You are on page 1of 19

Carton Corp.

out of which, 14,000 had been completed


without waiting for petitioner’s payment.
GR No. 176868, 26 July 2010. Respondent stated that petitioner was to
pick up the boxes at the factory as agreed
upon, but petitioner failed to do so.
FACTS: Respondent averred that, on October 8,
1998, petitioner’s representative, Bobby Que
Solar Harvest, Inc., entered into an
(Que), went to the factory and saw that the
agreement with respondent, Davao
boxes were ready for pick up. On February
Corrugated Carton Corporation, for the
20, 1999, Que visited the factory again and
purchase of corrugated carton boxes,
supposedly advised respondent to sell the
specifically designed for petitioners business
boxes as rejects to recoup the cost of the
of exporting fresh bananas. The agreement
unpaid 14,000 boxes, because petitioner’s
was not reduced into writing. To get the
transaction to ship bananas to China did not
production underway, petitioner deposited,
materialize. Respondent claimed that the
on March 31, 1998, US$40,150.00 in
boxes were occupying warehouse space
respondents US Dollar Savings Account
and that petitioner should be made to pay
with Westmont Bank, as full payment for the
storage fee at P60.00 per square meter for
ordered boxes.
every month from April 1998. As
Despite such payment, petitioner did not counterclaim, respondent prayed that
receive any boxes from respondent. On judgment be rendered ordering petitioner to
January 3, 2001, petitioner wrote a demand pay $15,400.00, plus interest, moral and
letter for reimbursement of the amount paid. exemplary damages, attorney’s fees, and
On February 19, 2001, respondent replied costs of the suit.
that the boxes had been completed as early
as April 3, 1998 and that petitioner failed to In its March 2, 2004 Decision, the Regional
pick them up from the former’s warehouse Trial Court (RTC) ruled that respondent did
30 days from completion, as agreed upon. not commit any breach of faith that would
Respondent mentioned that petitioner even justify rescission of the contract and the
placed an additional order of 24,000 boxes, consequent reimbursement of the amount
out of which, 14,000 had been manufactured paid by petitioner. The RTC said that
without any advanced payment from respondent was able to produce the ordered
petitioner. Respondent then demanded boxes but petitioner failed to obtain
petitioner to remove the boxes from the possession thereof because its ship did not
factory and to pay the balance of arrive.
US$15,400.00 for the additional boxes and
P132,000.00 as storage fee. On September 21, 2006, the CA denied the
appeal for lack of merit. The appellate court
On August 17, 2001, petitioner filed a held that petitioner failed to discharge its
Complaint for sum of money and damages burden of proving what it claimed to be the
against respondent. The Complaint averred parties’ agreement with respect to the
that the parties agreed that the boxes will be delivery of the boxes. According to the CA, it
delivered within 30 days from payment but was unthinkable that, over a period of more
respondent failed to manufacture and deliver than two years, petitioner did not even
the boxes within such time. demand for the delivery of the boxes. The
CA added that even assuming that the
In its Answer with Counterclaim, respondent agreement was for respondent to deliver the
insisted that, as early as April 3, 1998, it had boxes, respondent would not be liable for
already completed production of the 36,500 breach of contract as petitioner had not yet
boxes, contrary to petitioner’s allegation. demanded from it the delivery of the boxes.
According to respondent, petitioner, in fact,
made an additional order of 24,000 boxes, ISSUE:
qualify as a demand for the fulfillment of the
obligation. Petitioner’s witness also testified
Whether or not petitioner may claim that they made a follow-up of the boxes, but
reimbursement under Article 1191 of the not a demand. Note is taken of the fact that,
Civil Code? with respect to their claim for
reimbursement, the Complaint alleged and
the witness testified that a demand letter
HELD: was sent to respondent. Without a previous
demand for the fulfillment of the obligation,
petitioner would not have a cause of action
NO for rescission against respondent as the
latter would not yet be considered in breach
of its contractual obligation.
RATIO:

The right to rescind a contract arises once


the other party defaults in the performance
of his obligation. In determining when default
occurs, Art. 1191 should be taken in Spouses Lam v. Kodak Philippines, Ltd.
conjunction with Art. 1169 of the same law.
GR No. 167615, 11 January 2016
In reciprocal obligations, as in a contract of
sale, the general rule is that the fulfillment of FACTS:
the parties’ respective obligations should be
simultaneous. Hence, no demand is
generally necessary because, once a party On 8 January 1992, Spouses Lam and
fulfills his obligation and the other party does Kodak Philippines entered into an
not fulfill his, the latter automatically incurs in agreement for the sale of three (3) units of
delay. But when different dates for the Kodak Minilab System 22XL in the
performance of the obligations are fixed, the amount of 1,796,000.00 php per unit.
default for each obligation must be
determined by the rules given in the first
paragraph of the present article, that is, the
other party would incur in delay only from Spouse Lam issued 12 post-dated checks
the moment the other party demands as payment. They requested that Kodak
fulfillment of the former’s obligation. Thus, Philippiines not negotiate the first check
even in reciprocal obligations, if the period dated 31 March 1992 allegedly due to
for the fulfillment of the obligation is fixed, insufficiency of funds. The same request
demand upon the obligee is still necessary was made the following month. However,
before the obligor can be considered in both checks were negotiated by Kodak
default and before a cause of action for Philippines and were honoured by the bank.
rescission will accrue. The 10 other checks were subsequently
dishonoured after the Spouses Lam ordered
Evident from the records and even from the the bank to stop payment.
allegations in the complaint was the lack of
demand by petitioner upon respondent to
fulfill its obligation to manufacture and Kodak Philippines canceled the sale and
deliver the boxes. The Complaint only demanded that the Spouses return the unit it
alleged that petitioner made a “follow-up” delivered. Spouses Lam ignored the
upon respondent, which, however, would not
demand but also rescinded the contract for
failure to deliver the two (2) remaining units.
1. NO
2. YES

