Cosmetics on concrete after the formwork removal (construction joints, concrete drains from
formwork joints)
Concrete non-conformities (cleaning segregations and fixing them with SIKA repair material);
Mounting scaffolding for steel fixers on each level;
Moving the scaffolding between all the elements on one level;
Dismantling scaffolding and deposit it on site organization when it’s not needed;
Moving access platform and stairs from level to level;
Moving material platforms from level to level where it’s needed;
Making bannisters and covering openings for Health and Safety;
General site cleaning including moving the garbage container when the truck comes;
Moving the ecological Toilets from level to level and getting them down for cleaning;
Winter conditions (making enclosed partitions, handling heaters and checking them for fuel
etc);
Taking water out of the basements after rains;
Maintenance works on the washing ramp (it fills up with concrete remains after cleaning the
mixers);
Coloring the post-tensioned strands bellow the slab in order to avoid any damage of them
when fixing the supports for MEP equipment and the support for the suspended ceiling;
Material handling in-site;
Pouring concrete inside the strand pans after the injections procedures are finished;
Doing small construction related works (welding small metal pieces, mounting façade rails
before concrete pouring etc);
Operators (day and night) for the material elevator;
Site organization works (loading/unloading office containers, making access etc);
One month is an average of 28 working days. A day is made up of 10 working hours. So it comes up
to 142 months X 28 days X 10 hours = 39 760 hours.