You are on page 1of 9

IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 29, NO.

6, DECEMBER 2014 2605

Relevant Parameters in a Statistical


Analysis—Application to
Transmission-Line Energization
Patricia Mestas, Student Member, IEEE, and Maria Cristina Tavares, Senior Member, IEEE

Abstract—This paper summarizes the important factors that af- a standard deviation that represent the Gaussian distribution of
fect statistical switching transients studies during transmission- the pole spread. For this reason, the CB modeling requires that
line energization. These factors include the number of repetitions each pole be modeled independently from each other [5], [6].
to ensure the statistical characteristic of the study, the variation
range of the mean closing time of the circuit-breaker contacts, the On the other hand, during transmission-line switching opera-
model used for the representation of the transmission line, and the tions, several parameters affect the magnitude of transient over-
influence of transposition. In addition, a statistical analysis of mit- voltages on the line [2], [6]. These parameters can be distin-
igation methods to reduce overvoltages during transmission-line guished in two types: parameters that define the statistic sim-
energization maneuver is presented, specifically the use of surge ulation method and parameters related to the transmission-line
arresters, of controlled switching, and of a preinsertion resistor.
The shunt compensation degree is considered as an independent modeling.
parameter. Digital simulations were performed with PSCAD. The relevant parameters for the simulation method include
the determination of the number of repetitions required to ensure
Index Terms—Controlled switching, preinsertion resistor, statis-
tical analysis, surge arresters, transmission-line energization. the statistical significance of the study [7]. Besides, for line en-
ergization, the closing mean time must be distributed uniformly
over a given period [4]. Therefore, it is important to verify if the
I. INTRODUCTION period of variation (1 or 1/2cycle) of the fundamental frequency
produces results statistically different.

T HE determination of switching overvoltages is of funda-


mental importance for the design of electric power sys-
tems, since it provides the basis for insulation coordination of
Likewise, related to transmission-line modeling, it is impor-
tant to verify if the use of constant parameter line model [8]
or the frequency-dependent line model [9] will produce results
lines and substations, as well as for the equipment specifica- significantly different. Another important verification is if repre-
tion [1]. In turn, the insulation level required to withstand the senting the actual transposition scheme of the transmission line
switching overvoltages can have a significant influence on the compared to an assumed ideally transposed line (balanced line)
cost of transmission systems. Therefore, an accurate estimation has an influence on the overvoltage magnitude [10].
of the switching overvoltages magnitude under various condi- Another important factor during the transmission-line ener-
tions of operation is decisive for the project of transmission sys- gization study is the method used to mitigate transient overvolt-
tems [2]. ages in order to improve power-quality levels. The most used
The switching surge magnitudes depend upon the instant on techniques are surge arresters, controlled switching, and prein-
the voltage waveform at which the circuit-breaker contacts close sertion resistors. Each of these methods is directly related to the
electrically. Consequently, for the overvoltages evaluation, sta- CBs characteristics [3], [11] and should be analyzed considering
tistical studies should be performed because the closing instant the randomness of the event (CB eventual closing moment).
of the circuit breaker (CB) is characterized by a random be- Based on a case study of an actual power system, this paper
havior [2]–[4]. aims to evaluate switching transients during transmission-line
The CB randomness in the final closing instant can be mod- energization, taking into account diverse factors in a general
eled in electromagnetic programs through statistical switches. way. In addition, the possibilities of reducing switching surges
The closing instants of CBs must be defined for each phase are illustrated from the viewpoint of the statistical behavior of
switch by a mean value related to the closing mean instant and the CB. Also, the standard deviation, important statistical pa-
rameters of the CB, is analyzed for each overvoltage control
Manuscript received October 10, 2013; revised February 06, 2014; accepted method.
April 04, 2014. Date of publication July 01, 2014; date of current version
November 18, 2014. This work was supported in part by a grant from São
Paulo Research Foundation-FAPESP, and in part from CNPq, Brazil. Paper no.
TPWRD-01152-2013. II. ANALYZED SYSTEM
The authors are with the School of Electrical and Computer Engineering, Uni-
versity of Campinas (UNICAMP), Campinas 13083-250, SP, Brazil (e-mail: Fig. 1 shows the analyzed system based on an actual transmis-
pmestasv@dsce.fee.unicamp.br; cristina@dsce.fee.unicamp.br).
sion system of 500 kV and 1052 km. The study is focused on
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. the final line section, which corresponds to a 252-km-long line
Digital Object Identifier 10.1109/TPWRD.2014.2317875 from bus B4 to B5. The line was switched using the CB7 CB.

