You are on page 1of 254

SRI LANKA OPERATIONS CENTRE

 
Annex III Technical  Specification 
 
 
 
 
 
Special Provisions to Standard Specifications 
 
 
For 
 
 
ICTAD‐Construction and Maintenance of Roads 
and Bridges 
 
 
 
 

 
Series 100 – General              Page no: 1 of 63 
SRI LANKA OPERATIONS CENTRE

PREAMBLE TO ICTAD  
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MAINTENANCE OF ROAD 
AND BRIDGES 
 
The  works  shall  be  carried  out  in  conformity  with  the  ICTAD  standard  specifications  for 
construction and maintenance of Roads and Bridges ICTAD Publication no SCA/5, 1989 issued 
under  the  Authority  of  the  General  manager,  Road  Development  Authority,  Ministry  of 
highways, Sri Lanka.  
 
References  to  the  ‘Specification’  in  the  Contract  Documents  mean  the  Sri  Lankan‐ICTAD 
Construction  Specification.  The  Sri  Lankan‐ICTAD  Construction  Specification  is  hereby 
incorporated into the Contract as a Contract Document and the Contractor will be deemed to 
have full knowledge of this Specification. 
 
Copies of the Sri Lankan‐ICTAD Construction Specification are available at the above address 
on payment of the relevant fee. In the event of any conflict in the Specification the following 
precedence shall be apply: 
 
1.   Part  A:    General  Technical  Specifications:  ICTAD‐Standard  Specifications  for 
Construction and Maintenance of Roads & Bridges 
 
2.  Part  B:    Particular  Technical  Specifications:  Special  Provision  to  Standard 
Specification 
 
 
 

 
Series 100 – General              Page no: 2 of 63 
SRI LANKA OPERATIONS CENTRE

 
SERIES 100 ‐ GENERAL 
 
CONTENTS 
 
101.  ABBREVIATIONS..................................................................................................................7 

102.  DEFINITIONS .......................................................................................................................7 

103.  ARRANGEMENTS FOR TRAFFIC DURING CONSTRUCTION ...................................................11 


103.1.  GENERAL .............................................................................................................................11  
103.2.  USING PART OF THE ROAD ......................................................................................................13  
103.3.  TEMPORARY DIVERSION ..........................................................................................................13  
103.4.  TRAFFIC SAFETY AND CONTROL ................................................................................................13  
104.  CONTROL OF WORKS ........................................................................................................14 
104.1.  AUTHORITY OF THE ENGINEER ..................................................................................................14  
104.2.  CONFORMITY WITH PLANS AND SPECIFICATIONS ..........................................................................15 
104.3.  STANDARDS ..........................................................................................................................15  
104.4.  HEALTH AND SAFETY ..............................................................................................................15  
104.5.  PROTECTION OF PUBLIC SERVICE FACILITIES ................................................................................16 
104.6.  SAFETY RELATING TO TEMPORARY STRUCTURES...........................................................................16 
104.7.  SAFETY RELATING TO NAVIGABLE WATERWAYS ...........................................................................16 
104.8.  ENVIRONMENTAL REQUIREMENT ..............................................................................................17  
Emission standard values for Motor Vehicle Exhaust....................................................................18 
Emission standard values for Black Smoke Emission from boat/ship/vessel.................................18 
104.9.  CONSTRUCTION PROGRAMMING ..............................................................................................21  
104.10.  PROGRESS MEETINGS .............................................................................................................22  
104.11.  RETURNS AND REPORTS ..........................................................................................................22  
104.12.  TELECOMMUNICATIONS ..........................................................................................................23  
104.13.  COMPACTION – GENERAL .......................................................................................................23  
104.14.  MIXING & CONTROL OF MOISTURE CONTENT BEFORE COMPACTION ..............................................24 
104.15.  COMPACTION EQUIPMENT ......................................................................................................24  
104.16.  WATER AND POWER SUPPLY ARRANGEMENTS ............................................................................24 
104.17.  DRAINAGE DURING CONSTRUCTION...........................................................................................25  
104.18.  PREVENTION OF DAMAGES TO EMBANKMENTS, SUB‐GRADE LAYERS, PAVEMENT LAYERS AND SHOULDERS 
IN POSITION. ..........................................................................................................................................25 
104.19.  COMPACTION TRIALS..............................................................................................................25  
104.20.  COMPACTION CONTROL ..........................................................................................................25  
104.21.  DISPERSAL OF HAULING EQUIPMENT .........................................................................................26  
104.22.  PROTECTION TO NEWLY CONSTRUCTED LAYERS ...........................................................................26 
104.23.  BRIDGE CONSTRUCTION SEQUENCE ...........................................................................................26  
104.24.  MATERIALS TESTING BY INDEPENDENT LABORATORIES ..................................................................27 
104.25.  SPECIAL AND ADDITIONAL TESTING ...........................................................................................27  
104.26.  STAFF FOR MATERIALS TESTING ................................................................................................27  
104.27.  CODES AND STANDARDS .........................................................................................................27  
104.28.  TEST RESULTS AND RECORDS ...................................................................................................27  
104.29.  MEASUREMENT AND PAYMENT ................................................................................................27  
105.  CONTROL OF MATERIALS ..................................................................................................28 
105.1.  SOURCES OF SUPPLY AND QUALITY REQUIREMENTS......................................................................28 
105.2.  STORAGE OF MATERIALS .........................................................................................................28  
105.3.  HANDLING OF MATERIALS .......................................................................................................28  
105.4.  APPROVAL OF SOURCES OF MATERIAL (ADD THE FOLLOWING) .......................................................29 
105.5.  STOCKPILING OF MATERIALS (ADD THE FOLLOWING) ....................................................................29 
 
Series 100 – General              Page no: 3 of 63 
SRI LANKA OPERATIONS CENTRE

105.6.  TEMPORARY STOCKPILING OF MATERIALS (ADD THE FOLLOWING)...................................................29 
105.7.  CONTROL TESTS ON MATERIAL DURING CONSTRUCTION (ADD THE FOLLOWING) ...............................29 
105.8.  MATERIAL TESTING (ADD THE FOLLOWING) ................................................................................31 
105.9.  APPLICABILITY OF GENERAL SPECIFICATIONS (ADD THE FOLLOWING)................................................31 
105.10.  PAYMENT (ADD THE FOLLOWING).............................................................................................31  
106.  GENERAL RULES FOR MEASUREMENT AND PAYMENT .......................................................31 
106.1.  OVERHAUL ...........................................................................................................................33  
106.2  MEASUREMENT OF PAVEMENT FOR AREA AND VOLUME BASED PAYMENT........................................33 
a.  Area Basis..............................................................................................................................33 
b.  Volume Basis .........................................................................................................................33  
106.3  SCOPE OF RATES FOR DIFFERENT ITEMS OF WORK .......................................................................33 
106.4  FACILITIES FOR VERIFICATION OF MEASUREMENTS .......................................................................33 
106.5  SELECTION OF PAY ITEMS ........................................................................................................33  
106.6  SUB DIVISIONS WITHIN PAY ITEMS ...........................................................................................33  
106.7  SUBSTANTIAL COMPLETION OF THE WORKS (ADD THE FOLLOWING) ................................................33 
107.  SIEVE DESIGNATIONS ........................................................................................................34 

108.  CONTRACTOR’S ESTABLISHMENT ON SITE .........................................................................34 


108.1.  OFFICE, EQUIPMENT TESTING FACILITIES ETC. .............................................................................34 
108.2.  LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC ..................................................................34 
108.3.  MEASUREMENT.....................................................................................................................34  
108.4.  PAYMENT .............................................................................................................................35  
109.  INFORMATION FURNISHED BY THE EMPLOYER..................................................................36 

110.  WORKMANSHIP AND QUALITY CONTROL ..........................................................................36 

111.  SELECTION OF LABOUR .....................................................................................................37 

112.  WORK EXECUTED BY THE EMPLOYER OR OTHER CONTRACTORS........................................37 

113.  PROTECTION OF PUBLIC SERVICE FACILITIES......................................................................38 
113.1.  EXISTING SERVICES.................................................................................................................38  
113.2.  PAYMENT .............................................................................................................................38  
114.  MAINTENANCE OF EXISTING ROADS..................................................................................39 
114.1.  GENERAL OBLIGATIONS ..........................................................................................................39  
114.2.  PAYMENT .............................................................................................................................39  
115.  PROTECTION OF THE WORKS AND REQUIREMENTS TO BE MET BEFORE CONSTRUCTION OF 
NEW WORK ON TOP OF COMPLETED WORK IS COMMENCED ........................................................39 
115.1.  PAYMENT .............................................................................................................................40  
116.  REMEDIAL WORK ..............................................................................................................41 
116.1.  EARTHWORKS .......................................................................................................................41  
116.2.  LOCAL DEFECTS IN PAVEMENT LAYERS .......................................................................................41  
116.3.  CONCRETE ............................................................................................................................42  
116.4.  PAYMENT .............................................................................................................................42  
117.  WATER SUPPLY ARRANGEMENTS ......................................................................................42 
117.1.  PAYMENT .............................................................................................................................42  
118.  ELECTRCITY SUPPLY...........................................................................................................42 
118.1.  PAYMENT .............................................................................................................................42  
 
Series 100 – General              Page no: 4 of 63 
SRI LANKA OPERATIONS CENTRE

119.  PAYMENTS & TOLERENCES................................................................................................42 
119.1.  PAYMENT .............................................................................................................................43  
120.  PHOTOGRAPHIC RECORDS ................................................................................................43 
120.1.  PAYMENT .............................................................................................................................43  
121.  ACCESS TO SITE .................................................................................................................43 
121.1.  PAYMENT .............................................................................................................................44  
122.  CO‐OPERATION AT SITE.....................................................................................................44 
122.1.  PAYMENT .............................................................................................................................44  
123.  ROADS AND SITE TO BE KEPT CLEAN..................................................................................44 
123.1.  PAYMENT .............................................................................................................................44  
124.  SECURITY OF THE WORKS..................................................................................................44 
124.1.  PAYMENT .............................................................................................................................45  
125.  SUPPRESSION OF NOICE....................................................................................................45 
125.1.  PAYMENT .............................................................................................................................45  
126.  SAFETY..............................................................................................................................45 
126.1.  PAYMENT .............................................................................................................................46  
127.  METHOD OF WORKING .....................................................................................................46 
127.1.  PAYMENT .............................................................................................................................46  
128.  TEMPORARY WORKS.........................................................................................................46 
128.1.  PAYMENT .............................................................................................................................46  
129.  SETTING OUT AND CROSS SECTION SURVEY AND DRAWINGS ............................................47 
129.1.  GENERAL .............................................................................................................................47  
129.2.  SETTING OUT AND CROSS SECTIONS ..........................................................................................47  
129.3.  MEASUREMENT & PAYMENT ...................................................................................................48  
129.4.  PAYMENT .............................................................................................................................48  
130.  FACILITIES FOR THE ENGINEER AND HIS STAFF...................................................................48 
130.1  DESCRIPTION ........................................................................................................................48  
130.2  LAND FOR FACILITIES ..............................................................................................................49  
130.3  SOLE USE OF FACILITIES ..........................................................................................................50  
130.4  SERVICES..............................................................................................................................50 
130.5  RENTED PREMISES .................................................................................................................50  
130.6  OFFICES AND FURNISHINGS .....................................................................................................50  
130.7  ACCOMMODATION FOR THE ENGINEER ......................................................................................52  
130.8  ENGINEER’S LABORATORY AND EQUIPMENT ................................................................................54 
A)  MATERIALS TESTING BY INDEPENDENT LABORATORIES ..................................................................54 
B)  SPECIAL AND ADDITIONAL TESTING ...........................................................................................54  
C)   STAFF FOR MATERIALS TESTING ................................................................................................54  
130 (15)  SPECIAL AND ADDITIONAL TESTING  PROVISIONAL SUM .................................................................55 
130(16)  STAFF FOR MATERIALS TESTING   PERSON MONTH .......................................................................55 
130.9  STATIONERY FOR THE ENGINEER ...............................................................................................55  
130.10  PROVISION OF HOTEL ACCOMMODATION FOR THE ENGINEER AND HIS STAFF ....................................56 
130.11  SURVEY EQUIPMENT ..............................................................................................................57  
130.12  MAINTENANCE OF ENGINEER’S FACILITIES ..................................................................................58 
130.13  CLERICAL AND TECHNICAL STAFF ...............................................................................................59  

 
Series 100 – General              Page no: 5 of 63 
SRI LANKA OPERATIONS CENTRE

130.14  VEHICLES FOR THE ENGINEER, ..................................................................................................60  


131.  PROJECT SIGN BOARDS .....................................................................................................61 
131.1   DESCRIPTION ........................................................................................................................61  
131.2  MEASUREMENT.....................................................................................................................61  
131.3  PAYMENT .............................................................................................................................62  
132.  PROVISION OF INSURANCES, BONDS AND SECURITIES.......................................................62 
132.1  DESCRIPTION ........................................................................................................................62  
132.2  MEASUREMENT AND PAYMENT ................................................................................................62  
133.  MARBLE STONE FOR FOUNDATION LAYING.......................................................................62 
133.1   DESCRIPTION ........................................................................................................................62  
133.2  MEASUREMENT.....................................................................................................................62  
133.3  PAYMENT .............................................................................................................................63  
133  MARBLE STONE FOR FOUNDATION LAYING.......................................................................59 
133.1  DESCRIPTION ........................................................................................................................59  
133.2  PAYMENT..........................................................................................................................59 

 
Series 100 – General              Page no: 6 of 63 
SRI LANKA OPERATIONS CENTRE

SERIES 100 ‐ GENERAL 
 

101. ABBREVIATIONS 
 
Add the following :‐ 
 
m    metre 
km    kilometre 
Sq.m    square metre 
Cu.m    cubic metre 
cm    centimetre 
mm    millimetre 
gm.    gram 
kg    kilogram 
N    Newton 
kN    kilo newton 
HFL    High Flood Level 
LWL    Low Water Level 
WMM    Wet Mix Macadam 

102. DEFINITIONS 
 
Add the following : 
 
Aggregate – Hard mineral elements of construction material mixtures, for example: 
sand, gravel (crushed or uncrushed) or crushed rock 
 
Asphalt Concrete – A mixture to predetermined proportions of aggregate, filler and 
bituminous  binder  material  plant  mix  and  usually  placed  by  means  of  a  paving 
machine. 
 
Asphalt Surfacing ‐ The layer or layers of asphalt concrete constructed on top of the 
road base. 
 
Back Fill ‐ Excavated material, which is placed and compacted in trenches and around 
foundations. 
 
Batter Board ‐ A board of wood fixed to posts at the top of cuttings or the bottom of 
embankments which indicates the slope at which the cutting or embankment is to be 
constructed. 
 
Bitumen ‐ A class of black or dark‐coloured (solid, semisolid, or viscous) cementitious 
substances, natural or manufactured, composed principally of high molecular weight 
hydrocarbons, of which asphalts, tars, pitches, and asphaltites are typical.  
 
Borrow  Area/Borrow  Pit  ‐  An  area,  within  designated  boundaries,  outside  the 
Permanent Works, approved for the purpose of obtaining fill or pavement materials. 
A borrow pit is the excavated pit in a borrow area. 
 

 
Series 100 – General              Page no: 7 of 63 
SRI LANKA OPERATIONS CENTRE

Borrow  Material  ‐  Borrow  material  is  a  general  term  used  to  describe  material 
obtained from a borrow pit. 
 
Boulder  ‐  A  rock  fragment,  usually  rounded  by  weathering  or  abrasion,  with  an 
average dimension of 300mm or more.  
 
Capping  Layer  ‐  A  layer  of  selected  fill  material  placed  on  the  top  of  the  topmost 
embankment layer or the bottom of excavation. 
 
Chippings ‐ Chippings are single sized particles of crushed rock, crushed boulders or 
crushed gravel used for surface dressing. 
 
Coarse Aggregate ‐ Course aggregate is material retained on the 4.75mm sieve.  
 
Compliance Testing ‐ Testing of the completed works to ascertain compliance of the 
requirements of the Specification. 
 
Cut ‐ Cut shall mean all excavated material from the road prism including side drains. 
 
Cutting  ‐  That  portion  of  the  road  prism  from  where  material  is  excavated  to  sub‐
grade or road bed level. 
 
Earthworks  ‐  The  excavation  of  material  from  cuttings  and/or  the  construction  of 
embankments. 
 
Embankment  ‐  That  portion  of  the  road  prism  composed  of  approved  fill  material, 
which lies above the original ground and is bounded by the side slopes, described in 
the  Contract,  extending  downwards  and  outwards  from  the  outer  shoulder  break‐
points and on which the pavement is constructed. 
 
False work – Temporary staging & working platforms. 
 
Fill ‐ Material which is used for the construction of embankments. 
 
Fine Aggregate ‐ Fine aggregate is material passing the 4.75mm sieve.  
 
Footway  ‐  An  area  normally  adjacent  to  the  carriageway  provided  for  the  use  by 
pedestrians.  
 
Formwork  ‐  Temporary  boarding  or  sheeting  erected  to  contain  concrete  during 
placing, compacting and initial hardening including supports.  
 
Gabions ‐ Gabions consist of woven steel mesh boxes or mattresses filled with stone. 
 
Gravel  ‐  Gravel  is  naturally  occurring,  rounded,  granular  material  with  an  average 
dimension  of  more  than  5mm  and  less  than  300mm,  (it  does  not  apply  to  Gravel 
Wearing Courses).  
 
Prime Coat ‐ A bituminous treatment applied to the surface of a newly constructed 
unbound  road  base  prior  to  the  construction  of  a  bituminous  layer  or  surface 
treatment.  
 
Series 100 – General              Page no: 8 of 63 
SRI LANKA OPERATIONS CENTRE

 
Quality  Control  ‐  Procedures,  and/or  testing,  carried  out  prior  to,  or  during,  the 
construction  of  the  Works  for  the  purpose  of  ensuring  compliance  with  the 
requirements of the Specification. 
 
Quarry ‐ An area within designated boundaries, approved for the purpose of 
obtaining rock. 
  
Road Base ‐ A layer of material of defined thickness and width constructed on top of 
the  sub‐base,  or  in  the  absence  thereof,  the  sub‐grade.  A  road  base  may  extend 
beyond the carriageway. 
 
Roadway ‐ The roadway comprises the carriageway, shoulders and median. 
 
Rock ‐ A mass of hard mineral material which, when excavated, requires the use of 
explosives, sawing or splitting by mechanical means. 
 
Rip‐rap ‐ Unbounded stone provided to protect the surfaces of slopes and the beds 
of watercourses from erosion and scour. 
 
Scarify ‐ Loosen and break‐up soil or existing pavement layers by means of a machine 
fitted with tines. 
 
Shoulder Breakpoint ‐ The point on a cross section at which the extended flat planes 
of  the  surface  of  the  shoulder  and  the  outside  slope  of  the  fill  and  pavement 
intersect. 
 
Side Drain ‐ A longitudinal drain offset from, and parallel to, the carriageway. 
 
Stabilisation  ‐  The  treatment  of  pavement  materials  by  the  addition  of  lime  or 
Portland cement. 
 
Sub‐surface  Drain  ‐  A  covered  drain  constructed  to  intercept  and  remove  sub‐soil 
water. It includes all pipes and filter material in the drain. 
 
Surface  Dressing  ‐  The  sealing  or  resealing  of  the  surface  of  the  carriageway  or 
shoulders by means of one or more successive applications of bituminous binder and 
chippings. 
 
Tack Coat ‐ A bituminous treatment applied to the surface of an existing bituminous 
layer prior to the construction of a new bituminous layer. 
 
Topsoil  ‐  A  surface  layer  of  soil  which  contains  organic  matter  and  is  capable  of 
supporting the growth of vegetation. 
 
Traffic ‐ Vehicles, pedestrians and animals travelling along a route. 
 
Traffic  Lane  ‐  Part  of  a  carriageway  intended  for  a  single  stream  of  traffic  in  one 
direction, which has normally been demarcated as such by road markings.  
 

 
Series 100 – General              Page no: 9 of 63 
SRI LANKA OPERATIONS CENTRE

California  Bearing  Ratio  (CBR)‐Test  method  to  evaluate  the  bearing  capacity  of  the 
soil. 
 
Maximum Dry Density (MDD)‐ Maximum dry density as determined in the laboratory 
using Standard Compaction. 
 
Optimum Moisture Content (OMC)‐ Optimum moisture content as determined from 
moisture density relationship tests for Standard Compaction. 
 
Dynamic Cone Penetrometer (DCP)‐ Device for field checking of in situ CBR,  
 
All kinds of Soil‐ The soil type include clay, sand, gravel, boulders, hard rocks etc. 
 
In  this  Specification  the  following  terms,  words  or  expressions  shall  have  the 
meanings  hereby  assigned  to  them.  For  ease  of  understanding  certain  cross‐
sectional and pavement structure elements are illustrated in and Figure 2 & Figure 2. 
  
 
Figure 1 Terms and Definitions for Road Cross Section Elements 

Right of Way

Limit of Roadbed

Roadway

Carriageway
Shoulder
Traffic Lane Traffic Lane

Shoulder
Shoulder Break
Point

Embankment

Fill
Pavement Layers
Side Drain
Sub-grade (Top of Capping Layer
Fill Material) (if Required)

Roadbed (Existing Sub-grade (Bottom


Ground under of Excavation)
Embankment)

 
 

 
Series 100 – General              Page no: 10 of 63 
SRI LANKA OPERATIONS CENTRE

Figure 2 Terms and Definitions for Pavement Structure 

W e a r in g C o u r s e
S u r f a c in g L a y e r s
B a s e C o u r s e ( if a n y )

Road Pavement Layers


Road B ase

S u b -b a s e
S u b -g r a d e

C a p p in g L a y e r
( if r e q u ir e d )

 
Where the definition in the General Conditions of Contract differ from those in the 
Standard Specifications and Special provisions to Standard Specifications, the former 
shall apply. 

103. ARRANGEMENTS FOR TRAFFIC DURING CONSTRUCTION 

103.1. General 
Delete this sub‐section and substitute the following:‐ 
 
  From the date of Commencement of the Works to the date of issue of Taking‐over 
Certificate  for  the  whole  of  Works  as  provided  for  in  the  contract  the  Contractor 
shall  be  responsible  for  maintaining  the  uninterrupted  passage  of  vehicles  and 
pedestrians  along  the  project  road/right  of  way.    The  road  is  extensively  used  and 
due attention shall be paid by the Contractor to the maintenance and riding comfort 
of all roads/detours/diversions. 
 
  The types of maintenance situations described below include: 
  
  (i)  Construction  and  maintenance  of  temporary  detours  (away  from  existing 
road embankment) required to be built because the full width of the existing 
road  is  under  construction  or  where  works  on  cross  drainage  structures 
requires  the  provision  of a temporary detour including maintenance of the 
existing Bridge. 
 
  (ii)  Construction  and  maintenance  of  temporary  diversions  along  an  existing 
embankment  when  road  construction  is  progressing  half  width  beyond  the 
proposed centerline. 
 
(iii)  Maintenance of the existing road prior to commencement of construction. 
   
(iv)  Maintenance  of  completed  half  width  of  road  and  shoulder  opened  to 
traffic. 
 
(v) Maintenance  of  traffic  on  exposed  granular  layers  in  a  carriageway  under 
construction. 
 
Series 100 – General              Page no: 11 of 63 
SRI LANKA OPERATIONS CENTRE

 
The Contractor’s responsibilities shall include the rectification of any deterioration or 
damage  to  the  road,  intersections  or  driveways,  and  drainage  structures;  due  to 
passage of traffic, or rains or flood. The specific locations of any detour or diversions 
shall depend upon the Contractor’s method of working and the Contractor shall be 
deemed to have covered the same in quoting his rates. 
 
Upon  completion  of  a  days  work,  or  if  the  Works  are  to  be  left  unattended,  the 
Contractor shall leave the Works in such a condition so as to allow the safe passage 
of  traffic.    The  Contractor  shall  be  responsible  for  complying  with  all  regulations 
relating to the temporary closure of roads in Sri Lanka. 
 
The  Contractor  shall  provide  and  maintain  for  the  period  of  construction,  traffic 
control  and  safety  devices  including  Traffic  Signs,  Barricade  Boards,  Traffic  Cones, 
Lighting  Devices  etc.,  at  all  locations  where  work  is  in  progress  in  accordance  with 
Part  II  of  the  “Manual  of  Traffic  Control  Devices,  Road  Development  Authority, 
Ministry of Transport and Highways”. 
 
The  Contractor  shall  so  conduct  his  operations  as  to  offer  the  least  possible 
obstruction  and  inconvenience  to  the  public.  He  shall  have  under  construction  no 
greater length or amount of works than he can properly manage at a time with due 
regard to the rights of the public in maintaining a free flow of traffic. Unless provided 
otherwise  in  this  specification  all  traffic  shall  be  permitted  to  pass  through  the 
sections  of  the  works,  which  have  been  completed  and  opened  to  traffic  in 
accordance with the contract. 
 
Area of existing public roadway, traffic diversions or detours shall not be obstructed 
or used in any way by the Contractor for the dumping or stockpiling of materials, or 
parking of Contractor’s equipment 
 
At  least  15  days  before  commencing  work  on  any  section  of  the  works  the 
Contractor shall submit to the Engineer his proposals for the maintenance of traffic 
including  Working  Drawings  of  traffic  control  arrangements,  road  signs,  and  any 
temporary  road  works  including  detailed  typical  cross  sections  of  proposed 
detours/diversions  indicating  clearly  the  type  of  diversion,  proposed  material  and 
thickness  of  pavement  structure  and  surfacing  not  inferior  to  specifications  stated 
hereinafter, and a program showing the time over which the diversion is required to 
carry the traffic. 
 
The Engineer may require changes to the Contractor’s proposals prior to approving 
the  proposal  of  temporary  works  and  program.  The  standard  of  road  surfacing 
required  may  depend  on  the  duration  that  the  detour/diversion  is  required  to  be 
operational.  Approval  to  the  Contractor’s  proposal  shall  not  take  away  the 
Contractor’s  obligation  to  provide  for  the  uninterrupted  passage  of  vehicles  and 
pedestrians  at  all  times.  Where  necessary  the  Contractor  shall  strengthen  by  the 
addition  of  pavement  layers  or  by  additional  compaction  or  other  means,  any 
detours or diversions that may be found inadequate for traffic no extra cost to the 
contract. 
 
Material and equipment temporarily stored on, or adjacent to, the existing roadway 
shall  be  so  placed,  and  the  work  at  all  times,  shall  be  so  conducted  as  to  cause 
 
Series 100 – General              Page no: 12 of 63 
SRI LANKA OPERATIONS CENTRE

minimum  disruption  to  the  travelling  public.    Warning  signs  and  barrels  will  be 
required to separate the Contractor’s material and equipment from the public. 
 
The Contractor will not be permitted to have excavations open on both sides of the 
road at a particular chainage such that there is a step adjacent to public traffic which 
may  create  a  danger  to  traffic  i.e.  the  excavation  and  backfilling  with  sub‐base  or 
base  shall  be  flush  with  the  existing  road  level  on  one  side  before  excavation  can 
proceed on the other side of the road. 
 
The maximum length of one‐way working controlled by stop/go boards or flagmen 
shall  be  500  metres.    This  length  may  be  further  reduced  if  visibility  is  reduced  at 
bends on increased where appropriate at the Engineer’s discretion. 
 
During construction for operations which require one way traffic the Contractor shall 
be responsible for the removal of broken down vehicles including vehicles damaged 
in accidents and shall maintain one way uninterrupted traffic flow at all times 
As  an  alternative  or  in  addition  to  one‐way  working,  traffic  diversions  may  be 
arranged where this is feasible.  Such diversions shall be approved by the Engineer in 
conjunction  with  the  Traffic  Police.    The  Contractor  shall  be  responsible  for  the 
provision and maintenance of adequate signing for the duration of any diversion. 
 
The  Contractor  shall  arrange  for  the  Traffic  Police  to  be  in  attendance  for  traffic 
management whenever required. 
 
No separate payment for the maintenance or any other costs incurred whilst utilising 
the  diversion  shall  be  made.    All  costs  shall  be  deemed  to  be  included  in  the 
Contractor’s rates. 
 
All  earth  and  gravel  by‐passes  and  existing  gravel  roads  used  as  by‐passes  shall  be 
maintained in a safe trafficable condition by the Contractor.  Wherever required by 
the  Engineer,  the  roads  and  by‐passes  shall  be  graded  by  motor  grader  or  by 
approved  means  to  provide  a  smooth  riding  surface  free  of  corrugation.    All  pot‐
holes shall be promptly repaired by the contractor.  Drainage shall be kept in good 
order and the Contractor shall water the by‐passes as often as is necessary to keep 
dust down. 

103.2. Using Part of the Road 
No change. 

103.3. Temporary Diversion 
No change 

103.4. Traffic Safety and Control 
Delete this sub‐section and substitute the following: 
 
The  Contractor  shall,  after  consultation  with  the  Engineer,  all  the  concerned  Local 
Authorities and Police prepare a scheme of traffic management for carrying out the 
Works.  Such proposals shall be submitted to the Engineer for his approval, together 
with written approval / no objection certificates from the concerned authorities, not 
less than 30 days before the planned implementation of each proposal.   
 
 
Series 100 – General              Page no: 13 of 63 
SRI LANKA OPERATIONS CENTRE

The Contractor shall not commence any works affecting any public highway until all 
approved  traffic safety measures conforming to the Engineer’s prior approval have 
been fully implemented to the satisfaction of the Engineer.   
 
The  Contractor  shall  take  necessary  measures  for  the  safety  of  traffic  and  third 
parties  by  providing,  erecting  and  maintaining  all  signs,  lamps,  barriers,  traffic 
control  signals,  road  markings,  etc.  in  a  clean  and  legible  condition,  and  shall 
position,  re‐position,  cover  or  remove  them  as  required  by  the  progress  of  the 
Works. The barriers shall be strong. Red lanterns or warning lights shall be mounted 
on  the  barriers  at  nights  and  shall  be  kept  lit  till  sunrise.  If  the  Contractor  fails  to 
comply with these requirements, the Engineer shall order a third party to rectify the 
shortcomings and shall recover the cost of such works from the Contractor.  
 
a.  Measurement 
 
Arrangements  for  traffic  during  construction  shall  be  measured  per  month  for  the 
period  during  which  the  Contractor  maintains  the  arrangement  to  achieve  full 
compliance with the requirement of Section 103.   
 
b.  Payment 
 
The quantities measured in month and tenths of a month will be paid at the Contract 
rate per month. 
Payment will commence from the day that the Contractor commences a section of 
road  work  on  bridge  work  which  require  one  way  traffic  working  or  when  be 
constructs a diversion in accordance with Section 103. 
 
Payment will continue while such one way working or traffic diversions are in proper 
operation in accordance with the Contractor’s programme and to the satisfaction of 
the Engineer.  Payment will cease when no one way working or traffic diversions are 
in place.  The pay item shall be deemed to include for compliance with Section 103 
for as many locations that the Contractor is operating one way working or diversions 
for traffic at any one time whether this be one or several. 
 
No additional payment will be made for compliance with this clause. 
 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
103(1)  Provision  and  Maintenance  of 
Arrangements  for  traffic  during 
construction.  month. 
 

104. CONTROL OF WORKS 

104.1. Authority of the Engineer 
No change. 

 
Series 100 – General              Page no: 14 of 63 
SRI LANKA OPERATIONS CENTRE

104.2. Conformity with Plans and Specifications 
No change. 
 
Add sub‐clause 104.3 :‐ 
 

104.3. Standards 
 
When  materials  or  workmanship  are  required  by  these  Specifications  to  meet  or 
exceed specifically named codes or standards, it is the Contractor's responsibility to 
provide  such  specifically  named  codes  or  standards.    The  specified  codes  and 
standards  establish  the  quality  requirements  for  the  various  types  of  work  to  be 
performed and the methods for testing for determination that the required quality is 
achieved. 
 
All the codes of practice, standards and specifications applicable shall be the latest 
edition with all corrections and incorporations as on 30 days before the final date for 
submission of the bid. 
 
In the absence of any definite provisions in the specifications on any particular issue 
reference may be made to the latest codes of  ASTM and BS standards which ensure 
an  equal  or  higher  quality  than  the  standards  mentioned.  Where  even  these  are 
silent,  the  construction  and  completion  of  the  Works  and  relevant  tests  shall 
conform to sound engineering practice and, in case of any dispute arising out of the 
interpretation of the above, the decision of the Engineer shall be final and binding on 
the Contractor. 

104.4.  Health and Safety 
 
The Contractor shall in addition to complying with the specific requirements of the 
General Conditions and with the national standards of the Government of Sri Lanka 
in  respect  of  health  and  safety,  observe  and  maintain  standards,  towards  all of his 
employees, not less than those laid down by his own national standards or statutory 
regulations. 
 
He should take all reasonable steps including training and safety drill to ensure the 
safety of all persons on the site, whether in his employ or not. Safety is paramount. 
 
The  contractor  shall  provide  all  appropriate  protective  clothing  and  equipment  for 
the  work  to  be  done  and  ensure its proper use. Where required safety nets, belts, 
belts  harnesses  and  life  belts  and  rescue  boats  shall  be  provided.  All  safety  and 
rescue equipment shall be fully maintained and available for use at all times. 
 
The  contractor  shall  provide  and  maintain  in  prominent  and  well‐marked  positions 
all  necessary  first‐aid  equipment,  medical  supplies  and  other  facilities.  A  sufficient 
number  or  trained  personnel  shall  be  available  at  all  times  to  render  first  aid.  A 
suitably  equipped  room  shall  be  made  available  with  beds  and  stretchers  for 
emergency  medical  treatment,  and  a  planned  system  for  removal  to  hospital  for 
authorised persons requiring further treatment shall be provided by the contractor. 
 

 
Series 100 – General              Page no: 15 of 63 
SRI LANKA OPERATIONS CENTRE

The contractor shall report to the Engineer promptly and in writing particulars of any 
accident  or  unusual  or  unforeseen  the  occurrences  on  the  site,  whether  likely  to 
affect progress of the work or not. 
   
No  payment  would  be  made  for  services  under  this  clause  as  the  same  shall  be 
deemed to have been included in the general obligation of the Contractor. 

104.5.  Protection of Public Service Facilities  
 
Immediately on receipt of the notice to commence the works, the Contractor shall 
make  a  survey  to  identify  all  surface  and  under  ground  Electric/Telephone  poles, 
service  lines  viz  gas/fuel  pipe,  water  line,  survey  Bench  Marks  (BM)  and  other 
facilities  etc.  likely  to  impede/obstruct  his  works  and  shall  submit  a  survey  and 
chainage wise list of these obstructions to the Engineer.   
 
Any services affected by the Works shall be temporarily supported by the Contractor 
who  shall  also  take  all  measures  reasonably  required  by  the  various  bodies  to 
protect their services and property during the progress of the works. 
 
No separate payment shall be made for the survey, identification and any temporary 
support  or  protection  of  services,  as  it  will  be  deemed  to  be  under  the  general 
obligation of the Contractor.  
 
As  directed  by  the  Engineer,  the  Contractor  will  arrange  for  the  relocation  and/or 
removal of public services by the appropriate authority. 
 
Payment  for  any  charges  made  by  these  authorities  shall  be  made  as  shown  in 
Section‐203. 
 

104.6.  Safety Relating to Temporary Structures 
 
The contractor must submit complete design calculations plans and technical details 
of  all  proposed  temporary  structures  for  the  engineers  prior  approval  before  their 
construction  commences.  The  Engineers  approval  will  not  relieve  the contractor of 
any contractual liabilities. 
 
The  contractor  must  also  ensure  that  all  necessary  safety  regulations  and 
precautions  must  be  complied  with  during  the  erection,  use  and  dismantling  of 
temporary  structures  no  separate  payment  will  be  made  for  temporary  structures 
which  are  not  scheduled  in  the  Bill  of  Quantities.  They  will  have  been  deemed  to 
have been included in the rate items listed in the Bill of Quantities.      

104.7.  Safety Relating to Navigable Waterways 
 
The Contractor shall in addition to complying with the specific requirements of the 
General Conditions and with the national standards of the Government of Sri Lanka 
in respect of navigable waterways, shall comply with all orders and directions given 
by  the  Engineer  in  respect  of  the  safety  of  navigation  and  with  requirements  for 
marking watching and lighting any structure, craft or equipment which may be used 
in the construction of the works. 
 
Series 100 – General              Page no: 16 of 63 
SRI LANKA OPERATIONS CENTRE

 
The  contractor  shall  not  lay  down  or  provide  permanent  moorings  for  his  floating 
plant. The Contractor’s temporary moorings shall be positioned and installed to the 
approval  of  the  Engineer.  Prior  notification  of  their  installation  shall  be  officially 
given to all users of the waterway. 
 
Spoil  excavated  or  dredged  by  the  Contractor  shall  not  be  deposited  in  such 
locations as will infill or cause silting up of existing low water channels. 
 
The  Contractor  shall  without  delay  raise  and  remove  or  recover  any  material, 
construction  plant  (floating  or  otherwise)  or  vessel  belonging  to  or  hired  by  him 
which may be sunk stranded or gone adrift in the course of construction completion 
or maintenance of the works, or otherwise deal with the same as the Engineer may 
direct. 
 
The  Contractor  shall  take  all  necessary  precautions  and  measures  to  avoid 
interruption  of  service  of  the  existing  ferry  or  navigation  as  a  consequence  of  his 
temporary works or construction of the permanent works. 
   
No  payment  would  be  made  for  services  under  this  clause  as  the  same  shall  be 
deemed to have been included in the general obligation of the Contractor. 

104.8.  Environmental Requirement 
 
The  Contractor  shall  comply,  with  the  Environmental  Monitoring  guideline  in 
accordance  with  the  requirement  of  Statutes/Law  of  the  Government  of  Sri  Lanka 
and  International  standards.  In  respect  of  controlling  damage  to  the  environment 
and controlling pollution the Contractor shall be bound to follow the regulation/law 
of the Government of Sri Lanka and any statutory bodies or the requirement of such 
laws of his own home country whichever is more stringent 
 

(1)  Specific Environmental Concerns  
 
The specific environmental concerns are: 
 
• Emissions to air (dust, smoke etc.) 
• Emissions to land (solid and liquid domestic & industrial waste etc.) 
• Emission to water (dredge spoil, surface & foul water drainage etc.) 
• Noise and visual pollution 
 
These  are  now  discussed  one  by  one  while  it  will  be  indicated  to  which  particular 
contract they are applicable. 
 
(2) Emissions to air 
 
• Generation of dust 
 
The  spread  of  wind  blown  soil  particles  derived  from  unpaved  haulage  and  access 
roads, reclaimed areas and stockpiles of soil, and dust from rock handling may cause 

 
Series 100 – General              Page no: 17 of 63 
SRI LANKA OPERATIONS CENTRE

a problem during the dry season if strong winds prevail. Such dust may cause health 
risks for the labourers and for the population living nearby. 
 
As  part  of  his  obligation  to  minimise  disturbance  to  other  users.  The  Contractor  is 
required  to  water  unpaved  roads  under  dry  weather  conditions  and  impose  speed 
limits on access and haulage roads. 
 
The nature of a major earthworks operation inevitably gives rise to a dust nuisance 
the effects of which are to be minimized as far as practicable by watering and route 
and  speed  control  of  vehicles.  The  dust  nuisance  from  the  Contractor’s  crushing 
plant is to be controlled by the use of water sprays. 
 
• Air pollution 
 
Exhaust emissions caused by the use of vehicles, machinery and other engine driven 
equipment  used  by  the  contractors  should  not  exceed  the  exhaust  emission 
standards as set forward in the tables below. 
 

Emission standard values for Motor Vehicle Exhaust 
 
Parameters  Unit  Standard 
determinates  Value 
‐  Black smoke (1)  Hattridge Smoke Unit (HSU)  65(3) 
(2)
‐  CO   g/m3  24 
(2)
‐  hydrocarbon   percent volume  4(4) 
(2)
‐     NOx   g/m3  2 
ppm  180 
g/m3  2 
ppm  600 
 
(1) measured at two thirds of maximum rotating speed 
(2) whichever is lower out of two values expressed in two different units 
(3) For vehicles more than 5 years old, or that have completed 80,000 km the standard 
value is 75 HSU 
(4) Two and tree wheeler vehicles with engine displacement less than cm3 the standard 
value is 5 volume percentage. 
 

Emission standard values for Black Smoke Emission from boat/ship/vessel 
 
Parameters determinats  Unit  Standard 
Value 
‐ Black smoke (1)  Hattridge Smoke Unit (HSU)  65(3) 
   
(1) measured at two thirds of maximum rotating speed 
 
The ambient air quality in and around the work site should meet the standard values 
for  ambient  air  quality  described  in  the  following  table.  Regular  maintenance  of 
engines  and  equipment  is  considered  to  be  important  for  reducing  emission  and 
emissions.  
 
Series 100 – General              Page no: 18 of 63 
SRI LANKA OPERATIONS CENTRE

 
Ambient air quality standards for different categories of environments. 
 
  Concentration {μg/m3] 
Category of Environment  Suspended Particu SO2  CO  Nox 
Mater 
• industrial and mixed use   500  120  5000  100 
• commercial and mixed use  400  100  5000  100 
• residential and rural  200  80  2000  800 
• sensitive  100  30  1000  300 
   
 
The category of environment of the area surrounding the work site can be characterized as 
rural. For ambient air quality the standards for residential and rural areas should therefore 
be met.  
 
• Garbage separation 
 
- All chemical products must be collected separately from the “normal garbage 
- Used oil must be collected into “used oil” drums. 
- Used batteries must be collected in “used batteries” storage for recycling 
- Used oil fuel filters must be collected in a leakage free drum 
 
Garbage collecting system: The location of the garbage containers will be set out in the plan 
of the working area and camp area. The garbage from any vessels will be brought ashore. 
 
Garbage discharge: The garbage will be brought to a dedicated area approved for disposal 
by the Engineer. 
  
• Other environmental procedures: 
 
- Building/construction  material  must  be  ordered  from  the  stores  in  the  exact 
amounts needed, if possible in the right size, to minimize wastage. 
- All material must be stored in the correct way. 
- Leftover material (usable) must be re‐used or recycled. 
- Discharging or charging of chemicals shall take place above a “leakage bin” 
- Cleaning of tools (painting) shall take place in a bin, suitable for handling solvents. 
- Causing nuisance shall be kept to a minimum 
- The working area must be kept clean and tidy 
- Effective maintenance of equipment is demanded. 
 
(3)  Emission to water 
 
The Engineer is required to approve all work method associated with the excavating of soil 
below  water  level  and  subsequent  disposal.    Locations  for  disposal  of  soil  excavated  from 
below water level in order of preference are: 
 
(1) Disposal on land through hydraulic fill; 
(2) Disposal on char land if not occupied for agriculture; 
(3) Aquatic disposal into the deepest channels of the river. 
 
 
Series 100 – General              Page no: 19 of 63 
SRI LANKA OPERATIONS CENTRE

Unless approved otherwise, dredged material shall be deposited on land.  
 
• Land disposal 
 
‐ Test have revealed the presence of any toxic or polluting substance in the river bed 
material. 
‐ the  bunds  or  embankments  for  the  hydraulic  fill  are  to  be  of  such  quality  that  no 
spills or breaches occur, damaging neighboring land; 
‐ to  prevent  water  logging  of  agricultural  areas  in  the  flood  plains  surrounding 
hydraulic fill areas, drains shall be constructed around the embankments to evacuate 
water by gravity to the river; 
 
• Aquate disposal 
 
‐ The concentration of suspended sediment in the effluent from the excavation works, 
discharged into natural or existing water courses shall never exceed 4,000 ppm. 
‐ Disposal  of  dredged  material  shall  only  take  place  on  char  land  if  not  occupied  for 
agricultural purposes or in the major river channel minimizing the impact on riverine 
transport and on aquatic (organisms living in or at the river bottom); 
 
(4) Noise and visual pollution 
 
• Visual pollution 
 
The contractor shall ensure all temporary works are kept neat and tidy and the site 
cleaned regularly. 
     
• Noise pollution 
 
The Contractor, in planning his works must recognize the distinction between noise 
pollution as experienced by the villagers living around the works and noise hazards 
to the labour working on the construction sites 
 
In the case of villagers the main forms of noise pollution will be: 
 
- pile driving 
- crushing plant 
- generators 
- haulage and compaction equipment 
- earth and rock moving equipment is of consideration. 
 
These activities should be confined to day time operation and not after 10pm. 
In  the  case  of  Contractors  labour  the  impact  of  noise  pollution  on  operators  and 
adjacent personnel could be much more of a problem: 
 
  Ear  protectors  shall  be  used  in  any  environment  where  the  noise  may  exceed  the 
level of 80 dB (A). 
 
  Notice boards must be placed in areas where the noise exceeds this level and where 
ear protectors must be worn. Noise levels should be measured if any doubt exists. 
 
 
Series 100 – General              Page no: 20 of 63 
SRI LANKA OPERATIONS CENTRE

Spot  checks  shall  be  made  by  Engineer  with  the  assistance  of  Department  of 
Environment  to  verify  whether  ear  protectors  (a)  are  provided  by  the  various 
contractor and (b) are in fact used by the labour working in the noisy area. 
 
No payment will be made for services under this clause as the same shall be deemed 
to have been included in the general obligation of the Contractor. 

104.9.  Construction Programming 
 
The programme required by Clause‐13 of the General Conditions of Contract shall be 
updated  monthly,  unless  agreed  otherwise  with  the  Engineer,  and  shall  be  in  the 
form  of  a  bar  chart  and  time/location  chart,  covering  all  the  main  items  of  work, 
showing  their  interrelation  with  and  interdependence  on  other  items  of  work,  and 
be  laid  out  in  a  format  which  will  permit  progress  of  the  various  items  to  be 
indicated  on  it  throughout  the  execution  of  the  work.  It  shall  be  supported  by  a 
critical  path  network  in  form  capable  of  being  updated,  showing  all  requisite 
operations,  earliest  and  latest  start  and  finish  dates,  durations,  float  and  critical 
activities. 
 
The programme shall show inter alia: 
 
a)  The dates by which the contractor requires information from the Engineer in respect 
of further detailed Drawings or schedules. 
   
b)  The  dates  by  which  the  contractor  requires  instruction  from  the  Engineer  to  carry 
out work described in the contract as provisional sums.   
 
c)  The  dates  by  which  the  contractor  will  require  to  place  any  Nominated  Sub‐
contracts. 
 
d)  The delivery periods and dates of arrival on site of all major plant and materials and 
their relationship with the river regime. 
 
e)  The  dates  and  periods  during  which  the  contractor  will  require  to  enter  onto  sites 
allocated to other contracts in the execution of his works. 
 
f)  The  dates  and  periods  set  out  on  Drawings  and  described  more  fully  in  Volumes‐2 
and 3 of the Particular Specification.  
 
The  method  statement  required  in  accordance  with  Clause‐13  of  the  General 
Conditions of Contract shall include a list of major items of plant and equipment to 
be  used,  methods  of  movement  of  materials,  temporary  works  and  other  like 
mattress. 
 
The contractor must submit working drawings as necessary with programme details. 
No work should be carried out on the programme submitted without the Engineer’s 
prior  written  approval  should  the  contractor  carry  out  work  prior  to  the  Engineer 
approval the Engineer will have the right to withhold payment for such work. 
 
If  the  programme  is  to  be  revised  by  reason  of  the  Contractor  falling  behind  his 
programme, he shall produce a revised programme showing the modifications to the 
 
Series 100 – General              Page no: 21 of 63 
SRI LANKA OPERATIONS CENTRE

original programme necessary to ensure completion of the works or any part thereof 
within the time for completion as defined in Clause 13 of the Conditions of Contract 
or any extended time granted pursuant to Clause 43 of the Conditions of Contract.  
Any  proposal  to  increase  the  tempo  of  the  work  must  be  accompanied by positive 
steps to increase production by providing more labour and plant on Site, or by using 
the available labour and plant in a more efficient manner. 
 
Failure on the part of the Contractor to work according to the programme or revised 
programme, shall be sufficient reason for the Employer to take steps as provided for 
in the Conditions of Contract and shall be construed as not executing the Works in 
accordance with the Contract. 
 
The approval by the Engineer of any programme shall have no contractual significance 
other than that the Engineer would be satisfied if the work is carried out according to 
such  programme  and  that  the  Contractor  undertakes  to  carry  out  the  work  in 
accordance with the programme, nor shall it limit the right of the Engineer to instruct 
the Contractor to vary the programme should circumstances make this necessary.  The 
above shall not be taken to limit the right of the Contractor to claim for damages or 
extension  of  time  to  which  he  may  be  fairly  entitled  to  in  terms  of  the  General 
Conditions of Contract for delay or disruption of his activities. 
 
Should the Employer request and the Contractor undertake to finish the whole or part 
of  the  Works  ahead  of  the  time  originally  required  by  the  Contract,  payment  for 
accelerating  the  work  shall  only  be  made  if  agreed  to  beforehand  in  writing  and 
according to the terms of such agreement 
 
No  payment  would  be  made  for  services  under  this  clause  as  the  same  shall  be 
deemed to have been included in the general obligation of the Contractor. 

104.10. Progress Meetings  
 
Meeting  will  be  held  at  intervals  not  exceeding  one  month  between  the  Engineer 
and the contractor to discuss the progress of the works and any problems that may 
have arisen. The contractor shall give to the Engineer at these meetings details of his 
progress to date in relation to the programme.  
 
No  payment  would  be  made  for  services  under  this  clause  as  the  same  shall  be 
deemed to have been included in the general obligation of the Contractor. 

104.11. Returns and Reports  
 
At  monthly  intervals  the  contractor  shall,  in  accordance  with  his  obligations  under 
Clause 35 of the General Conditions of Contract, supply to the Engineer, returns of 
labour and constructional Plant and, in addition, a schedule of the main work items 
in  each  section  of  the  works  showing  progress  during  the  previous  week  and 
proposed progress for the coming week and total progress to date.  
 
At  monthly  intervals,  and  not  later  than  the  first  week  in  every  month,  the 
contractor  shall  submit  to  the  Engineer  a  progress  report  for  the  previous  month 
that shall include, but not be limited to the following: 
 
 
Series 100 – General              Page no: 22 of 63 
SRI LANKA OPERATIONS CENTRE

a)  a  programme  marked  up  with  any  agreed  amendments  and  showing  the 
actual percentage completion of each of the main items of work, in such a 
way  that  comparison  can  be  made  with  the  scheduled  percentage 
completion of each item. 
 
  b)  Weather and other conditions, including daily temperature range, humidity 
rainfall, wind speed and direction, river levels etc. 
 
c)  Summary of staff and labour employed on the site. 
 
  d)  Schedule  of  Constructional  Equipment  on  site  with  dates  of  arrival  and 
departure as appropriate including equipment operational condition.. 
   
  e)  Schedule of principal material items with dates of placing orders progress of 
manufacture, dates of delivery to site etc. 
 
f)  Record of site safety 
 
All  reports,  statements,  returns,  diagrams  or  drawings  etc.  which  the  contractor  is 
required  to  submit  to  the  Engineer  during  the  progress  of  the  works  shall  be 
furnished in quadruplicate unless otherwise directed. 
No  payment  would  be  made  for  services  under  this  clause  as  the  same  shall  be 
deemed to have been included in the general obligation of the Contractor. 

104.12. Telecommunications 
 
The  Contractor  shall  provide  and  maintain  telephone,  fax  and  e‐mail    and  mobile 
telephone  with  necessary  connections  and  facilities  in  the  site  office  during  the 
period of the construction and maintenance. The Contractor shall also maintain the 
telephone facilities and pay all bills for the whole period as stated above. 

104.13. Compaction – General 
 
Compaction  of  materials  shall  be  carried  out  in  layers  of  uniform  thickness  using 
approved compaction equipment including combinations thereof if required by the 
Engineer to achieve the specified compaction. 
 
Compaction  with  rollers  shall  commence  at  the  edges  and  progress  towards  the 
centre  except  in  super  elevated  and  other  stretches  of  unidirectional  cross‐fall, 
where the rolling shall commence at the lower edge and progress towards the upper 
edge.    When  commencing  rolling  from  an  edge,  rollers  shall  run  forward  and 
backward  along  the  edge  several  times  till  the  edge  strip  becomes  firm  to  provide 
lateral support.  The roller shall then move inwards parallel to the centre line of the 
road  in  successive  passes  with  the  tracks  made  by  successive  passes  overlapping.  
Rolling shall continue till the specified degree of compaction is achieved throughout.  
When rolling is terminated at an edge, the procedure similar to that for commencing 
rolling at an edge shall be adopted.  During rolling, the top of the layer being rolled 
shall  be  checked  for  levels  and  cross‐fall  and  any  irregularities  in  these  regards, 
corrected by scarifying the material in the affected area and by removing or adding 
materials and continuing with the rolling until the entire area being rolled has been 
brought to a state of uniform and desired compaction. 
 
Series 100 – General              Page no: 23 of 63 
SRI LANKA OPERATIONS CENTRE

104.14. Mixing & Control of Moisture Content Before Compaction 
 
Before  compaction  is commenced (other than for bituminous mixes), each layer of 
uncompacted  material  shall  be  brought  to  a  state  of  uniform  composition,  texture 
and  moisture  content  by  thorough  mixing  and  addition  of  water  or  drying  as 
required.  The Contractor shall be deemed to have taken account of the fact that the 
materials  encountered  may  vary  widely  with  respect  to  their  in‐situ  moisture 
contents and the moisture contents at which the materials are to be compacted as 
to be specified separately for each type of material.  Accordingly, the materials may 
have  to  be  wetted  by  adding  water  or  dried  to  the  required  degree,  along  with 
intimate mixing of the entire mass of the materials. 

104.15. Compaction Equipment 
 
Mechanical  equipment  shall  be  used  for  compacting  materials  by  rolling,  tamping 
and watering the materials (if needed) before compaction.  For other operation such 
as  spreading,  mixing  and  shaping,  manually  operated  tools  and  equipment  is 
preferred  on  mechanical  equipment  alone  or  a  combination  of  two  shall  be  used.  
The  choice  of  equipment  and  the  procedure  of  their  use  shall  be  subject  to  the 
approval  of  the  Engineer,  upon  his  being  satisfied  about  their  effectiveness  on  the 
basis of trial compactions. 
 
It shall be understood by the Contractor that different type of materials are likely to 
require  different  kind  of  compaction  equipment,  including  successive  applications 
thereof, for achieving the specified degrees of compaction and the Contractor shall 
keep  available  a  fleet  of  compaction  equipment  of  the  requisite  kinds,  sizes  and 
number. 
 
 
For  compacting  along  narrow  strips  e.g.  along  widening  of  pavements  and  in 
restricted  areas  e.g.  behind  bridge  abutments,  appropriate  sized  purpose  made 
compacting  equipment  will  be  required  and  the  same  shall  be  provided  by  the 
Contractor. 
 
All equipment shall be of modern construction by established manufacturers and of 
proven  efficiency  and  shall  be  operated  and  maintained  at  all  times  by  skilled 
personnel in a manner acceptable to the Engineer. 
 

104.16. Water and Power Supply Arrangements  
 
The Contractor shall 
 
a. provide at his own risk and cost all water, lighting and electric  power required for 
use in the works at such frequent locations as are necessary and shall pay all costs, 
fees  and  charges  in  connection  therewith  and  allow  all  sub‐contractors  free  use  of 
the  same.  The  Contractor  shall  make  his  own arrangement for his requirements of 
potable water, by 
 

 
Series 100 – General              Page no: 24 of 63 
SRI LANKA OPERATIONS CENTRE

b. provide and maintain temporary water storage together with any distribution piping 
which may be necessary and subsequently remove all installations to the approval of 
the Engineers. 
 
c. Provide, wire for, and connect lighting and power for the works. 
 
d. Provide  mechanically  driven  and  operated  water  bowsers  with  effective  spray 
equipment at all times to ensure that compaction can proceed without any hold up 
on account of watering. 
 

104.17. Drainage during Construction    
 
All embankment, sub‐grade, shoulder and pavement layers under construction shall 
be protected from any accumulation of water due to rains or other causes and from 
erosion due to flow of water. All such layers under construction shall be provided 
with cross fall to facilitate surface run‐off and, if necessary, the cross fall shall be 
supplemented with temporary drains to prevent accumulation of water. 
 

104.18. Prevention of Damages to Embankments, Sub‐grade Layers, Pavement Layers and 
Shoulders in Position. 
 
Excavations  for  new  constructions  and  placement  of  materials  and  their  in  situ 
processing and compaction for new construction shall be done in such a manner and 
with  such  precautions  as  not  to  cause  any  damage  to  embankments,  sub‐grade 
layers,  shoulders  and  pavement  layers  in  position  including  those  pre‐existing  and 
intended to form part of the improved road. 
 

104.19. Compaction Trials 
For  demonstrating  the  efficacy  of  mixing  and  compaction  equipment  and  the 
working  methods  proposed  to  be  used  by  the  Contractor  for  different  kinds  of 
materials,  the  Contractor  shall  carry  out  compaction  trials  before  full‐scale 
construction  on  the  road  and  during  construction  throughout  the  course  of  the 
contract as required by and in close cooperation with the Engineer.  Based on results 
of  compaction  trials  and  construction  observation,  the  Engineer  shall  reserve  the 
right to direct the use of particular mixing and compaction equipment and methods 
and  disallow  the  use  of  others  for  compacting  different  kinds  of  materials  in 
accordance with these specifications. 

104.20. Compaction Control 
 
After the compaction of each layer of material, field density tests shall be done on 
the  compacted  material.  For  locating  test  points,  successive  compaction  panels 
covering the entire area of work shall be designated in advance of compaction. The 
frequency of the tests (in terms of square metres of compacted area of each layer 
for which minimum one test is to be done) shall be separately specified for different 
kinds  of  material.  The  test  locations  shall  be  chosen  through  random  sampling 
techniques. 

 
Series 100 – General              Page no: 25 of 63 
SRI LANKA OPERATIONS CENTRE

 
  Acceptance of compaction by the Engineer shall be based on the mean value of 5 to 
10 determinations of field dry density. The mean dry density of a set of tests shall be 
equal  to  or  exceeding  the  specified  value  and  the  standard  deviation  shall  not 
exceed 4 percent of the mean dry density. If this is not satisfied the entire work to, 
which the set of density tests relates shall be treated as ‘non‐acceptable’. 
 
For  material  other  than  bituminous  mixes,  the  compaction  panels  in  which  the 
compaction  work  is  found  as  non‐acceptable  shall  be  given  re‐compaction 
accompanied  with  scarifying  and  wetting/drying  for  the  entire  thickness  of  the 
compacted  layer  to  achieve  the  specified  degree  of  compaction.  In  case  of 
bituminous mixes, the compaction panels in which the compaction work is found as 
non‐acceptable  shall  be  stripped  off  and  re‐laid  with  fresh  bituminous  mix  and  re‐
compacted. 

104.21. Dispersal of Hauling Equipment 
 
Hauling  equipment  bringing  materials  to  the  site  of  work  shall  be  dispersed 
uniformly  over  the  surface  of  the  previously  constructed  layers  in  order  to  avoid 
rutting and uneven compaction.  The materials from hauling equipment shall not be 
dumped in concentrated heaps but deposited as evenly distributed layers. 

104.22.  Protection to Newly Constructed Layers 
 
No  traffic  other  than  construction  traffic  shall  be  allowed  on  any  earthwork  or 
pavement layer until a surfacing has been applied either as single surface treatment 
or an asphalt concrete layer.  The approval of the Engineer shall be required before 
traffic is allowed to pass over newly constructed road.  Any defects caused by traffic 
passing  over  the  construction  layers  shall  be  remedied  in  accordance  with  these 
Specifications. 

104.23. Bridge Construction Sequence 
 
The  Contractor  shall  programme  the  construction  sequences  for  all  bridges  and 
submit  a  written  statement  thereof  for  the  approval  of  the  Engineer.    The  bridge 
construction  sequence  shall  consider,  as  a  minimum,  each  phase  of  bridge 
construction with respect to traffic control the effects on the existing bridges and the 
completed bridges.  Where the Contractor proposes to partially demolish an existing 
bridge  to  allow  for  phased  construction,  he  shall  demonstrate  to  the  Engineer’s 
approval  that  the  partially  demolished  bridge  is  safe  for  use  by  his  equipment  and 
other road users. 
 
The control of traffic during the construction of the bridge will be in accordance with 
the Specification, 103.  Where the bridge construction sequence has been specified 
on the Drawings, the Contractor shall follow the sequence specified.  The Contractor 
may propose an alternative construction sequence provided he can demonstrate, in 
a written statement, that the sequence is not detrimental to the Works or road users 
in any way. 
 

 
Series 100 – General              Page no: 26 of 63 
SRI LANKA OPERATIONS CENTRE

No work shall commence on a bridge until the written consent to the construction 
sequence  has  been  given  by  the  Engineer  in  compliance  with  clause  13  of  the 
General Conditions of Contract. 
 

104.24. Materials Testing by Independent Laboratories 
 
In addition to the Site testing facilities described Sub Section 130.8, the Contractor 
shall be responsible for arranging for the field and off‐Site laboratory tests indicated 
as  the  responsibility  of  the  Contractor  in  the  Specifications,  to  be  performed  by 
testing  laboratories  approved  by  the  Engineer.  The  Contractor  shall  be  responsible 
for  all  attendance  on  staff  from  these  approved  testing  laboratories,  including  if 
necessary the provision of transport for personnel, equipment and test specimens. 

104.25. Special and Additional Testing 
 
In addition to the testing described above, the Engineer may require further testing 
to  be  carried  out.  Such  special  and  additional  testing  shall  be  arranged  by  the 
Contractor under the direction of the Engineer. 

104.26.  Staff for Materials Testing 
 
The  Contractor  shall  provide  qualified  laboratory  engineers,  technicians,  assistants, 
labourers,  etc.  to  carry  out  sampling  and  testing  of  materials  in  accordance  with 
these Specifications. Laboratory staff shall be subject to the approval of the Engineer 
and be available to assist the Engineer with materials testing, as and when required. 

104.27. Codes and Standards 
 
All the codes of practice, standards and specifications applicable shall be the latest 
edition with all corrections and incorporations as on 30 (thirty) days before the final 
date for submission of the tender. The Contractor will supply two (2) copies of the 
codes of practices, standards, one to the Engineer and other to the Contractor’s use. 

104.28. Test Results and Records 
 
The  Contractor  shall  maintain  complete  records  of  test  results  which  may  be 
inspected by the Engineer at any time. All test results shall be recorded on standard 
forms  approved  by  the  Engineer  and  shall  be  countersigned  by  the  Engineer. 
Completed  forms  shall  clearly  show  the  locations  of  samples,  sampling  dates  and 
testing  dates.  Samples  shall  be  numbered  serially  at  the  time  of  sampling.  The 
Engineer  may  witness  any  sampling  or  testing  carried  out  in  the  laboratory.  The 
Contractor shall have the right to witness any sampling or testing carried out by the 
Engineer. On completion of the Contract the original copies of all test results shall be 
handed over to the Employer, via the Engineer. 

104.29. Measurement and Payment 
 
No  separate  payment  shall  be  made  for  compliance  items  under  this  section.  
Payment shall be deemed to be included in the contractor’s rates. 
 
Series 100 – General              Page no: 27 of 63 
SRI LANKA OPERATIONS CENTRE

105. CONTROL OF MATERIALS 

105.1. Sources of Supply and Quality Requirements 
Delete the text of sub‐clause 105.1 and substitute the following :‐ 
 
The  Contractor  shall  be  responsible  for  the  provision  of  all  materials  required  to 
construct the Works.  All material salvaged and/or removed from the works remains 
the property of the Government.  The Contractor shall be responsible for the cost of 
replacement in the event of unauthorised use or removal. 
 
The Contractor shall be responsible for opening up all quarries and borrow areas and 
shall organise his method of operations so that only materials of a type and quality 
approved by the Engineer shall be selected for use in the Works. 
 
The Contractor is at liberty to select and use material from his own sources providing 
the requirements of this section are fully met. 

105.2. Storage of Materials 
Delete the text of sub‐clause 105.2 and substitute the following :‐ 
 
Materials shall be stored  in such a manner as to ensure preservation of their specific 
quality and suitability for use in the Works. Stored materials shall be located so that 
they are readily available for use and can be easily inspected by the Engineer. Private 
property  shall  not  be  used  for  storage  purposes  without  the  written  permission  of 
the owner or lessee. 
 
Storage  sites  shall  be  free  of  vegetation  and  debris,  free  draining  and  if  necessary 
shall  be  elevated.  Material  placed  directly  on  the  ground  shall  not  be  used  in  the 
Works  unless  the  site  has  been  prepared  and  surfaced  with  a  10  (ten)  centimeter 
layer of sand or gravel to the satisfaction of the Engineer. 
 
Stockpiled material shall be stored in such a manner as to prevent segregation and 
excessive  moisture  content.  The  maximum  height  of  stockpiles  shall  be  limited  to 
five metres. 
 
Stockpiling  of  the  various  aggregates  to  be  used  for  asphalt  concrete,  bituminous 
surface  treatment,  penetration  macadam  or  concrete  will  be  permitted  only  in 
separate stockpiles for each nominal size of aggregate. These shall be separated to 
prevent mixing of materials. 
 
Aggregate  stockpiles  for  base  course  and  sub‐base  shall  be  protected  from  rain  to 
prevent saturation of the aggregates which would result in a reduction in the quality 
of the placed material or adversely affect the placement of the material. 
 

105.3. Handling of Materials 
No change. 

 
Series 100 – General              Page no: 28 of 63 
SRI LANKA OPERATIONS CENTRE

105.4. Approval of Sources of Material (Add the following) 
The  sources  of  the  materials  shall  be  selected  by  the  Contractor,  but  approved  by 
the  Engineer  before  the  materials  are  haulage  to  be  used  on  the  site.    For  this 
purpose,  the  Contractor  shall  furnish  all  relevant  test  data  for  representative 
samples  from  each  source  area  as  desired  by  the  Engineer  and  also  afford 
opportunities for the Engineer to visit the sources areas. 
 
Notwithstanding approval of sources of materials, materials as brought to the work 
site for use in the Works shall be subject to acceptance or rejection by the Engineer 
based on quality control tests to be performed before use in construction. 

105.5. Stockpiling of Materials (Add the following) 
 
All materials brought to the Site shall be stockpiled and stored carefully at approved 
locations  and  in  a  systematic  manner  so  as  to  prevent  deterioration  or  mixing  of 
different materials or contamination.  Materials which have suffered contamination 
or  deterioration  due  to  improper  storage  shall  not  be  used  in  Works  and  shall  be 
removed from the stock piling area. 
 
The materials shall be free from foreign, organic or any other deleterious substances 
such  as  vegetation  and  perishable  matters,  or  any  other  substance  which  in  the 
opinion of the Engineer may affect placing mixing and compaction of the material or 
adversely  affect  the  future  performance  of  the  Works.    Material  may  be  tested  in 
stockpiles by the Engineer to check suitability for use in the Works. 

105.6. Temporary Stockpiling of Materials (Add the following) 
 
Where the work programme is such that materials cannot be placed directly in their 
required  position  or  mixing  of  two  or  more  materials  is  required  to  meet  the 
requirements  of  the  Specification  for  a  material  the  Engineer  may  authorise  their 
removal  into  temporary  stockpiles.    Stockpile  sites  shall  be  to  the  Engineer’s 
approval and shall be prepared by clearing and grading followed by compaction. 
 
The material shall be stockpiled in successive layers of approved thickness over the 
full stockpile area to the approximate dimensions required by the Engineer and shall 
subsequently be reloaded and placed. 

105.7. Control Tests on Material During Construction (Add the following) 
 
The  Contractor  shall  use  only  such  materials  in  construction  as  conform  to  the 
requirements  regarding  composition,  grading,  physical  properties  and  engineering 
characteristics,  as  specified  for  different  kinds  of  materials.  For  this  purpose  pre‐
construction control tests shall be carried out on representative samples collected at 
random  of  materials  brought  to  construction  site  or  at  stockpiles  on  the  following 
scale.  The  Engineer  shall  have  the  authority  to  have  these  tests  at  more  frequent 
intervals where quality of a material is in doubt. 
 
Table 105‐7‐A   

 
Series 100 – General              Page no: 29 of 63 
SRI LANKA OPERATIONS CENTRE

Qty. of material for 
which minimum one 
Type of Material  Type of Test 
test or one set of  
test is to be done 
     
Ordinary fill for  Particle size analysis  4000 cu.m. 
embankment  Atterberg limits  4000 cu.m. 
  Moisture  density  4000 cu.m. 
relationship  4000 cu.m 
CBR  Test  (set  of  3 
specimens) 
Selected fill for  Particle size analysis  2000 cu.m. 
granular capping  Atterberg limits  2000 cu.m 
layer 
  Moisture  density  2000 cu.m. 
relationship 
  CBR  test  (set  of  3  2000 cu.m. 
specimens) 
Aggregates for  Particle size analysis   500 cu.m. 
granular sub‐base  Plasticity Index  2000 cu.m. 
  Moisture  density  2000 cu.m. 
relationship 
  CBR  Test  (set  of  3  2000 cu.m. 
specimens) 
  Los  Angeles  abrasion  2000 cu.m. 
test 
  Water Absorption  2000 cu.m. 
Aggregates for bit  Particle size analysis   250 cu.m. 
road base and  Plasticity Index  1000 cu.m. 
wearing course 
  Water absorption  1000 cu.m. 
  Los  Angeles  abrasion  1000 cu.m. 
test 
  Bulk specific gravity  1000 cu.m. 
  Flakiness index  1000 cu.m. 
 
Moisture content test before compaction of materials shall be carried out on a layer 
by layer basis for each compaction panel on the following scale: 
 
Table 105‐7‐B 
Area of layer under compaction for 
Type of Materials  which minimum one moisture 
content test is to be done 
   
Ordinary fill for embankment  1000 m2 
Granular capping layer  750 m2 
Aggregates for granular sub‐base  500 m2 
 
Moisture  content  test  shall  be  repeated  whenever  the  moisture  content  of  the 
material  changes  due  to  drying  or  wetting  or  if  there  be  uncertainty  (e.g.  due  to 
 
Series 100 – General              Page no: 30 of 63 
SRI LANKA OPERATIONS CENTRE

variability) in the results of earlier tests. 

105.8. Material Testing (Add the following) 
 
The  physical  properties  and  engineering  characteristics  of  the materials mentioned 
in  these  specifications  shall  be  established  through  appropriate  tests  on 
representative  samples  collected  in  such  manners  and  at  such  frequency  as 
described in Table‐105‐7‐A or as directed by the Engineer. The tests shall be carried 
out  in  accordance  with  test  methods  as  mentioned  in  these  specifications  or  as 
required by the Engineer. 
 
Moisture  density  relationship  tests  on  fill  materials,  sands,  soil‐sand  mixes  and 
aggregates of different kind shall be carried out (as per AASHTO:T180).  
 

105.9. Applicability of General Specifications (Add the following) 
 
These  General  Specifications  shall  apply  in  combinations  with  specifications  in 
particular  for  embankments,  pavement  layers  and  shoulders,  etc,  given  separately. 
In  case  of  any  conflict  between  the  General  Specifications  and  the  separate 
specifications given in particular, the provisions of the later shall govern. 
 

105.10. Payment (Add the following) 
 
No separate payment shall be made for items under this section.  Payment shall be 
deemed to be included in the Contractor’s rates. 

106. GENERAL RULES FOR MEASUREMENT AND PAYMENT 
 
Add the following :‐ 
 
Unless  stated  to  the  contrary,  any  thickness,  area  or  volume  in  any  items  of  the 
Works shall be measured only on finished work after compaction. 
 
The  payments  for  the  various  items  shown  in  the  Bill  of Quantities shall constitute 
full compensation for performing all of the requirements of the Contract for the item 
of  work  as  specified  including  furnishing  all  necessary  materials,  labour,  tools, 
equipment, supplies, testing, and incidentals. 
 
The  Contractor  shall  be  deemed  to  have  complied  with  the  requirements  of  Bill  of 
Quantities,  Contract  Rates,  Pay  Items,  Material  at  site,  Provisional  Sums,  as  listed 
below.  Contractor  should  also  fulfil  with  the  requirement  of  General  Conditions  of 
Contract clause 12 Sufficiency of Tender. 
 
Bill of Quantities 
 
The quantities set out in the Bill of Quantities are estimated quantities and are used 
for  the  comparison  of  Tenders  and  awarding  the  Contract.    It  must  be  clearly 
understood that only the actual quantities of work done or materials supplied will be 

 
Series 100 – General              Page no: 31 of 63 
SRI LANKA OPERATIONS CENTRE

measured for payment, and that the billed quantities may be increased or decreased 
as provided for by the General Conditions of Contract. 
 