Kodak Philippines filed a complaint for


replevin and/or recovery of sum of money
with the Makati RTC, which then issued the RATIO:
decision in their favour ordering the seizure
of the unit. Upon appeal to the CA, the case
was remanded to the trial court. 1. Based on the foregoing, the
intention of the parties is for there to
be a single transaction covering all
RTC found that Kodak Philippines defaulted three (3) units of the Minilab
in the performance of its obligation under its Equipment. Respondent’s obligation
Letter Agreement wit the Spouses. It held was to deliver all products
that the failure to deliver two (2) of out the purchased under a “package” and,
three (3) units of the equipment causes the in turn, petitioners’ obligation was to
Lam Spouses to stop paying for the rest of pay for the total purchase price,
the instalments. Likewise, the RTC ruled payable in installments.
that when the Spouses accepted the
delivery of the first unit, they became liable The intention of the parties to bind
for the fair value of the goods received. themselves to an indivisible
Thus, they were under the obligation to pay obligation can be further discerned
for the amount, and the failure to deliver the through their direct acts in relation to
remaining units did not give them the right to the package deal. There was only
suspend payment for the unit already one agreement covering all three (3)
delivered. RTC dismissed the case, ordering units of the Minilab Equipment and
the petitioners to pay. Upon appeal to the their accessories.
CA, raising the issue of the failure to order
There is no indication in the Letter
Kodak Philippines to pay. The CA affirmed
Agreement that the units’ petitioners
the RTC’s decision. They ruled that the
ordered were covered by three (3)
Letter Agreement executed by the parties
separate transactions. The factors
showed that their obligations were
considered by the Court of Appeals
susceptible of partial performance and the
are mere incidents of the execution
contract between the parties was validly
of the obligation, which is to deliver
rescinded. Hence, this petition.
three units of the Minilab Equipment
on the part of respondent and
payment for all three on the part of
ISSUE: petitioners. The intention to create
an indivisible contract is apparent
from the benefits that the Letter
1. Whether or not the contract Agreement afforded to both parties.
between petitioners pertained to Petitioners were given the 19%
obligations that are susceptible of discount on account of a multiple
partial performance. order, with the discount being
2. Whether or not the CA correctly equally applicable to all units that
ordered mutual restitution they sought to acquire. The
provision on “no downpayment” was
also applicable to all units.
HELD: Respondent, in turn, was entitled to
payment of all three Minilab
Equipment units, payable by
installments.
The Wellex Group, Inc. v. U-Land Airlines
2. Rescission under Article 1191 has Co., Ltd.
the effect of mutual restitution. GR No. 167519, 14 January 2015

When rescission is sought under


Article 1191 of the Civil Code, it
need not be judicially invoked FACTS:
because the power to resolve is
implied in reciprocal obligations. The
right to resolve allows an injured Wellex and U-Land agreed to develop a
party to minimize the damages he or long-term business relationship through the
she may suffer on account of the creation of joint interest in airline operations
other party’s failure to perform what and property development projects in the
is incumbent upon him or her. When Philippines. The agreement includes:
a party fails to comply with his or her Acquisition of APIC and PEC shares;
obligation, the other party’s right to Operation and management of
resolve the contract is triggered. The APIC/PEC/APC; Entering into and funding a
resolution immediately produces joint development agreement; and the option
legal effects if the non-performing to acquire from WELLEX shares of stock of
party does not question the EXPRESS SAVINGS BANK ("ESB") up to
resolution. Court intervention only 40% of the outstanding capital stock of ESB
becomes necessary when the party of U-Land. The provisions of the
who allegedly failed to comply with memorandum were agreed to be executed
his or her obligation disputes the within 40 days from its execution date.
resolution of the contract. Since
both parties in this case have
exercised their right to resolve under The 40-day period lapsed but Wellex and U-
Article 1191, there is no need for a Land were not able to enter into any share
judicial decree before the resolution purchase agreement although drafts were
produces effects. exchanged between the two. However,
Despite the absence of a share purchase
As discussed earlier, the breach agreement, U-Land remitted to Wellex a
committed by petitioners was the total of US$7,499,945.00. Wellex
nonperformance of a reciprocal acknowledged the receipt of these
obligation, not a violation of the remittances in a confirmation letter
terms and conditions of the addressed to U-Land and allegedly
mortgage contract. Therefore, the delivered stock certificates and TCTs of
automatic rescission and forfeiture subject properties. Despite these
of payment clauses stipulated in the transactions, Wellex and U-Land still failed
contract does not apply. Instead, to enter into the share purchase agreement
Civil Code provisions shall govern and the joint development agreement. Thus,
and regulate the resolution of this U-Land filed a Complaint praying for
controversy. rescission of the First Memorandum of
Agreement and damages against Wellex
Considering that the rescission of and for the issuance of a Writ of Preliminary
the contract is based on Article 1191 Attachment.
of the Civil Code, mutual restitution
is required to bring back the parties
to their original situation prior to the
inception of the contract.
RTC: Ruled In favor of Uland and ordered ISSUE:
rescission of contract under Art. 1911 of the
civil code. Basis of rescission: Wellex’s
misrepresentation that APIC was a majority Whether or not respondent U-Land correctly
shareholder of APC that compelled it to sought the principal relief of rescission or
enter into the agreement.. resolution under Article 1191.

“Notwithstanding the said HELD:


remittances, APIC does not own a
single share of APC. On the other YES
hand, defendant could not even
satisfactorily substantiate its claim
that at least it had the intention to RATIO:
cause the transfer of APC shares to
APIC. Defendant obviously did not
enter into the stipulated SPA
Respondent U-Land is praying for rescission
because it did not have the shares
or resolution under Article 1191, and not
of APC transferred to APIC despite
rescission under Article 1381. The failure of
its representations. Under the
one of the parties to comply with its
circumstances, it is clear that
reciprocal prestation allows the wronged
defendant fraudulently violated
party to seek the remedy of Article 1191.
the provisions of the MOA.”
The wronged party is entitled to rescission
or resolution under Article 1191, and even
the payment of damages. It is a principal
On appeal, the Court of Appeals affirmed action precisely because it is a violation of
the ruling of the Regional Trial Court. Hence the original reciprocal prestation. Article
this petition. 1381 and Article 1383, on the other hand,
pertain to rescission where creditors or even
third persons not privy to the contract can
Petitioners invokes Suria v. Intermediate file an action due to lesion or damage as a
Appellate Court, which held that an "action result of the contract. Rescission or
for rescission is not a principal action that is resolution under Article 1191, therefore, is a
retaliatory in character under Article 1191 of principal action that is immediately available
the Civil Code, but a subsidiary one which is to the party at the time that the reciprocal
available only in the absence of any other prestation was breached. Article 1383
legal remedy under Article 1384 of the Civil mandating that rescission be deemed a
Code. Respondent U-land avers that this subsidiary action cannot be applicable to
case was inapplicable because the pertinent rescission or resolution under Article 1191.
provision in Suria was not Article 1191 but Thus, respondent U-Land correctly sought
rescission under Article 1383 of the Civil the principal relief of rescission or resolution
Code. The "rescission" referred to in Article under Article 1191.
1191 referred to "resolution" of a contract
due to a breach of a mutual obligation, while
Article 1384 spoke of "rescission" because Enforcement of Section 9 of the First
of lesion and damage. Thus, the rescission Memorandum of Agreement has the same
that is relevant to the present case is that of effect as rescission or resolution under
Article 1191, which involves breach in a Article 1191 of the Civil Code. The parties
reciprocal obligation. are obligated to return to each other all that
they may have received as a result of the
breach by petitioner Wellex of the reciprocal
obligation. Therefore, the Court of Appeals GR No. 171127, 11 March 2015
did not err in affirming the rescission granted
by the trial court.
FACTS:

