Professional Documents
Culture Documents
Table of Contents
TABLE OF FIGURES ................................................................................................................................................. 3
WOODY 2000 PROJECT .......................................................................................................................................... 4
A- PROJECT BACKGROUND INFORMATION ......................................................................................................................4
1. Project Sponsor: ...........................................................................................................................................4
2. Project Objectives: ........................................................................................................................................5
3. Problems mentioned in the case study:........................................................................................................5
B- PROJECT MANAGEMENT PLAN METHODOLOGY AND EXTERNAL RESOURCES .......................................................................8
1. Planning Methodology .................................................................................................................................8
2. Resources used in the planning ....................................................................................................................8
C- PROJECT MANAGEMENT PLAN AND STATEMENT OF WORK (SOW) ................................................................................8
1. Feasibility Study............................................................................................................................................8
2. The Scoping Process Group ..........................................................................................................................9
a. Assign a project manager ......................................................................................................................................... 9
b. Develop a high-level project execution method statement. .................................................................................... 9
c. Review the project headlines with the sponsor. .................................................................................................... 10
d. Identify the components of the project management plan.................................................................................... 10
e. Secure the sponsor approval to plan the project. .................................................................................................. 12
f. Hire and assign project management team. ........................................................................................................... 12
3. The Planning Process Group .......................................................................................................................12
a. Create project work break down structure WBS. ................................................................................................... 12
b. Define all the works in the project by developing an activity list. .......................................................................... 13
c. Estimate the activities duration. ............................................................................................................................. 15
d. Estimate activities resources. ................................................................................................................................. 16
e. Estimate project cost. ............................................................................................................................................. 17
f. Sequence the activities, and adjust activities duration .......................................................................................... 18
g. Allocate cost and manpower to the activities ........................................................................................................ 19
Original Manpower histogram: .......................................................................................................................... 19
Leveled Manpower Histogram ........................................................................................................................... 19
Primavera Cash Flow:......................................................................................................................................... 20
Microsoft Excel Cash Flow: ................................................................................................................................ 20
h. Develop risk management plan. ............................................................................................................................. 21
Mitigate the risks: .............................................................................................................................................. 21
Transfer the risks: .............................................................................................................................................. 21
i. Develop closing, testing and commissioning plan. ................................................................................................. 21
j. Setup the project progress evaluation criteria ....................................................................................................... 22
k. Create drawings and materials tracking logs. ......................................................................................................... 22
Shop drawings log: ............................................................................................................................................. 22
Materials tracking log: ....................................................................................................................................... 23
l. Gain the sponsor approval to lunch the project. .................................................................................................... 24
4. The Launching Process Group ....................................................................................................................24
a. Recruiting the project team .................................................................................................................................... 24
b. Establishing the scope change management process............................................................................................. 25
c. Managing team communications: .......................................................................................................................... 25
d. Finalizing the project schedule: .............................................................................................................................. 25
D- UPDATE OF THE PROJECT MANAGEMENT PLAN .........................................................................................................25
1. The Monitoring and Controlling Process Group .........................................................................................25
a. Report project performance: .................................................................................................................................. 25
1|Page
b. Call for weekly meeting: ......................................................................................................................................... 26
c. Monitor the project risks and identify new risks. ................................................................................................... 26
d. Process project changes: ........................................................................................................................................ 26
2. The Closing Process Group .........................................................................................................................26
E- CONCLUSIONS AND RECOMMENDATIONS..................................................................................................................27
2|Page
Table of Figures
Figure 1 : Work break down structure WBS ............................................................................................... 13
Figure 2: Activity list .................................................................................................................................. 14
Figure 3: Activities duration ....................................................................................................................... 15
Figure 4: Activities resources ..................................................................................................................... 16
Figure 5: Estimate project cost.................................................................................................................... 17
Figure 6: Sequence the activities ................................................................................................................ 18
Figure 7: Original Manpower histogram .................................................................................................... 19
Figure 8: Leveled Manpower Histogram .................................................................................................... 20
Figure 9: Primavera Cash Flow .................................................................................................................. 20
Figure 10: Microsoft Excel Cash Flow ....................................................................................................... 21
Figure 11: Shop drawings log ..................................................................................................................... 23
Figure 12: Materials tracking log ................................................................................................................ 24
3|Page
Woody 2000 project
Reference to (Wideman (n.d)) case study subject of the woody 2000 project, Author divided the
project into five main topics. First topic is project background information, which highlight the
project sponsor, project objectives and identified problem in the case study. Second topic is the
project management plan methodology and the planning tools / software used in the project. Third
topic is the project management plan, which include the project feasibility study, Scoping Process
Group, Planning Process Group, and Launching Process Group. Fourth topic is the update of the
project management plan to monitor the project progress and close the project. Finally, the fifth
1. Project Sponsor:
Ron Carpenter established the company in 1954, and later on, his wife Mrs. Emelia
Carpenter was involved on running the company on his behalf. Their son, John
new channel of subcontract work to the company by supplying and installing counter-
tops, cabinets and similar fixtures for new commercial construction. The company is
known as “woody” referring to its creator, and it has a good reputation in the local
market.