0885-8977 © 2014 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
2606 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 29, NO. 6, DECEMBER 2014

Fig. 1. The 500-kV transmission system.

TABLE I
BASIC LINE UNITARY PARAMETERS 60 Hz

Fig. 2. Closing instants defined by a mean value and a standard deviation ,


associated with variation over a given time period by uniform distribution.

The compensation scheme is composed of three single-phase


reactors banks with a quality factor (X/R) of 400, grounded It is possible to observe in Fig. 2 that about 68% of values
through a neutral reactor with a quality factor of 40. drawn are within one standard deviation away from the mean
The line parameters for the fundamental frequency (60 Hz) (area under the points to ). About 95% of the values lies
are shown in Table I. within two standard deviations (area under the points to );
The transient analysis and power system modeling were car- and about 99.7% is within three standard deviations (area under
ried out through simulations by using PSCAD [12]. The time the points to ).
step used for all simulations was 50 s. The statistical analysis The closing speed of CB poles is subject to variations deter-
was performed using the software OriginPro 8 [13]. mined by the temperature, the wear, and other factors. The CB
model accommodates these variations in the closing pole spread
III. STATISTICAL BEHAVIOR OF THE CB
according to normal distribution.
The statistical nature of the overvoltages is caused by the ran- Some of the operating time variations are predictable and
domness in which each pole of the CB connects the line to the some are purely statistical. The CB operating time is ex-
voltage source. Thus, the mechanical poles spread, the instant pressed as the sum of three terms [14]
in the fundamental frequency cycle at which the command of
the operation is done, and the electric arc established between (1)
the contacts before its closing determine the effective circuit
breaker’s closing [2], [6]. is the mean operating time under normal operating con-
The nonsimultaneity of the mechanical closing of the CB con- ditions that can be measured. is a predictable varia-
tacts can be simulated by systematic or statistical switches [4]. tion of the operating time that can be corrected. is a
For the systematic switches, the closing instant is varied purely statistical variation of the operating time. Closing mean
in equal increments between a minimum and a maximum, time (point ) indicated in Fig. 2 is the sum of .
searching the maximum overvoltages. For the statistical The parcel represents the randomness of the closing
switches, two steps are necessary. First, the closing mean event, and the statistical results are not compromised by the
time should be varied over a given time period by uniform nominal closing time, even if it represents a high-speed CB.
distribution. Second, the pole span should be represented with a The electric arc occurs when, during the contacts approxi-
statistical parameter, typically a Gaussian (normal) distribution. mation, the potential difference between them exceeds the de-
Fig. 2 shows an example to illustrate the statistical switch creasing voltage of the dielectric withstand. The electric arc is
behavior. The closing command corresponds to the closing another random parameter in the generation of transients; how-
mean time (point ), which is issued randomly with respect ever, in [15], it is reported that its effect is minimal in high-speed
to the phase angle of the reference signal. Since the statistical CBs. Otherwise, its effect can be easily included in the analysis
switching case consists of a given number of separate simu- by increasing the maximum mechanical dispersion between CB
lations, the closing mean time must be varied with a uniform poles.
distribution from point to point (01 cycle of the power In the present study, SF gas live-tank CBs were assumed to
frequency). have been installed on the power system. The statistical perfor-
The pole spread of the CB has a statistical behavior according mance of this CB has been represented in PSCAD by a statis-
to a normal distribution and is expressed in standard deviation tical switch, according to [15]. A high-speed CB with a closing
. The maximum pole spread of the CB is information time of 13 ms at each pole was selected. The standard deviation
normally provided in the CBs manufacturer specifications and is 1 ms, and the normal distribution curve is truncated at
is linked to the CB by the truncation of the Gaussian curve. and .
MESTAS AND TAVARES: RELEVANT PARAMETERS IN A STATISTICAL ANALYSIS—APPLICATION TO TRANSMISSION-LINE ENERGIZATION 2607