Contrary to petitioner Wellex’s argument,


this is not rescission under Article 1381 of Edmer Cortejo was brought to the
the Civil Code. This case does not involve Emergency Room of the SJDH because of
prejudicial transactions affecting guardians, difficulty in breathing, chest pain, stomach
absentees, or fraud of creditors. Article pain and fever.
1381(3) pertains in particular to a series of
fraudulent actions on the part of the debtor
who is in the process of transferring or
Based on the initial examinations and the
alienating property that can be used to
chest x-ray, Edmer was diagnosed with
satisfy the obligation of the debtor to the
“bronchopneumonia”. Edmer was referred to
creditor. There is no allegation of fraud for
Dr. Casumpang and he confirimed the initial
purposes of evading obligations to other
diagnosis of bronchopneumonia.
creditors. The actions of the parties involving
the terms of the First Memorandum of
Agreement do not fall under any of the
enumerated contracts that may be subject of While under observation, Edmer’s
rescission. symptoms were persisting which included
fever and traces of blood in his sputum, and
upon alerting Dr. Casumpang, he reassured
Mrs. Corteho that her son’s illness is
Furthermore, in the rescission by reason of
bronchopneumonia.
lesion or economic prejudice, the cause of
action is subordinated to the existence of
that prejudice, because it is the raison detre
as well as the measure of the right to The following day, Edmer vomited
rescind. Hence, where the defendant makes “phlegmn” with blood streak, and upon
good the damages caused, the action examination ordered by Dr. Casumpang,
cannot be maintained or continued, as due to the advice of Dr. Sanga, Edmer’s
expressly provided in Articles 1383 and blood test showed that he is suffering from
1384. But the operation of these two articles Dengue Hemorrhagic Fever, which
is limited to the cases of rescission for lesión prompted his parents to transfer him to the
enumerated in Article 1381 of the Civil Code Makati Medical Center, instead of the
of the Philippines, and does not apply to transferring him to the ICU which Dr.
cases under Article 1191. Casumpang suggested.

The obligations of the parties gave rise to Upon examination in the Makati Medical
reciprocal prestations, which arose from the Center, the attending physician diagnosed
same cause: the desire of both parties to Edmer with Dengue Fever Stage IV that was
enter into a share purchase agreement that already in its irreversible stage. Soon, after
would allow both parties to expand their Edmer died. Believing that Edmer’s death
respective airline operations in the was caused by the negligent and erroneous
Philippines and other neighboring countries. diagnosis of his doctors, the respondent
instituted an action for damages against
SJDH, and its physicians: Dr. Casumpang
and Dr. Sanga before the RTC of Makati.
Casumpang v. Cortejo
physician is an independent contractor.

RTC ruled in favor of the respondent and SJDH impliedly held out and clothed Dr.
held that the physicians were negligent. Casumpang with apparent authority leading
They also held that SJDH was solidarily the respondent to believe that he is an
liable for the damages. Upon appeal the the employee or agent of the hospital.
CA, the CA affirmed en toto the RTC’s
ruling. Hence, this petition. SJDH impliedly held out Dr. Casumpang,
not only as an accredited member of
Fortune Care, but also as a member of its
ISSUE: medical staff.

SJDH cannot now disclaim liability since


Whether or not the SJDH is solidary there is no showing that Mrs. Cortejo or the
liable with the physicians respondent knew, or should have known,
that Dr. Casumpang is only an independent
contractor of the hospital. In this case,
estoppel has already set in.
HELD:

YES De Carmen v. Spouses Sabordo

GR No. 181723, 11 August 2014

RATIO:
FACTS:

We affirm the hospital’s liability not on the


basis of Article 2180 of the Civil Code, but Sometime in 1961, the spouses Suico, along
on the basis of the doctrine of apparent with several business partners, entered into
authority or agency by estoppel. a business venture by establishing a rice
and corn mill at Mandaue City, Cebu. As
Despite the absence of employer-employee part of their capital, they obtained a loan
relationship between SJDH and the from the Development Bank of the
petitioning doctors, SJDH is not free from Philippines (DBP), and to secure the said
liability. loan, four parcels of land owned by the
Suico spouses, denominated as Lots 506,
As a rule, hospitals are not liable for the
512, 513 and 514, and another lot owned by
negligence of its independent contractors.
their business partner, Juliana Del Rosario,
However, it may be found liable if the
were mortgaged.
physician or independent contractor acts as
an ostensible agent of the hospital. This Subsequently, the Suico spouses and their
exception is also known as the “doctrine of business partners failed to pay their loan
apparent authority.” obligations forcing DBP to foreclose the
mortgage. After the Suico spouses and their
Therefore, we hold that, under the doctrine
partners failed to redeem the foreclosed
of apparent authority, a hospital can be held
properties, DBP consolidated its ownership
vicariously liable for the negligent acts of a
over the same. Nonetheless, DBP later
physician providing care at the hospital,
allowed the Suico spouses and Flores
regardless of whether the physician is an
spouses, as substitutes for Juliana Del
independent contractor, unless the patient
Rosario, to repurchase the subject lots by
knows, or should have known, that the
way of a conditional sale for the sum of the payment of P127,500.00, but alleging
P240,571.00. The Suico and Flores spouses that they cannot determine as to whom such
were able to pay the down payment and the payment shall be made, petitioner and her
first monthly amortization, but no monthly coheirs filed a Complaint with the RTC of
installments were made thereafter. San Carlos City, Negros Occidental seeking
Threatened with the cancellation of the to compel herein respondents and RPB to
conditional sale, the Suico and Flores interplead and litigate between themselves
spouses sold their rights over the said their respective interests on the above
properties to herein respondents Restituto mentioned sum of money. The Complaint
and Mima Sabordo, subject to the condition also prayed that respondents be directed to
that the latter shall pay the balance of the substitute Lots 506 and 514 with other real
sale price. On September 3, 1974, estate properties as collateral for their
respondents and the Suico and Flores outstanding obligation with RPB and that the
spouses executed a supplemental latter be ordered to accept the substitute
agreement whereby they affirmed that what collateral and release the mortgage on Lots
was actually sold to respondents were Lots 506 and 514. Upon filing of their complaint,
512 and 513, while Lots 506 and 514 were the heirs of Toribio deposited the amount of
given to them as usufructuaries. DBP P127,500.00 with the RTC of San Carlos
approved the sale of rights of the Suico and City, Branch 59.
Flores spouses in favor of herein
respondents. Subsequently, respondents On December 5, 2001, the RTC rendered
were able to repurchase the foreclosed judgment, dismissing the Complaint of
properties of the Suico and Flores spouses. petitioner and her co-heirs for lack of merit.
Respondents’ Counterclaim was likewise
On September 13, 1976, respondent dismissed.
Restituto Sabordo (Restituto) filed with the
then Court of First Instance an original Petitioner and her coheirs filed an appeal
action for declaratory relief with damages with the CA contending that the judicial
and prayer for a writ of preliminary injunction deposit or consignation of the amount of
raising the issue of whether or not the Suico P127,500.00 was valid and binding and
spouses have the right to recover from produced the effect of payment of the
respondents Lots 506 and 514. purchase price of the subject lots. In its
assailed Decision, the CA denied the above
In its Decision dated December 17, 1986, appeal for lack of merit and affirmed the
the Regional Trial Court (RTC) of San disputed RTC Decision.
Carlos City, Negros Occidental, ruled in
favor of the Suico spouses directing that the
latter have until August 31, 1987 within
which to redeem or buy back from ISSUE:
respondents Lots 506 and 514.

In a Resolution dated February 13, 1991, Whether or not there was a valid
the CA granted the Suico spouses an consignation.
additional period of 90 days from notice
within which to exercise their option to
purchase or redeem the disputed lots. Later, HELD:
they discovered that respondents mortgaged
Lots 506 and 514 with Republic Planters
Bank (RPB) as security for a loan, which,
NO
subsequently, became delinquent.

Thereafter, claiming that they are ready with


RATIO: Company (FEBTC), which the SEC
approved and issued the Certificate of Filing
of the Articles of Merger and Plan of Merger
In the cases of Del Rosario v. Sandico, 85 and between BPI, the surviving corporation,
Phil. 170 (1949) and Salvante v. Cruz, 88 and FEBTC, the absorbed corporation. By
Phil. 236 (1951), likewise cited as authority virtue of said merger, all the assets and
by petitioner, this Court held that, for a liabilities of FEBTC were transferred to and
consignation or deposit with the court of an absorbed by BPI.
amount due on a judgment to be considered
as payment, there must be prior tender to Consequently, Spouses Domingo defaulted
the judgment creditor who refuses to accept in their installments. BPI, being the surviving
it. The same principle was reiterated in the corporation after the merger, demanded that
later case of Pabugais v. Sahijwani, 423 the spouses Domingo pay the balance of the
SCRA 596 (2004). As stated above, tender Promissory Note including other charges or
of payment involves a positive and to return the subject vehicle for purposes of
unconditional act by the obligor of offering foreclosure. When the Spouses Domingo
legal tender currency as payment to the still failed to comply with its demands, BPI
obligee for the formerÊs obligation and filed a complaint with the MTC. Spouses
demanding that the latter accept the same. Domingo argued that BPI had no cause of
In the instant case, the Court finds no action against them and that Maryden
cogent reason to depart from the findings of Domingo once obtained a car loan from
the CA and the RTC that petitioner and her FEBTC but sold it to Carmelita Gonzales
coheirs failed to make a prior valid tender of with the bank’s conformity and the buyer
payment to respondents. subsequently assumed payment of the
balance of the mortgaged loan.
Furthermore, the fact that the subject lots
are in danger of being foreclosed does not MTC rendered a decision in favor of BPI as
excuse petitioner and her coheirs from the bank was able to establish by
tendering payment to respondents, as preponderance of evidence a valid cause of
directed by the court. action against the spouses. They held that
novation is never presumed and must be
BPI v. Domingo clearly shown by express agreement or by
acts of equal import. The MeTC found
GR No. 169407, 25 March 2015 Amador’s bare testimony as insufficient
evidence to prove that he and his wife Mercy
had been expressly released from their
FACTS: obligations and that Carmelita Gonzales
(Carmelita) assumed their place as the new
debtor within the context of subjective
novation. Upon appeal to the RTC, the RTC
Spouses Domingo executed a promissory
held that in novation, consent of the creditor
note in favour of Makati Auto Centre payable
to the substitution of the debtor need not be
in 48 successive instalments. They
by express agreement, it can be merely
simultaneously executed a Deed of Chattel
implied.
Mortgage over a 1993 Mazda vehicle to
secure payment of the promissory note.
To the RTC, the following circumstances
demonstrated the implied consent of BPI to
the novation: (1) BPI had knowledge of the
Makati Auto Center, Inc. then assigned, Deed of Sale and Assumption of Mortgage
ceded, and transferred all its rights and executed between Mercy and Carmelita, but
interests over the said Promissory Note and did not interpose any objection to the same;
chattel mortgage to Far East Bank and Trust and (2) BPI (through FEBTC) returned the
personal checks of the spouses Domingo of said agreement, and still it did not
and accepted the payments made by interpose any objection to the same; (2) BPI
Carmelita. The RTC also noted that BPI (through FEBTC) returned the spouses
made a demand for payment upon the Domingo’s checks and accepted Carmelita’s
spouses Domingo only after 30 months from payments; and (3) BPI did not demand any
the time Carmelita assumed payments for payment from the spouses Domingo not
the installments due. The RTC reasoned until 30 months after Carmelita assumed the
that if the spouses Domingo truly remained payment of balance on the Promissory Note.
as debtors, BPI would not have wasted time
in demanding payments from them. Absent proof that BPI gave its clear and
unmistakable consent to release the
Upon appeal to the CA, the CA affirmed the spouses Domingo from the obligation to pay
decision of the RTC that novation took the car loan, Carmelita is simply considered
place. Hence, this petition. an additional debtor. Consequently, BPI can
still enforce the obligation against the
ISSUE: spouses Domingo even 30 months after it
had started accepting payments from
Carmelita.
Whether or not there had been a novation
of the loan obligation with chattel It is worthy to stress that Amador, as the
mortgage of the Spouses Domingo to BPI party asserting novation, bears the burden
so that the spouses Domingo were of proving its existence. Amador cannot
released from said obligation and simply rely on the failure of BPI to produce
Carmelita was substituted as debtor. the checks if these were not actually
returned to the spouses Domingo. There is
simply not enough evidence to establish the
prima facie existence of novation to shift the
HELD:
burden of evidence to BPI to controvert the
same.