4|Page
2. Project Objectives:
Because of the limited space of the manufacture area, and the mini-boom in commercial
construction in 1989, there was a good market to expand the company production, and
develop the production area. The project objectives defined by the sponsors was as per the
following:
After the author study of woody 2000 project, and reference to (Wysocki 2012) project
management life cycle (PMLC), Author highlighted the problems/ mistakes done in the
case study, and the correct action as per the process group, and as per Table number 1.
5|Page
Table 1
6|Page
D There was lack of monitoring the project An effective monitoring plan
progress, in result the following delays could highlight the manufacture
occurred. drawings approval importance,
prevent the delays of its
Delay the approval of the approval, and reschedule the
D.1 manufacture drawings delayed Tie-In of power and other
the procurement two weeks. utilities -if required- as per
Scheduled Tie-In of power and project progress.
other utilities delayed two weeks.
Monitoring Monitoring risk, Discovering and solving Monitoring risks and discover
and problems was not part of project problem before they happened
Controlling procedures, and as a results: will give the opportunity to
Process plan to solve these problems in
Group
Local inspection authority did not a proactive way; this
approve the surplus paint monitoring includes the internal
disposal. and external stockholders. In
D.2
Project delayed 6 months. addition, this will ensure that
Project cost overrun. the project will continue on
Customer delivery dates were track as per specification, on
missed. time and budget.
Some general contractors
cancelled their contracts.
E There was no plan for closing the project The closing process group
“neither Moneysworth nor Leadbetter should be part of the project
had prepared any meaningful planning management plan and should
for completion such as owner's include the following:
inspection and acceptance of the
Closing building, or testing, dry-running and Gaining client approval of
Process production start-up of the production having met project
E.1 train. They also failed to insist that EID
Group requirements
obtain the building occupation Planning and installing
certificate.” deliverables
Writing the final project
report
7|Page
B- Project Management Plan methodology and external resources
1. Planning Methodology
Project management plan based on (Wysocki, 2012, p64) Five Process Groups:
The author used the oracle primavera v.8.1 to sequence the activities, drew network
diagram and Gantt chart. Moreover, Microsoft Excel 2013 to drew the cash flow. All the
outputs from different software embedded in this final project Microsoft Word document.
1. Feasibility Study
Woody’s company maintained a good reputation in the local market and the mini-boom in
commercial construction will increase the wood’s product demand. Therefore, expanding
the production area by 25% will return tangible profits; will maintain woody’s client
8|Page
2. The Scoping Process Group
None of the wood’s company available resources can manage the project;
After the new project manager John discussion with the production people, he
created a high level project execution method statement as a starting point, the
method statement defines how and what will be executed in order to finish the
project on time, within budget, as per the sponsor requirements, and as per the
following:
9|Page
c. Review the project headlines with the sponsor.
After the creation of the high-level method statement, the project manager
john called for a meeting with the company directors to review the main
headlines and proceed with the next step. John persuaded the sponsors to
finish the project design before starting the execution to mitigate risks of
reworks.
groups, and because he studied MSc in Liverpool University, he used the MSc
text book (Wysocki 2012) to add more value of the project management plan.
John identified the project management plan components as per the following:
chart.
Allocate cost and manpower to the activities to create cash flow and
manpower histogram.
10 | P a g e
Develop risk management plan.
to compare the Earned value (EV) against Planned Value (PV) and
reactive actions.
Call for weekly meeting to discuss the project progress and risks with
11 | P a g e
Secure all project documents, such as warranties, certificate of
authority’s approvals.