IV. STATISTICAL EVALUATION TABLE II


TRANSIENT OVERVOLTAGES AT LINE END. ANALYSIS
The overvoltage magnitudes generated during line energiza- OF THE NUMBER OF SIMULATIONS
tion follow a normal distribution (verified by the Kolmogorov-
Smirnov test). Therefore, the analysis of variance (ANOVA)
can be used for the statistical evaluation of overvoltages mag-
nitude [7].
ANOVA is essentially an inferential analysis procedure for
testing the statistical significance among different groups of data
for homogeneity. It is a robust test because it is not limited to
comparing the means of only two groups [7].
-test is part of the ANOVA process. It is used to assess
whether the expected values of a quantitative variable within
several predefined groups differ from each other [7].
The following aspects were evaluated:
• minimum number of simulations to ensure the statistical
significance of the study;
• the range variation of the mean closing time of CB con-
tacts;
• model used to represent the transmission line;
• influence of the line transposition scheme on the results of
overvoltages. TABLE III
The shunt compensation degree was taken as an independent ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT THE LINE END.
MINIMUM NUMBER OF ENERGIZATIONS
parameter.

A. Number of Simulations
In order to determine the number of simulations necessary to
ensure the statistical representation of the study, different num-
bers of shots were analyzed, specifically: 100, 200, 300, 400,
and 500 simulations of the transmission-line energization, each
using a different set of CB closing times.
The multiple run feature available in PSCAD, making use of
a random number generator, enables a new selection of closing
mean times for the CB to be applied for each multiple case.
The breaker closing is initiated randomly over a period of one **Significance level of 1%
cycle (in this case, more than 16.67 ms) and each pole closes BG: between group; WG: within group
according to [15] over a spread defined by a normal distribu-
tion with the specified mean and standard deviation. The com- The ANOVA test was applied to establish if there exist sta-
bination of both factors enables achieving a different set of CB tistically significant differences between groups, as shown in
closing times for each simulation, which results in nonrepeat- Table III.
able tests. The results of the ANOVA test do not show statistically sig-
The line was considered ideally transposed and the depen- nificant differences between groups. That means that the shots
dence of the longitudinal parameters with the frequency was number (100, 200, 300, 400, or 500) will result in similar over-
modeled using the frequency-dependent (Phase) transmission- voltage profiles.
line model [9]. The existing surge arresters of the line ends were Since the shot number results in similar overvoltages, either
not represented so that the worst overvoltages were not limited option can be used for simulations. Due to the processing speed
by such devices. of current computers, for this paper a central value was selected:
The energization was performed at the final section of the in this case, 300 runs.
transmission line (Fig. 1). The shunt reactive compensation of
this line section was varied for 90, 70, and 50%. B. Mean Closing Time
Table II presents a summary of the maximum, mean, stan- This analysis aims to determine if the variation of the range
dard deviation, and coefficient of variation (CV) obtained for for the mean closing time over 1 or 1/2 cycle of the fundamental
the overvoltages at the open end of the transmission line. frequency influences the overvoltages magnitude.
As expected, the overvoltage magnitude increases with a de- As in the previous analysis, the line was considered as ide-
creasing compensation level. However, for each compensation ally transposed and the frequency dependence of the line longi-
level, there is a similarity between the results of the groups com- tudinal parameters was modeled using the frequency-dependent
posed of a different number of simulations. (phase) model.
2608 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 29, NO. 6, DECEMBER 2014

TABLE IV TABLE VI
TRANSIENT OVERVOLTAGES AT LINE-END. ANALYSIS OF MEAN TRANSIENT OVERVOLTAGES AT LINE END. ANALYSIS OF
TIME VARIATION TRANSMISSION-LINE MODEL INFLUENCE

