You are on page 1of 17

State of Louisiana

Comprehensive Inspection Form - Gas Distribution Pipeline


Name of Owner:      
Unit:       Operated by:
HQ Address: System/Unit Name & Address:
           

Co. Official:       Operator contact:      


Title:       Phone No.:      
Phone No.:       Fax No.:      
Emergency Phone No.:       Emergency Phone No.:      
Persons Interviewed Title Phone No. E-mail address

                 


                 
                 
                 
                 
                 
                 
                 
Inspector:       Inspection Date(s)      
Company System Maps available for review?      

Unit Description
     

Portion of Unit Inspected:


     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 1
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

GAS SYSTEM OPERATIONS


Gas Supplier       Date:      
Residential Commercial Industrial Other
Unaccounted for       Services:                        
Gas:
MAOP Operating Pressure(s) (Within last year) Actual Operating Pressure
(At time of Inspection)
Feeder:                  
Town:                  
Other:                  
Does the operator have any transmission pipelines?      

49CFR PART 191

REPORTING PROCEDURES S U N/A N/C


.605(b)(4) Procedures for gathering data for incident reporting
191.5 Telephonically reporting incidents to NRC (800) 424-8802 La. DNR (225) 342-5505                
191.15(a) 30-day follow-up written report (Form 7100-2)                
191.15(b) Supplemental report (to 30-day follow-up)                
.605(a) 191.23 Reporting safety-related condition (SRCR)                
191.25 Filing the SRCR within 5 days of determination, but not later than 10 days after discovery                
.605(d) Instructions to enable operation and maintenance personnel to recognize potential Safety Related Conditions                

Comments:
     

49CFR PART 192

.13(c) CUSTOMER AND EFV INSTALLATION NOTIFICATION PROCEDURES S U N/A N/C


.16 Procedures for notifying new customers, within 90 days, of their responsibility for those selections of service
               
lines not maintained by the operator.
.381 If EFVs are installed, do they meet the performance requirements of §192.381?                
.383 Does the operator have a voluntary installation program for excess flow valves and does the program
               
meet the requirements outlined in §192.383? Are records adequate?
.383 If the operator does not have a voluntary program for EFV installations, are customers notified in
               
accordance with §192.383? Are records adequate?

.605(a) NORMAL OPERATING and MAINTENANCE PROCEDURES S U N/A N/C


.605(a) O&M Plan review and update procedure (1 per year/15 months)                
.605(b)(3) Making construction records, maps, and operating history available to appropriate operating personnel                
.605(b)(5) Start up and shut down of the pipeline to assure operation within MAOP plus allowable buildup                
.605(b)(8) Periodically reviewing the work done by operator’s personnel to determine the effectiveness and
adequacy of the procedures used in normal operation and maintenance and modifying the procedures                
when deficiencies are found
.605(b)(9) Taking adequate precautions in excavated trenches to protect personnel from the hazards of unsafe
accumulations of vapors or gas, and making available when needed at the excavation, emergency rescue                
equipment, including a breathing apparatus and a rescue harness and line
.605(b)(10) Routine inspection and testing of pipe-type or bottle-type holders                
.605(b)(11) Responding promptly to a report of a gas odor inside or near a building, unless the operator’s
               
emergency proced. under §192.615(a)(3) specifically apply to these reports.

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 2
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

Comments:
     

.605(a) CHANGE in CLASS LOCATION PROCEDURES S U N/A N/C


.609 Class location study                
.611 Confirmation or revision of MAOP                

Comments:
     

.613 CONTINUING SURVEILLANCE PROCEDURES S U N/A N/C


.613(a) Procedures for surveillance and required actions relating to change in class location, failures, leakage
history, corrosion, substantial changes in CP requirements, and unusual operating and maintenance                
conditions
.613(b) Procedures requiring MAOP to be reduced, or other actions to be taken, if a segment of pipeline is in
               
unsatisfactory condition

Comments:
     