Contract Rates 
 
In  computing  the  final  contract  amount,  payments  shall  be  based  on  actual 
quantities only of authorised work done in accordance with the Specifications and/or 
Drawings.    The tendered rates shall apply, subject to the provisions of the General 
Conditions of Contract, irrespective of whether the actual quantities are more or less 
than the billed quantities. 
 
The Contractor shall accept the payment provided in the Contract and represented 
by  the  prices  tendered  by  him  in  the  Bill  of  Quantities,  as  payment  in  full  for 
executing  and  completing  the  work  as  specified,  for  procuring  and  furnishing  all 
materials,  labour,  supervision,  plant,  tools  and  equipment,  for  wastage,  transport, 
loading  and  offloading,  handling,  maintenance,  temporary  work,  testing,  quality 
control  including  process  control,  overheads,  profit,  risk  and  other  obligations  and 
for all other incidentals necessary for the completion of the work and maintenance 
during the Period of Maintenance. 
 
This Clause shall be applicable in full to all pay items except as these requirements 
may be specifically amended in each case. 
 
In particular the Contractor shall be deemed to have included time related and fixed 
costs as specified in sub section108 under the appropriate items in the General and 
Preliminary section of the Bill of Quantities and not in rates for work items. 
 
Pay Items 
 
The  descriptions  under  the  pay  items  in  the  various  sections  of  the  Specifications, 
indicating the work to be allowed for in the tendered prices for such pay items, are 
for  the  guidance  of  the  Contractor  and  do  not  necessarily  repeat  all  the  details  of 
work and materials required by and described in the Specifications. 
 
These  descriptions  shall  be  read  in  conjunction  with  the  relevant  Specifications 
and/or Drawings and the Contractor shall, when tendering, allow for his prices to be 
inclusive as indicated above. 
 
Materials on Site 
 
No payment will be made in any Certificate for any materials on site until such time 
as they have been incorporated in the permanent works and approved. 
 
Provisional Sums 
 
The  Bill  of  Quantities  may  contain  certain  Provisional  Sums  so  designated  and 
entered  as  a  preliminary  allowance  to  cover  the  cost  of  work,  materials,  goods  or 
services to be provided by the Contractor and which have not been fully specified or 
measured  or  to  cover  the  cost  of  unforeseen  items  of  work  or  contingent 
expenditure.    Work  done  under  a  Provisional  Sum  shall  only  be  executed  upon  a 
written order by the Engineer which order shall also specify the method of payment.   
 
Series 100 – General              Page no: 32 of 63 
SRI LANKA OPERATIONS CENTRE

 
The Contractor shall furnish to the Engineer such receipts or other vouchers as may be 
necessary  to  prove  the  amounts  paid and, before ordering materials, shall submit to 
the Engineer quotations for the same for his approval. In respect of such of the works 
executed  on  a  day  works  basis,  the  Contractor  shall,  during  the  continuance  of  such 
work, deliver each day to the Engineer an exact list of the names, occupation and time 
of all workmen employed on such work and a statement showing the description and 
quantity  of  all  materials  and  equipment  used  other  than  the  Contractors  equipment 
which  is  included  in  the  percentage  addition  in  accordance  with  such  day  work 
schedule.  Each  list  and  statement  will,  if  correct,  or  when  agreed,  be  signed  by  the 
Engineer and a copy returned to the Contractor. 
 
The Contractor shall not be entitled to any payment unless such lists and statements 
have  been  fully  and  punctually  provided.  Where  the  Engineer  considers  that  for  any 
reason the provision of such lists was impracticable he shall nevertheless be entitled to 
authorise payment for such work provided that, such work or value thereof shall, in his 
opinion, be fair and reasonable 

106.1. Overhaul 
No overhaul on materials shall be measured or paid.  The cost of haulage is deemed 
to  be  included  in  tendered  rates  for  supply  of  materials  in  accordance  with 
Conditions of Contract Clause No. 12 

106.2 Measurement of Pavement for Area and Volume Based Payment 

a. Area Basis 
Add the following paragraph: 
 
Dimensions used to determine area shall be measured horizontally. 

b. Volume Basis 
No change. 

106.3 Scope of Rates for Different Items of Work 
No change. 

106.4 Facilities for Verification of Measurements 
No change. 

106.5 Selection of Pay Items 
No change. 

106.6 Sub Divisions Within Pay Items 
No change. 

106.7 Substantial Completion of the Works (Add the following) 
 
The  Contractor  shall  note  that  the  Engineer  reserves  the  right  not  to  certify  the 
Works to be "substantially completed" as required by the General Conditions of the 

 
Series 100 – General              Page no: 33 of 63 
SRI LANKA OPERATIONS CENTRE

Contract, unless the following portions of the Works are completed according to the 
Specifications: 
 
(a)  all  bituminous  seal  works  or,  where  a  seal  is  not  included,  the  uppermost 
gravel layer. 
 
(b)  all  drains  and  drainage  structures,  for  the  construction  of  which  timeous 
instructions were given by the Engineer. 
 
(c)  finishing of all support or retaining structures. 
 
Opening  of  individual  sections  or  lots  shall  not  entitle  the  Contractor  to  receive  a 
Completion Certificate unless the sections are separately identified in the contract or 
qualifies otherwise in terms of Clause 46 of the Conditions of Contract. 
 

107. SIEVE DESIGNATIONS 
 
No changes to Standard Specifications. 

108. CONTRACTOR’S ESTABLISHMENT ON SITE 

108.1. Office, Equipment Testing Facilities etc. 
 
It  is  the  Contractor’s  responsibility  to  acquire  land  for  the  siting  of  all  his  offices, 
accommodation, stores, testing facilities, equipment yards and workshops and for all 
temporary  works  and  for  the  reinstatement  of  such  land  on  completion  of  the 
Contract to the satisfaction of the owners.  The Contractor shall obtain the approval 
of  the  Engineer  to  the  siting  of  offices,  accommodation,  stores,  testing  facilities 
equipment yards and workshops before such land is acquired and he shall indemnify 
the  Employer  against  all  claims  and  charges  in  respect  of  the  occupation,  use  and 
reinstatement of the land. 
 
The  Contractor  is  solely  responsible  for  the  satisfactory  accommodation  of  all  his 
employees and for complying with all regulations and requirements in this respect. 

108.2. Legal relations and Responsibility to the Public 
 
The  Contractor  shall  take  the  steps  necessary  to  comply  with  the  terms  of  the 
Conditions  of  Contract,  particularly  in  respect  of  the  insurances  and  indemnities 
required, and he shall comply with all regulations of statutory authorities. 

108.3. Measurement 
 
The Contractor’s Site Establishment shall be measured under three items :‐ 
 
(a)  as  a  lump  sum  for  Establishing  of  all  the  facilities  on  or  adjacent  to  the 
Site that the Contractor deems necessary for fulfilment of all his obligations 
under  the  Contract.    These  facilities  shall  include  but  not  be  limited  to: 
Transport  of  plant,  buildings,  temporary  facilities  to  the  site,  Provision  and 

 
Series 100 – General              Page no: 34 of 63 
SRI LANKA OPERATIONS CENTRE

erection  of  temporary  buildings,  office  facilities  on  the  site,  Provision  of 
access  roads,  hard  standings  etc.  within  construction  camps,  Airfares, 
temporary  accommodation  during  the  mobilisation  phase,  permits,  bonds 
etc.  necessary  to  establish  expatriate  supervisory  personnel  upon  the  site, 
Establishment of testing and process control facilities on the site, Erection of 
contract  signboards,  Provision  of  transportation  facilities  for  supervisory, 
administrative and technical personnel, Provision of housing for supervisory, 
administrative and technical personnel. 
 
The  Contractor’s  price  for  the  lump  sum  shall  be  a  true  reflection  of  the 
Contractor’s  costs  taking  into  account  the  Advanced  Payment  and  the 
Contractor shall provide a breakdown of the lump sum with proof of actual 
costs to justify the lump sum price to the Engineer. Payment for mobilisation 
shall be made when the Contractor has established himself upon the site to 
the satisfaction of the Engineer.  
 
(b)  by  month  or  weeks  for  maintaining  the  Contractor’s  Site  Establishment 
for as long as necessary to execute and complete the Works.  The monthly 
rate for maintaining the facilities shall be deemed to include for but not be 
limited to: Salaries, leave fares, gratuities and miscellaneous entitlements of 
supervisory  personnel,  technical  personnel,  surveyors,  administrative 
personnel,  security  personnel,  store  men  etc,  Maintenance  of  offices, 
buildings,  laboratories  and  transportation  facilities  for  administrative, 
supervisory  and  technical  personnel,  Communications,  Maintenance  of 
housing for administrative, supervisory and technical personnel, Overheads 
off  site,  Financing  charges,  Compliance  with  the  provisions  of  the  contract 
whether specified or implied. 
   
This  item  shall  not  include  for  maintenance  or  depreciation  of  plant,    the 
cost of which shall be deemed to be included in the relevant work item. 
 
 
(c) Payment for demobilisation shall be compensation in full for the costs of 
removing  plant,  equipment,  facilities  and  personnel  from  the  site and shall 
include  (but  not  necessarily  be  limited  to):Transport  of  plant,  buildings, 
temporary  facilities  from  the  site  and  export  if  required,  Dismantling  and 
removal  of  all  temporary  facilities  on  the  site,  Airfares  for  repatriation  of 
expatriate  personnel,  Removal  of  contract  sign  boards,  Restoration  of  all 
construction camp areas to a satisfactory condition. 
 

108.4. Payment 
  Item                Unit 
  108(1)    Mobilisation          Lump Sum 
 
108(2)    Maintenance of the Contractor's  
      Establishment          Month 
     
  108(3)    Demobilisation        Lump Sum 
 

 
Series 100 – General              Page no: 35 of 63 
SRI LANKA OPERATIONS CENTRE

109. INFORMATION FURNISHED BY THE EMPLOYER 
 
Certain  information  contained  in these Contract documents or provided separately 
prior  to  Tender  by  the  Employer  is  being  offered  in  good  faith  but  the  type  of 
information supplied, no guarantee can be given that any or all of the information is 
correct or representative of the actual conditions. 
 
The Employer accepts no liability for the correctness or otherwise of the information 
supplied  or  for  the  resulting  damages,  whether  direct  or  consequential,  should  it 
prove during the course of the Contract that the information supplied is either not 
correct  or  not  representative.    Any  reliance  which  the  Contractor  places  on  this 
information  shall  be  at  his  own  risk  and  the  Contractor  shall  be  deemed  to  have 
checked the correctness of the information prior to submission of his Tender. 

110. WORKMANSHIP AND QUALITY CONTROL 
 
The  Contractor  in  responsible  for  producing  work  which  conforms  in  quality  and 
accuracy of detail to the requirements of the Contract see such clause 6 of General 
Conditions  of  Contract  and  the  Contractor  shall,  at  his  own  expense,  institute  a 
quality  control  system  and  provide  experienced  engineers,  foremen,  surveyors, 
materials  technicians,  other  technicians  and  other  technical  staff,  together  with  all 
transport, instruments and equipment, to ensure adequate supervision and quality 
control of the Works at all times. 
 
The  cost  of  all supervision and quality control, including testing, carried out by the 
Contractor  shall  be  deemed  to  be  included  in  the  rates  tendered  for  the  related 
items of work, except where as specifically provided for in the Contract. 
 
The Contractor’s attention is drawn to the provisions of the various sections of the 
Specifications regarding the minimum frequency of testing that will be required for 
quality  control.    The  Contractor  shall,  at  his  own  initiative,  increase  this  frequency 
where necessary to ensure adequate control. 
 
On  completion  of  every  part  of  the  Works  and  submission  to  the  Engineer  for 
examination, the Contractor shall submit to the Engineer the results of all relevant 
tests  and  survey  checks  that  he  has  carried  out  indicating  compliance  with  the 
Specifications. 
 
For  cement,  bitumen,  mild  steel  deformed  bars,  high  tensile  steel,  pre‐stressing 
materials,  bearings,  and  similar  other  materials  the  Contractor  shall  furnish  the 
manufactures  test  certificates  to  the  Engineer.    When  required  by  the  Engineer  to 
carry  out  some  essential  tests  at  the  manufactures’  plants  or  at  laboratories  other 
than the site laboratory, the cost of samples, sampling, testing and furnishing of test 
certificates shall be borne by the Contractor.  
 
The method of sampling and testing of materials shall be as required under relevant 
clauses stipulated in these Specifications or as approved by the Engineer. 
 
The Contractor shall be required to demonstrate the adequacy of the equipment for 
each  operation  to  establish  its  their  capability  to  achieve  the  requirements  to  the 
Specification to the satisfaction of the Engineer before commencement of the work. 
 
Series 100 – General              Page no: 36 of 63 
SRI LANKA OPERATIONS CENTRE

 
All  equipment  provided  shall  be  of  proven  efficiency  and  purpose  made  for  the 
required operation and shall be operated by skilled operators and maintained at all 
times to perform its proper function in a manner acceptable to the Engineer. 
 
No  equipment  or  personnel  will  be  removed  from  Site  without  Consult  of  the 
Engineer [see sub‐clause 49(1) of General Conditions of Contract]. 
 

111. SELECTION OF LABOUR 
 
The  Contractor  will  be  expected  to  maximise  the  use  of  labour  for  all  operations 
where it can be effectively used to attain the required standards. The Contractor is 
expected to show number of Labourers used each month including participation of 
female worker if appropriate in specific project area in the form shown below: 
 
Month  Work Days Generated  Number of Labourers 
Male  Female  Total  Male  Female  Total 
             
 
Initiation  of  Equal  participation  of  women  for  the  work  shall  be  encouraged.  To 
achieve this, the Contractor is expected to select the labour force by lottery for the 
local  community  as  much  as  possible  if  the  skilled  people  are  available.  Prior  to 
recruiting  the  labour,  the  Contractor  should  inform  the  people  in  the  surrounding 
area at least 5 days before the selection takes place by announcing through a public 
announcement  system  and  by  displaying  posters  in  public  places  of  the  target 
villages (Any person within than 3 km of the work site). All participants of the lottery 
will be registered as per their identification card. Two parallel draws will be arranged 
for  men  and  women  separately,  so  that  equal  numbers  of  men  and  women  are 
selected. The Contractor can select more people than he needs, keeping them in a 
reserve list, to allow for changes in the attendance. A new lottery should take place 
if the work proceeds for more than two months. 
 
No Child labour shall be selected for the works; the age limitation of the child shall 
be in accordance to Sri Lankan Labour standard. 
 
The Contractor is responsible for training the labourers. 
 

112. WORK EXECUTED BY THE EMPLOYER OR OTHER CONTRACTORS 
 
The  Employer  reserves  the  right  to  execute,  on  the  Site,  works  not  included  in  the 
Contract  and  to  employ  for  this  purpose  either  his  own  employees  or  other 
contractors (see clause 31 of the General Conditions of Contract) 
 
The  Contractor  shall  ensure  that  neither  his  own  operations  nor  the  actions  of  his 
employees shall interfere with the operations of the Employer or his contractors on 
such  works  and  the  same  obligations  shall  be  imposed  on  the  Employer  or 
contractors in respect of work being executed under the Contract. 
 

 
Series 100 – General              Page no: 37 of 63 
SRI LANKA OPERATIONS CENTRE

The  Contractor  shall  provide  unhindered  access  to  all  parts  of  the  Site  to  the 
Employer and authorised representatives of the Employer and of public bodies and 
corporations  and  to  contractors  employed  by  the  Employer  and  he  shall  make 
available  to  such  authorised  persons  the  use  of  all  temporary  access  tracks  in  or 
about the Site. 

113. PROTECTION OF PUBLIC SERVICE FACILITIES 
 
Any work involved in moving and reinstating existing services that may be affected 
by the construction of the Works shall be undertaken by the appropriate statutory 
authority. 

113.1. Existing Services 
 
The  Contractor  may  be  ordered  to  carry  out  certain  works  for  and  on  behalf  of 
various  statutory  service  authorities  and  he  shall  also  provide,  with  the  prior 
approval  of  the  Engineer,  such  assistance  to  the  various  bodies  as,  may  be 
authorised by the Engineer. 
 
No removal of or alterations to any public utility shall be carried out unless ordered 
by the Engineer. 
 
The  Contractor  shall  take  all  reasonable  precautions  to  protect,  and  shall  provide 
temporary support to, existing services during construction and during relocation of 
such services. 
 
Whenever services are encountered that interferes with the execution of the works 
and requires moving or relocation, the Contractor shall advise the Engineer who will 
determine the extent of the work involved. 
 
Any pipe, cable, conduit or other known service of any nature whatsoever, which has 
been  damaged  as  a  result  of  the  Contractor’s  operations  shall  be  repaired  and 
reinstated  forthwith  by  the  Contractor  or  by  the  authority  concerned,  all  at  the 
expense of the Contractor and to the satisfaction of the Engineer. 
 
The Employer will not be held liable or responsible for any delay in completion of the 
Works  under  this  Contract  which  may  occur  due  to  any  damage  occurring  to  such 
services in consequence of the Contractor’s operations. 

113.2. Payment 
 
The  work  of  temporarily  supporting  and  protecting  public  utility  services  during 
execution of the Works shall be deemed to be included in the Contractor’s rates and 
prices and no extra payment shall be made for the same. 
 
The  Engineer  may  instruct  the  Contractor  to  assist  in  the  demolition  and/or 
rebuilding  of  property  within  or  outside  the  ROW.    The  amount  of  work  involved 
shall be determined on Site and as instructed by the Engineer. 
 
Payment for such work shall be made under a Provisional Sum and shall be based on 
the Special Schedule of Rates for such work in force at the time. 
 
Series 100 – General              Page no: 38 of 63 
SRI LANKA OPERATIONS CENTRE

 
 
The Pay Item shall be :‐ 
 
Item No  Description  Pay Unit 
 
113.1   Demolition/Rebuilding of Property   Prov. Sum 

114. MAINTENANCE OF EXISTING ROADS 

114.1. General Obligations 
 
The  Contractor  shall  take  all  reasonable  steps  to  minimise  nuisance  during  the 
construction of the works (see clause 22 of General Conditions of Contract). 
 
All existing highway and roads used by vehicles of the Contractor or any of his sub‐
contractors or suppliers of materials or plant, and similarly any new roads which are 
part of the Works and which are being used by traffic, shall be kept clean and clear 
of  all  dust/mud/extraneous  materials  dropped  by  the  said  vehicles  or  their  tyres.  
Similarly,  all  dust/mud/extraneous  materials  from  the  Works  spreading  on  these 
highways shall be immediately cleared by the Contractor. 
 
Clearance shall be affected immediately by manual sweeping and removal of debris, 
or, if directed by the Engineer, by mechanical sweeping and clearing equipment, and 
all  dust,  mud  and  other  debris  shall  be  removed  entirely  from  the  road  surface.  
Additionally,  if  so  directed  by  the  Engineer,  the  road  surface  shall  be  hosed  or 
watered using suitable equipment. 
 
Any  structural  damage  caused  to  the  existing  roads  by  the  Contractor’s 
constructional plant or equipment shall be made good at Contractor’s expense. 
 

114.2. Payment 
 
All these activities shall be deemed to be the included in the Contractor’s rates and 
prices and no separate payment will be made therefore. 
 

115. PROTECTION  OF  THE  WORKS  AND  REQUIREMENTS  TO  BE  MET  BEFORE 
CONSTRUCTION OF NEW WORK ON TOP OF COMPLETED WORK IS COMMENCED 
 
The  general  obligations  of  the  Contractor  in  terms  of  the  Conditions  of  Contract 
“Care of the Works” shall include, inter alia, the following :‐ 
 
i) The provision of temporary drainage works such as drains, open channels, banks 
etc.  and  the  furnishing  and  operation  of  temporary  pumps  and  such  other 
equipment  as  may  be  necessary  to  adequately  drain,  protect  and  dewater  the 
Works and Temporary Works.  This will be in addition to any permanent drainage 
works  specified  and  installed,  and  in  addition  to  any  temporary  drainage  works 
specifically paid for separately. 

 
Series 100 – General              Page no: 39 of 63 
SRI LANKA OPERATIONS CENTRE

 
ii) Care shall be exercised not to allow material in borrow pits to become excessively 
wet, to keep all completed layers properly drained, to avoid dumps of material on 
completed layer work that shall inhibit surface drainage or form wet spots under 
and around dumps, and to protect all parts of the Works against erosion by floods 
and rain. 
 
iii) Material  shall  not  be  spread  on  a  layer  that  is  so  wet  that  damage  could  be 
caused  to  the  layer  during  compaction  of  a  subsequent  layer  when  the  road  is 
open to traffic 
 
iv) When material is spread out on the road, it shall, during wet periods, be given a 
good cross fall and a light compaction on the surface with a steel‐wheeled roller, 
in order to facilitate run‐off during rainy weather. 
 
v) Fill  and  cut  slopes  shall  be  promptly  repaired  whenever  damaged  by  surface 
water. 
 
vi) Excavations for pipe drains, culverts, service ducts and similar structures shall be 
adequately protected against possible ingress of water during rainstorms 
 
vii) All  completed  layer  work shall be protected and maintained until the following 
layer  is  applied.    Maintenance  shall  include  immediate  repair  of  any  damage  or 
defects which may occur and shall be repeated as often as necessary to keep the 
layer in tact and in good condition. 
 
viii) Before  any  completed  layer  is  primed  or  a  following  layer  is  constructed 
thereon, any damage to the existing layer shall be repaired in a manner approved 
by  the  Engineer,  so  that  after  repair,  or  reconstruction  if  necessary,  it  will 
conform  in  all  respects  to  the  requirements  specified  for  that  layer.    All  repair 
work shall be submitted to the Engineer for inspection before covering up. 
 
ix) The  Contractor  shall  inform  the  Engineer  of  damage  or  defects  to  any  work 
before  repair  or  maintenance  and  the  Engineer  shall  instruct  the  extent  and 
method of repair.  The previously constructed layer shall be thoroughly cleaned 
of  all  foreign  material  and  the  Contractor  shall  request  its  inspection  by  the 
Engineer before construction of the following layer or application of a prime coat, 
surfacing  or  surface  treatment.    In  the  case  of  all  bituminous  work  in  particular 
the  existing  layer  shall  be  thoroughly  broomed  and  all  dung,  clay,  and  other 
deleterious material completely removed.  Where necessary the surface shall be 
sprayed  with  water  before,  during  and  after  brooming  to  remove  all  foreign 
material. 

115.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 
 

 
Series 100 – General              Page no: 40 of 63 
SRI LANKA OPERATIONS CENTRE

116. REMEDIAL WORK 
 
When upon examination by the Engineer any part of the Works or any plant fails to 
conform to the Specification requirements, or is at any stage before final acceptance 
damaged so that it no longer conforms to the requirements of the Specifications, the 
Engineer  shall  instruct  its  complete  removal  and  replacement,  at  the  Contractor’s 
expense, with satisfactory work, plant or material.  In special cases the Engineer may 
instruct the Contractor to apply remedial measures in order to make good any such 
defects  or  damage.    The  actual  remedial  measures  taken  shall  be  entirely  at  the 
Contractor’s  own  cost  but  subject  to  the  Engineer’s  approval  regarding  the  details 
thereof. 
 
In  particular  remedial  measures  shall  ensure  that  the  final  product  is  in  full 
compliance with the Specifications, shall not endanger or damage any other part of 
the  Works  and  shall  be  carefully  controlled  and  submitted  to  the  Engineer  for 
examination when completed or at any intermediate stage as may be required. 
For the guidance of the Contractor an indication about what may be required in the 
more common cases of defects or damage is given below, but the Engineer will in no 
way  be  bound  to  approve  of  or  adhere  to  the  measures  indicated,  as  the  actual 
remedial measures will be dictated by the circumstances of each particular case. 

116.1. Earthworks 
 
i) Where a cut slope has been over‐excavated, reinstatement by backfilling will not 
normally be permitted and the entire slope may need to be re‐trimmed to obtain 
a uniform slope 
ii) Where  the  floor  of  a  cutting  has  been  over  excavated  it  will  normally  require 
backfilling and re‐compaction with approved material of higher quality then the 
cut  material.    All  necessary  measures  shall  be  taken  to  drain  ground  water  that 
may accumulate in backfilled sections. 
iii) Excess widths of fills will need to be trimmed to the design profile. 
iv) Where  erosion has occurred on the surface of cuts or fills, the damage shall be 
made good by backfilling with suitable material and re‐trimming.  In more serious 
cases  the  slope  may  have  to  be  cut  back  and  backfilled  after  benching  and 
compacted  to  the  required  standard  of  compaction  with  suitable  small 
equipment followed by re‐trimming. 

116.2. Local Defects in Pavement Layers 
 
i) Where  remedial  measures  are  taken  to  make  good  localised  defects  the  length 
and  width  of  the  area  to  be  repaired  by  equipment  shall  be  such  as  to 
accommodate the full width of the equipment used and of a reasonable length to 
ensure effective repair. 
 
ii) The depth to which material will have to be removed will depend on the defect 
and the type of material.  Gravel layers will need to be broken up to a depth of at 
least 75mm and crushed stone will usually need breaking up over its full depth.  
Asphalt material will normally require removal for its full depth. 

 
Series 100 – General              Page no: 41 of 63 
SRI LANKA OPERATIONS CENTRE

116.3. Concrete 
 
Defective concrete work will normally need the cutting back and complete removal 
of  any  weak  or  honey‐combed  sections  and  making  good  using  approved  bonding 
agents to bind fresh concrete to old concrete.  Cracks, of permitted to remain, shall 
be  injected  with  approved  compounds  and  test  cores  drilled  to test the efficacy of 
the injection process. 
 

116.4. Payment 
 
The Contractor shall undertake remedial work at his own expense. 

117. WATER SUPPLY ARRANGEMENTS 
 
The  Contractor  shall  make  his  own  arrangements  for  the  procurement, 
transportation,  storage,  distribution  and  application  of  water  needed  for 
construction and other purposes except where otherwise specified.  
 
Only clean water free from undesirable concentrations of deleterious salts and other 
materials shall be used.  All sources of water used shall be approved by the Engineer. 
 
The Contractor shall ensure that sufficient supply of water is at all times available to 
ensure that sufficient supply of water is at all times available to ensure continuity of 
work. 

117.1. Payment  
 
No direct payment shall be made for providing water and the cost thereof shall be 
included  in  the  rates  tendered  for  the  various  items  of  work  for  which  water  is 
needed. 

118. ELECTRCITY SUPPLY 
 
The  Contractor  shall  provide  and  maintain  at  his  own  expense  his  own  electrical 
supply  and  shall  provide  and  maintain  all  temporary  power  and  lighting  and  all 
associated  apparatus  for  the  duration  of  the  Contract  at  his  own  expense.  Once 
equipment  becomes  redundant,  and  having  received  the  approval  from  the 
Engineer,  the  Contractor  shall  disconnect  and  remove  said  equipment  and  make 
good any works disturbed at his own expense. 

118.1. Payment  
 
No direct payment shall be made for providing electricity supply and the cost thereof 
shall  be  included  in  the  rates  tendered  for  the  various  items  of  work  for  which 
electricity is needed. 

119. PAYMENTS & TOLERENCES 
 

 
Series 100 – General              Page no: 42 of 63 
SRI LANKA OPERATIONS CENTRE

The work specified in the various sections of these Specifications shall comply with 
the  various  dimensional  and  other  tolerances  specified  in  each  case.    Where  no 
tolerances  are  specified,  the  standard  of  workmanship  shall  be  in  accordance  with 
normal good practice.  
 
Where  the  work  is  not  constructed  in  accordance  with  the  "authorised"  dimensions, 
plus  or  minus  any  tolerances  allowed,  the  engineer  may  nevertheless  in  his  sole 
discretion  accept  the  work  for  payment.    In  such  cases  no  payment  will  be  made  in 
respect  of  quantities  of  work  or  material  in  excess  of  those  calculated  from  the 
"authorised"  dimensions  and  where  the  actual  dimensions  are  less  than  the 
"authorised" dimensions, minus any tolerance allowed, quantities for payment shall be 
based on the actual dimensions as constructed. 

119.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

120. PHOTOGRAPHIC RECORDS 
The  Engineer  shall  make  photographs  and  other  records  to  be  agreed  with  the 
Contractor of the condition of the surfaces of the site immediately before entering 
upon them for the purpose of constructing the Works. Each month, the Contractor 
shall make a set of up to 100 digital colour photographs illustrating progress of the 
Works, or any other photograph that he may deem necessary for record purposes, 
and provide these to the Engineer for his records. The copyright of all photographs 
shall be vested in the Employer and the Contractor shall not use any photograph for 
any purpose whatsoever without the Engineer's approval 

120.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

121. ACCESS TO SITE 
 
The Contractor shall make his own arrangements for access to the various parts of 
the Site where works are to be constructed but all such accesses shall be subject to 
the approval of the Engineer. 
 
Where the access to the Site proposed to be used by the Contractor lies across the land 
of any third party the Contractor shall produce to the Engineer the written consent of 
the owner and the occupier of the land over which the access lies before making use of 
the same. 
 
The Contractor shall also make a record to be agreed by the Engineer of the conditions 
of  the  surfaces  of  any  land  (and  of  any  crops  on  such  land)  over  which  access  lies 
before he uses it for access purposes and he shall keep all such surfaces in a reasonable 
state  of  repair  during  the  executing  of  the  Works.    On  the  termination  of  the 

 
Series 100 – General              Page no: 43 of 63 
SRI LANKA OPERATIONS CENTRE

Contractor's use of such access he shall restore any lands, roads or other property to a 
condition at least equal to that existing before his first entry upon them. 

121.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

122. CO‐OPERATION AT SITE 
 
All  work  shall  be  carried  out  in  such  a  way  as  to  allow  access  and  afford  all 
reasonable facilities for any other contractor and his workmen and for the workmen 
of  the  Employer  and  any  other  person  who  may  be  employed  in  the  execution 
and/or operation at or near the site of any work in connection with the Contract or 
otherwise. 
 
The Contractor shall use his best endeavours to co‐operate with such persons without 
interfering with them and shall observe all the instructions and orders of the Engineer 
in that connection. 
 
In the preparation of his programme of work the Contractor shall at all times take full 
account of and co‐ordinate with the programming of work of other contractors. 

122.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

123. ROADS AND SITE TO BE KEPT CLEAN 
 
The  Contractor  shall  take  great  care  and  all  reasonable  precautions  to  ensure  that 
roads and thoroughfares used by him either for the construction of the Works or for 
the  transport  of  plant,  labour  and  materials  are  not  made  dirty  as  a  result  of  such 
construction  or  transport  and  in  the  event  of  their  becoming  thus  dirtied  in  the 
opinion of the Engineer the Contractor shall take all necessary and immediate steps 
to clean them. 

123.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

124. SECURITY OF THE WORKS  
 
The contractor’s responsibility for the security and safe working environment of the 
site commences from the time possession is given to him by the Employer. 

 
Series 100 – General              Page no: 44 of 63 
SRI LANKA OPERATIONS CENTRE

 
As soon as possible after possession has been given, the boundary of the site shall be 
marked  out,  and  the  contractor  shall  submit  to  the  Engineer  for  approval  his 
proposals for maintaining the boundary and the security within. 
 
The contractor’s proposals shall include a security control system which shall consist 
of sufficient equipment and personnel to prevent unauthorized access and which can 
meet the prevailing circumstances to ensure the safety and security of persons and 
property on the site. 
 
The  contractor  shall  erect  and  maintain  at  his  own  expense  suitable  and  approval 
temporary fencing and gates to enclose certain areas of the works being carried out, 
the  office  and    accommodation  compounds,  and  other  areas  of  land  as  may  be 
necessary  to  implement  his  obligations  under  the  contract  or  as  directed  by  the 
Engineer. 
   
All authorized persons shall be registered by the Engineer and this register shall be 
provided and maintained by the contractor. 
 

124.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

125. SUPPRESSION OF NOICE 
 
The Contractor shall make every reasonable endeavour both by means of temporary 
works  and  by  the  use  of  appropriate  plant  or  silencing  devices  to  ensure  that  the 
level  of  noise  resulting  from  the  execution  of  the  Works  does  not  constitute  a 
nuisance. 

125.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

126. SAFETY 
 
The  Engineer  shall  be  notified  by  the  Contractor  immediately  any  accident  occurs 
whether on Site or off Site in which the Contractor is directly involved which results 
in  any  injury  to  any  person  whether  directly  concerned  with  the  Site  or  whether  a 
third party.  Such initial notification may be verbal and shall be followed by a written 
comprehensive report within 24 hours of the accident. 
 
Transportation  of  any  material  by  the  Contractor  shall  be  in  suitable  vehicles  which 
when loaded do not cause spillage and all loads shall be suitably secured.  Any vehicle 

 
Series 100 – General              Page no: 45 of 63 
SRI LANKA OPERATIONS CENTRE

which does not comply with this requirement or any of the local traffic regulations and 
laws shall be removed from the Site. 

126.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

127. METHOD OF WORKING 
 
The  Contractor  shall  adopt  a  method  of  working  such  as to permit the satisfactory 
and  timely  completion  of  the  Works  and  to  limit  disturbance  and  damage  to  a 
minimum. 
 
The  Contractor  shall  only  open  up  sections  of the Works for which his resources are 
sufficient  to  maintain  continuous  and  methodical  progress.    If  in  the  opinion  of  the 
Engineer, the Contractor has not complied with the foregoing, he shall be entitled to 
suspend  sections  of  the  works  pursuant  to  clause  40  of  the  General  Conditions  of 
Contract  until  other  sections  have  been  completed  to  a  stage  where  risk  of  damage 
through exposure to traffic and the elements and inconvenience to public traffic has 
been minimised. 
 
Constructional Plant used in the execution of the Works shall be of a design and used in 
a  manner  approved  by  the  Engineer.  The  Engineer  may  at  any  time  withdraw  his 
approval  for  any  method  of  working  proposed  by  the  Contractor and the Contractor 
shall immediately adopt another method of Working.  If such change shall be required 
to  achieve  satisfactory  progress  or  workmanship,  the  Contractor  shall  have  no  claim 
against the Employer for costs incurred by him in changing the method of working or in 
the provision and use of other plant. 

127.1. Payment 
 
Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 

128. TEMPORARY WORKS 
 
The Contractor shall provide, maintain and remove on completion of the Works all 
temporary  works  necessary  for  the  construction  of  this  permanent  works.    All 
temporary works shall be properly designed and constructed to carry such loads as 
may  be  imposed  upon  them  and  shall  be  safe  and  suitable  in  every  respect  for 
providing  access  or  carrying  plant  or  for  the  construction  of  the  Works  or  other 
purposes. 

128.1. Payment 
 

 
Series 100 – General              Page no: 46 of 63 
SRI LANKA OPERATIONS CENTRE

Work performed as part of the above obligations shall not be measured and paid for 
separately  and  the  cost  thereof  is deemed to be included in the Contractor’s rates 
and prices. 
 

129. SETTING OUT AND CROSS SECTION SURVEY AND DRAWINGS 

129.1. General 
 
The Contractor’s attention is drawn to the requirements of clause 18 of the General 
Conditions of Contract regarding setting out. 
 
The Contractor shall check the condition of all permanent Ground Markers and shall 
satisfy himself that they have not been damaged or disturbed and are true in regard 
to position and level.  Where markers have been destroyed, damaged or displaced 
the Contractor shall reinstate a new marker based on the markers which remain.  A 
new marker shall not be used unless its true position and level has been established 
and the new values verified by the Engineer. 
 
Where  a  marker  is  likely  to  be  disturbed  during  construction  operations  the 
Contractor shall establish suitable reference markers at locations where they will not 
be  disturbed  during  construction.    No  marker  shall  be  covered,  disturbed  or 
destroyed before accurate reference markers have been established and the details 
of the position and levels of such markers have been submitted to the Engineer and 
approved by him.  The Contractor’s reference markers shall be of at least the same 
quality and durability as that of the existing markers. 
 
The Contractor shall submit to the Engineer the method of setting out he proposes 
to  employ.    To  ensure  beyond  doubt  that  the  complex  elements  of  the  road  or 
structure are truly and correctly located the Contractor shall check all setting out by 
a different approved method.  The Engineer may at any time request the Contractor 
to submit proof that his setting out has been satisfactorily checked. 
 
Accurate control of line and level shall be provided by the Contractor at all stages of 
construction.  In respect of the road itself control shall be at 20m intervals, or such 
closer  intervals  as  may  be  directed,  on  horizontal  and  vertical  curves.    Wherever 
necessary,  but  particularly  on  completion  of  the  sub  grade,  sub  base  and  the  base 
the  Contractor  shall  re‐establish  stake‐line  pegs  at  sufficiently  close  intervals  to 
accurately  determine  the  edges  of  the  base,  surfacing  and  kerbing,  guard‐rails  and 
other road elements permanently exposed to the eye. 
 
The  Contractor  shall  make  all  provisions  necessary  for  the  Engineer  to  check  and 
measure  the  setting  out  of  the  Works  and  shall  be  in  attendance  to  agree 
measurements and levels before construction works commence. 

129.2. Setting Out and Cross Sections 
 
The Contractor shall set out the centre‐line and establish chainage reference points 
which  are  to  be  marked  out  on  site  and  recorded.    Level  Bench  Marks  at  the  both 
sides  of  the  bridge  shall  be  established  and  checked  regularly  and  tied  into  the 
Permanent Ground Markers. 
 
Series 100 – General              Page no: 47 of 63 
SRI LANKA OPERATIONS CENTRE

 
The  Contractor  shall  survey  the  existing  ground  along  cross  sections  to  the  centre 
line  at  20m  intervals,  or  such  closer  intervals  as  may  be  directed  by  the  Engineer.  
Levels shall be taken at all changes of slope and all features to a distance of 5 metres 
beyond the right of way.  Distance between levels shall not exceed 5 metres. 
 
The Contractor shall prepare cross sections in AutoCAD format indicating the existing 
road,  shoulder  and  other  features,  Chainage,  offset  and  agreed  levels,  to  a  format 
agreed  with  the  Engineer.    The  cross  sections  shall  be  suitable  for  plotting  to  a 
horizontal scale of 1:50 and a vertical scale of 1:20 on A3 size page. 
 
The  Contractor  shall  complete  the  cross  section  drawings  by  adding  the  new 
carriageway, shoulder, ditches, side slopes and pavement construction layers 
 
The cross sections shall be the basis for measurement and payment. 
 
The  Contractor  shall  complete  the  setting  out  of  the  centre‐line  within  four  weeks 
following  the  date  of  the  Engineer’s  Notice  to  Commence  the  Works.    Sufficient 
survey and drafting staff shall be available to enable the full setting out of the Works 
and for the drawing up of cross sections to be complete such that no delay is caused 
to the setting out of the Works. 
 
The Contractor shall employ on the Works sufficient qualified surveyors with at least 
2 years experience in similar works and have a thorough knowledge and experience 
of computer methods for calculating quantities.  The surveyors shall have available 
sufficient  modern  survey  equipment  and  instruments  which  shall  be  to  the 
Engineer’s  approval.  The  Contractor  shall  assist  and  supply  services  of  his surveyor 
and  his  team  to  the  Engineer  whenever  required  by  the  Engineer  or  his 
Representatives in checking and measuring the Works. 
 
No  construction  work  shall  commence  on  any  section  of  the  road  until  the  cross 
sections for the whole of that section have been completed. 
 

129.3. Measurement & Payment 
 
No  separate  payment  shall  be  made  for  compliance  items  under  this  section.  
Payment shall be deemed to be included in the contractor’s rates. 

129.4. Payment 
 
No separate payment shall be made for items under this section.  Payment shall be 
deemed to be included in the Contractor’s rates. 
 

130. FACILITIES FOR THE ENGINEER AND HIS STAFF 

130.1  Description 
 

 
Series 100 – General              Page no: 48 of 63 
SRI LANKA OPERATIONS CENTRE

“The  Contractor  shall  provide  offices,  laboratories  (with  equipment),  housing, 


vehicles,  survey  equipment  and  support  staff  for  the  Engineer  and  his  staff  as 
described in Appendices 2 to 7 inclusive”. 
 
For the purpose of this Clause the phrase “Engineer and his staff” shall be taken to 
describe any of the following: 
 
a) Supervision consultant’s staff 
b) Road Development Authority (RDA) staff 
 
The  facilities  shall  include  the  provision  of  the  land,  site  grading,  access  roads, 
parking  facilities  for  vehicles,  construction  of  buildings  and  all  other  necessary 
appurtenance such as drainage systems, fences, utilities, area development etc. 
 
The  Contractor  shall  supply  furniture,  fittings,  equipment,  labour  and  material  as 
detailed in the Appendices in order to provide fully functioning and usable facilities 
and  to  provide  the  Engineer’s  staff  with  the  necessary  resources  for  the 
administration and supervision of the Works. 
 
After  providing  the  facilities,  the  Contractor  shall  maintain  them  for  the  required 
duration of the Contract.  “The cost of such maintenance is deemed to be included in 
the Contract Price and shall include but shall not be limited to the following :‐ 
 
− Keeping  buildings  in  good  repair  and  decorative  order,  and  free  from  pests, 
insects etc. 
 
− Cleaning offices and laboratory daily. 
 
− Maintaining the grounds around buildings. 
 
− Supplying kitchen‐ware and crockery and cleaning materials. 
 
− Supplying toilet and cleaning equipment and materials. 
 
− Providing  power,  drainage  ,  telephone  services,  fax  and  E‐mail  facilities  & 
cellelular telephones. 
 
− Servicing and repairing all fittings and equipment installed. 
eg : air ‐ conditioners, fans, cookers etc. 
 
− Provide adequate security for offices and Engineer’s laboratory. 
 
Upon Completion of the Works and when instructed by the Engineer the Contractor 
shall remove the facilities to the satisfaction of the Engineer. 

130.2  Land for Facilities 
 
The  Contractor  shall  construct  the  facilities  on  land  purchased  or  leased  by  the 
Contractor. 
 

 
Series 100 – General              Page no: 49 of 63 
SRI LANKA OPERATIONS CENTRE

Where  the  Contractor  leases  land  for  construction  of  the  facilities,  the  Contractor 
shall ensure the terms of the land lease allow the use of the premises for as long as 
they  are  required  and  shall  take  into  account  possible  extension  or  overrun  of  the 
Contract  period  and  use  of  the  facilities  after  the  issue  of  the  Defects  Liability 
Certificates.    The  terms  of  the  lease  shall  incorporate  provisions  whereby  the 
Contractor may assign his interests to the Employer. 
 
The Employer may elect to provide land for facilities in which case adjustment will be 
made to the appropriate Bill of Quantities.  The Employer shall not be, or deemed to 
be, responsible or obligated to provide land for facilities. 

130.3  Sole Use of Facilities 
 
The facilities shall be for the sole use of the Engineer and his staff during the period 
of the Contract and as further required to finalise measurement, payment etc., but 
shall  revert  to  the  Contractor when no longer required, unless otherwise stated or 
directed. 

130.4  Services 
 
The  Contractor  shall  arrange,  where  possible,  for  the  connection  of  water  mains, 
drainage and sewerage and mains electricity to all facilities.  In circumstances where 
location  of  facilities  makes  such  connections  impracticable,  the  Contractor  shall 
provide and operate generators to supply adequate power and shall provide pumps 
to supply water from wells or storage tanks. 
 
Telephone services including at least one direct line shall be provided as indicated in 
the Appendices. 

130.5  Rented Premises 
 
Rented  offices  and  housing  accommodation  as  an  alternative  to  constructing 
buildings may be considered by the Engineer in locations where large town centres 
are conveniently situated along the Works.  Rents payable shall be at normal market 
rates and shall be subject to the approval of the Engineer.  The total cost for using 
the  alternative  of  rented  offices  and/or  accommodation  shall  be  such  that  there is 
no  extra  cost  to  the  Employer  compared  with  the  priced  items.    Payment  for  such 
accommodation  would  be  made  monthly  through  the  monthly  Certificate,  on  the 
basis of approved rent charges plus 10%.  Where rented accommodation is chosen 
by  the  Contractor  and  approved  by  the  Engineer,  the  Contractor  shall  provide  and 
fix, those items of furniture, equipment and fittings as listed in Appendices which the 
Engineer shall select.  In this case, the Contractor shall provide a breakdown of the 
relevant Bill Item detailing his rate per item of furniture.  Payment shall be made on 
the basis of the rate multiplied by the number of items provided. 
When rented accommodation is approved by the Engineer, a Variation Order will be 
issued to cover changes on the above pricing basis. 

130.6  Offices and Furnishings  
 
Description 

 
Series 100 – General              Page no: 50 of 63 
SRI LANKA OPERATIONS CENTRE

 
The offices to be provided are described in Appendix 2.  The offices including fittings, 
furnishings and equipment, shall be completed within 12 weeks from the date of the 
Engineer’s  Notice  to  Commence  the  Works.    Where  the  Engineer  approves,  the 
Contractor  may  rent  suitable  premises  in  accordance  with  the  Specifications.    The 
offices shall remain the property of the Contractor on Completion of the Works. 
Any  rented  offices  provided  shall  be  available  and  ready  for  use  within  6  weeks  of 
the above date. 
The  Contractor  shall  provide  temporary  office  space  for  the  period  from  6  weeks 
from  the  date  of  the  Notice  to  Commence  the  Works  until  completion  of  the 
permanent offices.  In the event of the Contractor failing to provide such temporary 
or  permanent  office  facilities  the  Engineer  will  provide  suitable  offices  for  his  use 
and any costs may be deducted by the Employer from the Contractor in accordance 
with Clause 49.4 of the conditions of Contract. 
 
The fittings, furnishings and equipment to be provided in the offices are described in 
Appendix  2,  and  shall  remain  the  property  of  the  Contractor  on  completion  of 
Works. 
 
Measurement 
 
Offices  for  the  Engineer  shall  be  measured  as  the  number  of  each  type  of  office 
provided. 
 
Furniture for the offices of the Engineer shall be measured as a lump sum item for 
each complete set of fittings, furnishings and equipment provided for Type 1 or Type 
2 office. 
 
Payment 
 
Payment for each type of office shall include for: 
 
(1) Acquisition and payment for land whether purchased or leased. 
(2) Provision  and  subsequent  removal  of  the  building  and  access  roads,  hard 
standing and fences etc. 
(3) Connection  and  subsequent  disconnection  of  electricity,  telephone  and  water 
services or alternative provision of same. 
(4) Provision of drainage systems for both sewerage and surface waters. 
(5) Reinstatement of all land to the satisfaction of the Engineer. 
 
Payment  for  each  office  shall  be  made  upon  completion  of  each  office  and  upon 
occupation  by  the  Chief  Resident  Engineer/Resident  Engineer  and  his  staff  to  the 
extent  that  they  can  properly  perform  their  duties  under  the  Contract  to  the 
satisfaction of the Engineer. 
 
Payment for Furniture for each type of office shall include procurement, delivery and 
installation of all the items detailed in Appendix 3. 
 
Payment  for  each  set  of  Furniture  provided  shall  be  made  upon  satisfactory 
installation and acceptance by the Engineer of all items to be provided. 
 
 
Series 100 – General              Page no: 51 of 63 
SRI LANKA OPERATIONS CENTRE

The payment for offices furniture and services shall represent full and final payment 
for  the  Contract  Items  and  Contractor  shall  not  be  entitled  to  any  further 
compensation  irrespective  of  any  extension  to  the  Contract  period  for  whatever 
reason. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
130 (1)  Provide office Type 1  Lump Sum 
 
130 (2)  Provide office Type 2  Lump Sum 
 
130 (3)  Provide Engineer’s Laboratory  Lump Sum 
 
130 (4)  Provide furniture for Office Type 1  Lump Sum 
 
130 (5)  Provide equipment for Office Type 1  Lump Sum 
     
130 (6)  Provide furniture for Office Type 2  Lump Sum 
 
130 (7)  Provide equipment for Office Type 2  Lump Sum 
 
130 (8)  Provide furniture for Engineer’s Laboratory  Lump Sum 
 
130 (9)  Provide equipment for Laboratory  Lump Sum 
 

130.7  Accommodation for the Engineer 
 
Description 
 
The  accommodation  to  be  provided  for  the  Engineer  and  staff  is  described  in 
Appendix 3.  The furniture, fittings and equipment for each house are also detailed 
and listed in Appendix 3.  The houses and furniture etc. remain the property of the 
Contractor on contract completion. 
 
The  accommodation  together  with  furniture,  etc.,  shall  be  complete  and  ready  for 
occupation within 12 weeks from the date of the Engineer’s notice to Commence the 
Works. 
 
Where the Engineer approves, the Contractor may rent suitable accommodation. 
 
Any  rented  accommodation  provided  shall  be  available  and  ready  for  occupation 
within 6 weeks of the above date. 
 
Where  the  Contractor  fails  to  provide  the  houses  within  the  time  specified,  the 
Contractor  shall  provide,  at  no  cost  to  the  Employer,  suitable  hotel  or  other 
accommodation  as  approved  by  the  Engineer  for  the  site  staff  intended  to  occupy 
the houses until such time as the houses are ready for occupation. 
 
 
Series 100 – General              Page no: 52 of 63 
SRI LANKA OPERATIONS CENTRE

 
Measurement 
 
Accommodation for the Engineer shall be measured as the number of each type of 
house provided. 
 
Furniture, fittings, equipment etc., for the houses for the Engineer and his staff shall 
be  measured  as  a  lump  sum  item  for  each  complete  set  of  furniture,  fittings  and 
equipment provided for each type of house. 
 
 
Payment 
 
Payment for each type of house shall include : 
 
(1) Acquisition and payment for land, whether purchased or leased. 
(2) Provision  and  subsequent  removal  of  building,  access  roads,  hard  standing, 
fences etc. 
(3) Connection  and  subsequent  disconnection  of  electrical,  telephone  and  water 
services or alternative provisions for same. 
(4) Provision of drainage systems, for both sewerage and surface water 
(5) Reinstatement of land to the satisfaction of the Engineer. 
 
Payment for each house shall be made upon satisfactory completion of each house 
and upon occupation by the intended resident(s). 
Payment for furniture, fittings, and equipment for each type of house shall include 
procurement, delivery and installation of all the items detailed in Appendix 5. 
 
Payment  for  each  set  of  furniture  provided  will  be  made  upon  satisfactory 
installation and acceptance by the Engineer of all the items to be provided. 
 
The  payments  for  houses  and  furniture  shall  represent  full  and  final  payments  for 
the  Contract  Items  and  the  Contractor  shall  not  be  entitled  to  any  further 
compensation  irrespective  of  any  extension  to  the  Contact  period  for  whatever 
reason. 
 
Pay items shall be :‐ 
 
Item No.  Description  Pay unit 
 
130(10)  Provide Type 1 accommodation  Lump Sum 
 
130(11)  Provide Type 2 accommodation  Lump Sum 
 
130(12)  Provide furniture, fittings and  
  equipment to Type 1 accommodation  Lump Sum 
 
130(13)  Provide furniture, fittings and 
  equipment to Type 2 accommodation  Lump Sum 
 

 
Series 100 – General              Page no: 53 of 63 
SRI LANKA OPERATIONS CENTRE

130.8  Engineer’s Laboratory and Equipment 
 
Description 
 
The Engineer’s Laboratory to be provided is described in Appendix 6.  The Laboratory 
is  required  for  testing  materials  used  for  the  Permanent  Works  therefore  priority 
shall be given to its construction and the supply of equipment required as detailed in 
Appendix 7.  The operational Laboratory facility, complete with equipment, shall be 
ready for use within 12 weeks from the date of the Engineer’s Notice to Commence 
the Works. 
At the end of its use the Laboratory and equipment shall become the property of the 
Contractor. 

a) Materials Testing by Independent Laboratories 
 
In addition to the Site testing facilities described Sub Section 130.8, the Contractor 
shall be responsible for arranging for the field and off‐Site laboratory tests indicated 
as  the  responsibility  of  the  Contractor  in  the  Specifications,  to  be  performed  by 
testing  laboratories  approved  by  the  Engineer.  The  Contractor  shall  be  responsible 
for  all  attendance  on  staff  from  these  approved  testing  laboratories,  including  if 
necessary the provision of transport for personnel, equipment and test specimens. 

b) Special and Additional Testing 
 
In addition to the testing described above, the Engineer may require further testing 
to  be  carried  out.  Such  special  and  additional  testing  shall  be  arranged  by  the 
Contractor under the direction of the Engineer. 

c) Staff for Materials Testing 
 
The  Contractor  shall  provide  qualified  laboratory  engineers,  technicians,  assistants, 
labourers,  etc.  to  carry  out  sampling  and  testing  of  materials  in  accordance  with 
these Specifications. Laboratory staff shall be subject to the approval of the Engineer 
and be available to assist the Engineer with materials testing, as and when required. 
 
Measurement 
 
The Engineer’s Laboratory shall be measured as the unit number provided. 
 
Laboratory  equipment  shall  be  measured  as  a  Provisional  sum  item  for  the  set  of 
equipment provided and installed and tested. 
 
Payment 
 
Payment for the Engineer’s Laboratory shall include for: 
 
(1) Acquisition and payment for land whether purchased or leased. 
(2) Provision  and  subsequent  removal  of  the  building,  access  road,  hardstanding, 
fences etc. 

 
Series 100 – General              Page no: 54 of 63 
SRI LANKA OPERATIONS CENTRE

(3) Connection  and  subsequent  disconnection  of  electrical  and  water  services,  or 
alternative provisions. 
(4) Provision of drainage systems for waste, sewerage and surface water. 
(5) Reinstatement of land to the satisfaction of the Engineer. 
 
Payment for the Engineer’s laboratory shall be made upon satisfactory completion of 
the  Laboratory  and  upon  occupation  and  use  of  the  Laboratory  by  the  Engineer’s 
Representative  to  the  extent  laboratory  staff  can  properly  perform  their  duties 
under the Contract to the satisfaction of the Engineer. 
 
Payment  for  the  Laboratory  Equipment  shall  include  procurement,  delivery, 
installation  and  testing  of  all  the  items  listed  in  Appendix  9.    Contractor  shall 
maintain the equipment in good serviceable order through the Contract period. 
 
Payment  for  the  set  of  Laboratory  Equipment  will  be  made  upon  satisfactory 
installation  and  testing  and  acceptance  by  the  Engineer  of  all  the  items  to  be 
provided. 
 
The  payments  for  the  Laboratory  and  Equipment  shall  represent  full  and  final 
payments  for  the  Contract  items  and  the  Contractor  shall  not  be  entitled  to  any 
further  compensation  irrespective  of  any  extension  to  the  Contract  period  for 
whatever reason. 
 
Pay items shall be:‐ 
Item No.  Description  Pay unit 
 
130 (14)  Provide Engineer’s Laboratory  Provisional sum 
  Building includingEquipment as  
  per Appendix 7 
 

130 (15)  Special and Additional Testing    Provisional sum 

130(16) Staff for Materials Testing      Person Month 
 

130.9  Stationery for the Engineer 
 
Description 
 
The Contractor shall provide stationery for the Engineer and his staff as required and 
duly requisitioned by authorised personnel.  Stationery shall include all consumable 
items  and  shall  include  paper,  printing  materials  (e.g.  printer  cartridges,  printer 
ribbons, copier toner etc.) and all general office requisites.  This item excludes parts, 
etc., required for repair or replacement in equipment supplied by the Contractor for 
the  offices.    Such  parts  would  be  included  in  the  Contractor’s  obligation  for 
maintenance of offices. 
 
Measurement 

 
Series 100 – General              Page no: 55 of 63 
SRI LANKA OPERATIONS CENTRE

Stationery for the Engineer shall not be measured but payment shall be based on the 
original  invoices  and  receipts  for  stationery  material  ordered  and  received  by  the 
Project Manager/Engineer’s Representative’s staff. 
 
Payment 
Payment for stationery shall be the actual net invoiced price of stationery provided 
(with  all  suppliers’  discounts  deducted)  with  a  fixed  10  %  (Ten  percent)  of  the  net 
invoiced price added to allow for all procurement and delivery costs incurred by the 
Contractor.  Payment of invoiced cost with the 10 % mark‐up shall be full payment 
for stationery provided and shall be made from the provisional sum item contained 
in the Bill of Quantities. 
 
Pay items shall be :‐ 
 
Item No.  Description  Pay unit 
 
130 (17)  Provide Stationery for the   month  
  Engineer  

130.10  Provision of Hotel Accommodation for the Engineer and his Staff 
 
Description 
 
The  Contractor  shall  be  responsible  for  providing  hotel  or  other  approved 
accommodation  (including  meals  etc.  but  excluding  alcoholic  beverages)  for  the 
Resident Engineer and other staff who should be provided with housing during the 
mobilisation  period  until  the  housing  and  furnishing  specified  in  the  Contract  are 
ready for occupation by the staff. 
 
The standards of the hotel accommodation shall be to the approval of the Engineer. 
 
Measurement 
 
Provision of Hotel Accommodation shall be measured as the number of man‐weeks 
of  accommodation  provided.    Accommodation  provided  after  the  time  the  houses 
for  the  Engineer  are  due  to  be  completed  will  not  be  measured,  and  shall  be 
supplied at the Contractor’s expense. 
 
Payment 
 
Payment  will  be  made  against  accommodation  invoices  as  instructed  by  the 
Engineer. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
130 (18)  Provide hotel accommodation   Provisional Sum  
  for Engineer’s staff 
 

 
Series 100 – General              Page no: 56 of 63 
SRI LANKA OPERATIONS CENTRE

130.11  Survey Equipment 
 
Description 
 
The equipment to be provided is detailed in Appendix 5. 
 
The  equipment  shall  be  provided  within  10  weeks  from  the  date  of  the  Engineer’s 
Notice to Commence the Works. 
 
The Contractor shall be fully responsible for the equipment which shall include:‐ 
 
(a) Maintaining, calibrating and servicing equipment as required. 
(b) Repairing all defects including accidental damage as required. 
(c) Replacing any lost or stolen items. 
(d) Effecting insurance of the equipment against damage or loss. 
 
The  equipment  shall  be  supplied  and  maintained  for  as  long  as  it  is  required 
including  period  after  the  Completion  of  construction  for  final  measurement 
purposes. 
 
The  equipment  with  the  exception  of  consumable  items  shall  be  returned  to  the 
Contractor when no longer required by the Engineers and shall remain the property 
of the Contractor. 
 
Measurement 
 
Survey  Equipment  shall  be  measured  as  a  lump  sum  item  for  complete  set  of 
instruments  and  items  detailed  in  Appendix  5  satisfactorily  provided,  and 
maintained. 
 
Payment 
 
Payment for Survey Equipment shall be made at the stated Provisional sum price and 
shall be payable when all the items are provided.  This payment shall represent full 
and final payment to the Contractor for the Contract Item for the complete period of 
use and the Contractor shall not be entitled for further compensation irrespective of 
any increase to the Contract period for whatever reason. 
 
In the event the Contractor fails to maintain, repair or replace any Equipment item, 
the Engineer shall effect such maintenance, repairs or replacement and shall deduct 
the cost from payment due under this Contract Item. 
 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
130 (19)  Provide Survey Equipment   Lump sum  
  as per Appendix 5 

 
Series 100 – General              Page no: 57 of 63 
SRI LANKA OPERATIONS CENTRE

130.12  Maintenance of Engineer’s Facilities 
 
Description 
 
The Contractor shall maintain in good decorative and working order all the buildings 
and  the  contents  thereof  supplied  under  the  Contract.    The  Contractor  shall  be 
responsible for supplying all power, water and telephone services to all the facilities, 
and shall meet all costs for these services unless otherwise stated. 
 
The Maintenance of the Engineer’s offices and Laboratory shall include daily cleaning 
to the satisfaction of the Engineer’s Representative and provision of toilet materials.  
Cleaning of housing is excluded from the Contract scope. 
 
The Contractor shall maintain all grounds and gardens that surround the buildings to 
the satisfaction of the Engineer. 
 
The  Contractor  shall  maintain  in  good  condition,  service  regularly  and  repair  or 
replace  as  required  all  items  of  furniture,  fittings  and  equipment  supplied  and 
installed in the offices, laboratory and houses. 
 
The Contractor shall provide adequate security to guard and secure the facilities on a 
24 hours per day basis. 
 
The  Contractor  shall  be  responsible  for  the  cost  of  all  local  telephone  charges  but 
shall  not  be  responsible  for  the  cost  of  any  overseas  calls  made  from  telephones 
provided in offices and any calls made from telephones provided in houses. 
 
The Contractor shall provide adequate number of driver, fuel, oil, insurance, license 
maintenance, repairs and all other running and maintenance for vehicle. 
 
Measurement 
 
Maintenance of each facility shall be measured as the number of weeks during which 
maintenance  for  each  facility  is  satisfactorily  provided.    Maintenance  shall  not  be 
measured during any period occurring between the expiration of the Contract period 
(including  awarded  Extension  of  Time)  and  the  date  the  Works  are  certified  as 
complete.    Measurement  will  be  made  for  maintenance  performed  after  the 
certified completion of the Works, during the time the facilities are required by the 
Engineer’s staff for post‐construction Contract completion activities. 
 
Payment 
 
Payment  for  Maintenance  of  each  facility  shall  include,  all  labour,  materials  and 
equipment required for satisfactory maintenance of the facilities and shall include all 
other  costs  including  but  not  limited  to  supply  of  electricity,  water  and  telephone, 
cleaning,  disposal  of  rubbish,  guarding,  repairing  equipment  and  all  other  work 
required  to  ensure  the  facilities  and  equipment  provided  are  in  good  operational 
order. 
 
 
Pay items shall be :‐ 
 
Series 100 – General              Page no: 58 of 63 
SRI LANKA OPERATIONS CENTRE

 
Item No.  Description  Pay unit 
 
130 (20)  Maintenance of office Type 1  Month 
  Including furniture, fittings 
  and equipment 
 
130 (21)  Maintenance of office Type 2   Month 
  including furniture, fittings 
  and equipment 
 
130 (21A)  Maintenance of Engineer’s Laboratory  Month 
  including furniture, fittings 
  and equipment 
 
130(22)  Maintenance of accommodation  Month 
  Type 1 including furniture, 
  fittings and equipment 
 
  130(23)  Maintenance of accommodation  Month 
    Type 2 including furniture, 
    fittings and equipment 
 
  130(24)  Maintenance of vehicle type 1   Month 
    Including driver, fuel, oil, insurance,  
    license  maintenance, repairs and  
    all other running and maintenance     
   
  130(25)  Maintenance of vehicle type 2   Month 
    Including (boat man,) fuel, oil, insurance,  
    license  maintenance, repairs and  
    all other running and maintenance 

130.13  Clerical and Technical Staff 
 
Description 
 
The  Contractor  shall  provide  the  Engineer  with  staff  to  assist  in  the  administration 
and  supervision  of  the  Works.    The  staff  provided  shall  be  experienced  and  be 
capable  of  performing  their  allotted  duties.    Engineer  shall  obtain  Employer’s prior 
approval for recruitment of these staff.  The Contractor shall ensure the continuity of 
the services of the selected personnel. 
 
In  particular,  laboratory  and  survey  assistants  shall  be  capable  of  assisting  the 
Engineer’s  staff  in  material  testing  and  survey  work  respectively  and  have  at  least 
five  years  experience  in  similar  works.    Draughtsman  shall  be  conversant  in  civil 
works and have at least 3 years experience in AutoCAD Drafting. Secretaries and the 
Administrators/Clerks shall be experienced in using computers/word processors and 
be  capable  of  using  the  latest  version  of  Microsoft  Office  computer  software  and 
have a good command of the English Language. 
 
 
Series 100 – General              Page no: 59 of 63 
SRI LANKA OPERATIONS CENTRE

Measurement 
 
Measurement of staff for the Engineer shall be by the number of weeks during which 
each  person  is  provided  and  actually  works.    Measurement  will  exclude  periods 
during  which  the  person  is  absent  for  any  reason.    Such  absence  shall  include 
approved vacation, sick leave, etc., but not public mercantile holidays. 
 
The working hours per day and the days per week shall be the same as those worked 
by  the  Contractor’s  own  site  personnel  in  similar  positions  plus  all  necessary 
overtime as required by the Engineer. 
 
Payment 
 
Payment for staff shall be at the unit rate for each classification as stated in the Bill 
of Quantities and which shall include all costs associated with their employment.  No 
additional payment for any extra hours worked or other reasons will be made. 
 
Pay items shall be:‐ 
Item No.  Description  Pay unit 
 
130 (26)  Workmen (classified unskilled)  Person Month 
 
130 (27)  Workmen (classified skilled)  Person Month 
 
 
130 (28)  Survey Assistants (classified skilled)  Person Month 
 
130 (29)  Secretary  Person Month 
 
130 (30)  Administrator/Clerk  Person Month 
 
130 (31)  Office /Field Assistant  Person Month 
 
130 (32)  Draughtsman  Person Month 

130.14  Vehicles for the Engineer, 
 
Description 
 
The  Contractor  shall  provide  new  plain  coloured  air‐conditioned  motor  vehicles  as 
described in Appendix 4 for the exclusive use of the Engineer, and his staff for any 
purpose in connection with the Project.  Each vehicle shall be to the approval of the 
Engineer.  The vehicles shall be licensed and insured for use on the public highway 
with  comprehensive  insurance  cover  for  any  qualified  driver  authorised  by  the 
Engineer,  together  with  any  authorised  passengers  and  the  carriage  of  good  or 
samples.    For  each  vehicle,  the  Contractor  shall  provide  a  competent,  qualified 
driver, subject to approval by Engineer, or Engineer’s Representative, holding a valid 
driver’s licence.  The Contractor shall provide fuel, oil and maintenance in conformity 
with the vehicle manufacture’s recommendations and shall clean the vehicles inside 
and outside as required during the period of the Contract.  A suitable replacement 
shall  be  provided  for  any  vehicle  out  of  service  for  more  than  24  hours.    Vehicles 
 
Series 100 – General              Page no: 60 of 63 
SRI LANKA OPERATIONS CENTRE

shall be provided for as long as they are required by the Engineer’s staff including a 
period beyond the certified date for Completion of the Works and shall remain the 
property of the Engineer on completion. 
 
Measurement 
 
Vehicles  for  the  Engineer’s  staff  shall  be  measured  as  the  number  of  weeks  each 
type of vehicle is provided and maintained. Measurement shall be made during the 
total period the vehicles in use by the Engineer’s staff as instructed by the Engineer.  
Vehicles  not  provided  for  the  full  day  will  be  measured  for  deduction  on  pro‐rata 
basis of Contract unit rate. 
 
Payment 
 
Payment  for  vehicles  shall  be  made  at  the  unit  price  for  each  type  of  vehicle  as 
contained in the Bill of Quantities. Payment shall only the supply of the vehicle costs. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
130 (33)  Provide  Provsional Sum  
  vehicle Type 1 
 
130 (34)  Provide  Provsional Sum  
  vehicle Type 2 
 

131. PROJECT SIGN BOARDS 

131.1   Description 
 
The Contractor shall erect where directed sign boards in a format acceptable to the 
Engineer. At the end of the defect liability period all such signs shall be removed and the 
ground reinstated to the approval of the Engineer. Each sign shall be of no less than 2 m2 
area and comprise white lettering on a blue background.  The following information should 
be given on each board: 
 
  °  Project Title (Construction of Permanent Steel Bridges programme) 
  °  Description & Location of the Project  
°  Name of Funding Agency (Spanish Government) 
° Name of Project Implementation Organisation (United Nations Office 
  for Project Services (UNOPS)  
° Contractor's Name 
° Duration of Contract 

131.2  Measurement 
Project  signboards  shall  be  measured  as  the  number  of  sign  boards,  satisfactorily 
provided, installed, maintained and removed throughout the Contract period. 

 
Series 100 – General              Page no: 61 of 63 
SRI LANKA OPERATIONS CENTRE

131.3  Payment 
Payment shall be made at the stated unit rate per signboard.  The price shall be full 
compensation for all materials and labour required to perform the work described. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
131(1)  Provide and maintain  
Project Sign Board  Number 
 

132. PROVISION OF INSURANCES, BONDS AND SECURITIES 

132.1  Description 
 
The  Contractor  shall  provide  all  necessary  Insurances,  Bonds,  Guarantees  and 
Securities  as  are  required  and  detailed  in  the  Tender  Documents,  Conditions  of 
Contract or this Specification. 

132.2  Measurement and Payment 
 
Measurement shall be as a lump sum payment for all expenditure with regard to the 
provision of Insurances, Bonds and Securities. 
 
Payment shall be made on submission of the original Insurance, Bond, Guarantee or 
Security or proof of payment of the same provided that the original shall be made 
available to the Engineer within a reasonable time after proof of payment. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay Unit 
 
132(1)  Provide all necessary Insurances for workforce   Lump Sum 
    For all Risks 
 
132(2)  Provide all necessary Bonds, Securities  Lump Sum 
 

133. MARBLE STONE FOR FOUNDATION LAYING  

133.1   Description 
 
The Contractor shall erect where directed Marble stone for foundation laying in a 
format acceptable to the Engineer. Marble stone shall be of no less than 1 m2 area 
and the stand (Stone masonry work) height no less than 2m, width no less than 2m 
thickness no less than 1m. 

133.2  Measurement 
 
 
Series 100 – General              Page no: 62 of 63 
SRI LANKA OPERATIONS CENTRE

Marble  stone  with  stand  shall  be  measured  as  the  number,  satisfactorily  provided, 
installed, maintained throughout the Contract period. 

133.3  Payment 
 
Payment  shall  be  made  at  the  stated  unit  rate  per  Marble  stone  with  stand.    The 
price shall be full compensation for all materials and labour required to perform the 
work described. 
 
Pay items shall be:‐ 
 
Item No.  Description  Pay unit 
 
133(1)  Provide and maintain  
Marble stone for foundation laying  Number 
 

 
Series 100 – General              Page no: 63 of 63 
SRI LANKA OPERATIONS CENTRE

SERIES 200 ‐ SITE CLEARING 
 
 
CONTENTS 
 
 
201.  CLEARING AND GRUBBING ..................................................................................................2 
201.1.  Description ......................................................................................................................... 2 
201.2.  Preservation of Property .................................................................................................... 2 
201.3.  Construction Methods........................................................................................................ 2 
.a.  General.................................................................................................................................... 2 
.b.  Clearing and grubbing............................................................................................................. 2 
.c.  Disposal of Cleared Material................................................................................................... 3 
201.4.  Measurement ..................................................................................................................... 4 
201.5.  Payment.............................................................................................................................. 4 
.a.  Clearing and grubbing............................................................................................................. 4 
.b.  Removal of trees and removal of stumps of previously felled trees ....................................... 5 
202.  REMOVAL OF EXISTING STRUCTURES ..................................................................................6 
202.1.  Description ......................................................................................................................... 6 
202.2.  Dismantling of Structures ................................................................................................... 6 
202.3.  Salvaged Materials.............................................................................................................. 7 
202.4.  Removal of Fences.............................................................................................................. 7 
202.5.  Back‐filling .......................................................................................................................... 7 
202.6.  Measurement ..................................................................................................................... 8 
202.7.  Payment.............................................................................................................................. 8 
203.  REMOVAL OF ELECTRIC/TELEPHONE POLES .........................................................................8 

204.  REMOVAL OF EXISTING PAVEMENT.....................................................................................8 
204.1.  Description ......................................................................................................................... 8 
204.2.  METHOD ............................................................................................................................. 9 
204.3.  MEASUREMENT .................................................................................................................. 9 
204.4.  PAYMENT............................................................................................................................ 9 
 
 
 

 
Series 200 – Site Clearing               Page no: 1 of 9 
SRI LANKA OPERATIONS CENTRE

SERIES 200 ‐ SITE CLEARING 
 

201. CLEARING AND GRUBBING 

Delete the whole text of clause 201 and substitute the following :‐ 

201.1. Description 

This  work  shall  consist  of  all  clearing  and  grubbing  necessary  for  the  performance  of  the 
work covered by the Contract in accordance with the Specifications. 
 
The work shall consist of clearing and grubbing the designated areas within the right of way 
of  all  trees,  dead  wood,  snags,  vegetation,  rubbish  and  objectionable  material  and  shall 
include grubbing stumps and roots and disposing of all material resulting from the clearing 
and grubbing.  It shall also include the demolition, removal and disposal of structures (other 
than  those  to  be  removed  in  accordance  with  clause  202)  that  obtrude  into  or  encroach 
upon or obstruct the work except where provided for otherwise.  

201.2. Preservation of Property 

Existing  roads,  improvements,  facilities,  adjacent  property,  utilities,  services,  and  trees  and 
plants designated for preservation shall be carefully protected from injury or damage which 
could result from the Contractor’s operations. 