TABLE VII
TABLE V ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT LINE END.
ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT LINE END. MEAN TRANSMISSION-LINE MODEL INFLUENCE
TIME VARIATION

was performed for 90, 70, and 50% of shunt compensation. The
surge arresters at the line ends were not represented.
For each range, 300 shots were performed (01 cycle or Table VI shows the comparison of the results obtained. For
cycle). The analysis was conducted for 90, 70, and 50% of shunt the three compensation levels, it is possible to verify higher
compensation. overvoltages magnitude when the transmission line is modeled
Table IV shows that both ranges of variation present similar through the Bergeron model.
overvoltage magnitude for each compensation level. Table VII shows the results of the ANOVA test. Comparing
Through the -test of ANOVA shown in Table V, it can be the values, it can be seen that statistically significant differ-
concluded that the fact of adopting 1 or 1/2 cycle of the funda- ences exist between the two study groups regarding the trans-
mental frequency, as the range of variation for the mean closing mission-line model.
time, does not alter the results concerning the maximum tran- The results are consistent because the resistive part of the
sient overvoltages at the end of the transmission line. line series impedance increases with the frequency, resulting
From the results, the statistical studies of transmission-line in greater transient attenuation. Consequently, when the line is
energization are proposed, and the closing instants can be dis- represented by constant longitudinal parameters, the switching
tributed uniformly over 1 cycle of the fundamental frequency. overvoltages will have higher values. However, these results
will not be observed in the field.
C. Transmission-Line Model The Bergeron model should not be used for transient studies.
The goal of this evaluation is to verify if the results for line In contrast, the phase model will give more accurate represen-
energization will vary when a different line model is used. tation for a wide range of frequencies contained in the transient
For this purpose, the following transmission-line models phenomena, compared to the constant parameter line model.
were analyzed:
D. Line Transposition
1) line model with constant frequency parameters or Berg-
eron model [8]; Transmission lines employ phase transposition in order to min-
2) line model with frequency dependence of longitudinal pa- imize their own unbalance. In a practical sense, this is achieved by
rameters represented or phase model [9]. periodically rotating the phase positions in the circuit [10]. In gen-
For each transmission-line model, 300 shots were performed eral, in Brazil, the transposition scheme is commonly used, which
and one cycle of the fundamental frequency was considered for uses three towers such that the lines are divided into four parts,
the variation of the range for the mean closing time. The analysis respectively, with , , , and of its length.
MESTAS AND TAVARES: RELEVANT PARAMETERS IN A STATISTICAL ANALYSIS—APPLICATION TO TRANSMISSION-LINE ENERGIZATION 2609

TABLE VIII TABLE IX


TRANSIENT OVERVOLTAGES AT THE LINE END. ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT THE LINE END.
INFLUENCE OF LINE TRANSPOSITION INFLUENCE OF LINE TRANSPOSITION.