After listing the project management plan component, John called for a meeting
plan content, the project manager proceeded and hire the Designer Firm, and
the project management team. John signed a contract with a Design Office, and
The Project Manager with the planning engineer created the project WBS
12 | P a g e
Figure 1 : Work break down structure WBS
construction manager, and the planning engineer to identify the project activity
13 | P a g e
Figure 2: Activity list
14 | P a g e
c. Estimate the activities duration.
After the creation of the activity list, Project team estimated the activities
15 | P a g e
d. Estimate activities resources.
After the estimation of the activities duration, the project team assigned the
manpower required to execute each task on the chosen duration as per figure 4
16 | P a g e
e. Estimate project cost.
After the estimation of the required manpower for each activity, the project
team estimated the project cost by assigning each task with the expected cost.
The project manager founded that the project budget will exceed the proposed
17 | P a g e
f. Sequence the activities, and adjust activities duration
Project duration is18 months, using Oracle Primavera scheduling tool to draw
18 | P a g e
g. Allocate cost and manpower to the activities
To create cash flow and manpower histogram, manpower and cost should be
It was noticed that the manpower needs leveling to reduce the risks
associated with performing too many tasks at the same time. Therefore,
activities earlier to level the resources as per figure 8 (this change will
19 | P a g e
Figure 8: Leveled Manpower Histogram
After leveling the resources, the cash flow is created from Primavera
as per figure 9
20 | P a g e
Figure 10: Microsoft Excel Cash Flow
The plan to manage risks associated with this project divided into two main
By leveling resources to avoid doing too many tasks at the same time.
By instructing, the contractor to procure all the materials and assign the
21 | P a g e
The project schedule allow for 30 days to close the project, before starting this
tasks, project team should identify what exactly is required to close the project
probably. Project team should also focus on the local municipality requirements
Mainly to measure the progress planned value and earned value are the main
After finalizing the time schedule, each task has a shop drawing should
22 | P a g e
Figure 11: Shop drawings log
to mitigate the risks of materials being delayed and delay the related
task, the material tracking log is very important document to keep focus
23 | P a g e
Figure 12: Materials tracking log
After the creation of the project management plan, it should be submitted to the
sponsor for approval to start the project. However, in some cases, the planning
process group is being done parallel with the execution process group, which
consider high risk. In this case, study it is recommended to finish the planning
process group and obtain the sponsor approval before starting the lunching
process group.
24 | P a g e
After the approval of the project management plan, the project manager is
Any changes to the original scope of work, should be done within the scope
management process and revise the project schedule, cash flow, manpower
Create an organization chart clarifying the roles and responsibilities for every
team member. The project manager setup a weekly meeting to discuss the work
progress, and another technical meetings to solve any problems could delay the
project.
Project schedule could be impacted with different process, for example, the
resource leveling affected the cash flow and the Gantt chart, any modifications
25 | P a g e
Using Earned Value Management (EVM) to compare the Earned value (EV)
against Planned Value (PV) and keep the forecast completion date on target by
To discuss the project progress and risks with the project team.
26 | P a g e
E- Conclusions and recommendations
This project represent a great opportunity to Wood’s company to expand the production,
increase the company profit, and fulfill the company commitments towards their clients. In
order to effectively manage the project, a professional project manager with project
management background is required to manage this project. The project should be designed
by expert design office, and executed by a professional contractor. The project manager
role is to manage and coordinate between the design office and the contractor, create and
monitor the project management plan. Resource leveling performed to mitigate the risks of
executing too many activities at the same time. by assigning a designer office and
contractor to supervise and execute the works respectively, Woody’s company transferred
the associated risks to the third party. However, the project manager is responsible to
manage the performance of all parties and report the progress as per the project
References:
KERZNER, H., 2009. Project management [electronic book] : a systems approach to planning,
scheduling, and controlling / Harold Kerzner. Hoboken, NJ : John Wiley & Sons, 2009; 10th ed.
knowledge (PMBOK guide). 4th edn. Newtown Square, Pa.: Project Management Institute.
Wideman, M. (n.d.) Project management case study: the custom woodworking company -
27 | P a g e
WYSOCKI, R.K., 2012. Effective project management. 6th edn. Indianapolis, IN: Wiley.
28 | P a g e