201.3. Construction Methods 

a. General 
 
Generally  clearing  and  grubbing  shall  be  performed  on  the  areas  designated  by  staking  or 
detailed in the Contract Documents.  If no areas are designated in the Special Provisions or 
on the Drawings the areas shall in principle be as follows : 
 
Clearing and grubbing shall be carried out over the area designated by the Engineer. 

b. Clearing and grubbing 
 
Where embankment fill is to be constructed all topsoil shall be removed to an average depth 
of  0.15m.    All  surface  objects,  all  trees,  including  stumps  and  roots,  stumps  and  roots  of 
previously  felled  trees,  overhanging  branches,  except  those  trees  and  objects  the  Engineer 
directs  to  be  left  undisturbed,  shall  be  cleared  and  grubbing  subject  to  the  following 
provisions : 
 
(i) Outside the limits of the earthworks these are allowed to remain provided that the 
top  of  the  stumps  are  not  more  than  0.30m  above  ground  level.    However,  trees 
within  these  limits  shall  be  cut  so  that  the  stumps  are  in  line  with  the  natural 
ground level as far as practicable. 
 
(ii) In  areas  of  embankment  construction  stumps  and  roots  and  solid  objects  shall  be 
removed  to  a  minimum  depth  of  0.5m  below  the  top  level  of  the  subgrade  or 
(perpendicular)  below  the  slopes  of  the  embankments;  the  removal  of  these 
materials shall be to an extent of 1m outside the embankments. 

 
 
Series 200 – Site Clearing               Page no: 2 of 9 
SRI LANKA OPERATIONS CENTRE

(iii) Where  lined  drains  or  ditches  are  to  be  constructed  stumps  and  roots  shall  be 
removed  to  a  minimum  depth  of  0.25m  below  the  excavated  bottom  or  into  the 
shaped slope. 
 
(iv) Where the embankment fill is more than 3m high non‐perishable solid objects may 
be permitted to remain provided that the top of such objects is not more than 0.5m 
above natural ground level and the compaction of earthworks will not be hindered. 
 
(v) In cut areas stumps and roots shall be removed to a depth of at least 0.5m below 
the top of the subgrade over which the pavement is to be constructed to an extent 
of at least 0.5m outside the limits of the base course. 
 
(vi) When  instructed  by  the  Engineer,  the  Contractor  shall  demolish  wholly  or  in part, 
remove and dispose of all buildings, foundation, underground chambers, pits, tanks, 
structures, fences and any other obstructions, which have not been designated to 
remain.  Prior  to  demolition  the  Contractor  shall  ensure  that  services  have  been 
disconnected  to  the  satisfaction  of  the  appropriate  authorities  and/or  owner.  All 
holes resulting from the removal of the structures shall be backfilled with approved 
material  compacted  to  92%MDD  (AASHTO  180)  up  to  existing  ground  level  or  to 
such level as directed by the Engineer.  
 
The  Contractor  shall  carefully  dismantle  such  structures  and  stack  in  separate 
heaps. All materials, which in the opinion of the Engineer, are not suitable for re‐use 
shall be removed from the site to spoil areas. Re‐usable materials shall remain the 
property of the employer and shall be preserved and protected by the Contractor 
until removed by the Employer or until the expiry of the Defects Liability Period or 
its equivalent. 
 
(vii) Where, as a consequence of clearing and grubbing, fill material is required in order 
to restore the original ground level, it shall be acceptable fill material which shall be 
compacted  to  the  density  prescribed  for  layers  at  that  depth  below  finished  sub‐
grade.  Such replacement of materials shall be considered incidental to clearing and 
grubbing  and  shall  not  be  measured  for  payment.    Acceptable  fill  material  for 
backfilling depressions or excavations shall include brick, stone and concrete debris 
if  approved  by  the  Engineer  and  this  material  shall  be  compacted  in  layers  to 
achieve stable backfill to the approval of the Engineer. 

c. Disposal of Cleared Material 
 
(i) Saleable timber as designated by the Engineer shall be neatly stored in an approved 
accessible  place  within  or  near  the  right  of  way  as  directed  and  shall  be  trimmed 
and  staked  in  accordance  with  the  requirements  of  the  appropriate  Government 
Agency to which the timber belongs. 
 
(ii) Unsaleable  timber  may  be  used  by  the  Contractor  for  his  own  purposes  in 
connection with the Contract always provided that he has ascertained and complied 
with the requirements of the appropriate Government Agencies or Authorities. 
 
(iii) All unsaleable timber except that to be used and all brushes, stumps, roots, logs and 
other refuse from the clearing and from the grubbing operations shall be burned or 
be disposed by other means approved by the Engineer. 
 
In  such  cases  the  Contractor  will  be  solely  responsible  for  making  the  necessary 
agreements and for paying the resulting expenses. 
 
 
Series 200 – Site Clearing               Page no: 3 of 9 
SRI LANKA OPERATIONS CENTRE

Piles  of  material  for  burning  shall  be  placed  either  at  or  near  the  centre  of  the 
cleared  area,  or  in  adjacent  open  spaces  where  no  damage  to  trees,  other 
vegetation and adjacent property shall occur. 
 
All burning shall be done in conformance with the regulations and at such times and 
in such a manner as to prevent the fire from spreading to areas adjoining the right 
of way. 
 
(iv) should the clearing and grubbing be done at a time when burning is not permitted, 
the  Contractor  shall  pile  all  material  which  is to be burned outside the slope lines 
and at a time when burning is permitted he shall return such material to the grade 
and burn it. 
 
(v) At the end of such operations the roadway and adjacent areas shall be left with a 
neat  and  finished  appearance.    No  accumulation  of  burnt,  half  burnt  or  other 
material shall remain on or adjacent to the right of way. 

201.4. Measurement 
 
Clearing and grubbing will be measured on an area basis by the square metre, as indicated in 
the Bills of Quantities.  The work of clearing and grubbing at disposal sites, material sites, and 
borrow pit sites shall not be paid for when such are outside the areas designated for clearing 
or  grubbing  and  the  Contractor  is  permitted  to  exercise  his  own  option  as  to  whether  he 
elects to use such disposal sites or borrow pit sites. 
 
Any areas occupied by an existing asphaltic concrete, concrete or sealed road or otherwise 
maintained  area  are  excluded  from  the  designated  areas  and  shall  not  be  included  in 
measurement as defined in this sub‐clause. 
 
Removal  of  trees  including  stumps  and  roots  unless  otherwise  specified,  of  girth  less  than 
500 mm shall be considered as included in clearing and grubbing. 
 
Removal of trees including stumps and roots, as well as stumps and roots of previously felled 
trees of girth greater than 500 mm shall be measured in numbers and separately assessed 
according to the size categories given below : 
 
(i) girth greater than or equal to 250 mm and less than 1000 mm 
(ii) girth greater than or equal to 1000 mm and less than 2000 mm 
(iii) girth greater than or equal to 2000 mm and less than 3000 mm 
(iv) girth greater than or equal to 3000 mm 
For the above purpose the girth shall be measured as follows : 
 
− for trees at a level of 1 m above average ground level 
− for stumps of previously felled trees at a level of 1 m above average ground level or 
in case the stumps are lower, at the highest level of the stumps. 
 
Branches of overhanging trees of girth greater than 300 mm shall be measured as directed 
by the Engineer.  The girth shall be the girth of cut. 

201.5. Payment 

a. Clearing and grubbing 
 

 
Series 200 – Site Clearing               Page no: 4 of 9 
SRI LANKA OPERATIONS CENTRE

This  work  measured  as  provided  above  shall  be  paid  for  at  the  Contract  unit  as  detailed 
below  per  square  metre.    The  rates  shall  be  full  compensation  for  furnishing  all  labour, 
materials,  tools,  equipment  and  incidentals  necessary  to  do  the  work  and  for  doing  all  the 
clearing and grubbing in the designated areas and as specified in these Specifications and the 
Special Provisions and as directed by the Engineer including the removal and disposal of all 
the resulting material. 

b. Removal of trees and removal of stumps of previously felled trees 
 
Payment for removal of trees and stumps shall be made at the Contract unit rates and shall 
be the payment in full for carrying out the required operations including full compensation 
for  all labour, materials, tools, equipment and incidentals necessary to complete the work.  
These will include felling, excavating, backfilling, handling, transporting and disposal. 
 
 
Pay Items and Pay Units shall be as follows :‐ 
 
 
No  Pay Item  Pay Unit 
201.(1) Clearing and grubbing  Sq. metre   
201.(2) Removal of trees; girth 250 ‐ 1000 mm  Number   
201.(3) Removal of trees; girth 1000 ‐2000 mm   Number   
201.(4) Removal of trees; girth 2000 ‐3000 mm   Number   
201.(5) Removal of trees; girth 3000 mm and over   Number   
201.(6) Removal of stumps of previously felled trees; girth 250 ‐  Number 
1000 mm   
201.(7) Removal of stumps of previously felled trees; girth 1000 ‐  Number 
2000 mm    
201.(7.1) Removal of stumps of previously felled trees; girth 2000 ‐  Number 
3000 mm   
201.(7.2) Removal of stumps of previously felled trees; girth 3000  Number 
mm and over   
201.(7.3) Removal of overhanging branches; girth 300 mm and over  Number 
 

 
Series 200 – Site Clearing               Page no: 5 of 9 
SRI LANKA OPERATIONS CENTRE

202. REMOVAL OF EXISTING STRUCTURES 
 
Delete the entire Clause and substitute with the following :‐ 

202.1. Description 
 
This  work  shall  consist  of  dismantling  and  removing,  as  hereinafter  set  forth,  existing 
culverts, masonry and brickwork structures, walkways, medians, kerbs and other structures 
such as guard‐rails, manholes, catch basins, inlets etc. which are in place, but interfere with 
the new construction and are not suitable to remain in place, and salvaging/disposing of the 
resulting  materials.    All  materials  obtained  from  dismantling  shall  be  the  property  of  the 
Employer. 
 
Culverts and other structures, which are within the existing highway boundary and which are 
designated  to  be  removed,  shall  be  removed  down  to  the  limits  and  extent  specified 
hereinafter or as shown in the Drawings or as indicated by the Engineer. 
 
Dismantling and removal operations shall be carried out with such equipment and in such a 
manner as to level undisturbed, adjacent pavement, structures and any other specified to be 
left in place. 
 
All operations necessary for the removal of any existing structure which might endanger new 
construction shall be completed prior to the start of new work. 
 
Dismantling of bridges and parts of bridges for reconstruction, extension, redecking and so 
on  are  included  as  separate  items  in  each  separate  Bridges  Bill  of  Quantities  and  are  not 
included in this item.  Demolition, removal and disposal of private and public buildings etc. 
necessary  to  widen  the  existing  highway  boundary  to  achieve  the  full  right  of  way  are 
deemed to be included in the item.  Clearing and grubbing where not previously removed by 
the Engineer or land occupier. 

202.2. Dismantling of Structures 
 
The structures shall be dismantled carefully and the resulting materials so removed as not to 
cause any damage to the serviceable materials to be salvaged, the part of the structure to be 
retained and any other properties or structures nearby. 
 
Unless otherwise specified, the superstructure portion of culverts shall be entirely removed 
and  other  parts  removed  to  below  the  ground  level  or  as  necessary  depending  upon  the 
interference they cause to the new construction.  Removal of overlaying or adjacent material 
if  required  in  connection  with  the  dismantling  of  the  structures,  shall  be  deemed  to  be 
included in this item. 
 
Where  existing  culverts  are  to  be  rehabilitated  only  such  part  or  parts  of  the  existing 
structure shall be removed as are necessary to provide a proper connection to the new work.  
The  connecting  edges  shall  be  cut,  chipped  and  trimmed  to  the  required  lines  and  grades 
without weakening or damaging any part of the structure to be retained.  Reinforcing bars 
which  are  to  be  left  in  place  so  as  to  project  into  new  work  as  dowels  or  ties  shall  not  be 
damaged during removal of concrete. 
 
Pipe culverts shall be carefully removed in such a manner as to avoid damage to the pipes 
where instructed by the Engineer. 
 

 
Series 200 – Site Clearing               Page no: 6 of 9 
SRI LANKA OPERATIONS CENTRE

Masonry and brick work structures shall be dismantled to the extent shown in the drawing 
and as directed by the Engineer. 
 
All concrete pavement in carriageway designated for removal shall be broken up for ease of 
removal and carried to stockpiles at locations designated by the Engineer. 
 
Where the existing road signs, kilometre posts, mile posts or guard stones are to be removed 
they shall be carefully excavated and removed including breaking of the concrete base.  The 
serviceable  materials  shall  be  transported  and  stacked  at  locations  approved  by  the 
Engineer, and the unserviceable materials shall be disposed of as directed by the Engineer  

202.3. Salvaged Materials 
 
Materials which may be used directly in the Permanent Works shall be stockpiled separately 
from those which require processing for reuse.  The materials selected for processing should 
be  of  such  quality  as  will  meet  the  Specifications  after  breaking,  screening  and/or  mixing 
with better quality materials if necessary.  The responsibility of selecting a particular material 
for processing and/or incorporating in the Permanent Works shall lie with the Contractor. 
 
Acceptability of the materials (after processing as the case may be) shall be determined by 
the Engineer and only such materials that fully satisfy the Specifications in all respects shall 
be permitted for incorporation in the Permanent Works.  The materials failing to satisfy the 
Specifications  may  be  used  in  the  Temporary  Works  or  may be used in the lower layers of 
embankments or to fill depressions, stump holes etc. with the approval of the Engineer.  The 
materials not required by the Contractor for incorporation in the Works, but which are of use 
to the Employer shall be neatly stockpiled as directed by the Engineer. 
 
Structural/reinforcing steel obtained from dismantling of the existing structures shall not be 
considered  suitable  for  use  in  the  Permanent  Works  and  shall  be  stored  in  a  neat  and 
presentable  manner  in  locations  suitable  for loading.  Structures or portions thereof which 
are specified in the Contract for re‐erection shall be stored in separate stockpiles. 
 
Pipe  culverts  that  are  removed  in  good  condition  shall  be  cleaned and neatly stockpiled at 
points designated by the Engineer. 
 
All  the  products  of  dismantling  operations  which  in  the  opinion  of  the  Engineer  cannot  be 
used in the Works or reused by the Employer shall be disposed of outside the highway right‐
of‐way or may be spread in deep borrow pits, as directed by the Engineer. 
 
The Contractor shall comply with all laws, ordinances, building regulations etc. as prevailing 
in Sri Lanka.  Unless otherwise permitted by the Engineer, the Contractor shall furnish, erect 
and maintain suitable barricades to prevent personal injury or damage to property. 

202.4. Removal of Fences 
 
The work shall consist of removal at locations as instructed by the Engineer.  The re‐useable 
material  shall  be  removed  with  due  care  and  stacked  and stored for re‐use.  The unusable 
material and debris shall be transported and disposed as instructed by the Engineer. 

202.5. Back‐filling 
 
As instructed by the Engineer, holes and depressions caused by dismantling operations shall 
be  back‐filled  with  excavated  or  other  approved  materials  and  thoroughly  compacted  to 
match surrounding areas. 

 
Series 200 – Site Clearing               Page no: 7 of 9 
SRI LANKA OPERATIONS CENTRE

202.6. Measurement 
 
The required and accepted work of dismantling and removal of the structures etc. shall be 
paid as lump sum amount for each structure. 

202.7. Payment 
 
Payment of the lump sum for dismantling and removal of structures shall be made.  
 
Payment shall include full compensation for carrying out the operations described including 
but not limited to excavation, backfilling of excavations using approved materials, preparing 
and shaping, handling, sorting out, salvaging, stockpiling, disposing etc. of material. 
 
Pay Items shall be :‐ 
 
Pay Item  Pay Unit 
 
202(1)  Removal of Existing Structures (Specify the structure)   Lump Sum 
 

203. REMOVAL OF ELECTRIC/TELEPHONE POLES 
 
The  work  of  removal  of  electric/telephone  poles,  transmission  pylons  and/or  line,  where 
required shall be carried out by the appropriate service authority.  The contractor, however, 
may be required to provide assistance to such authorities.   
 
Payment for any such assistance shall be paid under Dayworks. 
 

204.  REMOVAL OF EXISTING PAVEMENT 

204.1.  Description 
 
This item shall consist of the removal of existing pavement (flexible or rigid) including base 
course,  sub‐base  and  shoulders  as  applicable  and  as  directed  by  the  Engineer.  Materials 
suitable for re‐use shall be indicated by the Engineer and shall be stored as instructed by the 
Engineer at locations provided by the Contractor.  
 
The  existing  pavement  and  shoulders  may  consist  of  layers  of  varying  thickness  of  the 
following materials:  
 
- blended and natural sands and soil; 
- brick soling; 
- broken brick and sand aggregate; 
- herring‐bone brick; 
- broken stone aggregate, water‐bound or bitumen penetrated; 
- broken stone with sand, water‐bound or bitumen penetrated; 
- broken stone aggregate/sand bitumen pre‐mix; 
- river gravel/sand bitumen/ pre‐mix; 
- seal‐coats with river pebble chipping stone; 
- seal‐coats with broken stone chipping; 
- other combinations of bricks, stone ,sand and bitumen. 
 

 
Series 200 – Site Clearing               Page no: 8 of 9 
SRI LANKA OPERATIONS CENTRE

Prior  to  the  removal  of  any  existing  road  pavement  the  contractor  shall  excavate  trial  pits  and 
trenches  as  required  by  the  Engineer  to  ascertain  in  detail  the  depth  and  composition  of  the 
pavement and this cost shall be included in the Contractor’s rates generally. 
 
All bituminous seal coats, wearing course and leveling course shall be removed, and if not suitable for 
use elsewhere, shall be disposed of by the Contractor. 
 
All  bricks  and  suitable  bricks  chips  shall  be  removed  and  the  material  may  be  processed  for  re‐use 
where approved by the Engineer. 
 
All  recovered  material  shall  be  the  Contractor’s  property.  Materials  the  Contractor  considers  to  be 
suitable  for  re‐use  in  the  Works  shall  be  taken  to  the  Contractor’s  materials  preparation  areas  for 
stockpiling and re‐processing. The remaining unsuitable material shall be removed off site. 
 
All  recovered  materials,  suitable  for  re‐use  as  sub  base  layer  in  the  works,  as  approved  by  the 
Engineer  are  to  be  reused  after  processing,  in  the  works  and  the  contractor  is  expected  to  take 
account of this when submitting his tender. 
 
The  Engineer’s  approval  to  the  re‐use  of  the  material  shall  be  granted  if  laboratory  test  results 
confirms the material complies with the Specification’s requirements. 

204.2.  METHOD  
 
The  pavement  and  base  course  may  be removed by either hand or machine provided the methods 
used do not cause an undue wastage of material. All recovered pavement material suitable of re‐use 
shall be handled as specified above. 

204.3.  MEASUREMENT 
 
The  unit  of  measurement  for  the  removal  of  existing  pavement  material  shall  be  cubic  metres  of 
bituminous  wearing/leveling  course,  concrete  slab  or  full  pavement  structure  removed,  as  the  case 
may be. The volume shall be measured by taking field measurements for length, width and depth of 
removed area or as directed by the Engineer. 

204.4.  PAYMENT  
 
These materials measured as provided here in above shall be paid for at the contract unit price for 
the  items  shown  in  BoQ.  Payment  shall  be  for  full  compensation  for  removing  separating,  loading, 
transporting  and  stock‐piling  or  otherwise  disposing  of  all  materials,  and  for  all  labour,  equipment, 
tools and incidentals necessary to complete this item of the works.  While quoting rate for this work it 
is expected that the contractor shall include discount for the cost of unusable salvaged materials. 
 
Pay Items shall be :‐ 
 
Pay Item  Pay Unit 
 
204(1)  Removal of Existing Pavement  Lump Sum 
 

 
Series 200 – Site Clearing               Page no: 9 of 9 
SRI LANKA OPERATIONS CENTRE

SERIES 400 ‐ SUB‐BASES, BASES AND SHOULDERS 
 
 
CONTENTS 
 
401. SOIL SUB‐BASES ............................................................................................................................. 3
401.1. DESCRIPTION ............................................................................................................................. 3
401.2. MATERIALS ............................................................................................................................... 3
401.3. MECHANICAL STABILISATION (BLENDING)........................................................................................... 4
401.4. CONSTRUCTION REQUIREMENTS ...................................................................................................... 7
a. Preliminaries .............................................................................................................................. 7
b. Placing and Compaction of Subbase Material................................................................................ 7
c. Degree of Compaction of Subbase................................................................................................ 8
d. Quality Control ........................................................................................................................... 8
e. Finishing Operations ................................................................................................................... 8
f. Protection of Subbase ................................................................................................................. 8
401.5. MEASUREMENT AND PAYMENT ....................................................................................................... 9
a. Measurement............................................................................................................................. 9
b. Payments ................................................................................................................................... 9
402. STABILISED SOIL SUBBASES AND BASES........................................................................................... 9

403. SINGLE SIZED AGGREGATE BASES.................................................................................................... 9

404. WATER BOUND AND DRY BOUND MACADAM BASES....................................................................... 9

405. DENSE GRADED AGGREGATE BASES ................................................................................................ 9


405.1. DESCRIPTION ............................................................................................................................. 9
405.2. MATERIALS ............................................................................................................................. 10
Crushed Rock or Boulder Aggregates.................................................................................................. 10
405.3. CONSTRUCTION REQUIREMENTS .................................................................................................... 11
a. Preparation of Existing Surface .................................................................................................. 11
b. Spreading and Rolling ............................................................................................................... 11
c. Field Density Testing ................................................................................................................. 12
d. Finishing Operations and Quality Control.................................................................................... 12
e. Aftercare.................................................................................................................................. 12
405.4. MEASUREMENT AND PAYMENT ..................................................................................................... 12
a. Measurement........................................................................................................................... 12
b. Payments ................................................................................................................................. 13
406. PENETRATION MACADAM BASES.................................................................................................. 13

407. BITUMENBOUND BASES ............................................................................................................... 13

408. RECONSTRUCTION OF AGGREGATE BASES..................................................................................... 13
408.1. DESCRIPTION ........................................................................................................................... 13
408.2. MATERIALS ............................................................................................................................. 13
408.3. CONSTRUCTION REQUIREMENTS .................................................................................................... 13
a. Rebuilding of Existing Pavement ................................................................................................ 14
b. Field Density Testing ................................................................................................................. 14
c. Finishing Operations and Quality Control.................................................................................... 14
d. Aftercare.................................................................................................................................. 14
408.4. MEASUREMENT AND PAYMENT ..................................................................................................... 14
a. Measurement........................................................................................................................... 14

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 1 of 15 
SRI LANKA OPERATIONS CENTRE

b. Payments ................................................................................................................................. 14
409. SHOULDER CONSTRUCTION .......................................................................................................... 15
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 2 of 15 
SRI LANKA OPERATIONS CENTRE

SERIES 400 ‐ SUB‐BASES, BASES AND SHOULDERS 
 

401. SOIL SUB‐BASES 
 
Delete the Heading and replace with :‐ 
 
SUB‐BASES 

401.1. Description 
 
Delete this Subsection and substitute the following :‐ 
 
This work shall consist of supplying, processing, hauling with any lead and lift, spreading, watering and 
compacting  sub‐base  material  on  a  existing  pavement  or  prepared  and  accepted  sub‐grade  in 
accordance with the specifications and to the lines, levels, dimensions and cross‐profiles shown on the 
drawings or as required by the Engineer and maintaining the finished sub‐base as required. Processing 
shall  include,  where  necessary,  crushing,  screening,  separation,  blending,  and  any  other  operation 
necessary to produce a material conforming to the requirements of this specification. 

401.2. Materials 
 
Delete this Subsection and substitute the following :‐ 
 
The materials for sub‐base course shall consist of any one of the followings: 
 
‐  gravel/brick  aggregates  or  a  mixture  of  gravel/brick  aggregate  and  sand  or a mixture of gravel/brick 
aggregates and naturally occurring granular materials finer than 4.75 mm. 
 
‐  recycled  materials  obtained  from  salvaged  existing  pavement  including  gravel/brick 
aggregates, stone aggregates, broken concrete slabs, broken whole bricks etc. with admixture of local 
sand or naturally occuring granular materials finer than 4.75 mm but excluding materials mixed with 
bituminous  binder.  They  shall  be  clean,  strong,  durable,  of  fairly  cubical  shape,  and  free  of 
disintegrated  pieces,  organic  and  other  deleterious  matter  and  adherence  coatings.  The  aggregate 
shall  preferably  by  hydrophobic  and  of  low  porosity.  Local  sand  or  naturally  occuring  granular 
materials  shall  be  free  from  vegetation,  soft  particles  and  excess  clay  or  any  other  substance.  The 
crushed stone shall comply with the requirements in Section 1708.2 
  
The materials shall be well graded and conform to the following grading limits : 
 
Table 4.1.1 
 
Sieve Size  Percentage by Weight 
Passing 
50 mm  100 
25  mm  70‐90 
19 mm  60‐80 
9.5 mm  40‐70 
4.75  mm  25‐60 
0.075 mm  0‐15 
 
The sub‐base materials shall meet the following physical requirements: 
- The deleterious substances in the sub‐base material shall not exceed the following limits: 
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 3 of 15 
SRI LANKA OPERATIONS CENTRE

 Material   % (By Weight) 
 
 Coal      1.0% 
 Clay, Clay agglomerates  0.25% 
 Soft particles    3.0% 
 Shale/Chert    2.5% 
 
‐  The fraction of the materials passing 0.425 mm sieve shall have a liquid limit less than 30 (AASHTO: T 
89) and a plasticity index not more than 6 (AASHTO: T 90). 
 
‐  The aggregates shall have a Los Angeles abrasion loss (AASHTO: T 96) of not more than 40%. 
 
‐  The materials, when tested in accordance with AASHTO: T 193, have a CBR value of not less than 40% 
after four days soaking when compacted to 98% of the maximum dry density as determined according 
to AASHTO: T 180 Method D. 
 
‐  Stone  chips  shall  be  prepared  by  breaking  and/or  crushing  moderate  to  Stone.  The  material  shall 
comprise hard, durable particles, clean and free from excess thin or elongated pieces. 
 
‐  The bulk specific gravity of stone aggregates and recycled pavement materials shall not be less than 
1.60 and 
 
‐  Water absorption shall not exceed 18%. 
 
  The material for gravel shall be obtained from approved sources in borrow or cut or from such other 
sources of supply as may be specified or approved for use from time to time.  The material used shall 
be  aggregate,  as  dug  soils,  or  material  obtained  by  blending  two  or  more  soils  or  soil/sand  mixes 
referred to as mechanical stabilisation. 
 
The  Contractor’s  attention  is  drawn  to  the  scarcity  of  naturally  occurring  subbase  material  ad  shall 
make  due  allowance  for  mixing  of  materials  in  mechanical  stabilisation  in  accordance  with  Section 
401.3 below. 
 
Material for subbase shall be as specified in Section 1708.2 
 

401.3. Mechanical Stabilisation (Blending) 
 
Delete this Subsection and substitute the following :‐ 
 
Material to be Stabilised 
 
Material  to  be  stabilised  shall  be  any  naturally  occurring  cohesive  or  non‐cohesive  soil  or  processed 
material,  the  properties  of  which  can  be  permanently  improved  by  the  process  of  stabilisation  to 
comply with the requirements of this Specification for the relevant material.  It shall have a minimum 
coefficient of uniformity of 5. 
 
Binder 
 
The binder used shall be either lime or Portland cement, whichever is appropriate for the properties of 
the material to be stabilised. 
Lime  shall  comply  with  the  requirements  of  AASHTO  M‐216.  The  use  of  un‐slaked  lime  will  not  be 
permitted. 
Portland  cement  shall  comply  with  the  requirements  of  AASHTO  M‐85,  Type  II  or  equivalent  ISO 
standard class. The use of rapid‐hardening Portland cement will not be permitted. 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 4 of 15 
SRI LANKA OPERATIONS CENTRE

 
Water 
 
The  water  used  in  mixing  and  curing  concrete  shall  be  tested by methods described in AASHTO test 
Method  T26.  All  water  shall  be  clean  and  free  from  salt,  oil  or  acid,  vegetable  or  other  substance 
injurious  to  the  finished  product.    The  use  of  river  water  will  be  subject  to  the  approval  of  the 
Engineer.  Such  approvals  may  be  withdrawn  from  time  to  time  depending  on  the  condition  of  the 
river. 
 
Mix Design of Material for Stabilisation 
 
Optimum Moisture Content 
 
The  moisture  content  of  the  mixed  material  shall  be  the  optimum  for  compaction  by  rolling 
determined in accordance with AASHTO T‐180. 
 
Binder Content 
 
The binder content that is necessary to achieve the California Bearing Ratio (CBR) requirements of the 
stabilised material shall be determined on specimens compacted to 95% of the maximum dry density 
determined in accordance with the requirements of AASHTO T‐180 at the optimum moisture content 
referred to above. 
 
California Bearing Ratio (CBR) Requirements 
 
The  minimum  soaked  California  Bearing  Ratio  (CBR)  of  the  mixed  material  when  determined  in 
accordance with AASHTO T‐193 at a density of 95% of the maximum dry density when determined in 
accordance with AASHTO T‐180 method D, shall comply with the requirements shown in Table 6‐1. 
Table 401‐1 California Bearing Ratio (CBR) Requirements for Mixed Material for Stabilisation 
 
Layer  Minimum 
CBR 
Sub‐grade  15 
Sub‐base/Gravel Wearing Course  30 
Road‐base  80 
 
Construction Requirements for Stabilisation 
 
Equipment 
The binder shall be placed and uniformly spread on the material to be stabilised at the required rate 
either,  manually  or  mechanically  by  means  of  purpose  made  equipment  approved  by  the 
Engineer/Supervisor. 
Mixing  equipment  shall  be  either  an  agricultural  rotovator  or  purpose  made  rotovating  equipment. 
The required quantity of water shall be dispensed mechanically through either an attachment on the 
mixing equipment or separately by means of a purpose made water bowser. 
The  material  shall  be  compacted  by  the  use  of  approved  vibrating  or  non‐vibrating  rollers  steel 
wheeled or pneumatic tyred rollers.  
Curing  equipment  shall  be  hand  held  bituminous  spraying  equipment  approved  by  the 
Engineer/Supervisor. 
 
Spreading, Mixing and Compaction 
 
Imported material, which is to be stabilised, shall be mechanically spread to the required thickness by 
use of either a grader or a paving machine in such a manner that segregation is avoided. 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 5 of 15 
SRI LANKA OPERATIONS CENTRE

 
Immediately prior to the application of the binder, water shall be evenly distributed over the whole of 
the  surface  to  be  stabilised  and  thoroughly  mixed  into  the  material  to  be  stabilised.    The  moisture 
content  of  the  mixed  material  shall  be  adjusted  as  necessary,  either  by  the  uniform  application  of 
water or drying out, to achieve within –1% to +2% of the optimum moisture content when determined 
in accordance with AASHTO T‐180. 
 
The binder shall be evenly spread at the required rate of application over the whole of the surface to 
be stabilised either manually or by approved mechanical means. 
 
The binder shall be mixed into the material to be stabilised until it is evenly distributed throughout the 
mass of the material using the equipment specified above. 
 
Compaction  shall  be  carried  out  in  accordance  with  the  requirements  of  subsections 
104.4,104.5,104.6..  The  method  employed  shall  ensure  that  the  material  can  be  fully  compacted 
without the development of shear planes and that a well‐closed uncrazed finish can be is achieved. 
 
A sufficient number of compacting units shall be employed to ensure that, from the time the binder is 
first  added,  the  process  of  spreading,  applying  water,  mixing  and  compaction,  shaping  and  final 
finishing, is completed within 2 hours in the case of Portland cement binder and 4 hours in the case of 
lime binder. 
 
Construction Joints 
 
Transverse and longitudinal construction joints shall be formed by cutting back the edges of previously 
stabilised areas to form a sound vertical face. 
 
Curing of Completed Work 
 
The stabilised material shall be protected against rapid drying out for a minimum period of seven days 
immediately upon completion of the work. 
 
The methods of curing shall be one of the following: 
 
2
The application of bituminous emulsion at a rate of between 0.5 to 1.1 Kg/m  of residual bitumen in 
accordance with the requirements of AASHTO. 
 
The manual application of saturated hessian covered by impermeable polythene sheeting which shall 
be firmly held in position. The hessian shall be kept wet for the whole of the curing period. 
 
Trial Areas 
 
Prior to the commencement of normal working the Contractor shall construct a trial area of not less 
than 1000 square metres using the materials and equipment proposed for the work to demonstrate 
compliance with the requirements of this Clause. 
 
Defects 
 
Any remedial work, which is required to rectify defects in the completed layer, shall extend through 
the full depth of the layer and over an area stipulated by the Engineer/Supervisor. 
 
Traffic  
 
No construction equipment or road traffic shall be permitted on the completed layer until the curing 
period has elapsed. 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 6 of 15 
SRI LANKA OPERATIONS CENTRE

 
Weather Limitations 
 
In situ stabilisation shall not be undertaken in the following adverse weather conditions: 
 
During wet conditions; 
 
When rain is imminent; 
 
During excessively windy conditions. 

401.4. Construction Requirements 

a. Preliminaries 
 
No change. 

b. Placing and Compaction of Subbase Material 
 
Add the following :‐ 
 
  The improved sub‐grade underlying the sub‐base shall remain true to cross fall or super elevation and 
be free from any irregularities, cracks, depressions, loose materials or other local defects prior to the 
laying of the sub base. To the extent any such defects might exist the affected areas shall be redone to 
the  requirements  of  specification  and  to  the  satisfaction  of  the Engineer and the sub grade shall be 
protected against any further damage until covered by the sub‐base course. 
 
  Mixing  or  screening  of  aggregates  as  required  to  achieve  the  specified  grading  shall  be  done  in  a 
stacking yard. Mechanical means or a combination of manual labour and machine may do the mixing. 
The materials shall be mixed thoroughly and uniformly to have a homogenous mass also satisfying the 
grading requirements. During mixing, water shall be added to keep the mixed materials moist so as to 
prevent segregation during transportation. 
 
  In any stretch, materials of the both halves of the road will be the same source as well as the same 
grading of aggregates. 
 
  The sub base materials shall be spread in layers, the compacted thickness of which shall not exceed 
150mm. The Engineer, may agree, on satisfactory demonstration by the contractor that for the type of 
sub‐base materials and equipment used, layer thickness up to 200 mm can be rolled to a the specified 
level of uniform compaction. The spreading shall be done using methods acceptable to the Engineer. 
The required amount of water, predetermined from laboratory tests and field trials, shall be added if 
necessary and mixed thoroughly. If the material is too wet it shall be dried by aeration. The moisture 
content of the sub base material during compaction shall be guided by the optimum moisture content 
as determined according to AASHTO: T 180 Method D and as decided by the Engineer on the basis of 
field compaction trials.   
 
 On completion of spreading and watering, the surface shall be shaped as per cross section shown in 
drawing and compacted using approved compaction equipment and procedure 
 
Where  an  existing  subbase  layer  is  to  be  improved  by  the  addition  of  a  layer  of  material  less  than 
100mm thick, the existing surface shall be scarified to a depth instructed by the Engineer, mixed with 
the imported material to form a homogeneous layer of minimum depth 100mm, recompacted to the 
dry  density  specified  for  the  layer  and  formed  to  the  lines  and  levels  shown  on  the  drawings  or  as 
instructed by the Engineer. 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 7 of 15 
SRI LANKA OPERATIONS CENTRE

 
Where subbase is laid over an existing bituminous pavement, the surface shall be punctured to permit 
drainage  through  the  surface.    Puncturing  shall  create  drainage  holes  of  not  less  them  20  mm  in 
diameter though the existing bitumen layer to the underlying base at 500 mm centres on a grid across 
the area being prepared. 

c. Degree of Compaction of Subbase 
 
Delete this Sub section and substitute the following :‐ 
 
The  subbase  shall  be  compacted  to  not  less  than  98%  of  the  maximum  dry  density  (MDD)  of  the 
material as determined by BS1377, Test 13 (Modified) or AASHTO T180. 

d. Quality Control 
 
Delete this sub section and substitute the following :‐ 
   
  After compaction of each layer field density measurements by BS1377 test 15 and or AASHTO: T 191 
will be done at the rate of one test per 300 square metre or less of compacted area. The test shall be 
made  to  the  full  depth  of  the  layer.  Test  locations  should  be  chosen  through  random  sampling 
techniques or as directed by the Engineer. 
 

e. Finishing Operations 
 
Add the following :‐ 
 
  Tests  for  conformity  with  the  specified  surface  tolerances  as  described  in  Section  1601  of  the 
specification shall be made immediately after initial compaction, and variations shall be corrected by 
removing  or  adding  material  as  may  be  necessary.  After  final  rolling,  the  smoothness  of  the  course 
shall  be  checked  again  and  any  irregularity  of  the  surface  exceeding  the  above  limits  and  any  areas 
defective in texture, compaction or composition shall be corrected as directed by the Engineer. 
 

f. Protection of Subbase 
 
Delete this Subsection and substitute the following :‐ 
 
The Contractor shall protect and maintain the subbase at his own expense.  Maintenance shall include 
the immediate repair of any damage or defects which may occur and shall be repeated as often as is 
necessary to keep the subbase continuously intact.  Repairs shall be done in such a manner that will 
ensure  restoration  to  an  even  and  uniform  surface  and  may  involve  scarifying,  watering  and 
recompacting. 
 
Where the sub‐base is required to carry traffic in both directions using part width only, the Contractor 
shall  ensure  that  the  wheel  path  position  is  varied,  by  means  of  coning  or  similar  traffic  control 
measures.  If exposure to traffic over a part width is expected to be prolonged, the Engineer may order 
a protective layer of not less than 100mm of sub‐base quality material to be spread and compacted 
over the part width exposed to traffic. 
 
The sub‐base shall be finished to give a hard dense surface throughout and free from irregularities of 
any  kind.    The  finished  surface  levels  shall  vary  not  more  than  tolerances  indicated  in  Table  1601‐1.  
The deviation from straight edge 3 metres long laid on the surface parallel to the centreline or at right 
angles to the centreline on a cross fall shall not exceed the allowable tolerances. Sub‐base which does 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 8 of 15 
SRI LANKA OPERATIONS CENTRE

not conform to the above requirements shall be reworked, watered and thoroughly recompacted to 
conform. 
 

401.5. Measurement and Payment 

a. Measurement 
 
Delete this Sub section and substitute the following :‐ 
 
The  Subbase  shall  be  measured  by  the  cubic  metres  of  material  compacted  in  place  and  accepted.  
Measurement  shall  be  based  on  the  cross  section  of  the  sub  base  shown  in  the  drawings  and  the 
actual length measured horizontally along the centreline of the surface of the road, or in case of edge 
widening, along the centreline of the widened section. 

b. Payments 
 
Delete after paragraph three and insert the following :‐ 
 
The payment for subbase will be based on the contract unit rate for the completed work and accepted 
of  the  subbase  which  shall  include  full  compensation  for  providing  all  materials  labour,  tools, 
equipment  and  incidentals  necessary  to  carry  out  the  construction  works  in  accordance  with  the 
specifications. 
 
 
The Pay items and Pay units will be as follows :‐ 
 
Pay Item  Unit of Measurement 
 
401(1)  Provide and place Subbase  Cu. Metre 

402. STABILISED SOIL SUBBASES AND BASES 
 
No change. 

403. SINGLE SIZED AGGREGATE BASES 
 
No change. 

404. WATER BOUND AND DRY BOUND MACADAM BASES 
 
No change. 

405. DENSE GRADED AGGREGATE BASES 

405.1. Description 
 
Delete this Sub‐section and substitute the following :‐ 
 
This  work  shall  consist  of  supplying,  processing,  hauling,  spreading,  watering  and  compacting  lower 
base materials on a prepared and accepted graded aggregate sub‐base layer in accordance with the 
specifications  and  the  lines,  levels,  dimensions  and  cross  profiles  shown  on  the  drawings  and  as 
directed  by  the  Engineer  and  maintaining  the  finished  aggregate  base  as  required.  Processing  shall 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 9 of 15 
SRI LANKA OPERATIONS CENTRE

include, where necessary, crushing screening, separation, blending, and any other operation necessary 
to produce a material conforming to the requirements of this specification. 

405.2. Materials 
 
The aggregates for the lower base course shall consist of any one of the following: 
 
‐  crushed rock or boulders from natural sources 
‐  crushed gravel from natural sources 
 
Different  kinds  of  materials  shall  not  be  mixed  together  except  that  sand  or  naturally  occurring 
granular  materials  finer  than  4.75  mm  size  can  be  mixed  with  any  of  these  materials  to  meet  the 
grading requirements. Further within any stretch of road not less than 2 km in length of both sides, 
only one kind of material shall be used. 
 
The contractor shall seek prior approval of the Engineer regarding the kind of materials proposed to be 
used by him in different stretches of road. Any material larger in size than 4.75 mm shall be of crushed 
aggregate with minimum one broken face.  
 
 The materials shall be well graded and conforming to the general requirements of sub section 1701.3 
(a).  and  grading  requirements  of  Table  1701  ‐  5  of  sub  section  1701.3  (b).  and  or  to  the  following 
grading: 

Crushed Rock or Boulder Aggregates 
 
Sieve Size  Percentage by Weight 
Passing 
50 mm  100 
25  mm  70‐90 
19 mm  60‐80 
9.5 mm  35‐70 
4.75  mm  27 ‐ 45 
0.425 mm  6‐16 
0.075 mm  0 – 8 
 
Crushed Gravel Aggregates 
 
Sieve Size  Percentage by Weight 
Passing 
28 mm  100 
19 mm  85‐100 
9.5 mm  60‐80 
4.75 mm  30‐60 
2.36 mm  20‐40 
0.60 mm  5‐25 
0.075 mm  0‐5 
   
The materials shall be free from decomposed stones, organic matters, soft particles, excess clay or any 
other  substance  that  is  considered  deleterious  by  the  Engineer.  The  base  materials  shall  meet  the 
following physical requirements: 
 
‐  The fraction of the materials passing 0.425 mm sieve shall have a liquid limit less than 30 (AASHTO: T 
89) and a plasticity index not more than 6 (AASHTO: T 90). 
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 10 of 15 
SRI LANKA OPERATIONS CENTRE

‐  The aggregates shall have a Los Angeles abrasion loss (AASHTO: T 96) of not more than 40%. 
 
‐  The materials, when tested in accordance with AASHTO: T 193, have a CBR value of not less than 80% 
after four days soaking when compacted to 98% of the maximum dry density as determined according 
to AASHTO: T 180 Method D. 

405.3. Construction Requirements 
 
Delete this Sub section and substitute the following :‐ 

a. Preparation of Existing Surface 
 
Prior to laying of Lower Base Course the underlying layer shall be the surface shall be brushed free of 
dust and extraneous matter and shall be shaped true to cross fall or super elevation and shall be rolled 
as necessary till the surface is smooth, firm and tight. The prepared underlying layer shall be protected 
against damage until covered by the base course. 
 
Where  the  base  course  is  laid  over  an  existing  bituminous  pavement,  the  surface  shall  be  lightly 
scarified  and/or  punctured  to  permit  drainage  through  the  surface  where  the  surface  shape  is  not 
adequately crowned in the opinion of the Engineer, and cleaned of any scarified material before laying 
the  base  course.    During  this  operation  the  Contractor  shall  not  damage  the  underlying  pavement 
layer.  Any damage to the existing underlying layer which results due to careless scarification shall be 
rectified forthwith by the Contractor to the approval of the Engineer at the Contractor’s own cost. 

b. Spreading and Rolling 
 
Delete this Subsection and substitute the following :‐ 
 
The  aggregate  shall  be  spread  uniformly  and  without  segregation  over  the  prepared  surface  of  an 
underlying layer which complies with the specified requirements for the layer concerned, or over the 
surfacing  of  an  existing  pavement,  and  in  quantities  sufficient  to  ensure  that  after  compaction  the 
completed layer will comply with all requirements of layer thickness, levels, cross section and density. 
 
Aggregate shall be spread such that the minimum thickness of each layer after compaction shall be not 
less than 100 mm.  The maximum thickness will depend on the type of compaction equipment used 
and on the specified layer thickness but shall not normally exceed 200 mm compacted thickness unless 
otherwise agreed or instructed by the Engineer. 
 
In  order to minimise for segregation, the material shall be kept wet during transport and spreading.  
The dumps of material shall be spread out to a flat‐surfaced layer with a thickness suitable for mixing.  
Thereafter  the  required  amount  of  water  shall  be  added  and  the  material  thoroughly  mixed  with  a 
suitable approved means until a uniform homogeneous mixture is achieved.  The required amount of 
water  and  moisture  content  shall  be  determined  by  carrying  out  field  trials  but  shall  normally  be 
within 2% of the predetermined optimum moisture content at the time of compaction.  The material 
deposited on the prepared existing surface may be spread and shaped by any method which will not 
cause  the  segregation  of  coarse  and  fine  particles.    The  Contractor  shall  ensure  that  joints  in 
consecutive pavement layers do not coincide.  All areas of segregated coarse and fine material shall be 
corrected  by  re‐mixing  or  removing  and  replacing  with  well  graded  material  to  the  approval  of  the 
Engineer.    The  base  material  shall  be  compacted  using  approved  vibratory  compaction  equipment 
whose vibrators shall function correctly in accordance with the manufacturer’s instructions. 
 
After mixing the material shall be graded to achieve the specified thickness with due allowance made 
for decrease in thickness due to compaction such that after compaction the surface of the aggregate 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 11 of 15 
SRI LANKA OPERATIONS CENTRE

base  is  within  the  specified  level  tolerance.    The  material  shall  then  be  thoroughly  compacted  by 
means of approved equipment so that the specified density is obtained throughout the whole layer. 
The rolling shall be carried out by a series of over lapping longitudinal passes working from the edge 
towards the centre, except on super elevated sections where the rolling shall proceed from the lower 
edge to the higher edge. 
 
The finally compacted layer shall be firm and stable with a closely knit mosaic like surface texture of 
exposed  aggregate  free  from  surface  laminations,  portions  exhibiting  segregation  of  the  fine  and 
coarse aggregates, corrugations or other defects that may be detrimental to the performance of the 
layer.  The surface shall be brushed to ensure a surface free from excess fines and loose aggregate. 
Where, in the opinion of the Engineer, the completed surface of the base is unacceptable, the surface 
shall be rectified in a manner approved by the Engineer. 
The  aggregate  base  shall  be  compacted  to  not  less  than  98%  of  the  maximum  dry  density  of  the 
material as determined by BS1377, Test 13 (Modified) or AASHTO T180. 

c. Field Density Testing 
 
Delete this Subsection and substitute the following :‐ 
 
The degree of compaction shall be checked by field density measurements (BS1377 test 15 or AASHTO 
T191) at the rate of one test for every 300 Sq.m subjected to minimum of two Tests for each section or 
as directed by the Engineer. 

d. Finishing Operations and Quality Control 
 
Add the following :‐ 
 
On completion of the base the Contractor shall remove all windrows to facilitate proper drainage of 
the finished surface. 

e. Aftercare 
 
Delete this subsection and substitute the following :‐ 
 
The  Contractor  shall  protect  and  maintain  the  completed  base  layer  at  his  own  expense  until  the 
surfacing is applied.  Maintenance shall include the immediate repair of any damage or defects which 
may occur and shall be repeated as often as is necessary to keep the layer continuously intact and in 
good condition.  Repairs shall be done in such a manner that will ensure restoration to an even and 
uniform surface.  Traffic shall not be allowed directly on any unprimed base layer unless instructed or 
authorized by the Engineer. 
The completed base shall be primed as soon as possible after approval from the Engineer. 

405.4. Measurement and Payment 

a. Measurement 
 
Delete this Sub section and insert the following :‐ 
 
The  dense  graded  base  shall  be  measured  by  the  cubic  metres  of  material  compacted  in  place  and 
accepted.  Measurement shall be based on the cross section of the base shown in the drawings and 
the actual length measured horizontally along the centreline of the surface of the road, or in case of 
edge widening, along the centreline of the widened section. 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 12 of 15 
SRI LANKA OPERATIONS CENTRE

b. Payments 
 
The  payment  will  be  based  on  the  contract  unit  rate  for  the  completed  work  and  accepted  of  the 
dense  graded  base  which  shall  include  full  compensation  for  providing  all  materials,  labour,  tools 
equipment and incidentals necessary to carry out the construction works to the specifications. 
 
 
The Pay items and Pay units will be as follows :‐ 
 
Pay Item  Unit of Measurement  
 
405(1)  Provide and place 37.5 (40) mm  
Dense Graded Aggregate Base  Cu. metre 

406. PENETRATION MACADAM BASES 
 
No change. 

407. BITUMENBOUND BASES 
 
No change. 

408. RECONSTRUCTION OF AGGREGATE BASES 
 
Delete the heading and replace with:‐ 
 
RECONSTRUCTION OF EXISTING PAVEMENT 

408.1. Description 
 
Delete this Subsection and substitute the following:‐ 
 
This  work  consists  of  the  reconstruction  of  the  existing  bitumen  surfaced  pavement  which  requires 
strengthening and/or reshaping generally in confined areas or patches at locations instructed by the 
Engineer. 
 
Work shall be carried out by scarifying the existing pavement to the depth instructed by the Engineer, 
addition  of  approved  imported  aggregate  and  thorough  mixing  with  existing  pavement  material  by 
grader  or  by  hand  or  other  approved  methods  in  small  areas  to  ensure  an  unsegregated, 
homogeneous material. 

408.2. Materials 
 
Delete this Subsection and substitute the following:‐ 
 
Material for the reconstruction of existing pavements shall be aggregates which conform to the single 
sized  aggregates  or  the  graded  aggregates  as  shown  in  Tables  1701.4  and  1705  of  sub‐section 
1701.3(b) or as instructed by the Engineer. 
The  aggregate  shall  consist  of  hard  durable  particles  of  fragmented  rock  from  a  quarry  approved by 
the Engineer, and shall be free of dust, organic matter, clay and silt or any other deleterious matter. 

408.3. Construction Requirements 
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 13 of 15 
SRI LANKA OPERATIONS CENTRE

Delete this Subsection and substitute the following :‐ 

a. Rebuilding of Existing Pavement 
 
The  existing  pavement  shall  be  sufficiently  scarified  to  enable  the  existing  bituminous  layer  to  be 
removed.  In removing the bituminous layer the Contractor shall ensure that as much of the adhering 
existing  aggregate  as  possible  is  dislodged  and  left  remaining  to  be  mixed  with  the  aggregate  to  be 
added. 
 
Where instructed by the Engineer existing material considered of poor quality shall be removed and 
disposed  of.  Extra aggregate shall then be added to the existing pavement material and thoroughly 
mixed either in place or alongside the area to be strengthened.  Compaction and surface finish shall be 
carried  out  as  specified  in  section  405.    Where  graded  aggregate  of  37.5  (40)  mm  maximum  size  is 
used, the added aggregate shall be in such quantities that after compaction there shall be a minimum 
aggregate thickness at any place of 100 mm and the maximum compacted thickness shall not exceed 
150 mm unless otherwise specified or agreed by the Engineer. 
 
Once mixed the material shall be compacted to not less than 98% of the maximum dry density of the 
material as determined by BS1377, Test 13 (Modified) or AASHTO T180. 

b. Field Density Testing 
 
The degree of compaction shall be checked by field density measurements (BS1377 test 15 or AASHTO 
T191) at the rate of one test for every 100 Sq.m. 

c. Finishing Operations and Quality Control 
 
The rebuilt pavement shall be finished to the requirements of section 1601. 
 
The quality of the material shall be controlled in accordance with section 1602. 

d. Aftercare 
 
The Contractor shall protect and maintain the completed pavement layer at his own expense until the 
following layer is applied.  Maintenance shall include the immediate repair of any damage or defects 
which may occur and shall be repeated as often as is necessary to keep the layer continuously intact 
and in good condition.  Repairs shall be done in such a manner that will ensure restoration to an even 
and uniform surface. 

408.4. Measurement and Payment 
 
Delete this Sub section and substitute the following :‐ 

a. Measurement 
 
The rebuilt aggregate layer shall be measured by the cubic metres of material compacted in place and 
accepted.  Measurement shall be based on the dimensions as instructed by the Engineer. 
 
Scarifying and removal of bituminous pieces shall be measured in square metres of surface area. 

b. Payments 
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 14 of 15 
SRI LANKA OPERATIONS CENTRE

The payment will be based on the contract unit rate for the completed work of the rebuilt layer which 
shall include full compensation for providing all materials other than those specified in the Payment 
Item,  labour,  tools,  equipment  and  incidentals  necessary  to  carry  out  the  construction  works  to  the 
specifications. 
 
The Pay items and Pay units will be as follows :‐ 
 
 
Pay Item  Unit of Measurement  
 
408(1) Scarify and remove existing bitumen layer  Sq. metre 
408(2) Excavate and dispose of surplus material  Cu. metre 
408(3) Provide additional aggregate  Cu. metre 
408(4) Rebuild existing pavement layer  Cu. metre 

409. SHOULDER CONSTRUCTION 
 
No change. 
 

Series 400 – Sub‐Bases, Bases And Shoulders          Page no: 15 of 15 
SRI LANKA OPERATIONS CENTRE

SERIES 500 ‐ SURFACE APPLICATIONS 
 
 
 
CONTENTS 
 
 
 
501.  PRIME COAT .......................................................................................................................2 
501.1.  Description .................................................................................................................2 
501.2.  Materials ....................................................................................................................2 
501.3.  Construction Requirements ........................................................................................2 
501.4.  Measurement and Payment........................................................................................5 
502.  TACK COAT..........................................................................................................................7 

503.  HOT BITUMEN APPLICATIONS .............................................................................................7 

504.  SAND SEALING ....................................................................................................................7 

505.  SEAL COAT TREATMENTS (SURFACE DRESSINGS) .................................................................8 


505.1.  Description .................................................................................................................8 
505.2.  Materials ....................................................................................................................8 
505.3.  Construction Requirements ...................................................................................... 10 
506.  ASPHALTIC CONCRETE SURFACING .................................................................................... 17 
506.1.  Description ............................................................................................................... 17 
506.2.  Materials .................................................................................................................. 18 
506.3.  Mix Requirements .................................................................................................... 18 
506.4.  Job Mix Formula ....................................................................................................... 20 
506.5.  Construction Requirements ...................................................................................... 21 
506.6.  Measurement and Payment...................................................................................... 28 
507.  COLD MIX SURFACINGS ..................................................................................................... 30 
507.6  Measurement and Payment...................................................................................... 30 
 

Series 500 – Surface Applications             Page no: 1 of 30 
SRI LANKA OPERATIONS CENTRE

SERIES 500 ‐ SURFACE APPLICATIONS 
 

501. PRIME COAT 

501.1. Description 
No change 

501.2. Materials 

Delete this sub‐section and substitute the following :‐ 

a. Prime Material 
The prime coat shall consist of penetration grade bitumen complying with sub section 1702.1 
from a source approved by the Engineer, medium curing cutback bitumen MC‐30, MC‐70 or 
MC‐250  complying  with  sub  section  1702.2  from  a  source  approved  by  the  Engineer  or 
bituminous  emulsion  of  grade  CSS‐1  or  CSS1h  complying  with  subsection  1702.3.    The 
application  rate  of  binder  to  be  used  shall  be instructed by the Engineer on Site after field 
trials.  These field trials shall be carried out by the Contractor as instructed by and under the 
supervision of the Engineer and the cost thereof shall be deemed to be included in the prime 
coat rates.  The object of the trials is to achieve the optimum penetration and efficacy of the 
prime coat. 
 
The indicative rate of spread of bituminous material for the prime coat shall be in the range 

of 0.5 to 1.5 l/m
 
b. Mineral Aggregate for blinding 
 
The  blinding  layer,  if  any,  shall  be  crushed  rock  or  river  sand  having  a  grading  within  the 
limits of table 501‐1.  The aggregate shall be clean, hard and free from excessive dust.  It shall 
contain no clay, loam or other deleterious material. 
 
Table 501‐1 Grading Envelope for Sand for Prime Coat 
Sieve size   Percentage Passing  
(mm)  (by mass) 
   
4.75  100 
2.36  80 ‐ 100 
1.18  60 ‐ 95 
.6  30 ‐ 80 
.3  20 ‐ 55 
.075  10 ‐ 30 
   
 

501.3. Construction Requirements 

Series 500 – Surface Applications             Page no: 2 of 30 
SRI LANKA OPERATIONS CENTRE

Delete this sub section and substitute the following :‐ 
 

a. Weather Limitations 
 
The  prime  coat  shall  be  applied  only  when  the  existing  surface  is  dry  or  sufficiently  low  in 
moisture  to  assure  uniform  distribution  of  the  bituminous  material,  when  the  atmospheric 
temperature is above 15oC, and when the weather is not foggy or rainy or rain, in the opinion 
of the Engineer, is imminent.  The temperature requirements may be waived, but only when 
so instructed by the Engineer. 
 
b. Preparation of Surface 
 
The layer to be primed shall be cleaned of all loose and deleterious material by means of a 
rotary  broom  and/or  hand  brooms  or  other  approved  means.    The  brushing  force  shall  be 
sufficient to dislodge all adhering material without damaging the pavement surface.  Scale, 
clay  and  other  foreign  material  shall  be  removed  by  hand  where  instructed.    The  exposed 
surface shall be kept moist up to the time of spraying.  If the moisture content is too high to 
permit full penetration of the prime coat in the opinion of the Engineer the Contractor shall 
delay prime coat application until the moisture content is satisfactory for full penetration as 
instructed by the Engineer. 
 
The surface shall be prepared in this manner to expose a hard tight mosaic of large aggregate 
in the base course.  Hardened impervious films or layers of compacted fine material over the 
larger aggregate shall be removed by appropriate methods which shall avoid damaging the 
underlying surface as approved by the Engineer. 
 
Before any prime material is sprayed the layer to be primed shall be checked for compliance 
with  the  surface  and  other  requirements  specified.    Any  sections  not  complying  with  the 
specifications  shall  be  corrected  and  remedial  measures  taken  to  the  satisfaction  of  the 
Engineer before priming operations are permitted. 
 
c. Application of Prime Coat 
 
Primer shall be applied by the distributor to the prepared upper base at a nominal of 1.0 litre 
per sq. metre (residual bitumen) but shall be within the range 0.80 ‐ 1.40 ltires per sq. metre 
and  temperature  defined  in  Table  501.2  by  means  of  a  bitumen  distributor  or  by  hand 
sprayer or any other means approved by the Engineer. The actual rate of application shall be 
decided  by  the  Engineer  based  on  the  results  of  test  areas.  Sufficient  prime  coat  shall  be 
applied  so  that  maximum  penetration  is  achieved  without  excess  asphalt remaining on the 
surface. The Engineer may alter the previous established rate of application where he deems 
it  necessary.  Additional  primer  shall  be  applied  where  surface  conditions  indicate  it  to  be 
necessary, if the Engineer so directs. No further courses shall be applied until the prime coat 
has been cured as indicated below. 
 
The surfaces of structures and trees adjacent to the areas being treated shall be protected in 
such a manner as to prevent their being spattered or marred. No asphaltic material shall be 
is charged into a borrow pit or gutter. 
 
The  distributor  shall  be  functioning  properly  in  accordance  with  the  manufacturer’s 
instructions with all spray nozzles functioning and delivering prime coat at the same evenly 

Series 500 – Surface Applications             Page no: 3 of 30 
SRI LANKA OPERATIONS CENTRE

distributed  rate.    There  shall  be  no  leakages  or  drips  of  oil,  diesel  or  bituminous  material 
from the distributor. 
 
The total width of primed surface shall be 300mm wider than the specified width of the final 
surfacing or and the edges of the prime shall be parallel to the centre‐line of the road. 
 
The  prescribed  prime  coat  application  rate  may  be  achieved  by  two  or  more  repeated 
applications when necessary to avoid flow of prime coat on steep crossfalls or gradients. 
 
Any  areas  deemed  by  the  Engineer  to  be  deficient  in  prime  coat  after  passage  of  the 
distributor shall be made good by hand‐lance. 
 
Spray record sheets containing details of ambient temperature, spraying temperature, areas 
sprayed  and  quantities  of  materials  used  shall  be  submitted  by  the  Contractor  on  a  daily 
basis for approval by the Engineer. 
 
Table 501‐2 Spraying Temperatures for Prime Coat  
 
Prime Coat Type  Temperature Degrees 
  Celsius  
MC 30    or 45% Cutback Bitumen  40‐70 
MC 70    or 35% Cutback Bitumen  55‐90 
MC 250   or 25% Cutback Bitumen  75‐110 
CSS‐1 or CSS‐1h Emulsion  20‐70 
 
d. Aftercare 
 
Following the prime coat application, the primed, unblinded surface shall be allowed to cure 
for  a  minimum  24  hours  without  being  disturbed  so  as  to  allow  the  prime  coat  to  fully 
penetrate the surface unless full penetration and curing has taken place in the opinion of the 
Engineer in a shorter period.  If after 24 hours the prime coat has not sufficiently cured to 
permit trafficking without being picked up, and the Contractor wishes to open the section to 
traffic,  the  Engineer  shall  either  instruct  that  the  area  be  left  for  a  further  period  until  the 
prime coat has fully penetrated and aired to allow traffic to pass or permit the Contractor to 
place mineral aggregate for blinding applied at a rate and in the places instructed to blot up 
the excess bitumen. 
 
As  soon  as  the  primed  surface  has  cured  sufficiently  or  mineral  aggregate  for  blinding  has 
been applied to allow traffic to pass over the road without the prime coat being picked up, 
the road shall, where practicable, be opened to public traffic for a period of 14 days or less if 
agreed by the Engineer.  During this period the primed area under traffic shall be maintained 
and all damage caused by traffic shall be repaired as instructed by the Engineer at no extra 
cost.    Thereafter  the  contractor  shall  maintain  the  primed  surface  and  shall  protect  the 
surface until the application of surfacing by taking suitable precautions including for example 
supplying and spreading a protective layer of sand at no extra cost. 
 
No payment shall be made for mineral aggregate for blinding which shall only be used for the 
convenience of the Contractor in early opening the primed areas to traffic. 
 
e. Quality Control 
 
Samples  of  the  bituminous  material  that  the  Contractor  proposes  to  use,  together  with  a 
statement  as  to  their  source  and  character  shall  be  submitted  and  approved  before  use of 

Series 500 – Surface Applications             Page no: 4 of 30 
SRI LANKA OPERATIONS CENTRE

such material.  The Contractor shall require the manufacturer or producer of the material to 
furnish  material  subject  to  this  and  all  other  pertinent  requirements.  Only  satisfactory 
materials, so demonstrated by service tests, shall be acceptable. 
 
The  Contractor  shall  furnish  vendor’s  certified  test  reports  for  each  consignment  of 
bituminous  material  supplied.    The  reports  shall  be  delivered  to  the  Engineer  before 
permission is granted for use of the material.  The furnishing of the vendor’s reports shall not 
be  interpreted  as  basis  for  final  acceptance.    All  such  test  reports  shall  be  subject  to 
verification by testing samples of materials received. 
 
Control  of  the  quality  of  materials  and  work  shall  be  exercised  in  accordance  with  section 
1602. 
 

501.4. Measurement and Payment 

 
Delete this sub section and substitute the following :‐ 
 

a. Measurement 
 
The measurements shall be made on one of the following three alternatives for prime coat as 
specified in Bill of Quantities: 
 
Bitumen Penetration Grade 80‐100 cut back using Kerosene or diesel to the extent instructed 
by the Engineer after trails on Site. 
 
The volume of bitumen and the volume of kerosene/diesel will be paid for separately 
according  to  the  pay  items  but  the  total  of  the  two  volumes  shall  be  the  volume  of 
prime  coat  thoroughly  mixed  in  the  correct  proportions  actually  placed  on  the  road 
calculated  at  the  instructed  rate  per  square  metre  over  the  area  specified  to  be 
covered. 

Series 500 – Surface Applications             Page no: 5 of 30 
SRI LANKA OPERATIONS CENTRE

Medium curing MC‐70 from an approved source. 
 
The  volume  of  MC‐70  will  be  paid  as  the  volume  actually  placed  on  the  road 
calculated  at  the  instructed  rate  per  square  metre  over  the  area  specified  to  be 
covered. 
 
Emulsion CSS‐1 or CSS‐1h. 
 
The  volume  of  MC‐70  will  be  paid  as  the  volume  actually  placed  on  the  road 
calculated  at  the  instructed  rate  per  square  metre  over  the  area  specified  to  be 
covered. 
 
b. Payment 
 
Payment will be made for either alternative (I), (ii) or (iii) at the Contract Unit rates or rate for 
the alternative elected and priced by the Contractor and shall include full compensation for 
providing  all  materials,  mixing  where  required,  placement,  labour  equipment  total  and 
incidentals to complete the prime coat as specified. 
 
Pay Item  Pay Unit 
 
Alternative (i) 
 
501 (1) Bitumen Penetration grade80‐100  Litres 
 
501 (2) Kerosene/Diesel as Cutter  Litres 
 
OR 
 
Alternative (ii) 
 
501 (1)a  Prime Coat MC‐70  Litres 
OR 
 
Alternative (iii) 
 
501 (1)b  Prime Coat Emulsion  Litres 

Series 500 – Surface Applications             Page no: 6 of 30 
SRI LANKA OPERATIONS CENTRE

502. TACK COAT 
 
No change. 

503. HOT BITUMEN APPLICATIONS 
 
No change. 

504. SAND SEALING 
 
No change. 

Series 500 – Surface Applications             Page no: 7 of 30 
SRI LANKA OPERATIONS CENTRE

505. SEAL COAT TREATMENTS (SURFACE DRESSINGS) 
 
Delete the text of section 505 and substitute the following :‐ 
 

505.1. Description 
 
Surface Dressing shall be the process of spraying the surface to be dressed with bituminous 
binder,  covering  the  binder  with  natural  or  crushed  stone  cover  aggregate  and  rolling  the 
resulting  surface.  The  Contractor  shall  familiarise  himself  with  the  contents  of  the  British 
Transport & Road Research Laboratory Overseas Road Note 3 ‐ “ A Guide to Surface Dressing 
in Tropical and Sub‐Tropical Countries” ‐ hereinafter referred to as TRRL‐ORN 3. Much of the 
Specification  for  Seal  Coat  Treatment  is  based  on  TRRL‐ORN  3,  including  the  design  of  the 
surface dressing and knowledge of the principles of the Surface Dressing Process is essential 
to the Contractor. 
 
The requirement for a single or double surface dressing shall be specified on the Drawings. 
 

505.2. Materials 

a. Binders 
 
The bitumen binder shall consist of Penetration grade bitumen, cutback bitumen or bitumen 
emulsion, as specified in the relevant item of the Bill of Quantities. 
 
Bitumen  binder  shall  comply  with  sub‐section  1702.1  form  a  source  approved  by  the 
Employer. The grade shall be 80/100 pen unless otherwise specified in the relevant item of 
the Bill of Quantities. 
 
Cutback bitumen binder shall comprise penetration grade 80/100 bitumen and cutter which 
shall be diesel or kerosene or a mixture of both prepared on Site.  The type and proportion of 
cutter if required shall be instructed by the Engineer on Site, in the range 1% to 10% after 
design  of  the  surface  dressing  in  accordance  with  the  procedures  set  out  in  Chapter  5  of 
TRRL‐ORN 3.  
 
Approval  of  the  source  of  supply  of  bitumen  shall  be  obtained  from  the  Engineer  prior  to 
delivery  of  the  material.  The  Engineer  will  require  test  certificates  to  confirm  compliance 
with  the  specified  requirements  and  may  require  samples  for  independent  testing  prior  to 
issue of such approval.  No bituminous material other than that represented by samples and 
test certificates submitted shall be used by the Contractor except with the written consent of 
the  Engineer  and  the  material  shall  comply  in  all  respects  with  the  requirements  herein.  
Blending of bituminous materials from different refineries shall not be permitted without the 
knowledge and approval of the Engineer. 
 
Problems have been experienced with bitumen in some parts of Asia that relate to bitumen 
chemistry, in particular to undesirably high paraffin wax contents.  Some penetration grade 
bitumens may comply with standard specification requirements but perform badly in service 
due to high paraffin wax content or some other compositional factor.  Bitumen proposed for 
use shall be tested to establish the following: 
 
• Viscosity characteristics at 60 and 135 degrees centigrade 

Series 500 – Surface Applications             Page no: 8 of 30 
SRI LANKA OPERATIONS CENTRE

• Rolling  Thin  Film  Oven  Test  (RTFOT  results  indicate  the  resistance  of  bitumen  to 
hardening under the influence of heat and air) 
• Paraffin wax content (DIN test procedure) 
 
Bitumen  emulsion  binder  shall  be  quick‐breaking  anionic  or  cationic,  dependent  on  cover 
aggregate type, from a source approved by the Engineer and having a bitumen content (% by 
weight) of not less than 60 and viscosity (Degrees Angler at 20°C) between 6 and 20.  The 
grade shall be that specified in the relevant item of the Bill of Quantities. 
 
b. Cover Aggregate 
 
Cover  aggregate  specified  in  the  relevant  items  of  the  Bill  of  Quantities  shall  be  obtained 
from a source approved by the Engineer and shall be natural screened gravel or crushed hard 
rock/stone, clean and free from adhering dust, achieved by washing and drying, or any other 
detrimental substance that could impair the adhesion of bitumen and shall conform to the 
requirements of sub‐clause 1701.3 Cover Aggregate for surface. 
 
For specific contracts, pre‐coated cover aggregates shall be required as recommended in the 
contract drawings. Cover aggregate shall be pre‐coated using cut back bitumen penetration 
grade 80‐100 in the ratio of 30% to 70% bitumen to cutter unless otherwise instructed by the 
Engineer. Pre‐coating material shall be thinly and evenly applied by means of a fine pressure 
spray  to  a  moving  stream  of  aggregate  or  by  mixing  with  the  aggregate  in  an  approved 
mixing  plant  so  that  all  particles  are  fully  coated  but  do  not  contain  excess  material.    The 
coating  shall  be  such  that  no  material  will  drip  from  a  particle  of  aggregate  suspended 
between  the  fingers.    Mixing  in  stockpiles  will  only  be  permitted  of  the  Contractor  can 
demonstrate  compliance  for  mixing  to  the  approval  of  the  Engineer.  Aggregate  shall  not 
contain sufficient moisture to cause uneven distribution of the pre‐coating material and shall 
not be used in the work until the moisture has evaporated and the pre‐coating material has 
adhered effectively to the aggregate. Pre‐coating of aggregate shall not be carried out when 
rain  is  imminent  unless  the  aggregate  is  subsequently  covered  or  unless  the  mixing  of  an 
adhesion  agent  in  the  pre‐coating  material  has  been  authorised  by  the  Engineer.  In  areas 
subject  to  dusty  conditions,  pre‐coated  aggregate  shall  not  be  stockpiled  for  any  period 
longer than is necessary for moisture to dry out.  When there is a visible coating of dust on 
the particles the Engineer may direct that portions of the stockpiles be pre‐coated again. 
 
Stockpiling  of  aggregates  will  be  permitted  only  at  locations  approved  by  the  Engineer.    A 
separate stockpile shall be made for each nominal size of aggregate at each location. 
 
The  site  of  the  stockpile  shall  be  cleared  of  all  vegetation  and  debris,  graded  and  drained, 
and  where  the  Engineer  deems  it  necessary,  the  area  shall  be  surfaced  with  a  100  mm 
compacted layer of approved material to prevent contamination of the lower layer of cover 
aggregate. 
 
Unless otherwise approved by the Engineer each stockpile shall be built at least two metes 
high by tipping in layers not more than one metre deep over the whole area of the stockpile.  
The  Contractor  shall  supply  and  planking  or  other  material  required  in  connection  with 
movement of vehicles over and about the stockpiles. 
 
The  bottom  50  mm  layer  of  cover  aggregate  or  any  contaminated  aggregate  shall  not  be 
used in the work unless otherwise approved by the Engineer. 
 
Stockpiles  shall  be  kept  dry  from  rainfall  or  ingress  of  water  by  covering  with  approved 
waterproof membranes and maintaining ground drainage to avoid seepage of ground water 
into stockpile. 

