This document discusses the testing and operation of an SF6 gas handling system for a 3 MeV, 30 kW DC accelerator. Key points:
- The accelerator is housed inside a pressure vessel filled with SF6 gas for insulation. The gas handling system introduces SF6 gas into the vessel after evacuation and recovers the gas with minimal losses.
- Components of the system include storage tanks, a vacuum pump, compressor, dryers and filters. The accelerator vessel and lines are evacuated to 1 mbar before charging with SF6.
- Gas is transferred between the storage tanks and accelerator vessel while maintaining a pressure of 6 kg/cm2. The system recovers, purifies and stores the gas to allow maintenance with
This document discusses the testing and operation of an SF6 gas handling system for a 3 MeV, 30 kW DC accelerator. Key points:
- The accelerator is housed inside a pressure vessel filled with SF6 gas for insulation. The gas handling system introduces SF6 gas into the vessel after evacuation and recovers the gas with minimal losses.
- Components of the system include storage tanks, a vacuum pump, compressor, dryers and filters. The accelerator vessel and lines are evacuated to 1 mbar before charging with SF6.
- Gas is transferred between the storage tanks and accelerator vessel while maintaining a pressure of 6 kg/cm2. The system recovers, purifies and stores the gas to allow maintenance with
This document discusses the testing and operation of an SF6 gas handling system for a 3 MeV, 30 kW DC accelerator. Key points:
- The accelerator is housed inside a pressure vessel filled with SF6 gas for insulation. The gas handling system introduces SF6 gas into the vessel after evacuation and recovers the gas with minimal losses.
- Components of the system include storage tanks, a vacuum pump, compressor, dryers and filters. The accelerator vessel and lines are evacuated to 1 mbar before charging with SF6.
- Gas is transferred between the storage tanks and accelerator vessel while maintaining a pressure of 6 kg/cm2. The system recovers, purifies and stores the gas to allow maintenance with
TESTING AND OPERATIONNAL EXPERIANCE OF SF6 GAS HANDLING
SYSTEM FOR 3 MeV, 30 kW DC ACCELERATOR AT EBC, KHARGHAR,
NAVI MUMBAI Shyam Rao Ghodke, Mahendra Kumar, Rajesh Barnwal, Susanta Nayak, D Jayaprakash, Vijay Sharma, S. K. Srivastava, R I. Bakthsing, Rehim Rajan, D K Sharma, S Devangan, Dr. K. C. Mittal and Dr. L. M. Gantayet
Electron Beam Centre, Accelerator & Pulse Power Division, BARC, Mumbai – 400085 e-mail: ghodke_barc@yahoo.co.in
Abstract: The 3 MeV Accelerator Project involves insulation and efficient cooling. Hence there is a need of
designing, fabrication, installation, commissioning and SF6 gas and its handling system. Normal operating operation of a 3 MeV, 30 kW Industrial Electron Beam pressure inside the accelerator is 6 kg/cm 2. The Accelerator with a terminal voltage of 3 MV and is accelerator tank has to be evacuated up to vacuum of 1 housed inside the ‘Electron Beam Centre’ (EBC) building at Kharghar, Navi Mumbai. The Accelerator has mbar before filling the gas. Detail design [2] and capability of delivering electron beam of 3 MeV energy fabrication [3] of the accelerator pressure vessel using for radiation processing application for ecological and ASME B&PV Code SECVIII, DIV1, reported earlier. economical reason the SF6 gas is reincorporated into closed cycle because gas should not be released into the atmosphere. The aim of the SF 6 Gas Handling System is to introduce the gas at high pressure to the accelerator pressure vessel after evacuation and to bring back into the storage tanks with minimum loss. The gas handling system also provides purification of gas, prevention from mixing with air or any other substances, which may contaminate and thus bring down the high voltage insulation characteristics of the gas. Accelerator is tested up to 1.6 MeV Voltage with SF 6 gas. SF6 gas transfer system involved design of pressure vessel as well as piping. This paper discusses about vacuum testing, pressure testing, methods adopted to reduce leakage and helium leak testing of Accelerator pressure vessel (Height: 7 m, Diameter: 2.1 m). It tells about filing and transfer of SF6 gas with minimum loss and recovery of gas. Operation and safety of different components of SF6 gas handling system is also discussed in the paper.