NO The Court is therefore convinced that there


is no novation by delegacion in this case
and Amador remains a debtor of BPI. The
RATIO: Court reinstates the MeTC judgment
ordering Amador to pay for the balance on
the Promissory Note.
The burden of establishing a novation is on
the party who asserts its existence. Contrary
to the findings of the Court of Appeals and Spouses Mamaril v. The Boy Scout of the
the RTC, Amador failed to discharge such Philippines
burden, as he was unable to present proof
of the clear and unmistakable consent of GR No. 179382, 14 January 2013
BPI to the substitution of debtors.

Irrefragably, there is no express consent of FACTS:


BPI to the substitution of debtors. The Court
of Appeals and the RTC inferred the consent
of BPI from the following facts: (1) BPI had a Spouses Mamaril are jeepney operators
copy of the Deed of Sale and Assumption of since 1971. They would park their six (6)
Mortgage executed between Mercy and passenger jeepneys every night at the Boy
Carmelita in its file, indicating its knowledge Scout of the Philippines’ (BSP) compound
located at 181 Concepcion Street, Malate, BSP was also adjudged liable because the
Manila for a fee. On May 26, 1995 at 8 in the Guard Service Contract it entered into with
evening, all these vehicles were parked AIB offered protection to all properties inside
inside the BSP compound. One of the the BSP premises, which necessarily
vehicles was missing and was never included Sps. Mamaril’s vehicles. Moreover,
recovered. According to the security guards the said contract stipulated AIB’s obligation
Cesario Peña (Peña) and Vicente Gaddi to indemnify BSP for all losses or damages
(Gaddi) of AIB Security Agency, Inc. (AIB) that may be caused by any act or
with whom BSP had contracted for its negligence of its security guards.
security and protection, a male person who Accordingly, the BSP, AIB, and security
looked familiar to them took the subject guards Peña and Gaddi were held jointly
vehicle out of the compound. and severally liable for the loss suffered by
Sps. Mamaril.
Sps. Mamaril filed a complaint for damages
before the Regional Trial Court (RTC) of In its assailed Decision, the CA affirmed the
Manila, Branch 39, against BSP, AIB, Peña finding of negligence on the part of security
and Gaddi. In support thereof, Sps. Mamaril guards Peña and Gaddi. However, it
averred that the loss of the subject vehicle absolved BSP from any liability, holding that
was due to the gross negligence of the the Guard Service Contract is purely
above-named security guards on-duty who between BSP and AIB and that there was
allowed the subject vehicle to be driven out nothing therein that would indicate any
by a stranger despite their agreement that obligation and/or liability on the part of BSP
only authorized drivers duly endorsed by the in favor of third persons, such as Sps.
owners could do so. Peña and Gaddi even Mamaril. Nor was there evidence sufficient
admitted their negligence during the ensuing to establish that BSP was negligent.
investigation. Notwithstanding, BSP and AIB
did not heed Sps. Mamaril’s demands for a ISSUE:
conference to settle the matter. They
therefore prayed that Peña and Gaddi,
together with AIB and BSP, be held liable. Whether or not BSP should be liable for
the loss to the Spouses Mamaril.
In its Answer, BSP denied any liability
contending that not only did Sps. Mamaril
directly deal with AIB with respect to the
HELD:
manner by which the parked vehicles would
be handled, but the parking ticket itself
expressly stated that the “Management shall
not be responsible for loss of vehicle or any NO
of its accessories or article left therein.” It
also claimed that Sps. Mamaril erroneously
relied on the Guard Service Contract. Apart RATIO:
from not being parties thereto, its provisions
cover only the protection of BSP’s
properties, its officers, and employees.
Article 20 of the Civil Code provides that
every person, who, contrary to law, willfully
The RTC found that the act of Peña and
or negligently causes damage to another,
Gaddi in allowing the entry of an unidentified
shall indemnify the latter for the same.
person and letting him drive out the subject
Similarly, Article 2176 of the Civil Code
vehicle in violation of their internal
states: Art. 2176. Whoever by act or
agreement with Sps. Mamaril constituted
omission causes damage to another, there
gross negligence, rendering AIB and its
being fault or negligence, is obliged to pay
security guards liable for the former’s loss.
for the damage done. Such fault or Lorenzo Shipping v. BJ Marthel
negligence, if there is no preexisting Intenational, Inc.
contractual relation between the parties, is
called a quasi-delict and is governed by the GR No. 145483, 19 November 2004
provisions of this Chapter. In this case, it is
undisputed that the proximate cause of the
loss of Sps. Mamaril’s vehicle was the FACTS:
negligent act of security guards Peña and
Gaddi in allowing an unidentified person to
drive out the subject vehicle. Proximate Petitioner Lorenzo Shipping Corporation is a
cause has been defined as that cause, domestic corporation engaged in coastwise
which, in natural and continuous sequence, shipping. It used to own the cargo vessel
unbroken by any efficient intervening cause, M/V Dadiangas Express.
produces the injury or loss, and without
which the result would not have occurred.
Moreover, Peña and Gaddi failed to refute
On the other hand, respondent BJ Marthel
Sps. Mamaril’s contention that they readily
International, Inc. is a business entity
admitted being at fault during the
engaged in trading, marketing, and selling of
investigation that ensued.
various industrial commodities. It is also an
importer and distributor of different brands of
In the instant case, the owners parked their
engines and spare parts.
six (6) passenger jeepneys inside the BSP
compound for a monthly fee of P300.00 for
each unit and took the keys home with them.
From 1987 up to the institution of this case,
Hence, a lessor-lessee relationship respondent supplied petitioner with spare
indubitably existed between them and BSP. parts for the latter’s marine engines.
On this score, Article 1654 of the Civil Code Sometime in 1989, petitioner asked
provides that “[t]he lessor (BSP) is obliged: respondent for a quotation for various
(1) to deliver the thing which is the object of machine parts. Acceding to this request,
the contract in such a condition as to render respondent furnished petitioner with a formal
it fit for the use intended; (2) to make on the quotation
same during the lease all the necessary
repairs in order to keep it suitable for the use
to which it has been devoted, unless there is It was stipulated in the contract that
a stipulation to the contrary; and (3) to DELIVERY is within 2 months after receipt
maintain the lessee in the peaceful and of firm order. The TERMS is 25% upon
adequate enjoyment of the lease for the delivery, balance payable in 5 bi-monthly
entire duration of the contract. In relation equal and Installment[s] not to exceed 90
thereto, Article 1664 of the same Code days.
states that [t]he lessor is not obliged to
answer for a mere act of trespass which a
third person may cause on the use of the
Petitioner thereafter issued to respondent
thing leased; but the lessee shall have a
Purchase Order. For the procurement of one
direct action against the intruder. Here, BSP
set of cylinder liner, valued at P477,000, to
was not remiss in its obligation to provide
be used for M/V Dadiangas Express.
Sps. Mamaril a suitable parking space for
Instead of paying the 25% down payment for
their jeepneys as it even hired security
the first cylinder liner, petitioner issued in
guards to secure the premises; hence, it
favor of respondent ten post-dated checks to
should not be held liable for the loss
be drawn against the former's account with
suffered by Sps. Mamaril.
Allied Banking Corporation. The checks
were supposed to represent the full payment reckoned from June 1991 until the full
of the aforementioned cylinder liner. payment of the principal; attorney's fees;
costs of suits; exemplary damages; actual
damages; and compensatory damages.
Subsequently, petitioner issued Purchase
Order dated 15 January 1990, for yet
another unit of cylinder liner. This purchase In an Order dated 25 July 1991, the court a
order stated the term of payment to be "25% quo granted respondent's prayer for the
upon delivery, balance payable in 5 bi- issuance of a preliminary attachment. On 09
monthly equal installment[s]. On 26 January August 1991, petitioner filed an Urgent Ex-
1990, respondent deposited petitioner's Parte Motion to Discharge Writ of
check that was postdated 18 January 1990, Attachment attaching thereto a counter-bond
however, the drawee bank due to as required by the Rules of Court. On even
insufficiency of funds dishonoured the same. date, the trial court issued an Order lifting
Respondent eventually returned the the levy on petitioner's properties and the
remaining nine post-dated checks to garnishment of its bank accounts.
petitioner.

