floor RLSD option.

Fig. 7. Typical floor layout for Children’s City.


¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390 389

Fig. 9. First floor framing plan—hot rolled sections and 0.9 mm Holo-
rib Z28 are used.

Fig. 8. First floor framing plan—hot rolled sections and local decking the locally available decking material. This means that
are used.
engineers at UAE should consider the imported decking
material for composite construction. They are reluctant
6. Conclusions to do so since the purchase cost of the imported steel
deck is very high, as much as 200% higher than the
Budget rates of floor construction given in Table 2 local decking (Tables 3 and 4). However, these case
indicate that composite steel floor construction rates are studies show that the initial cost of a specific material
heavily dependent on the availability of material, expe- or method should not be such a big concern for
rienced professionals and skilled laborer. It is clear from engineers. One should always look at the overall costs
the case studies in Section 5 that when steel decking, and long-term advantages while deciding on which
such as Richard Lees Steel Decking, is used composite material and systems to use for construction in general.
with slab and beams then it could provide considerable All the costs provided in this paper relate to the floor
savings for steel framed structures. There is a lack of construction and this alone is not enough to judge the
technical details regarding the composite behavior of overall cost of a building with different floor systems.

Table 4
Comparison of Richard Lees Holorib Z28 and various local decking per square meter floor area

Types of decking Structural steel Decking details Total cost


a b
(US$ym2)
Tonnage of Fabrication Erection Beam fire 1.0 h fire Shear studs Mesh Price
steel (US$ym2) (US$ym2) proof area proofingc (US$ym2) (US$ym2)
2 2 2
(tonnesym ) (m ) (US$ym )
RLSD 0.9 mm HOLORIB Z28 0.129 96.49 22.83 163 3.96 2.60 A142 18.05 143.93
Tiger steel, 1.0 mm 47y180 0.149 117.56 26.37 189 4.59 4.85 A142 10.88 164.25
Tiger steel, 1.0 mm TS75 0.149 117.56 26.37 189 4.59 4.85 A142 11.7 165.07
Aseel construction, 0.9 mm 45y150 0.149 117.56 26.37 189 4.59 4.85 A142 12.5 165.87
Profiles RHF, standard profile 0.149 117.56 26.37 189 4.59 4.85 A142 7.07 160.44
0.9 mm RH 45y150
Alwahaj metal industries, 1.0 mm 0.149 117.56 26.37 189 4.59 4.85 A142 9.8 163.17
Wahajclad 45y185
a
Fabricationqsupply of materialqpainting, etc., say US$ 789ytonne for local decking and US$ 748ytonne for Holorib option.
b
Erection only: US$ 177ytonne for hot rolled sections.
c
Fire proofing: Tuleila heat insulation—1 h fire proofing US$ 6.12ym2.
390 ¸
M. Celikag / Construction and Building Materials 18 (2004) 383–390

Before deciding on which framing system to use it is w4x West Bay and Salam Twin Towers, Doha, Qatar. British steel.
highly advisable to consider the numerous advantages British steel sections plates and commercial steels, March
1997.
mentioned in Section 2 of this paper in addition to the w5x Prebble A, A decade of export achievement. Building with
floor cost. Besides cost, it should be kept in mind that steel, Vol. 8, No. 1, Westerham Press, May 1980; pp. 21–24.
sometimes aesthetics may be equally important to the w6x UAE Interact, The official website for the Ministry of Infor-
client. All these factors should finally be balanced to mation and Culture in the UAE, http:yywww.uaeinteract.comy
achieve an acceptable design. cultureyarchitectureyasp.
w7x Gauliard JL, Plank R, Wyss U, editors. Merits of steel construc-
tion, European convention for constructional steelwork, 1998;
Acknowledgments pp. 1–24.
w8x Trebilcock P, Lawson M, Smart C, Adaptability in steel,
Gratitude is extended to Corus Middle East Dubai concepts in steel 1, British steel. British steel sections plates
(formerly British Steel Middle East Dubai), Richard and commercial steels, April 1995; pp. 1–24.
Lees Steel Decking of UK for allowing and encouraging w9x Richard Lees Steel Decking of UK Product Technical Detail
me to develop this study. Sincere thanks to the staff of Catalogue, Richard Lees Steel Decking is part of the Kvaerner
group companies, 1999.
Emirates Building Systems, Cleveland Bridge Engineer- w10x ASTM A572M-94c High strength low alloy columbium–
ing Middle East, Schuster Pechtold and Partners and vanadium structural steel.
Tuleila Heat Insulation in UAE for all the technical w11x BS 5950: Part 1: Structural use of steelwork in building. Code
support which helped greatly in building up the cost of practice for design in simple and continuous construction:
comparisons for the case studies. hot rolled sections, 1990.
w12x BS 5950: Part 3: Section 3.1: Design of composite construction.
References Code of practice for design of simple and continuous composite
beams, 1990.
w1x Todd A., Steel or concrete, the economics of commercial w13x BS 5950: Part 4: Code of practice for design of floors with
buildings, British steel structural advisory service: British steel profiled steel sheeting, 1982.
sections plates and commercial steels, February 1996. pp. 2– w14x Corus (formerly British Steel) Structural Sections to BS4: Part
15. 1 and BS 4848: Part 4. British steel sections plates and
w2x Hart A. Multi-storey buildings. In: Owens G, Knowles P, commercial steels, December 1998; pp. 2–5.
editors. 5th ed. Steel designers manual, the steel construction w15x BS 4: Part 1: Specification for hot rolled sections, 1993.
institute. Blackwell Science, 1992. p. 36 –80. w16x BS 4848: Part 4: Hot rolled structural steel sections, equal and
w3x Gray BA, Walker HB. Steel framed multi-storey buildings the unequal angles, 1986.
economics of construction in the UK, Constrado. London: w17x Westok Cellular Beams, Westok Structural Services Limited,
Grove Colour prints Limited, September 1982. p. 3 –37. England. July 1997; pp. 3–14.

You might also like