Ideal transposition is a mathematical average of the unbal-


anced line. This is equivalent to visualizing an infinite number of
transposition cycles, where the line segment length approaches and to evaluate the overvoltages control methods in statistical
zero. The result is a series impedance matrix and a shunt admit- terms.
tance matrix that are perfectly symmetrical and balanced [16]. For each of the three control methods, 300 shots were per-
Usually, in transient studies, such as the line energization, the formed; and one cycle of the fundamental frequency was con-
lines are represented as balanced lines (ideally transposed). sidered for the variation range of the mean closing time; the
In order to determine the influence of the transposition transmission line was modeled by the phase model with the ac-
scheme on the overvoltage magnitude, the transmission line tual transposition scheme. The analysis was performed for 90%
was modeled for the following cases: of shunt compensation, and the surge arresters at the line ends
were not represented, unless when it was the mitigation method.
1) transmission line ideally transposed (IT);
2) transmission line with real transposition scheme (RT) A. Metal–Oxide Surge Arresters
(transposition scheme 1/6-1/3-1/3-1/6).
The modern metal–oxide surge arresters with lower pro-
For each transposition scheme, 300 shots were performed.
tection levels and higher energy dissipation capacity can be
The transmission line was represented by the phase model. One
very simple and potentially more economical devices to reduce
cycle of the fundamental frequency was considered for the vari-
switching overvoltages [3], [17].
ation range of the mean closing time. The analysis was per-
From the statistical perspective, when surge arresters are used
formed for 90, 70, and 50% of shunt compensation. The surge
as the control method, the closing of the CB is regarded as un-
arresters at the line ends were not represented.
controlled[11]. Fig. 3 shows the closing instants for each pole,
Table VIII shows that the line model used was decisive for the
during line energization.
results. In all cases analyzed, higher overvoltages were observed
In this case, an order to close the three phases at the same in-
when the line was modeled with an actual transposition scheme.
stant is sent, which means that the mean closing time is the
These results are coherent as the transposition will generate same for the three phases, but the individual operating instants
reflection points, making the voltage waveform noisier, re- of each phase follow a Gaussian distribution with a standard de-
sulting in higher overvoltages. viation; in this case, 1 ms was used. Angle represents the time
Table IX shows the results of ANOVA. In this case, the -test interval between the closing of the former and of the last pole.
shows statistically significant differences between treatments, The closing time variations are purely statistical, so each pole
depending on the line simulation with or without a real transpo- closes at a different instant. The time intervals between the in-
sition scheme. stant when the closing order is given, and the instants ,
From the obtained results, it is recommended that the trans- and when the poles 1, 2, and 3 effectively close are indicated
mission lines should be represented with the field-existing trans- by , , and .
position cycles and not through ideally transposed line models. For Brazilian 500-kV transmission lines, the surge arresters
normally specified are the metal–oxide type, having a rated
V. STATISTICAL ANALYSIS OF MITIGATION PROCEDURES voltage of 420 kV and a rated energy-absorption capacity of
As has been described before, closing the contacts of a CB 13 kJ/kV, which corresponds to a total absorption of 5.46 MJ.
are normally done in a totally random way and, consequently, The surge arresters were appropriately modeled according to
transient overvoltages may appear in the system. A typical way its V-I characteristic curve. Three classes of surge arresters were
for reducing overvoltages is to add components, such as surge analyzed:
arresters, resistors, or a combination of both. Nevertheless, it • Class 5–420-kV rated arrester with a protection level of
would also be possible to control these transients by operating 830 kV at 2 kA, normally specified for 500-kV Brazilian
the CB in synchronism with a voltage waveshape. transmission lines;
Since each of mentioned methods are directly related to the • Class 5–396-kV rated arrester with a protection level of
random behavior of CBs, this part of the paper aims to illustrate 783 kV at 2 kA; according to [3] and [17], this arrester
2610 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 29, NO. 6, DECEMBER 2014

TABLE X
TRANSIENT OVERVOLTAGES AT THE LINE END USING THE SURGE ARRESTER

TABLE XI
ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT THE LINE END.
SURGE ARRESTERS AS THE CONTROL METHOD

Fig. 3. Closing instants of CB poles. Surge arresters.

provided more effective performance and greater reduction


in overvoltages;
• Class 3–360 kV rated arrester with a protection level of
742 kV at 2 kA; this case was simulated with an illustra-
tive and comparative purpose because the appropriate se-
lection of the surge arrester is determined not only by the
protective level, but also by the operational characteristics
of the system as a whole.
The traditional solution of one arrester at each line terminal is
preferentially adopted, although a third arrester in the middle of
the line can bring further reduction of the line switching over-
voltages [3], [18]. However, technical-economical constraints
may not recommend the use of the latter solution. For the present
analysis, surge arresters were assumed to have been installed at
either ends of the transmission lines.
Table X shows representative values of overvoltages for the
three types of surge arresters analyzed. It can be seen that the
overvoltages magnitude are reduced as the surge arrester-rated Fig. 4. Closing instants of CB poles. Controlled switching.
voltage decreases.
Table XI shows the results of ANOVA. The -test confirms switching overvoltage. For transmission-line energization,
statistically significant differences between treatments. closing commands are delayed in such a way that switching
will occur very close to the voltage across CB zero crossing
B. Controlled Switching [3], [19].
The controlled switching involves the individual closing of Fig. 4 shows the closing instant for each pole. The sequence
each phase in the CB at the optimal point of wave to reduce starts closing the phase A at zero crossing, followed by the phase
MESTAS AND TAVARES: RELEVANT PARAMETERS IN A STATISTICAL ANALYSIS—APPLICATION TO TRANSMISSION-LINE ENERGIZATION 2611

TABLE XII
TRANSIENT OVERVOLTAGES AT THE LINE END USING CONTROLLED
SWITCHING.

