Description of Project/ Type of Job/Work to be Performed Balingueo 230 kV SS Project (Sp13.BSSP.Lt-0152) Replacement of Inert Gas
Cylinders
NGCP Group/Dept/Division/Section Not applicable
Contractor/Subcontractor Maxipro Development Corporation/Fire Solutions Inc.
Project/Work Location NGCP Sta. Barbara Substation
Total No. of Personnel/Workers Involved 5 Workers
Detailed
Requirements, Hazard/Risk/Incident Responsible
Activities/Job Schedule Status of Control
Control Measures Person/s
Tasks/Steps
1.Transport of • Plan route to avoid unnecessary delays FSI During the transport of personnel & Open
cylinders and • Determine road conditions materials
personnel • Observe safe driving & obey traffic
regulations
• Check cylinders if securely fastened
during the travel

2. Hauling of new gas • Conduct toolbox meeting prior to start of FSI During the hauling activities Open
cylinders to site area activity
• Wear appropriate PPEs
• Wait for clearance to start of work
• Observe work safety rules inside
substation
• Injury due to improper lifting & handling
of cylinders
3. Replacement of old • Injury due to improper execution FSI During the replacement activities Open
cylinders with new • Foot injury from fallen cylinders
cylinders • Mishandling of cylinders
• Wear PPEs at all times
4. Hauling of old gas • Injury due to improper execution MDC During the hauling activities Open
cylinder to vehicle • Wear PPEs at all times

1
JSP Prepared By REYNAN PAREJA – MDC Engineer Date October 17, 2018

JSP Reviewd By REYNANTE BUENO – MDC VP Date October 17, 2018

JSP Approved By ROBERTO LAZONA – CPM, NLPD Date


JSP Approved By MICHAEL ASUNCION – OIC, QSE Supervisor Date

JSP Approved By RICHARD LUBUIGUIN – Acting QSE Officer Date

JSP Approved By ARMDN SORIANO – PE BALINGUEO SS Date

JSP Approved By APOLINAR MARINO JR. – OIC SS Mgr., NLD3 Date


FLORENDO DE LUNA – OIC, Dist. Sr. Mgr.