.605(a) DAMAGE PREVENTION PROGRAM PROCEDURES S U N/A N/C


.614(c) Participation in a qualified one-call program, or if available, a company program that complies
with the following:
(1) Identify persons who engage in excavating                
(2) Provide notification to the public in the One Call area                
(3) Provide means for receiving and recording notifications of pending excavations                
(4) Provide notification of pending excavations to the members                
(5) Provide means of temporary marking for the pipeline in the vicinity of the excavations                
(6) Provides for follow-up inspection of the pipeline where there is reason to believe the
               
pipeline could be damaged
(i) Inspection must be done to verify integrity of the pipeline                
(ii) After blasting, a leak survey must be conducted as part of the inspection by the operator                

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 3
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

Comments:
     

.615 EMERGENCY PROCEDURES S U N/A N/C


.615(a)(1) Receiving, identifying, and classifying notices of events which require immediate response
               
by the operator
.615(a)(2) Establish and maintain communication with appropriate public officials regarding possible emergency                
.615(a)(3) Prompt response to each of the following emergencies:
(i) Gas detected inside a building                
(ii) Fire located near a pipeline                
(iii) Explosion near a pipeline                
(iv) Natural disaster                
.615(a)(4) Availability of personnel, equipment, instruments, tools, and material required at the scene of an
               
emergency
.615(a)(5) Actions directed towards protecting people first, then property                
.615(a)(6) Emergency shutdown or pressure reduction to minimize hazards to life or property                
.615(a)(7) Making safe any actual or potential hazard to life or property                
.615(a)(8) Notifying appropriate public officials required at the emergency scene and coordinating planned and
               
actual responses with these officials
.615(a)(9) Instructions for restoring service outages after the emergency has been rendered safe                

.615(a)(10) Investigating accidents and failures as soon as possible after the emergency                
.615(b)(1) Furnishing applicable portions of the emergency plan to supervisory personnel who are responsible
               
for emergency action
.615(b)(2) Training appropriate employees as to the requirements of the emergency plan and verifying
               
effectiveness of training
.615(b)(3) Reviewing activities following emergencies to determine if the procedures were effective                
.615(c) Establish and maintain liaison with appropriate public officials, such that both the operator and public
               
officials are aware of each other’s resources and capabilities in dealing with gas emergencies

Comments:
     

.605(a) PUBLIC EDUCATION PROCEDURES S U N/A N/C


.616 Establishing a continuing educational program (in English and other pertinent languages) to better
inform the public in how to recognize and report potential gas pipeline emergencies [prior to June 20,                
2006]
.616 Public Awareness Program in accordance with API RP 1162 [HQ clearinghouse review after June 20,
2006. Small propane distribution systems and master meter operators w/less than 25 customers – after
June 20, 2007]

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 4
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

Comments:
     

.617 FAILURE INVESTIGATION PROCEDURES S U N/A N/C


.617 Analyzing accidents and failures including laboratory analysis where appropriate to determine cause
               
and prevention of recurrence

Comments:
     

.605(a) MAOP PROCEDURES S U N/A N/C


.619 Establishing MAOP so that it is commensurate with the class location                
MAOP can be determined by:
(a) Design and test or                
(b) By highest operating pressure to which the segment of line was subjected between July 1, 1965
               
and July 1, 1970.
.621 MAOP - High Pressure Distribution Systems                
.623 Max./Min. Allowable Operating Pressure - Low Pressure Distribution Systems                

Comments:
     

.13(c) PRESSURE TEST PROCEDURES S U N/A N/C


.503 Pressure testing                

Comments:
     

.605(a) ODORIZATION of GAS PROCEDURES S U N/A N/C


.625(a) Distribution lines must contain odorized gas. – must be readily detectable by person with normal sense
               
of smell at 1/5 of the LEL
.625(f) Periodic gas sampling, using an instrument capable of determining the percentage of gas in air at which
               
the odor becomes readily detectable.

Comments:
     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 5
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.605(a) TAPPING PIPELINES UNDER PRESSURE PROCEDURES S U N/A N/C


.627 Hot taps must be made by a qualified crew
               
NDT testing is suggested prior to tapping the pipe. Reference API RP 2201 for Best Practices.