Series 500 – Surface Applications             Page no: 9 of 30 
SRI LANKA OPERATIONS CENTRE

 
c. Adhesion Agents 
 
Prior  to  the  commencement  of  the  surface  dressing,  the  Contractor  shall  carry  out  tests 
under the supervision of the Engineer to determine the adhesion qualities of the aggregate 
and  binder  to  be  used.    These  adhesion  tests  will  include,  but  not  be  limited  to  ,  the 
Immersion  Tray  Test  described  in  Appendix  3  of  TRRL‐ORN  3.    If,  in  the  opinion  of  the 
Engineer,  the  tests  and  trials  indicate  the  need,  the  Engineer  shall  instruct  the  use  of  a 
proprietary  adhesion  agent  :as  admixture  to  the  bitumen  binder;  to  be  applied  along  with 
pre‐coating to the cover aggregate 
 
The Contractor shall supply and apply the specified adhesion agent in the quantities and in 
the  manner  instructed  by  the  Engineer  and  in  accordance  with  the  manufacture’s 
instructions.    The  Contractor  shall  pre‐coat  cover  aggregates  only  when  instructed  by  the 
Engineer. 
 

505.3. Construction Requirements 

a. Bitumen Distributors 
 
Operation 
 
Distributors shall be of constant volume or preferably constant pressure type, self‐propelled, 
equipped with pneumatic tyres and have a minimum binder capacity of 4000 litres and each 
machine  shall  require  the  approval  in  writing  of  the  Engineer  for  use  in  constructing  the 
Works. 
 
Approval will depend on fulfilling the following requirements : 
 
Distributors  shall  be  equipped  with  low  range  speedometer  (fifth  wheel)  in  good  working 
condition,  so  located  to  be  visible  to  the  driver  to  enable  him  to  maintain  accurately  the 
constant  speed  for  spraying  binder  at  the  uniform specified rate.  They shall be fitted with 
either a calibrated pressure gauge which accurately records the pressure of the bitumen at 
the  spray  bar  for  constant  pressure  distributors,  or  a  binder  pump  delivery  meter  for 
constant  volume  distributors.    Binder  pumps  shall  be  capable  of  maintaining  constant 
pressure or constant volume during spray runs. 
 
Distributors  shall  be  fitted  with  burners  in  combination  with  a  circulating  pump  capable  of 
maintaining the bitumen without overheating within the specified temperature range and an 
accurately calibrated thermometer for indicating the spraying temperature of the bitumen. 
 
The  spray  bar  shall  be  capable  of  applying  bitumen  binder  to  a  minimum  width  of  2.30 
meters  with  provision  for  application  of  lesser  widths  by  closing  jets.    The  spray  bar  shall 
have the capability of being raised and lowered to specified heights above the road and of 
being  adjusted  so  that  it  is  parallel  with  the  road  surface.    The  distributors  shall  be  so 
designed to allow the circulation of hot binder through the spray bar when not spraying. 
 
Spray  bars  shall  be  fitted  with  either  slotted  spray  jets  or  preferably  whirling  spray  jets, 
whose  essential  features  are  the  ability  to  spray  binder  uniformly  at  the  specified  rate  of 
spray,  such  that  the  speed  of  the  distributor  can  be  matched  by  the  following  chipping 
spreader  during  its  normal  chip  spreading  operation.    If  whirling  spray  jets  are  fitted  the 

Series 500 – Surface Applications             Page no: 10 of 30 
SRI LANKA OPERATIONS CENTRE

spray  bar  shall  be  protected  by  a  hood  to  reduce  wind  interference.    Distributors  shall  be 
fitted with hand‐lances with nozzle spray attachments for spraying small, inaccessible areas 
and to correct deficiencies in the spray rate. 
 
Prior  to  surface  dressing  operations,  distributors  shall  be  checked  for  leakages  from  spray 
jets  and  any  other  sources  and  these  shall  be  eliminated.    Distributors  shall  then  be 
calibrated  by  a  method  approved  by  the  Engineer  and  under  his  supervision,  to  establish 
uniformity of lateral spray of bitumen to within ±10% permitted variation at any point on the 
surface  from  the  mean  spray  rate.    This  calibration  includes  setting  the  spray  bar  height 
above the surface to be sprayed, in accordance with the manufacturer’s instructions, so as to 
ensure  that  the  designed  overlap  of  jets  is  achieved.    All  spray  jets  shall  be  functioning  so 
that each jet requirement has been achieved.  Calibration shall be undertaken in accordance 
with  the  manufacturer’s  instructions  or  in  accordance  with  TRRL‐ORN  3  ‐  Section  6.3 
Distributor Speed Control and Calibration ‐ to establish the relationship between spray rate 
and  road  speed  for  constant  pressure  distributors  and  in  addition,  bitumen  pump  delivery 
rate and spray bar width for constant volume distributors.  The distributors shall be capable 
of achieving a mean spray rate measured by the TRRL‐ORN 3 Method B, which shall not vary 
by more than ±5% from the specified spray rate. 
 
Safety and Maintenance 
 
Bitumen heating, pumping and spraying operations shall be entrusted only to personnel who 
have  been  adequately  trained  and  who  are  competent  in  the  use  of  the  equipment.  
Unauthorised  personnel  shall  not  be  allowed  to  remain  in  the  vicinity  during  the  above 
operations.  Authorised personnel shall be provided with, and be required to wear, suitable 
protective clothing, i.e. overalls, heat‐proof gloves, boots, helmets and goggles. 
 
Special care is needed when changing the type of binder being used in the distributor.  When 
changing from hot binders to bitumen emulsions, all residual binder in the tank and spraying 
system  shall  be  drained  completely  and  the  spraying  system  flushed  using  diesel.    When 
changing  from  emulsions  to  hot  binders,  all  emulsion  shall  be  drained/flushed  from  the 
distributor in order to avoid foaming when hot binder is loaded.  When it is necessary to load 
hot  binder  after  using  the  distributor  for  spraying  cutback  bitumen,  the  cutback  bitumen 
shall be drained completely and the manhole left open for some time to allow solvent vapour 
to escape. 
 
The  spray  bar  shall  be  emptied  of  binder  by  blowing  with  air,  or  by  diesel  flushing  when 
spraying is suspended for lengthy periods and at the end of each day’s work. 
 
The binder shall be introduced into the distributor at a temperature equal to or just above 
the  spraying  temperature  after  preheating  in  separate  tanks  fitted  with  burners  and 
circulating pumps for this purpose.  The capacity of the decanters/preheating tank shall be 
sufficient to preheat the binder required for the full day’s work. 
 
The distributor burners shall be used only to make relatively small adjustments to the binder 
temperature  and  shall  not  be  used  to  raise  the  binder  from  ambient  to  spraying 
temperature.    Under  no  circumstances  shall  distributor  burners  be  operated  during  the 
spraying operation, or when the level of binder in the tank is less than 150 mm over the top 
of the flues, or when the distributor is moving.  The need for end of day maintenance of the 
distributor is emphasised to reduce fire risk and to ensure its adequate performance when 
next used for binder application. 
 
Maintenance of all equipment for the surface dressing operation shall be under the control 
of  a  competent  senior  mechanic,  approved  by  the  Engineer  and  fully  experienced  in  the 
maintenance of all equipment and in the calibration of the bitumen distributor. 

Series 500 – Surface Applications             Page no: 11 of 30 
SRI LANKA OPERATIONS CENTRE

 
The  Contractor  shall  provide  all  necessary  traffic  control  equipment  and  shall  inform  the 
engineer  at  least  14  days  before  commencing  the  surface  dressing  Work,  of  his  detailed 
arrangements  for  traffic  control.    After  review  the  Engineer  will  inform  the  Contractor  in 
writing of his approval, subject to any modifications to the Contractor’s arrangements which 
he requires for traffic and convenience of the public. 
 
b. Workmanship 
Preparation of Surface 
 
Surface  dressing  operations  shall  not  commence  until  the  Engineer  has  inspected  and 
approved the primed base course.  Major defects or damage shall be rectified by complete 
reworking of the base course after removal and disposal of the defective primed base course. 
 
However if the surface to be treated contains small but limited holes or depressions, which in 
the  opinion  of  the  Engineer  require  treatment,  such  irregularities  shall  be  repaired  by 
removal  of  all  loose  and  defective  material  and  replacement  with  a  patching  mixture 
compatible with the surrounding surface or other material approved by the Engineer, which 
shall be compacted to produce a tight surface conforming with the adjacent area.   
 
Irregularities  which  impair  the  riding  qualities  shall  be  corrected  as  instructed  by  the 
Engineer. 
 
Immediately prior to the application of binder, all loose dust and detrimental material shall 
be  removed  by  sweeping  and  blowing  by  air  compressor  or  by  other  means.    If  necessary, 
adhering mud and other material shall be removed by hand using wire brushes and water.  
Road furniture (manhole covers etc.), shall be protected from bitumen spray with adhesive 
paper  or  similar  material.    Kerbstones,  roadside  furniture  and  any  other  objects  which  will 
not benefit from binder spray shall be protected in a manner approved by the Engineer. 
 
c. Application of Binder 
 
The  application  rate  and  spraying  temperature  of  specified  bitumen  binder,  cut  back  or 
emulsion shall be instructed by the Engineer on Site after design of the surface dressing, in 
accordance with the procedures set out in Chapter 5 of TRRL‐ORN 3.  The range of spraying 
temperature for binders is given in TRRL‐ORN 3 Table 9.  
 
The Contractor shall present his detailed programme and arrangements and methods for the 
planning and execution of the surface dressing process to the Engineer for approval at least 
28  days  before  he  intends  to  commence  this  Work.    The  Contractor’s  authorised 
representative  shall  be  responsible  for  preparation  of  the  programmes  and  arrangements 
and the Contractor shall not commence surface dressing until the Engineer has approved his 
programme. 
 
The Contractor shall base his programme on TRRL‐ORN 3 ‐ Section 7.  The Surface Dressing 
Process, Sub‐Section 7.1 Planning and 7.2 The Surface Dressing Operation ‐ by selecting the 
activities  appropriate  to  his  particular  Work  Programme.    The  Contractor  shall  appoint  a 
surface  dressing  supervisor  approved  by  the  Engineer  who  shall  be  fully  competent  to 
organise  and  implement  the  surface  dressing  operation  with  experience  in  operating  all 
essential equipment. 
 
All  operations  associated  with  the  surface  dressing  process  shall  be  described  in  the 
Contractor’s arrangements and shall include but not be limited to : 

Series 500 – Surface Applications             Page no: 12 of 30 
SRI LANKA OPERATIONS CENTRE

 
method  of  bitumen  supply,  decanting,  cutting  back  where  required,  heating  and  storing, 
transfer to distributor including lists of equipment and capacities; 
location and method of production of cover aggregates and pre‐coating with type and output 
of equipment, including crushers where appropriate; and. 
method of performing the surface dressing process including type and capacity/weight of all 
main and ancillary items of equipment along with workforce details. 
 
The Contractor shall provide, one day in advance, his following day’s surface dressing Work 
Programme, including his expected spray lengths and widths for each run with details of the 
quantity  of  cover  aggregate  available  in  approved  chip  spreaders  standing  by  at  the 
commencement  of  the  spray  run.    Spraying  shall  not  commence  until  sufficient  cover 
aggregate is in this position to cover the area programmed for spraying. 
 
The distributor shall be filled with preheated bitumen binder on the same day, shortly before 
start  of  binder  application.    The  distributor  spray  bar  and  jets  shall  be  preheated  by 
circulating  hot  binder  and  the  jets  operated  for  at  least  10  seconds  for  testing.    This 
operation  shall  be  carried  out  before  each  spray  run,  off‐road  onto  trays,  or  at  a  location 
where no environmental damage will be created.  Jets shall be inspected by the Engineer for 
shape,  direction,  blockage  or  any  other  defects  which  shall  be  corrected  before  spraying  is 
permitted.    At  the  end  of  each  spray  run  the  distributor  shall  be  driven  off‐road  to  avoid 
binder  drippage  on  the  pavement  surface.    Binder  drippage  from  any  location  which  may 
contaminate  the  road  surface  shall  be  sufficient  for  the  Engineer  to  order  removal  of  the 
offending source from the roadway until repairs are completed. 
As  emergency/temporary  measures,  drip  protection  of  the  pavement  surface  shall  be 
provided by use of buckets/trays etc.  These shall be available for use at all times, along with 
equipment for removal of binder spillages on the pavement surface, to the approval of the 
Engineer. 
 
The  Contractor  shall  carry  out  a  trial section of surface dressing at a location instructed by 
the Engineer to demonstrate to the Engineer that his surface dressing operation is capable of 
constructing the surface dressing in accordance with the Specification.  The trial length shall 
be  minimum  200  meters  using  full  spray  bar  width  with  full  width  application  of  cover 
aggregate.    If  the  trial  section  of  surface  dressing  complies  with  the  Specification,  the 
Contractor shall receive payment for the Work in accordance with the Contract as if it were 
Permanent  Work.    If  the  trial  section  of  surface  dressing  fails  to  comply  with  the 
Specification, the Contractor shall carry out further trials until his surface dressing operation 
complies  with  the  Specification.    No  payment  will  be  made  for  trial  sections  that  do  not 
comply with the Specification. 
 
When the Engineer is satisfied that the Contractor is capable of constructing surface dressing 
that complies with the Specification after trial section or sections, the Contractor will receive 
permission to commence surface dressing as permanent Work on the road pavement. 
 
Application of binder shall only be undertaken when the surface is dry or slightly damp, but 
in no circumstances when wet.  If in the opinion of the Engineer rainfall is likely before the 
application  of  binder  or  cover  aggregate  or  the  temperature  or  the  pavement  surface  has 
time to fall below the specified minimum temperature of 15°C, the Engineer will instruct the 
Contractor  to  delay  surface  dressing  work  until  weather  conditions  are  satisfactory.    Areas 
damaged  by  rainfall  shall  be  rectified  by  the  Contractor  without  additional  payment,  in  a 
manner instructed by the Engineer. 
 
If in the opinion of the Engineer the ambient temperature is too cold for surface dressing, the 
Contractor  shall  delay  this  operation  until  the  temperature  increases  to  the  specified 
minimum level of 15°C. 

Series 500 – Surface Applications             Page no: 13 of 30 
SRI LANKA OPERATIONS CENTRE

 
Building paper or other approved protective material shall be used at the start and finish of 
each spray run of sufficient width (not less than 600mm) to enable the distributor to reach 
its calibrated road speed with spray jets open before discharging binder onto the pavement 
under treatment.  Ends of previous surface treatment runs shall be trimmed back to clean, 
straight  transverse  edges  and  these  shall  form  the  start  point  for  subsequent  runs,  with 
completed  work  suitably  protected  as  described  above.    Spray  runs  will  be  limited  to  300 
metres  length  initially  until  the  Contractor  demonstrates  his  ability  to  plan  and  execute 
longer  lengths.    Spray  widths  shall  be  calculated  allowing  for  150mm  longitudinal  overlap 
with adjoining passes and for the width that the following chipping spreader is able to cover.  
Longitudinal sprayed butt joints will not be permitted.  The Contractor shall submit his spray 
width and length proposals to the Engineer for approval. 
 
During  spraying  all  passing  traffic  shall  be  stopped.    If  spray  jets  block,  or  the  chipping 
spreader stops, or any other event occurs which may affect the surface treatment process, 
then the spray bar operator immediately shall stop spraying.  When the defective equipment 
or operation is rectified, spraying may restart with the Engineer’s approval. 
 
The distributor shall be dipped and the binder temperature recorded before and after each 
spray  run  and  spray  length  and  width  recorded  on  approved  Record  Sheets.    The  hot 
application rate shall be calculated and recorded and checked against the specified rate.  The 
calculated actual rate shall not vary by more than ±5% from the specified rate.  The actual 
quantity of binder sprayed corrected to 15.6°C shall be calculated. 
 
At least eight clean pre‐weighed metal spray trays shall be available for sampling the spray 
rate for each spray run, to be used in accordance with TRRL‐ORN 3 ‐ Section 6.3 Method B ‐ if 
so instructed by the Engineer. 
 
To  ensure  that  the  spray  runs  are  parallel  with  the  road  pavement  the  road  centreline  or 
edgeline shall be marked every 25 metres and a string line laid out for the distributor driver 
to follow with the guide bar attached to his side of the cab. 
 
Where a second surface dressing is specified, the first surface dressing shall be left open to 
traffic for a minimum period of 21 days and preferably a longer period before applying the 
second surface dressing unless special approval is obtained from the Engineer for a shorter 
period.    Surplus  chippings  shall  be  removed  by  firm  hand‐brooming  or  power‐brooming 
before applying the second surface dressing. 
 
The  spraying  widths  shall  be  so  selected  that  the  centreline  joint  of  the  second  surface 
dressing is offset from that in the first surface dressing by a minimum 300 mm. 
 
Hand‐pouring  pots  or  hand‐lances  shall  be  used to touch up carefully any parts of the first 
surface missed by the distributor/chipping spreader, or for the treatment of areas in which 
the  distributor  cannot  operate  and  in  this  case  only,  chippings  may  be  applied  by  an 
approved manual method. 
 
 
Areas damaged by excess bitumen or spillages of diesel or other deleterious material shall be 
repaired by careful cutting out and removal followed by careful hand‐poured or hand‐lance 
application of binder and chipping in a manner approved by the Engineer. 
 
The second surface dressing shall be undertaken when the first surface has been approved 
by the Engineer after all surplus chippings are removed, repairs carried out and the surface 
thoroughly  cleaned  as  specified.    The  procedures  to  be  followed  are  those  specified  for 
Surface Dressing in this Specification. 

Series 500 – Surface Applications             Page no: 14 of 30 
SRI LANKA OPERATIONS CENTRE

 
d. Application of Cover Aggregate 
 
The cover aggregate shall be applied at the rate instructed by the Engineer on Site in square 
metres of coverage per cubic metre of loose aggregate after design of the surface dressing, 
in accordance with procedures set out in Chapter 5 of TRRL‐ORN 3. 
 
The  cover  aggregate  shall  be  applied  immediately  after  the  binder  is  applied  and  with  the 
approval of the Engineer may be applied slightly damp if not pre‐coated to depress dust and 
help adhesion.  Aggregate applied to sprayed bitumen emulsion shall, however, be dry. 
 
The  cover  aggregate  shall  be  applied  using  approved  mechanical  spreaders,  which  shall  be 
tailgate mounted on tipper trucks, pushed spreaders or self‐propelled spreaders, specifically 
manufactured  for  the  purpose  and  they  shall  preferably  be  metered  or  any  other  means 
approved by the Engineer.  They shall be capable of uniformly spreading cover aggregate at 
the instructed rate such that they can deliver the rate specified whilst travelling at the same 
speed as the binder distributors during spraying. 
 
The  bitumen  binder  surface  shall  be  covered  with  cover  aggregate  closely  packed  in  one 
layer so that adjacent chippings are touching and no bitumen binder is left uncovered. 
 
A sufficient number of loaded spreaders shall be available at the start of binder application 
to provide cover aggregate over the whole area programmed for spraying.  The Contractor 
shall  not  commence  spraying  unless  sufficient  loaded  spreaders  are  in  place.    Aggregate 
spreading by manual methods will not be permitted except in circumstances where: 
 
a. mechanical spreaders cannot operate effectively or safely; 
b. additional aggregate (back‐up work) is required; 
c. breakdown  of  mechanical  spreaders  occurs  during  the  spreading  operations  before 
stoppage of spraying; 
d. minor surface repairs are instructed. 
e. Labour based contracts. 
 
The  spreader  shall  follow  the  distributor  at  an  interval  not  exceeding  10m  for  hot  binder 
work  and  not  exceeding  5m  when  using  bitumen  emulsion  binder.    A  back‐up  vehicle  or 
other approved means shall be constantly in attendance during surface dressing, from which 
additional aggregate may be hand‐applied to ensure complete and rapid coverage. 
 
 
Where an adjoining pass of the distributor is required, no aggregate shall be applied to the 
binder over a 150 ‐ 200 mm strip so as to permit subsequent overlap. 
 
Under  no  circumstances  will  general  brooming  of  the  chipped  surface  be  permitted.  
Aggregate  spillage  shall  be  removed  with  care  and  excess  aggregates  may  be  brushed  off 
carefully after a minimum of 3 days under traffic, after approval of the Engineer. 
 
The cover aggregate shall be rolled with pneumatic multi ‐ tyred power rollers.  Pneumatic ‐ 
tyred  rollers  shall  have  a  wheel  load  in  the  1000  ‐  2000kg  range.    Tyre  pressures  and  sizes 
shall  be  in  accordance with the manufacture’s recommendations and shall be the same on 
each  axle  and  tyres  shall  be  smooth  and  in  good  condition  to  provide  uniform  rolling  of 
chippings.  Engineer  may  approve  use  of  smooth  wheel  roller  having  sufficient  weight  to 
embed  the  stone  chippings  into  the  binder  without  crushing  them.  The  roller  shall  follow 
directly behind the spreader and shall continue to roll at a speed of approximately 8 ‐ 10kph. 

Series 500 – Surface Applications             Page no: 15 of 30 
SRI LANKA OPERATIONS CENTRE

Engineer shall fix the minimum number of roller passes for each coat, which shall not be less 
than four. Each pass shall overlap the previous pass by minimum half width of roller rolling 
shall be continued until all cover aggregate particles are firmly bedded.  Tyres / Wheels shall 
be  in  good  condition  and  be  kept  clean  and  smooth  to  avoid  pick‐up  of  bitumen  and 
chippings. 
 
e. Quality Control 

Bitumen 
 
The Contractor shall obtain a manufacture’s test certificate clearly cross‐referenced to each 
bitumen  consignment  purchased  for  use  in  the  Works  confirming  compliance  of  that 
consignment with the Specification.  The Contractor shall not use any bitumen until the test 
certificates are received for that batch.  The Contractor shall sample in the presence of the 
Engineer at least every 100 tonnes and every batch of bitumen after delivery to the Site in 
sufficient  quantity  to  carry  out  one  set  of  tests  for  compliance  of  the  bitumen  with  the 
Specification.  Testing will be carried out at a laboratory in Colombo and the Contractor shall 
arrange for transport of the samples in sealed containers to the laboratory. 
 
Bitumen Binder shall comply with the requirement of section 1702. 
 
Cover Aggregate 
 
The  Contractor  shall  sample,  in  the  presence  of  the  Engineer  initially  one  set  of  3 
representative  specimens  for  each  source  of  supply  and  subsequently  when  warranted  by 
changes  in  the  quality  of  aggregates  for  Aggregate  Crushing  Value  or  Los  Angeles  Abrasion 
3
Value  and  at  least  every  50  m   for  Grading  and  Particle  shape  (flakiness  &  elongation).  
Additional samples shall be taken for testing where visible changes in the properties of the 
cover aggregates are observed by the Engineer. 
 
Cover aggregate shall comply with the requirements of sub section 1701.3 
 
Surface finish 
 
The surface finish shall confirm to the requirements of the contract on alignment and surface 
regularity sub section 1601. 
 
f. Measurement 
 
The quantity of binder measured for payment of bitumen emulsion or bitumen grade 80/100 
pen  and,  if  applicable,  cutter  shall  be  the  actual  number  of  litres  at  15.6°C  used  in  the 
accepted Work as instructed by the Engineer on Site.  The conversion of binder material from 
the  spraying  temperature  at  the  time  of  measurement  to  the  volume  at  15.6°C  shall  be 
carried out according to ASTM D 1250‐56, ASTM ‐ IP Petroleum Measurement Tables.  The 
measured quantity shall be calculated as the product of the area sprayed and the application 
rate  instructed  by  the  Engineer  or  the  actual  quantity  sprayed  on  the  area  and  accepted, 
whichever is the lower. 
 
If cut‐back bitumen is used as binder, the quantity of binder measured for payment shall be 
separated  into  bitumen  grade  80/100  pen  and  cutter  in  the  proportion  instructed  by  the 
Engineer for cut‐back bitumen.  The quantities of Bitumen grade 80/100 pen and cutter so 
calculated shall be paid separately at the rates in the relevant items in the Bill of Quantities. 

Series 500 – Surface Applications             Page no: 16 of 30 
SRI LANKA OPERATIONS CENTRE

 
The quantity of adhesion agent measured for payment shall be the actual quantity in litres at 
15.6°C  used  as  instructed  by  the  Engineer.    The  Contractor  shall  inform  the  Engineer  24 
hours  in  advance  of  his  intention  to  apply  the  adhesion  agent  in  the  manner  and  quantity 
instructed by the Engineer so that joint measurement of the quantity used for be agreed.  If 
the Contractor fails to inform the Engineer no payment will be made for adhesion agent. 
 
The quantity of cover aggregate measured for payment shall be the number of cubic metres 
used  as  instructed  by  the  Engineer  on  Site.    The  measured  quantity  shall  be  calculated  as 
either  the  product  of  the  area  which  received  cover  aggregate  and  the  application  rate 
instructed by the Engineer or the actual quantity used and accepted, whichever is the lower. 
 
g. Payment 
 
Payment  shall  be  made  at  the  contract  unit  rates  as  per  the  net  quantities  of  materials 
instructed by the Engineer or actually used and measured for the surface dressing works; per 
litre  for  supplying  and  applying  (a)  bitumen  grade  80/100  pen,  (b)  cutter,  (c)  bitumen 
emulsion  and  (a)  adhesion  agent  (Provisional  Item);  and  per  cubic  metre  for  supply  and 
application  of  cover  aggregate.    This  prices  shall  be  full  compensation  for  furnishing  all 
materials  and  for  all  preparation,  delivering  and  application  of  these  materials  and  for  all 
labour, equipment, tools and incidentals required for completing the surface dressing. 
 
 
Pay Item  Pay Unit 
 
505(1)  Bitumen per grade (80‐100)  Litre 
505(2)  Kerosene/diesel or other approved cutter  Litre 
505(1)a  Emulsion  Litre 
505(3)  Adhesion agent  Litre 
3
505(4)  20 mm chips  m 
505(5)  10 mm chips  m3 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

506. ASPHALTIC CONCRETE SURFACING 

506.1. Description 
 

Series 500 – Surface Applications             Page no: 17 of 30 
SRI LANKA OPERATIONS CENTRE

This work shall consist of furnishing materials, mixing at a central mixing plant, and spreading 
and compacting asphaltic concrete wearing course on an approved base course as and where 
shown  on  the  Drawings  and  as  instructed  by  the  Engineer.    The  wearing  course  will  be 
typically of 50 mm thickness as specified. 
 

506.2. Materials 
 
Materials  used  shall  conform  to  the  requirements  of  the  following,  unless  otherwise 
specified :‐ 
 
(a) The bitumen binder shall be 60‐70 penetration grade bitumen to sub section 1702.1. 
 
(b) The coarse aggregate shall be of nominal maximum size 20 mm and the fine aggregate 
shall conform to the general requirements of sub section 1701.3 (a).  When the coarse 
and  fine  aggregate  are  combined,  along  with  filler  where  required,  the  combined 
grading requirements shall be as given in sub section 506.3 for wearing Course Type 3. 
The  Contractor  shall  control  the  production  of  course  aggregate,  fine  aggregate  and 
filler for asphaltic concrete at the crushing and screening plant such that the grading 
of aggregates in stockpiles shall be uniform and consistent throughout the period of 
asphalt  production  and  paving  operations.    Regular  sampling  of  stockpiles  by  the 
Contractor  shall  be  carried  out  to  demonstrate  the  uniformity  and  consistency  of 
grading of the aggregate production to the satisfaction of the Engineer.  If significant 
changes  occur  to  the  aggregate  grading  during  crushing  and  screening  this  will 
immediately effect the grading of the asphaltic concrete mix produced by the asphalt 
plant  rendering  it  out  of  compliance  with  the  job  mix  formula.    Therefore  the 
Contractor  shall  take  immediate  steps  to  rectify  the  irregularity  in  aggregate 
production  and/or  submit  a  new  job  mix  formula  based  on  the  changed  aggregate 
gradings for the approval of the Engineer. 
 
Filler, where separately used in the mix, shall be cement, hydrated lime, crusher fines 
or other inert material to section 1706. 
 

506.3. Mix Requirements 

a. Combined Grading of Aggregate and Binder Content 
 
The  grading  requirements  for  the  combined  aggregate  and  the  binder  content  shall  be  as 
given in Table 506‐1 for the wearing courses type 1,2,3,4.  The wearing course shall be Type 3 
with nominal maximum size of aggregate 20mm. 

Series 500 – Surface Applications             Page no: 18 of 30 
SRI LANKA OPERATIONS CENTRE

Table  506.1  ‐  Aggregate  grading,  binder  content  and  thickness  requirements  for  wearing 
courses 
 
Mix classification   Wearing  Wearing  Wearing  Wearing 
Course  Course  Course  Course 
1  2  3  4 
Thickness mm ‐ Max.  75  45  75  75 
Min.  35  25  40  35 
Sieve Size         
mm/μm         
25.0  ‐  ‐  100  ‐ 
19.0  100  100  90 ‐ 100  100 
12.5  80 ‐ 100  80 ‐ 100  ‐  79 ‐ 90 
  9.5  65 ‐   93  73 ‐   93  56 ‐   80  60 ‐ 80 
  4.75  45 ‐   73  52 ‐   69  35 ‐   65  40 ‐ 65 
  2.36  35 ‐   58  32 ‐   50  23 ‐   49  27 ‐ 48 
  1.18  26 ‐   48  25 ‐   43  ‐  20 ‐ 40 
600  18 ‐   38  19 ‐   35  ‐  15 ‐ 35 
300  13 ‐   28  14 ‐   27  05 ‐   19  10 ‐ 25 
150  08 ‐   20  09 ‐   18  ‐  07 ‐ 17 
 75  04 ‐   12  05 ‐   10  02 ‐   08  05 ‐ 09 
   
Percentage  binder  4.0‐6.5  3.5‐6.0  3.5‐6.0  4.0‐6.5 
content by total weight of 
mix 
 
Note 
 
The sieve sizes used herein are of ASTM designation.  However equivalent BS sizes as given in 
Table 107‐1 of section 107, may be used with the prior approval of the Engineer. 
 
b. Mix Characteristics 
 
The  mix  characteristics  as  determined  by  the  Marshall  Mix  Designs  procedure  shall  be  as 
given in Table 506‐2(a) and 506‐2(b) for binder courses and for wearing courses respectively 
for  low,  medium  or  high  traffic  depending  on  whether  the  cumulative  number  of  standard 
axles,  for  the  design  life  of  the  surfacing,  is  less  than  10,000  or  between  10,000  and 
1,000,000 or greater than 1,000,000 respectively. 
 
In  the  determination  of  the  above,  laboratory  samples  shall  be  prepared  and  tested  as 
specified in sub section 1802.4(a). 
 
The wearing course mix shall be determined by using Table 506‐2(b) ‐ High Traffic category. 
 

Series 500 – Surface Applications             Page no: 19 of 30 
SRI LANKA OPERATIONS CENTRE

Table 506‐2(a) ‐ Binder Courses 
 
No  Description  Low Traffic  Medium Traffic  High Traffic 
1  Marshall  stability  Not less than 2.25  Not less than 4.5  Not less than 7.0 
in KN 
2  Marshall  flow  8 to 20  8 to 18  8 to 16 
(0.25 mm) 
3  Air  voids  in  mix  3 to 7  3 to 7  3 to 7 
percent 
4  Voids  in  mineral  Not less than 14  Not less than 14  Not less than 14 
aggregate percent 
 
 
Table 506‐2(b) ‐ Wearing Courses 
 
No  Description  Low Traffic  Medium Traffic  High Traffic 
1  Marshall  stability  Not less than 2.25  Not less than 3.33  Not less than 7.0 
in KN 
2  Marshall  flow  8 to 20  8 to 18  8 to 16 
(0.25 mm) 
3  Air  voids  in  total  3 to 5  3 to 5  3 to 5 
mix (percent) 
4  Voids  in  mineral  Not less than 14  Not less than 14  Not less than 14 
aggregate 
(percent) 
 
 

506.4. Job Mix Formula 
 
The Contractor shall submit to the Engineer in writing at least two weeks before the start of 
the work, the job mix formula proposed to be used by him for the work based on trial mix 
designs carried out in accordance with “Mix Design Methods for Asphalt Concrete (MS ‐ 2)” 
published by the American Asphalt Institute or similar approved method which shall give the 
following details :‐ 
 
(i) A single percentage of aggregate passing each specified test sieve. 
(ii) A single percentage of binder content by total weight of total mix. 
(iii) A single temperature at which the mix is emptied from the mixer which shall exceed 
145 degrees C. 
(iv) A  single  temperature  at  which  the  mix  is  to  be  delivered  to  the  paver  on  the  road 
which shall exceed 135 degrees C. 
 
In addition the Contractor shall given the sources, locations of all materials and the details of 
the mix design based on requirements given in Table 506‐2 (a) and (b). 
 
The Engineer shall check the proposed Job Mix Formula for compliance with the Specification 
and shall approve the same when compliance is achieved. 
 
All mixes produced shall conform to the job mix formula approved by the Engineer within the 
ranges of tolerances given in Table 506‐3. 
 
Table 506‐3 ‐ Job Mix Tolerance for Single Test 
 

Series 500 – Surface Applications             Page no: 20 of 30 
SRI LANKA OPERATIONS CENTRE

Aggregate Passing 12.5 mm and larger  ± 8% 
Aggregate Passing 9.5 mm and 4.7 mm sieves  ± 7% 
Aggregate Passing 2.36 mm and 1.18 mm sieves  ± 6% 
Aggregate Passing 600 μm and 300 μm sieves  ± 5% 
Aggregate Passing 150 μm sieves  ± 4% 
Aggregate Passing 75 μm sieves  ± 3% 
Binder content percent weight of total mix  ± 0.4% 
Temperature of mixture when emptied from mixer  ± 10 C% 
Temperature of mixture when delivered on road  ± 10 C% 
 
If a change in the materials or source of materials is proposed, or a change in the grading of 
the coarse and fine aggregate or filled occurs a new job mix formula shall be submitted and 
approved before the mix containing the new material is delivered to site. 
 
When  unsatisfactory  results  or  changed  conditions  make  it  necessary,  the  Contractor,  if 
required, shall submit a new job mix formula to the Engineer for approval. 
 

506.5. Construction Requirements 

a. Preparation of Existing Surface 

 
(i) Where asphaltic concrete surfacings are laid over newly constructed aggregate bases, 
prior to construction, the surface shall be cleaned of extraneous matter and applied 
with a prime coat as per section 501. 
 
(ii) Where  asphaltic  concrete  surfacings  are  laid  on  existing  pavements,  the  surfaces  of 
such pavements shall be corrected to the required width and profile as instructed.  All 
potholes, ruts, depressions and damaged edges, shall be corrected as given in sections 
1102 & 1103.  Areas requiring reshaping and strengthening shall be corrected as per 
section 408. 
 
On  these  corrected  surfaces,  where  required,  a  tack  coat  shall  be  applied  as  per 
section 502. 
 
iii. Where  the  mix  is  laid  over  cement  concrete  pavements  or  bridge  decks,  joints  and 
cracks  shall  be  cleaned  and  filled  with  bituminous  material  as  approved,  and  any 
unevenness of the surface shall be corrected as required.  A tack coat as per section 
502 shall then be applied to the surface. 
b. Weather Limitations 

 
The bituminous mix shall not be laid during rainy weather or when the surface on which it is 
laid is damp or wet. 
 

c. Limitations Due to Equipment Etc. 
 
No  work  shall  be  carried  out  when  there  is  insufficient  equipment  for  hauling,  spreading, 
compaction and finishing or insufficient labour to ensure progress at a rate compatible with 
the output of the mixing plant to ensure a continuous paving operation. 

Series 500 – Surface Applications             Page no: 21 of 30 
SRI LANKA OPERATIONS CENTRE

 
d. Thickness of Compacted Mix 

 
Tolerances for the wearing coarse thickness shall be in accordance with clause 1601. 
 

e. Mixing Plant and the Preparation of Mix 
 
An  approved  mixing  plant  of  the  automatic  batch  type  or  of  the  continuous  type  shall  be 
used  for  the  preparation  of  the  mix,  which  shall  have  the  capacity  sufficient  to  supply  the 
paver continuously.  The asphalt mixing plant shall generally comply with and be operated in 
accordance  with  the  “Asphalt  Plant  Manual  (MS‐3)  “  published  by  the  American  Asphalt 
Institute. 
 
The mixer shall be capable of accurately batching the aggregates, filler and binder and mixing 
same  thoroughly  so  that  the  mixed  material  on  discharge  from  the  mixer  is  uniform  in 
composition and that all aggregate particles are completely coated. 
 
Batch type plants, shall be equipped with suitable means for accurately weighing of each bin 
size of aggregate and the filler.  The scales of such weighing mechanisms shall be calibrated 
at  the  frequencies  as  instructed  by  the  Engineer  using  standard  weights.    The  Contractor 
shall always have at hand sufficient weights for such calibration. 
 
In  continuous  type  plants  the  gate  openings  of  the  aggregate  shall  be  calibrated  by  an 
approved  process  of  weighing  test  samples.    The  bitumen  feed  line  shall  have  a  by‐pass 
arrangement  in order that the meter can be calibrated.  These calibrations shall be carried 
out at frequencies instructed by the Engineer. 
 
The mixing plant shall be capable of heating the aggregate and the binder separately to the 
appropriate  temperatures.    When  wet  aggregate  is  used,  the  plant  shall  have  an  added 
capacity to dry the aggregate before heating. 
 
The binder and mineral aggregate shall be heated separately to temperatures between 140 
and 170 degrees C, and 150 and 170 degrees C respectively.  The materials shall be mixed at 
temperatures within absolute limits of 145 and 170 degrees C, even allowing for tolerances. 
 
The  plant  shall,  if  situated  in  urban  areas  or  required  by  the  Ministry  of  Transport  and 
Highways/Environmental  Authority  be  equipped  with  an  approved  dust  collector  so 
constructed  as  to  waste  or  return  uniformly  to  the  elevator  all  or  any  part  of  the  material 
collected. 
 
The mixing plant shall be capable of loading the mix into transport vehicles in such a manner 
that segregation does not occur. 
 
 
 
In addition the plant shall be provided with the following :‐ 
 
Covered  protected  ladders  or  stairways  with  secure  hand  rails  in  adequate  number 
which shall be placed at all points required for accessibility to all operations. 
Covering devices for pulleys, belts and drive mechanisms and other moving parts. 
Ample and unobstructed space on the mixing platform. 

Series 500 – Surface Applications             Page no: 22 of 30 
SRI LANKA OPERATIONS CENTRE

A clear and unobstructed passage at all times in and around the tipper loading space 
which shall be kept free from drippings from the mixing platform. 
Insulated  flexible  pipe  connections  to  carry  hot  bitumen  from  the  heated  storage 
tanks to the mixer. 
 
f. Transport of Mix 
 
The  mix  shall  be  transported  from  the  mixing  plant  to  the  point  of  use  in suitable purpose 
made tipping trucks. 
 
The  trucks  shall  be  in  good  mechanical  condition  at  all  times.    They  shall  have  clean  and 
smooth  metal  beds,  that  have  been  sprayed  with  water  or  lime  solution  or  any  other 
detergent solution approved by the Engineer, to prevent the mix from adhering to the beds.  
The amount of sprayed fluid shall however be kept to a practical minimum.  All precautions 
shall  be  taken  to  avoid  segregation  of  mixed  materials  and  to  ensure  that  they  do  not 
become contaminated with dust or foreign matter. 
 
Any  truck  causing  excessive  segregation  of  bituminous  material  by  its  spring  suspension  or 
other  contributing  factors,  or  that  shows  oil  leaks  in  detrimental  amounts  or  that  causes 
undue delays shall, upon instruction of the Engineer, be removed from the Works until such 
conditions are corrected. 
 
When instructed by the Engineer, each load shall be covered with a properly fastened canvas 
or  other  suitable  material  of  such  size  as  to  protect  the  mix  from  the  weather  or  dust.    In 
order  that  the  mix  shall  be  delivered  to  the  Site  within  the  specified  temperature  range, 
during cold weather or during long hauls, properly fastened insulating covers shall be used. 
 
Loading and transporting shall be co‐ordinated such that spreading, compacting and finishing 
shall  be  completed  during  daylight  hours unless adequate illumination, as approved by the 
Engineer, is provided by the Contractor.  Working during darkness will not be permitted. 
 
The mix shall be delivered to the paver at the site at a minimum temperature of 135 degrees 
Centigrade. 
 
g. Paving Plant and Laying of the Mix 
The mix shall be laid immediately after transporting, by means of approved mechanical self 
powered  pavers.    They  shall  be  capable  of  spreading,  finishing  and  providing  initial 
compaction  to  the  mix  so  that,  the  surfacing  can  be  finished  to  the  required  lines,  grades, 
levels,  dimensions  and  cross  sections  intended,  either  over  the  entire  width  or  over  such 
other partial widths as may be practicable.  The paving operation shall generally be carried 
out  in  accordance  with  the  “Asphalt  Paving  Manual  (MS‐8)”  published  by  the  American 
Asphalt Institute. 
 
The pavers shall be equipped with receiving hoppers and spreading screws of the reversing 
type to place the mix evenly in front of adjustable steering devices and shall have reverse as 
well  as  forward  travelling  speeds.    They  shall  also  be  furnished  with  a  vibrating  screed 
(levelling)  unit  equipped  with  suitable  burners  or  heaters  and  tamping  bars  or  vibration 
attachments all operating in accordance with the manufactures instructions. 
 
The pavers shall be able to confine the edges of the pavement to true lines without the use 
of stationary side forms.  The equipment shall include blending or joint levelling devices for 
smoothing and adjusting longitudinal joints between lanes.  The assembly shall be adjustable 

Series 500 – Surface Applications             Page no: 23 of 30 
SRI LANKA OPERATIONS CENTRE

to achieve the cross sectional shape and level tolerances prescribed and shall be so designed 
and operated as to place the required thickness and weight per square metre of material. 
 
A fully trained and experienced operator shall be in direct charge of the paver at all times.  
The pavers shall be operated so as to avoid dragging of the material. 
 
The bituminous mix, after spreading, finishing and initial compaction by the paver, shall have 
a smooth surface free of irregularities causes by dragging, tearing or gouging. 
 
During construction, if it is seen that the paver in operation leaves on the surfacing tracks or 
indented areas or other objectionable irregularities or segregation of mix, which cannot be 
satisfactorily corrected by normal operations, the use of such a paver shall be discontinued 
forthwith and another satisfactory paver shall be provided by the Contractor. 
 
In  narrow  widths  and  in  restricted  areas  where  the  paver  cannot  operate,  the  mix  may  be 
manually laid, in which case, care shall be taken to avoid segregation.  Manually laid strips 
shall be rolled at the same time as the paver laid work and allowance shall be made for extra 
compaction  of  these  strips  using  appropriate  approved  purpose  made  compaction 
equipment.    Any  defects  in  the  laid  surface  shall  immediately  be  rectified  before  rolling 
commences and there shall be no unnecessary scattering back by hand of material on paver 
laid work. 
h. Compaction Procedure 
Immediately  after  the  mix  has  been  spread  as  struck  off,  the  surface  shall  be  checked  and 
any irregularities adjusted.  Rolling shall commence as soon as the material will support the 
roller  without  undue  displacement  or  cracking.    The  mix  shall  then  be  thoroughly  and 
uniformly compacted by rolling, according to the sequence of rolling as given below :‐ 
 
(i) Transverse joints 
(ii) Longitudinal joints, where applicable 
(iii) Outside edge 
(iv) Initial or breakdown rolling 
(v) Second or intermediate rolling 
(vi) Finish or final rolling 
 
Normally the first rolling of all joints and edges and the initial or breakdown rolling, shall all 
be  done  with  static  weight  (tandem  or  three  wheel)  or  vibratory  steel  wheeled  tandem 
rollers and the second or intermediate rolling with pneumatic tyred rollers.  Use of any other 
rollers for the above purposes shall be with the prior approval of the Engineer.  During initial 
or breakdown rolling, the direction of travel of the roller shall be such that the powered or 
driving wheel passes over the uncompacted mix first, before the driven wheel.  The second 
intermediate rolling shall follow the initial or breakdown rolling as closely as possible while 
the bituminous mix is still plastic and at a temperature that will result in maximum density.  
The  final  rolling  shall  be  accomplished  with  static  weight  tandems  or  vibratory  tandems 
(without vibration) while the material is still warm enough for removal of roller marks. 
 
In  general  the  type  roller  or  roller  combination  to  be  used  shall  be  proposed  by  the 
Contractor  for  the  approval  of  the  Engineer  prior  to  the  commencement  of  work  and  the 
rollers shall satisfy the requirements given in 506.5(j). 
 
The  speed  of  the  rollers  shall  not  exceed  the  limits  given  in  table  506‐4  and  shall  be  at  all 
times be slow enough to avoid displacement of the hot mix. 
 
Table 506‐4 
 

Series 500 – Surface Applications             Page no: 24 of 30 
SRI LANKA OPERATIONS CENTRE

Type of roller  Speed (Km/hr) 
 
  Breakdown  Intermediate  Finish 
Steel Wheeled Rollers  3  5  5 
Pneumatic Tyred Rollers  5  5  8 
Vibratory Rollers  5  5  ‐ 
 
 
During stages of initial, intermediate and final rolling, rolling shall commence at the low side 
of  the  spread  and  progress  towards  the  higher  side  parallel  to  the  centre  line  of  the 
pavement. 
 

Series 500 – Surface Applications             Page no: 25 of 30 
SRI LANKA OPERATIONS CENTRE

When the roller has passed over the whole area once, any high spots or depressions which 
become  apparent  shall  be  corrected  by  either  removing  or  by  adding  fresh  material.    The 
rolling  shall  be  continued  till  the  entire  surface  has  been  compacted  adequately  and  the 
roller  marks  have  been  eliminated.    Each  pass  of  the  roller  shall  uniformly overlap not less 
than  one  half  of  the  proceeding  pass.    The  roller  wheels  shall  be  kept  damp  if  required  to 
avoid  the  material  sticking  to  the  wheels  and  being  picked  up.    However,  the  quantity  of 
water used for this purpose shall be the minimum required and shall not form puddles on the 
area under compaction. 
 
When using a vibratory roller for the compaction of a surfacing the vibration shall be turned 
off before the roller stops when reversing direction, and turned on after it starts in the new 
direction. 
 
Vibratory  rollers  shall  not  be  used  for  surfacings  of  thickness  less  than  50mm,  unless 
otherwise approved by the Engineer. 
 
The breakdown and the intermediate rolling shall be carried out at temperature not less than 
135 degrees C and 115 degrees C respectively. 
 
The final rolling shall be completed before the temperature of the mix falls below 90 degrees 
C. 
 
Rollers shall not be allowed to stand on newly laid material until 6 hours has elapsed after 
completion of the compaction of the surfacing. 
 
When  the  bituminous  mix  is  spread  in  areas  that  are  inaccessible  to  rollers  such  as  places 
near  kerbs  and  manholes  etc.,  compaction  shall  be  achieved  by  hand  tampers,  mechanical 
tampers,  or  small  vibrating  plate  compactors  to  the  approval  of  the  Engineer.    In  such 
locations spreading and compacting shall be carried out promptly before the mix cools below 
a minimum of 120 degree C. 
 
The  density  of  all  samples  taken  from  the  compacted  surface  course  shall  not  be  less  than 
98% of the Marshall Density at the point appropriate to the locations.  The sample densities 
shall be determined as given in sub section 1802.4(c). 
 
i. Not in Use 

j. Requirements of Compacting Equipment 

 
(i) General 
Generally,  with  each  paver,  a  minimum  of  3  rollers  shall  be  provided  by  the 
Contractor.    On  small  projects  involving  a  total  of  less  than  5000  tonnes  of  material 
the minimum requirements shall be one tandem roller. 
 
All  rollers  shall  be  self  propelled,  capable  of  being  reversed  without  backlash  and 
equipped with power steering, dual controls allowing operation from either the right 
or left side.  They shall have water tanks with sprinkler systems to ensure even wetting 
of rolls or tyres. 
 
The rolling surface of the wheels of a steel wheel roller shall be checked for wear.  If 
grooves or pits have worn into the rolling surface, the roller shall not be used on the 
work area. 

Series 500 – Surface Applications             Page no: 26 of 30 
SRI LANKA OPERATIONS CENTRE

 
Each  roller  shall  have  a  calibration  chart  showing  the  relationship  between  depth  of 
ballast  and  weight  and  giving  the  tare  weight  of  the  roller.    Each  roller  shall  be  in  a 
good condition and shall be operated by a competent and experienced driver. 
 
(ii)  Steel Wheeled Rollers 
Steel  wheeled  rollers  (tandem  or  three  wheel)  shall  weigh  not  less  than  8  metric 
tonnes.  The minimum rolling pressure of the rear wheels of each three wheeled roller 
or at least one roll of each tandem roller shall be 35 KN/m of roller width. 
 
(iii) Pneumatic Tyred Rollers 
Pneumatic tyred rollers shall have not less than seven wheels (3 wheels on the front 
axle and four on the rear) fitted with smooth tread compactor tyres, of equal size and 
construction,  capable  of  operating  at  inflated  pressures  upto  850  kN/square  metre.  
The wheels shall be able to move up and down independently of one another.  Wheels 
shall be equally spaced along both axle lines and arranged so that tyres on one axle 
line tract falls midway between those on the other with an overlap.  The tyres shall be 
kept  inflated  to  the  manufacturers  specified  operating  pressures  with  variation  not 
exceeding 36 kN/square metre.  Means shall be provided for checking and adjusting 
the tyre pressures on the job at all times.  For each size and type of tyre used, each 
roller  shall  have  charts  or  tabulations  showing  the  relationship  between  wheel load, 
inflation  pressure  and  tyre  contact  pressure,  width  and  area.    Each  roller  shall  be 
equipped  with  means  of  adjusting  its  total  weight  by  ballasting  so  that  the  load  per 
wheel  can  be  varied  from  1,500  to  2,500  kilograms.    In  operation  the  tyre  inflation 
pressure and the wheel load shall be adjusted, as required by the Engineer, to meet 
the  requirements  of  each  particular  application  in  general  the  compaction  of  any 
course with a pneumatic tyred roller shall be accomplished with contact pressures as 
high as the material will support. 
 
(iv) Vibratory Rollers 
Generally  Vibratory  rollers  shall  be  equipped  with  automatic  vibration  control which 
cuts out the vibratory system before the machine comes to a halt. 
 
The  minimum  operating  weight  of  the  roller  shall  be  6  tonnes  and  minimum  drum 
width  0.9  m,  the  minimum  linear  drum  applied  force  44  KN/m  and  the  minimum 
frequency of vibration 33 Hz (200 cycles/min). 
 
k. Joints 
 
Both longitudinal and transverse joints in successive courses shall be staggered so as not to 
be one above the other.  As far as practicable, longitudinal joints shall be arranged so that 
the joints in the top course shall be at the location of the line dividing the traffic lanes, and 
the transverse joints shall be staggered at a minimum of 250 mm and be straight. 
 
Longitudinal  and  transverse  joints  shall  be  made  in  a  careful  manner  so  that  well  bonded 
sealed joints are provided for the full depth of the course.  No mixture shall be placed against 
previously rolled material unless the edge is trimmed vertically to line and the vertical edge 
applied  with  a  very  thin  coating  of  binder  just  before  additional  mix  is  placed  against  the 
previously compacted material. 
 
Paving shall be as nearly continuous as possible and rollers shall pass over the unprotected 
end of freshly laid mix only when authorised by the Engineer.  In all such cases provision shall 
be made for a properly bonded and sealed joint with the new surface for the full depth of 
the course as specified above.  Before placing mix against them, all contact surfaces of kerbs, 

Series 500 – Surface Applications             Page no: 27 of 30 
SRI LANKA OPERATIONS CENTRE

gutters, manholes, etc., shall be given a thin uniform coating of hot bitumen and the joints 
between these structures and the surface mix shall be effectively sealed by the subsequent 
spreading, finishing and compaction operations. 
 
l. Miscellaneous Requirements 
 
The Contractor shall provide suitable means for keeping all small tools clean and free from 
accumulations of bituminous material.  He shall provide and have ready for use at all times 
enough tarpaulins or covers, as may be directed by the Engineer, for use in any emergency 
such as rain, chilling wind, excessive dust or unavoidable delay, for the purpose of covering 
or protecting any material that may have been dumped and not spread.  Generally the hot 
mix shall be discharged directly from the asphalt delivery trucks into paver receiving hopper 
unless the Engineer approves dumping and spreading by hand in difficult areas not accessible 
by  paver  when  spreading  and  compaction  shall  be  carried  out  promptly  at a minimum mix 
temperature of 120 degree C. 
 
m. Aftercare 
 
Sections of the newly finished work shall be protected from traffic of any kind until the mix 
has  sufficiently  hardened.    Also  traffic  shall  normally,  not  be  permitted  over  newly  laid 
surfaces at least for twelve hours after laying or the temperature of the newly laid surfacing 
has achieved the ambient temperature. 
 
In  the  event  any  binder  course  is  constructed  initially  the  surface  so  formed  shall  be 
maintained  in  its  finished  condition  until  the  surface  course  is  placed  thereon,  and  any 
damage caused shall be made good by the contractor.  If the damage could be attributed to 
the negligence of the contractor is it shall be corrected at his own expense. 
 
n. Surface Finish and Quality Control 
 
The  Asphaltic  Concrete  Surfacings  shall  be  finished  to  the  requirements  given  in  section 
1601. 
 
The Contractor on the quality of materials and works shall be exercised in accordance with 
section 1602. 
 

506.6. Measurement and Payment 

a. Measurement 
 
Asphaltic  Concrete  Surfacings  shall  be  measured  by  sq.m  of  mix  furnished,  spread, 
compacted, completed and accepted.  Measurements shall be of the areas and thickness as 
shown on the Drawings, described in the Specification or instructed by the Engineer. 
 
Deficiencies in thickness of the wearing course shall, unless an overlay is constructed at the 
Contractor’s expense, result in a proportion only of the wearing course area being measured 
for payment.  Proportions shall be determined in accordance with the thickness deficiencies 
and area proportions described below. 
 

Series 500 – Surface Applications             Page no: 28 of 30 
SRI LANKA OPERATIONS CENTRE

Thickness  of  asphaltic  concrete  wearing  course  shall  be  determined  by  average  calliper 
measurement of cores, rounded upwards to the nearest mm. 
 
Paved  sections  to  be  measured  separately  shall  consist  of  each  300  lin.m  section  in  each 
traffic lane.  The last section in each traffic lane shall be 300 m plus the fractional part of 300 
m remaining.  Other areas such as intersections, entrances, crossovers, ramps, etc. shall be 
measured  a  one  section  and  the  thickness  of  each  shall  be  determined  separately.    Small 
irregular unit areas may be included as part of another section. 
 
One core shall be taken from each section by the Contractor at approved locations and in the 
presence of the Engineer.  When the measurement of the core from any paved section is not 
deficient by more than 5 mm from the specified thickness, the core will be deemed to be of 
the specified thickness as shown on the Drawings. 
 
When the measurement of the core from any paved section is deficient by more than 5 mm 
but not more than 15 mm, 2 additional cores spaced at not less than 100 m shall be taken 
and used together with the first core to determine the average thickness of such section 
 
When  the  measurement  of  the  core  from  any  paved  section  is  less  than  the  specified 
thickness by more than 15 mm, the average thickness of such section shall be determined by 
taking  additional  cores  at  not  less  than  5  m  intervals  parallel  to  the  centreline  in  each 
direction  from  the  affected  location  until,  in  each  direction,  a  core  is  taken  which  is  not 
deficient by more than 20 mm.  Exploratory cores for deficient thickness will not be used in 
average thickness determinations. 
 
Any deficiencies in the total thickness of wearing courses shall be subject to a proportional 
reduction in the area of wearing course measured for payment.  Alternatively, the Contractor 
shall  construct  all  at  his  own  expense,  a  wearing  course  overlay,  if  practicable  in  the 
judgement  of  the  Engineer.    Any  such  overlay  shall  be  a  minimum  of  40  mm  compacted 
thickness and to the specified standard of the course it is overlaying. 
 
 
Where the average total thickness of wearing course is deficient by more than 5 mm but not 
more than 20 mm, adjustments shall be made in the area measurements as follows. 
 
Deficiency in Total Thickness of Wearing Courses 
 
Deficiency in Thickness as  Proportion of Wearing Course Area 
Determined by Cores (mm)  Measured for Payment 
 
0.0 to 5.0  100% 
5.1 to 10.0  80% 
10.1 to 15.0  60% 
15.1 to 20.0  40% 
 
b. Payment 
 
Payment for asphaltic concrete surfacing will be made at the contract unit rate for the item 
as  measured  above.    The  price  shall  be  full  compensation  for  furnishing  all  materials,  for 
mixing and placing of the mixed material and for providing all plant, machinery, equipment, 
tools, labour and incidentals necessary to complete the work to these specifications. 
 
 
The Pay Item and Pay Unit will be as follows :‐ 

Series 500 – Surface Applications             Page no: 29 of 30 
SRI LANKA OPERATIONS CENTRE

 
Pay Item  Pay Unit 
 
506 (1)  Asphaltic Concrete Surfacing Wearing Course  sq. m. 
compacted thickness 50 mm 
 
506 (2)  Asphaltic Concrete Surfacing Binder Course  sq. m. 
compacted thickness 50 mm 
 

507. COLD MIX SURFACINGS 

507.6 Measurement and Payment 

a. Measurement 
 
Delete this Sub section and substitute the following :‐ 
 
The  Cold  mix  surfacings  shall  be  measured  by  the  Square  metres  of  material  compacted in 
place and accepted.  Measurement shall be based on the width shown in the cross section 
drawings and the actual length measured horizontally along the centreline of the surface of 
the road. 
 

b. Payments 
 
Delete after paragraph three and insert the following :‐ 
 
The payment for Cold mix surfacing will be based on the contract unit rate for the completed 
work  of  the  Cold  mix  surfacing  which  shall  include  full  compensation  for  providing  all 
materials  labour,  tools,  equipment  and  incidentals  necessary  to  carry  out  the  construction 
works in accordance with the specifications. 
 
 
The Pay items and Pay units will be as follows :‐ 
 
Pay Item  Pay Unit 
 
507(1)  Provide and place Cold mix surfacing  Sq. Metre 
 

Series 500 – Surface Applications             Page no: 30 of 30 
SRI LANKA OPERATIONS CENTRE

SERIES 600 – UNPAVED ROADS 
 
 
 
CONTENTS 
 
 
 
601  GRAVELLING OF EARTH ROADS AND REGRAVELLING OF GRAVEL ROADS..................................... 2 
601.1.  Description......................................................................................................................... 2 
601.2.  Materials............................................................................................................................ 2 
601.3.  Mechanical Stabilisation (Blending) .................................................................................... 3 
601.4.  Construction Requirements ................................................................................................ 3 
601.5.  Measurement and Payment ............................................................................................... 4 
 

Series 600 – Unpaved Roads            Page no: 1 of 4 
SRI LANKA OPERATIONS CENTRE

SERIES 600 – GRAVEL WEARING COURSE   
 

601  GRAVELLING OF EARTH ROADS AND REGRAVELLING OF GRAVEL ROADS 
 
Delete the Heading and replace with:‐ 
 
GRAVEL WEARING COURSE 

601.1. Description 
 
Delete this Subsection and substitute the following :‐ 
 
This  work  shall  consist  of  the  placing  and  compacting  of  gravel  wearing  course  on  an  existing 
pavement  or  prepared  subgrade  in  accordance  with  lines,  levels,  grades,  dimensions  and  cross 
sections shown on the drawings and as instructed by the Engineer. 

601.2.  Materials 
 
Delete this Subsection and substitute the following :‐ 
 
The material for gravel wearing course shall be obtained from sources located by the contractor and 
approved by the Engineer or from existing pavement layers.  The material used shall be aggregate, as 
dug  soils,  or  material  obtained  by  blending  two  or  more  soils  or  soil  /  sand  mixes  referred  to  as 
mechanical stabilisation. 
 
The  Contractor’s  attention  is  drawn  to  the  scarcity  of  naturally  occurring  gravel  and  shall  make  due 
allowance for mixing of materials in mechanical stabilisation in accordance with Section 601.3 below. 
 
The material for gravel wearing course shall have the following characteristics :‐ 
 
     
SL  Properties  Test Method  Sub‐base 
No.  AASHTO 
1. Liquid Limit (LL) not to exceed (%)   T89  40 
2. Plasticity Index (PI) not to exceed  T90  12 
(%)   
3. Plasticity  Product  (PP)  (PI  x  %    240 
passing 0.075) not to exceed 
4. Maximum  Dry  Density  not  less  T180/Bs1377.  1750 
than (kg/m3)  Test 14  
5. 4 ‐ days Soaked CBR at 98% MDD  T193  30 
not less than (%) 
 
Materials of slightly higher values of PI and LL may be allowed at the discretion of the Engineer if the 
plasticity product does not exceed 240. 
 
 
 
 
 
 
 
 

Series 600 – Unpaved Roads            Page no: 2 of 4 
SRI LANKA OPERATIONS CENTRE

 
Grading Requirements for Sub‐base Material :‐ 
 
The grading of the material shall be a smooth curve within and approximately parallel to the grading 
envelope given below: 
 
Sieve Size (mm)  % Passing 
37.5  100 
20  80 – 100 
10  55 ‐ 80 
5  40 –60 
2.36  30 – 50 
0.425  15 ‐ 30 
0.075  5 – 15 
 
The  Contractor  shall  make  due  allowance  for  mixing  of  materials  in  mechanical  stabilisation  when 
necessary. 
 

601.3.  Mechanical Stabilisation (Blending) 
 
No change. 

601.4. Construction Requirements 

a. Minimum Thickness of Gravel Wearing Course 
 
Delete this Subsection and substitute the following :‐ 
 
The minimum thickness of gravel wearing surface shall be 100mm, unless otherwise specified.  

b. Preparation of Existing Surface 
 
No change. 

c. Placing and Compaction of Gravel 
 
Delete this Subsection and substitute the following :‐ 
 
Gravel wearing course material shall be spread by means of graders or other equipment or by manual 
spreading as approved by the Engineer. Gravel wearing course material shall be compacted by means 
of  self‐propelled  or  towed  steel  wheeled  rollers  which  are  capable  of  achieving  the  density 
requirements  stipulated  in  this  Clause.    Water  shall  be  applied  by  means  of  equipment  which  is 
capable of distributing the applied water uniformly over the surface of the layer. The gravel wearing 
course and gravel shoulder material shall be crushed and/or screened at source to remove all oversize 
material.  The  material  shall  be  transported  in  such  a  way,  that  no  segregation  occurs.  The  material 
shall be spread in layers to achieve the specified thickness requirement.  
 
Prior to compaction, the moisture content of the spread material shall be adjusted as necessary either 
by  the  uniform  application  of  water  or  drying  out,  to  achieve  within  ‐1%  to  +2%  of  the  optimum 
moisture content when determined in accordance with by BS1377, Test 13 (Modified) or AASHTO T‐
180. 
 

Series 600 – Unpaved Roads            Page no: 3 of 4 
SRI LANKA OPERATIONS CENTRE

The material shall be compacted by the use of approved rollers progressing gradually from the outside 
towards the centre of the layer, except on superelevated curves, where the rolling shall begin at the 
low side and progress to the high side. Each succeeding pass shall overlap the previous pass by at least 
one third of the roller width. Rolling shall continue until the entire thickness of each layer is thoroughly 
and  uniformly  compacted  to  the  specified  density.  Any  area,  which  is  inaccessible  to  rolling 
equipment, shall be compacted by means of mechanical tampers or other equipment approved by the 
Engineer. Upon completion of compaction, the surface of the completed layer shall be tightly bound, 
free from movement under the compaction plant, and free from laminations, ridges, cracks or loose or 
segregated material. 
The in‐situ density of the completed layer shall not be less than 95% of the maximum dry density when 
determined  in  accordance  with  the  requirements  of  BS1377,  Test  13  (Modified)  or  AASHTO  T‐180 
method D. The dry density shall be determined in accordance with the requirements of AASHTO T‐190.  
Alternatively, if approved by the Engineer/Supervisor, the dry density may be determined by use of a 
nuclear  densometer  which  shall  be  accurately  calibrated  before  use,  and  at  intervals  thereafter, 
against results obtained in accordance with AASHTO T‐190.   
 

d. Surface Finish and Quality Control 
 
No Change. 

601.5. Measurement and Payment 
 
Delete this Sub section and substitute the following :‐ 
 
The  Gravel  wearing  course  shall  be  measured  as  finished  and  accepted  work  in  position  in  Cubic 
metres.  Volume  measurements  shall  be  based  on  cross  section  drawings  and  the  actual  length 
measured parallel to the grade line of the road 
 

Payments 
 
Delete after paragraph three and insert the following :‐ 
 
The payment for Gravel wearing course will be based on the contract unit rate for the completed work 
of the Gravel wearing course which shall include full compensation for providing all materials labour, 
tools, equipment and incidentals necessary to carry out the construction works in accordance with the 
specifications. 
 
 
The Pay items and Pay units will be as follows :‐ 
 
Pay Item  Unit of Measurement 
 
401(1)  Provide and place Gravel wearing course  Cu. Metre 

Series 600 – Unpaved Roads            Page no: 4 of 4 
SRI LANKA OPERATIONS CENTRE

SERIES 700 ‐ DRAINAGE CONSTRUCTION 
 
 
 
CONTENTS 
 
 
 
701.  ROADSIDE AND LEADAWAY SURFACE DRAINS.................................................................2 
701.1.  Description .................................................................................................................2 
701.2.  Materials ....................................................................................................................2 
701.3.  Construction Requirements. .......................................................................................2 
701.4.  Measurement & Payment. ..........................................................................................3 
702.  SUB SURFACE DRAINS (UNDERDRAINS) ...........................................................................4 
702.1.  Description .................................................................................................................4 
702.2.  Materials ....................................................................................................................4 
702.3.  Construction Requirements ........................................................................................4 
702.4.  Measurement and Payment........................................................................................4 
703.  MANHOLES, CATCHPITS AND INLETS ...............................................................................5 
703.1.  Description .................................................................................................................5 
703.2.  Materials ....................................................................................................................5 
703.3.  Construction Requirements ........................................................................................5 
703.4.  Grade Adjustment of Existing Structures .....................................................................5 
703.5.  Measurement and Payment........................................................................................5 
704.  UNDERGROUND PIPE DRAINS .........................................................................................6 

705.  DRAINAGE BACKFILL BEHIND EARTH RETAINING STRUCTURES ........................................6 


705.1.  Description .................................................................................................................6 
705.2.  Materials ....................................................................................................................6 
705.3.  Construction Requirements ........................................................................................6 
705.4.  Measurement and Payment........................................................................................7 
706.  WEEP HOLES FOR EARTH RETAINING STRUCTURES ..........................................................8 
706.1.  Description .................................................................................................................8 
706.2.  Materials ....................................................................................................................8 
706.3.  Construction Requirements ........................................................................................8 
706.4.  Measurement and Payment........................................................................................8 
707.  PIPE CULVERTS................................................................................................................8 
707.1.  Description .................................................................................................................8 
707.2.  Materials ....................................................................................................................9 
707.3.  Construction Requirements ........................................................................................9 
707.4.  Jointing..................................................................................................................... 11 
707.5.  Backfilling ................................................................................................................. 11 
707.6.  Headwalls, Wingwalls, and other ancillary works ...................................................... 11 
707.7.  Measurement and Payment...................................................................................... 11 
 

Series 700 –Drainage Construction            Page no: 1 of 12 
SRI LANKA OPERATIONS CENTRE

SERIES 700 ‐ DRAINAGE CONSTRUCTION 
 

701. ROADSIDE AND LEADAWAY SURFACE DRAINS 

701.1. Description 
 
Delete sub section and substitute the following :‐ 
 
This work shall consist of the construction of roadside and leadaway surface drains, unlined 
or  lined  and  covered  where  required,  to  dimensions  grades  and  in  positions  shown  in  the 
Drawings or instructed by the Engineer. 

701.2. Materials 
 
Add at the end of the sub section :‐ 
 
(e) The cover slabs shall be precast and meet the requirements of section 1705. 

701.3. Construction Requirements. 

a. Cutting and Formation of Earth Drains 
 
Add at the end of the paragraph one :‐ 
 
The excavation shall be carried out as section 301A. 

b. Lined Drains 
 
Delete paragraphs 2 to 4 and substitute the following :‐ 
 
Where the lining is of precast sections, they shall be of A or B class concrete of Grade 20/20 
or Grade 20/40, laid on a prepared bed to line and level.  Unless otherwise instructed, the 
joints shall be filled using 1:3 cement mortar. 
 
Insitu  construction  with  concrete  (A  or  B  class  concrete  of  Grade  20/20  or  20/40),  R.R 
masonry  or  brick  or  block  work  shall  be  carried  out  as  given  in  the  Drawings  and  with  the 
requirements of section1006 & 1007 or as instructed by the Engineer.  Where specified, or 
where found necessary, they shall be surface lined with 1:3 cement mortar with neat cement 
finishing.    Bricks,  blocks  or  other  material  used  shall  be  subject  to  the  approval  of  the 
Engineer. 
 
Rubble  paving  with  mortar  jointing,  where  specified,  shall  be  carried  out  using  selected 
rubble, hammer dressed as necessary, to ensure proper embankment of the rubble and also 
to  obtain  a  reasonable  smoothness  to  the  surface  finish  after  the  jointing with 1:3 cement 
mortar is completed. 
 
Add at the end of the sub section :‐ 

c. Cover slabs 
 
Where it is required for the lined drains to be covered, unless otherwise instructed, the slabs 
shall be of precast concrete of Class A or B of grade 25/20, and reinforced as indicated in the 
Drawings. 

Series 700 –Drainage Construction            Page no: 2 of 12 
SRI LANKA OPERATIONS CENTRE

701.4. Measurement & Payment. 

a. Measurement. 
 
Delete paragraph one and substitute the following :‐ 
 
The  excavation  for  lined  and  unlined  drains  shall  be  measured  and  paid  as  provided  in 
section  301A.  The  quoted  rates  shall  include  cost  of  formwork,  reinforcement.  Plastering 
with neat cement smooth finishing shall be measured separately.  

b. Payment. 
 
Delete Pay Items and Pay Units and substitute the following :‐ 
 
 
Pay Item  Unit of Measurement 
 
701(1)  Lining of Drains with precast units, 
class A or B 20/40 concrete units  Ln. metre 
 
701(2)  Precast reinforced Cover Slabs 75 mm 
thick, with class A or B 25/20 concrete  Sq. metre 
 
701(3)  Precast reinforced Cover Slabs 100 mm 
thick, with class A or B 25/20 concrete  Sq. metre 
 
701(4)  Precast reinforced Cover Slabs 125 mm 
thick, with class A or B 25/20 concrete  Sq. metre 
 
701(5)  Lining of Drains with Insitu class A or B 
Grade 20 unreinforced concrete  Cu. Metre 
 
701(6)  Lining of Drains with Insitu class A or B 
20 reinforced concrete  Cu. Metre 
 
701(7)  Lining of Drains with R.R. Masonry  Cu. Metre 
 
701(8)  Lining of Drains with Brick Masonry  Cu. Metre 
 
701(9)  Lining of Drains with Block Masonry  Cu. metre 
 
701(10)  Rubble Paving in Drains  Sq. metre 
 
701(11)  Plastering    Sq. metre 
   
 

Series 700 –Drainage Construction            Page no: 3 of 12 
SRI LANKA OPERATIONS CENTRE

702. SUB SURFACE DRAINS (UNDERDRAINS) 

702.1. Description 
 
No change. 

702.2. Materials 
 
(a) Delete paragraph two and substitute the following :‐ 
 
Unless otherwise instructed, the perforated pipe to be installed shall be of 150 mm diameter 
PVC pipe, at least 4 mm thick.  The pipe shall be drilled with 4 rows of 8 mm diameter holes 
at  150mm  centres  on  the  bottom  half  of  the  perimeter  of  the  pipe  as  shown  on  the 
Drawings. 

702.3. Construction Requirements 
 
(a) Underdrains 
 
Add the following :‐ 
 
The permeable material shall be laid and lightly compacted in layers not exceeding 300mm.  
Care shall be taken to prevent the contamination of permeable material during construction 
of  the  subsurface  drains  and  all  permeable  material  contaminated  by  soil  or  silt  or  other 
deleterious material shall be removed and replaced by the Contractor at his own expense. 
 
Where specified or ordered by the Engineer, geofabric filter as specified in Section 1710 shall 
be installed as shown on the Drawings.  Filter fabric shall not be exposed to direct sunlight 
for  prolonged  periods  and  shall  be  protected  from  mechanical  damage  during  installation 
and construction. 