INTRODUCTION: A 3 MeV, 30 kW DC industrial
electron accelerator has been designed and is working at 1.6 MeV energy & 5 kW power at Electron Beam Centre, Kharghar, Navi Mumbai. Schematic of the accelerator is shown in Fig. 1. [13] The accelerator and its high voltage power supply are housed in a pressure vessel filled with Sulphur Figure 1: Schematic diagram of 3MeV DC accelerator Hexa Fluoride (SF6) gas as a high voltage insulating The basic function of a gas handling or recovery media at 6 kg/cm2. [1] system is to reclaim the insulating gas from an accelerator The Accelerator Pressure vessel [2] is the main vessel, purify, and store it in storage tanks until the body of the Accelerator, which houses high voltage internal modification have been completed, evacuate the multiplier columns, RF electrodes, corona shields, high air from the accelerator vessel and then recharge it with voltage terminals, electron gun, accelerating tubes, RF insulating gas, in a minimum time. From a practical point transformer etc. All of these components require SF6 gas of view of accelerator working, it is very desirable that the cycle time be a small fraction of a working shift, so After this it is connected with transfer line by opening the that the trouble can be diagnosed and corrective measure valve and it is throttled until the compressor inlet pressure can be taken. SF6 gas has been handling with the help of reaches above atmosphere to match the pumping speeds compressor and vacuum pump. Both of these components of the compressor. During the evacuation phase, the are fifty metre away from two numbers of storage tanks vacuum pump outlet is goes through the mist eliminator and main accelerator tank. To increase the conductance of or oil filter made of charcoal, which prevents mixing of pipeline, hence reducing the evacuation time, selected 3” pump oil with SF6 gas. With this mechanism we can NB, Schedule 40, SS 304 L pipe line. Different sub achieve ultimate vacuum inside accelerator tank up to 1 systems and processes are discussed below. mbar. At atmospheric pressure 155 kg of SF 6 gas will be remain but because of above mechanism at 1 mbar Accelerator tank and storage tanks: The pressure only 0.22 kg of SF6 gas remains in the accelerator tank and storage tank are made of ASME SA accelerator tank. This gas will be thrown to atmosphere 516 Gr70 Boiler grade Carbon Steel plates. Both with the help of Nitrogen purging up to 1 bar and accelerator and storage tanks are designed for 10 kg/cm 2 evacuation. of internal pressure and vacuum as external pressure as The main function of vacuum pump is to per ASME B&PV Code Sec VIII Div I [2]. The size of minimize the loss of SF 6 gas during maintenance of accelerator tank is 2120 mm internal diameter, 20 mm accelerator, storage tanks, dryers, filters, pipe lines, etc. wall thickness, 7 m height. The size of storage tank is SF6 gas handling room is 50 meter away from main 1760 mm internal diameter, 15.0 mm wall thickness & accelerator and storage vessels. We have to evacuate the 7000 mm length. Figure 1 shows accelerator tank with accelerator and storage tank from this room with the help accelerator components. of 3000 lpm capacity watercooled double stage Rotary vane Pump. Charging: Vessel, dryer, filter and pipe line evacuated up to 1 mbar before charging the gas in accelerator tank. Drying: The SF6 breakdown products are known to be First time charging in the accelerator vessel was completely removed by passing the gas through activated accomplished by pressure equalisation between the newly alumina. Aim is to achieve dew point better than 36 procured SF6 gas in cylinders and the accelerator vessel. degree Celsius. During non operation period of the For recharging of the accelerator vessel, pressure was accelerator, the SF6 gas is circulated through a large equalised between storage tank and accelerator tank. activated alumina dryer. This is primarily done to During recharging the gas passes from the storage tanks maintain the moisture content in the gas within tolerable to the accelerator vessel through the particulate filters. We limits for proper operation of the accelerator. However, it are storing the gas at a pressure of 6 kg/cm 2g in storage also helps to minimize breakdown