Comments:
     

.605(a) PIPELINE PURGING PROCEDURES S U N/A N/C


.629 Purging of pipelines must be done to prevent entrapment of an explosive mixture in the pipeline
     
(a) Lines containing air must be properly purged.                
(b) Lines containing gas must be properly purged                

Comments:
     

.605(a) MAINTENANCE PROCEDURES S U N/A N/C


.703(b) Each segment of pipeline that becomes unsafe must be replaced, repaired, or removed from
               
service
(c) Hazardous leaks must be repaired promptly                

Comments:
     

.605(b) DISTRIBUTION SYSTEM PATROLLING & LEAKAGE SURVEY PROCEDURES S U N/A N/C
.721(a) Frequency of patrolling mains must be determined by the severity of the conditions which could cause
               
failure or leakage (i.e., consider cast iron, weather conditions, known slip areas, etc.)
.721(b) Mains in places or on structures where anticipated physical movement or external loading could cause
failure or leakage must be patrolled . . .
(b)(1) In business districts at intervals not exceeding 4½ months, but at least four times each calendar year;
               
and
(b)(2) Outside business districts at intervals not exceeding 7½ months, but at least twice each calendar year                
.723(a) & (b) Periodic leak surveys determined by the nature of the operations and conditions.                
(b)(1) In business districts as specified, 1/yr (15 months)                
(b)(2) Outside of business districts as specified, once every 5 calendar years/63 mos.; for unprotected lines
               
subject to .465(e) where electrical surveys are impractical, once every 3 years/39 mos.

Comments:
     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 6
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.605(b) LINE MARKER PROCEDURES S U N/A N/C


.707 Line markers installed and labeled as required                

Comments:
     

.605(b) TEST REQUIREMENTS FOR REINSTATING SERVICE LINES S U N/A N/C


.725(a) Except for .725(b), disconnected service lines must be tested the same as a new service line.                
(b) Service lines that are temporarily disconnected must be tested from the point of disconnection, the same
               
as a new service line, before reconnect. See code for exception to this.

Comments:
     

.605(b) ABANDONMENT or DEACTIVATION of FACILITIES PROCEDURES S U N/A N/C


.727(b) Operator must disconnect both ends, purge, and seal each end before abandonment or a period of
               
deactivation where the pipeline is not being maintained.
(c) Except for service lines, each inactive pipeline that is not being maintained under Part 192 must be
               
disconnected from all gas sources/supplies, purged, and sealed at each end.
(d) Whenever service to a customer is discontinued, do the procedures indicate one of the following:
(1) The valve that is closed to prevent the flow of gas to the customer must be provided with a
locking device or other means designed to prevent the opening of the valve by persons other than                
those authorized by the operator
(2) A mechanical device or fitting that will prevent the flow of gas must be installed in the service
               
line or in the meter assembly
(3) The customer’s piping must be physically disconnected from the gas supply and the open pipe
               
ends sealed
(e) If air is used for purging, the operator shall ensure that a combustible mixture is not present after
               
purging
.727(g) Operator must file reports upon abandoning underwater facilities crossing navigable waterways,
               
including offshore facilities.

Comments:
     

.605(b) PRESSURE LIMITING and REGULATING STATION PROCEDURES S U N/A N/C


.739(a) Inspection and testing procedures for pressure limiting stations, relief devices, pressure regulating
               
stations and equipment (1 per yr/15 months)
(1) In good mechanical condition                
(2) Adequate from the standpoint of capacity and reliability of operation for the service in which it is
               
employed
(3) Set to control or relieve at correct pressures consistent with .201(a), except for .739(b).                
(4) Properly installed and protected from dirt, liquids, and other conditions that may prevent
               
proper . operation
.739(b) For steel lines if MAOP is determined per .619(c) and the MAOP is 60 psi (414 kPa) gage or more . . .

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 7
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.605(b) PRESSURE LIMITING and REGULATING STATION PROCEDURES S U N/A N/C


1If MAOP produces hoop stress
1Then the pressure limit is:
that
1Is greater than 72 percent of SMYS 1MAOP plus 4 percent                
1A pressure that will prevent unsafe operation of the pipeline
1Is unknown as a percent of SMYS
considering its operating and maintenance history and MAOP

.741 Telemetering or Recording Gauges


(a) In place to indicate gas pressure in the district that is supplied by more than one regulating station                
(b) Determine the need in a distribution system supplied by only one district station                
(c) Inspect equipment and take corrective measures when indications of abnormally high or low
               
pressure
.743 Testing of Relief Devices
.743 (a) Capacity must be consistent with .201(a) except for .739(b), and be determined 1 per yr/15 mo.                
(b) If calculated, capacities must be compared; annual review and documentation are
               
required.
(c) If insufficient capacity, new or additional devices must be installed to provide required capacity.                