Petitioner afterwards filed its Answer


However, the parties presented disparate alleging therein that time was of the essence
accounts of what happened to the check, in the delivery of the cylinder liners and that
which was previously dishonoured. the delivery on 20 April 1990 of said items
Petitioner claimed that it replaced said check was late as respondent committed to deliver
with a good one, the proceeds of which were said items "within two (2) months after
applied to its other obligation to respondent. receipt of firm order" from petitioner.
For its part, respondent insisted that it
returned said post-dated check to petitioner.
Subsequently, respondent filed a Second
Amended Complaint with Preliminary
On 20 April 1990, Pajarillo delivered the two Attachment dated 25 October 1991. The
cylinder liners at petitioner's warehouse in amendment introduced dealt solely with the
North Harbor, Manila. The sales invoices number of post-dated checks issued by
evidencing the delivery of the cylinder liners petitioner as full payment for the first
both contain the notation "subject to cylinder liner it ordered from respondent.
verification" under which the signature of Whereas in the first amended complaint,
Eric Go, petitioner's warehouseman, only nine post-dated checks were involved.
appeared.

ISSUE:
Due to the failure of the parties to settle the
matter, respondent filed an action for sum of
money and damages before the Regional 1. Whether or not respondent incurred
Trial Court (RTC) of Makati City. In its delay in performing its obligation
complaint, respondent (plaintiff below) under the contract of sale
alleged that despite its repeated oral and
written demands, petitioner obstinately
refused to settle its obligations. Respondent
2. Whether or not petitioner validly
prayed that petitioner be ordered to pay for
rescinded said contract.
the value of the cylinder liners plus accrued
interest of P111,300 as of May 1991 and
additional interest of 14% per annum to be
HELD: primordial and “once the intention of
the parties has been ascertained,
that element is deemed as an
1. NO integral part of the contract as
2. NO though it has been originally
expressed in unequivocal terms.”