702.4. Measurement and Payment 

a. Measurement 
Add the following :‐ 
 
The  rate  for  filter  fabric  shall  include  full  compensation  for  furnishing,  procuring,  cutting, 
overlap, jointing, placing and protecting the fabric as specified as well as for wastage. 

b. Payment 
Add the following :‐ 
 
Pay Item  Pay Unit 
 
702(3) Provide and place filter fabric  Sq. metre 
 

Series 700 –Drainage Construction            Page no: 4 of 12 
SRI LANKA OPERATIONS CENTRE

703. MANHOLES, CATCHPITS AND INLETS 

703.1. Description 
 
No change 

703.2. Materials 
 
Delete the first paragraph and substitute the following :‐ 
 
Concrete for precast units or for insitu construction shall be A or B class, and of grade 20/20.  
Materials for rubble and brick or block masonry shall be as specified in section 1006 & 1007 
respectively. 

703.3. Construction Requirements 
 
Delete paragraphs 3 to 5 and substitute the following :‐ 
 
Precast units, reinforced or unreinforced, shall be manufactured using concrete of Class A or 
B and of grade 20/20 unless specified in the drawings.  The installations of precast units shall 
be to required lines and on prepared beds of approved soils, concrete or any other material 
as indicated in the Drawings or as instructed by the Engineer. 
 
Insitu  construction  of  catchpits  and  manholes  shall  be  carried  out  using  concrete,  rubble 
masonry, brick masonry, or block masonry, as specified or instructed on site.  The concrete 
used  shall  be  of  Class  A  or  B  and  of  grade  20/40  unless  specified  in  drawings  .    Rubble 
masonry, brick or block masonry shall conform to the requirements of section 1006 and 1007 
respectively,  
 
Insitu construction of inlets shall be carried out using concrete of Class A or B and of grade 
20/20. 

703.4. Grade Adjustment of Existing Structures 
No change. 

703.5. Measurement and Payment 

a. Measurement 
No change. 

b. Payment 
Delete Pay Items and Pay Units and substitute the following :‐ 
 
 
Pay Item  Unit of Measurement 
 
703(1)  Manholes cast insitu, concrete   Number 
703(2)  Manholes rubble masonry   Number 
703(3)  Manholes brick masonry   Number 
703(4)  Manholes block masonry   Number 
 
703(5)  Concrete Manhole reconstructed   Number 
703(6)  Rubble Manholes reconstructed   Number 

Series 700 –Drainage Construction            Page no: 5 of 12 
SRI LANKA OPERATIONS CENTRE

703(7)  Brick Manholes reconstructed   Number 


703(8)  Block Manholes reconstructed  Number 
 
703(9)  Catchpits cast insitu, concrete   Number 
703(10)  Catchpits rubble masonry   Number 
703(11)  Catchpits brick masonry   Number 
703(12)  Catchpits block masonry   Number 
 
703(13)  Inlets cast insitu, concrete   Number 
 

704. UNDERGROUND PIPE DRAINS  
 
No change. 

705. DRAINAGE BACKFILL BEHIND EARTH RETAINING STRUCTURES 

705.1. Description 
 
No change. 

705.2. Materials 

a. Aggregate backfill 
 
No Change 

b. Filter Medium 
 
Delete the second paragraph and substitute the following :‐ 
 
The  back  of  abutment,  wing  wall,  return  wall  shall  be  provided  with  a  vertical  layer  of 
granular fill material about 1m thick to serve as a filter media. 
 
  Filter shall consist of sound gravel stone, Over Burnt brick ballast and coarse sand and shall 
require the Engineers approval prior to use. 
 
  The  filter  material  shall  be  well  compacted  to  a  firm  condition  and  constructed  along  with 
selected  granular  fill  materials.    The  small  size  materials  shall  be  placed  towards  soil  and 
bigger  size  towards  the  wall  and  provided  over  the  entire  surface  behind  walls  to  the  full 
height. 
 
  Selected Granular Fill Materials 
 
  Granular  materials  to  be  used  for  backfilling  and  bedding  underneath  foundation  for  box 
culvert  shall  be  granular  materials  equivalent  to  subbase  standards,  Section  400  of  this 
specification. The extent of granular filling shall be as shown in the drawing or as directed by 
the Engineer.  
 
The  aggregate  and  filter  medium  shall  be  free  of  organic  material,  clay  or  other  materials 
which will adversely affect the free drainage of water. 

705.3. Construction Requirements 
 

Series 700 –Drainage Construction            Page no: 6 of 12 
SRI LANKA OPERATIONS CENTRE

Delete paragraph 2 and 3 and substitute the following :‐ 
 
Back  filling  with  filter  material  shall  be  done  with  approved  material  after  concrete  or 
masonry is fully set and carried out in such a way as not to cause undue thrust on any part of 
the  structure.    All  space  between  foundation  masonry  or  concrete  and  the  sides  of 
excavation  shall  be  refilled  to  the  original  surface  making  due  allowance  for  settlement  in 
150mm loose layers each of which shall be compacted to the Engineer’s approval. 
  
  The fill materials behind the structure and foundation shall be laid in layers simultaneously 
with  the laying of filter media on each side of structure and the compaction shall be done 
with  mechanical  tampers  or  any  other  methods  as  approved  by  the  Engineer  to  avoid 
displacement and unequal pressure on the structure. 
 
  Construction  of  embankment  shall  be  suspended  at  such  points  to  be  determined  by  the 
Engineer  from  where  embankment  shall  form  approaches.    Filling  behind  the  structures 
forming  a  part  of  approaches  shall  be  carried  out  on  completion  of  the  work  on  the  main 
embankment.  In no case there shall there be any interference of construction of abutments, 
wings return walls with that of embankment. 
 
  The sequence of filling behind abutments wing walls and return walls shall be so controlled 
that the assumptions made in the design are fulfilled as indicated in the relevant drawings.  
For  example,  if  the  earth  pressure  in  front  of  the  abutment  is  assumed  in  the  design,  the 
front filling shall also be done simultaneously along with the filling behind abutment, layers 
by  layers  and  in  case  the  filling  behind  abutment  before  placing  the  superstructures  is 
considered  not  desirable,  the  filling  behind  abutment  should  be  deferred  to  a  later  date.  
Wedging action against structures shall be prevented by taking special precautions and the 
slopes  bounding  the  excavation  for  the  structure  shall  be  stepped  or  serrated  to  prevent 
such wedging action.  Adequate numbers of weep holes as per specification Clause No. 3.12 
of  specification  shall  be  provided  to  prevent  any  accumulation  of  water  and  build  up  of 
hydrostatic pressure behind the walls. 
 

705.4. Measurement and Payment 

a. Measurement 
 
Delete and substitute the following :‐ 
 
Mode of measurement for filter and bedding material shall be in cubic metre of compacted 
volume as shown in drawing or as instructed by the Engineer 

b. Payment 
 
Add the following :‐ 
 
Unit rate shall include cost of materials, labour and tools and plants, compaction, testing and 
all as specified to complete the work, and shall include the cost of any necessary excavation 
of unsuitable material. 
 
 
Pay Item               Pay Unit 
 
705(1) Excavating, as necessary, providing,  
placing and compacting approved  
granular materials beneath floor slabs 

Series 700 –Drainage Construction            Page no: 7 of 12 
SRI LANKA OPERATIONS CENTRE

of culverts as per drawings and Section  
705 of specification.                    Cubic Metre 
 
705(2)    Providing, laying granular filler back  
    filling behind abutment and behind 
    wing walls for Box Culvert including  
    compaction all complete as per  
Section 705 of specification.                  Cubic Metre 
 
705(3)  Providing and filling selected granular  
filler materials behind abutments and  
behind retaining walls in layers as per  
the drawings and specification and  
direction of the Engineer.                  Cubic Metre 
 

706. WEEP HOLES FOR EARTH RETAINING STRUCTURES 

706.1. Description 
 
No change. 

706.2. Materials 
 
Delete paragraph 1 and substitute the following :‐ 
 
Unless otherwise instructed, the pipes shall made of PVC of 75 mm inside diameter. 

706.3. Construction Requirements 
 
No change 

706.4. Measurement and Payment 

a. Measurement 
 
No change 

b. Payment 
 
Delete Pay Items and Pay Units and substitute the following :‐ 
 
Pay Item  Unit of Measurement 
 
706(1)  Weepholes using 75 mm dia. PVC pipes  Ln. Metre 
 
706(2)  Weepholes 75 mm dia. cast insitu  Ln. Metre 
 

707. PIPE CULVERTS 

707.1. Description 
 

Series 700 –Drainage Construction            Page no: 8 of 12 
SRI LANKA OPERATIONS CENTRE

Delete this sub‐section and substitute the following :‐ 
 
This  work  shall  consist  of  supplying,  jointing,  bedding  of  reinforced  concrete  pipes  of  the 
required  type,  diameter  and  length  in  the  construction  of  culverts.    The  scope  of  work 
includes  the  construction  of  new  culverts,  and  the  extension  and  modification  of  existing 
drainage structures. 
 
The work also includes the construction of headwalls, wingwalls, aprons, catchpits and other 
ancillary items necessary for completion.  All work shall be carried out to lines and levels and 
dimensions shown in Drawings or as instructed by the Engineer. 

707.2. Materials 
 
Delete paragraph 1 &2 and substitute the following :‐ 
 
Materials for pipe culverts shall be: 
 
Insert after (c) :‐ 
 
 (d) Concrete for pipe bedding of class A or B, as instructed by the Engineer or as specified in 
the Drawings. 

707.3. Construction Requirements 

a. Excavation 
 
Add the following at the beginning of this sub‐section:‐ 
 
The  Contractor  shall  take  all  necessary  precautions  to  safeguard  the  stability  of  all  trench 
excavations and ensure that the safety of no person shall be placed in jeopardy. 
 
Surface  drainage  shall  be  controlled  by  the  construction  of  temporary  earth  berms  and 
drainage  channels  to  prevent  storm  water  from  entering  the  working  area.    No  separate 
payment shall be made for such temporary drainage measures. 
 
The  amount  by  which  the  excavation  is  to  exceed  the  proposed  level  of  the  invert  of  the 
culvert shall be sufficient to allow for the type and thickness of bedding material to be placed 
as specified or as shown on the Drawings. 
 
The  width  of  excavation  shall  be  equal  to  the  nominal  internal  diameter  of  the  pipe  plus 
0.5m on each side.  Where pipe culverts consist of two or more pipes next to each other the 
minimum  spacing  between  each  pipe  shall  be  300mm  or  half  the  outside  pipe  diameter 
whichever is the greater, up to a maximum of 900mm. 
 
Delete paragraph 4 and substitute the following two paragraphs:‐ 
 
Where  rock  or  other  unyielding  material  is  encountered  it  shall  be  removed  below  the 
foundation level for a depth of 0.3 m, or 0.04 m for each metre of fill over the top of the pipe 
whichever is greater, but not to exceed 0.75 of the inside diameter of the pipe. 
 
Where the soil encountered at the designed grade is unstable, soft or spongy such material 
under the pipe and for a width of 0.5m on each side of the pipe, shall be removed to a depth 
instructed by the Engineer, and replaced by sand or other selected material as instructed by 
the Engineer to provide an adequate support for the pipe.  When instructed by the Engineer, 
the Contractor shall construct a blinding layer of concrete to provide a suitable working floor. 

Series 700 –Drainage Construction            Page no: 9 of 12 
SRI LANKA OPERATIONS CENTRE

b. Bedding of Pipes 
 
Add the following at the beginning of this sub‐clause :‐ 
 
Construction of culverts shall begin at one end, the position of which shall be fixed as shown 
on  the  Drawings  or  as  instructed  by  the  Engineer.    The  position  of  the  other  end  of  the 
culvert  shall  normally  be  determined  by  the  end  of  the  last  whole  unit,  the  top  of  which 
breaks through the fill slope.  However, in the case of skew culverts or culverts with a cover 
less  than  0.5m  at  the  shoulder,  the  Engineer  may  instruct  that  the  end  unit  be  cut  to  the 
length and skew required. 
 
Any units which deform or crack, or which are not constructed to the required lines, levels 
and grades, or which become displaced in the process of work or during the Defects Liability 
Period, shall be removed and replaced by the Contractor at his own expense. 
 
Precast units shall be lifted and handled by means of approved lifting devices/methods only.  
Lifting eyes shall be caulked with a suitable mortar after the units have been installed. 
 
The  Contractor  shall  exercise  due  care  not  to  damage,  overstress  or  displace  any 
prefabricated  culvert  with  his  own  traffic  or  compaction  equipment  and  shall  provide 
additional  cover  over  the  culverts  to  ensure  that  the  culvert  is  adequately  protected  from 
Site equipment. 
 
Where culverts are constructed on gradients exceeding 1 in 4 particular care shall be taken 
to protect excavations against storm water damage and the trenches shall be excavated to 
firm  ground.    The  trenches  shall  be  backfilled  with  selected  gravel  or  concrete  if  it  is 
necessary to over‐excavate in order to obtain a firm floor. 
 
After  first  completing  the  outlet  structure,  the  culvert  units  shall  be  laid  in  the  normal 
manner, starting from the lower end and placing successive units firmly against each other to 
prevent  subsequent  movement.    The  lowest  unit  shall  be  securely  cast  into  the  outlet 
structure  and  thrust  and  anchor  blocks  shall  be  constructed  as  required  according  to  the 
Drawings. 
 
Backfilling of trenches or around the pipes shall begin at the lower end and be carried out in 
horizontal layers. 
 
(I) Concrete Bedding  
 
Delete sub section and substitute the following :‐ 
 
The  pipe  shall  be  bedded  in  a  continuous  cradle  of  class  A  or  B  concrete  of  grade  20/40 
having  a  minimum  thickness  of  0.25  times  the  external  diameter  of  the  pipe  or  200  mm 
which ever is greater.  The concrete shall extend up the sides of the pipes to a height of at 
least 10 % the external diameter or 200 mm which ever is the greater.  The minimum width 
of the cradle shall be the external diameter of the pipe plus 0.25 times the external diameter 
on either side and shall be constructed monolithically without horizontal construction joints.  
The cradle shall be such that the pipe can be seated fully in it and the pipe shall be laid on 
the concrete bedding before the concrete is set. 
 
Where shown on the Drawings or instructed by the Engineer pipes shall be fully encased in 
class  A  or  B  concrete  of  grade  20/40  (reinforced  or  un  reinforced)  of  minimum  thickness 
200mm.    Temporary  supports  shall  be  provided  near  the  pipe  ends  to  support  the  pipes 
during the placing of the concrete.  The concrete shall be placed in such a way that all spaces 
under the pipe are completely filled.  Poker vibrators shall be used to ensure that all spaces 

Series 700 –Drainage Construction            Page no: 10 of 12 
SRI LANKA OPERATIONS CENTRE

under and around the pipe are properly filled with concrete.  Concrete casing shall be cast in 
one continuous operation until completed. 
 
(II) Granular Bedding  
 
Delete sub section and substitute the following :‐ 
 
Granular bedding when required shall be provided by bedding the pipe in a trench of depth 
0.1 m plus 0.3 times the external diameter of the pipe.  The granular bedding shall be sand or 
any other selected fill and shall be accurately shaped by a template to fit the lower part of 
the  pipe.    The  selected  granular  bedding  shall  surround  the  pipe  up  to  a  height  of  0.1  m 
above  the  top  of  the  pipe.    In  appropriate  circumstances  the  Engineer  may  permit 
compaction of sand bedding by hydraulic compaction (flooding) subject to approval of trials 
carried out by the Contractor. 

707.4. Jointing 
 
Add the following at the beginning of this sub‐clause:‐ 
 
Where  partial  demolition  is  required  for  extension  work  to  existing  structures,  the  contact 
face shall be cut to predetermined lines and levels, loose and fragmented material removed 
and projecting steel cleaned and bent or cut as instructed by the Engineer.  Where no partial 
demolition but only extension is required, the contact area shall be roughened and cleaned 
of all dirt and loose particles. 
Where  dowels  are  required  they  shall  be  installed  with  an  approved  type  of  epoxy‐resin 
grout  in  holes  drilled  into  the  existing  structure  in  accordance  with  details  shown  on  the 
Drawings. 
New concrete shall be bonded to the old concrete by using a cement paste or slurry or an 
approved type of bonding agent. 
 

707.5. Backfilling 
 
Add the following :‐ 
 
The material used for the backfilling of those portions of culverts subject to traffic loads shall 
be  selected  material  of  at  least  subbase  quality  or  such  lower  quality  as  the  Engineer  may 
permit. 
 
The  backfilling  material  shall  be  thoroughly  tamped  in  under  the  flanks  of  the  culverts  to 
provide  uniform  bedding  to  the  Engineer’s  satisfaction.    Adequate  cover  over  the  culvert 
shall  be  provided  before  the  contractor  routes  his  construction  equipment  across  it.  
Hydraulic  compaction  of  backfilling  may  be  permitted  in  appropriate  circumstances  after 
successful trials. 

707.6. Headwalls, Wingwalls, and other ancillary works 
 
No change. 

707.7. Measurement and Payment 

a. Measurement  
 
Delete Paragraph 1 and substitute the following :‐ 

Series 700 –Drainage Construction            Page no: 11 of 12 
SRI LANKA OPERATIONS CENTRE

 
Concrete  for  bedding,  encasement  and  granular  aggregate  bedding  shall  be  measured  in 
cubic metres of material laid and compacted.  The rate shall include shuttering if required. 
Payment  for  shaping  and  compacting  of  stable  in‐situ  bedding  material  shall  be  per  linear 
metre of culvert length. 
Reinforcement steel shall be paid by weight 
 

b. Payment 
 
Delete Pay Items and Pay Units and substitute the following :‐ 
 
Pay Item  Unit of Measurement  
 
707(1)  Concrete Bedding/Cradle  Cu. Metre 
707(2)  Granular Bedding  Cu. Metre 
707(3)  Concrete to Encasement  Cu. Metre 
707(4)  Reinforcement Steel to concrete encasement  kg 
707(5)  In‐situ Bedding material  Cu. Metre 
 
707(6)  Reinforced concrete pipe 600mm Dia      Ln. Metre 
707(7)  Reinforced concrete pipe 900mm Dia      Ln. Metre 
707(8)  Reinforced concrete pipe 1200mm Dia      Ln. Metre 
707(9)  Reinforced concrete pipe 2000mm Dia      Ln. Metre 
707(10)Excavation in unclassified suitable material 
and backfill to structures  Cu. metre 
707(11)Excavation in hard rock  
and backfill to structuresCu. metre 
707(12)Excavation in unsuitable material 
  and backfill to structuresCu. Metre 

Series 700 –Drainage Construction            Page no: 12 of 12 
SRI LANKA OPERATIONS CENTRE

SERIES 800 ‐ INCIDENTAL CONSTRUCTIONS 
 
 
CONTENTS 
 
801 TOPSOILING ........................................................................................................3
801.1 Description ..................................................................................................3
801.2 Materials .....................................................................................................3
801.3 Construction Methods..................................................................................3
801.4 Measurement and Payment..........................................................................3
802 GRASSING...........................................................................................................4
802.1 Description ..................................................................................................4
802.2 Materials .....................................................................................................4
802.3 Construction Requirements ..........................................................................4
802.4 Measurement and Payment..........................................................................5
803 PLANTING TREES SHRUBS VINES ETC. ...................................................................5

804 RIP RAP PROTECTION FOR EMBANKMENTS SLOPES...............................................6
804.1 Description ..................................................................................................6
804.2 Materials .....................................................................................................6
805 GABION WALLS ...................................................................................................6
805.1 Description ..................................................................................................6
805.2 Materials .....................................................................................................6
805.3 Construction Requirements ..........................................................................6
805.4 Measurement and Payment..........................................................................8
806 PAVED SIDE WALKS .............................................................................................8
806.1 Description ..................................................................................................8
806.2 Materials .....................................................................................................8
806.3 Construction Requirements ..........................................................................8
806.4 Measurement and Payment..........................................................................8
807 PRECAST CONCRETE KERBS AND CHANNELS..........................................................9
807.1 Description ..................................................................................................9
807.2 Materials .....................................................................................................9
807.3 Construction Requirements ..........................................................................9
807.4 Measurement and Payment..........................................................................9
808 GUARD RAILS AND WALLS, GUARD STONES, AND GUIDE POSTS ...........................10
808.1 Description ................................................................................................10
808.2 Materials ...................................................................................................10
808.3 Construction Requirements ........................................................................10
808.4 Measurement and Payment........................................................................12
809 FENCING ...........................................................................................................12

810 ROAD MARKINGS ..............................................................................................12


810.1 Description ................................................................................................12

Series 800 – Incidental Constructions         Page no: 1 of 29 
SRI LANKA OPERATIONS CENTRE

810.2 Materials ...................................................................................................12


810.3 Construction Requirements ........................................................................12
810.4 Measurement and Payment........................................................................13
811 ROAD SIGNS......................................................................................................14
811.1 Description ................................................................................................14
811.2 Materials ...................................................................................................14
811.3 Construction Requirements ........................................................................14
811.4 Measurement and Payment........................................................................15
812 BUS BAYS..........................................................................................................15
812.1 Description ................................................................................................15
812.2 Materials ...................................................................................................15
812.3 Construction Requirements ........................................................................15
812.4 Measurement and Payment........................................................................15
813 CONCRETE KERB INLETS .....................................................................................16
813.1 Description ................................................................................................16
813.2 Materials ...................................................................................................16
813.3 Construction Requirements ........................................................................16
813.4 Measurement and Payment........................................................................16
814 HNADRAILS, UPRIGHTS AND END PILASTERS.......................................................16
814.1 Description ................................................................................................16
814.2 Materials ...................................................................................................17
814.3 Construction Requirements ........................................................................17
814.4 Measurement and Payment........................................................................18
815.3 Measurement and Payment .............................................................................27
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SERIES 800 ‐ INCIDENTAL CONSTRUCTIONS 

Series 800 – Incidental Constructions         Page no: 2 of 29 
SRI LANKA OPERATIONS CENTRE

801 TOPSOILING 

801.1 Description 
 
Delete sub section and substitute the following :‐ 
 
This work shall consist of supply of topsoil furnished and transported from approved sources 
or  stockpiles  and  spread  in  conformity  with  these  specifications  at  locations  shown  on 
Drawings or as instructed by the Engineer.  Generally where topsoil is stockpiled adjacent to 
the  Works,  embankment  slopes  shall  be  topsoiled  in  accordance  with  the  Engineer’s 
instructions. 

801.2 Materials 
 
No change. 

801.3 Construction Methods 
 
Add to paragraph 2 :‐ 
 
Where  ordered  by  the  Engineer  the  area  to  be  top  soiled  shall  be  roughened  by  hand 
scarifying,  or  by  any  other  means  approved  by  the  Engineer;  to  ensure  the  stability  of  the 
topsoil on the area. 
 
Delete paragraph 3 and substitute the following :‐ 
 
After the Engineer has approved the prepared and graded areas, topsoil shall be spread to a 
depth which after settlement shall not be less than 75 mm or as instructed by the Engineer.  
Spreading  shall  not  be  done  when  the  ground  or  the  topsoil  is  excessively  wet  or  in  a 
condition  considered  detrimental  to  the  work.  The  topsoil  layer  shall  be  levelled  off  and 
raked. 

801.4 Measurement and Payment 
 
Delete subsection and substitute the following :‐ 

a. Measurement 
 
The  quantities  to  be  paid  for  shall  be  the  number  of  square  metres  of  topsoil  of  100  mm 
loose thickness completed in place and accepted. 

b. Payment 
 
The  quantities  of  topsoil  will  be  paid  for  at  the  contract  unit  price  which  shall  be  full 
compensation  for  transporting  from  stockpile  and  spreading  material  to  the  required 
thickness, levelling it off to a smooth surface, for removing any stones as specified, and for 
roughening  the  surface  to  be  top  soiled  and  shall  including  all  labour  equipment  tools  and 
incidentals necessary to complete the work. 
 
Pay items and Pay Units will be as follows. 
 
Pay Item  Unit of Measurement  

Series 800 – Incidental Constructions         Page no: 3 of 29 
SRI LANKA OPERATIONS CENTRE

801(1)  Topsoil spread supplied from  
  Stock piles (Excavated topsoil)  Sq. metre 

802 GRASSING 

802.1 Description 
 
No change. 

802.2 Materials 
 
Add the following :‐ 
 
c. Grass Sods 
 
Grass  sods  shall  be  free  from  noxious  weeds  and  diseases  and  shall  contain  a  minimum  of 
50mm of topsoil. 
 
d. Fertilizer 
 
The  type  of  fertilizer  to  be  used  shall  be  one  or  more  of  the  following  and/or  any  other 
fertilizer as ordered or approved by the Engineer :‐ 
 
i) Agricultural Lime 
ii) Super Phosphate 
iii) Limestone ammonium‐nitrate 
 
The Contractor shall have the top 150mm of the prepared surfaces tested to determine the 
amount  and  type  of  fertilizer  required  for  establishing  proper  growth  conditions  for  the 
grass.  The fertilizer shall be evenly applied over all surfaces where grass is to be planted and 
shall  then  be  thoroughly  mixed  with  the  soil  to  a  depth  of  150mm  either  mechanically  or 
manually. 

802.3 Construction Requirements 
 
Delete paragraph 3 and substitute the following :‐ 
 
Seeding shall be done just before or during the rainy season or as instructed by the Engineer.  
The method of seeding and application of fertiliser, water and mulch shall be subject to the 
approval of the Engineer. 
 
Delete paragraph 6 and substitute the following :‐ 
 
Sodding shall be done just before or during the rainy season or as instructed by the Engineer.  
The  Contractor  shall  notify  the  Engineer  not  less  than  7  days  before  cutting  of  sods  begin.  
Sods will be approved by the Engineer, in its original position before cutting and delivery to 
site.    Areas  to  be  sodded  shall  be  given  a  layer  of  topsoil  75mm  thick  unless,  due  to  the 
presence of suitable subsoil, the Engineer orders that the topsoil be omitted. 
 
The  areas  to  be  sodded  shall  be  thoroughly  watered  beforehand so that they are wet to a 
depth of at least 150mm when sodding is to be done. 
 
At the end of paragraph add the following :‐ 
 

Series 800 – Incidental Constructions         Page no: 4 of 29 
SRI LANKA OPERATIONS CENTRE

On  side  slopes  steeper  than  2  to  1,  the  laying  of  sods  shall  be  started  from  bottom  to 
upwards. 
 
At points where water may flow over a sodded area, the upper edges of the sod strips shall 
be turned into the soil below the adjacent area and a layer of earth placed over this followed 
by its thorough compaction. 
 
Delete last paragraph and substitute the following :‐ 
 
Where  the  side  slope  is  2  to  1  or  steeper  and  the  distance  along  the  slope  is  more  than  2 
metres,  the  sods  shall  be  staked  with  pegs  or  nails  spaced  approximately  500  to  1000 mm 
along  the  longitudinal  axis  of  the  sod  strips.  Stakes  shall  be  driven  approximately  plumb 
through the sods to be almost flush with them. 
 
After  the  sods  have  been  laid  in position, the surface shall be cleaned of loose sod, excess 
soil and other foreign material. Thereafter a thin layer of top soil shall be scattered over the 
surface of top dressing and the area thoroughly moistened by sprinkling with water. 
 
The sods shall be watered by the Contractor for a period of at least four weeks after laying. 
Watering  shall  be  so  done  as  to  avoid  erosion  and  prevent  damage  to  sodded  areas  by 
wheels of water tanks. 
 
The  Contractor  shall  erect  necessary  warning  signs  and  barriers,  repair  or  replace  sodded 
areas  failing  to  show  uniform  growth  of  grass  or  damaged  by  his  operations  and  shall 
otherwise maintain the sod at his cost until final acceptance. 
 

802.4 Measurement and Payment 

a. Measurement 
No Change. 

b.  Payment 
 
Add the following :‐ 
 
Payment shall include for pre‐watering and watering the sods, replanting dead areas and for 
the supply and placing of timber stakes and for all other incidentals that may be required to 
establish an acceptable cover and to maintain the grass. 
 
Delete Pay Item No. 3 and substitute the following :‐ 
 
Pay Item  Unit of Measurement  
 
802(1)  Sodding (Solid)  Sq. metre 
802(2)  Furnish and apply fertilizer  Prov. Sum 
 

803 PLANTING TREES SHRUBS VINES ETC. 
 
No Change. 

Series 800 – Incidental Constructions         Page no: 5 of 29 
SRI LANKA OPERATIONS CENTRE

804 RIP RAP PROTECTION FOR EMBANKMENTS SLOPES 

804.1 Description 
 
No change. 

804.2 Materials 

a. Dumped Rip Rap 
 
Delete this paragraph and substitute the following :‐ 
 
‘Stone  used  for  dumped  rip‐rap  shall  be  hard,  durable,  angular  in  shape  and  resistant  to 
weathering and water action.  Rounded stones and broken concrete will not be acceptable.  
The stone shall be at least 500mm in maximum dimension and more than 100mm minimum 
dimension and be well graded between these two limiting dimensions’. 
 

805 GABION WALLS 

805.1 Description 
 
Add the following :‐ 
 
This  section  covers  the  construction  of  gabion  walls,  mattresses  and  aprons  for  the 
construction  of  retaining  walls,  lining  of  channels,  revetments  and  other  anti‐erosion 
structures. 
Generally gabions shall be flexible, galvanised steel wire mesh cages packed with rock. 

805.2 Materials 
 
Delete sub section and substitute the following :‐ 
 
Unless otherwise specified the material used shall meet the following requirements. 
 
(a) Double  twisted  hexagonal  mesh  made  of  zinc  coated  mild  steel  conforming  to  BS 
1052/1980, BS 443/1982 
(b) Binding and connecting wire of 3.0 mm diameter galvanised to the same standard 
as the mesh wire 
(c) Broken  rock  for  filling  baskets  shall  preferably  be  of  sizes  normally  varying  from 
about 100 mm in minimum dimension to 300 mm in maximum dimension and they 
shall  be  clean,  hard  and  durable,  free  from  weathered  pieces  and  extraneous 
matter.  The rock shall be well graded between the two limiting sizes 
(d) Where indicated on the Drawings or ordered by the Engineer, a layer of filter fabric, 
or  approved  equivalent  material  shall  be  placed  on  the  prepared  surface  prior  to 
the  placing  of  the  gabions.    The  material  shall  be  placed  as  instructed  in  vertical 
strips with a minimum overlap of 300mm and shall be properly fastened to prevent 
any movement or slipping during the placing of gabions 
 

805.3 Construction Requirements 
 
In the second paragraph delete : “or rubble masonry” 

Series 800 – Incidental Constructions         Page no: 6 of 29 
SRI LANKA OPERATIONS CENTRE

 
Delete paragraph 3 and substitute the following. 
 
The  concrete  shall  be  of  class  C  grade  15/40  for  unreinforced  base  layer  and  class  B  grade 
20/20 for reinforced base layer. 
 
To the end of paragraph 4 add the following :‐ 
 
Baskets shall, where appropriate, be maintained square and with vertical sides during filling.  
Internal tie wires shall be inserted and baskets shall be tensioned. 
 
Delete paragraph 5 and substitute the following. 
 
The  wire  baskets  for  gabions  shall  be  made  out  of  double  twisted  hexagonal  mesh.    The 
width of gabion boxes will be 1‐2 metres or as instructed by the Engineer.  The length shall 
be multiples of one metre subject to a maximum of 4.0 m.  The gabions will have diaphragm 
walls at 1.0 m intervals. 
 
The general specifications of gabions area follows :‐ 
 
Thickness  Mesh type  Wire Dia.  Stone size  D50 
(mm)  (cmxcm)  (mm)  (mm)  (mm) 
         
500  10 x 12  2.70  120 ‐ 250  190 
1000  10 x 12  2.70  120 ‐ 250  190 
 
Add the following :‐ 
 
Mattresses,  which  are  generally  only  used  as  single  layer  aprons  in  revetments  or  at  the 
entrance or exit to culverts to prevent scour and minimise erosion, shall be sub‐divided by 
diaphragms  into  cells  having  a  width  of  600  mm  or  1.0m  as  specified  or  instructed  by  the 
Engineer. 
 
The  cut  edges  of  all  mesh  used  in  the  construction  of  gabions,  except  the  bottom  edge  of 
diaphragms and end panels, shall be selvedged with galvanised wire having a diameter of at 
least 0.5 mm more than that of the mesh wire. 
The diaphragms and end panels shall be selvedged on the top and vertical sides only. 
 
Sufficient  binding  and  connecting  wire  shall  be  supplied  with  the  gabion  cages  to  perform 
the wiring operations in accordance to these specifications.  The diameter of the wire shall 
be at least 3.2mm. 
 
The methods of assembly shall be in accordance with the manufacturers instructions but the 
Contractor  shall  ensure  that  sufficient  connecting  wire  braces  are  provided  to  prevent 
deformation of the cages as they are being filled with stone. 
It is essential that the corners of the gabion cages be securely wired together to provide a 
uniform  surface  and  to  ensure  that  the  structure  does  not  appear  as  a  series  of  blocks  or 
panels. 
 
Particular  care  shall  be  exercised  in  filling  visible  faces  of  gabion  boxes,  for  which  only 
selected stone of adequate size shall be used and be so prepacked that a fair faced finish is 
obtained.  The filling of boxes shall be done in stages in order to prevent deformation and 
bulging. 
 

Series 800 – Incidental Constructions         Page no: 7 of 29 
SRI LANKA OPERATIONS CENTRE

The  filling  of  mattresses  shall  be  carried  out  by  spreading  random  stones  on  the  first layer 
and using selected stones for the top layer so as to present a dry stone‐pitched surface. 

805.4 Measurement and Payment 

a. Measurement 
 
Delete paragraph 2 

b. Payment 
 
Delete pay item 805(2) 
 

806 PAVED SIDE WALKS 

806.1 Description 
 
No Change. 

806.2 Materials 
 
Delete (b) and substitute the following :‐ 
 
(b) Bed course material shall consist of sand, gravel, crushed stone or other approved 
granular material of 10 mm maximum size. 
 

806.3 Construction Requirements 
 
Delete (c) and substitute the following :‐ 
 
The  precast  concrete  slabs  as  indicated  in  Drawings  shall  be  laid  to  line  and  level  on  a 
prepared  bed  course  material.    The  bed  course  material  shall  be  spread  and  uniformly 
compacted on an approved solid foundation to a thickness of not less than 50 mm.  Unless 
otherwise instructed by the Engineer, the slabs shall be laid side by side to a close fit and the 
joints filled with fine sand or crusher dust. 

806.4 Measurement and Payment 

a. Measurement 
 
No Change 

b. Payment 
 
Delete Pay Items and substitute the following. 
 
Pay Item  Unit of Measurement  
 
806(1)  Paving (precast concrete slabs)  Sq. metre 
 
806(2)  Bed course material 50mm thick  Sq. Metre 

Series 800 – Incidental Constructions         Page no: 8 of 29 
SRI LANKA OPERATIONS CENTRE

807 PRECAST CONCRETE KERBS AND CHANNELS 

807.1 Description 
 
No Change. 

807.2 Materials 
 
Delete sub section and substitute the following :‐ 
 
Concrete for precast or cast in place units and concrete for kerbs shall be of Class A or B of 
grade 20/20 in accordance with Section 1001. 
 
The  other  material  used  shall  meet  the  requirements  of  the  following,  unless  otherwise 
specified :‐ 
 
(a) Reinforcement steel to SLS 375 or CS 26 
(b) Bed course material shall consist of sand, gravel, crushed stone or other approved 
granular material of 10 mm maximum size 
(c) Cement mortar for jointing to sub section 1703.2 

807.3 Construction Requirements 

a. Precast Concrete Units 
 
Delete paragraph 3 & 4 and substitute the following :‐ 
 
Where precast kerbs without the channel sections are to be used, they shall be laid over a 
concrete  bed,  275  mm  wide  and  of  minimum  thickness  of  100  mm,  of  grade  15/40  as 
indicated  in  the  Drawings.    The  kerb  units  are  to be laid so that the face and the top lines 
conform to the lines and grades indicate in the Drawings.  Unless otherwise instructed by the 
Engineer the joint spacings between kerb units shall be set approximately to a uniform width 
of 12 mm which shall be filled with 1:3 cement mortar, thoroughly rammed and troweled to 
a neat finish. 

807.4 Measurement and Payment 

a. Measurement 
 
No Change 

b.  Payment 
Delete Pay Items and substitute the following. 
 
Pay Item  Unit of Measurement  
 
807(1)  New Kerbs (precast concrete)  Ln. metre 
807(2)  Reset kerbs (pre‐cast concrete)  Ln. metre 
 

Series 800 – Incidental Constructions         Page no: 9 of 29 
SRI LANKA OPERATIONS CENTRE

808 GUARD RAILS AND WALLS, GUARD STONES, AND GUIDE POSTS 

808.1 Description 
 
No Change. 

808.2 Materials 
 
Add the following :‐ 
 
(g) Steel railway lines salvaged from railway stores or RDA stores. 

808.3 Construction Requirements 

a. Guard Rails 
 
Delete paragraph 2 & 3 and substitute the following :‐ 
 
Concrete posts shall be of rectangular type with size of 150 x 100 and shape as shown on the 
drawing or as directed by the Engineer. Concrete shall be of grade 30 and shall comply with 
the  specification  for  structural  concrete  work.  No  materials  other  than  the  essential 
ingredients i.e. cement, aggregates and water, shall ordinarily be used in the manufacture of 
concrete. Reinforcement shall be mild steel bars and clean, free from loose rust, loose mill 
scale, and foreign coating. Bending of bars shall be done as per drawing and in a manner that 
will  not  injure  the  material.  Shuttering  shall  be  of  dressed  softwood  timber  or  steel  plain 
sheets with true surfaces and edges, mortar tight and stoutly braced together. And or Timber 
Posts, pre‐treated with creosote or similar protective coating approved by the Engineer, of 
size 150 x 100 shall be set vertically in concrete footings of grade 15/40 at intervals of 1.5 m 
apart. 
 
Railings made from galvanised steel of thickness not less than 8 gauge, in corrugated shape 
corresponding  exactly  with  the  dimensions  of  sections  manufactured  by  ARMCO  or  similar 
proprietary manufacturers, shall be fixed on posts as indicated in Drawings in a manner that 
will  result  in  smooth  continuous  tight  rail  closely  conforming  to  the  line  and  grade  of  the 
highway or as indicated in the Drawings.  Laps in railings shall be parallel to the direction of 
flow of traffic.  All cut edges shall be shop painted with approved galvanised paint using two 
coats. 
 
The holes for the posts shall be or sufficient size to permit proper setting of the posts and to 
allow sufficient room for backfilling and tamping. 
 
The holes shall be spaced to suit the standard length of guardrail supplied. 
 
The guardrail complete shall be erected true to line and level and the holes shall be backfilled 
with a 12:1 mixture of soil:cement  only after the Engineer has signified his approval.  When 
the backfilling is complete and the bracing removed the posts must be rigid and vertical and 
the guardrail true to line and level and firmly fastened to the posts.  Excess material shall be 
disposed of as instructed by the Engineer. 
 
At locations instructed by the Engineer adjacent to long sheer drops on the outside of bends 
the Contractor shall erect steel railway‐line guard rail on posts at the same height and at the 
same  centres  as  for  galvanised  steel  guard  rail.    Posts  shall  be  erected  rigidly  in  concrete.  
Steel  railway  lines  shall  be  bent  to  the  road  curvature  joined  using  purpose  made  plates 
solidly bolted. 

Series 800 – Incidental Constructions         Page no: 10 of 29 
SRI LANKA OPERATIONS CENTRE

b. Guard Walls and Guard Stones 
 
Delete paragraph 1 and substitute the following. 
 
Guard  walls  shall  be  reinforced  concrete  precast  or  cast  insitu  to  dimensions  given  in 
Drawings.  Guard stones shall be either reinforced concrete or cast in‐situ concrete or stone 
masonry all as shown on the Drawings and/or as ordered by the Engineer.  The concrete shall 
be class A or B concrete of grade 20/20.  Forms used for concreting shall be wood, metal, or 
suitable material and shall extend the full depth of the concrete. 
 
Delete paragraph 4 & 5 and substitute the following. 
 
Compaction of the concrete placed in the forms shall be by vibration.  Forms shall be left in 
place  for  24  hours  or  until  the  concrete  has  set sufficiently so that they could be removed 
without  injury  to  the  concrete  placed.    The  finished  concrete  shall  be  kept  moist  for  a 
minimum of 7 days.  The method of curing shall be subject to the approval of the Engineer. 
 

c. Guide Posts 
 
Delete paragraph 1 and substitute the following :‐ 
 
Guard  posts  shall  be  of  circular  type  with  size  and  shape  as  shown  on  the  drawing  or  as 
directed  by  the  Engineer.  Concrete  shall  be  of  grade  30  and  shall  comply  with  the 
specification for structural concrete work. No materials other than the essential ingredients 
i.e. cement, aggregates and water, shall ordinarily be used in the manufacture of concrete. 
 
Reinforcement shall be mild steel bars and clean, free from loose rust, loose mill scale, and 
foreign coating. Bending of bars shall be done as per drawing and in a manner that will not 
injure the material. 
 
Shuttering shall be of dressed softwood timber or steel plain sheets with true surfaces and 
edges, mortar tight and stoutly braced together. 
 
Concrete shall be thoroughly mixed in proportions as approved by the Engineer, satisfying its 
specified grade. Mixing shall be done in a mechanical mixer and be continued till materials 
are uniformly distributed and an uniform colour of the entire mass is obtained. If however 
hand mixing is permitted by the Engineer, it shall be done on a smooth watertight platform 
large enough to allow efficient turning over of the ingredients of concrete before and after 
adding water. In such cases of hand mixing the quantity of cement shall be increased by ten 
(10) per cent above the amount required for specified grade. The inside faces of formwork 
shall be soaped or oiled to prevent adhesion of concrete, but such soap or oil shall be such as 
not  to  stain  the  concrete.  Reinforcements  contained  in  the  guard  post  shall  be  placed  and 
firmly  held  in  correct  position  with  specified  clear  cover  as  shown  on  the  drawing  or  as 
directed  by  the  Engineer.  The  method  of  transporting  and  placing  the  concrete  shall  be 
approved  by  the  Engineer.  Concrete  shall  be  kept  in  the  forms  for  at  least  seven  (7)  days 
during  which  time  it  shall  be  kept  moist  and  sheltered  from  the  Sun.  Posts  shall  not  be 
erected until fourteen (14) days after casting and during this period shall not be subjected to 
any loading or rough handling. While striking off the formwork care shall be taken to prevent 
any  damage  to  the  concrete.  Any  damage  caused  during  concreting,  removal  of  shuttering 
and transporting the guard posts to their place of installation shall have to be made good at 
the contractor's own expense. While erecting the posts necessary excavation shall be done 
and back filled with approved material after proper compaction so that the posts stand truly 

Series 800 – Incidental Constructions         Page no: 11 of 29 
SRI LANKA OPERATIONS CENTRE

vertical, in lines, grades as shown on the drawing at specified locations or as directed by the 
Engineer. 
 

808.4 Measurement and Payment 

a. Measurement 
 
No Change. 

b.  Payment 
Delete Pay Items and substitute the following :‐ 
 
Pay Item  Unit of Measurement  
 
 
808(1)  Guard Rails (galvanised steel)  Ln. metre 
808(2)  Guard Rails (Steel Railway Line)  Ln. metre 
808(3)  Guard Stones (concrete)  Number 
808(4)  Guard Stones (masonry)  Number 
808(5)  Guide Posts (100mm Upvc pipe)  Number 

809 FENCING 
No Change. 
 

810 ROAD MARKINGS 

810.1 Description 
 
Delete sub section and substitute the following :‐ 
 
The work shall consist of the applications of road markings including the installation of road 
studs on the finished paved areas of road in accordance with the Manual of Traffic Control 
Devices of Road Development Authority, Ministry of Transport and Highways and the Motor 
Traffic Act. 

810.2 Materials 
 
Add at end of sub section :‐ 
 
Before  delivery  of  materials  to  Site  the  Contractor  shall  forward  certificates  of  origin 
specifying  physical  and  chemical  characteristics  and  the  constituents  of  the  paint  from  the 
manufacture.    Before  delivery  or  during  the  work  the  Engineer  may  call  for  any  test 
considered necessary to the application.  All such tests shall be performed at the expense of 
the Contractor and shall be considered subsidiary to the work. 

810.3 Construction Requirements 
 
Add the following :‐ 
 
e. Equipment 
 

Series 800 – Incidental Constructions         Page no: 12 of 29 
SRI LANKA OPERATIONS CENTRE

The road marking equipment shall be purpose made of approved type and manufacture and 
be  capable  of  painting  the  markings  to  a  uniform  width  within  the  tolerances  specified 
without the paint running or splashing.  The equipment shall be capable of painting lines of 
different widths by adjustment of the spray jets on the machine or by means of additional 
equipment attached to the machine. 
 
f. Setting Out 
 
The  lines,  symbols,  figures  or  marks  shall  be  set  out  by  means  of  paint  spots  of  the  same 
colour as that of the proposed final lines and marks.  Normally spots of approximately 10mm 
in diameter spaced at 1.5m intervals shall be sufficient. 
After spotting the positions of the proposed road markings are to be indicated on the road.  
These  premarkings  shall  be  approved  by  the  Engineer  prior  to  the  commencement  of  any 
painting operations. 
 
The positions of any road studs shall be marked out on the road and shall be approved by the 
Engineer before they are fixed in position. 
 
g. Tolerances 
 
The  width  of  lines  and  other  markings  shall  not  deviate  from  the  specified  width  by  more 
than 5%. 
 
The position of lines, letters, figures, arrows, reflective road studs and other markings shall 
not deviate from the true position specified by more than 20mm. 
 
The alignment of any edge of a longitudinal line shall not deviate from the true alignment by 
more than 10mm in 15m. 
 
The  lengths  of  segments  of  broken  longitudinal  lines  shall  not  deviate  from  the  specified 
length by more than 150mm. 
 
h. Rectification of Faulty Workmanship 
 
If any material not complying with the requirements is delivered to site or used in the Works, 
or if any sub‐standard work is carried out, such material or work shall be removed, replaced 
or  repaired  as  required  by  the  Engineer,  at  the  Contractor’s  own  cost.    Rejected  traffic 
markings  and  paint  that  has  been  splashed  or  has  dripped  onto  the  surfacing,  kerbs, 
structures or other such surfaces shall be removed by the Contractor at his own cost, in such 
a way that the markings or spilt paint will not show up again later. 

810.4 Measurement and Payment 

a. Measurement 
 
Delete this sub‐section and substitute the following :‐ 
 
Road  markings  shall  be  measured  by  the  actual  length  in  linear  metres  for  the  specified 
widths completed and accepted. 
 
Reflecting road studs shall be measured in number supplied, installed and accepted. 

b.  Payment 
 

Series 800 – Incidental Constructions         Page no: 13 of 29 
SRI LANKA OPERATIONS CENTRE

Delete Pay Items and substitute Pay Items below :‐ 
 
Pay Item  Unit of Measurement 
 
810(1)  Road Markings 
Reflectorised thermoplastic paint 
100mm wide  Ln. metre 
150mm wide  Ln. metre 
200mm wide  Ln. metre 
 
810(2)  Road Markings 
Reflectorised road marking paint 
100mm wide  Ln. metre 
150mm wide  Ln. metre 
200mm wide  Ln. metre 
 
810(3)  Rreflecting road studs  Number 
 

811 ROAD SIGNS 

811.1 Description 
 
Delete sub section and substitute the following :‐ 
This work covers the provision and installation of permanent road signs and post assemblies 
as shown on the drawings or as directed by the Engineer. The signs will be ground mounted 
and  erected  at  the  side  of  the  road  as  shown  on  the  drawings  or  as  specified  in  these 
specifications. Prior to manufacture and fabrication of the signs, the Contractor shall submit 
to the Engineer for approval (and in conformity with the Motor Traffic Act), detail execution 
drawings  and  the  Manual  of  Traffic  Control  Devices  of  the  Road  Development  Authority, 
Ministry of Transport and Highways showing letter sizes, symbols and sign layout, sign panel 
dimension, post height for sign structures. 
 

811.2 Materials 
 
Add the following :‐ 
 
e. Preservatives, Paints and Finishes 
 
Delete paragraph 3 and substitute the following :‐ 
 
The  Retro‐reflective  material  to  be  supplied  shall  be  High  Intensity  Grade  sheeting  (High 
Performance Wide Angle Retro‐reflective Sheeting) and shall be in accordance with ASTM D 
4956‐90 “Standard Specification for Retroreflective Sheeting for Traffic Control”. 
 
The  material  shall  be  supplied  with  a  pressure‐sensitive  or  heat  applied  adhesive  backing 
protected  by  a  removable  liner  and  shall  be  of  the  correct  type  for  the  backing  surface  to 
which it is to be applied. 

811.3 Construction Requirements 

a.  Mounting Posts 
 

Series 800 – Incidental Constructions         Page no: 14 of 29 
SRI LANKA OPERATIONS CENTRE

Delete paragraph 1 and section substitute the following :‐ 
 
Posts for mounting standard types of road sign shall be as indicated in the Drawings. 

811.4 Measurement and Payment 

a. Measurement 
 
No change. 

b. Payment 
 
Pay Item  Pay Unit 
 
811(1)  Provide and erect single pole road signs  Number 
811(2)  Provide and erect double pole road signs  Number 
 
Add the Following Series :‐ 

812 BUS BAYS  
 

812.1 Description 
 
This work shall consist of constructing Bus‐bay at locations of bus stoppage as decided by the 
Engineer  with  proper  signs  in  accordance  with  these  specifications  and  drawings  or  as 
directed by the Engineer. The length of Bus‐bay will depend on storage bay length of number 
of buses to be pulled in plus tolerance, which shall be 15 metre minimum for each bus or as 
directed by the Engineer. 
 

812.2 Materials 
 
Bus‐bay  shall  be  constructed  at  specified  location  by  widening  the  formation  level  and 
pavement  along  with  raised  kerbs  for  separating  it  from  main  carriageway  with  shape  and 
dimension  as  shown  on  the  drawing.  The  materials  required  for  various  items  of  works 
involved  in  constructing  the  bus‐bay  e.g.  earthwork,  pavement,  kerbs  etc.  shall  be  in 
accordance with the provisions of this specification. 
 

812.3 Construction Requirements 
 
The various item of work involved shall be similar as specified in these specifications under 
different clauses for materials, pavement, embankment, kerb(s) for the roadway. 
 

812.4 Measurement and Payment 
 
Bus‐bay  shall  be  constructed  at  locations  and  accepted  as  determined  from  actual  counts. 
Earthwork,  pavement  work,  shoulders  shall  be  measured  separately  and  will  be  paid  for 
along  with  the  respective  items  of  works  involved  included  in  the  BoQ.  Raised  kerbs  are 
required  to  form  a  complete  bus  bay  unit.  Drainage  outlet  shall  be  provided.  Payment  for 
kerbs and Drainage outlets will be made through respective pay items in the BoQ. 
 

Series 800 – Incidental Constructions         Page no: 15 of 29 
SRI LANKA OPERATIONS CENTRE

813 CONCRETE KERB INLETS 

813.1 Description 
 
This work shall consist of the construction of kerb inlets to lines, levels and grades as shown 
on the Drawings or as indicated by the Engineer. 
 
The  dimension  of  the  inlets  shall  be  as  shown  on  the  Drawings  or  as  instructed  by  the 
Engineer. 

813.2 Materials 
 
Concrete for precast or cast in place units and concrete for kerbs shall be of Class A or B of 
grade 20/20 as per section 1001. 
 
The  other  material  used  shall  meet  the  requirements  of  the  following,  unless  otherwise 
specified. 
 
(a) Reinforcement steel to SLS 375 or CS 26 
(b) Bed course material shall consist of sand, gravel, crushed stone or other approved 
material of 10 mm maximum size 
(c) Cement mortar for jointing to sub section 1703.2 

813.3 Construction Requirements 
 
The  Construction  requirements  shall  be  the  same  as  subsection  807.3  (a)  &  (b)  for 
installation of kerbs. 

813.4 Measurement and Payment 

a. Measurement 
 
Kerb inlet furnished accepted and placed shall be measured by the number. 

b.  Payment 
 
The  payment  will  be  based  on  the  contract  unit  rate  for  the  item  which  shall  include  full 
compensation for supplying and installing the kerb inlet.  The rate shall also include the cost 
of  all  materials,  labour,  equipment  tools  and  other  incidentals  necessary  to  complete  the 
works to these specifications. 
 
Pay Item  Unit of Measurement  
 
813(1)  Kerb Inlets   Number 
 

814 HNADRAILS, UPRIGHTS AND END PILASTERS 

814.1 Description 
 
This work shall consist of the construction of handrails, uprights and pilasters at the locations 
and  to  the  dimensions,  lines  and  levels  shown  on  the  drawings  or  as  instructed  by  the 
Engineer. 

Series 800 – Incidental Constructions         Page no: 16 of 29 
SRI LANKA OPERATIONS CENTRE

 
Handrails and uprights, which are meant essentially to protect vehicles and pedestrians from 
falling off the edge of bridge decks, shall be positioned away from the carriageway edge so as 
not to interfere with the normal movements of traffic. 
 
End pilasters shall be positioned at the ends of the handrails behind the movement joints, in 
each corner of the bridge decks. 

814.2 Materials 
 
Concrete used for the casting of handrails, uprights and end pilasters shall be of Grade A or B 
as given in Section 1001 and as specified. 
 
The  other  materials  used  shall  meet  the  requirements  of  the  following  unless  otherwise 
specified :‐ 
 
a) Reinforcing steel to SLS 375, CS 26 or BS 4449 
b) Cement mortar for jointing to sub‐section 1703.2 
c) Bitumen joint fillers shall be of the approved varieties. 
 

814.3 Construction Requirements 
 
a) Handrails and Uprights 
 
Handrails  and  uprights  shall  consist  of  precast  concrete  post  and  rail  jointed  with  in‐situ 
concrete and mortar joints.  Their assembly and erection shall be as shown in the Drawings 
or as instructed by the Engineer.  Concreting of posts and rails shall be in accordance with 
Section 1001 and reinforcement in accordance with Section 1002 
 
Posts  shall  be  set  vertical  in  pockets  filled  with  concrete  as  shown  on  the  Drawings  or  as 
instructed by the Engineer. 
 
Rails  shall  be  set  parallel  to  the  bridge  deck  or  as  instructed  by  the  Engineer.    Jointing 
between  rails  and  between  posts  and  railing  shall  only  be  carried  out  after  the  posts  have 
set.  Joint mortar and in‐situ concrete shall be trowelled to a neat finish. 
 
No  Site  drilling  or  cutting  of  pre‐cast  posts  and  rails  shall  be  permitted  without  the  prior 
approval of the Engineer. 
 
b) End Pilasters 
 
End  pilasters  shall  be  precast  or  cast  in‐situ  using  concrete  of  the  specified  grade.    Their 
assembly and erection shall be as shown on the Drawings of as instructed by the Engineer.  
Forms for the concrete shall be wood, metal or suitable material and shall extend to the full 
depth of the concrete. 
All  forms  shall  be  free  from  warp  and  of  sufficient  strength  to  resist  the  pressure  of  the 
concrete  without  displacement.    All  forms  shall  be  clean  and  coated  with  an  approved  oil 
before concrete is placed and compacted.  Reinforcement shall be maintained in its correct 
position during concreting. 
 
Concrete shall be proportioned, mixed and placed in accordance with the grade of concrete 
specified.    Compaction  of  the  concrete  placed  in  the  forms  shall  be  by  vibration  or  other 
acceptable methods.  Forms shall be left in place for 24 hours or until the concrete has set 
sufficiently so that they can be removed without deformation to the concrete placed.  The 

Series 800 – Incidental Constructions         Page no: 17 of 29 
SRI LANKA OPERATIONS CENTRE

finished concrete shall be kept moist for a minimum of 7 days.  The method of curing shall be 
subject to the approval of the Engineer. 

814.4 Measurement and Payment 

a. Measurement 
 
Unless otherwise specified, handrails and uprights shall be measured by the length in metres 
of the handrails and end pilasters by the number of each. 

b. Payment 
The unit rate of each item of work shall be for full compensation for all labour, equipment, 
tools, materials and incidentals necessary to complete the work as specified. 
 
The pay Items and Pay Units will be as follows :‐ 
 
Pay Item  Pay Unit 
 
814(1)  Handrails and Uprights  Ln. metre 
814(2)  End Pilasters  Number 
 
815  BRIDGE LIGHTING 
 
815.1  GENERAL 
 
Scope of Work 
 
The  work  consists  of  supply,  delivery  to  site  installation  and  putting  into  commission  after 
requisite tests for the Bridge street lighting services and associated system: 
 
The services comprises 
 
Bridge lighting 
Approach lighting 
Power connection from existing Ceylon Electricity Board system 
L.T. distribution system for bridge/Approach lighting. 
 
Regulations and Standard 
 
The  electrical  installation  shall  comply  with  this  specifications  with  all  relevant  British 
Standard and Code of Practice and with the Electricity Rules of the Government of Sri Lanka 
and in particular with the followings :‐ 
 
Ceylon Electricity Board Authority requirement 
Local fire prevention Authority requirement 
British code of practice ‐ current at the time of installation 
All local authorities statutory by law of regulation. 
Any special requirement of Chief Electrical Inspector, Government of Sri Lanka 
 
Environment 
 
All equipment and material supplied shall be suitable for continuous operation and storage 
at 
Temperature 5°C to 40°C 
Relative Humidity ‐ up to 98% 

Series 800 – Incidental Constructions         Page no: 18 of 29 
SRI LANKA OPERATIONS CENTRE

Attitude  : Sea level 
Air pollution ‐ Industrial (assumed) 
The equipment and materials shall be suitable for outdoor use. 
 
Programme 
 
The  Contractor  shall  provide  at  the  tender  stage  a  full  detailed  bar‐chart  of  his  proposed 
programme showing the number of personnel required to complete the various installation 
within  a  given  time  scale  starting  and  finishing  date  of  each  activity  including  import  of 
material commissioning as well as testing to suit the Authority requirement and up to date 
modify or redraft the programme as necessary. 
 
The programme shall comply with the overall completion dates. 
 
Materials and Workmanship 
 
All materials and the constructional plant shall supply by the contractor. All the material shall 
be  of  highest  quality  and  the  suitable  for  its  intended  use  and  shall  comply  with  relevant 
British Standard or other international standard by and be installed in accordance with codes 
of practice and manufacture’s recommendation and the specification. 
 
All operatives shall be suitably qualified and experienced for the work they are carrying out. 
All  workmanship  shall  be  of  highest  standard  and  shall  be  upto  the  satisfaction  of  the 
supervising officer.  The contractor shall set up his own quality control procedure to ensure 
that  materials  received  on  site  are  of  the  correct  quality  and  are  installed  in  the  best 
workmanship like manner. 
 
Poor materials and workmanship or any material workmanship found not satisfactory by the 
Engineer‐in‐charge  shall  be  removed  and  replaced  at  once  by  the  contractors  at  his  own 
expenses  and  no  extension  of  time  will  be  granted  as  result  of  any  delay  incurred.  The 
contractor shall implement and maintain a quality system conforming to the requirement of 
BS 5750 or equivalent standard approved by the purchaser, to enable full compliance  with 
the requirement of the specification. 
 
Name Manufactures/Suppliers 
 
Not  with  standing  that  suppliers  may  have  been  named  or  approved  by  the  Engineer‐in‐
charge, it shall be the contractor's responsibility to ensure that all materials and components 
are upto specification in respect of manufacturer, finish and performance. 
 
The contractor shall be responsible for ensuring that such materials are available to suit the 
construction  programme  and  for  ensuring  that  materials  etc.  are  ordered  in  time  to 
accommodate delivery to suit that requirement. 
 
Samples 
 
The  engineer‐in‐charge  reserves  the  right  to  call  for  samples  of  some  or  all  materials  and 
products to be used.  
 
The  contractor  shall  obtain  such  samples  as  required  and  submit  them  to  the  Engineer‐in‐
charge within 14 (fourteen) days of a request to do so. 
 
The contractor shall allow in his tender for obtaining such samples as required. 
 
Material to be new and unused 

Series 800 – Incidental Constructions         Page no: 19 of 29 
SRI LANKA OPERATIONS CENTRE

 
All  the  materials to be supplied by the contractor under the terms of the contract shall be 
new. Any used or worn material shall not be used in the works. Though they may satisfy the 
specifications. 
 
Supervision 
 
The contractor shall employ a competent, qualified site engineer who shall be in charge of 
the  work  during  all  working  hours  and  shall  be  the  dully  accredited  representative  of  the 
contractor empowered to take instructions from the Engineer‐in‐charge and to execute same 
and  who  must  be  in  attendance  at  the  premises  until  the  whole  of  the  works  have  been 
completed and accepted on behalf of the Client by the Engineer‐in‐charge. The construction 
site  shall  be  the  normal  place  of  work  for  the  contractor's  site  Engineer  and  during  his 
periods of absence from site, a deputy shall be nominated and approved by the Engineer‐in‐
charge. The contractor’s representatives shall attend meetings at site or at the offices of the 
professional team when called upon so to do. 
 
Operating Conditions and Guarantee 
 
The  contractor  works  shall  be  of  such  construction,  manufacture  and  finish  as  to  render 
them suitable for operating throughout their expected life and to maintain design conditions. 
 
Working Drawing 
 
The  contractor  shall  be  responsible  for  providing  fully  dimensioned  installation  working 
drawings for all and very pert of the works. The working drawings shall be submitted to the 
Engineer‐in‐charge for approval in good time to meet an agreed programme for the works. 
 
The drawings shall include the following: 
 
a)  Detailed  conduit,  cables  route  and  connection,  design  for  street  lighting  poles, 
distribution boxes etc. 
 
b)  fully detailed  co‐ordinated drawings  indicating all plant, equipment, cable routes, 
electrical conduits pipe work that is to be installed, giving lines, levels and positions 
of equipment. 
 
c)     Drawings of manufactured and fabricated items and equipment. 
 
d)  Wiring  diagrams  showing  external  wiring  between  manufacturers  equipment  and 
controls, instruments and instrument panels switchgear. 
 
Information Required With The Tender 
 
a)  The tender shall submit with tender the description of all materials and equipment 
that  he  proposes  to  use  along  with  their  technical  literature.  BSS  references, 
performance figures, wiring diagram and dimension of the equipment. 
 
b)     Name of manufacturers of the major items being offered. 
 
c)     A statement of compliance as the specification. 
 
d)     Confirmation that the proposed layout is satisfactory. 
 
As Fitted Record Drawings 

Series 800 – Incidental Constructions         Page no: 20 of 29 
SRI LANKA OPERATIONS CENTRE

 
The  contractor  shall  supply  to  the  Engineer‐in‐charge  as  a  pre‐requisite  to  practical 
completion  of  the  works,  comprehensive  as  fitted  record  drawings  finalized  in  detail  and 
approved  by  Engineer‐in‐charge.  The  contractor  shall  demonstrate  from  time  to  time  as 
required  by  the  Engineer‐in‐charge  throughout  the  execution  of  the  works,  that  adequate 
and  accurate  records  are  being  kept  such  as  well  ensure  the  ultimate  completeness  and 
accuracy  of  as  fitted  record  drawing  and  that  the  record  drawings  themselves  are  being 
progressively compiled as the work on site proceeds. 
 
The  contractor  shall  submit  one  copy  of  the  as  fitted  drawings  for  the  Engineer‐in‐charge 
approval prior to supply of final negatives. 
 
Operating and Maintenance Instruction 
 
At the time of practical completion of the contract the contractor shall provide complete set 
at  operating  and  maintenance  instruction  manuals  in  approved  good  quality  ring  binders 
with printed covers. The type, size, appearances and cover printing of the manuals shall be 
agreed with the Engineer‐in‐charge and samples shall be submitted for final approval before 
supplying the required number of manuals. 
 
The operating and maintenance manuals shall contain: 
 
a)  A complete description of each mechanical and electrical system including control 
systems,  giving  its  function  or  purpose,  duties,  method  of  operation,  balancing  or 
adjusting,  related  to  the  appropriate  ''As  fitted"  drawings  and  cross‐referenced  as 
necessary. 
 
b)    Instruction  for  any  precautionary  measure  from  time  to  time  necessary  (e.g. 
corrosion etc.). 
 
c)  A  complete  set  of  test  certificates  as  appropriate  to  the  various  electrical  system 
and equipment. 
 
Testing and Commissioning: 
 
General 
 
The procedure for commissioning and testing shall be agreed with the Engineer‐in‐charge. 
 
The  contractor  shall  then  conduct  the  tests  and  provide  all  facilities  for  the  Architect  to 
witness and inspect all their results, instruments and labour for those tests shall be provided 
by  the  contractor  and  records  shall  be  made  by  the  contractor  of  all  tests  and  the  results 
submitted to the Engineer‐in‐charge on approved test certificates and test result sheets. 
 
Facilities shall be made available for representative of the Engineer Ceylon Electricity Board 
and  Chief  Electrical  Inspector.  Government  of  Sri  Lanka  to  witness  tests  as  required.  A 
suitable qualified representative of the contractor shall be available for all tests. 
 
Where tests show that the plant and equipment do not function in a manner satisfactory to 
the Engineer‐in‐charge meeting the design parameters laid down by the Engineer‐in‐charge 
then  the  contractor  shall  carry  out  at  their  own  expense  such  remedial  works  as  may  be 
required. 
 
Electrical Work Test and Inspection 
 

Series 800 – Incidental Constructions         Page no: 21 of 29 
SRI LANKA OPERATIONS CENTRE

Testing  of  equipment  at  the  manufacturers  works  prior  to  dispatch  shall  be  carried  out  in 
accordance with the relevant B.S. Specifically   or   Code   of   practice   and   manufacturers 
recommendations  and  the  contractor  shall  submit  copies  of  the  manufacturers  test 
certificates to the Engineer for approval. 
 
Electrical Site Test 
 
The  contractor  shall  carry  out  site  tests  on  completed  installations  in  accordance  with  the 
current  edition  of  the  IEE  Regulations,  the  appropriate  B.S.  Specification/Code  of  practice, 
and equipment manufacturers recommendations. The tests shall include, but not be limited 
to the following : 
 
LV Cables 
 
Upon  completion  of  a  cable  end  or  straight  through  joint  and  before  connection  to  any 
equipment, an installation resistance test shall be carried out and an infinity reasing obtained 
with a 2000 Volt Meter. A similar test shall be carried out after the expiration of an agreed 
period and should lower values of insulation resistance be obtained, the faulty seals shall be 
re‐made at the contractor's expense and to the satisfaction of the engineer‐in‐charge. 
 
The continuity of each cable sheath shall be tested between the point at which the earthing 
connection is may to the switchboard and the most distant point of the run. 
 
Earthing 
 
The resistance of all earth electrodes, shall be measured as laid down in BS CP 1013 (1965) 
and the current edition of the IEE Regulation of earth electrode networks for power earthing 
shall not exceed 2 Ohms. Continuity tests using a "Ductor Ohmeter" type low voltage heavy 
current instrument shell also be carried out. 
 
Visual Inspection 
 
i)  A visual inspection shall be made to verify that the power installation equipment is: 
In  compliance  with  the  Standards  quoted  in  this  specification,  Correctly  selected 
and erected. Not visibly damaged. 
 
ii)  The visual inspection shall include, as relevant 
 
  Connection of conductors,  
  identification of conductors 
  selection of conductors for current carrying capacity and voltage drop. 
connection  of  single  pole  devices  for  protection  or  switching  in  phase  conductors 
only ton distribution circuits only) 
  presence of fire barrirs and protection against thermal effects, 
  methods of protection against direct contract (including  measurement  of distance  
where appropriate) i.e. 
 
815.2  CONSTRUCTIONAL REQUIREMENT 
 
Light Fixture 
 
The  light  fittings  shall  comply  with  the  relevant  requirement  of  applicable  BS  including  BS 
4533.  The  light  feature  shall  be  90W  low  pressure  sodium  lamp  (SOX‐90W)  complete  with 
starting  gears,  holder,  light  weight  glass  fiber  reinforced  polyester  housing,  clear 
methacrylate  bowl,  high  purity  anodized  aluminum  reflectors.  All  exposed  metal  parts  of 

Series 800 – Incidental Constructions         Page no: 22 of 29 
SRI LANKA OPERATIONS CENTRE

stainless  steel,  suitable  for  side  entry  on  mast,  Neoprene  ring  in  spigot‐entry  to  prevent 
ingress of water and insects etc. 
 
Appropriate samples of light fixture shall be submitted prior to installation. The street light 
fixture  shall  be  installed  in  accordance  with  applicable  fitting  layout  drawing.  Each  fitting 
shall be complete with all accessories and consumable shall be considered as one unit. 
 
Street Light Post 
 
Steel  galvanized  pole  as  specified  in  the  drawings  shall  be  fabricated  and  installed  as  per 
relevant code and standards and Ceylon Electricity Board standard. A junction box complete 
with accessories and opening lid just above the base plate of pole shall be provided. 
 
The pole shall have galvanized steel base plate of 12mmthick of size 200mmx200mm with a 
hole of 37mm die at the center and four hole of size 20mm at the corners of the plate. The 
distance between the poles shall be as specified in the layout drawing. 
 
Arrangement  shall  be  provided  for  termination  of  cables  at  each  pole  complete  with 
connectors fuse, earthling block, sealing arrangement at the entrance of the cable to avoid 
ingress of water and vermin. The sealing of the cable at pole shall be water light. 
 
PVC Insulated Cable 
 
The  cables  shall  be  armoured/  non‐armoured  as  specified  on  the  drawings/schedule,  shall 
have 600/1090 volt grade PVC insulation and shall comply with B.S. 6004 conductors shall be 
plain annealed copper to B.S. 6360. 
 
The  following  colours  shall  identify  the  core  of  multicore  PVC  insulated  armoured/ 
unarmoured cable. 
 
AC  Three phase     :  phase: Red‐Yellow, Blue 
  (3/4 cores)    :  Neutral: Black 
  single phase    :  phase‐Red 
  (2 core)    :  neutral‐Black  
 
The conductor shall be insulated with type 5 PVC complying with B.S. 6746. The cable shall 
be filled internally and sheathed with PVC to B.S. 6746 type 1 and where used underground 
or external or specified shall be single wire armoured and PVC sheathed overall. Contractor 
shall be responsible to ensure that cable sizes and lengths are correct and comply with the 
relevant standard. 
 
Jointing and Terminating 
 
a)  The outer sheath or armour of all cables shall be securely retained by the use of the 
correct type and size of brass cable gland. Such cable glands shall securely retain the 
outer sheath or armour without damaging it. 
 
b)  Where cable glands are used for terminating cables within non‐metallic boxes, the 
earth  continuity  shall  be  maintained  by  a  bonding  strap  having  a  resistance  not 
higher than an equivalent length of cable sheath or armour. 
 
c)  Every  cable  core  termination  shall  be  of  the  sealed  or  compression  socket  type, 
unless the cable i. terminated in an approved connector. 
 

Series 800 – Incidental Constructions         Page no: 23 of 29 
SRI LANKA OPERATIONS CENTRE

d)  Cable  core  terminations  shall  securely  contain  and  anchor  all  the  wires  of  the 
conductor, and shall not impose any appreciable mechanical strain on the terminal 
socket, or connector. 
 
e)  Soldering fluxes, which remain acidic or corrosive after soldering is completed shall 
not be used. 
 
f)  The cable glands shall be secured by brass lock washers and fitted with the correct 
shrouds. 
 
g)  All cable joints, termination and seals shall be made only by an experienced jointer 
and shall be acceptable to the Engineer‐in‐charge. 
 
h)  Termination, joints and seals shall be made in full accordance with the current IEE 
Regulations. 
 
i)  Joints  shall  be  enclosed  in  purpose  made  cast  iron  box  filled  with  compound  and 
fitted with armours clamps and an electrical continuity copper strip bonded to the 
armouring on either side of the box. 
 
j)  Where  the  cable  is  cut  during  the  course  of  installation  the  open  ends  shall  be 
sealed immediately by means of sell adhesive non‐hydroscopic tape or a wax water‐
tight seal to make an air and water‐tight‐joint. 
 
k)  Approved tests shall be carried out on all cables and materials before jointing. 
 
Minimum Internal Radu of Bends 
 
This shall be in accordance with the cable manufactures recommendation. For PVC insulated 
cables the minimum bending radu shall not be less than 8 times the cable diameter. 
 