product contamination tanks. Liquid storage is not preferred to avoid brittle introduced by corona point’s discharge. Moisture level in fracture of storage vessel at low temperature (below zero SF6 gas at 10, 0, 10, 20, 30 & 40 degree Celsius will degree Celsius) due to adiabatic expansion of gas. For be 1492, 744, 316, 126, 46 & 16 ppm by weight further pressurization air compressor is used. Final respectively. pressure in accelerator tank should be 6 kg/cm 2g. SF6 gas Vertical vessel twin column activated alumina is procured from M/S Solve Flore, Germany conforming filled dryer is used for removal of moisture and to DIN IEC 376 with 99.9 percent purity. breakdown products. Each dryer column having100 kg Alumina balls get saturated after absorbing 1 litre of Recovery: For recovery of SF6 gas from accelerator water. Activation of alumina balls is done by passing tank to storage tank we have to do equalisation of preheated air at 1500C through alumina bed via blower & pressure and then removal with the help of compressor up heater. It takes 6 hours to regenerate. Coarse and fine to 1 kg/cm2g pressure in accelerator tank. When the filters are provided to make sure that dust free gas is accelerator pressure drops below zero psig the flow is circulated through the accelerator column. Coarse filter is diverted through the vacuum pump to maintain the inlet Pleated Bag type filter suitable for filtering 0.3micron pressure to the compressor near atmospheric. Vacuum size dust particles. Fine filter is a cartridge type filter pump will be isolated from gas transfer line up to 1 having borosilicate glass fibre cartridge mounted into SS kg/cm2 pressure in the accelerator tank and pipe line. housing, suitable for filtering 0.01 micron size dust Leak testing of the accelerator tank is undertaken particles. with respect to safety aspect of the human occupancy. Since the operation team has to go around the accelerator for surveillance as well as verification of operational Air compressor system: This system consist of air parameters, during the conditioning and beam trial compressor with motor & flywheel, after cooler, its experiments; ambiance presence of SF6 gas need to be cooling system, air receiver, control panel, skid frame, maintained well below the allowable threshold limit value etc. In 3 MeV accelerator compressed SF 6 gas will be at 20 ppm. Allowable threshold limit value of new SF6 is 1000 ppm. Helium leak testing of the accelerator tank in required at 6 kg/cm2 at accelerator tank and up to 8 pressure mode is done in the sniffer mode of the leak kg/cm2 in storage tanks. Before filling the gas, SF 6 gas testing, employing a mass spectrometer leak detector handling system has to evacuate. Vacuum pump outlet (MSLD). will be given to compressor system to evacuate the Tank is pressurized at 6 kg/cm2 with a mixture of system and transfer remaining SF6 gas into storage tank. Nitrogen and Helium (85:15) by volume. Sealing all the During pressurization of accelerator tank we equalize the ports and the main flange couplings with polythene bags, pressure of accelerator tank and storage tank without leaked out Helium is collected in 12 hours. Leaked out using compressor system. Equalization pressure will be ~ quantity of helium is registered in an MSLD, using a 3 kg/cm2. Compressor system will do further sniffer probe. Three leaks are detected and rectified later. pressurization of accelerator tank. Compressor system Hydro and pneumatic testing: pressure vessels are will do recirculation of SF6 gas through moisture removal hydrostatically tested at a pressure of 13 kg/cm 2g. During system for purification. Compressor system is the main hydrostatic testing entire assembly were held for a period engine of SF6 gas handling system. of 4 hours to observe many joints. No leakage and drop in pressure was observed. Test was found satisfactory. Method to reduce leakage: Pneumatic testing of vessel is conducted at a pressure of I. We have used forged and machined weld neck flanges 11 kg/cm2g. At this pressure soap solution was applied on of outer diameter 2400 mm in accelerator vessel to make welded joints and no leakage was observed for 4 hours. possible 100% radiography. We have used 30 numbers of Thereafter pressure was reduced