TABLE XIII
ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT THE LINE END.
CONTROLLED SWITCHING AS A CONTROL METHOD

C and, finally, by phase B. In this case, the closing of the CB is


regarded as controlled.
Fig. 5. Closing instants of CB poles. No controlled switching.
The zero crossing instant of the voltage wave across the CB
corresponds to the closing mean time and of phases
A, C, and B, respectively; with 60 of delay between them. TABLE XIV
Values and are the time intervals from the TRANSIENT OVERVOLTAGES AT THE LINE END USING THE
PREINSERTION RESISTOR
closing command to the actual mechanical contact of poles 1, 2,
and 3, respectively. The effective closing instant , and
follow normal distribution.
The effectiveness of controlled switching depends on several
factors; the most important is the CB operating time consis-
tency. Breakers with a deviation in operating times (i.e., sta-
tistical scatter) of less than 1 ms and with a steep rate of
decay of dielectric strength (RDDS) are best suited for con-
trolled switching applications [18]–[20].
Furthermore, the CB must close fast enough so that the As shown in Fig. 5, when the CB is provided with a prein-
prestrike does not miss closing the phase at the voltage zero sertion resistor, the main and the auxiliaries’ contacts have tol-
crossing. In this regard, three values of CB closing time stan- erance in the closing instants. In the present study, two mean
dard deviation were analyzed: 1.0, 0.5, and 0.2 ms. values were adopted: and corresponding to the mean
Table XII shows the overvoltages magnitudes at the terminal time of the main contacts closing and the mean closing time of
receiver. The reduction of the standard deviation of the CB causes the auxiliary contacts, respectively. The instants , , and
a slight reduction of the maximum voltage at the line end. , correspond to the actual closing instant of the main
However, the results of the ANOVA test shown in Table XIII and auxiliary CBs, respectively.
do not report significant differences between groups, which The CB closing was considered uncontrolled. The mean time
means that overvoltages are statistically equal for the three of the main contacts of the CB closing is similar for the three
groups. It would not be necessary to specify a CB with ex- phases.
tremely small standard deviation. The mean closing time of the auxiliary CB contacts is also
similar for the three phases. In this sense, three standards devi-
C. Preinsertion Resistor ation values for the closing time of the auxiliary CB contacts
The traditional method to control switching overvoltages in were analyzed: 1.0, 0.5, and 0.2 ms. The objective of this varia-
transmission lines involves the installation of preinsertion resis- tion was to analyze the impact of the auxiliary CB precision on
tors in the CB. Although it is an effective method, its implemen- the magnitude of the overvoltages.
tation and maintenance costs are very high [3],[17],[18] Table XIV shows the overvoltages values. The reduction of
The closing resistors are inserted in series with the load auxiliary CB standard deviation does not imply reducing max-
circuit, acting as a voltage divider, being switched after a given imum voltage at the remote line terminal.
time, before closing the main contacts—thereby damping the From the results of ANOVA presented in Table XV, it is ver-
switching transient overvoltages. In this study, an existing ified that although the closing time precision of the auxiliary
400- resistor was simulated, with an insertion mean time of CB is increased by the reduction of the standard deviation, this
8 ms. factor does not influence overvoltages magnitude.
2612 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 29, NO. 6, DECEMBER 2014