Cross Site Installation of Cable 
 
a)  Cable shall be laid or installed in one length from terminal point to terminal point. 
No through joints will be permitted, unless authorized in writing by the Engineer‐in‐
charge  and  then  only  if  the  need  arises  due  to  an  alternation  in  route  length 
necessitated  by  circumstances  which  the  contractor  could  riot  reasonably  have 
foreseen. If any such through joint is authorized for a cable laid underground, the 
position shall be identified precisely over the joint, at ground level, by means of a 
suitable  inscribed  concrete  cable  marker.  Any  such  joint  authorized  for  a  cable 
installed above ground shall be located in such a position as to be readily accessible 
at all times. All through joints shall be core to core (phase to phase). 
 
b)  Cables  shall  be  delivered  to  and  handled  around  the  site  on  cable  drums.  During 
installation  cables  shall  be  played  out  from  the  top  of  the  drum,  guided  by 
supporting runners where necessary and the drum braked to avoid over‐run, Cables 
shall not be handled, run off drums or installed when the ambient temperature is at 
or below 0°C. 
 
c)  The cable trenches shall be excavated by the contractor to ensure that the cable are 
laid  at  least  at  a  depth  of  500mm  below  the  ground  surface  upon  a  bed  of  sand 
150mm deep. The depth of trench shall be as directed by the Engineer‐in‐charge. 
 
d)  Cable ducts shall be provided under roads and other paved area. 
 

Series 800 – Incidental Constructions         Page no: 24 of 29 
SRI LANKA OPERATIONS CENTRE

e)  After  approval  of  the  lay  the  trench  shall  be  back‐filled  by  material,  which  has 
passed through a 12mm riddle. 
 
f)  Power cables shall be laid with a slight snake formation to ensure there is minimum 
strain during expansion and contraction due to temperature variations. 
 
g)  Where a number of cables (including signal cables) are laid in a common trench: 
 
 i)  The cables shall be laid in accordance with the appropriate drawing. 
  ii)  The cables need not all be laid at 500mm below ground level (due to trench width 
restriction). 
  iii)  Cables  carrying  power  shall  be  a  minimum  of  300mm  from  signal  and 
telecommunications cables. 
  iv)  The  cable  formation  shall  minimize  crossings  (to  points  where  cables  divert  to 
locations). 
 
h)  Cable tray shall be used while running cable under the bridge. 
 
Street Light Distribution Board 
 
The  distribution  board  shall  be  made  of  18  SWG  M.S.  sheet  and  should  be  of  suitable 
dimension so as to accommodate the circuit breakers, cotactor, relay, energy meter, photo 
cell and bus‐bars with sufficient spacing and be spray painted with gray/white enamel paint, 
shall have hinged type door with best quality door handle, door locks and door latches. The 
distribution board shall be of double door type i.e. one cover door inside through which only 
the  knobs  of  MCB/MCCB,  manual/auto  switches  etc,  are  accessible.  The  distribution  board 
shall  be  suitable  for  outdoor  mounting,  dust  and  rain  proof  and  shall  have  knockouts  for 
conduit entry and exist at the bottom. The DB shall be installed at a height of 820mm feet 
above  the  ground  with  the  help  of  MS  angle  embedded  in  the  ground  with  CC  work.  A 
copper  plate‐earthing  block  must  be  provided  inside  the  board.  The  circuit  breakers  and 
contactor  shall  be  AEG,  SIEMENS,  MITSUBISHI  or  of  approved  brand.  The  work  shall  be 
complete  in  all  respect  including  all  necessary  arrangements  as  per  drawing  circuit 
breakers/isolators,  of  DB  shall  be  designed  for  operation  on  a  240/400V,  50Hz,  3  phase,  4 
wire  system,  Breakers  shall  have  inverse  time  tripping  with  thermal  and  magnetic  trip 
element. All circuit breaker shall be trip free and shall be of the indicating type. The panels 
shall have the phase clearly marked and where required, must have solid neutral buses. The 
panels shall be constructed as per schedule, and shall comply with relevant requirements of 
applicable BS including BS 4649, where applicable, and would be painted with two (2) coats 
of  gray  Duco  to  BS  38  IC  shade,  with  standard  concentric  knockouts  of  required  sizes  all 
around. The panels shall have directory frames and printed directory on/in side of door. The 
door is to be provided with flush lock handle. AH doors are to be keyed alike, all hinges shall 
be concealed. 
 
The  MCB/MCCBs  shall  be  quick‐make,  quick‐break  type,  and  shall  have  inverse‐time  limit 
characteristics will instantaneous magnetic trip elements functioning on overloads above the 
normal  operating  range.  All  circuit  breakers  shell  is  trip‐free.  Ratings  and  frame  sizes  of 
breakers  shall  be  in  accordance  with  schedule.    All  lugs  must  be  of  the  shoulder  less 
mechanical type. The MCB must comply with BS 3871: part 1 (1965) category M4 (5A‐60A). 
Rated  voltage  240/400V,  A.C.    50Hz,  interrupting  capacity  4000  amp  capable  of  providing 
overload  and  short  circuit  protection,  through  thermal  and  magnetic  trip  actions 
respectively,  temperature  rating,  400C  preferably  trivialized  (moisture  fungus  corrosion 
treated),  terminal  capability  upto  35mm²  wire.  The  MCCB's  shall  have  the  following 
symmetrical interrupting capacity at 480V A.C. if not indicated otherwise: 
 
Upto          10A        :    4   KA  

Series 800 – Incidental Constructions         Page no: 25 of 29 
SRI LANKA OPERATIONS CENTRE

10A      to    60A     :  14  KA 


70A      to    200A     :  22  KA  
200A      to    500A     :  30  KA  
 
The continuous current ratings of individual MCBFICCB's may he varied within + 15X at the 
time of installation without any cost implication. 
 
Earthing 
 
Materials 
 
Earth Electrode 
 
 i)  Pipe Electrode (where applicable) 
 
    This would be 38mm die G.I, pipe with two 3mm die holes across the diameter at 
every 1200mm at the pipe. 
 
 ii)  Plate Electrode (where applicable) 
 
    This earth electrode shall be cold roiled double copper plate 600mmx600mmx3mm 
having provision for connecting the earth lead. 
 
Earthling Lead 
 
Earthling  lead  shall  consist  of  copper  conductor  of  100%  conductivity  at  20°C  (68DF), 
Annsealed copper stranded with weight resistively of 0.15328 Ohm‐gram/m² at 20°C (68°F) 
and  density  of  0.32117  lb/in³,  for  meeting  the  requirement  of  BS  6360:1969  or  its  metric 
adoption. All terminal lugs shall be of copper and nut bolts of brass. 
 
Earthling Block 
 
The earthling block shall be of solid electrolytic copper cost and machine of size and have at 
least  103mm  dia/drilled  holes  for  accommodating  the  terminal  of  the  earth  continuity 
conductor. Requisite number of brass nuts and bolts shall also be provided. 
 
Earth Inspection Pit 
 
Bricks  used  shall  be  1st  class  on  stone  chips.  Only  approved  quality  cement  shall  be  used. 
Stone chip for 75mm RCC cover shall be 25mm down graded with 10mm die M.S. hook (of 
50mm dia) shall be provided in the cover slab. 
 
Installation 
 
Pipe Electrode 
 
The pipe earth electrode shall be buried below ground level at 12 meter by tube‐well sinking 
method. The earth lead from the DB to the main earth electrode shall be installed in G.I. pipe 
of specified diameter. The terminal connected to the earth electrode shall use a brass clamp. 
After  making  the  connection.  The  clamp  shall  be  covered  with  bitumen  poured  hot,  and 
covered with jute cloth. The length of pipe electrode may vary to give the maximum earth 
resistance of 1 Ohm in the driest season. 
 
Plate Electrode 
 

Series 800 – Incidental Constructions         Page no: 26 of 29 
SRI LANKA OPERATIONS CENTRE

The plate earth electrode (if applicable) shall be buried below ground level as per schedule 
and installed in an upright position if completely surrounded by a bed or at least 300mm of 
charcoal  fixed  with  line  and  packed hard. Distance between any two‐earth electrodes shall 
be at least 8 meters. 
 
Earthling Leads 
 
The earthling leads from the earth electrode shall be connected to the earthling block near 
DB. A double run of specified copper conductor (preferably tinned) shall be brought out of 
specified lead for the earth electrode through G.I. pipe from the electrode and connected to 
the earth block. There shall be no joint in the copper earth lead. All earthing lead shall follow 
the  shortest  and  most  direct  route  to  earth  electrode  and  sharp  bends  and  joints  shall  be 
avoided.  The  earthling  leads  shall  be  made  mechanically  strong  and  electrically  continuous 
with minimum of resistance. 
 
Earth Inspection Pit 
 
The earth inspection pit shall be (450mmx450x450mm inside dimension) 1st class brick with 
finished plaster surface including the RCC pit cover (100mm thickness 1:2:40 ratio). The slab 
shall have level surface and the pit shall have well formed regular sides. Water curing for the 
slab and the pit shall be done for a minimum of 6 days. 

815.3 Measurement and Payment 

a. Measurement 
 
Unless otherwise specified, Light Fixture shall be measured by the number of lighting point 
each. 

b. Payment 
 
The  unit  rate  of  this  item  of  work  shall  be  for  full  compensation  for  all  labour, equipment, 
tools, materials and incidentals necessary to complete the work as specified. 
 
The pay Items and Pay Units will be as follows :‐ 
 
Pay Item  Pay Unit 
 
815(1)  Lighting Point  Number 
 
 
816.   RELOCATION OF PUBLIC UTILITIES 
 
816.1  Description 
 
This  work  covers  all  the  requirements  for  the  relocation  of  public  utilities.  The  Contractors 
attention is brought to the requirements of the relocation of all existing utilities and services. 
The  Contractor  shall  carefully  liase  with  all  the  concerned  authorities  for  the  remova1  of 
exiting  services,  all  necessary  temporary  arrangements  and  final  relocation  and  installation 
of the utilities. 
 
816.2  Materials 
 
The material used in both temporary and permanent works associated with the relocation of 
utilities  shall  meet  the  requirements  of  the  respective  authorities.  The  Engineer  will  liase 

Series 800 – Incidental Constructions         Page no: 27 of 29 
SRI LANKA OPERATIONS CENTRE

with the Authorities on all matters relating to necessary diversion and relocation works, but 
the  Contractor  shall  retain  full  responsibility  for  coordinating  the  implementation  of  all 
relocation work which shall be an integral component of the Works. 
 
816.3  Construction  Requirement 
 
The Contractor should note that all utility companies have been notified of the scope of the 
Works  and  the  necessity  for  the  removal  and  relocation  of  power  lines,  cables  as  well  as 
water and gas mains. The concerned authorities will undertake Works for the relocation of 
existing  utilities  during  the  Works  programme  but  the  Contractor  may  also  be  required  to 
undertake works in operations involving the relocation of existing utilities. The precise details 
of  individual  requirements  will  be  agreed  upon  between  the  interested  parties  after  the 
award of Contract and such details shall be reflected in the programme to be submitted. The 
Contractors  attention  is  brought  to  the  need  to  cooperation  with  concerned  Utility 
authorities.  In  particular,  the  Contractor  shall  prepare  in  his  working  schedule  a  realistic 
programme allowing reasonable times for the removal and relocation of utility lines, for both 
commencement  and  completion  times,  which  shall  be  based  on  advance  negotiations  and 
agreements  with  the  respective  authorities  allowing  reasonable  time  in  all  cases  for  the 
carrying out of this work. The programme to be furnished for the whole the works and shall 
take account all negotiations and agreements on all such matters. 
 
The Contractor shall adopt construction methods that will make allowance for the removal 
and  relocation  of  existing  utilities  in  accordance  with  the  specifications  of  the  respective 
authorities as well as the instruction of the Engineer. The Contractor shall propose full details 
for the works that are affected by the removal and relocation of all utilities. Such proposals 
shall take into account the Contractors full obligations for the Works as well as the minimal 
disruption to utility services. 
 
816.4  Measurement and Payment 
 
Measurement and payment for the removal and relocation of some existing utility services 
may  be  made  on  the  basis  of  Prime  Cost  (P.C.)  item  allowed  for  all  such  works.  Such 
payments will cover for possible payments to be made by the Contractor to the concerned 
authorities for work operations undertaken by the authorities in connection with the works 
for relocation of existing utilities. The Contractor shall indicate in the Tender the percentage 
adjustment  required  for  the  use  of  the  P.C.  item  which  shall  cover  all  the  Contractors 
obligations  for  implementing  this  work  item.  Where  appropriate,  the  Engineer  may  also 
order work for the removal and relocation of utilities services on a Force Account Basis. Such 
payments  shall  be  full  compensation  for  complying  with  this  section  of  the  Specification, 
Conditions of Contract for the whole of the Works. 
 
 
Pay items         Pay Unit 
816(1) Relocation of Public Utilities Provisional Sum 
 
plus % Allowance for Overheads, etc. on the Provisional Sum to be inserted by the Contractor 
Prime Cost 
 
 
 
 
 
 
 
 

Series 800 – Incidental Constructions         Page no: 28 of 29 
SRI LANKA OPERATIONS CENTRE

 
 
 
 

Series 800 – Incidental Constructions         Page no: 29 of 29 
SRI LANKA OPERATIONS CENTRE

SERIES 900 – RIGID PAVEMENTS 
 
 
 
CONTENTS 
 
 
 
900  RIGID PAVEMENTS ..............................................................................................................2 
901  Cement Concrete Pavement............................................................................................2 
901.1  Description .................................................................................................................2 
901.2  Materials, mix requirements and testing for quality ....................................................2 
901.3  Construction Requirements ........................................................................................5 
901.4  Measurement and Payment...................................................................................... 11 
 

Series 900 –Rigid Pavements           Page no: 1 of 12 
SRI LANKA OPERATIONS CENTRE

SERIES 900 – RIGID PAVEMENTS 
 
 

900  RIGID PAVEMENTS 

901  Cement Concrete Pavement 

901.1  Description 

Delete this sub‐section and substitute the following :‐ 
This section covers the specification of materials for, and the construction of, un‐reinforced 
and reinforced concrete pavement slabs. The concrete pavement shall be constructed to the 
dimensions and cross sectional profiles shown in the contract drawings. 
 

901.2 Materials, mix requirements and testing for quality 

Delete this sub‐section and substitute the following :‐ 
The  contractor  shall  submit  the  details  and  material  sources  of  all  the  materials  to  the 
Engineer for the approval. Samples shall be submitted to the Engineer, and when approved 
by  him  all  materials  used  in  the  work  shall  all  respects  be  equal  thereto.  If  alternative 
materials are proposed, 28 days notification is required for the approval. 
All  concrete  for  use  in  pavements  shall  comply  with  BS  5328,  except  where  otherwise 
specified in this clause.  

a. Cement 
The cement shall be Ordinary Portland Cement complying with the requirements of BS 12 or 
 
AASHTO M‐85 or SLS 107.
b. Aggregates 
Coarse & fine aggregates shall comply with the requirements in sub section 1701.2 
c. Water 
Water for mixing and curing shall comply with SLS 522.  
d. Reinforcement 
Steel reinforcement shall comply with any of the following standards and be in prefabricated 
sheets or bars assembled on site and be free from oil, dirt, loose rust or scale. 
 
  Steel fabric in flat sheets      BS 4483 
  Hot rolled steel bars Grade 250    BS 4449 
  Hot rolled steel bars Grade 460    BS 4449 
  Cold worked steel bars       BS 4461 
When deformed bars are used they shall confirm to type 2 bond classification of BS 4449 & 
BS 4461. 
e. Dowel Bars  
Dowel bars shall be Grade 250 steel complying with BS 4449 and shall be free from oil, dirt, 
loose rust or scale. They shall be straight, free of burrs or other irregularities and the sliding 
ends sawn or, if approved by the Engineer, cropped cleanly with no protrusions outside the 
normal diameter of the bar. 

Series 900 –Rigid Pavements           Page no: 2 of 12 
SRI LANKA OPERATIONS CENTRE

f. Tie Bars  
Unless otherwise stated in the Contract, tie bars in transverse or longitudinal joints shall be 
Grade 250 steel or Grade 460 deformed steel bars complying with BS 4449 or BS 4461. Tie 
bars  shall  be  free  from  oil,  dirt,  loose rust and scale. Tie bars which are to be cranked and 
later straightened shall be of mild steel. 
g. Admixtures 
An air‐entraining admixture complying with the requirements of BS 5075 Part 2 shall be used 
in  the  concrete.  In  addition,  water  reducing  retarding  admixtures  complying  with  BS  5075 
Part  1  may  also  be  used with the approval of the Engineer. Admixtures containing Calcium 
Chloride shall not be used.  
h. Expansion Joint Filler Board 
The  expansion  joint  filler  board  shall  be  of  either  cork  or  fibrous  compressible  material 
complying with either AASHTO M‐153 or AASHTO M213. Alternatively a bonded combination 
of rigid and compressible material approved by the Engineer, shall be used. 
i. Joint Sealants 
Joint  seals  shall  consist  of  hot  or  cold  applied  elastomeric  type  sealant  or  preformed 
compression sealant. Hot applied sealant shall comply with the requirements of AASHTO M‐
282  or  ASTM  D3406  or  D3569.  Cold  applied  elastomeric  type  sealant  shall  comply  with 
AASHTO M‐282 or BS 5212 Preformed compression seals shall be made of polychloroprene 
elastomers complying with BS 2752 and ASTM D2628. 
j. Class & Strength of Concrete  
Concrete shall be of class A confirming to sub sections of this series and shall be designed to 
have a minimum compressive strength of 25 N/Sqm at 28 days. The water content shall be 
the minimum required to provide the agreed workability for full compaction of the concrete 
to  the  required  density,  as  determined  by  trial  mixes  or  other  means  approved  by  the 
Engineer, and maximum free water – cement ratio shall be 0.5. 
k. Maximum size and grading of aggregate 

The  nominal  size  of  coarse  aggregate  shall  not  exceed  40mm.  When  the  spacing  between 
longitudinal reinforcement is less than 90mm, the nominal size of coarse aggregate shall not 
exceed 20mm. 

l. Compliance Testing 

Concrete Strength 
 Sampling  and  testing  and  compliance  for  the  specified  characteristic  strength  of  the 
designed mixes shall be in accordance with BS 5328, except that it shall be at the following 
rate of sampling and testing and with the following requirements. 
150 mm concrete cubes shall be made and cured in pairs and tested in accordance with BS 
1881 from concrete delivered to the paving plant, each pair being from different delivery of 
concrete. At least one pair of cubes shall be made for each 600 Sqm of concrete slab and not 
less than 6 pairs shall be made each day for each type of mix. For areas less than 600 Sqm, at 
least 4 cubes shall be made for each 100 Sqm or less. This rate of sampling and testing may 
be reduced at the Engineer’s discretion. 
For areas of 600 Sqm or more, one cube of each pair shall be tested in compression at 7 days 
and the other at 28 days after mixing. Groups of four consecutive results from single cubes 
tested at 28 days shall be used for assessing the strength for compliance with BS 5328. For 
areas less than 600 Sqm, two cubes shall be tested at 7 days and two tested at 28 days and 
assessed as in BS 5328. 

Series 900 –Rigid Pavements           Page no: 3 of 12 
SRI LANKA OPERATIONS CENTRE

The ratio R between 7 and 28 day strengths shall be established for the mix to be used in the 
slab by testing pairs of cubes at each age on at least 6 batches of the trial mix. The average 
strength of the 7 day pair of cubes shall be divided by the average strength of the 28 day pair 
of cubes for each batch and the ratio R shall be the average of these six values. The ratio R 
shall be expressed to three decimal places. 
If during the construction of the trial length or during normal working the average value of 
any  4  consecutive  7  day  test  results  falls  below  the  strengths  given  in  Table  “7  Day  Cube 
Strengths”  then  the  cement  content  of  the  concrete  shall  without  extra  payment,  be 
increased  by  5%  by  mass  or  by  an  amount  agreed  by  the  Engineer.  The  increased  cement 
content  shall  be  maintained  at  least  until  the  four  corresponding  28  days  have  been 
assessed. If the cement content is increased, the concrete mix shall be adjusted to maintain 
the required workability. 
 
TABLE :  7 Day Cube Strengths 
Grade of Concrete  OPC Mixes  R available  N/Sq  OPC  Mixes  R  not 
mm  available N/Sq mm 
40  43 R  31 
30  33 R  24 
25  27.5 R  19 
20  22 R  15 
15  17 R  12 
10  10 R  7.5 
 
  Workability 
The workability of the concrete at the point of placing shall enable the concrete to be fully 
compacted and finished without undue flow. The optimum workability for the mix to suit the 
paving  plant  being  used  shall  be  determined  by  the  Contractor  and  approved  by  the 
Engineer. 
The  workability  shall  be  determined  by  the  Compacting  Factor  Test,  or  the  VeBe  test  or 
alternatively by the Slump test, all in accordance with BS 1881, at the minimum rate of one 
determination per 300 Sqm of slab laid or 6 times per day. For areas less than 300 Sqm the 
rate shall be at least one determination to each 20 m length of slab or at least 3 times per 
day. Tests for workability shall be carried out at the point of placing, in conjunction with tests 
for  strength  and  any  tests  for  air  content.  The  workability  shall  be  maintained  at  the 
optimum within the following tolerances. 
  Compaction Factor (CF)  ±  0.03 
  Slump        ±  20mm 
VeBe  ±    3Secs  or  as  agreed  by  the  Engi neer  as  a  result 
of trial mixes 
Any  alteration  to  the  optimum  workability  necessitated  by  a  change  in  conditions  shall  be 
agreed beforehand by the Engineer. 
If any determination of workability gives a result outside the tolerance a further test shall be 
made immediately on the next available load of concrete.The average of the two consecutive 
results and the difference between them shall be calculated. If the average is not within the 
0.03(CF)  or  10mm  (slump)  or  ±3  Secs  (VeBe)  of  the  optimum  value  or  the  difference  is 

Series 900 –Rigid Pavements           Page no: 4 of 12 
SRI LANKA OPERATIONS CENTRE

greater than 0.06 for CF or 20mm for slump or 6 Secs fo VeBe or other value agreed with the 
Engineer, subsequent samples shall be taken from the next loads, which shall not be allowed 
to discharge into the Works until compliance with the specification has been established. 
Trial Mixes 
The  Contractor  shall  carryout  laboratory  trials  of  designed  mixes  with  the  materials  from  all 
sources  to  be  used  in  the  contract.  Trial  mixes  shall  be  made  in  the  presence  of  the  Engineer 
or  his  representative  and  shall  be  subject  to  the  approval  of  the  Engineer.  They  shall  be 
repeated if necessary until the proportions that will produce a concrete which complies in all 
respects with this specification have been determined. 
The  proportions  determined  as  a  result  of  the  laboratory  trial  mixes  may  be  adjusted  if 
necessary during the construction of the trial length. Thereafter neither the materials nor the 
mix proportions shall be varied in any way except the written approval of the Engineer. 
Any  changes  in  sources  of  materials  or  mix  proportions  that  are  proposed    by  the  Contractor 
during  the  course  of  the  Works  shall  be  assessed  by  making  laboratory  trial  mixes  and  the 
construction  of  a  further  trial  length,  unless  approval  is  given  by  the  Engineer  for  minor 
adjustments. 

901.3 Construction Requirements 

Delete this sub section and substitute the following :‐ 
Subgrade requirements 
 
The  concrete  pavement  shall  be  placed  on  an  approved  subbase  of  approved  type  and 
thickness. The subbase may be of natural soil confirming to section 401 or of stabilised soils 
confirming  to  section  402.  The  subbase  may  also  be  of  graded  granular  material  to  that  of 
graded aggregate base to section 405. 
 
Separation Membrane 
 
A separation membrane shall be used between jointed reinforced concrete surface slabs or 
unreinforced  concrete  surface  slabs  and  the  subbase.  Separation  membranes  shall  be 
impermeable  plastic  sheeting  125  µm  thick  laid  flat  without  creases.  Where  an  overlap  of 
plastic sheets is necessary this shall be at least 300mm. There shall be no standing water on 
or under the membrane when the concrete is placed upon it. 
 
Steel Reinforcement 
 
Laps in longitudinal bars shall be not less than 35 times bar diameter or 450 mm whichever is 
greater. Laps in any transverse reinforcement shall be a minimum of 300mm.  
 
The reinforcement shall be fixed on approved metal supports and retained in position at the 
required  depth  below  the  finished  surface  and  distance  from  the  edge  of  the  slab  so  as  to 
ensure that the required cover is achieved. Reinforcement assembled on site shall be tied, or 
firmly fixed, by a procedure agreed with the Engineer, at sufficient intersections to provide 
the above rigidity. 
 
Unless  otherwise  described  in  contract,  any  transverse  bars  shall  be  at  right  angles  to  the 
longitudinal axis of the carriageway.The transverse reinforcement in the centre of each slab 
width shall be a minimum of 12 mm diameter bars at 600 mm centres in reinforced concrete 
slabs. This reinforcement shall be at least 600 mm longer than one third of the width of the 
slab  and  be  lapped  to  other  transverse  reinforcement  bars,  or  be  continuous  across  the 
whole width of the slab. Transverse reinforcement shall terminate at 125± 25 mm from the 

Series 900 –Rigid Pavements           Page no: 5 of 12 
SRI LANKA OPERATIONS CENTRE

edges of the slab and longitudinal joint. The longitudinal reinforcement shall terminate 300 ± 
50 mm from any transverse joint. 
 
Transverse Joints 
 
Transverse joints shall be contraction, expansion or warping joints constructed at the spacing 
described in the contract. Joins in the surface slab, road base and subbase shall be staggered 
so that they are not coincident vertically and at least 1m apart. 
 
Transverse joints shall be straight within the following tolerances along the intended line of 
the joint, which is the straight line transverse to the longitudinal axis of the carriageway at 
the position agreed by the Engineer, or as described in the contract. 
(i) Deviation of the filler board or bottom crack inducer from the intended line 
of the joint shall be not greater than ± 10mm. 
(ii) The best fit straight line through the joint groove as constructed shall not 
be more than 25 mm from the intended line of the joint. 
(iii) Deviations  of  the  joint  groove  from  the  best  fit  straight  line  of  the  joint 
shall be not greater than 10 mm. 
(iv) When  top  groove  formers  and  bottom  crack  inducers  are  used,  the  joint 
groove  as  constructed  shall  be  located  vertically  above  the  bottom  crack 
inducer within a horizontal tolerance of  ± 25mm   
Transverse joints on each side of a longitudinal joint shall be in line with each other of the 
same type and width. 
 
Contraction Joints 
 
Contraction  joint  shall  consist  of  a  sawn  joint  groove  or  a  wet  formed  joint  groove,  dowel 
bars and a sealing groove. 
 
Expansion Joint 
 
Expansion joint shall consist of a joint filler board, dowel bars and a sealing groove. 
The filler board shall be positioned vertically within the pre‐fabricated joint assemblies along 
the  line  of  the  joint.  The  joint  filler  board  together  with  the  sealing  groove  shall  provide  a 
complete separation of adjacent slabs and any spaces around dowel bars and between the 
sub‐base  and  the  filler  board  shall  be  packed  with  a  suitable  compressible  material  after 
fixing the joint assembly. 
 
Warping Joints 
 
Warping joint shall consist of a sawn joint groove or a wet formed joint groove, dowel bars 
and a sealing groove. 
 
Construction Joints 
 
Construction  joints  made  at  the  end  of  a  working  day  in  unreinforced  concrete  slabs  and 
jointed reinforced concrete slabs shall be expansion joints or contraction joints. In the event 
of  mechanical  break  down  in  concreting  machinery,  or  at  the  onset  of  adverse  weather, 
emergency joints may be formed at not less than 2.5 m from preceding or succeeding joint 
position.  Emergency  joints  in  unreinforced  concrete  slabs  shall  be  either  expansion  or 
contraction joint. Emergency joints in reinforced concrete slabs shall be made by positioning 
a  stop  end  formwork sufficiently rigid to ensure that dowel bars, tie bars or reinforcement 
will  be  held  in  position  in  compliance  with  the  specification,  and  placed  in  such  a  position 
that it permits the longitudinal reinforcement to project through the joint for a distance of at 
least 750mm. 

Series 900 –Rigid Pavements           Page no: 6 of 12 
SRI LANKA OPERATIONS CENTRE

 
Construction joints in continuously reinforced concrete slabs at the end of the day or in an 
emergency shall not be constructed within 1.5 m of any lap in the longitudinal reinforcement 
without  the  approval  of  the  Engineer.  The  stop  end  formwork  shall  be  sufficiently  rigid  to 
ensure that the longitudinal reinforcement and the tie bars which project through the joint 
are held in the correct position. 
 
Longitudinal Joints 
 
Longitudinal  joints  shall  be  wet  formed  or  constructed  in  surface  slabs  between  or  at  the 
centre of traffic lanes within the allowable position in the contract. Joints in the surface slab, 
road base or subbase shall be staggered so that they are not coincident vertically and are at 
least 300 mm apart. The positions of all longitudinal joints in any slab shall be agreed by the 
Engineer  prior  to  construction  of  the  slab.  Longitudinal  joints  shall  be  constructed  in  the 
positions agreed by the Engineer within the following tolerances. 
 
(i) Deviations of the bottom crack inducer from the intended line of the joint, 
parallel to the axis of the road shall be not greater than ± 13mm. 
(ii) The  joint  groove  shall  be  located  vertically  above  the  bottom  crack 
inducers within a horizontal tolerance of ± 25mm. 
(iii) The best fit line along the constructed joint groove, shall be not more than 
25 mm from the intended line of the joint. 
(iv) Deviations of the joint groove from the best fit line of the joint shall be not 
greater than 10mm. 
 
Tie  bars  may  be  replaced  by  continuous  transverse  reinforcement  across  the  joints  in 
continuously reinforced concrete slabs which are constructed in more than one lane width in 
operation, provided that the transverse reinforcement is a minimum of 12 mm dia. bars at 
600mm centres.   
 
Longitudinal Construction Joints  
 
Longitudinal  construction  joints  between  separate  slabs  shall  have  tie  bars  with  a  joint 
groove.  Alternatively,  if  split  forms  are  used,  the  transverse  reinforcement,  if  12  mm 
diameter or more, may be continued across the joint for a minimum of 500 mm or 30 times 
the diameter of the transverse reinforcement bars, whichever is the greater. A joint groove is 
not  required  in  construction  joints  in  continuously  reinforced  concrete  road  bases.  Where 
the  edge  of  the  concrete  slab  is  damaged  it  shall  be  made  good  to  the  satisfaction  of  the 
Engineer before the adjacent slab is constructed. 
 
Dowel Bars 
 
Dowel  bars  shall  be  supported  on  cradles  in  fabricated  joint  assemblies  positioned  prior  to 
construction of the slab. Cradles supporting the dowel bars shall not extend across the line of 
the  joint.  For  contraction  joints  in  slabs  constructed  in  two  layers,  as  an  alternative  to 
prefabricated  assemblies,  dowel  bars  may  be  mechanically  inserted  with  vibration  into  the 
bottom  layer  of  the  plastic  concrete  by  a  method  which  ensures  full  recompaction  of  the 
concrete around the dowel bars. 
 
Dowel bars shall be positioned at the mid – depth from the surface level of the slab, ± 20mm. 
They shall be aligned parallel to the finished surface of the slab. 
 
Dowel bars shall be covered by a thin plastic sheath for at least two thirds of the length from 
one  end  for  dowel  bars  in  contraction  joints  or  half  the  length  plus  50mm  for  expansion 

Series 900 –Rigid Pavements           Page no: 7 of 12 
SRI LANKA OPERATIONS CENTRE

joints. The sheath shall be tough, durable and of an average thickness not greater than 1.25 
mm.  
 
For expansion joints, a closely fitting cap 100 mm long consisting water proofed card board 
or an approved synthetic material shall be placed over sheathed end of each dowel bar. An 
expansion  space  equal  in  length  to  the  thickness  of  the  joint  filler  board  shall  b  formed 
between the end of the cap and the end of the dowel bar. 
 
Tie Bars 
 
Tie  bars  and  reinforcement  projecting  across  a  longitudinal  joint  shall  be  protected  from 
corrosion for 75 mm each side of the joint by a suitable protective coating. In the case where 
the  bars  are  cranked  for  construction  joints  and  later  straightened  any  damage  to  the 
protection shall be made good before adjacent concrete is laid. 
 
Joint Grooves 
 
Joint grooves shall be formed or sawn in the surface slabs to promote cracks at the required 
positions.  Transverse  joint  grooves  shall  either  be  sawn  in  the  hardened  concrete  or  wet 
formed  in  plastic  concrete.  Longitudinal  joint  grooves  shall  be  wet  –  formed  in  plastic 
concrete. 
 
Sawn  Transverse  Joint  Grooves  –  Sawing  shall  be  undertaken  as  soon  as  possible  after  the 
concrete has hardened sufficiently to enable a sharp edged groove to be produced without 
disrupting  the  concrete  and  before  random  cracks  develop  in  the  slab.  The  groves  shall  be 
between ¼ and 1/3 of the specified width not less than 3mm. 
 
Wet‐formed Transverse Joint Groves ‐ Grooves shall be formed in the plastic concrete, prior 
to the final regulation and finishing of the surface, either by vibrating a metal blade into the 
concrete to the required depth and inserting a groove former into the groove, or the groove 
former may be vibrated vertically into the plastic concrete. The disturbed concrete shall be 
fully recompacted around the former on each side and the surface regulated. However if the 
groove  is  wider  than  15  mm,  surface  regularity  shall  be  achieved  by  removing  disturbed 
concrete. The groove former shall then remain in the correct position, alignment and depth 
below  the  surface,  until  temporary  or  permanent  sealing  is carried out. The groove former 
shall be made of an approved rigid material of a width not greater than the required width of 
the sealing groove. It shall be smooth sided with rounded protrusions no greater than 3mm. 
Any  removable  part  of  the  groove  former  may  be  tapered  with  a  maximum  difference  in 
width of 2mm in 20 mm depth. 
 
Wet‐formed Longitudinal Joint Groves ‐ Groove forming sealing strips for longitudinal joints 
shall be of firm compressible strips of ethylene vinyl acetate foam of minimum density of 90 
kg/m3, or synthetic rubber, or similar material and shall be approved by the Engineer. They 
shall have a minimum thickness of 5 mm and shall be sufficiently rigid to remain vertical and 
straight  in  the  concrete  without  curving  or  stretching.    They  shall  be  inserted  or  fixed 
continuously  along  the  joint.  The  depth  of  groove  forming  sealing  strips  for  construction 
joints shall be not less than 25 mm. 
 
Joint Filler Board 
 
Joint filler board for expansion joints and manhole and gully slab joints shall be of thickness 
25 mm or the thickness described in the contract, within a tolerance of ± 1.5 mm, of a firm 
compressible  material  or  a  bonded  combination  of  compressible  and  rigid  materials  of 
sufficient rigidity to resist deformation during the passage of the concrete paving plant. The 
depth of the joint filler board for manhole and gully slabs shall be the full depth of the sealing 

Series 900 –Rigid Pavements           Page no: 8 of 12 
SRI LANKA OPERATIONS CENTRE

groove. The depth of the filler board for expansion joint shall be as described in the contract. 
Holes  for  dowel  bars  shall  be  accurately  bored  or  punched  out  to  form  a  sliding  fit  for  the 
sheathed dowel bar. 
 
Preparation and Sealing of Joint Grooves 
 
Joints shall not be sealed within 14 days after construction. 
The part of the grove former used to form the sealing groove or any temporary seal shall be 
removed  cleanly  without  damaging  the  joint  arises  to  a  minimum  depth  of  25  mm,  where 
compression seals are used or otherwise to the depth shown in contract for applied sealants. 
The  sealing  grooves  shall  be  cleaned  out  immediately  after  sawing.  The  sides  of  the  joint 
sealing  groove  shall  be  scoured  by  dry  abrasive  blasting.  Alternatively,  when  compression 
seals  are  used,  the  sides  of  the  groove  may  be  ground  or  wire  brushed.  For  hot  and  cold 
applied sealants, compressible caulking material, debonding strip or tape or cord compatible 
with the sealant, of suitable size to fill the width of the sealing groove, shall be firmly packed 
or stuck in the bottom of the sealing groove. All grooves shall be cleaned of any dirt or loose 
material by air blasting with filtered, oil – free filtered air. The groove shall be clean and dry 
at the time of priming and sealing. 
 
When hot or cold applied sealants are used, an appropriate primer shall be used and it shall 
be  applied  in  accordance  with  the  manufacturer’s  recommendations.  The  sealant  shall  be 
applied within the minimum and maximum drying times of the primer recommended by the 
manufacturer. 
 
Hot  applied  sealants  shall  be  heated  in  and  applied  from  thermostatically  controlled, 
indirectly heated dispenser with a recirculating pump. The sealant shall not be heated to a 
temperature  higher  than  the  safe  heating  temperature  nor  for  a  period  longer  than  safe 
heating period, as specified by the manufacturer. The dispenser shall be cleaned out at the 
end of the each day and reheated materials shall not be used. 
 
The  components  of  cold  applied  sealants  shall  be  thoroughly  mixed  in  the  correct 
proportions in accordance with the manufacturer’s instructions using an automatic metering 
and  mixing  dispenser  approved  by  the  Engineer  or,  for  hand  application,  using  a  power 
operated paddle mixer for sufficient time to produce a homogeneous mix without entrapped 
air. As soon as possible after mixing and within the work life of the sealant, the material shall 
be dispensed in to the joint or applied using a caulking gun, to the correct level below the 
concrete surface. The tack‐free time shall be achieved within 3 hours for machine dispensed 
material, or within 12 hours for hand applied sealants. 
 
When  performed  compression  seals  are  used,  the  width  of  the  seal  shall  be  selected  in 
relation  to  the  width  of  the  sealing  groove,  the  bay    lengths  and  manufacturer’s 
recommendations  so  that  the  estimated  maximum  width  of  the  joint  opening  shall  be  not 
more than 70% of the original width of the seal. Compression seals shall be inserted into the 
grooves without prior extension or rotation and where recommended by the manufacturer, 
with a lubricant adhesive which is compatible with the seal and the concrete. The adhesive 
shall be applied to both sides of the sealing groove or the seal or to both. The seal shall be 
positioned with its axis perpendicular to the concrete surface. Excess adhesive on the top of 
the seal shall be removed. 
 
Delivery, Storage and Batching of Concreting Materials 
Cement  shall  be  kept  dry  and  used  in  the  order  in  which  it  is  delivered  to  the  site.  Bulk 
cement  shall  be  stored  in  purpose  made  silos.    Bagged  cement  shall  be  stored  under  dry 
weather proof covers on raised floors.  Each consignment shall be kept separate and distinct 
and used in the order in which it is delivered to the Site.  No cement shall be stored on Site 
for longer than 3 months. 

Series 900 –Rigid Pavements           Page no: 9 of 12 
SRI LANKA OPERATIONS CENTRE

 
 Aggregate  shall  be  delivered  to  and  stored  on  the  site  in  separate  nominal  single  sizes  of 
coarse aggregate and fine aggregate. .  Fine aggregate shall have been deposited at the site 
of mixing for at least 8 hours before use. If the contractor proposes to blend aggregate from 
two separate sources, he shall obtain the Engineer’s prior approval for the blending process 
and  for  the  arrangements  for  inspection  during  the  course  of  the  work.  The  bases  of 
stockpiles shall be suitably surfaced to prevent contamination of the aggregate.  Aggregates 
brought to the site shall be kept free from contact with deleterious matter. Aggregates shall 
be measured by mass and provision shall be made for batching each nominal size or blend of 
aggregate separately, to the tolerances specified in BS 5328. 
 
Proportioning the Mix 
The constituents of the mix shall be batched by weight to the accuracy required in BS 5328.  
Allowance  for  any  variation  shall  be  made  so  that  the  specified  maximum  water  –  cement 
ratio is not exceeded nor the cement content reduced below the minimum specified. 
 
Calibration of Measuring Equipment 
 
A Certificate of Calibration verifying the accuracy of the equipment used for measuring the 
quantities of the constituents of the concrete mix shall be provided by the Contractor when 
required by the Engineer and each time the batching and mixing plant is commissioned for 
use. 
 
 
  Mixing concrete 
   
Unless otherwise permitted by the Engineer, concrete shall be mixed on Site in a stationary 
batch type mixer in compliance with BS 5328. The drums or blades of mixer shall be operated 
at  the  speed  used  for  testing,  in  accordance  with  BS  3963  for  mix  proportions  required, 
within a tolerance of ± 1 revolution per minute. and the blades shall be replaced when it is 
no  longer  possible  to  maintain  the  tolerances  by  adjustment  The  rated  output  of  the 
batching  and  mixing  plant  shall  exceed  by  at  least  a  third  the  amount  of  concrete  that  is 
required  at  a  constant  rate  to  achieve  planned  rate  of  progress.  All  mixing  drums  or  pans, 
which  have  been  out  of  use  for  more  than 30 minutes, shall be thoroughly cleaned before 
any fresh concrete is mixed in them. 
 
The air‐entraining agent shall be added at the mixer, by an apparatus capable of dispensing 
the  correct  dose  within  the  limits  given  in  BS  5328,  into  the  mixing  water,  so  as  to  ensure 
uniform distribution of the agent throughout the batch during mixing. 
 
Following the addition of water, the concrete shall be mixed for at least the minimum time 
recommended by the manufacturer of the mixing plant prior to discharge from the mixer.  
 
Transporting Concrete 
 
 The freshly mixed concrete shall be covered during transit and while awaiting discharge to 
prevent wetting by rain or evaporation of moisture.  It shall be transported and delivered so 
that segregation or loss of the constituent materials is reduced to the minimum. 
 
Concrete spreading & compaction 
 
The  concrete  shall  be  spread  uniformly  without  segregation  or  varying  degree  of  pre‐
compaction, by conveyor, chute or by other means approved by the Engineer. The concrete 
shall be struck off by a screed so that the average and differential surcharge is sufficient to 
ensure that after compaction the surface is to be the required levels. 

Series 900 –Rigid Pavements           Page no: 10 of 12 
SRI LANKA OPERATIONS CENTRE

 
The  concrete  shall  be  compacted  by  vibrating  finishing  beams.  In  addition,  internal  porker 
vibration shall be used for slabs thicker than 200mm and may be used for lesser thicknesses. 
When used, the porkers shall be at points not more than 500mm apart over the whole area 
of the slab, and adjacent to the side forms or the edge of the previously constructed slab. 
 
After  the  final  regulation  of  the  surface  of  the  slab  and  before  application  of  the  curing 
membrane the surface of the concrete slabs to be used as running surfaces shall be brush‐
textured in a direction at right angles to the longitudinal axis of the carriageway. The brushed 
surface  texture  shall  be  applied  evenly  across  the  slab  in  one  direction  by  the  use  of 
approved wire brush not less than 450mm wide. 
 
Curing 
Immediately after the application of the surface texture described the surface and sides of 
the slab shall be cured by the application of an approved curing compound. Alternatively, 
small  areas  may  be  cured  by  the  use  of  polythene  sheeting  in  accordance  with  the 
instructions of the Engineer. Curing shall be carried out for a minimum period of 7 days 

Trial Length 
At  least  14  days  prior  to  the  construction  of  the  trial  length  of  concrete  pavement  the 
Contractor shall submit for the Engineer’s approval a detailed description of the proposed 
materials,  plant,  equipment  &  construction  methods.  No  trials  of  new  materials,  plant, 
equipment  or  construction  methods;  nor  any  development  of  them  shall  be  permitted 
either during the construction of the trial length or in any subsequent paving work, unless 
they form part of further approved trials. The Contractor shall demonstrate the materials, 
plant,  equipment  and  methods  of  construction  that  are  proposed  for  concrete  paving,  by 
first constructing 100m long for mechanised construction and at least 20m for hand guided 
methods. At least two transverse joints inclusive of an expansion joint and one longitudinal 
joint shall be constructed and assessed in the trial length. The trial length shall comply with 
the specification in all respects. 

Construction by Machine 

The  concrete  pavement  shall  be  constructed  by  either  fixed  form  or  by  slip  form  paving 
plant, in a continuous process. The slab may be constructed in either one or two layers. In 
two layer construction the thickness of the top layer shall not be less than 50mm or twice 
the maximum size of the coarse aggregate, which ever is the greater, and shall be at least 
15mm thicker than the depth of the groove former, if used. 

901.4  Measurement and Payment 

Delete this sub section and substitute the following :‐ 

  Measurement 

Concrete  pavements  shall  be  measured  as  finished  work  in  position  in  square  metres  of 
surface area. There shall not be separate measurement for the reinforcement nor formwork 
and deemed to be included in the rate for the concrete. Joints shall be measured separately 
in linear metres as specified. 

  Payment 
Payment shall be based on the contract unit rate for each item of completed and accepted 
work,  which  shall  include  full  compensation  for  materials  inclusive  of  reinforcement  & 
formwork, labour, equipment, transport, hire charges and incidentals necessary to complete 
the work. 

Series 900 –Rigid Pavements           Page no: 11 of 12 
SRI LANKA OPERATIONS CENTRE

 
The Pay items and Pay Units shall be:‐ 
 
Pay Item  Pay Unit 
 
 
901 (1) Concrete Pavement  Sqm 
 
901 (2) Expansion joint as detailed in drawings  m 
 
901 (3) Contraction joint as detailed in drawings  m 
 
 
 
  

Series 900 –Rigid Pavements           Page no: 12 of 12 
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

SERIES 1000 - BRIDGES AND OTHER STRUCTURES

CONTENTS

1001. CONCRETE FOR STRUCTURES....................................................................... 1002


1001.1. Description ................................................................................................ 1002
1001.2. Materials.................................................................................................... 1002
1001.3. Classification & uses of concrete .............................................................. 1002
1001.4. Proportioning of Materials ......................................................................... 1002
1001.5. Grade of Concrete..................................................................................... 1004
1001.6. Workability of Concrete ............................................................................. 1005
1001.7. Testing of Concrete for Acceptance.......................................................... 1006
1001.8. Mixing of Concrete .................................................................................... 1009
1001.9. Placing and Compaction of Concrete........................................................ 1011
1001.10. Underwater Concreting ............................................................................. 1016
1001.11. Curing of Concreting ................................................................................. 1016
1001.13 Measurement and payment ...................................................................... 1017
1002. STEEL REINFORCEMENT FOR CONCRETE STRUCTURES .......................... 1018
1002.1. Description ................................................................................................ 1018
1002.2. Materials.................................................................................................... 1018
1002.3. Construction Requirements....................................................................... 1019
1002.4. Measurement & Payment.......................................................................... 1020
1003. PRESTRESSING FOR STRUCTURES............................................................... 1021
1003.1. DESCRIPTION.......................................................................................... 1021
1003.2. MATERIALS.............................................................................................. 1022
1003.3. WORKMANSHIP....................................................................................... 1028
1003.4. TENSIONING............................................................................................ 1030
1003.5. JOINTS IN CONSTRUCTION WITH PRE-CAST UNITS.......................... 1032
1003.6. GROUTING............................................................................................... 1032
1003.7. TRANSPORTATION, STORAGE AND ERECTION OF UNITS:............... 1034
1003.8. QUALITY CONTROL ................................................................................ 1034
1003.9. SAFETY IN CONSTRUCTION:................................................................. 1037
1003.10. MEASUREMENT: ..................................................................................... 1037
1003.11. PAYMENT:................................................................................................ 1037
1004 PILE FOUNDATIONS FOR STRUCTURES........................................................ 1038
1004.1 a) Description ............................................................................................ 1038
1004.1 .1 Coffer Dam/ Artificial Island.................................................................. 1038
1004.2 Materials.................................................................................................... 1042
1004.3 Manufacturing and protective requirements for piles ................................ 1044
1004.4 Construction requirements of driven piles................................................. 1044
1004.5 Construction requirements of cast insitu piles (bored piles)...................... 1044
1005 WELL FOUNDATIONS FOR STRUCTURES ..................................................... 1071
1005.1 Description ............................................................................................... 1071
1006. RANDOM RUBBLE MASONRY.......................................................................... 1071

1007. BRICK WORK AND BLOCK WORK FOR STRUCTURES ................................ 1071

1008. FORMWORK FOR STRUCTURES ..................................................................... 1071

Page 1000
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

1009. BRIDGE EXPANSION JOINTS ........................................................................... 1071

1010 BRIDGE BEARINGS .......................................................................................... 1073

1011 WEARING COURSE ........................................................................................... 1077

Page 1001
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

SERIES 1000 - BRIDGES AND OTHER STRUCTURES

1001. CONCRETE FOR STRUCTURES

1001.1.Description
No change.

1001.2.Materials
Add to the end of the paragraph the following:-

Supply of materials:
• UNOPS shall supply of basic construction materials such as Cement, and
necessary formwork materials except propping/supporting materials binding wires,
nails to the contractor at site. All necessary formwork materials shall be black
laminated plywood.
• Contractor shall transport the all materials from the stock yard to the batching
plant yard (for production of concrete by their own batching plant,) and finally
pouring site to pour concrete including all other necessary local transports. Supply
of all other materials related to the mixing of concrete such as Metal, Sand,
Admixture/Reterders, fresh water, ice if required to control the concrete
temperature and required tools and equipments shall be provided by the
Contractor.
• Contractor shall be responsible for preparing, fitting, fixing and installation of the
formworks. Contractor shall supply the all necessary tools, equipments and
materials for the fitting/fixing of the form works/ scaffoldings.

The contractor shall be responsible to transport the concrete from the batching plant to
the casting location by their own transit mixer/truck. The pouring of concrete shall be
commenced by Contractor including all necessary labours and equipments, tools etc,
complete. Before start to produce concrete, contractor must be ensuring that all the
equipments are in working condition e.g. transit mixer/ pump car etc, & all other
necessary equipments. An official material requisition form shall be designed and singed
& submit to the project office approval stated that all the equipments are working
condition.

Contractor shall be responsible for the payment of concrete volume If any wastage of
concrete due to breakage of the necessary equipments/ plants and any negligence of the
contractor during pouring of concrete. A stand by equipments must be available/ arranged
at site during concrete to avoid this payment.

1001.3.Classification & uses of concrete

Add to the end of the paragraph the following:-

Unless otherwise described in the Contract, concrete shall be a Class A designed mix.

1001.4.Proportioning of Materials

Delete subsections (d), and substitute with the following:-

a) When designing the concrete mix, the Contractor shall consider the following
conditions:

Page 1002
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

1) Strength
The class of the concrete is to be as shown on the Drawings. The class is the specified
characteristic cylinder strength at 28 days. Concrete mixes shall be designed to comply
with Specifications Sub Section 1001.7.

2) Water/Cement Ratio

The ratio of free water to cement shall be as indicated for the respective class in Table
1001-5-A. More over for concrete in barriers, edge beams and bridge decks directly
exposed to traffic or concrete in pile caps or abutments in contact with the ground, the
water cement ratio shall not exceed 0.45, unless approved by the Engineer.

3) Cement Content

The minimum cement content shall be as indicated for the respective class in Table
1001-5-A. The maximum cement content shall not exceed 500 kg/m3 unless otherwise
agreed by the Engineer.

4) Minimum Filler Content


Filler content (fine aggregate less than 0.25 mm and cement) shall not be less than as
follows (except for mass concrete).

Maximum coarse 20 40
aggregate size (mm)
Minimum filler 435 350
content (kg/m3 of
concrete)

5) Coarse Aggregate

The maximum size of coarse aggregate will generally be stated on the Drawings; either
40 mm or 20 mm, in accordance with Sub Section 1701.2 of ”ICTAD, Standard
Specifications for construction and maintenance of Roads and Bridges”. Grading and
quality is to comply with the requirements of Table 1701-1 of Sub Section 1701.2 of
”ICTAD Standard Specifications for construction and maintenance of Roads and Bridges”.

6) Fine Aggregate

The grading and quality is to comply with the requirements of Sub Section 1701.2 of
”ICTAD Standard Specifications for construction and maintenance of Roads and Bridges”.

7) Workability

The concrete shall be of suitable workability to comply with Specifications Sub Section
1001.6.

b) Trial Mixes

After the Contractor has received approval for the cement and aggregate to be used, he
shall prepare trial mixes with concrete of designed proportions to prove and establish
workability, strength, water cement/ratio, surface criteria etc. Methods of transporting
fresh concrete and the compaction equipment shall be considered. The trial mixes shall
be made and compacted in the presence of the Engineer, using the same type of plant
and equipment as will be used for the Works.

Page 1003
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

From each trial mix, cylinders or cubes shall be made and tested in accordance with
Specifications Sub Section 1001.7.

From the same mix as that from which the test specimens are made, the workability of the
concrete shall be determined by the slump test in accordance with Specifications Sub
Section 1001.6. The remainder of the mix shall be cast in a wooden mould and
compacted. After 24 hours the sides of the mould shall be struck and the surface
examined in order to satisfy the Engineer that an acceptable surface can be obtained with
the mix.

The trial mix proportions should be approved if the required strength is obtained from
tests carried out in accordance with Specifications Sub Section 1001.7., and the
consistency and surface is to the satisfaction of the Engineer.

When a mix has been approved, no variations shall be made in the mix proportions, or in
the type, size, grading zone or source, of any of the constituents without the consent of
the Engineer, who may require further trial mixes to be made before any such variations
are approved.

Until the results of trial mixes for a particular class have been approved by the Engineer,
no concrete of the relevant class shall be placed in the Works. When the Contractor
intends to purchase factory-made precast concrete units, trial mixes may be dispensed
with provided that evidence is given to satisfy the Engineer that the factory regularly
produces concrete which complies with the Specifications. The evidence shall include
details of mix proportions, water/cement ratios, slump tests and strengths obtained at 28
days.
The contractor shall submit for the Engineer’s approval, prior to the supply of any
designed mix, the following information:-

(a) Appropriate existing data as evidence of satisfactory previous performance for target
mean strength, current margin, and workability and water/cement ratio or full details of
tests on trial mixes.

(b) Quantities of each material per cubic metre, of fully compacted concrete.

The current margin for a concrete mix shall be 1.64 times the standard deviation of cube
tests on at least 40 separate batches of concrete of similar proportions and produced over
a period not exceeding 6 months, by the same plant under similar supervision, but not
less than one third of the characteristic strength up to Grade 15 or 7.5 N/Sqm for concrete
of grade 20 or above.

1001.5.Grade of Concrete

Add the following:-

Concrete for use in the various elements of structures shall be as shown in Table 1001-5-
A and as specified on the Drawings.

TABLE 1001-5-A

The compressive strength of concrete (Cylinder Strength) have been assumed as follows:

Page 1004
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Pre-stressed concrete: fc’ = 50 N/mm² (Grade 60, Cube Strength)


Curb, Deck slab, RCC Girder fc’ = 30 N/mm² (Grade 37, Cube Strength)
Parapets footpath slab, Approach slab fc’ = 25 N/mm² (Grade 31, Cube Strength)
Concrete for Bored cast insitu pile fc’ = 30 N/mm² (Grade 37, Cube Strength)
Pile Cap: fc’ = 30 N/mm² (Grade 37, Cube Strength)
Concrete for piers, abutments and foundation: fc’ = 30 N/mm² (Grade 37, Cube Strength)
Cement Concrete Block: fc’ = 20 N/mm2 (Grade 25, Cube Strength)
Mass Cement Concrete: fc’ = 15 N/mm2 (Grade 19, Cube Strength)

Concrete Concrete Characteristic Maximum Maximum Size Minimum


Class Strength (N/mm2 @ 28 free of Coarse Cement Content
days) water/cemen Aggregate (Kg/m3)
Cylinder Cube (150 mm) t ratio (mm)
(150 x 300 mm)
40 210
10 10 13 0.60
20 240
40 250
15 15 19 0.55
20 275
40 300
20 20 25 0.50
20 325
40 325
25 25 31 0.50
20 350
40 350
30 30 37 0.45
20 375
40 375
35 35 44 0.45
20 400
40 400
40 40 50 0.42
20 425
40 425
45 45 56 0.42
20 450
40 450
50 50 60 0.42
20 475

Where, fc’ is the compressive strength at 28 days.

Note: Concrete strength quoted in Table 1001-5-A is the 28 days compressive cylinder
strength as well as cube strength.

1001.6.Workability of Concrete

Delete subsection, substitute with the following :-

The workability of the fresh concrete shall be such that the concrete is suitable for the
conditions of handling and placing so that after compaction it surrounds all reinforcement,
tendons and ducts and completely fills the formwork. Workability shall be measured for
each batch or at such times as directed by the Engineer using one of the following tests in
accordance with BS 1881 and shall be within the following limits of required values.

Slump ± 25 mm or ± one third of the required value, which ever is


the greater.
Compacting factor ± 0.03 where the required value is 0.90 or more.
± 0.04 where the required value is between 0.80 and 0.90
± 0.05 where the required value 0.80 or less.
Vebe ± 3 seconds or ± one fifth of the required value, which ever
is the greater.

Typical values of workability are tabulated below.

Page 1005
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Description of Compacting Factor Slump


workability
Very low 0.78 0 - 25
Low 0.85 25 - 50
Medium 0.92 50 - 100
High 0.95 100 - 175

Unless otherwise specified in the contract, very low workability shall be confined to high
strength vibrated concrete, carried out under controlled conditions and for RCC slabs and
beams, foundations, columns, etc. low workability shall be used.

1001.7.Testing of Concrete for Acceptance

Delete subsection, substitute with the following:-

i) General

The Contractor shall assume the full responsibility for the quality of the concrete
conforming to these Specifications and this responsibility shall not be relieved by the
testing carried out and approved by the Engineer.

The Contractor shall thus at his own discretion establish additional testing procedures as
necessary.

ii) Control of Concrete Production

1) Materials

Materials used shall be tested in accordance with Sub Section 1001.2.

2) Plant and Equipment

Batching plants will be tested by the Contractor in a manor approved by the Engineer
before any major concrete casting and at any other time if requested by the Engineer.

3) Fresh Concrete

The frequency of slump tests shall be as directed by the Engineer, with at least one test
per 25 m³ of concrete.

iii) Control of Strength

1) Sampling and Testing

Cube tests may be substituted for cylinder tests if acceptable to both the Engineer and
the Contractor. If cube tests are adopted, the concrete characteristic strengths shall be as
shown in Table 1001-5-A. All other requirements of the Specifications shall equally apply
to cubes or cylinders.
The Contractor shall take samples of the concrete for testing. The number, frequency and
location shall be decided by the Engineer. A minimum of 3 concrete cubes/cylinders
should be taken for each day’s casting, or for every 15 m³ of concrete cast in large pours.
The slump of concrete samples shall be measured in accordance with Specifications Sub
Section 1001.6.

Page 1006
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

2) Strength Requirement
The results of the testing shall conform to the strength requirements according to British
standard BS-5400: Part 7, as given below, or to any mathematically correct statistical test
for each casting section.

iv) Characteristic strength

The characteristic strength of concrete is the 28 days strength below which not more than
5% of the test results may be expected to fall.

v) Target Mean Strength

The concrete mix shall be designed to have a mean strength greater than the required
characteristic strength by at least the current margin.

The current margin for each particular type of concrete mix shall be determined; it may be
taken as having the smaller of the values given by (1) or (2) below.

1) 1.64 times the standard deviation of tests on at least 100 separate batches of
concrete of nominally similar proportions of similar materials and produced over a
period not exceeding 12 months by the same plant under similar supervision, but
not less than 2.5 N/mm2 for concrete of grade 10 or 3.75 N/mm2 for concrete of
grade 15 or above.

2) 1.64 times the standard deviation of tests on at least 40 separate batches of


concrete of nominally similar proportions of similar materials and produced over a
period exceeding 5 days but not exceeding 6 months by the same plant under
similar supervision, but not less than 5 N/mm2 for concrete of grade 10 or 7.5
N/mm2 for concrete of grade 15 or above.

Where there are no or insufficient data to satisfy (1) or (2) above, the current margin for
the initial mix design should be taken as shown in table 1001-7-A for corresponding
strength classes. This margin should be used as the current margin only until sufficient
data are available to satisfy (1) or (2) above. However, when the required characteristic
strength approaches the maximum permissible strength of concrete made with a
particular aggregate. A smaller margin may be permitted by the Engineer for initial mix
design.

Table 1001-7-a

Specified characteristic Target Mean Current


Strength, MPa Strength, MPa Margin, MPa

35 50 15

Page 1007
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

30 45 15
25 40 15
20 30 10
15 25 10
10 20 10

vi) Testing Plan


Each cube shall be made from a single sample taken from randomly selected batches of
concrete. The samples shall be taken at the point of discharge from the mixer or, in the
case of ready-mixed concrete, at the point of discharge from the delivery vehicle.

Compliance with the specified characteristic strength may be assumed if:

1) The average strength determined from any group of three consecutive test cubes
exceeds the specified characteristic strength by not less than 0.5 times the current
margin, and

2) Each individual test result is greater than 85% of the specified characteristic strength.

If only one cube result fails to meet the second requirement (2) then that result may be
considered to represent only the particular batch of concrete from which that cube was
taken provided the average strength of the group satisfies the first requirement.

If more than one cube in a group fails to meet the second requirement or if the average
strength of any group of three consecutive test cubes fails to meet the first requirement
then all the concrete in all the batches represented by all such cubes shall be deemed not
to comply with the strength requirements. For the purposes of this sub-section, the
batches of concrete represented by a group of three consecutive test cubes shall include
the batches from which samples were taken to make the first and the last cubes in the
group of three, together with all the intervening batches.

vii) Action to be taken in the event of Non-Compliance with the Testing Plan.

When the average strength of three consecutive test cubes fails to meet the first
requirement in (vi), above, the mix proportions of subsequent batches of concrete should
be modified to increase the strength.

The action to be taken in respect of the concrete which is represented by the test-cubes
which fail to meet either of the requirements shall be determined by the Engineer. This
may range from qualified acceptance in less severe cases, to rejection and removal in the
most severe cases.
The Engineer may also require the Contractor at his own expenses to prove statistically
the strength, by boring out cores and testing them according to a programme approved by
the Engineer. The age of the concrete and degree of hardening at the time of the new
testing shall be considered. The equivalent cylinder/cube strength shall comply the
minimum characteristic strength or as decided by the Engineer.

viii) Control of Hardening

If the Contractor wants to remove forms and scaffolding earlier than specified herein,
extra test specimens shall be cast by the Contractor in accordance with the instruction of

Page 1008
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

the Engineer. These specimens shall be tested the day before removal of the form. On
the basis of the test results the Engineer shall take the final decision on the time for the
removal of forms.

For prestressed concrete, extra test specimens shall be cast by the Contractor in
accordance with the instructions of the Engineer, to determine the time for tensioning the
tendons. On the basis of the test results, the Engineer shall decide upon the time for
prestressing the concrete.

1001.8.Mixing of Concrete

Delete subsections (d) and substitute with the following :-

d) Central Plant Mixers

These mixers shall be of approved drum type capable of combining the aggregate,
cement and water into a thoroughly mixed and uniform mass within the specified mixing
period and of discharging the mixture without segregation. Central plant mixers shall be
equipped with an acceptable timing device that will not permit the batch to be discharged
until the specified mixing time has elapsed. The water system for a central mixer shall be
either a calibrated measuring tank or a meter and shall not necessarily be an integral part
of the mixer.

The mixers shall be cleaned at suitable intervals. They shall be examined daily for
changes in interior condition. The pick up and throw-over blades in the drum shall be
replaced when they have lost 10% of their depth.
In addition to the requirements for mixers at local sites detailed above, central plant
mixers which have a capacity of between 2 and 5 cubic metres, or greater than 5 cubic
metres, should have a minimum mixing time of 90 and 120 seconds respectively,
provided tests indicate that the concrete produced is equivalent in strength and uniformity
to that attained as stated in the preceding paragraphs.
Mixed concrete shall be transported from the central mixing plant to the site of work in
agitator trucks or, upon written permission of the Engineer, in non-agitator trucks.
Delivery of concrete shall be so regulated that placing is at a continuous rate unless
delayed by the placing operations. The intervals between delivery of batches shall not be
so great as to allow the concrete in place to harden partially, and in no case shall such an
interval exceed 30 minutes.

Add additional section as follows:

f) Agitator Trucks
Unless otherwise permitted in writing by the Engineer, agitator trucks shall have
watertight revolving drums suitably mounted and shall be capable of transporting and
discharging the concrete without segregation. The agitating speed of the drum shall not
be less than two or more than six revolutions per minute. The volume of mixed concrete
permitted in the drum shall not exceed the manufacturer’s rating nor exceed 80% the
gross volume of the drum.
Upon approval by the Engineer, open-top, revolving-blade truck mixers may be used in
lieu of agitating trucks for transportation of central plant mixed concrete.

Page 1009
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Gross volume of agitator bodies expressed in cubic feet or cubic metres shall be supplied
by the mixer manufacturer. The interval between introduction of water into the mixer drum
and final discharge of the concrete from the agitator shall not exceed 45 minutes. During
this interval the mix shall be agitated continuously.

g) Non-Agitator Trucks

Bodies of non-agitating equipment shall be smooth, water-tight metal containers equipped


with gates that will permit control of the discharge of the concrete. Covers shall be
provided when needed for protection against the weather. The non-agitating equipment
shall permit delivery of the concrete to the site of the work in a thoroughly mixed and
uniform mass with a satisfactory degree of discharge. Uniformity shall be satisfactory if
samples from the one-quarter and three quarter points of the load do not differ by more
than 30 mm in slump. Discharge of concrete shall be completed within 30 minutes after
the introduction of the mixing water to the cement and aggregate.

h) Truck or Transit Mixers


These shall be equipped with electrically actuated counters by which the number of
revolutions of the drum or blades may readily be verified and the counters shall be
actuated at the commencement of mixing operations at designated mixing speeds. The
mixer when loaded shall not be filled to more than 60% of the drum gross volume. The
mixer shall be capable of combining the ingredients of the concrete into a thoroughly
mixed and uniform mass and of discharging the concrete with a satisfactory degree of
uniformity. Except when intended for use exclusively as agitators, truck mixers shall be
provided with a water measuring device to measure accurately the quantity of water for
each batch. The delivered amount of water shall be within plus or minus 1% of the
indicated amount.

Truck mixers may be used for complete mixing at the batch plant and as truck agitators
for delivery of concrete to job sites, or they may be used for complete mixing of the
concrete at the job site. They shall either be a closed watertight revolving drum or an
open top revolving blade or paddle type.

The amount of mixing shall be designated in number of revolutions of the mixer drum.
When a truck mixer is used for complete mixing, each batch of concrete shall be mixed
for between 70 and 100 revolutions of the drum or blades at the rate of rotation
designated by the manufacturer of the equipment as the “mixing speed”. Such
designation shall appear on a metal plate attached to the mixer. If the batch is at least 0.5
cubic metres less than guaranteed capacity, the number of revolutions at mixing speed
may be reduced to not less than 50. Mixing in excess of 100 revolutions shall be at the
agitating speed. All materials, including the mixing water, shall be in the mixer drum
before actuating the revolution counter which will indicate the number of revolutions of the
drum or blades.

When wash water (flush water) is used as a portion of the mixing water for the
succeeding batch, it shall be accurately measured and taken into account in determining
the amount of additional mixing water required. When wash water is carried on the truck
mixer, it shall be carried in a compartment separate from the one used for carrying or
measuring the mixing water. The Engineer will specify the amount of wash or flush water,
when permitted any may specify a “dry” drum if wash water is used without measurement
or without supervision.

When a truck is used for complete mixing at the batch plant, mixing operations shall begin
within 30 minutes after the cement has been added to the aggregate. After mixing, the

Page 1010
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

truck mixer shall be used as an agitator, when transporting concrete, at the speed
designated by the manufacturer of the equipment as agitating speed. Concrete discharge
shall be completed within 45 minutes after the addition of the cement to the aggregates.
Each batch of concrete delivered at the job site shall be accompanied by a time slip
issued at the batching plant, bearing the time of departure there from. When the truck
mixer is used for the complete mixing of the concrete at the job site, the mixing operation
shall begin within 30 minutes after the cement has been added to the aggregates.

The rate of discharge of the plastic concrete from the mixer drum shall be controlled by
the speed of rotation of the drum in the discharge direction with the discharge gate fully
open.

1001.9. Placing and Compaction of Concrete

Delete subsection, substitute with the following:-

The temperature of concrete at the time of placing shall not exceed 35oC. In preparation
for the placing of concrete all sawdust, chips and other construction debris and
extraneous matter shall be removed from the interior of forms. Struts, stays and braces,
serving temporarily to hold the forms in correct shape and alignment, pending the placing
of concrete at their locations, shall be removed when the concrete placing has reached an
elevation rendering their service unnecessary. These temporary members shall be
entirely removed from the forms and not buried in the concrete.

Concrete must reach its final position in the forms within 20 minutes of the completion of
mixing, or as directed by the Engineer.

Concrete shall be placed so as to avoid segregation (from lower gradient to upper


gradient) of the materials and the displacement of the reinforcement. The use of long
troughs, chutes and pipes for conveying concrete from the mixer to the forms shall be
permitted only on written authorisation of the Engineer. In case an inferior quality of
concrete is produced by the use of such conveyors, the Engineer may order
discontinuance of their use and the institution of a satisfactory method of placing.

Open troughs and chutes shall be of metal or metal lined. Where long steep slopes are
required, the chutes shall be equipped with baffles or be in short lengths that reverse the
direction of movement.

All chutes, troughs and pipes shall be kept clean and free from coatings of hardened
concrete by thoroughly flushing with water after each run. Water used for flushing shall be
discharged clear of the structure.

When placing operations would involve dropping the concrete more than 1.5 m, it shall be
deposited through sheet metal or other approved pipes. As far as practicable, the pipes
shall be kept full of concrete during placing and their lower ends shall be kept buried in
the newly placed concrete. After initial set of the concrete, the forms shall not be jarred
and no strain shall be placed on the ends of reinforcement bars which project.

Concrete, during and immediately after depositing, shall be thoroughly compacted. The
compaction shall be done by mechanical vibration subject of the following provisions:

1) The vibration shall be internal unless special authorisation of other methods is given by
the Engineer or as provided herein.

Page 1011
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

2) Vibrators shall be of a type and design approved by the Engineer. They shall be
capable of transmitting vibration to the concrete at frequencies of not less than 4,500
impulses per minute.

3) The intensity of vibration shall be such as to visibly affect a mass of concrete of 20 mm


slump over a radius of at least 450 mm.

4) The Contractor shall provide a sufficient number of vibrators to properly compact each
batch immediately after it is placed in the forms.

5) Vibrators shall be manipulated to thoroughly work the concrete around the


reinforcement and embedded fixtures, and into the corners and angles of the forms.
Vibration shall be applied at the point of deposit and in the area of freshly deposited
concrete. The vibrators shall be inserted and withdrawn from the concrete slowly. The
vibration shall be of sufficient duration and intensity to thoroughly compact the concrete,
but shall not be continued so as to cause segregation. Vibration shall not be continued at
any one point to the extent that localised areas of grout are formed.

Application of vibrators shall be at points uniformly spaced and not further apart than
twice the radius over which the vibration is visibly effective.

6) Vibration shall not be applied directly or through the reinforcement to sections or layers
of concrete which have hardened to the degree that the concrete ceases to be plastic
under vibration. It shall not be used to make concrete flow in the forms over distances so
great as to cause segregation, and vibrators shall not be used to transport concrete in the
forms.

7) Vibration shall be supplemented by such spading as is necessary to ensure smooth


surfaces and dense concrete along form surfaces and in corners and locations impossible
to reach with the vibrators.

8) The provisions of this Section shall also apply to precast piling, concrete cribbing and
other precast members except that, if approved by the Engineer, the manufacturer’s
methods of vibration may be used.

Concrete shall be placed in horizontal layers not more than 600 mm thick except as
hereinafter provided. When less than a complete layer is placed in one operation, it shall
be terminated in a vertical bulkhead. Each layer shall be placed and compacted before
the preceding batch has taken initial set to prevent injury to the green concrete and avoid
surfaces of separation between the batches. Each layer shall be compacted so as to
avoid the formation of a construction joint with a preceding layer which has not taken
initial set.

When the placing of concrete is temporarily discontinued, the concrete, after becoming
firm enough to retain its form, shall be cleaned of laitance and other objectionable
material to a sufficient depth to expose sound concrete. To avoid visible joints as far as
possible upon exposed faces, the top surface of the concrete adjacent to the forms shall
be smoothed with a trowel. Where a “feather edge” might be produced at a construction
joint, as in the sloped top surface of a wing wall, an inset form shall be used to produce a
blocked out portion in the preceding layer which shall produce an edge thickness of not
less than 150 mm in the succeeding layer. Work shall not be discontinued within 450 mm
of the top of any face, unless provision has been made for a coping less then 450 mm
thick, in which case, if permitted by the Engineer, a construction joint may be made at the
under side of the coping.

Page 1012
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Immediately following the discontinuance of placing concrete all accumulations of mortar


splashed upon the reinforcement steel and the surfaces of forms shall be removed. Dried
mortar chips and dust shall not be puddled into the unset concrete. If the accumulations
are not removed prior to the concrete becoming set, care shall be exercised not to injure
or break the concrete-steel bond at and near the surface of the concrete, while cleaning
the reinforcement steel.

