9.1.3.2 Installation of Bypass Tray Only 3. Ensure that the power is turned OFF.

Procedure NOTE The sequence for checking the power is different depending on the
1. Open and check the packaged accessories. machine models. Check carefully for the applicable models described in
• Bypass Tray Bundled Items the procedures before proceeding with the appropriate procedures.
No. Name Qty Japan IBG [100V Models] Ensure that the power of the AC unit, IOT and IIT are
1 Bypass Tray 1 O O turned OFF.
2 Screw 2 O O [200V Models] Ensure that the power of the AC unit and IOT are turned
OFF.

j0fu91xxH

• Bypass Installation Kit (HCF not installed) Bundled Items


No. Name Qty Japan IBG
1 MSI Feed Out Chute 1 O O
2 MSI Gear Assembly 1 O O
3 Deltite Tap Screw 3 O O
j0fu81999

4. Remove the tape and securing material.


5. Replace the IOT Side HCF Chute with the MSI Feed Out Chute.
(1) Remove the Left Upper Cover.

j0fu91xxL

2. Check the exterior.

j0fu91017

9-31 9.1 Installation of Device


Chapter 9 Installation
9-32 Chapter 9 Installation
9.1 Installation of Device

(2) Disconnect the connector on the right side of the IOT Side HCF Chute. (4) Install the MSI Gear Assembly with the screws (x3).

j0fu91145 j0fu910619

(3) Remove the screws (x3) and remove the IOT Side HCF Chute. (5) Remove the screw on the Takeaway Upper Chute and slide it forward.

j0fu91147
j0fu91146
(6) Install the MSI Chute Assembly on the Main Unit. (8) Install the Left Upper Cover on the Main Unit with the screws (x2).

j0fu91019 j0fu91017

(7) Connect the connectors. 6. Install the Bypass Tray on the Main Unit.
(1) Install the Bypass Tray on the Main Unit with the screws (x2).

j0fu91020 0fu911097

9-33 9.1 Installation of Device


Chapter 9 Installation
9-34 Chapter 9 Installation
9.1 Installation of Device

(2) Connect the Lattice connector of the Bypass Tray to the Main Unit. (2) Check the following items:
• Machine operation
• Paper run
• Image quality
• Strange noises
• Odor
• Other trouble
(3) If no problems are found, turn OFF the power.
NOTE The sequence for turning OFF the power is different depending on
the machine models. Check carefully for the applicable models
described in the procedures before proceeding with the appropriate
procedures.
[100V Models] Turn OFF the power of the IIT followed by the IOT and
AC unit.
j0fu910661 [200V Models] Turn OFF the power of the IOT followed by the AC
unit.
7. Load paper in the tray.
8. Check the operation.
(1) Connect the power plug and turn ON the power.
NOTE The sequence for turning ON the power is different depending on the
machine models. Check carefully for the applicable models
described in the procedures before proceeding with the appropriate
procedures.
[100V Models] Turn ON the power of the AC unit followed by the IOT
and IIT.
[200V Models] Turn ON the power of the AC unit followed by the IOT.

j0fu81999

(4) Unplug the power cord.

j0fu81999