RATIO: As an aside, let it be underscored


that “[e]ven where time is of the
essence, a breach of the contract in
1. In determining whether time is of the that respect by one of the parties
essence in a contract, the ultimate may be waived by the other party’s
criterion is the actual or apparent subsequently treating the contract
intention of the parties and before as still in force.” Petitioner’s receipt
time may be so regarded by a court, of the cylinder liners when they were
there must be a sufficient delivered to its warehouse on 20
manifestation, either in the contract April 1990 clearly indicates that it
itself or the surrounding considered the contract of sale to be
circumstances of that intention. still subsisting up to that time.
Petitioner insists that although its Indeed, had the contract of sale
purchase orders did not specify the been cancelled already as claimed
dates when the cylinder liners were by petitioner, it no longer had any
supposed to be delivered, business receiving the cylinder
nevertheless, respondent should liners even if said receipt was
abide by the term of delivery “subject to verification.” By
appearing on the quotation it accepting the cylinder liners when
submitted to petitioner. Petitioner these were delivered to its
theorizes that the quotation warehouse, petitioner indisputably
embodied the offer from respondent waived the claimed delay in the
while the purchase order delivery of said items.
represented its (petitioner’s)
acceptance of the proposed terms 2. Their having been no failure on the
of the contract of sale. Thus, part of the respondent to perform its
petitioner is of the view that these obligation, the power to rescind the
two documents “cannot be taken contract is unavailing to the
separately as if there were two petitioner. Article 1191 of the New
distinct contracts.” We do not agree. Civil Code runs as follows: The
It is a cardinal rule in interpretation power to rescind obligations is
of contracts that if the terms thereof implied in reciprocal ones, in case
are clear and leave no doubt as to one of the obligors should not
the intention of the contracting comply with what is incumbent upon
parties, the literal meaning shall him. The law explicitly gives either
control. However, in order to party the right to rescind the
ascertain the intention of the parties, contract only upon the failure of the
their contemporaneous and other to perform the obligation
subsequent acts should be assumed thereunder. The right,
considered. While this Court however, is not an unbridled one.
recognizes the principle that This Court in the case of University
contracts are respected as the law of the Philippines v. De los Angeles,
between the contracting parties, this speaking through the eminent civilist
principle is tempered by the rule that Justice J.B.L. Reyes, exhorts: Of
the intention of the parties is course, it must be understood that
the act of a party in treating a
contract as cancelled or resolved on
account of infractions by the other On March 18, 1996, spouses Johnson and
contracting party must be made Evangeline Sy secured a loan from Land
known to the other and is always Bank Legazpi City in the amount of PhP 16
provisional, being ever subject to million. The loan was secured by three (3)
scrutiny and review by the proper residential lots, five (5) cargo trucks, and a
court. If the other party denied that warehouse. Under the loan agreement, PhP
rescission is justified, it is free to 6 million of the loan would be short-term and
resort to judicial action in its own would mature on February 28, 1997, while
behalf, and bring the matter to court. the balance of PhP 10 million would be
Then, should the court, after due payable in seven (7) years.
hearing, decide that the resolution of
the contract was not warranted, the Subsequently, however, the Spouses Sy
responsible party will be sentenced found they could no longer pay their loan.
to damages; in the contrary case, On December 9, 1996, they sold three (3) of
the resolution will be affirmed, and their mortgaged parcels of land for PhP
the consequent indemnity awarded 150,000 to Angelina Gloria Ong,
to the party prejudiced. (Emphasis Evangeline’s mother, under a Deed of Sale
supplied) In other words, the party with Assumption of Mortgage.
who deems the contract violated
Evangeline’s father, petitioner Alfredo Ong,
may consider it resolved or
later went to Land Bank to inform it about
rescinded, and act accordingly,
the sale and assumption of mortgage. Atty.
without previous court action, but it
Edna Hingco, the Legazpi City Land Bank
proceeds at its own risk. For it is
Branch Head, told Alfredo and his counsel
only the final judgment of the
Atty. Ireneo de Lumen that there was
corresponding court that will
nothing wrong with the agreement with the
conclusively and finally settles
Spouses Sy but provided them with
whether the action taken was or was
requirements for the assumption of
not correct in law. But the law
mortgage. They were also told that Alfredo
definitely does not require that the
should pay part of the principal which was
contracting party who believes itself
computed at PhP 750,000 and to update
injured must first file suit and wait for
due or accrued interests on the promissory
a judgment before taking
notes so that Atty. Hingco could easily
extrajudicial steps to protect its
approve the assumption of mortgage. Two
interest. Otherwise, the party injured
weeks later, Alfredo issued a check for PhP
by the other’s breach will have to
750,000 and personally gave it to Atty.
passively sit and watch its damages
Hingco. A receipt was issued for his
accumulate during the pendency of
payment. He also submitted the other
the suit until the final judgment of
documents required by Land Bank, such as
rescission is rendered when the law
financial statements for 1994 and 1995. Atty.
itself requires that he should
Hingco then informed Alfredo that the
exercise due diligence to minimize
certificate of title of the Spouses Sy would
its own damages.
be transferred in his name but this never
Land Bank of the Philippines v. Ong materialized. No notice of transfer was sent
to him.
GR No. 190755, 19 November 2004
Alfredo later found out that his application
for assumption of mortgage was not
FACTS: approved by Land Bank. The bank learned
from its credit investigation report that the
Ong’s had a real estate mortgage in the disapproval of the assumption of mortgage
amount of PhP 18,300,000 with another but was just told that the accounts of the
bank that was past due. Alfredo claimed that spouses Sy had matured and gone unpaid.
this was fully paid later on. Nonetheless,
Land Bank foreclosed the mortgage of the The CA affirmed the RTC Decision. It held
Spouses Sy after several months. Alfredo that Alfredo’s recourse is not against the Sy
only learned of the foreclosure when he saw spouses. According to the appellate court,
the subject mortgage properties included in the payment of PhP 750,000 was for the
a Notice of Foreclosure of Mortgage and approval of his assumption of mortgage and
Auction Sale at the RTC in Tabaco, Albay. not for payment of arrears incurred by the
Alfredo’s other counsel, Atty. Madrilejos, Sy spouses. As such, it ruled that it would
subsequently talked to Land Bank’s lawyer be incorrect to consider Alfredo a third
and was told that the PhP 750,000 he paid person with no interest in the fulfillment of
would be returned to him. the obligation under Article 1236 of the Civil
Code. Although Land Bank was not bound
On December 12, 1997, Alfredo initiated an by the Deed between Alfredo and the
action for recovery of sum of money with Spouses Sy, the appellate court found that
damages against Land Bank in Civil Case Alfredo and Land Bank’s active preparations
No. T-1941, as Alfredo’s payment was not for Alfredo’s assumption of mortgage
returned by Land Bank. Alfredo maintained essentially novated the agreement.
that Land Bank’s foreclosure without
informing him of the denial of his assumption ISSUE:
of the mortgage was done in bad faith. He
argued that he was lured into believing that
his payment of PhP 750,000 would cause Whether or not the assumption of
Land Bank to approve his assumption of the mortgage novated the agreement.
loan of the Spouses Sy and the transfer of
the mortgaged properties in his and his
wife’s name.
HELD:
Testifying for Land Bank, Atty. Hingco
claimed during trial that as branch manager
she had no authority to approve loans and NO
could not assure anybody that their
assumption of mortgage would be approved.
RATIO:
According to Atty. Hingco, the bank
processes an assumption of mortgage as a
new loan, since the new borrower is
On the matter of novation, Spouses
considered a new client. They used
Benjamin and Agrifina Lim v. M.B. Finance
character, capacity, capital, collateral, and
Corporation, 508 SCRA 556 (2006),
conditions in determining who can qualify to
provides the following discussion: Novation,
assume a loan. Alfredo’s proposal to
in its broad concept, may either be extinctive
assume the loan, she explained, was
or modificatory. It is extinctive when an old
referred to a separate office, the Lending
obligation is terminated by the creation of a
Center.
new obligation that takes the place of the
former; it is merely modificatory when the
The RTC held that the contract approving
old obligation subsists to the extent it
the assumption of mortgage was not
remains compatible with the amendatory
perfected as a result of the credit
agreement. An extinctive novation results
investigation conducted on Alfredo. It noted
either by changing the object or principal
that Alfredo was not even informed of the
conditions (objective or real), or by On the evening of 6 July 2004, AMA
substituting the person of the debtor or removed all its office equipment and
subrogating a third person in the rights of furniture from the leased premises. The
the creditor (subjective or personal). Under following day, New World received a letter
this mode, novation would have dual from AMA dated 6 July 2004 stating that the
functions one to extinguish an existing former had decided to pre terminate the
obligation, the other to substitute a new one contract effective immediately on the ground
in its place requiring a conflux of four of business losses due to a drastic decline in
essential requisites: (1) a previous valid enrollment. AMA also demanded the refund
obligation; (2) an agreement of all parties of its advance rental and security deposit.
concerned to a new contract; (3) the
extinguishment of the old obligation; and New World replied in a letter dated 12 July
(4) the birth of a valid new obligation. x x 2004, to which was attached a Statement of
x Account indicating the following amounts to
be paid by AMA. Despite the meetings
We do not agree, then, with the CA in between the parties, they failed to arrive at a
holding that there was a novation in the settlement regarding the payment of the
contract between the parties. Not all the foregoing amounts.
elements of novation were present. Novation
must be expressly consented to. Moreover, On 27 October 2004, New World filed a
the conflicting intention and acts of the complaint for a sum of money and damages
parties underscore the absence of any against AMA before the Regional Trial Court
express disclosure or circumstances with of Marikina City, Branch 156 (RTC).
which to deduce a clear and unequivocal
intent by the parties to novate the old According to the RTC, AMA never denied
agreement. that it had arrearages equivalent to two
months rent. Other than its allegation that it
New World Developers and Management did not participate in the preparation of the
Inc. v. AMA Computer Center, Inc. Statement of Account, AMA did not proffer
GR No. 187930, 23 February 2015 any evidence disputing the unpaid rent. For
its part, New World clearly explained the
FACTS: existence of the arrears.