TABLE XV 3) Regarding the transmission-line model, it is strongly rec-


ANALYSIS OF VARIANCE OF MAXIMUM OVERVOLTAGES AT THE LINE END. ommended that a model that properly represents the fre-
PREINSERTION RESISTOR AS THE CONTROL METHOD
quency dependence of longitudinal parameters be used. A
simple model like the Bergeron model should be avoided.
4) Regarding the line transposition, the actual transposition
should be modeled, and the line should not be considered
as a balanced one.
Another important contribution presented in this paper is the
statistical analysis of mitigation methods applied to the trans-
mission-line energization maneuver. It can be stated that the
characteristics of low protective levels and high-discharge en-
ergy capabilities of the modern surge arresters provide a poten-
tially economical device. The preinsertion resistor method has
better performance to reduce the overvoltages; however, the re-
sults for controlled switching methods are just slightly higher.
It is suggested then that the controlled switching method should
be used for mitigating transmission-line energization overvolt-
ages instead of the preinsertion resistor due to the drawbacks of
the latter method, such as higher implementation and mainte-
nance costs.

REFERENCES
[1] J. D. Glover, M. S. Sarma, and T. J. Overbye, Power System Anal-
ysis and Design, 4th ed. Independence, KY, USA: Cengage Learning,
Fig. 6. Comparison of maximum overvoltages at the line end. 2008.
[2] A. I. Ibrahim and H. W. Dommel, “A knowledge base for switching
surge transients,” presented at the Int. Conf. Power Syst. Transients,
Montreal, QC, Canada, 2005.
D. Comparative Analysis of Control Methods [3] A. C. Carvalho, M. Lacorte, and O. O. Knudsen, “Improved EHV line
switching surge control by application of MO-arrester and controlled
Since several alternatives among each mitigation method switching,” in Proc. Int. Conf. Energy Manage. Power Del., 1995, pp.
were studied, just the following items were considered for 292–297.
comparing the methods: [4] “ATP—Alternative Transient Program—Rule Book,” Leuven EMTP
Center, Herverlee, Belgium, 1987.
• the 396-kV rated voltage surge arrester;
[5] J. A. Martinez, R. Natarajan, and E. Camm, “Comparison of statistical
• the CB with a standard deviation of 0.5 ms for controlled switching results using Gaussian, uniform and systematic switching
switching; approaches,” in Proc. IEEE Power Eng. Soc. Summer Meeting, Seattle,
• preinsertion resistor. WA, USA, 2000, vol. 2, pp. 884–889.
[6] D. W. Durbak, A. M. Gole, E. H. Camm, M. Marz, R. C. Degeneff,
Fig. 6 shows a graphical comparison of the results of the ana- R. P. O’Leary, R. Natarajan, J. A. Martinez-Velasco, K. C. Lee,
lyzed methods. The preinsertion resistor method has better per- A. Morched, R. Shanahan, E. R. Pratico, G. C. Thomann, B. Sh-
formance to reduce the overvoltages; however, the difference perling, A. J. F. Keri, D. A. Woodford, L. Rugeles, V. Rashkes,
with the controlled switching is very small. Since the preinser- and A. Sharshar, “Modeling guidelines for switching transients,”
Model. Anal. Syst. Transients using Digital Syst., IEEE Special Publ.,
tion resistor has other drawbacks, controlled switching should TP-133-0, 1998.
be considered when overvoltages at the energization maneuver [7] D. C. Montgomery and G. C. Runger, Applied Statistics and Proba-
must be reduced. bility for Engineers, 3rd ed. Hoboken, NJ, USA: Wiley, 2003.
[8] J. R. Marti, L. Marti, and H. Dommel, “Transmission line models for
steady-state and transients analysis,” presented at the IEEE/NTUA
VI. CONCLUSION Athens Power Tech Conf., Athens, Greece, 1993.
[9] A. Morched, B. Gustavsen, and M. Tartibi, “A universal line model
The main contribution of this paper was the identification of
for accurate calculation of electromagnetic transients on overhead lines
relevant parameters in a transient study. The study was applied and cables,” IEEE Trans. Power Del., vol. 14, no. 3, pp. 1032–1038,
to transmission-line energization and the main results can be Jul. 1999.
summarized as follows. [10] A. V. Elguera, M. C. Tavares, and C. M. Portela, “Evaluating the im-
portance of properly representing actual transmission line transposition
1) Regarding the number of shots, in the range of 100 to 500, for electromagnetic transient studies,” presented at the Int. Conf. Power
no relevant statistical difference was observed. This means Syst. Transients, Lyon, France, 2007.
that the result will be the same if a study is performed either [11] L. Paris, “Basic considerations of magnitude reduction of switching
surges due to line energization,” IEEE Trans. Power App. Syst., vol.
with 100 or 500 shots. PAS-87, no. 1, pp. 295–305, Jan. 1968.
2) Regarding the variation range of the mean closing time [12] “PSCAD/EMTDC V4.2 User’s Guide,” HVDC Research Centre Inc.,
of CB contacts, no relevant statistical difference was ob- Winnipeg, MB, Canada, 2005.
served. Adopt either 1 or 1/2 cycle of the fundamental fre- [13] “Origin 8 User Guide,” OriginLab Corporation, 2007.
[14] J. H. Brunke and K. J. Fröhlich, “Elimination of transformer inrush
quency since the variation range of the mean closing time currents by controlled switching, part I,” IEEE Trans. Power Del., vol.
does not alter the results. 16, no. 2, pp. 276–280, Apr. 2002.
MESTAS AND TAVARES: RELEVANT PARAMETERS IN A STATISTICAL ANALYSIS—APPLICATION TO TRANSMISSION-LINE ENERGIZATION 2613