For simple spans, concrete shall preferably be deposited by beginning at the centre of the
span and working from the centre toward the ends. Concrete in girders shall be deposited
uniformly for the full length of the girder and brought up evenly in horizontal layers. For
continuous spans, the concrete placing sequence shall be as shown on the plans or
agreed on by the Engineer.

Concrete in slab and girder haunches less than 1.0 metre in height shall be placed at the
same time as that in the girder stem.

Concrete in slab spans shall be placed in one continuous operation for each span unless
otherwise provided.

Concrete in T-beam or deck girder spans may be placed in one continuous operation if
permitted by the Engineer.

Concrete in columns and pier shafts shall be placed in one continuous operation, unless
otherwise directed.

Unless otherwise permitted by the Engineer, no concrete shall be placed in the


superstructure until the column forms have been stripped sufficiently to determine the
character of the concrete in the columns. The load of the superstructure shall not be
applied to the supporting structures until they have been in place at least 14 days, unless
otherwise permitted by the Engineer.

Pneumatic placing of concrete shall be permitted only if authorised by the Engineer. The
equipment shall be so arranged that vibration does not damage freshly placed concrete.

Where concrete is conveyed and placed by pneumatic means the equipment shall be
suitable in kind and adequate in capacity for the work. The machine shall be located as
close as practicable to the place of deposit. The position of the discharge end of the line
shall not be more than 3 metres from the point of deposit. The discharge lines shall be
horizontal or inclined upwards from the machine. At the conclusion of placement the
entire equipment shall be thoroughly cleaned.

Placement of concrete by pumping shall be permitted only if authorised by the Engineer.


The equipment shall be so arranged that vibrations do not damage freshly placed
concrete. Where concrete is conveyed and placed by mechanically applied pressure, the
equipment shall be suitable in kind and adequate in capacity for the work. The operation
of the pump shall be such that a continuous stream of concrete without air pockets is
produced. When pumping is completed, the concrete remaining in the pipeline, if it is to
be used, shall be ejected in such a manner that there is not contamination of the concrete
or separation of the ingredients. After this operation, the entire equipment shall be
thoroughly cleaned.

Add additional Paragraph as follows:

Perforations and Embedment of Special Devices

Page 1013
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

The Contractor is responsible for determining in advance of making any concrete pours,
all requirements for perforation of concrete sections or embedment therein of special
devices of other trades, such as conduits, pipes, weep holes, drainage pipes, fastenings,
etc. Any concrete poured without prior provision having been made, shall be subject to
correction at the Contractor’s expense.
Special devices to be embedded:

• Expansion joints
• Drain outlets including fixing bolts for down pipes
• Bolts and inserts for sign posts
• Bolts and inserts for various purposes regarding inspection and maintenance as
directed by the Engineer

Other devices not mentioned above shall be shown on the Drawings, or directed by the
Engineer. The inserts and fittings should conform to Sections 5.9 and 5.10 of this
Specification.

Finishing Concrete Surfaces

One of the following types of finishing shall be applied to concrete surfaces:

Type A – Concrete Deck

Immediately after placing concrete, concrete decks shall be struck off using templates to
provide proper crowns and shall be finished smooth to the correct levels. Finish shall be
slightly but uniformly roughened by brushing. The finished surface shall not vary more
then 10 mm from a 3 metre straight edge placed in any direction on the roadway.
Deviation from the grade line shall not be more than + 30 mm in any 20 metre length.

Type B - Kerb and Sidewalk Surface

Exposed faces of kerbs and sidewalks shall be finished to true lines and grades. The kerb
surface shall be wood floated to a smooth but not slippery finish. Sidewalk surfaces shall
be slightly but uniformly roughened by brushing.

Type C - Ordinary Finish

An ordinary finish is defined as the finish left on a surface after the removal of the forms
when all holes left by form ties have been filled, and any minor surface defects have been
repaired. The surface shall be true and even, free from depressions or projections.

The concrete in bridge seats, caps, and tops of walls shall be struck off with a straight
edge and floated to true grade. Under no circumstances shall the use of mortar topping
for concrete surfaces be permitted.

Type D - Rubbed Finish

After the removal of forms the rubbing of concrete shall be started as soon as its condition
permits. Immediately before starting this work the concrete shall be kept thoroughly
saturated with water for a minimum period of three hours. Sufficient time shall have
elapsed before the wetting down to allow the mortar used in patching to have thoroughly
set. A medium coarse carborundum stone shall be used for rubbing a small amount of
mortar on the face. The mortar used shall be composed of cement and fine aggregate

Page 1014
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

mixed in the same proportions as that used in the concrete being finished. Rubbing shall
be continued until all form marks, projections, and irregularities have been removed, all
voids filled, and a uniform surface has been obtained. The paste produced by this rubbing
shall be left in place at this time. The final finish shall be obtained by rubbing with a fine
carborundum stone and water until the entire surface is of a smooth texture and uniform
colour.

After the final rubbing has been completed and the surface has dried, burlap shall be
used to remove loose powder. The final surface shall be free from unsound patches,
paste, powder and objectionable marks.

Type E - Bush hammer Finish

Bush hammering shall be carried out by treating the surface with an approved heavy duty
power hammer fitted with a multi-point tool which shall be operated over the surface to
remove 5 to 6 mm of concrete paste and expose maximum areas of coarse aggregate.

Aggregate left embedded shall not be fractured or loose. 25 mm wide bands at all corners
and arises shall be left as cast. The finish surface shall be even and of uniform
appearance and shall be washed with water upon completion.

Type F - Ribbed Finish

Ribs shall be vertical and to the dimensions shown on the Drawings. The direction of the
grain of the timber forming the ribs shall be vertical.

Type G – Prestressed Concrete Girder Surface

Exposed faces of Prestressed Girder (i.e. Bottom and side surface) shall be finished to
true lines and grades. The Prestressed Girder surface (i.e. Bottom and side surface) shall
be wood floated to a smooth and slippery finish. Top surfaces shall be slightly but
uniformly roughened by brushing.

Construction Joints

A) General

Construction joints shall be made only where located on the plans or shown in the pouring
schedule, unless otherwise approved by the Engineer. If not detailed on the plans, or in
the case of emergency, construction joints shall be placed as directed by the Engineer.
Shear keys or inclined reinforcement shall be used where necessary to transmit shear or
bond the two sections together.

B) Bonding

Before depositing new concrete on or against concrete which has hardened, the forms
shall be re tightened. The surface of the hardened concrete shall be roughened as
required by the Engineer, in a manner that does not leave loosened particles of aggregate
or damaged concrete at the surface. It shall be thoroughly cleaned of foreign matter and
laitance, and saturated with water. To ensure an excess of mortar at the juncture of the
hardened and the newly deposited concrete, the cleaned and saturated surfaces,
including vertical and inclined surfaces, no grout shall be used at the interface of new and
old concrete. The Placing of concrete shall be carried continuously from joint to joint. The

Page 1015
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

face edges of all joints which are exposed to view shall be carefully finished true to line
and elevation.

1001.10. Underwater Concreting

Delete subsection, substitute with the following:-

Concrete shall not be deposited in water except with the approval of the Engineer and
under his immediate supervision; and in this case the method of placing shall be as
defined in this Section.
Concrete placed under water shall be carefully placed in a compact mass, in its final
position, by means of a tremie tube and shall not be disturbed after being deposited.
Special care must be exercised to maintain still water at the point of deposit. Concrete
shall not be placed in running water. The method of depositing concrete shall be so
regulated as to produce approximately horizontal surfaces.

Concrete seals shall be placed in one continuous operation. When a tremie tube or pipe
is used, it shall consist of a tube or pipe not less than 150 mm in diameter. All joints in the
tube shall be watertight. The means of supporting the tremie tube shall be such as to
permit free movement of the discharge end over the entire top of the concrete and to
permit its being lowered rapidly when necessary to choke off or retard the flow. The
tremie tube shall be filled by a method that prevents washing of the concrete. The
discharge end shall be completely submerged in concrete at all times and the tremie tube
shall be kept full. Concrete slump shall not be less than 200 mm. Dewatering shall
proceed only when the concrete seal is considered strong enough to withstand any
pressure to be exerted upon it. This time shall be decided by the Engineer.

All laitance or other unsatisfactory material shall be removed from the exposed surface by
scraping, jetting, chipping or other means, which do not injure the seal unduly.

1001.11. Curing of Concreting

Add additional section as follows:

Removal of Scaffolding and Formwork

Forms and scaffolding shall not be removed without the approval of the Engineer. The
Engineer’s approval shall not relieve the Contractor of his Contract responsibilities. Any
kentledge blocks and bracing shall be removed at the same time as the forms and in no
case shall any portion of the wood forms be left in the concrete.
Forms used on exposed vertical faces shall remain in place for periods which shall be
determined by the Engineer and normally not less than 3 days. Supporting scaffolding
and forms under slabs, beams and girders shall normally remain in place until the full
required strength of the concrete has been obtained. If a shorter period is requested, this
may be permitted by the Engineer. In such case, special test specimens (see Section
1001.7) shall be cast to monitor the hardening. All structures shall be fully stripped before
adjacent structures are cast.

Repair of Concrete
As soon as the form has been stripped, the Contractor shall advise the Engineer who
shall inspect the concrete before any improvement of the surface takes place. All wire or
metal devices used for securing the formwork which project from or appear on the surface

Page 1016
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

of the finished concrete shall be removed or cut back to at least a depth equal to the
required reinforcement cover. All holes and pockets so formed shall be painted with an
epoxy bonding agent and prior to filing with cement mortar mixed in the same proportions
as the fine aggregate to cement of the concrete mix used for that particular section of the
structure. Excessive honeycombing shall be sufficient to cause rejection of portions of the
structure containing this honeycombing. The Contractor, on receipt of written orders from
the Engineer, shall remove and rebuild such portions of the structure at his own expense.
Smaller honeycombing and other defects can be repaired using epoxy grout if permitted
by the Engineer. Structural, maintenance and aesthetical points of view shall be taken
into consideration before such approval, if any, may be given. The method of repair shall
be approved by the Engineer and an extension of period for a certain part of the
performance bond may be required.

1001.13 Measurement and payment

a. Measurement

This work shall be measured as the volume in cubic metres of concrete of the specified
strength placed and finished complete and accepted. Volumes shall be computed from
the dimensions shown on the Drawings or as ordered by the Engineer. No deductions
shall be made from the measured quantities for drainage, openings or pipes less than
300mm in diameter, conduits, chamfers, reinforcing bars, expansion/Construction joints
or pile heads embedded in the concrete. No measurements shall be considered for
transportation from batching plant to casting location or preparing, fitting, fixing of
formworks/ scaffolding deemed to be inclusive to the unit rate.

b. Payment

Payment will be at the contract unit rate for each class of concrete and shall be full
compensation of labour, formwork preparation, fittings/fixing, tools, plants and other,
curing etc complete and incidental required to complete the work except the cement
and formwork plywood materials. Contractor shall supply necessary coarse aggregate
(Metal), sand, water, ice where necessary, retarder, temporary supports/ propping etc
complete. All basic construction materials such as Cement, and form works shall be
supplied by UNOPS from stock yard and contractor shall be responsible for local
carriage from stock yard to the mixing plant and pouring i/c labour to the structural
member to complete the job.

Pay Items shall be:

Pay item Description Pay unit


1001 (1) Pouring of concrete at Pile, Pile/Pier Cap including Cubic metre
the labour and necessary equipments, plants/
materials. Except supply of Cement and form works
plywood materials. The unit rate is inclusive of the
labour & necessary equipments for fitting/fixing of
scaffolding and formworks preparing, fittings/fixing

Page 1017
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

with appropriate supply of scaffolding/ propping and


water leakage arrangements etc complete
1001 (2) Pouring of concrete at Abutment, wing wall, back Cubic metre
wall, approach slab, deck slab, curbs/utility ducts,
rails and rail posts, Prestressed Girder etc. including
the labour and necessary equipments, plants/
materials Except supply of Cement, and form work
plywoord materials. The unit rate is inclusive of the
labour & necessary equipments for fitting/fixing of
scaffolding and formworks preparing, fittings/fixing
with appropriate supply of scaffolding/ propping and
water leakage arrangements etc complete
1001 (3) Pouring of concrete for ancillary works (Drains, Cubic metre
drain cover slab, footpath cover slab, guard post,
etc. including the labour and necessary equipments,
plants/ materials Except supply of Cement, and form
works plywood materials. The unit rate is inclusive
of the labour & necessary equipments for
fitting/fixing of scaffolding and formworks preparing,
fittings/fixing with appropriate supply of scaffolding/
propping and water leakage arrangements etc
complete

1002. STEEL REINFORCEMENT FOR CONCRETE STRUCTURES

1002.1.Description
No change.

1002.2.Materials

Supply of materials:
• UNOPS shall supply of reinforcement steel bars to the contractor at site
• Contractor shall transport the materials from reinforcement stock yard to
fabrication location and all other necessary local transports, supply all materials
related to the fabrications including binding wires of the reinforcing bars, required
nails, tools and equipments.

Delete subsections (d) and (e), and substitute with the following :-

(d) Hot rolled and cold worked steel bars shall comply with BS 4449 except that no
bar shall contain a flash weld.

(e) Hard drawn mild steel wire shall comply with BS 4482.

Add additional section as follows:

(f) Steel fabric reinforcement shall comply with BS 4483 and shall be delivered to site
in flat mats or pre-bent.

Page 1018
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

(g) Ordering Material

The name of the proposed supplier (or suppliers) of the reinforcement shall be submitted
as soon as possible to the Engineer for his approval. The Contractor shall also submit all
relevant data on the steel required by the Engineer, such as breaking strength, yield
strength, characteristics on elongation, chemical composition etc.

Copies of orders placed shall be submitted to the Engineer.

Bar reinforcement shall be transported in standard bundles, tagged and marked in


accordance with the Code of Standard Practice of the Concrete Reinforcing Steel
Institute.

No steel shall be delivered without a manufacturer’s certificate guaranteeing the yield


stress, which shall be submitted to the Engineer.

The steel shall be stored on Site and marked in a way that later enables identification of
the steel corresponding to each certificate.

(h) Tests

In addition to those data on steel to be submitted by the Contractor, specified test results
for rebar brought on site shall be submitted to the Engineer for approval.

The Contractor shall cut out steel samples as directed by the Engineer and these
samples shall be tested according to the Engineer’s instructions by an approved Testing
Institution. Expenses incurred in connection with cutting out, transporting and testing of
the samples shall be paid for by the Contractor. In general, two samples shall be tested
from each 50 tons of a particular size of reinforcement delivered to the site.

1002.3.Construction Requirements

a. Protection & Storage


No change.

b. Cutting & Bending


Add to end of paragraph the following :-

No Secondary straitening and bending of HTS bars will be allowed. Stirrups and tie bars
shall be bent around a pin having a diameter not less than four times the minimum
thickness of the bar. Bends for other bars, where full tension in the bar may occur, shall
be made around a pin having a diameter not less than twenty times the bar diameter. The
bars shall be cut and bent within the tolerances given in BS 4466. The Contractor shall
be responsible for the correct fit of the bars and the achievement of the required cover as
given on the Drawings or established by the Engineer.

c. Placing & fixing of reinforcement


Delete the sentence of the first paragraph: ‘As far as possible,
bar…………maximum tensile stress’ and substitute the following :-

Page 1019
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Reinforcement shall be furnished in the lengths indicated on the Drawings. When the
Contractor wishes to use more splices than are indicated and/or necessary, the
Contractor shall furnish Working Drawings to the Engineer for approval in accordance
with the guidelines provided on the Contract Drawings. If such additional splices are
approved, the extra weight occasioned by such splices shall not be included in the
measurement of reinforcement for payment.
All splices for high yield deformed steel bars and mild steel plain steel bars shall have lap
lengths as shown on the Drawings. Lap splices shall generally be located at points of
minimum tension in bars. Except where otherwise shown on the Drawings lap splices
shall be made with the bars placed in contact and securely wired together.

Delete the 3rd paragraph and substitute the following :-

Substitutions of bars shall be permitted only with specific authorisation by the Engineer
and at the expense of the Contractor. If bars are substituted they shall have a cross
sectional area equivalent to the design area, or larger. If substitutions of bars are
permitted, the Contractor shall produce working drawings and reinforcing detailing at his
own expense and to the approval of the Engineer.

d) Binding Wire: Reinforcement binding wire shall be 24 BWG galvanized iron wire.

1002.4.Measurement & Payment

a. Measurement
Delete the sentence of the paragraph: ‘Wastage over laps,………rate for
reinforcement’ and substitute the following :-

In computing the weight to be measured, the theoretical weights of bars of the cross
section shown on the Drawings or authorized shall be used. The weight shall be
calculated based on a constant mass of 0.00785 kg/mm² per metre run.

The computed weight shall not include the extra material incurred when bars larger than
those specified are used, or the extra material necessary for splices when bars shorter
than those specified are used with the permission of the Engineer, or the weight of any
devices used to support or fasten the reinforcement in the correct position including any
necessary chairs.

b. Payment

Payment shall be allowed for lap splices not shown when the bars are longer than 12
metres. Only one lap splice per every started 12 metres will be paid for.

The payment shall be full compensation for the fabrication, placing of the reinforcement
excluding the supply of Reinforcing bars but including all binding materials, spacer bars,
Support (Be-bar chair), cutting, and bending, labour, and equipment, tools, cleaning of the
re-bars / foreign materials and incidentals necessary to complete the work.

Pay item Description Pay unit


1002 (1) Transport the materials from reinforcement stock yard to Tonnes
fabrication location, Cutting, bending, fabrication, placing/
installation the reinforcing steel bars in position for Pile works

Page 1020
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

by using of necessary equipments , excluding supply of


reinforcing steel bars as drawing for all diameter
1002 (2) Transport the materials from reinforcement stock yard to Tonnes
fabrication location, Cutting, bending, fabrication, placing the
reinforcing steel bars in position for Pile cap by using of
necessary equipments works excluding supply of reinforcing
steel bars as drawing for all diameter
1002 (3) Transport the materials from reinforcement stock yard to Tonnes
fabrication location, Cutting, bending, fabrication placing the
reinforcing steel bars in position for Abutment, wing wall,
back walls or any vertical walls by using of necessary
equipments, excluding supply of reinforcing steel bars as
drawing for all diameter
1002 (4) Transport the materials from reinforcement stock yard to Tonnes
fabrication location, Cutting, bending, fabrication, placing/
installation the reinforcing steel bars in position for Deck,
approach slab, curbs, rail post/rail bar and any horizontal
members by using of necessary equipments, excluding
supply of reinforcing steel bars as drawing for all diameter
1002 (5) Transport the materials from reinforcement stock yard to Tonnes
fabrication location, Cutting, bending, fabrication, placing/
installation the reinforcing steel bars in position for Ancillary
works (Drain, all covers), guard, Pile works by using of
necessary equipments, excluding supply of reinforcing steel
bars as drawing for all diameter

1003. PRESTRESSING FOR STRUCTURES


Delete all sections and add these following sections:

1003.1. DESCRIPTION

This work shall consist of prestressing precast or cast-on-place concrete by furnishing,


placing and tensioning of prestressing steel in accordance with details shown on the
drawing and as specified in these specifications and the special provisions. It includes
prestressing by post-tensioning methods.

This work shall include the furnishing and installation of any appurtenant items necessary
for the particular prestressing system to be used, including but not limited to ducts,
anchorage assemblies and grout used for pressure grouting ducts.

For cast-in-place prestressed concrete, the term "member" as used in this Section shall
be considered to mean the concrete that is to be prestressed.

When members are to be constructed with part of the reinforcement pretensioned and
part post-tensioned, the applicable requirement of this specification shall apply to each
method.

Page 1021
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Construction of prestressed concrete members of highway bridges requires extensive and


thorough knowledge of the science and technique involved and shall be entrusted only to
qualified engineers with adequate practical experience in this field of bridge engineering
and who are capable of ensuring proper execution of work. It shall be ensured that such
an engineer is always present during the prestressing operation of the structural
members.

Concreting for the construction of prestressed concrete members of highway bridges shall
conform to the requirements of Clause 1001 "Concrete Works" and Clause 1002 "Steel
Reinforcement for Structures" in so far as the requirements of these Clauses apply and
are not specifically modified by requirements set forth herein.

1003.2. MATERIALS

1003.2.1 Supply of Materials

Material to be supplied by the Employer (UNOPS) at site specified in the Special


Provisions:

• Elastomeric bearings and its accessories


• High strength strand for Prestressing Tendons.
• Ducts, support accessories, couplers, air vents for Pre-stressing
• Anchorages
• Form works and props (Full set of scaffoldings)

Contractor shall be responsible for local transportation from the stock yard to working
place for the issued materials by the Employer and Material to be supplied by the
Contractor are:

• High early strength cement and admixtures for grout


• Grout fittings
• Other incidental materials as required by the plans or specifications.

1003.2.2 Handling and Storage of Materials

Elastomeric Bearings

The elastomeric bearings and their metal components shall be stored clear of the ground
in a storage shed until required for installation. Particular care shall be taken to prevent
damage to the stainless steel surfaces of the bearings and the teflon coated bearing
pads. The protective wrapping around the stainless steel surfaces and teflon coated
bearing pads shall not be removed until immediately prior to the installation of the
bearings or shall not be removed at all if so directed by the Engineer in the field.

Anchorages

The anchorages shall be stored clear of the ground in an storage shed until the
anchorages or their components are required for installation. Care shall be taken to
prevent damage to the high tensile steel anchorages and in particular the formation of
nicks, bruises or other surface damage.

High Strength Strand

High strength strand shall be stored clear of the ground in a storage shed. The protective
packing around the reless packs shall not be removed until the strand is required for the

Page 1022
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

fabrication of the cables. The high strength strand shall at all times be protected from
corrosion and contamination by oil, dirt or other materials which may adversely affect the
performance of the cables.

Ducts

Ducts, couplers and air vents shall be stored clear of the ground in a storage shed until
required for installation. Care shall be taken to prevent damage to the ducts or their
components, making sure that no change occurs in the cross-sectioned shape of the
ducts and duct components.

Void Forms

Void forms shall be stored clear of the ground in a storage shed until the forms are
required for installation. The void forms shall be handled with care in order to prevent
weakening of the forms by physical damage.

Replacement of Damaged Materials

Material supplied by UNOPS to the Contractor, which in the opinion of the Engineer has
been damaged or otherwise rendered unusable by improper storage or handling by the
Contractor, shall be replaced by the Contractor at the Contractor's expense.

Falsework

Notwithstanding the reference to the falsework having to be supported on piling as per


Section Falsework of the "Specifications for Reinforced Concrete", the use of steel
scaffolding on mud sills will be permitted.

In the event that the Contractor elects to use steel scaffolding on mud sills, the Engineer
will require that selected parts of the falsework be tested to the estimated dead load plus
construction load in order to establish anticipated settlement. The Contractor shall provide
the Engineer with all pertinent data required for the determination of the construction
loads.

Unless there is a marked difference in the ground conditions under the structure, one test
load will be required only for falsework supported on natural ground and one test load for
falsework supported on fill.

The test loads shall not be carried out too far in advance of the concrete placing
operations to preclude the possibility of a change in the state of the natural ground and fill
from that at the time of the tests. In the event that a change in the state of the natural
ground or fill does take place between the time of the test and concrete placing
operations, the Engineer may require that the load test be repeated. The falsework shall
be arranged to provide uniform bearing pressure from the mud sills to the supporting
ground or fill to preclude the possibility of differential settlement of the falsework.

The field test loading of steel scaffolding on mud sills to establish anticipated settlement
shall in no way relieve the Contractor of the requirement to have the falsework designed
by a Registered Professional Engineer. The cutting or stepping of the bridge slopes to
facilitate the placing of mud sills shall be kept to a minimum, and the level surface
required for placing the steel scaffolding shall be obtained by means of timber cribs. All
cuts or steps in the slopes which may be permitted by the Engineer to facilitate the
erection of falsework shall be backfilled to the original cross-section and compaction by
the Contractor at his own expense after the removal of the falsework.

Page 1023
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Where required by plans or Special Provisions, the Contractor shall provide openings in
the falsework for highway or railway traffic to clearances as shown on the plans. The
openings in the falsework shall be designed and constructed so that the falsework will be
stable if subjected to impact by vehicles. No vehicles will be allowed through a falsework
unless a properly designed and constructed opening is provided.

In addition to the requirements for falsework removal, falsework shall not be removed until
the Engineer is satisfied that the stressing operations have been satisfactorily carried out.
All damage to the structure resulting from the removal of the falsework shall be repaired
by the Contractor at his own expense to the satisfaction of the Engineer.

Formworks

All Form work shall be of waterproof Plywood or steel and shall be built mortar tight and
rigid enough to maintain the concrete in position during placing, compacting, setting and
hardening.

The Form work shall be rigidly constructed, supported on a firm bearing base, and braced
so as to retain its shape and position and shall be set to the specified lines and levels.
The props shall be on firm ground over the compacted Coffer Dam and over the minimum
10mm thick steel plates or timber plank of adequate size to avoid any uneven settlement
during concreting operation. A design of Proping/shuttering materials calculation must be
submitted by the contractor for approval before start the formworks.

Metal ties or anchorages or P cones within the form shall be constructed to permit their
removal to a depth of 50mm from the face without disturbing the concrete, and shall be of
such design that the size of the cavity left is minimized.

In any case Timber Form works shall NOT be allowed to use.

Steel Form work shall be rigid with no surface blemish that will impair the quality of finish
of the concrete surface.

Forms shall be sufficiently tight to prevent loss of mortar from concrete.

Molding strips shall be placed in the corners of forms to produce edges on permanently
exposed concrete surfaces as shown on the drawings.

Except where otherwise directed, all forms shall be coated with oil on the concrete face
side. The oil used must be non-staining and have no adverse effect on paint or any other
finish.

All Form work shall be approved by the Engineer before placing of concrete commences.

1003.2.1 Prestressing Tendons

Prestressing tendons shall be high tensile seven-wire strand shall conform to the
requirements of the following specifications.

Strand

Uncoated seven-wire strand shall conform to the requirements of AASHTO M203 (ASTM
A416 – 85 Low-Relaxation) shall apply when specified.

Page 1024
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

All prestressing steel shall be protected against physical damage and rust or other results
of corrosion at all times from manufacture to grouting. Prestressing steel shall also be
free of deleterious material such as grease, oil, wax or paint. Prestressing steel that has
sustained physical damage at any time shall be rejected. The development of pitting or
other results of corrosion, other than rust stain, shall be cause for rejection.

Prestressing steel shall be packaged in containers or shipping forms for the protection of
the strand against physical damage and corrosion during shipping and storage. A
corrosion inhibitor which prevents rust or other results of corrosion shall be placed in the
package or form, or shall be incorporated in a corrosion inhibitor carrier type packaging
material, or when permitted by the Engineer, may be applied directly to the steel. The
corrosion inhibitor shall have no deleterious effect on the steel or concrete or bond
strength of steel to concrete or grout. Packaging or forms damaged from any cause shall
be immediately replaced or restored to original condition.

The shipping package or form shall be clearly marked with a statement that the package
contains high-tensile prestressing steel and the type or corrosion inhibitor used, including
the date packaged.

Special care will be taken by the Contractor to store the H. T. steel wires under suitable
shed as approved by the Engineer. He or his authorised representative shall always have
an easy access to the store yard for inspecting the H.T. wire/strands and satisfying
themselves regarding the condition thereof. The Contractor shall scrupulously follow any
modifications suggested by them.

All high tensile steel for prestressing work shall be stored about 30 cm clear of he ground
and protected from the weather, from splashes of any other liquid. It shall also be
invariably wrapped in gunny cloth, tarpaper or any other suitable wrapping material that
are chemically neutral. If it is required to be stored at site it shall be suitably covered.
Suitable and effective protection of the prestressing steel against corrosion and any other
mechanical damage shall be ensured. The prestressing steel shall be protected from the
splashes of the cutting operation of any oxy-acetylene torch or arc welding processes in
the vicinity. In no circumstances any prestressing tendons after manufacture be subjected
to any welding operation or on site heat treatment or metallic coating such as galvanizing.
As and when required by the Engineer, the contractor shall arrange to get the necessary
tests carried out at no extra cost to the Department to ensure that the physical
characteristics have not been impaired in any way.

Stock piling of H.T. steel in the open at the work site will not be allowed under any
circumstances.

1003.2.2 Post - Tensioning Anchorages and Couplers

All anchorage and couplers shall develop at least 95 percent of the minimum specified
ultimate strength of the prestressing steel, when tested in an unbonded state, without
exceeding anticipated set. The coupling of tendons shall not reduce the elongation at
rupture below the requirements of the tendon itself. Couplers and/or coupler components
shall be enclosed in housings long enough to permit the necessary movements. Couplers
for tendons shall be used only at locations specifically indicated and/or approved by the
Engineer. Couplers shall not be used at points of sharp tendon curvature.

Bonded Systems

Bond transfer lengths between anchorage and the zone where full prestressing force is
required under service and ultimate loads shall normally be sufficient to develop the

Page 1025
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

minimum specified ultimate strength of the prestressing steel. When anchorages or


couplers are located at critical sections under ultimate load, the ultimate strength require
of the bonded tendons shall not exceed the ultimate capacity of the tendon assembly,
including the anchorage or coupler, tested in an unbonded state.

Housings shall be designed so that complete grouting of all of the coupler components
will be accomplished during grouting of tendons.

Any anchorage devices with or without distribution plates required, as defined in the
AASHTO standard specifications for Highway Bridges and any supplementary
reinforcement required in the local zone of the anchorage, as defined in the AASHTO
"Guide specifications for design and construction of segmental concrete bridges".

1003.2.3 Identification and Testing

All strands to be shipped to the site shall be assigned a lot number and tagged for
identification purposes. Anchorage assemblies to be shipped shall be likewise identified.

Each reel of strand reinforcement shall be accompanied by a manufacturer's certificate of


compliance, a mill certificate, and a test report. The mill certificate and test report, cross-
sectional area, yield and ultimate strengths, elongation at rupture, modulus of elasticity,
and the stress strain curve for the actual prestressing steel intended for use. All values
certified shall be based on test values and nominal sectional areas of the material being
certified.

The Contractor shall furnish to the Engineer for verification testing the samples described
in the following sub-articles selected from each lot. If ordered by the Engineer, the
Inspector shall make the selection of samples at the manufacturer’s plant.

All samples submitted shall be representative of the lot to be furnished and in the case of
strand, shall be taken from the same master roll.

The actual strength of the prestressing steel shall not be less than specified by the
applicable ASTM Standard, and shall be determined by tests of representative samples of
the tendon material in conformance with ASTM Standards.

All of the materials specified for testing shall be supplied free of cost and shall be
delivered in time for tests to be made well in advance of anticipated time of use.

Post-tensioning Method Tendons:

The following lengths shall be furnished for each 20 ton, or portion thereof, lot of material
used in the work. For strand to be furnished with fittings - 150 cm between near ends of
fittings.

All anchorages, end fittings, couplers and exposed tendons, which will not be encased in
concrete or grout in the completed work, shall be permanently protected against
corrosion.

Except for anchorage devices without distribution plates which are tested in accordance
with the AASHTO standard specifications for Highway Bridges, the Contractor shall
furnish for testing, one specimen of each size of prestressing tendon, including couplings,
of the selected type, with end fittings and anchorage assembly attached, for strength tests
only. These specimens shall be 1.5 metre in clear length, measured between ends of

Page 1026
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

fittings. If the results of the test indicate the necessity of check tests, additional
specimens shall be furnished without cost.

When dynamic testing is required, the Contractor shall perform the testing and shall
furnish certified copies of test results that indicate conformance with the specified
requirements prior to installation of anchorages couplers.

For prestressing systems previously tested and approved on projects having the same
tendon configuration, the Engineer may not require complete tendon samples provided
there is no change in the material, design, or details previously approved. Shop drawings
or prestressing details shall identify the project on which approval was obtained,
otherwise testing shall be conducted.

1003.2.4 Corrosion Inhibitor:

Corrosion inhibitor shall consist of a vapor phase inhibitor (VPI) powder conforming to the
provisions of Federal Specification MIL-P-3420 or as otherwise approved by the Engineer.
When approved, water-soluble oil may be used on tendons as a corrosion inhibitor.

1003.2.5 Ducts:

Ducts used to provide holes or voids in the concrete for the placement of post-tensioned
bonded tendons may be either formed with removable cores or may consist of rigid or
semi-rigid ducts that are cast in to the concrete.

Ducts formed with removable cores shall be formed with no constrictions which would
tend to block the passage of grout. All coring materials shall be removed.

Ducts formed by sheath left in place shall be a type that will not permit the intrusion of
cement paste. They shall transfer bond stresses as required and shall retain shape under
the weight of the concrete and shall have sufficient strength to maintain their correct
alignment without visible wobble during placement of concrete.

Metal Ducts:

Sheathing for ducts shall be metal, except as provided herein. Such ducts shall be
galvanized ferrous metal and shall be fabricated with either welded or interlocked seams.
Galvanizing of welded seams will not be required. Rigid ducts shall have smooth inner
walls and shall be capable of being curved to the proper configuration without crimping or
flattening. Semi-rigid ducts shall be corrugated and when tendons are to be inserted after
the concrete has been placed their minimum wall thickness shall be as follows: 26 gauge
for ducts less than or equal to 2 - 16 mm diameter, 24 gauge for ducts greater than 2 - 16
mm diameter. When bar tendons are preassembled with such ducts, the duct thickness
shall not be less than 31 gauge.

Duct Area:

The inside diameter of ducts shall be at least 6 mm larger than the nominal diameter of
single strand tendons, or in the case of multiple strand tendons, the inside cross-sectional
area of the sheathing shall be at least two times the net area of the prestressing steel.
When tendons are to be placed by the pull through method, the duct area shall be at least
2-1/2 times the net are of the prestressing steel.

Duct Fittings:

Page 1027
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Coupling and transition fittings for ducts formed by sheathing shall be of ferrous metal and
shall be cement paste intrusion proof and of sufficient strength to prevent distortion or
displacement of the ducts during concrete placement.

All ducts or anchorage assemblies shall be provided with pipes or other suitable
connections at each end of the duct for the injection of grout after prestressing. As
specified in "Vents and Drains", duct shall also be provided with ports for venting or
grouting at high points and for draining at intermediate low points.

Vent and drain pipe shall be 12 mm minimum diameter standard pipe or suitable plastic
pipe. Connection to ducts shall be made with metallic or plastic structural fasteners. The
vents and drains shall be morter tight, taped as necessary, and shall provide means for
injection of grout through the vents and for sealing to prevent leakage of grout.

1003.2.6 Grout

Material for use in making grout that is to be placed in the ducts after tendons are post-
tensioned shall conform to the following:

(1) Portland Cement


Portland cement shall conform to one of the following: Specifications for Portland
Cement - AASHTO M 85, Types 1, 2 or 3.
Cement used for grouting shall be fresh and shall not contain any lumps or other
indication or hydration or "pack set".
(2) Water
The water used in the grout shall be potable, clean and free of injurious quantities of
substances known to be harmful to Portland cement, or prestressing steel.

(3) Admixtures

Admixtures, if used, shall impart the properties of low water content, good
flowability, minimum bleed and moderate expansion. They shall contain no
chemicals in quantities that may have harmful effect on the prestressing steel or
cement. Admixtures which, at the dosage used, contain chlorides in excess of
0.005 percent of weight of the cement used or contain any fluorides, sulphites, and
nitrates shall not be used.
When a grout-expanding admixture is required, or is used at the Contractor's option,
it shall be well dispersed through the other admixtures and shall produce a 2 to 6
percent unrestrained expansion the grout.
mount of admixture to obtain desired amount of expansion shall be determined by
tests. If the source of manufacture or brand of either admixture of cement changes
after testing, new test shall be conducted to determine proper proportions.
All admixtures shall be used in accordance with the instructions of the manufacturer.
Prestressing steel bars, may be obtained from the manufacturers in straight
condition. Any small adjustments necessary because of site conditions shall be
made by bending in a normal type bar bender. Bars shall not be bent when their
temperature is less than 10oC.

1003.3. WORKMANSHIP

1003.3.1 Cleaning:

All prestressing steel shall be free from loose mild scale, rust, oil, grease or any other
harmful matter at the time of its placing in the member. A slight film of rust is not
necessarily harmful and may improve bond.

Page 1028
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Cleaning of the steel may be carried out by immersion in suitable solvent solutions, wire
brushing, or passing through a pressure box containing carborundum power.

1003.3.2 Straightening:

As far as possible prestressing wire shall be obtained form the manufacturers in coils
having diameter of not less than 350 times the diameter of the wire itself, so that the wire
springs back straight on being uncoiled. If due to smaller diameter of the coil or any other
reason it does not happen the wire shall be straightened before use.

1003.3.3 Placement:

1003.3.3.1 Ducts

Ducts shall be rigidly supported at the proper locations in the forms by ties to reinforcing
steel which are adequate to prevent displacement during concrete placement.
Supplementary support bars shall be used where needed to maintain proper alignment of
the duct. Hold-down ties to the forms shall be used when the buoyancy of the ducts in the
fluid concrete would lift the reinforcing steel.

Joints between sections of duct shall be coupled with positive connections which do not
result in angle changes at the joints and will prevent the intrusion of cement paste.

After placing of ducts, reinforcement and forming is complete, an inspection shall be


made to locate possible duct damage.

All unintentional holes or openings in the duct must be repaired prior to concrete placing.

Grout openings and vents must be securely anchored to the duct and to either the forms
or to reinforcing steel to prevent displacement during concrete placing operations.
After installation in the forms, the ends of ducts shall at all times be covered as necessary
to prevent the entry of water or debris.
Vents and Drains
All ducts for continuous structures shall be vented at the high points of the duct profile,
except where the curvature is small, as in continuous slabs, and at additional locations as
shown on the drawings. Where freezing conditions can be anticipated prior to grouting,
drains shall be installed at low point in ducts where needed to prevent the accumulation of
water. Low-point drains shall remain open until grouting is started.
The ends of vents and drains shall be removed one inch below the surface of the
concrete after grouting has been completed and the void filled with mortar.

1003.3.3.2 Prestressing Steel

For Post-Tensioning:

All prestressing steel preassembled in ducts and installed prior to the placement of
concrete shall be accurately placed and held in position during concrete placement.
When the prestressing steel is installed after the concrete has been placed, the
Contractor shall demonstrate to the satisfaction of the Engineer that the ducts are free of
water and debris immediately prior to installation of the steel. The total number of strands
in an individual tendon may be pulled into the duct as a unit, or the individual strand may
be pulled or pushed through the duct.
Anchorage devices or block-out templates for anchorages shall be set and held so that
their axis coincides with the axis of the tendon and anchor plates are normal in all

Page 1029
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

directions to the tendon.


The prestressing steel shall be distributed so that the force in each girder steam is equal
or as required by the drawings, except as provided herein. For box girders with more
than two girder stems, at the Contractor's option, the prestressing force may vary up to 5
percent from the theoretical required force per girder stem provided the required total
force in the superstructure is obtained and the force is distributed symmetrically about the
centerline of the typical section.

1003.3.4 Cutting

Suitable mechanical or flame cutters shall do all cutting to length and trimming of ends.
When a flame cutter is used, care shall be taken to ensure that the flame does not come
in contact with other stressed steel.
In post-tensioning, ends of prestressing steel projecting beyond the anchorages shall be
cut after the grout has set.

1003.3.5 Welding

Welding of prestressing steel shall not be permitted.

1003.3.6 Protection on Work

Prestressing steel installed in members prior to placing and curing of the concrete, or
installed in the duct but not grouted within the time limit specified below, shall be
continuously protected against rust or other corrosion by means of a corrosion inhibitor
placed in the ducts or directly applied to the steel. The prestressing steel shall be so
protected until grouted or encased in concrete. Prestressing steel installed and tensioned
in members after placing and curing of the concrete and grouted within the time limit
specified below will not require the use of a corrosion inhibitor described herein and rust
which may form during the interval between tendon installation and grouting will not be
cause for rejection of the steel.

The permissible interval between tendon installation and grouting without use of a
corrosion inhibitor for various exposure conditions shall be as follows:
Very Damp Atmosphere or over saltwater (Humidity > 70%) 7 days
Moderate Atmosphere (Humidity from 40% to 70%) 15 days
Very Dry Atmosphere (Humidity < 40%) 20 days
After tendons are placed in ducts, the opening at the ends of the ducts shall be sealed to
prevent entry of moisture.
When steam curing is used, steel for post-tensioning shall not be installed until the steam
curing is completed.
Whenever electric welding is performed on or near members containing prestressing
steel, the welding ground shall be attached directly to the steel being welded. All
prestressing steel and hardware shall be protected from weld spatter or other damage.

1003.3.7 Anchorages

Anchor cones, blocks and plates shall be positioned and maintained during concreting so
that the centre line of the duct passes axially through the anchorage assembly.
All bearing surfaces of the anchorages shall be clean prior to concreting and tensioning.
Adequate provision shall be made for protection of the anchorage against corrosion.

1003.4. TENSIONING

1003.4.1 General Tensioning Requirements

Page 1030
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Prestressing steel shall be tensioned by hydraulic jacks so as to produce the forces


shown on the drawings or on the approved working drawing with appropriate allowances
for all losses. Losses to be provided for shall be as specified in Division I, AASHTO
standard specifications for Highway Bridge. For post-tensioned work the losses shall also
include the anchor set loss appropriate for the anchorage system employed.
The maximum temporary stress (jacking stress) and the stress in the steel before loss
due to creep and shrinkage shall not exceed the values allowed in Division I, AASTO
standard specification for Highway Bridge.
The method of tensioning employed shall be following as specified or approved:
Post-tensioning in which the reinforcing tendons are installed in voids or ducts within the
concrete and are stressed and anchored against the concrete after the development of
the required concrete strength. As a final operation under this method, the voids or ducts
are pressure-grouted.
During stressing of strand, individual wire failures may be accepted by the Engineer,
provided not more than one wire in any strand is broken and the area of broken wires
does not exceed 2 percent of the total area of the prestressing steel in the member.

Concrete Strength:

Prestressing forces shall not be applied or transferred to the concrete until the concrete
has attained the strength specified for initial stressing. In addition, cast-in-place concrete
for other than segmentally constructed bridges shall not be post-tensioned until at least
10 days after the last concrete has been placed in the member to be post-tensioned.

Prestressing Equipment:

Hydraulic jacks used to stress tendons shall be capable of providing and sustaining the
necessary forces and shall be equipped with either a pressure gauge or a load cell for
determining the jacking stress. The jacking system shall provide an independent means
by which the tendon elongation can be measured. The pressure gauge shall have an
accurately reading dial at least 150 mm in diameter or a digital display and each jack and
its gauge shall be calibrated as a unit with the cylinder extension in the approximate
position that it will be at final jacking force and shall be accompanied by a certified
calibration chart or curve. The load cell shall be calibrated and shall be provided with an
indicator by means of which the prestressing force in the tendon may be determined. The
range of the load cell shall be such that the lower 10 percent of the manufacturer's rated
capacity will not be used in determining the jacking stress. When approved by the
Engineer, calibrated proving rings may be used in lieu of load cells.
Recalibration of gauges shall be repeated at least annually and whenever gauge
pressures and elongation indicate materially different stresses.
Only oxygen flame or mechanical cutting devices shall be used to cut strand after
installation in the member or after stressing. Electric arc welders shall not be used.

Sequence of Stressing:

When the sequence of stressing individual tendons is not otherwise specified, the
stressing of post-tensioning tendons and the release of pretensioned tendons shall be
done in a sequence that produces a minimum of eccentric force in the member.

Measurement of Stress:

The Contractor shall provide a record of gauge pressures and tendon elongations for
each tendon for review and approval by the Engineer. Elongations shall be measured to
an accuracy of 1.6 mm. Stressing tails of post-tensioned tendons shall not be cut off until

Page 1031
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

the stressing records have been approved.


The stress in tendons during tensioning shall be determined by the gauge or load cell
readings and shall be verified with the measured elongations. Calculations of anticipated
elongations shall utilize the modulus of elasticity, based on nominal area, as furnished by
the manufacturer for the lot of steel being tensioned, or as determined by a bench test of
strand use in the work.
All tendons shall be tensioned to a preliminary force as necessary to eliminate any take-
up in the tensioning system before elongation readings are started. This preliminary force
shall be between 5 and 25 percent of the final jacking force. The initial force shall be
measured by a dynamometer by the approved method, so that its amount can be used as
a check against elongation as computed and as measured. Each strand shall be marked
prior to final stressing to permit measurement of elongation and to insure that all anchor
wedges set properly.
It is anticipated that there may be discrepancy in indicated stress between jack gauge
pressure and elongation. In such event, the loads used, as indicated by the gauge
pressure, shall produce a slight over-stress rather that under-stress. When a discrepancy
between gauge pressure and elongation of more than 5 percent in tendons over 15 metre
long or 7 percent in tendons of 15 metre or less in length occurs, the entire operation
shall be carefully checked and the source of error determined and corrected before
proceeding further.

1003.4.2 Post-Tensioning Method Requirements

Prior to post-tensioning any member, the Contractor shall demonstrate to the satisfaction
of the Engineer that the prestressing steel is free and unbounded in the duct.
All strands in each tendon, except for those in ducts with not more than four strands, shall
be stressed simultaneously with a multi-strand jack.
Tensioning shall be accomplished so as to provide the forces and elongations specified in
above.
Except as provided herein or when shown on the drawings or on the approved working
drawings, tendons in continuous post-tensioned members shall be tensioned by jacking at
each end of the tendon. For straight tendons and when one end stressing is shown on
the drawings, tensioning may be performed by jacking from one end or both ends of the
tendon at the option of the Contractor.

1003.5. JOINTS IN CONSTRUCTION WITH PRE-CAST UNITS


Joints between a series of precast concrete units which are to be prestressed together by
post-tensioning shall be such as to ensure even transfer of compression from one unit to
another.
Whatever be the method of jointing, the holes of the prestressing steel shall be accurately
made and shall meet one another in true alignment at ends. Jigs shall always be used.
Care shall be taken to ensure that the jointing material does not enter the duct or presses
the sheath against the prestressing steel.
The contractor shall submit the construction procedure as per specification and approved
by the Engineer.
Jointing by application of mortar on the face of a unit and then placing another unit
against it shall not be permitted.

1003.6. GROUTING

1003.6.1 General

When the post-tensioning method is used, the prestressing steel shall be provided with
permanent protection and shall be bonded to the concrete by completely filling the void

Page 1032
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

space between the duct and the tendon with grout.

1003.6.2 Preparation of Ducts

All ducts shall be clean and free of deleterious materials that would impair bonding or
interfere with grouting procedures.
Ducts with concrete wall (cored ducts) shall be flush to ensure that the concrete is
thoroughly wetted. Metal ducts shall be flushed if necessary to remove deleterious
material.
Water used for flushing ducts may contain slaked lime (calcium hydroxide) or quicklime
(calcium oxide) in the amount of 10 gm per litre.
After flushing, all water shall be blown out of the duct with oil-free compressed air.

1003.6.3 Equipment

The grouting equipment shall include a mixer capable of continuous mechanical mixing
which will produce a grout free of lumps and undispersed cement, a grout pump and
stand-by flushing equipment with water supply. The equipment shall be able to pump the
mixed grout in a manner that will comply with all requirements.
Accessory equipment that will provide for accurate solid and liquid measures shall be
provided to batch all materials.
The pump shall be a positive displacement type and be able to produce an outlet
pressure of at least 1.0 N/mm2. The pump should have seals adequate to prevent
introduction of oil, air or other foreign substance into the grout and to prevent loss of grout
or water.
A pressure gauge having a full-scale reading of no greater than 2.0 N/mm2 shall be
placed at some point in the grout line between the pump outlet and the duct inlet.
The grouting equipment shall contain a screen having clear openings of 3.0 mm
maximum size to screen the grout prior to its introduction into the grout pump. If a grout
with a thixotropic additive is used, a screen opening of 5.0 mm is satisfactory. This
screen shall be easily accessible for inspection and cleaning.
The grouting equipment shall utilize gravity feed to the pump inlet from a hopper attached
to and directly over it. The hopper must be kept at least partially full of grout at all times
during the pumping operation to prevent air from being drawn into the post-tensioning
duct.
Under normal conditions, the grouting equipment shall be capable of continuously
grouting the largest tendon on the project in no more than 20 minutes.

1003.6.4 Mixing of Grout:

Water shall be added to the mixer first, followed by Portland cement and admixture or a
required by the admixture manufacturer.
Mixing shall be of such duration as to obtain a uniform, thoroughly blended grout, without
excessive temperature increase or loss of expansive properties of the admixture. The
grout shall be continuously agitated until it is pumped.

Water shall not be added to increase grout flowability that has been decreased by
delayed use of the grout.
Proportions of materials shall be based on tests made on the grout before grouting is
begun, or may be selected based on prior documented experience with similar materials
and equipment and under comparable field conditions (weather, temperature etc.). The
water content shall be the minimum necessary for proper placement and when Type I or II
cement is used shall not exceed a water-cement ration of 0.45.
The water content required for Type III cement shall be established for a particular brand
based on tests.

Page 1033
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

The Engineer in accordance with the U.S. Crops of Engineers Method CRD-C79 may
determine the pumpability of the grout. When this method is used, the efflux time of the
grout sample immediately after mixing shall not be less than 11 seconds. The flow cone
test does not apply to grout which incorporates a thixotropic additive.

1003.6.5 Injection of Grout:

All grout and high-point vent openings shall be open when grouting starts. Grout shall be
allowed to flow from the first vent after the inlet pipe until any residual flushing water or
entrapped air has been removed, at which time the vent should be capped or otherwise
closed. Remaining vents shall be closed in sequence in the same manner.
The pumping pressure at the tendon inlet shall not exceed 1.7 N/mm2 (250 psi).
If the actual grouting pressure exceeds the maximum recommended pumping pressure,
grout may be injected at any vent that has been, or is ready to be capped as long as a
one-way flow of grout is maintained. If this procedure is used, the vent which is to be
used for injection shall be fitted with a positive shutoff.
When one-way flow of grout cannot be maintained, the grout shall be immediately flushed
out of the duct with water.
Grout shall be pumped through the duct and continuously wasted at the outlet pipe until
no visible slugs of water or air are ejected and the efflux time of the ejected grout, as
measured by a flow cone test, if used, is not less than that of the injected grout. To
ensure that the tendon remains filled with grout, the outlet shall then be closed and the
pumping pressure allowed to build to a minimum of 0.5 N/mm2 (75 psi) before the inlet
vent is closed. Plugs, caps or valves thus required shall not be removed or opened until
the grout has set.

1003.6.6 Temperature Considerations:

When temperatures are below 0oC, duct shall be kept free of water to avoid damage due
to freezing.
The temperature of the concrete shall be 1.7oC or higher from the time of grouting until
job cured 50 mm cubes of grout reach a minimum compressive strength of 5.5 N/mm2
(800 Psi)
Grout shall not be above 32oC during mixing or pumping. If necessary, the mixing water
shall be cooled.

1003.7. TRANSPORTATION, STORAGE AND ERECTION OF UNITS:

Precast concrete I girders shall be constructed as Cast in situ over the Coffer Dam
supported on the Pier Caps. Hence, any transportation, storage and erection shall not be
required. The bottom shuttering shall not allowed to open until gain the strength to sustain
the dead load and an approval shall be required from Engineer for such operation.

1003.8.QUALITY CONTROL

The specifications given hereunder shall be strictly followed for quality assurance of
prestress concrete works.

1003.8.1 Prestressing:

a) In all methods of tensioning, the stress induced in the tendons shall be determined
by measurement of elongation and also independently by direct measurement of
force using a pressure gauge or other means. The two determinations shall check

Page 1034
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

each other and the theoretical values within a tolerance of 3%.


b) Calculations for elongations and gauge readings must include appropriate
allowances for frictions, strand wire slippage and other factors as applicable.
c) Wire failure in tendons: Failure of wires in a post tensioning tendon is acceptable
provided the total area of wire failure is not more than 2 percent of the total area of
tendon in any member and also provided the Engineer is satisfied that the failure is
not symptomatic of more extensive distress condition.
If the total area failure exceeds 2%, representative samples from the whole batch
shall be got tested again. The high tensile steel shall be used further, only if the test
results are found satisfactory.
d) Prior to stringing of strands, bottom forms shall be inspected for cleanliness and
accuracy of alignment. Form surfaces to be in contact with concrete must be
treated with an effective release agent. Special care must be exercised to prevent
contamination of strands from release agents grease or other coatings.
e) The alignment and position of ducts within the member is critical. Short kinks and
wobbles shall be avoided. The trajectory of ducts shall not depart from the curve or
straight lines shown in the approved drawing by more than 1 in 240. The cable
position shall not deviate by more than 5mm from the designed trajectory vertically.
The area and alignment of ducts shall be such that tendons are free to move within
them and there shall be sufficient area left out to permit free passage of grout. The
inside cross sectional area of the duct shall be at least twice the net area of the
prestressing steel.
f) Schedule and sequence of tensioning tendons shall be as shown in the drawings.
g) The rate of applications of load shall be in accordance with manufacturer's
recommended procedure for post tensioning.
Slip must be measured at each end and the extension for the total length.
h) Anchorage: Anchorage devices for all posts tensioning systems must be aligned
with the direction of the axes of the tendons at the point attachment. Concrete
surfaces, against which the anchorage devices bear, must be normal to this line of
direction. Accurate measurement of anchorage losses due to slippage or other
causes shall be made and compared with the assumed losses shown in the post
tensioning schedule and when necessary, adjustments or corrections shall be made
in the operation.

1003.8.2 Cracking:

The principal objective of prestressing is the application of sufficient forces to concrete so


that members can be cast and placed in service without cracks. Some hair line cracks
which may form during casting or curing, if superficial, have no detrimental effect, on the
structural capacity of member. However to prevent any possible corrosion through hair
cracks deterioration of concrete suitable surface treatment approved by the Engineer
shall be given to the exposed surface.
The following precautions shall be taken by contractor to avoid cracking.
i) Ensure proper curing
ii) Release side forms as soon as practicable
iii) Use hoop steel around tendons near ends of beams
iv) Handle only from designated pick up points
v) Take adequate care during storage, transportation and reaction.

1003.8.3 Inspection and Records:

In general, the scope of inspections to be performed in prestressing work shall include the
following:
i) Identification examination acceptance and laboratory testing of materials.
ii) Inspection and recording of tensioning.

Page 1035
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

iii) Inspecting of beds and forms prior to concreting


iv) Checking of dimensions of members, position of tendons, reinforcing steel, other
incorporated material, opening, blackout, etc.
v) Continual inspection of batching, mixing, converting, placing, compacting, finishing
and curing of concrete.
vi) Preparation of concrete specimens for tests and performing of tests for slump, air
content, cube strength etc.
vii) General observations of casting site, equipment, working conditions, weather and
other items affecting product.
viii) final inspection of finished member.

1003.8.4 Record Keeping:

In order to establish evidence of proper manufacture and quality of prestressed concrete


members, a system of records as mentioned below shall be maintained by the contractor.
Two copies of the records shall be made and one copy duly signed by the contractor shall
be handed over to the Engineer.

i) Each prestressed concrete member shall be identified by bed and date cast and an
identification number which should be referenced to tensioning records, concreting
records, cube strength records, keeping these records shall be the responsibility of
the contractor.
ii) Submission of certified test reports for materials such as high tensile steel brought
by the contractor is the responsibility of the contractor. These reports shall show
that the materials comply with the applicable specifications.
iii) An accurate record of tensioning operation shall be kept. This record shall include,
but not be limited to the following:
a) Date of tensioning.
b) Casting identification.
c) Description, identification and number of members.
d) Manufacturer, size and class of tendon.
e) Identification of jacking equipment.
f) The actual net elongation of each tendon with allowance made for elastic
shortening of member.
g) Data on and date of grouting.
h) Any unforeseen problems encountered during tensioning such as wire
breakage, excessive slippage or other factors having an influence on the net
stress.
iv) Records of concrete operation and test shall be kept so that the following data will
be recorded for each member or each group of members cast on one bed.
a) Date, time and duration of casting.
b) Mix proportion.
c) Mixing water corrections.
d) Identification of casting bed and members.
e) Cube identification.
f) Ambient temperature, weather condition and concrete temperature.
g) Slump.
h) Method and duration of steam curing, if proposed.
i) Strength at prestressing.
j) 28 days cube strength.
v) All jacking and load measuring equipment shall be calibrated to the satisfaction of
the Engineer. Calibration data shall shown the following:
a) Date of calibration.
b) Agency or laboratory performing calibration.
c) Method of calibration.

Page 1036
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

d) A curve showing the full range of calibration with gauge readings plotted
against actual load.

1003.8.5 Dimensional Tolerance

The permissible dimensional tolerances are as given below:

a) In the length of member + 20 mm; - 20 mm


b) Flange width + 10 mm; - 10 mm
c) Depth + 10 mm
d) Flange thickness + 8 mm; - 4 mm
e) Web thickness + 8 mm

f) Camber deviation from design camber + 20 mm; - 20 mm


g) Position of tendons (in vertical plane) + 5 mm; - 5 mm
h) Bottom width + 10 mm; - 10 mm
i) Bottom thickness + 8 mm; - 4 mm
j) Position of handling devices + 150 mm; - 150 mm
k) Squareness of alignments (vertical + 10 mm
and horizontal alignment) - 10 mm
Tolerances against items (a), (j) and (k) are for 50 m lengths. For other lengths they shall
be proportional.
The contractor shall ensure the dimensions of the member within the above tolerances.
In case of PSC members not complying with the dimensional requirements within the
tolerances, remedial measures as required by the Engineer shall be carried out. If the
measures as required by the Engineer are not achieved the PSC member is liable to be
rejected.

1003.9. SAFETY IN CONSTRUCTION:

Detailed guidelines for safety in construction of prestressed Concrete Bridge Works is


included in section 3.19 of these specifications. The contractor shall strictly follow these
guidelines and as directed by the Engineer without limiting his responsibility against
safety of structures and construction personnel.

1003.10.MEASUREMENT:

High tensile tendons used in prestressed concrete shall be measured as the length of
tendons actually used in finished work. From the length so measured its weight shall be
calculated in tonnes.

Anchorage devices, ducts or metal sheath spacers and grouting shall be deemed to be
included in the item of high tensile steel and shall not be measured separately.

1003.11. PAYMENT:

The unit rate for high tensile steel shall cover the cost of all materials, labour, tools and
plant required for fixing, placing, tensioning, anchoring, and grouting the high tensile steel
in the pre-stressed cement concrete as shown on the drawings and as per clause of
specification. The cost of anchoring devices and ducts or metal sheath and grouting shall
also be included in this rate.

Page 1037
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Pay Item Description Unit of


No. Measurement
1003 Providing and laying H.T. tendons, of required Tonne
diameter in fabricated sheaths including necessary
joineries of approved quality including supplying,
fitting, fixing in position, spacers, anchorage's etc.,
stressing the cables with standard jacks complete
including grouting the duct with cement slurry all
as per drawing and specification and to the
Engineer direction.

1004 PILE FOUNDATIONS FOR STRUCTURES

1004.1 a) Description

Piling shall conform in all respect with the principles contained in BS 8004. Unless
otherwise stated, concrete, reinforcement and formwork shall be in accordance with the
requirements in specifications on the concrete structures. In the event of that the
provisions of other specifications clauses cause ambiguity or conflict with the
requirements of these specifications clauses, the later shall take precedence unless
otherwise approved by the Engineer.

Add to end of this Sub Section the followings :-

Piles through water and soft upper soil layers shall be provided with a permanent steel
casing if shown on the Drawings.

The pile boring shall be carried out using a temporary steel casing bored to the pile toe or
to a level approved by the Engineer if permanent steel casing not specified. The
temporary casing shall be withdrawn. Under certain circumstances the Contractor may be
permitted to bore all or part of the pile without casing under water or use drilling fluid to
stabilise the borehole as referred to in Sub Section 1004.2.

The piles shall be concreted and reinforced to resist pile loads and horizontal forces on
the pile caps according to the Drawings and these Specifications.

1004.1 .1 Coffer Dam/ Artificial Island

DESCRIPTION:

This work shall consist of the construction, material excavation within, dewatering,
maintenance and removal of cofferdams in accordance with the specifications at locations
designated in the Plans or in the Contract.

The work will be classified as follows:

(a) Cofferdam. This item shall consist of providing a method for the purpose of
constructing, in the dry, a specific foundation or other component of a structure in
accordance with Contract requirements. This may involve the design,
construction, maintenance, and removal of a watertight structure or may involve
alternate methods of de-watering and stabilizing the specific site. Construction of
foundation seals per Contract or as required per Contractor plans and schedule of

Page 1038
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

operations is also within the scope of work for the Cofferdam item. The Contractor
shall obtain any and all necessary permits or clearances for alternate methods.

A cofferdam may have only two or three sides depending upon the particular
location and the Contractor’s design.

Cofferdam Excavation, Earth. This item shall consist of all material excavated
within the pay limits as set forth in these specifications or indicated on the Plans
except solid rock, mortared stone masonry, concrete, and boulders measuring
0.5cubic meters (yards) or more.

Cofferdam Excavation, Rock. This item shall consist of all solid rock materials
excavated within the pay limits as set forth in these specifications or indicated on
the Plans, including all solid rock, mortared stone masonry, concrete, and
boulders measuring 0.5 cubic meters (yards) or more.

MATERIALS:

Gravel/ soil may be used for the construction of cofferdam as per design and approved by
Engineer.

Concrete used in a cofferdam foundation seal shall have a minimum 28 day compressive
strength of 20 MPa (3000 psi) and shall conform to the requirements of Section 1001.

GENERAL CONSTRUCTION REQUIREMENTS:

When the cast insitu piles are to be pitched in water, an earthen/sand Coffer dam where
possible shall be constructed raising the site of work, so as to make the construction in
the dry. The area of Cofferdam/island in these cases should be sufficient enough to allow
adequate working space, at least 2 times the outer dimension of the pile cap. The soil
forming the island shall be such as not to impede the sinking of the casing. Cofferdam/
Islands shall be protected against scour and the top level shall be sufficiently above the
anticipated water level during the construction period so that it is safe against wave or
tidal action. The top surface of the island shall be adequately leveled and casing placed.
The Contractor shall construct the diversion channel, if found necessary, from site
conditions. In case of any deep or fast flowing water where an island may not be possible,
the casing may be, floated and lowered in its final position with the help of necessary
equipment.

The locations and elevations for excavation shall be as indicated on the Plans. The
Engineer may order to removal of poor foundation material below the normal designated
elevation and replacement with an approved material.

All suitable excess excavated material shall be used in the formation of embankments as
indicated on the Plans, or as directed by the Engineer. The material shall be hauled and
disposed of with no additional compensation to the Contractor.

PRESERVATION OF CHANNEL:

Unless otherwise indicated on the Plans or ordered by the Engineer, the Contractor, in
performing the excavation, shall confine excavating operations to the site of the proposed
structure and to the limits of the cofferdam. The natural stream bed shall not be disturbed
without permission of the Engineer.

COFFERDAMS:

Page 1039
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

The Contractor shall prepare detailed plans and as schedule of operations for each
cofferdam specified in the Contract. Unless otherwise noted in the Contract Documents,
the design and structural details of the cofferdam structure or alternative dewatering and
stabilizing method shall be signed, stamped, and dated by a qualified Professional
Engineer (Structural or Civil) registered in the Institute of Engineers.

The Professional Engineer is responsible for ensuring that the proposed cofferdam meets
the following criteria:

(a) the design is structurally stable for all conditions to been countered
(e.g., soils, water, forces, and loadings);

(b) the design and details conform with the Contract and the applicable AASHTO
requirements in the “Standard Specifications for Highway Bridges”;

(c) the design and details are in conformance with applicable safety codes;

(d) the size and shape are adequate to construct the foundation and structural
components specified;

(e) the cofferdam is adequately watertight for proper performance of the work;
and

(f) any foundation seal is adequate to achieve its design function


(g) Cofferdam edges should be erosion free and adequate protected by Sand
filled gunny sacs
(h) Cofferdam should be constructed as per sequences of the piling construction
activities and guidance by Engineer.

One copy of the plans and schedule of operations shall be submitted to the Project
Manager for UNOPS use.

The submittal shall include plan, elevation and section details indicating the following:

(a) the waterway;

(b) information regarding the cofferdam and any foundation seal indicate if a seal
is required to ensure the structural integrity of the cofferdam during dewatering
and foundation construction and inspection;

(c) substructure location;

(d) dimensions of any temporary restrictions that are to be placed in the


waterway, e.g. barges, lines, earth dams, causeways, temporary diversion
channels and access bridging;

(e) the location, dimensions, clearances, and other relevant information for any
temporary scaffolding or netting;

(f) dewatered heads, taking into consideration fluctuations of water levels;

(g) details for screening, pumping and filtering discharge;

(h) a statement as to whether or not any equipment will be removed at night; and

Page 1040
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

(i) a schedule or sequence of operations - include placement of the foundation


seal, time from placement to dewatering, and foundation construction and
inspection.

The Contractor will be responsible for performing the work in accordance with the
submitted details and schedule of operations. All welding shall be performed in
accordance with BS code.

Cofferdam construction shall conform to AASHTO Standard Specifications for Highway


and Bridge Construction, Division II, Section 1.4.

Cofferdams shall be constructed so as to protect freshly placed concrete against damage


from sudden rising of the water level and to prevent damage to the foundation or other
structural component by erosion. The cofferdam shall be constructed so that no timber,
bracing, or forms will extend into the foundation or other structural component.

In the event the Contractor elects to place fill material in the stream to facilitate access to,
or be part of, a cofferdam operation, it shall be clean stone fill.

PUMPING:

Pumping from or dewatering of the interior of any cofferdam enclosure shall be performed
so that disturbance of the subsoil or freshly placed concrete will not occur. Dewatering of
a sealed cofferdam will be in conformance with the Contractor’s sequence or schedule of
operations. Pumping during the construction of a foundation or other structural
component shall be from a suitable sump separated from the concrete work.

INSPECTION OF FOUNDATION PIT:

Immediately following the completion of each foundation pit, the Contractor shall notify the
Engineer, who shall approve the depth of the pit and the nature of the foundation before
the placement of the concrete.

MEASUREMENT.

The quantity to be measured for payment will be on a lump sum basis for each cofferdam
segments specified on the Plans, profile or in the Contract.

PAYMENT:

The accepted quantity of Cofferdam will be paid for at the Contract lump sum price, which
price shall be full compensation for the preparation of detailed plans and schedule of
operations, performing the work specified, and the furnishing of all labor, tools,
equipment, materials, and incidentals necessary to complete the work, including the cost
of altering the cofferdam, foundation seals, sheeting, bracing, dewatering, installation and
maintenance of siltation and sedimentation control measures for treating cofferdam
discharge, incidentals necessary for properly constructing the foundation or structural
component, maintaining the cofferdam in a dewatered condition, and removing the
cofferdam when no longer required.

Payment for Cofferdam will be made as follows:

A payment of 75% of the lump sum bid price will be made when excavation within the limits of the
structural unit is completed, and the cofferdam has been successfully dewatered.

Pay item Description Pay unit

Page 1041
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

1004.1.1 (1) Lump sum payment for Cofferdam construction for Lump sum-1
Segment-1 including supply of all materials, tools,
equipments, maintain the scour free & dry
conditions during construction period etc. complete
as per the design and drawing and profile and
satisfaction of Engineer. The payments shall be
Segment length x Lump sum of 75%
1004.1.1 (2) Lump sum payment for Cofferdam construction for Lump sum-2
Segment-2 including supply of all materials, tools,
equipments, maintain the scour free & dry
conditions during construction period etc. complete
as per the design and drawing and profile and
satisfaction of Engineer. The payments shall be
Segment length x Lump sum of 75%
1004.1.1 (3) Lump sum payment for Cofferdam construction for Lump sum-3
Segment-3 including supply of all materials, tools,
equipments, maintain the scour free & dry
conditions during construction period etc. complete
as per the design and drawing and profile and
satisfaction of Engineer. The payments shall be
Segment length x Lump sum of 75%
1004.1.1 (4) The remaining 25% of the lump sum bid price will be Lump sum-4
made when the cofferdam has been completely
removed and excavated to the original position of
the river bed before cofferdam constructed.
However, in the event the Engineer (by written
order) requires a Cofferdam to be left in place, the
Contractor will be paid only for the documented cost
of the cofferdam material left in place excluding any
costs associated with the foundation seal.

1004.2 Materials

Add to additional Section as follows :-

(f) Drilling Fluid

The following sub section shall be complied with if bentonite mud is used to stabilise the
boreholes:

i) Supply

The Contractor shall obtain a certificate from the manufacturer of the bentonite powder,
showing the properties of the consignment delivered to the site. This certificate shall be
made available to the Engineer on request. The properties to be given by the

Page 1042
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

manufacturer are the apparent viscosity range (in centipoises) and the gel strength range
for solids in water.

Any other material proposed by the Contractor for the drilling fluid shall be approved by
the Engineer.

ii) Mixing

Bentonite and any other material shall be mixed thoroughly with clean water to make a
suspension which shall maintain the stability of the pile excavation for the period
necessary to place concrete and complete construction.

Where saline or chemically contaminated groundwater occurs, special precautions shall


be taken to modify the bentonite in fresh water so as to render it suitable in all respects
for the construction of piles.

iii) Tests

The frequency of testing drilling fluid and the method and procedure of sampling shall be
proposed by the Contractor and approved by the Engineer prior to the commencement of
the work. The frequency may subsequently be varied as required depending on the
consistency of the results obtained. The control tests shall cover the determination of
density, viscosity, gel strength and pH values.

The Contractor shall supply all equipment and experienced operators required to carry
out tests on the drilling mud. No additional payment shall be made for these tests which
shall be considered as an essential part of the drilling operations.

(g) Steel Casing

This part of the Specifications only deals with the permanent steel casing. For steel
casing used during boring of the pile see Section 1004.5, Construction Methods. When
permanent steel casing is shown on the Drawings, the steel shall conform to the AASHTO
Standard Specification M 183-79 (ASTM A36) or equivalent.

The minimum thickness of the permanent steel casing shall be 10 mm. The minimum
length shall be from 100 mm above the bottom of the pile cap to 5 metre under the
riverbed or into firm strata. If the permanent casing is used in the boring operation or if the
handling and transport require a greater thickness to avoid deformation or buckling, the
increase in thickness shall be provided by the Contractor at his own expense.

The steel casing shall be furnished in appropriate lengths and the joints shall be approved
by the Engineer.

The casing shall be handled and stored in a manner that shall prevent buckling and other
deformation as well as accumulation of dirt, oil and paint. When placed in the work it shall
be free from dirt, oil, grease, paint, mill scale and loose or thick rust. The outside surface
of the permanent casing of piles to river piers, for the depth indicated on the Drawings
from the underside of the pile cap shall receive two coats of anti-corrosion tar type paint.
The paint shall be approved by the Engineer and its application shall follow the
manufacturer's instructions.

(h) Length of Piles

The basic length of pile and its diameter is shown on drawings. The final length shall be

Page 1043
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

decided by the Engineer on the basis of study of the results of initial load test on piles and
on the basis of actually boring data observed on site for individual pile. Test piles shall be
installed as directed by the Engineer at selected locations at each bridge site.

1004.3 Manufacturing and protective requirements for piles

No change

1004.4 Construction requirements of driven piles

No change

1004.5 Construction requirements of cast insitu piles (bored piles)

Delete Sub Section and subslitute with the following:-

1004.5.1 CONSTRUCTION METHOD

a) General

The Contractor shall demonstrate to the satisfaction of the Engineer that his proposed
construction methods for the piles do not result in the pile shafts being weakened by
contamination of the concrete, by sectional reduction, by washing out of cement, by
breaking during pulling of temporary casings or in any other way, including the
construction of neighbouring piles.

i) Assumed Procedure

The following construction procedure has been assumed in the tender design. The final
construction procedure shall be as approved by the Engineer prior to commencing piling
operations.

1. Place permanent steel casing, if required, in position and embed casing toe into
river bed or firm strata. If no permanent steel casing is specified a sufficient length
of temporary steel casing shall be used to stabilise the upper part of the borehole.

2. Bore and excavate inside the steel casing down to casing toe level, or to a level
approved, and continue excavation to final pile tip level using either temporary
casing under water, or using drilling mud. The fluid level inside casings shall at all
times be at least 2 metres higher than outside the casings.

3. Carefully clean up all mud or sedimentation from the bottom of borehole.

4. Place reinforcement cage, inspection pipes etc.

5. Concrete continuously under water, or drilling fluid, by use of the tremie method.

6. Withdraw the temporary boring casing concurrently with concreting to the


instructed level.