Comments:
     

.605(b) VALVE AND VAULT MAINTENANCE PROCEDURES S U N/A N/C


Distribution Valves
.747 (a) Check and service each valve that may be necessary for the safe operation of a distribution system
               
(1 per yr/15 months)
(b) Prompt remedial action required, or designate alternative valve.                
Vaults
.749 Inspection of vaults greater than 200 cubic feet (1 per yr/15 months)                

.605(b) PREVENTION of ACCIDENTAL IGNITION PROCEDURES S U N/A N/C


.751 Reduce the hazard of fire or explosion by:
(a) Removal of ignition sources in presence of gas and providing for a fire extinguisher                
(b) Prevent welding or cutting on a pipeline containing a combustible mixture                
(c) Post warning signs                

Comments:
     

.605(b) CAULKED BELL AND SPIGOT JOINTS PROCEDURES S U N/A N/C


.753 Cast-iron caulked bell and spigot joint repair:

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 8
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.605(b) CAULKED BELL AND SPIGOT JOINTS PROCEDURES S U N/A N/C


(a) When subject to more than 25 psig, sealed with mechanical clamp, or sealed with material/device
which does not reduce flexibility, permanently bonds, and seals and bonds as prescribed in                
§192.753(a)(2)(iii)
(b) When subject to 25 psig or less, joints, when exposed for any reason, must be sealed by means
               
other than caulking

.605(b) PROTECTING CAST-IRON PIPELINE PROCEDURES S U N/A N/C


.755 Operator has knowledge that the support for a segment of a buried cast-iron pipeline is disturbed must
provide protection.
(a) Vibrations from heavy construction equipment, trains, trucks, buses or blasting?                
(b) Impact forces by vehicles?                
(c) Earth movement?                
(d) Other foreseeable outside forces which might subject the segment of pipeline to a bending stress                
(e) Provide permanent protection for the disturbed section as soon as feasible                

.13(c) WELDING AND WELD DEFECT REPAIR/REMOVAL PROCEDURES S U N/A N/C


.225 (a) Welding procedures must be qualified under Section 5 of API 1104 (19th ed.1999, 10/31/01
               
errata) or Section IX of ASME Boiler and Pressure Code (2001 ed.) by destructive test.
(b) Retention of welding procedure – details and test                
.227 (a) Welders must be qualified by Section 6 of API 1104 (19th ed.1999, 10/31/01 errata) or Section
               
IX of ASME Boiler and Pressure Code (2001 ed.) See exception in .227(b).
(b) Welders may be qualified under section I of Appendix C to weld on lines that operate at < 20%
               
SMYS.
.229 (a) To weld on compressor station piping and components, a welder must successfully complete a
               
destructive test
(b) Welder must have used welding process within the preceding 6 months                
(c) A welder qualified under .227(a)–
.229(c) (1) May not weld on pipe that operates at > 20% SMYS unless within the preceding 6
calendar months the welder has had one weld tested and found acceptable under the
sections 6 or 9 of API Standard 1104; may maintain an ongoing qualification status by                
performing welds tested and found acceptable at least twice per year, not exceeding 7½
months; may not requalify under an earlier referenced edition.
(2) May not weld on pipe that operates at < 20% SMYS unless is tested in accordance with
               
.229(c)(1) or requalifies under .229(d)(1) or (d)(2).
(d) Welders qualified under .227(b) may not weld unless:
(1) Requalified within 1 year/15 months, or                
(2) Within 7½ months but at least twice per year had a production weld pass a qualifying test                
.231 Welding operation must be protected from weather                
.233 Miter joints (consider pipe alignment)                
.235 Welding preparation and joint alignment                
.241 (a) Visual inspection must be conducted by an individual qualified by appropriate training and
               
experience to ensure:
(1) Compliance with the welding procedure                
(2) Weld is acceptable in accordance with Section 9 of API 1104                
(b) Welds on pipelines to be operated at 20% or more of SMYS must be nondestructively
tested in accordance with 192.243 except welds that are visually inspected and approved by                
a qualified welding inspector if:
(1) The nominal pipe diameter is less than 6 inches, or                
(2) The pipeline is to operate at a pressure that produces a hoop stress of less than 40% of
               
