Professional Documents
Culture Documents
2
When work operations travel, such as asphalting or road Moving the workarea and/or relocating the powerlines
maintenance, overhead powerlines must be identified prior to away from the workarea should be the first choice particularly
the start of work. Once identified, the work process must when the required overhead work is permanent. Work sites,
ensure personnel are not touching and/or walking near the such as well drilling operations, sign installations, etc. can
equipment until the overhead lines are cleared by the possibly be moved to another site location away from
equipment. The site supervisor should be responsible for overhead powerlines. A site assessment (discussed in
conducting a Job Briefing at the start of the work shift to Section VI) should identify whether the work location can be
ensure all personnel have been alerted of the locations of the moved and where it should be moved to minimum risk.
overhead powerlines and the required protocols to ensure When de-energizing is required, the utility should be
their safety which should include creating a barrier for contacted to request a temporary clearance. De-energizing
isolation. requires an open air gap, a test for nominal voltage, tags at
Touch potentials occur when equipment operators “clearance points” and the application of temporary protective
attempt to get out of the equipment and/or when personnel grounds. Temporary protective grounds must be installed to
are touching equipment when contact is made to an overhead provide an equipotential zone. The process should be
powerline. The equipment operator should remain inside the verified with a utility representative to ensure appropriate
cab until the overhead lines have been deenergized and grounds have been applied.
grounded. If the operator attempts to exit the equipment while
the equipment is energized, the operator becomes a path of
least resistance. If the equipment is on fire, the operator and
or emergency personnel should ensure they never touch the
equipment and ground at the same time.
3
and using barricades can prevent step and touch
potentials.
4
7. Has the electric utility owning the overhead power lines
been identified and contacted, as applicable?
8. Are workers trained to recognize hazards associated Minimum Approach Distance
with overhead power lines and have they been not maintained
instructed on how to avoid the hazards?
9. Are there electrical safety regulations that cover the
work to be performed?
10. Do all supervisors know the clearance and other
requirements?
11. Have safety controls been identified to ensure
personnel safety? If so, what are they?
12. Have all personnel been trained to understand safety
controls?
5
.
VIII. VITA
VI. CONCULUSIONS
VII. REFERENCES