to 10 kg/cm2 and held for pad type nozzles to make butt weld between nozzle and another 8 hours. accelerator shell. It insures 100% radiography in welding of nozzle and accelerator shell. Safety features: SF6 gas if released into the II. In 3” NB Schedule 40 pipe line of length 200 meter, all atmosphere, tend to accumulate in low laying areas joints are gasket joints with weld neck flanges to do 100% where there is no natural ventilation and may cause radiography. We have not used threaded joints in SF 6 gas asphyxiation. Individual breathing in such an atmosphere transformer system except for pressure gauge, quarter may experience symptoms which include headaches, inch ball valves and pressure transmitter. ringing in airs, dizziness, drowsiness, unconscious, III. Pipe line materials are tested for Chemical, Physical nausea, vomiting and depression of all the senses. The and Inter Granular Corrosion (IGC) test. Purging of skin of a victim of overexposure may have a blue color. Argon gas inside the pipe line also ensures sound weld. The purity should be more than 97%, the moisture content All welded joints are dye penetrant and radiographically should be better than 36 0C and SO2 should be less than tested. 50 ppm. We are maintaining above values with the help IV. Most of the places we have use butterfly valve for of M/s WIKA make ‘Breaker Analyser. The maximum controlling the flow but at specific locations where bulk permissible leakage of 0.5% per year should be allowed SF6 gas is stored, we have used ball valves with better as per IEC standard. Area monitoring systems with 0 leak tightness. 2000 ppm range based on infrared absorption VI. For checking the leakage we have used pressure drop spectroscopy have been installed at the various locations test, soap bubble test, Helium sniffer test, halogen sniffer of the accelerator and gas storage rooms and sensor kept test, vacuum decay test and Mass spectrometer leak at low level. Portable leak detectors with 050 ppm range detection (MSLD) test. based on infrared absorption spectroscopy has been used for detecting the leak tightness. The gas quality has been MSLD leak testing in pressure and vacuum monitored for purity, moisture and acid after recycling the mode: gas through moisture removal system. We have prepared handling procedures and instructions. Risks and warning signs are provided.
Acknowledgement: The authors are thankful to the
staff of electron Accelerator at EBC, Kharghar, Navi Mumbai. Authors gratefully acknowledges Mr. S K Gupta and Mr. Arun Agarwal for the technical support and sharing operational experience of SF6 gas transfer system of FOTIA, BARC, MUMBAI.
Conclusion: SF6 gas handling system is indigenously
developed and being operated at Electron Beam Centre (EBC), Kharghar, Navi Mumbai. All components are fabricated from local vendor of Mumbai. Vacuum and pressure testing of pressure vessels and piping is done for Fig. 3: Air compressor for SF6 transfer leak tightness and integrity of vessel. The SF 6 gas quality is being regularly monitored before accelerator operation. Emission/leakage of SF6 is maintained below TLV. SF 6 gas recovery is achieved up to 1 mbar pressure, only 0.22 kg loss in 1100 kg of SF6 gas. SF6 safety systems and monitors are installed at site and tested. SF 6 cooling system is also a part of SF6 handling system which is not discussed in the paper. 3 MeV Accelerator is working at 1.6 MeV energy and 5 kW power. Efforts to raise energy and power are going on.
Reference:
[1] Ghodke S R, et al, (2003), Tank Design for 3 MeV, 30
kW Industrial Electron Accelerator, InPAC 2003, Indore, India, 249. Figure 4: 3000 lpm rotary vacuum pump and root pump [2] Ghodke S R, et al, (2007), SF 6 Gas Handling System of capacity 4166 lpm. Only rotary vacuum pump is for 3 MEV, 30 KW Electron Beam Accelerator at EBC, sufficient to give vacuum up to 1 mbar in 2.5 hours. Kharghar, Navi Mumbai, APAC 2007, Raja Ramanna Centre for Advanced Technology (RRCAT), Indore, India, 779. [1] K C Mittal, et al, (2007), Development of 3 MeV, 30 kW DC Electron Accelerator at EBC, Kharghar, APAC 2007, RRCAT, Indore, India, 682.
Fig 5: Moisture removal system with control Panel
Fig. 2: SF6 gas storage tanks
Fig.6: Assembly of Accelerator before filling SF6 gas