While sympathizing with AMA in view of its


New World is the owner of a commercial business losses, the RTC ruled that AMA
building located in Manila. In 1998, AMA could not shirk from its contractual
agreed to lease the entire second floor of obligations, which provided that it had to pay
the building for its computer-learning center, liquidated damages equivalent to six months
and the parties entered into a Contract of rent in case of a pre termination of the lease.
Lease covering the eight-year period.
In the assailed Decision dated 22 January
The monthly rental for the first year was set 2009, the CA ordered AMA to pay New
at 181,500, with an annual escalation rate World.
equivalent to 15% for the succeeding years.
It was also provided that AMA may pre The CA also ruled that the RTC’s imposition
terminate the contract by sending notice in of liquidated damages equivalent to six
writing to New World at least six months months rent was iniquitous. While conceding
before the intended date. In case of pre that AMA was liable for liquidated damages
termination, AMA shall be liable for for pre terminating the lease, the CA also
liquidated damages in an amount equivalent recognized that stipulated penalties may be
to six months of the prevailing rent. equitably reduced by the courts based on its
sound discretion. Considering that the
unexpired portion of the term of lease was This Court is, first and foremost, one
already less than two years, and that AMA of law. While we are also a court of
had suffered business losses rendering it equity, we do not employ equitable
incapable of paying for its expenses, the CA principles when well-established
deemed that liquidated damages equivalent doctrines and positive provisions of
to four months rent was reasonable. the law clearly apply.

ISSUE:
The law does not relieve a party
from the consequences of a contract
1. Whether AMA is liable to pay six it entered into with all the required
months worth of rent as liquidated formalities. Courts have no power to
damages. ease the burden of obligations
2. Whether AMA remained liable for voluntarily assumed by parties, just
the rental arrears. because things did not turn out as
expected at the inception of the
HELD: contract. It must also be
emphasized that AMA is an entity
that has had significant business
1. YES experience, and is not a mere babe
2. NO in the woods.

RATIO: The fundamental rule is that a


contract is the law between the
parties. Unless it has been shown
1.
that its provisions are wholly or in
That [AMA] may pre-terminate this
part contrary to law, morals, good
Contract of Lease by notice in
customs, public order, or public
writing to [New World] at least six (6)
policy, the courts will strictly enforce
months before the intended date of
the contract.
pre termination, provided, however,
that in such case, [AMA] shall be
liable to [New World] for an amount
equivalent to six (6) months current 2. AMA assails the CA ruling mainly for
rental as liquidated damages; the imposition of legal interest on
the rent in arrears. AMA argues that
the advance rental has extinguished
its obligation as to the arrears. Thus,
Quite notable is the fact that AMA
it says, there is no more basis for
never denied its liability for the
the imposition of interest at the rate
payment of liquidated damages in
of 6% per annum from the date of
view of its pre termination of the
extrajudicial demand on 12 July
lease contract with New World.
2004 until the finality of the
What it claims, however, is that it is
Decision, plus interest at the rate of
entitled to the reduction of the
12% per annum from finality until full
amount due to the serious business
payment.
losses it suffered as a result of a
drastic decrease in its enrollment.

At this juncture, it is necessary to


look into the contract to determine
the purpose of the advance rental
and security deposit.

At the time of the pretermination of


the contract of lease, the monthly
rent stood at P233,310, inclusive of
taxes; hence, the two-month rental
arrears in the amount of P466,620.

Applying the security deposit of


P450,000 to the arrears will leave a
balance of P16,620 in New World’s
favor.

Given that we have found AMA


liable for liquidated damages
equivalent to six months’ rent in the
amount of P1,399,860 (monthly rent
of P233,310 multiplied by 6
months), its total liability to New
World is P1,416,480.

We then apply the advance rental of


P450,000 to this amount to arrive at
a total extinguishment of the liability
for the unpaid rentals and a partial
extinguishment of the liability for
liquidated damages. This shall leave
AMA still liable to New World in the
amount of P966,480 (P1,416,480
total liability less P450,000 advance
rental).

You might also like