SMYS and the welds are so limited in number that nondestructive testing is impractical
.241 (c) Acceptability based on visual inspection or NDT is determined according to Section 9 of API
1104. If a girth weld is unacceptable under Section 9 for a reason other than a crack, and if
               
Appendix A to API 1104 applies to the weld, the acceptability of the weld may be further
determined under that appendix.
Repair and Removal of Weld Defects

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 9
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.13(c) WELDING AND WELD DEFECT REPAIR/REMOVAL PROCEDURES S U N/A N/C


.245 (a) Each weld that is unacceptable must be removed or repaired. Except for offshore pipelines, a
               
weld must be removed if it has a crack that is more than 8% of the weld length
(b) Each weld that is repaired must have the defect removed down to sound metal, and the segment
to be repaired must be preheated if conditions exist which would adversely affect the quality of                
the weld repair. After repair, the weld must be inspected and found acceptable.
(c) Repair of a crack or any other defect in a previously repaired area must be in accordance with
               
a written weld repair procedure, qualified under §192.225
$ Sleeve Repair – low hydrogen rod (Best Practices –ref. API 1104 App. B, In Service
Welding)

Comments:
     

.13(c) NONDESTRUCTIVE TESTING PROCEDURES S U N/A N/C


.243 (a) Nondestructive testing of welds must be performed by any process, other than trepanning, that
               
clearly indicates defects that may affect the integrity of the weld
(b) Nondestructive testing of welds must be performed:
(1) In accordance with a written procedure, and                
(2) By persons trained and qualified in the established procedures and with the test equipment
               
used
(c) Procedures established for proper interpretation of each nondestructive test of a weld to ensure
               
acceptability of the weld under 192.241©
(d) When nondestructive testing is required under §192.241(b), the following percentage of each
day’s field butt welds, selected at random by the operator, must be nondestructively tested over
the entire circumference
(1) In Class 1 locations at least 10%                
(2) In Class 2 locations at least 15%                
(3) In Class 3 and 4 locations, at crossings of a major navigable river, offshore, and within
railroad or public highway rights-of-way, including tunnels, bridges, and overhead road
               
crossings, 100% unless impractical, then 90%. Nondestructive testing must be impractical
for each girth weld not tested.
(4) At pipeline tie-ins, 100%                
(e) Except for a welder whose work is isolated from the principal welding activity, a sample of
each welder’s work for each day must be nondestructively tested, when nondestructive testing is                
required under §192.241(b)
(f) Nondestructive testing – the operator must retain, for the life of the pipeline, a record showing by
mile post, engineering station, or by geographic feature, the number of welds nondestructively                
tested, the number of welds rejected, and the disposition of the rejected welds.

Comments:
     

.273(b) JOINING of PIPELINE MATERIALS S U N/A N/C


.281 Joining of plastic pipe
$ Type of plastic used                
$ Proper markings in accordance with §192.63                

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 10
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.273(b) JOINING of PIPELINE MATERIALS S U N/A N/C


$ Manufacturer                
$ Type of joint used                
.283 Qualified joining procedures for plastic pipe must be in place                
.285 Persons making joints with plastic pipe must be qualified                
.287 Persons inspecting plastic joints must be qualified                

Comments:
     

.605(b) CORROSION CONTROL PROCEDURES S U N/A N/C


.453 Are corrosion procedures established for:
$ Design                
$ Operations                
$ Installation                
$ Maintenance                
.455 (a) For pipelines installed after July 31, 1971, buried segments must be externally coated and
               