7. After hardening, break out the top section of the concrete pile to reach sound
concrete.

ii) Approval of Construction Method

Page 1044
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

In the tender, the Contractor shall describe the construction method he proposes,
including name of proposed Sub-contractor (if any), information on boring equipment,
materials, and methods of work and control of quality.

After the Contract has been awarded, the Contractor shall prepare a detailed programme
and establish a procedure for the pile construction. The detailed programme shall contain
all required information on materials, equipment, methods of work etc. and be approved in
writing by the Engineer. Such approval shall not, however, relieve the Contractor of his
responsibilities for pile construction. The import of any boring equipment or materials by
the Contractor, before he has received the Engineer’s approval of proposed construction
methods, shall be at the Contractor’s risk.

b) Setting Out Piles

The contractor shall be required to employ an approved Licensed Surveyor who will set
up the positions of the piles as shown in the pile layout plans of the detail design. The
contractor will be responsible for the accuracy of location and positioning of each pile.
Any errors in setting out and any consequential loss to the Employer will be made good
by the contractor to the satisfaction of the Engineer.

The contractor shall preserve the pegs set out by the Surveyor. Should any peg be
displaced or lost it must be replaced by a Licensed Surveyor to the approval of the
Engineer. Upon completion of all piling works, the contractor shall produce as-Built
drawings showing the positions of all piles as installed. The positions of piles shall be
verified by a Licensed Surveyor.

The Contractor shall check the casing position for each pile during and immediately after
placing the casing, and agree it with the Engineer.

c) Diameter of Piles

The diameter of a pile shall be not less than the specified diameter.

d) Tolerances

Position: The pile heads shall be positioned as shown on the Drawings within a maximum
deviation of 75 mm in either direction from its design position.

Verticality: For Bored cast-in-situ the maximum permitted deviation of the finished pile
from the vertical at any level is 1 in 100. The contractor shall demonstrate to the
satisfaction of Engineer the pile verticality in within the allowable tolerance.

Correction: Should piles be installed outside these tolerances affecting the design of the
structures, the contractor shall propose remedial design and carry out immediate remedial
measure to the approval of the Engineer. If any addition fund is required and shall be
borne by Contractor.

The Contractor shall provide suitable equipment, such as an inverted pendulum, to check
the verticality of the boreholes at intervals during drilling and prior to concreting.

e) Person in Charge

The piling work is to be carried out by full time operators and supervisory staff who must
be experienced in the installation of the proposed type of piles.

Page 1045
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

The contractor shall submit to the Engineer for approval, written evidence to show that the
persons who will be engaged in the works have such experience.

f) Pilling Equipments and Accessories

The equipment and accessories must be capable of safely, speedily and efficiently
installing piles to the design requirements at the project site. Sufficient units of
equipments and accessories must be provided to keep to the agreed construction
schedule.

g) Sequence of Installation of working piles

The Engineer reserves the absolute right and the Contractor shall recognise such right to
direct the installation of working piles in any sequences the Engineer deems necessary
for the satisfactory completion of the works.

h) Forcible correction Not permitted

Where piles have not been positioned within the specified limits no method of forcible
correction will be permitted.

e) Boring

i) Methods

Contractor shall carry out the works in accordance with a method statement which has
been approved the Engineer. This method statement shall include inter dia., length of
temporary casing, details of the constituent materials of any drilling fluid used for
stabilisation, the method of inspection, details of concrete mix, concreting method, the
minimum time between the completion of one pile and commencement of the next and
the pattern of construction.

Unless otherwise described in the specifications, reinforcement and concrete shall comply
with the requirements in specifications on concrete for structures. The contractor shall
ensure that damages dose not occur to completed piles through his method of working.
The contractor shall submit to the Engineer a pile installation programme. The proposed
sequences and timing of the pile installation shall be such that the installation works shall
not cause any damages to adjacent piles. Piling works shall not commence until approval
of the engineer has been obtained.

Method of excavation shall be proposed by the Contractor and approved by the Engineer.
Water or air jetting for boring of the piles shall not be allowed.

ii) Boring Near Recently Cast Piles

Piles shall not be bored so close to other piles which have recently been cast and which
contain workable or unset concrete so that a flow of concrete could be induced from or
damage caused to any of the piles. Boring and excavation for a pile shall not be
commenced until 24 hours after completion of any pile within a radius of 6 metres, centre
to centre.

iii) Stability of bore by Temporary Casing method

Page 1046
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Where the use of a temporary casing is required to maintain the stability of a bore, the
bottom of casing shall be kept a minimum of one (1) meter or more below the unstable
strata to prevent the inflow of soil and formation of cavities in the surrounding ground.
Temporary casing of approved quality or an approved alternative method shall be used to
maintain the stability of pile excavations, which might otherwise collapse. Temporary
casings shall be free from significant distortion. They shall be of uniform cross-section
throughout each continuous length. During concreting they shall be free from internal
projections and encrusted concrete which might prevent the proper formation of piles. If
temporary casings are damaged during installation in a manner which prevents the proper
formation of the pile, such casings shall be with drawn from the bore before concrete
placed, repaired if necessary, or other action taken as may be approved to continue the
construction of the pile.

iv) Stability of Pile Excavation Using Drilling Fluid

It is held that the Contractor has allowed in the unit rate of the pile for the implementation
of all necessary measures, including the provision of all materials, labour and plant, for
maintaining the stability of sides of boreholes during bored pile installation and successful
completion of the piles. The Contractor shall submit his proposed methods for agreement
prior to commencement of boring operations. Irrespective of the presence of ground
water, the sides of all boreholes shall be kept intact and no loose material shall be
permitted to fall into the bottom of the boreholes. The Contractor’s boring equipment shall
be able to sink a steel casing to support the sides of all boring.

If the sides of boreholes are found to be not table, temporary steel casing shall be driven
into stable stratum. The borehole shall be filled with drilling fluid (Bentonite) to a level
sufficiently to stabilise the boreholes.

If ground water is found in any hole in sufficient quantity or gushing out as to affect boring
operations or excavations and removal of soil from the boreholes, or the sides of
boreholes collapse, then a steel casing of appropriate size an length in conjunction with
stabilising fluid or any other alternative of sufficient strength shall be used to support the
sides of the borehole and permit boring operations to proceed smoothly and safely. The
proposed drilling fluid mix must be submitted to the Engineer for approval.

Excavation should not be exposed to the atmosphere longer than is necessary and shall
be covered at all times when work is in progress. Pile excavation shall be cast within 24
hours unless otherwise agreed by the Engineer.

In the event of rapid loss of drilling fluid from the borehole excavation and caused
instability of bore, the excavation shall be backfilled with out delay or other appropriate
and approved remedial measures taken by the Contractor like installing temporary casing
prior to resuming boring at that location.

v) Disposal of Excavated Material

No excavated material shall be dumped into the river or any connecting waterway without
the written approval of the Engineer. Excavated material shall be removed from site and
dumped either beyond areas affected by dredging, or taken to the Contractors approved
dumping areas on land. The Contractor shall be fully responsible for costs involved in
removing the excavated material to spoil. In disposal of unwanted drilling fluid, the
Contractor shall comply with the relevant government regulations and propose a proper
disposal method to be approved by Engineer.

vi) Pumping from Boreholes

Page 1047
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Pumping from a borehole shall not be permitted unless a casing has been placed into a
stable stratum which prevents the flow of water from other strata in significant quantities
into the boring, or unless it can be shown that pumping will not have a detrimental effect
on the surrounding soil or property.

vii) Obstructions

Where boulders or other obstructions render it impossible to bore the pile, excavation
operations inside pile casing as directed by the Engineer shall be carried out to remove
obstructions and the Contractor shall be reimbursed for such operations only when the
largest dimension of the obstruction exceeds 500 mm and the obstruction is found more
than 2 metres below river bed. This reimbursement shall be paid either by day work basis
or actual expenditures depend on possible lower cost. A log sheet for labour and
equipments used must be recorded to claim such reimbursements.

viii) Unexpected Ground Conditions

The Contractor shall report immediately to the Engineer any circumstances which indicate
that in the Contractor's opinion the ground conditions differ from those expected by him
from his interpretation of the site investigation reports.

ix) Boring Records

A record of all piles installed shall be kept by the contractor and signed by the Engineer
representative/Engineer and a copy of the record of the work done each day shall be
given to the Engineer within 24 hours. The form of record shall first be approved by the
Engineer before piling works commence. Any comments by the Engineer shall be
incorporated into the form.

All unexpected boring or installation conditions shall be noted in the records.

Two (2) bound sets of collated and certified (by the contractor’s Project Engineer) piling
records of all piles shall be submitted by the contractor to the Engineer after completion of
the piling works.

During the boring of the pile, the Contractor shall compile a 'boring log' indicating depths
and types of the various soil layers encountered. Disturbed samples shall be submitted to
the Engineer as requested. The Contractor shall allow for carrying out sampling and tests
to check soil strengths as required by the Engineer.

Submission of the pile record shall be as follows:


1. Name of supervisor
2. Pile forming equipment including Rig no.
3. Length, Diameter and reference number of the borehole
4. Existing ground level
5. Cut-off level, rock level (Hard Rock only-RQD 75%), pile toe level
6. Length of pile
7. Log of materials encountered and level of change in strata and where boring stops
8. Speed of boring through soil or Rock shall be recorded for every meter of drilling
9. Depth bored and detail inclination or displacement of the pile during boring and
date of inspection
10. Length of reinforcement casing, reinforcement details
11. Water table below ground level
12. Levels where seepage occurs

Page 1048
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

13. Results of tests on soils


14. Results of tests concrete cubes (Slump tests)
15. Length of Temporary casing if used
16. Date and actual volume of concrete placed in piles, time starts and complete
17. Concrete level after each truck of concrete
18. Details of all inspections
19. Details of all obstructions, delays and other interruptions
20. Signature of Resident Engineer or his representative
21. Weather condition
22. Method of casing (Wet/dry tremie)
23. Date and time boring start and complete and speed of drilling
24. Type of stabilising fluid
25. Collapse of bore or loss of drilling fluid
26. Cavities or Slump zone encountered.

x) Final Pile Toe Level

The final pile toe level shall be as indicated on the Drawing or as instructed by the
Engineer after due consideration of the Contractor's proposals, boring logs and test
results. The final toe level of other piles may subsequently be altered according to the
results of the test loadings detailed in Sub Section B (Pile TEST LOADING) of section
1004.5.

xi) Inspection and Cleaning Bottom of Excavation

Where practicable, all pile excavations shall be inspected for their full length before
concreting. The Contractor shall provide all the apparatus necessary for the inspection.

Inspection shall be carried out either from the ground level or below ground level at the
sole discretion of the Engineer prior to concrete being placed in the borehole. For such
inspection to be carried out safely, the Contractor shall provide all facilities and
assistance to enable the said inspection to be done. In the course of inspection any loose
or soft material in the borehole which is likely to affect the performance of the pile shall be
removed to the satisfaction of the Engineer.

In the case of inspection from ground level, the base of the boring shall be inspected by
approved method for wet hole and by means of light for dry hole to ensure that all loose,
disturbed and/or remoulded soil removed and that the sides of the boring will remain
stable during the subsequent concrete operations. The verticality and position of the
boring shall be checked to ensure that they meet the specified tolerances.

Inspection below ground level shall be carried out for the piles with shafts of 760 mm
diameter and above. For this purpose the Contractor shall, apart from providing other
safety measures, also provide the required facilities such as an approved type of a steel
safety case with an air-line, lifting cable and hoists, gas detector, lights etc. to enable
descent into and ascent from the borehole to be carried out safely with out any danger to
life. In this regard the safety precautions described in BS 8008:1996 “Safety precautions
and procedures for the construction and descent of machine-bored shafts for piling and
other purpose” shall generally be followed, unless otherwise directed by Engineer.

The time between final excavation and bottom cleaning and the start of concreting shall
be kept as short as possible and shall not exceed 6 hours. To achieve this, the final 2
metres of excavation shall not start until all preparations for cleaning, reinforcing and
concreting are finished. In case of unexpected delay the Contractor shall dump sand or
gravel in the bore to 2 metres above toe level. On completion of the drilling an interval is

Page 1049
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

required, to allow the fine materials to settle (15 minutes unless otherwise approved by
the Engineer). Thereafter the bottom of the excavation shall be carefully cleaned of mud,
sedimentation and other soft material by an approved method.

The Contractor shall show, to the satisfaction of the Engineer, that the bottom of the
excavation is clean. Sedimentation tests shall be carried out by the Contractor in the
presence of the Engineer.

If boring without casing, the diameter of the boring hole for a representative number of
piles shall be measured by calliper prior to the placing of concrete. The verticality of
boreholes will be checked as directed by the Engineer. These measurements shall be
done by the Contractor using approved equipment and no reimbursement shall be made.

xii) Rock Coring/Boring

Rock boring is the part of the contractor activities during piling works. Rock coring shall
means of coring of sound bedrock using a coring bucket or approved method. The used
of Chisel shall not be permitted. Coring of rock other than two items specified below shall
not be considered as coring in rock and only be considered as boring in soil.

• Rock socket length


• Cavity roof (in limestone formation)

Coring of inclined rock surface, limestone pinnacles, cavities and soil below boulder/
floater shall be considered as boring in soil.

Socket length shall be measured from the flattened horizontal bedrock surface. This flat
horizontal surface shall be probe using Kelly bar or steel bar at a minimum of five
positions over the borehole to confirm sound bedrock for socketing. The length of
socketing shall be considered from while Rock Quality Designation (RQD) value is more
than 75% in incremental fashion. Unless otherwise shall be considered boring in soil. The
socekting minimum length shall be 1 (One) times Diameter of Pile. Contractor shall
arrange for testing the RQD value for the confirmation to the design requirement.

While socketing/boring can not accomplish for 1x D ( 1 times diameter of pile) or any
other reason, then contractor required to arrange for Dowelling to fix the pile toe. A
separate unit rate shall be considered.

Engineer may request for rock boring more than 1x D while the pile penetration depth
becomes less than design length or any other reason due to unforeseen soil strata
changes with out change of agreed unit rate.

xiii) Cleaning out

Upon completion of boring the excavation shall be cleaned of all loose, disturbed and or
remoulded soil and sediment soil to expose a firm base of undisturbed material using a
suitable and effective method to be approved by Engineer.

xiv) Continuity of construction

A pile constructed in a stable soil with out the use of temporary casing or other support
shall be bored and concreted with out prolonged delay to ensure that the soil
characteristics are not significantly altered.

xv) Surface water

Page 1050
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

All boreholes shall be protected from the possibility of any surface water entering the hole
from time to tiem and until the hole completed and ready for concreting.

Xvi) Drilling fluid and Soil Tests

Minimum frequencies of testing are as follows:

• Fresh drilling fluid


• Drilling fluid taken from the bottom of the pile before concreting
• Recycle drilling fluid taken from desending machine
• Drilling fluid left in the bored hole for more than 12 hours

The frequency of testing drilling fluid and the method and procedure of sampling shall be
proposed by the contractor and agreed by the Engineer before the commencement of the
work. The frequency may subsequently be varies with the approval of the Engineer.
Control tests for density shall be carried out daily on the drilling fluid using suitable
apparatus. The measuring device shall be calibrated to read within 0.01 g/ml. The results
shall be within the ranges as follows:

Tests for Bentonite Drilling Fluids

Propery to be measured Compliance values Test Method/Apparatus


measured at 200C
Density Less than 1.1 g/ml Mud density balance
Fluid loss Less than 40 ml 30 minutes test
Viscosity 30 to 90 seconds or Marsh Cone method
less than 20cP Fann Viscometer
Shear Strength (10 minutes 1.4-10 M/m2 or Shearometer
gel strength 4-40 N/m2 Fann Viscometer
Sand Contents Less than 5% Screen
PH 9.5 to 12 PH indicator paper stips or
electrical PH meter

Note: Where the Fann Viscometer is used, the fluid sample should be screened by 300
µm sieving before testing.
Tests for drilling fluid other than bentonite have to be approved before use.

f) Placing Reinforcement

Reinforcement shall be free from rust and mud and not be placed until inspected and
accepted. Reinforcement cages shall be sufficiently rigid to ensure that they remain at
their correct level during the lifting and placing of the concrete and the extraction of
temporary lining tubes. Reinforcement shall be maintained in its correct position during
concreting of the pile. The minimum cover to all reinforcement shall not be less than 75
mm unless stated otherwise. Concrete spacer shall be provided at every 3 meter interval,
size and minimum yield strength of reinforcement shall be as specified in the drawing.
Details by which the Contractor plans to ensure the correct cover to and position of the
reinforcement shall be approved by Engineer.

The main longitudinal reinforcement bars in piles not exceeding 12 meters in length shall
be in one continuous length unless otherwise specified. In piles longer than 12 meters
and required to be reinforced throughout their full lengths when specified, joints with

Page 1051
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

staggered laps of alternate bars will be permitted in main longitudinal bars at 12 metre
nominal intervals unless otherwise specified in the drawings. Joints of reinforcement bars
shall comply with the specific requirements of BS 8110 clause 3.12.8

The contractor shall submit for approval a method statement on the manner by which he
intends to lower reinforcement cages into pile shafts. Where tack welding is carried out on
pile reinforcement of the purpose of hoisting, such welding shall be located witin the top
100 mm of each reinforcement cage.

If required by the Engineer, reinforcement cages shall be flushed with freash water to
remove accumulated salts or other deposits immediately prior to lowering into the pile
shaft.

g) Placing Concrete

i) Approval

No concreting shall take place before the bottom of the excavation has been cleaned, the
borehole inspected and approval obtained in writing from the Engineer.

The method for placing concrete requires to be approved and conform with the following:

• The method of placing and the workability of the concrete shall be such that a
continuous monolithic concrete shaft of the full cross section is formed.

• The concrete shall be placed continuously, and without such interruption as would
allow the previously placed batch to have hardened. In this respect the Contractor
shall submit details of his contingency plans, standby plant etc. to be utilised in the
event of an equipment failure.

• The use of pumped concrete and the methods in its use shall be approved.

• The Contractor shall take all precautions in the design of the mix and placing of
the concrete to avoid arching of the concrete in a casing. No spoil, liquid or other
foreign matter shall be allowed to contaminate the concrete.

ii) Workability of Concrete

Slump measured at the time of discharge into the pile boring shall be in accordance with
the following Table

Slump
Piling Mix
Typical Conditions of Use
Workability
Minimum Range
(mm) (mm)
Placed into water-free unlined or
permanently lined bore of 600 mm
diameter or over, or where casting level
A 75 75 - 150 lies below temporary casing: reinforcement
widely spaced, leaving ample room for free
movement of concrete between bars.

Where reinforcement is not spaced widely;


B 100 100 - 200
where cut-off level of concrete is within

Page 1052
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

temporary casing; where pile bore is water-


free and the diameter is less than 600 mm.

150 or
Where concrete is to be placed by tremie
C 150 200
under water or drilling mud or by pumping

iii) Placing Concrete in Wet Hole

Immediately after the boring for the pile has been completed, approval to commence
concreting shall be sought and, when this has been obtained, concreting shall start
forthwith and continue without interruption. All concrete for cast-in-situ piles shall be
compacted to produce a dense homogeneous mass by a method agreed by the Engineer.

Concrete to be placed under water or drilling fluid shall be placed by tremie in accordance
with BS 8004 Clauses 7.4.5.4.2 and 8.2.2.3.4 and shall not be discharged freely into the
water or drilling fluid. Where discrepancies arise, the provisions of this specification shall
precedence.

Alternative methods of placing concrete such as the use of a drop bottom bucket or hose
from a concrete pump will not be accepted by the Engineer. At no stage concrete be
permitted to discharge freely into drilling fluid.

Before placing concrete, the Contractor shall ensure that there is no accumulation of silt,
other material, or heavily contaminated bentonite suspension at the base of the boring,
which could impair the free flow of concrete from the pipe of the tremie. A sample of the
bentonite suspension shall be taken from the base of the boring using an approved
sampling device. If the specific gravity of the suspension exceeds 1.25, the placing of
concrete shall not proceed. In this event the Contractor shall modify or replace the drilling
fluid to meet the requirements of this specification.

The tremie concrete pipe shall consist of a series of metal pipes with internal diameter not
less than 250mm. The receiving hopper shall have a capacity at least equal to that of the
pipe it feeds. At all times, a sufficient quantity of concrete shall be maintained within the
pipe to ensure that the pressure from the concrete exceeds that from the water or drilling
fluid. It shall be so designed that external projections are minimised, allowing the tremie to
pass through reinforcing cages without causing damage. The internal face of the pipe of
the tremie shall be free from projections.

The concrete shall be a rich coherent mix of high workability in accordance with Sub
Section 1004.2 and shall be placed in such a manner that segregation does not occur.
During and after concreting, care shall be taken to avoid damage to the concrete from
pumping and dewatering operations.

The hopper and pipe of the tremie shall be clean and watertight throughout. The pipe
shall extend to the base of the boring and a sliding plug or barrier shall be placed in the
pipe to prevent direct contact between the first charge of concrete in the pipe of the tremie
and the water or drilling fluid. The pipe shall at all times penetrate the concrete, which has
previously been placed and shall not be withdrawn from the concrete until completion of
concreting. The bottom of the tremie pipe shall be kept at least 1.5 metres under the
surface of concrete once that amount of concrete has been placed. At all times a
sufficient quantity of concrete shall be maintained within the pipe to ensure that the
pressure from it exceeds that from the water or drilling fluid. The tremie pipe shall be
withdrawn upward gently behind the concrete level, and shall not be subject to any shock

Page 1053
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

ot violent movement either in dislodging the concrete within the pipe or for any other
reason.

Concrete placement shall be halted should a delay or breakdown occur during the
concreting operation which in the opinion of the Engineer, could cause a cold joint,
entrapment of latency in the tremie concrete, or otherwise lead to defective concrete.
Before the remainder of the pile shaft can be concreted, the pile shall be dewatered and
the top surface of the tremie concrete cut back to sound concrete and cleaned of all
laitance and weak concrete. The remainder of the pile shall either be cast by tremie or in
the dry, as directed by Engineer. If this remainder work can not be carried out due to
construction difficulty, the contractor will need to construct a replacement pile. If required
to strengthen the remainder pile by H pile or any other method, the relevant cost shall be
borne by contractor.

The concrete for each pile shall be from same source. The contractor is to ensure that the
supply from whatever source (whether site-mixed or ready mixed) is of sufficient quantity
so that concrete for each pile shall be placed with out such interruption.

All holes bored shall be concreted within same day. In the event of rain, the contractor is
to provide adequate shelter to keep the hole dry and to concrete under cover.

The actual volume of concrete used for each pile must be measured with the calculated
volume required. If the differences between thse two volumes indicates a possible
necking, the Contractor shall propose and carry out appropriate tests an measures to the
approval of the Engineer to ensure the adequacy of the pile.

h) Extraction of Temporary Casing

Temporary casings shall be extracted while the concrete within them remains sufficiently
workable to ensure that the concrete is not lifted and the resultant pile is continuous and
full section. Temporary casings shall be extracted in not more than 2 hours after
concreting has completed.

When casings and lining are withdrawn as concreting proceeds, a sufficient head of
concrete shall be maintained to prevent the entry of ground water which may cause
reduction of cross section of the pile. No concrete shall be placed after bottom of the
casing or lining has been lifted above the concete. Concrete shall be placed continuously
as the casing is extracted until the desire head of concrete is obtained.

Adequate precautions shall be taken in all cases where the withdrawal of casing could
result in excess heads of water or drilling fluid. Excess pressure heads are caused by
displacemjent of water or fluid by concrete as the concrte flows into its final position
against the wall of the shaft. Precautions such as the use of two or more discontinuous
lengths of casing (double casing) shall be deemed an acceptable method of construction
in this case.

i) Workability of Concrete

The method of placing and the workability of concrete shall be such that a continuous
monolithic concrete shaft of the full cross section is formed. The method of placing shall
be approved by Engineer. The contractor shall take all precautions in the design of the
mix an dthe placement of concrete to avoid arching of the concrete in the pile shaft. No
spoil, liquid or other deleterious matter shall be allowed to contaminate the concrete.

ii) Concrete Level

Page 1054
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

When the casing is being extracted a sufficient quantity of concrete shall be maintained
within it to ensure that pressure from external water, drilling fluid or soil is exceeded and
that the pile is neither reduced in section nor contaminated. The toe of the temporary
casing shall be kept a minimum of 2 metres under the outlet of the tremie. No concrete
shall be placed in the boring once the bottom of the casing has been lifted above the top
of the concrete; it shall be placed continuously as the casing is extracted until the desired
head of concrete is obtained.

Adequate precautions shall be taken in all cases where excess heads of water or drilling
fluid could be caused as the casing is withdrawn because of the displacement of water or
fluid by the concrete as it flows into its final position against the walls of the shaft.

The top of the pile shall be brought above the required cut-off level by an amount
sufficient to ensure a sound concrete at cut-off level and the surplus removed to ensure
satisfactory bonding of the pile haed to the structure.

The pile top shall after clean cutting be embedded 100 mm in the foundation, unless
otherwise specified in the drawings. On completion of concreting, the remaining empty
bore shall be backfilled with sand or lean concrete unless otherwise agreed by Engineer.

iii) Vibrating Extractors

The use of vibrating casing extractors shall be permitted.

iv) Reinforcement Cage

During concreting and pulling the casing, the reinforcement cage shall be secured against
uplift and the top shall be kept under close inspection.

v) Stripping Pile Head and Bonding

The piles shall be constructed to a sufficient height above the required cut-off levels
(Overcast) to ensure the all concrete at and below is homogeneous and free of laitance
and deleterious matter. The contractor be required to provide adequate reinforcement
with sufficient length to project above cut-off levels so can be that the reinforcement can
be bonded in the capping beams/ Pile cap. After completion of piling, the contractor shall
excavate and cut back the piles as necessary to verify the ct-off levels and to give
accurate details of the pile positions as compared with the positions indicated on the pile
layout plans of the details drawings. Defective concrete in the pile heads shall be cut
away and mede good with new concrete well bonded to the concrete in pile head. If the
pile is under cast, it shall be built-up with new concrete and a permanent casing. The pile
head breaking equipment and method statement shall be approved by Engineer before
commencement.

i) Temporary Support

The Contractor shall ensure that free standing piles are temporarily braced or stayed
immediately after driving to prevent loosening of the piles in the ground and to ensure that
no damage resulting from oscillation, vibration or movement of any free-standing pile
length can occur.

ii) Pile acceptance Criteria

The target termination depth, required socket length, concrete strength and the required
working pile capacities are shown in the Drawings. The actual termination depths and

Page 1055
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

socket lengths shall be agreed with the Engineer based on the review of the conditions
encountered during boring and prior to commencement of concreting. Pile shall be meet
tolerance requirements as specified and satisfy the integrity tests as specified.

iii) Measures in Case of Rejected Piles

If any pile is found unsatisfactory by any reason either non-release of chisel or bucket or
in the opinion of the Engineer for utilization in the structure it shall be cut off below the pile
cap if so ordered by the Engineer.

The pile shall be replaced as directed by the Engineer. All extra expenses shall be borne
by the Contractor and payment shall be made on the basis that no replacement pile had
to be provided for the unsatisfactory pile.

When the safe bearing value of any pile is found by test to be less than the design load,
longer piles or additional piles shall be installed as ordered in writing by the Engineer

j) Measurement and Payment

a) Measurement

Boring of piles shall be measured in metre for completed and accepted works. The
boring shall be measured from the Toe of the pile up-to existing/original Bed level
(cofferdam level shall not be considered) of the Rivers as per the approved design and
drawings. In case the boring commenced by using coffer-dam; then the length of boring
from the coffer dam to the existing river bed shall not be considered as pay item.
Concrete in the piles is to be measured by multiplying the cross-sectional areas of the
pile ordered by the length of piles as cast up to cut-off level as shown in the drawing, no
deduction shall be made for volume of steel. No measurement shall be made for
cutting or building up of pile head up to cut-off level. The pile head breaking shall be not
measured separately for payment.

Boring shall be commenced from the Coffer dam constructed by Employer (UNOPS).
The cost of boring shall not inclusive of cofferdam/ artificial island or any barge.

The reinforcement of concrete piles is to be measured in tonnes and shall be paid


separately under clause 1002. Cover blocks, binding wires or other materials required
for binding or supporting of reinforcement shall not to be measured.

Permanent steel casing shall be measured in meter length accepted and approved. The
temporary casing up to 6.0 meter shall not be considered as pay item.

b) Payment

The concrete and reinforcement shall be supplied by the Employer (UNOPS) as per
clause 1001 and 1002 of specifications.

The rates for boring shall include the costs of dressing, levelling and compaction of the
area necessary for movement of pile driving rig and other machinery.

The rates of boring shall cover all the necessary items of work required to complete the
pile foundation work including bringing the necessary plant and piling platform for piles
to the site, necessary setting out works, movement of piling equipment from one pile
location to the other. The rate shall also include for bringing and providing all labour
and material necessary for complete work including fencing and other precautionary

Page 1056
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

measures to be taken during construction of pile foundation. The rates shall also
including bottom cleaning as specified. The rates for boring shall include cost of boring
through all sorts of strata including hard rock, lime stones (RQD minimum 75% where
applicable, all jetting, drilling and /or all other works required to obtain specified
penetration pile.

The unit rate for permanent steel casing shall include cost of all materials, fixing in
positions including costs of all necessary labour and incidental as per required diameter
and depth all as specified to complete the work.

The unit rate for temporary steel casing shall be considered if exceed 6.0 meter as per
instruction of Engineer include all cost of providing and fixing in position and extraction
of casing after completion of work including all necessary labour and incidental as per
required diameter all as specified to complete the work.

Pay item Description of Item Pay Unit


1004(1) Boring in all types of soil/Sand/gravel/ lime stone/ Linear Metre
boulder/ Rock including 1XD (Equivalent to pile
diameter) to hard Rock socketing of minimum RQD
75% for cast-in-situ reinforced concrete bored piles in
accordance with Section 1004.5. Cost includes
supply, fixing and removal of 6 m (minimum)
temporary steel casing. The labour and necessary
equipments for Pouring of concrete shall be paid
separately under clause 1001 (1) and fabrication,
installation & fixing of steel re-bar casing shall be paid
separately under clause 1002.
1004(2) Rock boring for doweling works up to 5m depth/or
more to moderately hard rock minimum 75% RQD
and filling by G30 concrete with 02 nos. 25mm rebar
as per instruction of Engineering in charge

a) 125mm~150mm dia on existing ground Linear Metre


b) 125mm~150mm dia in water Linear Metre
1004(3) Rock boring for doweling works up to 5m depth/or
more to moderately hard rock minimum 75% RQD
and filling by G30 concrete with 01 no. 32mm rebar
as per instruction of Engineering in charge

a) 50mm dia on existing ground Linear Metre

Vertical Piles
a) Up to 20 meter length
i) 600mm dia Linear metre
ii) 750mm dia Linear metre
iii) 1000mm dia Linear metre
iv) 1200mm dia Linear metre

b) 20m to 30m length


i) 600mm dia Linear metre
ii) 750mm dia Linear metre
iii) 1000mm dia Linear metre
iv) 1200mm dia Linear metre

c) above 30m length

Page 1057
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

i) 600mm dia Linear metre


ii) 750mm dia Linear metre
iii) 1000mm dia Linear metre
iv) 1200mm dia Linear metre

1004(2) Providing and fixing in position additional


temporary steel casing in Cast-in-situ
piling in Abutment and piers in accordance
with Section 1004.5 and as per direction of
the Engineer. Extra length to 6m allowed
for in item 1004(1) above.

i) 600mm dia Linear metre


ii) 750mm dia Linear metre
iii) 1000mm dia Linear metre
iv) 1200mm dia Linear metre

1004(3) Providing and fixing in position of


permanent steel casing with specified
depth in Cast-in-situ piling in Abutment
and piers as per specification section
1004.5 and direction of the Engineer.

i) 600mm dia Linear metre


ii) 750mm dia Linear metre
iii) 1000mm dia Linear metre
iv) 1200mm dia Linear metre

B) PILE TEST LOADING (STATIC LOAD TEST)

a) Descriptions

1) General

This Section deals with the testing of a pile by the application of an axial load or force i.e
for Static Load test. It covers vertical piles tested in compression.

2) Definitions

i) Allowable Load

The load which may be safely applied to a pile after taking into account its ultimate
bearing capacity, negative friction, pile spacing, overall bearing capacity of the ground
below and allowable settlement.

ii) Compression Pile

A pile which is designed to resist an axial force such as would cause it to penetrate
further into the ground.

iii) Kentledge

The dead weight used in a loading test.

iv) Maintained Load Test

Page 1058
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

A loading test in which each increment of load is held constant either for a defined period
of time or until the rate of movement (settlement or uplift) falls to a specified value.

v) Pilot Pile

A pile installed before the commencement of the main piling works or a specific part of the
works for the purpose of establishing the suitability of the chosen type of pile and for
confirming its design, dimensions and bearing capacity. Pilot piles may be utilized as
working piles, subject to the Engineer’s approval.

vi) Proof Load

A load applied to a selected pile to confirm that it is suitable for the load at the settlement
specified. A proof load should not normally exceed 250% of the working load on a pile
except in circumstances where Special Provisions are provided for the testing of precast
piles driven to a set. In these circumstances, 300% is specified.

vii) Reaction System

The arrangement of kentledge, piles, anchors or rafts that provides a resistance against
which the pile is tested.

viii) Tension Pile

A pile which is designed to resist an axial force such as would cause it to be extracted
from the ground.

ix) Test Pile

Any pile to which a test loading is, or is to be, applied.

x) Ultimate Bearing Capacity

The load at which the resistance of the soil becomes fully mobilised.

xi) Working Load

The load which the pile is designed to carry.

xii) Working Pile

One of the piles forming the foundation of a structure.

b) Supervision

All tests shall be carried out only under the direction of an experienced and competent
supervisor conversant with the test equipment and test procedure. All personnel operating
the test equipment shall have been trained in its use.

c) Safety Precautions

1) General

Page 1059
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

When preparing for, conducting and dismantling a pile test the Contractor shall carry out
the requirement of the various regulations and other statutory instruments that are
applicable to the work for the provision and maintenance of safe working conditions, and
shall in addition make such other provision as may be necessary to safeguard against
any hazards that are involved in the testing or preparations for testing.

2) Kentledge

Where kentledge is used the Contractor shall construct the foundations for the kentledge
and any cribwork, beams or other supporting structure in such a manner that there will not
be differential settlement, bending or deflexion of an amount that constitutes a hazard to
safety or impairs the efficiency of the operation. The kentledge shall be adequately
bonded, tied or otherwise held together to prevent it falling apart, or becoming unstable
because of deflection of the supports. The weight of kentledge shall be greater than the
maximum test load and if the weight is estimated from the density and volume of the
constituent materials an adequate factor of safety against error shall be allowed.

3) Tension Piles and Ground Anchors


Where tension piles or ground anchors are used the Contractor shall ensure that the load
is correctly transmitted to all the tie rods or bolts. The extension of rods by welding shall
not be permitted unless it is known that the steel will not be reduced in strength by
welding. The bond stresses of the rods in tension shall not exceed normal permissible
bond stresses for the type of steel and grade of concrete used.

4) Testing Equipment
In all cases the Contractor shall ensure that when the hydraulic jack and load measuring
device are mounted on the pile head the whole system shall be stable up to the maximum
load to be applied. Means shall be provided to enable dial gauges to be read from a
position clear of the kentledge stack or test frame so that failure in any part of the system
due to overloading, buckling, loss of hydraulic pressure will not constitute a hazard to
personnel.
The hydraulic jack, pump, hoses, pipes, couplings and other apparatus to be operated
under hydraulic pressure shall be capable of withstanding a test pressure of 1.5 times the
maximum working pressure without leaking. The maximum test load or test pressure
expressed as a reading on the gauge in use shall be displayed and all operators shall be
made aware of this limit.

d) Construction of a Pilot Pile to be Test Loaded

1) Notice of Construction

The Contractor shall give the Engineer at least 48 hours notice of the commencement of
construction of any pilot pile, which is to be test loaded.

2) Method of Construction
Each pilot test pile shall be constructed in a manner similar to that to be used for the
construction of the working piles, and by the use of similar equipment and materials. Any
variation shall only be permitted with prior approval. Extra reinforcement and concrete of
increased strength shall be permitted in the shafts of pilot piles at the discretion of the
Engineer.
3) Boring or Driving Record

Page 1060
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

For each pilot pile which is to be tested a detailed record of the soils encountered during
boring, or of the progress during driving shall be made and submitted to the Engineer
daily not later than noon on the next working day.

4) Cut-Off Level

The pile shaft shall terminate at the normal cut-off level, or at a level required by the
Engineer.

The pile shaft shall be extended where necessary above the cut-off level of working piles
so that gauges and other apparatus to be used in the testing process are not damaged by
water or falling debris.

5) Pile Head for Compression Tests

For a pile that is tested in compression, the pile head or cap shall be formed to give a
plane surface which is normal to the axis of the pile, sufficiently large to accommodate the
loading and settlement-measuring equipment and adequately reinforced or protected to
prevent damage from the concentrated application of load from the loading equipment.

e) Preparation of a Working Pile to be Tested

If a test is required on a working pile the Contractor shall cut down or otherwise prepare
the pile for testing as required by the Engineer in accordance with SL. 4 and 5 of Sub
Sections d of section B.

f) Reaction Systems

1) Compression Tests
Compression tests shall be carried out using kentledge, tension piles or specially
constructed anchorages.

Where kentledge is to be used, it shall be supported on cribwork disposed around the pile
head so that its centre of gravity is on the axis of the pile. The bearing pressure under
supporting cribs shall be such as to ensure stability of the kentledge stack. Kentledge
shall not be carried directly on the pile head, except when directed by the Engineer.
2) Working Piles
Where working piles are used as reaction piles their movement shall be measured to
within an accuracy of 0.5 mm.
3) Spacing
Where kentledge is used for loading vertical piles in compression, the distance from the
edge of the test pile to the nearest part of the crib supporting the kentledge stack in
contact with the ground shall be not less than 1.3 metres. The centre to centre spacing of
vertical reaction piles, including working piles used as reaction piles, from a test pile shall
be not less than three times the diameter of the test pile or the reaction piles or 2 metres,
whichever is the greatest.
4) Adequate Reaction
The size, length and number of the piles or anchors, or the area of the rafts, shall be
adequate to transmit the maximum test load to the ground in a safe manner without
excessive movement or influence on the test pile.

Page 1061
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

5) Care of Piles
The method employed in the installation of any reaction piles, anchors or rafts shall be
such as to prevent damage to any test pile or working pile.
6) Loading Arrangement
The loading arrangement used shall be designed to transfer safely to the test pile the
maximum load required in testing. Full details shall be submitted to the Engineer prior to
any work related to the testing process being carried out on the Site.

g) Equipment for Applying Load


The equipment used for applying load shall consist of one or more hydraulic rams or jacks
with the total capacity of the jacks being at least equal to the required maximum load. The
jack or jacks shall be arranged in conjunction with the reaction system to deliver an axial
load to the test pile. The complete system shall be capable of transferring the maximum
load required for the test.

h) Measurement of Load
Suitable approved measuring devices for determining the load on the pile shall be
supplied by the Contractor. Certificates of calibration shall be supplied to the Engineer. In
addition, large diameter (i.e. exceeding 1.2 metre) test piles shall be instrumented at 5
different depths to measure the load distribution along the piles. The instrumentation shall
consist of both a mechanical system and strain gauges for measuring the pile
deformation. The mechanical system shall consist of 6 mm steel rods or high tensile steel
wires gauge No. 23, placed in steel tubes down to the various depths, and connected to
dial gauges at the top. The strain gauges shall be of a stable type, wholly protected by a
steel capsule. They shall be welded to the steel reinforcement, 2 gauges at each depth.
The Engineer shall approve the type of gauges to be used and other details on the
instrumentation.

i) Adjustability of Loading Equipment


The loading equipment shall be capable of adjustment throughout the test to obtain a
smooth increase of load or to maintain each load constant at the required stages of a
maintained loading test.

j) Measuring Movement of Pile Heads


1) General
In a maintained load test movement of the pile head shall be measured by two of the
methods as described below. One method for settlement measurements, the other
method for control.
2) Levelling Method
An optical or any other levelling method by reference to an external datum may be used.

Where a level and staff are used, the level and scale of the staff shall be chosen to
enable readings to be made to within an accuracy of 0.5 mm. A scale attached to the pile
or pile cap may be used instead of a levelling staff. At least two datum points shall be
established on permanent objects or other well-founded structures, or deep datum points
shall be installed. Each datum point shall be situated so that only one setting up of the
level is needed. No datum point shall be affected by the test loading or other operations

Page 1062
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

on the site. Where another method of levelling is proposed this shall be approved in
writing.
3) Independent Reference Frame
An independent reference frame may be set up to permit measurement of the movement
of the pile. The supports for the frame shall be founded in such a manner and at such a
distance from the test pile, kentledge support cribs, reaction piles, anchorages and rafts
that movements of the ground in the vicinity of the equipment do not cause movement of
the reference frame during the testing. Check observations of any movements of the
reference frame shall be made and a check shall be made of the movement of the pile
head relative to an external datum during the progress of the test. In no case shall the
supports be less than three test pile diameters or 2 metres, whichever is the greater, from
the centre of the test pile. The measurement of pile movement shall be made by two dial
gauges rigidly mounted on the reference frame that bear on surfaces normal to the pile
axis fixed to the pile cap or head. Alternatively the gauges may be fixed to the pile and
bear on surfaces on the reference frame. The dial gauges shall be placed in diametrically
opposed positions and be equidistant from the pile axis. The dial gauges shall enable
readings to be made to within an accuracy of 0.1 mm. The reference frames shall be
protected from sun and wind.
4) Other Methods
The Contractor may submit for approval any other method for measuring the movement of
pile heads.

k) Protection of Testing Equipment


1) Protection from Weather
Throughout the test period all equipment for measuring load and movement shall be
protected from the weather.
2) Prevention of Disturbance
Construction equipment and persons who are not involved in the testing process shall be
kept at a sufficient distance from the test to avoid disturbance to the measurement
apparatus.

l) Supervision
1) Notice of Test
The Contractor shall give the Engineer at least 24 hours notice of the commencement of
the test.
2) Records
During the progress of a test, the testing equipment and all records of the test as required
in Sub Section n (Presentation of Results, Schedule of Recorded Data) of Section 1004.5
shall be available for inspection by the Engineer.

m) Test Procedure
1) Proof Test by Maintained Load Test
The maximum load, which shall be applied in a proof test, is shown on the Drawings. The
loading and unloading shall be carried out in stages as shown in Table 1004-5-A or as
required by the Engineer. Following each application of an increment of load the load

Page 1063
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

shall be held for not less than the period shown in Table 1004-5-A or until the rate of
settlement is less than 0.25 mm/hour and is slowing down. The rate of settlement shall be
calculated from the slope of the curve obtained by plotting values of settlement versus
time and drawing a smooth curve through the points.
Each stage of unloading shall proceed after the expiry of the period shown in Table 1004-
5-A. For any period when the load is constant, time and settlement shall be recorded
immediately on reaching the load and at approximately 15 minute intervals for 1 hour, at
30 minute intervals between 1 hour and 4 hours, and at 1 hour intervals between 4 hours
and 12 hours after the application of the increment of load. The Engineer may require that
the full loading, or any portion of the loading, be maintained on the pile for periods longer
than shown in Table 1004-5-A.

Table 1004-5-A
Loading Sequence
Load as Percentage of Working
Load Minimum Time of Holding Load
Bored Piles Driven Piles
25 50 1 hour
50 100 1 hour
75 125 1 hour
100 150 1 hour
75 125 10 minutes
50 100 10 minutes
25 50 10 minutes
0 0 1 hour
100 150 6 hours
125 200 1 hour
125 250 6 hour
175 275 1 hour
200 300 24 hours Proof Road
175 275 10 minutes
150 250 10 minutes
125 225 10 minutes
100 200 10 minutes
75 150 10 minutes
50 100 10 minutes
25 50 10 minutes
0 0 1 hour

n) Presentation of Results

1) Results to be Submitted

Results shall be submitted as:

Page 1064
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

a) A summary in writing to the Engineer, unless otherwise directed, within 24 hours of


the completion of the test, which shall give for a proof test by maintained load for
each stage of loading, the period for which the load was held, the load and the
maximum settlement or uplift recorded.

b) The completed schedule of recorded data as given below within seven days of the
completion of the test.

2) Schedule of Recorded Data

The Contractor shall provide information about the tested pile in accordance with the
following schedule where applicable.
i) General
1) Site location
2) Contract identification
3) Proposed structure
4) Date of test

ii) Pile Details

1) Identification (number and location of the test pile)


2) Ground level at pile position
3) Head level as which test load is applied
4) Type of pile
5) Length in ground
6) Level in ground
7) Level of toe
8) Details of Permanent casing

iii) Installation Details

1) Dates and times of boring, driving and concreting of test pile and adjacent piles
2) Date and time of casting concrete
3) Driven length of pile or temporary casing at final set
4) Hammer type, size or weight
5) Dolly and packing, type and condition before and after driving
6) Driving log (depth, blows per 250 mm, interruptions or breaks in driving)
7) At final set and at redrive set, for drop or single acting hammers, the length of the
drop or stroke, for diesel hammers the length of the stroke and the blows per
minutes, for double-acting hammers the number of blows per minute
8) Condition of pile head or temporary casing after driving

iv) Test Procedure

1) Weight of kentledge
2) Tension pile, ground anchor or compression pile details
3) Plan of test arrangement showing position and distances of kentledge supports,
rafts, tension or compression piles and reference frame to test pile
4) Jack capacity
5) Method of Load measurement
6) Method(s) of penetration measurement
7) Relevant dates and times

v) Test Results

Page 1065
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

1) In tabular form
2) In graphical form: loads plotted against movements and time

o) Completion of a Test

1) Measuring Equipment

On completion of a test all equipment and measuring devices shall be dismantled,


checked and either stored so that they are available for use in further tests or removed
from the Site.

2) Kentledge

Kentledge and its supporting structure shall be removed from the test pile and stored so
that they are available for use in further tests or removed from the Site.

3) Temporary Piles

On completion of a preliminary test, temporary tension piles shall be cut off below ground
level, removed from the Site and the ground made good with approved material as
specified.

p) Measurment

The method of measurement for initial and routine load test shall be in numbers of pile
tested as per specifications.

q) Payment
Rates for initial testing of pilot piles for vertical compression/ static load test shall cover
complete installation and casting of test pile up to specified depth and all necessary work
including earth excavation up to cut-off level, for loading, supplying and fixing of testing
instruments recording the results, and unloading, dismantling and clearing the site.
These rates shall be inclusive of all plant/equipment, material and labour necessary for
any part of the works and submission of test results as specified.
Rates for routine static load test on working piles already driven shall cover cutting of pile
head up to test levels, earth excavation, all necessary wok for making arrangements for
loading, supplying and fixing of testing instruments, recording the results, and making all
arrangements for unloading, dismantling and clearing the site. All these rates shall also
cover all materials and labour necessary for any part of the works and submission of test
results as specified.

Pay items Unit

1004(4) Carrying out initial vertical


load test (Static) on pilot cast-in-situ pile Number (Each)

1004(5) Carrying out Routine vertical load


test (Static) on working cast-in-situ pile Number (Each)

1004.6 Sonic Integrity Test

1) Descriptions

Page 1066
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Non-Destructive Testing is to be performed by the Employer through RDA professionals


or any reputed organization appointed by the Engineer on a number of constructed
working piles at the location of each abutment and pier position of a structure to verify the
integrity of the installed piles. The apparatus for the Integrity Test shall be selected and
arranged by the testing organization. Tests shall be carried out only under the direction of
experienced and competent professionals conversant with the test equipment and test
procedure.

Test piles are to be selected by the Engineer. The Contractor shall provide detailed
records as recorded during installation of each pile which is to be tested. The Contractor
shall cut down all pile heads at the cut-off level or otherwise prepare the pile for testing as
required by the Engineer. The pile head shall be formed to give a plane surface which is
normal to the axis of the pile.

Sonic Integrity Testing is a quick method to check the continuity of installed foundation
piles. This method detects pile defects like cracks, soil intrusion and variations in
diameter. The final pile length can also be checked.

If any pile after Integrity Test is found unsatisfactory in the opinion of the Engineer for
utilisation in the structure, the pile shall be replaced as directed by the Engineer. All extra
expenses shall be borne by the Contractor and payment shall be made in accordance
with sub section 1004.3(A)(i) of the Specifications.

2) Measurement and Payment

Sonic Integrity Test described in the Specifications, shall be carried out by the BRRL or
any approved organization professionals and the necessary charges made by the testing
authorities for performing the tests will be made by the Contractor and the amount, shall
be reimbursed to the Contractor by the Employer from the Provisional Sum as indicated in
the Bill of Quantities. The Contractor should include all costs associated with the Integrity
Tests including all taxes, overhead and profit under Contractor’s mark up of BoQ item.

Pay items Unit

1004(6) Provision for Integrity Tests Number

1004.7 Pile Records

Add the following after the 2nd paragraph:-

In case of cast insitu pile the Contractor shall keep records as indicated below of the
installation of each pile and shall submit two signed copies of these records to the
Engineer not later than noon of the next working day after the pile is installed. The signed
records shall form a record of the work.

The following data are required:


a) Pile location
b) Pile reference number
c) Pile type
d) Nominal cross-sectional dimensions or diameter
e) Length of preformed pile
f) Date and time of driving or redriving
g) Ground level at commencement of installation of pile
h) Working level
i) Pile toe level

Page 1067
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

j) Type, weight, drop and mechanical condition of hammer and equivalent information
for other equipment
k) Number and type of packing used and type and condition of dolly used during
driving the pile
l) Set of pile in mm per 10 blows or number of blows per 250 mm of penetration
m) If required, the sets taken at intervals during the last 3 metres of driving
n) If required, temporary compression of ground and pile from time of a marked
increase in driving resistance until pile reaches its final level
o) All information regarding obstructions delays and other interruptions to the
sequence of work

1004.8 Pile Dynamic Tests

a) DESCRIPTION

High-strain dynamic testing is performed by obtaining and analyzing records of shaft force
and velocity under drop weight impacts for evaluations of shaft load carrying capacity,
structural integrity, and load-movement and shaft-soil load transfer relationships. Testing
procedures shall conform to the ASTM D 4945 specification unless as otherwise noted
below. The following are specifications and instructions for high-strain dynamic testing of
drilled and cast-in-place foundation shafts.

This work shall consist of furnishing all materials, equipment and labor necessary for
conducting high-strain dynamic tests on drilled and cast-in-place shafts (hereafter each
noted as test shaft). The Contractor shall be required to supply material and labor as
hereinafter specified and including prior to, during, and after the load test. High-strain
dynamic tests (herein also called dynamic tests) are non-destructive quick tests. It is
intended that the test shaft be left in a condition suitable for use in production.

b) EQUIPMENT

The Contractor shall supply all materials and equipment required to prepare the test shaft,
dynamically test it, and return the test shaft to a condition suitable for use in the finished
structure. Equipment and procedures required to perform the test include but are not
limited to:

• If a permanent casing is not used as a feature to construct the test shaft, then a shaft
top extension, consisting of a thin walled casing or equivalent, shall be used to extend
the test shaft by length equal to two diameters. This top length, defined as the “test
area” must be exposed and readily accessible by the Testing Engineer at the time of
the test. If the top of the test shaft is below grade, then the Contractor shall have
equipment available to remove surrounding soil (creating a safe working environment)
so as to completely expose a test area as described above. Windows on possibly four
opposite sides of the test shaft may have to be cut off in the steel casing to reach the
concrete.

• Means to insure flat, level, (axial to test shaft) and solid concrete shaft top. Concrete
should be level with, or above the casing.

• A drop weight in the range of one to two percent (1 - 2%) of the anticipated test shaft
capacity, or as determined by the Engineer. The impacting surface of the drop weight
should have an area between 70 and 130% of the test shaft top area. The shape of
the ram weight should be as regular as possible (square, round, hexagonal, etc).

Page 1068
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

• A guide allowing variable drop heights typically between 1 to 2 m, or as determined by


the Engineer.

• A t top cushion consisting of new sheets of plywood with total thickness between 50 to
150 mm, or as determined by the Engineer.

• If protruding reinforcing bars are present, the Contractor has the option to incorporate
the reinforcing steel in the test area. Upon successful completion of the dynamic test,
the surrounding concrete can then be removed as to make the foundation suitable for
use in the structure. If the Contractor selects not to incorporate the steel in such a
manner as described above, then a steel beam or pipe (cross sectional area
approximately 20% of the shaft cross sectional area) shall be supplied with sufficient
length such that the ram impact will not interfere with the reinforcing bars. Steel
striker plates and plywood cushion must also be sized so that they cover as much of
the impact area as possible.

• One (1) kW of 115 Volt AC power.

Surveyors' transit, laser light, or equivalent for measurements of pile set under each
impact.

c) DYNAMIC TESTING FIRM

It is the Contractor’s responsibility to employ and compensate a specialized dynamic


testing firm. Dynamic testing is to be performed by an independent specialist from a firm
with a minimum of five (5) years experience in dynamic testing. The actual dynamic test
shall be conducted and/or supervised by a Licensed Professional Engineer with at least
two (2) years of dynamic testing experience or who has achieved Basic Level or better on
the Foundation QC High Strain Dynamic Pile Testing Examination. Selection of the firm
must be acceptable by the Engineer.

The independent dynamic testing firm must supply the following testing instrumentation in
addition to that outlined in ASTM specification D 4945-00 Section 5:

• Pile Driving Analyzer® (PDA) manufactured by Pile Dynamics, Inc., model PAK, PAX
or PAL or equivalent.

• Four calibrated strain transducers.

• Four calibrated accelerometers.

Prior to performing the dynamic test, the Testing Engineer must be provided with soil
borings, shaft installation records, concrete properties (strength, etc.) and details
regarding the anticipated dynamic loading equipment. The test Engineer is required to
perform wave equation analyses (using GRLWEAP software by Pile Dynamics, Inc. or
equivalent) to determine the suitability of the proposed dynamic load testing equipment
and an acceptable range of ram drop heights so as not to cause damage in the test shaft
during the test.

d) PROCEDURE

• The test shaft shall be constructed using approved installation techniques.

• If a permanent casing is not required, then the upper length equal to two shaft
diameters, noted as the "test area", must be cased in a thin wall tube or equivalent as

Page 1069
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

noted above. Casing of this test area must be made as a continuation of the
construction of the test shaft. There should not be soil contamination or non-
uniformities in the concrete located within or below the test area. Test shaft top
concrete shall be made level to the casing and smoothed.

• Prior to testing time, the Contractor shall make the shaft test area length completely
accessible to the Testing Engineer.

• Prior to the test, four "windows" (approximate size of 150 by 150 mm diametrically
opposite of each other will be located and removed from the casing, if appropriate, or
an entire band of the casing removed to expose a smooth concrete surface for
attachment of the sensors. Sensors are typically attached at least one diameter
below the shaft top. Sensors might be attached to the steel if the impedance
percentage of the steel is relatively high, and if the permanent casing is relatively long
(extending several diameters below the sensors).

• In cases where casing is not present, the Testing Engineer, or Contractor under the
direction of the testing Engineer, shall smooth (by grinding) areas around the pile
circumference such that proper sensor attachment can be accomplished.

• Sensors shall be attached by the Testing Engineer ot at the direction of the Testing
Engineer to the exposed concrete or steel casing in a secure manner as to prevent
slippage under impact.

• Shaft top should be examined to insure concrete is flush with or above the casing.

• Apply plywood cushion and then striker plate to the shaft top. If reinforcing protrudes
from the shaft top, then the steel beam or pipe (used to transfer the impact to the
shaft top) should be secured in such a manner as not to move under impact.

• At least two (2) hammer impacts should be applied to the top of the shaft. First drop
height should be minimal to allow the Testing Engineer to assess the testing
equipment, the driving system and stresses on the foundation. Subsequent impacts
can then be applied by utilizing sequentially higher drop heights until either stresses in
the foundation are excessive or the shaft permanent set for the applied impact
exceeds 2.5 mm.

• Upon completion of the test, it is the Contractors' responsibility to return the shaft to
acceptable production condition.

e) REPORTING OF RESULTS

It is the Testing Engineers' responsibility to submit a timely report of the testing results. In
addition to the field results, results from at least one (1) CAPWAP® analysis or equivalent
shall be submitted. CAPWAP analyses shall be performed by an Engineer that has
achieved Advanced Level or better on the Foundation QC High Strain Dynamic Pile
Testing Examination. The report must also provide the following:

• Wave Equation analysis results obtained prior to testing.

• CAPWAP (or equivalent) analysis results.

Page 1070
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

• For each impact the maximum measured force, maximum calculated tension force,
transferred energy to the sensor location, corresponding stresses, and the Case
Method bearing capacity.

• Assessment of the test results both with respect to pile capacity and integrity.

f) METHOD OF PAYMENT

The high strain dynamic testing procedure shall be considered as any material, labor,
equipment, etc. required above and beyond the requirements of the installation of the
foundation to be tested. This item should include everything necessary to test the shaft,
under direction from the Engineer. All costs associated with the normal production of the
test shaft are measured and paid for elsewhere in the contract documents.

g) BASIS OF PAYMENT

The complete and accepted "High Strain Dynamic Load Test" shall be paid for at the
contract price bid for "High Strain Dynamic Load Test", each. This shall constitute full
compensation for all costs incurred during the procurement, installation, conducting of
test, and subsequent removal of test equipment.

Payments shall be made under:

Pay Item: Pay Unit:


High Strain Dynamic Load Test Each

1005 WELL FOUNDATIONS FOR STRUCTURES

1005.1 Description
No change.

Materials

Delete section: ‘(b) Steel for reinforcements…’ and substitute the following :-

(b) Steel for reinforcement to SLS 375, CS 26 or BS 4449.

1006. RANDOM RUBBLE MASONRY


No change

1007. BRICK WORK AND BLOCK WORK FOR STRUCTURES


No change

1008. FORMWORK FOR STRUCTURES


No change

1009. BRIDGE EXPANSION JOINTS

1009.1 Description

No Change

1009.2 Materials

Page 1071
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Supply of expansion joints shall be done by Employer (UNOPS) and contractor shall
responsible to be installing the expansion joints as per drawings at the expansion joint
location on slab and abutments

1009.3 Construction Requirements

a) No change

(b) Delete and substitute the following:-

Similar to open joints filled expansion joints shall be constructed where shown in the
drawings. The filler shall be in correct position when the concrete on one side of the
joint is placed. After removal of the form, concrete on the other side shall be placed.

The specified thickness of premoulded filler shall be provided at locations of expansion


joints where shown in the drawing. The material shall conform to the requirements of
AASHTO M33 (ASTM D994) and as approved by the Engineer. The filler shall consist
of large pieces as far as possible and assembly of small pieces to make up the required
size shall not be permitted.

The premoulded filler shall be placed in correct position before concrete is placed
against the filler. The material shall form part of the joint and while concreting, care
shall be taken to prevent the filler material from being displaced. After the work is
completed, the exposed face of the joint shall be cleaned of all loose material sticking to
it.

Where shown on the drawings, the joints shall be sealed with joint seals in accordance
with the details shown on the drawings and provisions in these specifications.

The joint seals shall consist of recess in the joint filler which shall be filled with asphalt
layer, bitumen or rubber bitumen or similar compound specially manufactured for
sealing joints in concrete as approved by the Engineer. The sealed joint shall comply
with the following requirements:

i) The seal shall be in planned position.


ii) The seal shall satisfactorily resist the intrusion of foreign material and water.
iii) The seal shall provide bump-free passage of traffic.

The premoulded filler in the joint shall be raked down to the specified depth as shown in
the drawing and to the profile of the finished road surface. All foreign matter shall be
removed from the recess to its bottom. At least 72 hours prior to installing the joint seal,
the contractor shall repair all spalls, fractures, breaks, or voids in the concrete surface
of the joint recess. Immediately prior to placing the seal, the joint shall be cleaned with
air jet to remove all residue and foreign matter and the joint surface shall be surface dry.

Seals of approved compound shall then be placed to completely fill up the prepared
recess in the joint.

(c) Joints provided with steelwork

Add to the end of the section the following :-

Page 1072
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Where proprietary expansion joints are used in bridge decks, the storage and installation
of joints, jointing materials, sealants and other associated items shall be in accordance
with the manufacturer’s recommendations.

Different joint systems shall not, except with the approval of the Engineer, be combined at
one end of a deck.

1009.4 Measurement and payment

Measurement: No change

b) Payment: The payment for expansion joints shall include for installation except
the supply of materials for expansion joints but including all labour,
tools, equipment, and incidentals necessary to complete the work as
specified in the drawings.

Pay item Description Pay Unit


1009 (1) Labour cost for Installation of Expansion Linear Metre
Joint with out supply of materials

1010 BRIDGE BEARINGS

Delete and substitute the following:-

Description

The work shall consist of furnishing and fixing in position of bearings in accordance with
the details shown on the drawings to the requirements of these specifications and the
applicable requirements of British Standards BS 5400: Part 9: ‘Bridge Bearing’ or
AASHTO M 251 of the AASHTO Standard Specifications of Highway Bridges.
The term "Elastomeric bearing" in this specification shall refer to bearing consisting of one
or more elastomer slabs bonded to metal plates during manufacture so as to form a
sandwich arrangement and caters for translation and/or rotation of superstructure by
elastic deformation of elastomer.

1010.2.Materials
Employer (UNOPS) shall supply the Elastomeric bearing to the Contractor and contractor
shall responsible to be placed the Bearing as per drawings over the bearing plinth on Pier
caps and Abutments.

1010.2.1 Properties of the Elastomer

The elastomer to be used for bearing shall be made from chloroprene rubber only
satisfying to the requirements of these specifications.

Grades of raw elastomer of proven use in elastomer bearings with low crystallization rates
and adequate shelf life (e.g. Neoprene WRT, Bayprene 110 or equivalent) shall be used.
No reclaimed elastomer or vulcanized wastage shall ne used. The raw elastomer content
of the compound shall not be lower than 60% and the ash content shall not exceed 5%.
Elastomer having all properties as given following table shall be used. Elastomer shall
high environmental resistance compatible with conditions of use. The adhesion strength
to steel plates shall not be less than 7 KN/m. Shear modulus of elastomer bearing shall

Page 1073
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

not be less than 0.80 Mpa nor greater than 1.20 Mpa.

The raw elastomer shall be Virgin Neoprene (polychloroprene). The elastomer compound
whose nominal hardness falls within the ranges of 46-55, 56-65 and 66-75 are classified
as types A, B and C respectively.
The elastomer compound shall meet the minimum requirements of Tables 1010(1) When
test specimens are cut from the finished product, the physical properties shall be
permitted to vary from those specified in Tables 1010(1) by 10 percent.

1010.2.2 Steel Laminates


Steel laminates used for reinforcement shall be made from rolled mild steel conforming to
ASTM A36 or A570, Grade 36 or Grade 40. The laminates shall have a minimum nominal
thickness of 16 gage. The steel plates separating the elastomeric layers will be
completely bonded by vulcanization to the elastomeric material on all surfaces using
special metal to rubber bonding adhesive.

1010.2.3 Bond
The vulcanized bond between fabric and reinforcement shall have a minimum peel
strength of 5.2 KN/m Steel laminated bearings shall develop a minimum peel strength of
7.0 KN/m2. Peel strength tests shall be performed by ASTM D429 Method B.

Table 1010(1)Neoprene Quality Control Tests


Test Method Properties of Elastomer Unit Type A Type B Type C
PHYSICAL
D 2240 Hardness (Shore A Durometer) IRHD 50 ± 5 60 ± 5 70 ± 5

D 412 Minimum Tensile Strength N/mm2/ 15.52 15.52 15.52


MPa
Minimum Ultimate Elongation 0% 400 350 300
ACCELERATED AGEING
D 573 70 hours at 100°C ± 1°C
Maximum change in Durometer IRHD 15 15 15
Hardness
Maximum change in Tensile % -15 -15 -15
Strength
Maximum change in Ultimate % -40 -40 -40
Elongation
COMPRESSION SET
D 395 22 Hours @ 100oC, Maximum % 35 35 35
Method B
OZONE RESISTANCE
D 1149 Test after 100 hours at 100 pphm No Cracks No No Cracks
ozone in air by volume, 20% Cracks
strain, 38oC ± 1oC

1010.3 Specification for Fabrication

a) Bearing with steel laminates shall be cast as a single unit in a mould and vulcanised
under heat and pressure. Casting of elements in separate units and subsequent
bonding shall not be permitted, nor shall cutting from large size cast be permitted.

b) Bearings of similar size to be used in particular bridge project shall be produced by

Page 1074
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

identical process and in one lot as far as practicable. Phased production may only
be resorted to when the total number of bearings is large enough.

c) The moulds used shall have standard surface finish adequate to produce bearings
free from any surface blemishes.

d) Steel plates for laminates shall be sand blasted, clean of all mill scales and shall be
free from all contaminants prior to bonding by vulcanisation. Rusted plates with
pitting shall not be used. All edges of plates shall be rounded.

e) Spacers used in mould to ensure cover and location of laminates shall be of


maximum size and number practicable. Care shall be taken to ensure uniform
vulcanising conditions and homogeneity of elastomer through the surface and body
of bearings.

Fabrication Tolerances
Laminated bearings shall be built to the specified dimension within the following
tolerances:

Overall Height
Design Thickness 32mm or less -0,+3mm
Design Thickness over 32mm -0,+6mm
2 Overall Horizontal Dimensions -0,+6mm

3 Thickness of Individual Layers of


Elastomer ± 20% of design
At any point within the bearings value,
maximum ± 3mm
4 Parallelism with Opposite Face
Top and bottom 1 in 200
Sides 1 in 50
5 Position of Exposed Connection
Members ± 3mm
Holes, slots or inserts
6 Edge Cover
Embedded laminates or connection -0,+3mm
members
Thickness -0, the smaller of
Top and bottom cover layer (if required) 1.5mm and +20%
of the nominal
cover layer
thickness

1010.4 Drawings

The Contractor shall supply and fix in position and maintain the bearings strictly in
accordance with the drawings and designs of this contract.

1010.5 Acceptance Specification

a) The manufacturer shall have at his plant all the test facilities required for the
process and acceptance control tests. The test facilities and their operation shall be
open to inspection by the Engineer on demand. The certificates on testing of Bridge
bearings obtained from any National Standard Testing Institute of Sri Lanka and or

Page 1075
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

RDA approved Testing Institute by the manufacturer will be acceptable.

b) Acceptance testing shall be commenced with the prior submittal of testing


programme by the manufacturer to the Engineer and after obtaining his approval.

c) The manufacturer of the bearings shall have not less than 5 (five) years successful
experience in manufacturing similar type and capacity bearings.

1010.6 Quality Control Certificate

A lot under acceptance shall comprise all bearings, including a pair of extra test bearings
of equal or near equal size produced under identical conditions of manufacture to be
supplied for a particular project.
The manufacturer shall certify for each lot of bearing under acceptance:

- that an adequate system of continuous quality control was operated in his plant.

- that the entire process remained in control during the production of the lot of
bearings under acceptance as verified from the quality control records/charts which
shall be open to inspection of the Engineer on demand.

- a certified copy of results of process control testing done on samples of elastomer


used in the production of the lot shall be appended and shall include at least the
following information:

Composition of the compound - raw elastomer and ash content, the grade of raw
elastomer used (including name, source, age on shelf). Test results of hardness,
tensile strength, elongation at break, compression set, accelerated ageing, etc.

1010.7 Certificate and Markings

Bearing shall be transported to bridge site after final acceptance by Engineer and shall be
accompanied by an authenticated copy of the certificate to that effect.

An information card giving the following details for the bearing, duly certified by the
manufacturer shall also be appended.

• Name of manufacturer
• Date of manufacture
• Elastomer grade used
• Bearing dimensions
• Production batch no
• Acceptance lot no
• Date of testing
• Specific bridge location
• Explanation of marking used on the bearing

All bearing shall have suitable index markings identifying the information as given above.
The markings shall be made in indelible ink or flexible paint and if practicable should be
visible after installation. The top of the bearing and direction of installation shall be
indicated.

1010.8 Installation

Page 1076
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Bearings shall be installed and grouted according to the supplier's instruction and as
shown on the Drawings, or as directed by the Engineer.

Care shall be taken in packing, transportation, storage and handling to avoid any
mechanical damage, contamination with oil, grease and dirt, undue exposure to sunlight
and weather.

Installation of multiple bearings one behind the other on a single line of support shall be of
identical dimensions.

Bearings shall be placed between true horizontal surfaces (maximum tolerance 0.2%
perpendicular to load) and at true plan position of their centre lines marked on receiving
surfaces (maximum tolerance ±3 mm). Concrete surfaces shall be free from local
irregularities (maximum tolerance ± 1 mm in height).

For cast in place concrete construction of superstructure, where bearings are installed
prior to its concreting, the forms around the bearings shall be soft enough for easy
removal. Forms shall also fit the bearings snugly and prevent any leakage of mortar
grout. Any mortar contaminating the bearings during concreting shall be completely
removed before setting.

a) Maintenance

After installation routine maintenance inspection of all bearings shall be made till the
expiry of the maintenance period to check for any surface cracking or signs of damage,
deterioration or distress.

Damaged bearings shall be replaced immediately. To avoid difference in stiffness, all


adjacent bearings on the same line of support shall also be replaced.

1010.9 Measurement

The quantities of elastomer bearings shall be measured in number of each type of


finished dimension completed and accepted by Engineer.

1010.10 Payment

The work measured shall be paid for at the Contract unit price of Each number of bridge
bearings as shown in the Bill of Quantities. The payment shall be full compensation of
concrete plinths, mortar beds, levelling etc. complete as per drawing and direction of
Engineer and incidentals necessary to complete the work except the supply of
Elastomeric Bearing.

Pay item Unit

1010(1) Placing/fixing of Elastomeric Bearings except supply of Bearing Number

1011 WEARING COURSE

a) Description

This work shall consist of providing wearing course to be laid over the deck slab of
structures either in cement concrete or in asphaltic surface as indicated on the drawings.
Newly constructed concrete deck structure shall have integrally cast concrete wearing

Page 1077
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

course. In rehabilitating structures where wearing course is required to be laid on the


existing concrete deck the same shall be in asphaltic surfacing. In both the cases the
finished deck level at top of wearing course shall be in line and level with the adjacent
road way level unless otherwise specifically mentioned on the drawing.

b) Thickness

The shape and size of wearing course shall be in conformity with the camber and
thickness as shown on the drawings, but in no case the thickness shall be less than 40
mm at any location.

c) Concrete Wearing Course

i) Materials

The materials for the concrete wearing course shall conform to those mentioned under
the specification Section 1001. The grade of concrete shall be Grade 35(Cylinder
Strength) and shall conform to specifications.

ii) Method of Laying

The cement concrete wearing shall be cast while the structural concrete for the deck is
green and has been levelled as shown in the drawing. The concrete for the wearing
course shall be laid and finished to line and level as shown in the drawing. It is to be
ensured to the satisfaction of the Engineer that the concrete of the wearing course when
set gets a firm grip with structural concrete and becomes integral thereto.

iii) Method of Measurement

The concrete for wearing course shall be measured in cubic metres as per specification
Section 1001.

d) Asphaltic Wearing Course

i) Description

This work shall consist of the construction of hot-mixed, hot-laid, bituminous mixture
conforming to the requirements of this section, spread and compacted in layers on a tack
coat on bridge deck of concrete slab in conformity with the lines grade and cross sections
shown in the drawings and as directed by the Engineer.

ii) Materials

Materials shall be in accordance with specification Sub Section 506.2. The gradation of
the combined graded aggregate and mineral for the wearing asphalt surface shall be as
specified in specification Sub Section 506.3

Bituminous material for tack coat shall be cut back asphalt as per specification Sub
Section 506.2

iii) Job-Mix Formula of Asphalt Concrete

The method of job mix shall be as per specification Sub Section 506.4

iv) Construction Method

Page 1078
UNOPS LKOC
New Thondamannaru Bridge Construction Programme Amendments to Standard Specification
Series 1000 - Bridge Designs

Reference is made to specification Sub Section 506.5 and the following shall be added
thereto.

Tack coat shall be provided prior to laying of the wearing course as per specification Sub
Section 502.

v) Method of Measurement

Measurement of asphaltic wearing course shall be as per specification Sub Section


506.6.

e) Measurement and Payment

Measurement and payment of wearing courses for concrete and asphaltic concrete
already scheduled under Sub Section 506 of specification.

Page 1079

You might also like