Date: November 7, 2018

To: Dr. Bruce


English 360 professor
California State University of Fullerton
From: Team I Can Fix That
Research Manager – Terrinda Alonzo

Subject: Progress Report for the iFixit replacement


guide for the ASUS K200MA-DS01T laptop.

Purpose
The purpose of this progress report on our iFixit replacement guides for the ASUS K200MA-
DS01T laptop is to demonstrate our groups progress of our project.

Summary
On October 3rd iFixit approved our proposal to create replacement guides for the ASUS
K200MA-DS01T laptop. We have completed 90% of the project and will be finished by
November 14th. We have completed our Group Charter, Progress Report 1, Group Proposal,
Trouble Shooting page, Device page, Progress Report 2, Progress Report 3, and one Completed
Guide. Before November 14 we will be finishing the rest of our guides along with Progress
Report 4 and an evaluation memo.

Problems Encountered
We have encountered a few problems such as not having enough overall steps for our guides as
well as scheduling dilemmas. To solve these problems we have added two more replacement
guides and are using our class time and weekends to work on what we need to accomplish in
person, Such as photography.
Completed iFixit tasks
Tasks W5 W6 W8 W10
Group 9/25
Charter
Progress 10/1
Report 1
Group 10/4
Proposal
Trouble 10/15
shooting
page
Device 10/17
page
Progress 10/17
Report 2
Progress 10/31
Report 3
1 10/31
Completed
Guide

Current work
Tasks W11 W12
Progress 11/7
Report
4
Eval 11/14
memo
Finals 11/14
Guides

Remaining Work
Tasks W13
Final 11/19
Project
Peer
review
Final 11/19
Project
Editing

Conclusion
We have successfully completed a group proposal, troubleshooting page, device page, and one
complete replacement guide. We project to be finished with the entire project on Wednesday
November 14 and will include in our Final Project Folder:
1. A one- to two-page memo evaluating your team’s performance and the iFixit project as a
whole. See page two of this document for instructions.
2. Team time sheet (compile your data into a single chart with a final total time for each team
member)
3. iFixit proposal with comments from iFixit
4. iFixit disassembly flow chart
5. Collected emails between your team and iFixit staff, arranged from earliest to latest.
6. The peer review sheet from the group that tested your iFixit guides.