(b) cathodically protected within one year after construction (see exceptions in code)
(c) Aluminum may not be installed in a buried or submerged pipeline if exposed to an environment
               
with a natural pH in excess of 8 (see exceptions in code)
.457 (a) All effectively coated steel transmission pipelines installed prior to August 1, 1971, must be
               
cathodically protected
(b) If installed before August 1, 1971, cathodic protection must be provided in areas of active
corrosion for: bare or ineffectively coated transmission lines, and bare or coated c/s, regulator                
sta., meter sta. piping, and (except for cast iron or ductile iron) bare or coated distribution lines.
.459 Examination of buried pipeline when exposed: if corrosion is found, further investigation is required                
.461 Procedures must address the protective coating requirements of the regulations. External coating
               
on the steel pipe must meet the requirements of this part.
.463 Cathodic protection level according to Appendix D criteria                
.465 (a) Pipe-to-soil monitoring (1 per yr/15 months)                
(b) Rectifier monitoring (6 per yr/2½ months)                
(c) Interference bond monitoring (as required)                
(d) Prompt remedial action to correct any deficiencies indicated by the monitoring                
.465 (e) Electrical surveys (closely spaced pipe to soil) on bare/unprotected lines, cathodically protect
               
active corrosion areas (1 per 3 years/39 months)
.467 Electrical isolation (include casings)                
.469 Sufficient test stations to determine CP adequacy                
.471 Test lead maintenance                
.473 Interference currents                
.475 (a) Proper procedures for transporting corrosive gas?                
(b) Removed pipe must be inspected for internal corrosion. If found, the adjacent pipe must be
inspected to determine extent. Certain pipe must be replaced. Steps must be taken to minimize                
internal corrosion.
.477 Internal corrosion control coupon (or other suit. Means) monitoring (2 per yr/7½ months)                
.479 (a) Each exposed pipe must be cleaned and coated (see exceptions under .479(c))                
Offshore splash zones and soil-to-air interfaces must be coated                
(b) Coating material must be suitable                
Coating is not required where operator has proven that corrosion will:
(c) (1) Only be a light surface oxide, or                

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 11
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

.605(b) CORROSION CONTROL PROCEDURES S U N/A N/C


(2) Not affect safe operation before next scheduled inspection                
.481 (a) Atmospheric corrosion control monitoring (1 per 3 yrs/39 months onshore)                
.481 (b) Special attention required at soil/air interfaces, thermal insulation, under disbonded coating, pipe
               
supports, splash zones, deck penetrations, spans over water
.481 (c) Protection must be provided if atmospheric corrosion is found (per §192.479)                
.483 Replacement and required pipe must be coated and cathodically protected (see code for exceptions)                
.485 (a) Procedures to replace pipe or reduce the MAOP if general corrosion has reduced the wall
               
thickness?
(b) Procedures to replace/repair pipe or reduce MAOP if localized corrosion has reduced wall
               
thickness (unless reliable engineering repair method exists)?
(c) Procedures to use Rstreng or B-31G to determine remaining wall strength?
.487 Remedial measures (distribution lines other than cast iron or ductile iron)                
.489 Remedial measures (cast iron and ductile iron pipelines)
.491 Corrosion control maps and record retention (pipeline service life or 5 yrs)                

Comments:
     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 12
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

PIPELINE INSPECTION (Field) S U N/A N/C


.179 Valve Protection from Tampering or Damage                
.463 Cathodic Protection                
.465 Rectifiers                
.479 Pipeline Components Exposed to the Atmosphere                
.605 Knowledge of Operating Personnel                
.707 ROW Markers, Road and Railroad Crossings                
.503 Pre-pressure Tested Pipe (Markings and Inventory)                
.739 Pressure Limiting and Regulating Devices (Mechanical)                
.741 Telemetering, Recording gauges                
.743 Pressure Limiting and Regulating Devices (Capacities)                
.747 Valve Maintenance                
.751 Warning Signs                

Comments:
     

REGULATORY REPORTING RECORDS S U N/A N/C


191.5 Telephonic reports to NRC                
191.15 Written incident reports; supplemental incident reports (Form F 7100.2)                
191 Annual Reports (Forms 7100.1-1, 7100.2-1)                
191.23 Safety related condition reports                
192.16 Customer Notification (Verification – 90 days – and Elements)                
192.727 (g) Abandoned facilities offshore, onshore crossing commercially navigable waterways reports                

CONSTRUCTION RECORDS S U N/A N/C


.225 Test Results to Qualify Welding Procedures                
.227 Welder Qualification                
.241 (a) Visual Weld Inspector Training/Experience                
.243 (b)(2) Nondestructive Technician Qualification                
(c) NDT procedures                
(f) Total Number of Girth Welds                
(f) Number of Welds Inspected by NDT                
(f) Number of Welds Rejected                
(f) Disposition of each Weld Rejected                
.303 Construction Specifications                
.325 Underground Clearance                
.327 Amount, Location, Cover of each Size of Pipe Installed                
.455 Cathodic Protection                