[15] D. A. Woodford and L. M. Wedepohl, “Transmission line energization Patricia Mestas (S’07) received the degree in electrical engineering from San
with breaker pre-strike,” in Proc. IEEE WESCANEX: Conf. Commun., Agustín de Arequipa University (UNSA), Arequipa, Peru, in 1998, and the M.Sc.
Power Comput., Canada, 1997, pp. 105–108. and Ph.D. degrees in electrical engineering–electrical energy from the University
[16] D. P. Kothari and I. J. Nagrath, Modern power system analysis, 3rd of Campinas (UNICAMP), Campinas, Brazil, in 2007 and 2011, respectively.
ed. New Delhi, India: Tata McGraw-Hill, 2003. From 2000-2003, she worked in the planning, assembly, and maintenance of
[17] L. Stenstrom and M. Mobedjina, “Limitation of switching overvoltages transmission lines. Currently, she is a Researcher with the School of Electrical
by use of transmission line surge arresters,” presented at the CIGRE and Computer Engineering, UNICAMP. Her main research interests include the
998 sc 33 Int. Conf., Zagreb, Croatia, 1998. study of electromagnetic transients, transmission lines, and digital simulations.
[18] P. V. Mestas and M. C. Tavares, “Comparative analysis of control
switching transient techniques in transmission lines energization Ma-
neuver,” Elect. Power Syst. Res., vol. 80, pp. 115–120, 2010. Maria Cristina Tavares (M’98–SM’08) received degrees in electrical engi-
[19] D. Goldsworthy, T. Roseburg, D. Tziouvaras, and J. Pope, “Controlled neering and the M.Sc. degree in electrical engineering from the Federal Uni-
switching of HVAC circuit breakers: Application examples and bene- versity of Rio de Janeiro (UFRJ), Rio de Janeiro, Brazil, in 1984 and 1991,
fits,” presented at the 61st Annu. Conf. Protect. Relay Eng., College respectively, and the D.Sc. degree in electrical engineering from the University
Station, TX, USA, 2008. of Campinas (UNICAMP), Campinas, Brazil, in 1998.
[20] P. Mestas, M. C. Tavares, and A. M. Gole, “Implementation and per- Currently, she is an Associate Professor at UNICAMP, where she has been
formance evaluation of a reclosing method for shunt reactor compen- since 2002. She has provided consultation for engineering firms and her main
sated transmission lines,” IEEE Trans. Power Del., vol. 26, no. 2, pp. interests are power system analysis, arc modeling, and very long distance trans-
954–962, Apr. 2011. mission systems.

You might also like