OPERATIONS and MAINTENANCE RECORDS S U N/A N/C


.517 (a) Pressure Testing (operates at or above 100 psig) – useful life of pipeline                

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 13
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

OPERATIONS and MAINTENANCE RECORDS S U N/A N/C


.517 (b) Pressure Testing (operates below 100 psig, service lines, plastic lines) – 5 years                
.603(b) .605(a) Procedural Manual Review – Operations and Maintenance (1 per yr/15 months)                
.605(b)(3) Availability of construction records, maps, operating history to operating personnel                
.605(b)(8) Periodic review of personnel work – effectiveness of normal O&M procedures                
.605(c)(4) Periodic review of personnel work – effectiveness of abnormal operation procedures                
.603(b) .614 Damage Prevention (Miscellaneous)                
.609 Class Location Study (If Applicable)                
.603(b) .615(b)(1) Location Specific Emergency Plan                
.615(b)(2) Emergency Procedure training, verify effectiveness of training                
.615(b)(3) Employee Emergency activity review, determine if procedures were followed.                
.615(c) Liaison Program with Public Officials                
.616 Public Education/Awareness Program                
.517 Pressure Testing                
.603(b) .619 .621 .623 Maximum Allowable Operating Pressure (MAOP)                
.625 Odorization of Gas                
.603(b) .721(b)(1) Patrolling Business District (4 per yr/4½ months)                
.721(b)(2) Patrolling Outside Business District (2 per yr/7½ months)                
.723(b)(1) Leakage Survey – business District (1 per yr/15 months)                
.723(b)(2) Leakage Survey
▪ Outside Business District (5 years)                
▪ Cathodically unprotected distribution lines (3 years)                
.725 Tests for reinstating service lines                
.603b/.727g .727 Abandoned Pipelines; Underwater Facility Reports                
.603(b) .739 Pressure Limiting and Regulating Stations (1 per yr/15 months)                
.743 Pressure Limiting and Regulator Stations – Capacity (1 per yr/15 months)                
.603(b) .747 Valve Maintenance Distribution Lines (1 per yr/15 months)                
.603(b) .749 Vault Maintenance (200 cubic feet)(1 per yr/15 months)                
.603(b) .751 Prevention of Accidental Ignition (hot work permits)                
.755 Caulked Bell and Spigot Joint Repair                
.225(b) Welding – Procedure                
.227/.229 Welding – Welder Qualification                
.243(b)(2) NDT – NDT Personnel Qualification                
.709 .243(f) NDT Records (Pipeline Life)                
Repair: pipe (Pipeline Life); Other than pipe (5 years)                

Comments:
     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 14
State of Louisiana Comprehensive Inspection Form – Gas Distribution Pipeline
Unless otherwise noted, all code references are to 49CFR Part 192. S – Satisfactory U – Unsatisfactory N/A – Not Applicable N/C – Not Checked

CORROSION CONTROL RECORDS S U N/A N/C


.491 .491(a) Maps or Records                
.491 .459 Examination of Buried Pipe when Exposed                
.491 .465(a) Annual Pipe-to-soil Monitoring (1 per yr/15 months)                
.491 .465(b) Rectifier Monitoring (6 per yr/2½ months)                
.491 .465(c) Interference Bond Monitoring – Critical (6 per yr/2½ months)                
.491 .465(c) Interference Bond Monitoring – Non-critical (1 per yr/15 months)                
.491 .465(d) Prompt Remedial Actions                
.491 .465(e) Unprotected Pipeline Surveys, CP active corrosion areas (1 per 3 cal yr/39 months)                
.491 .467 Electrical Isolation (Including Casings)                
.491 .469 Test Stations – Sufficient Number                
.491 .471 Test Lead Maintenance                
.491 .473 Interference Currents                
.491 .475(a) Internal Corrosion; Corrosive Gas Investigation                
.491 .475(b) Internal Corrosion; Internal Surface Inspection; Pipe Replacement                
.491 .477 Internal Corrosion Control Coupon Monitoring (2 per yr/7½ months)                
.491 .481 Atmospheric Corrosion Control Monitoring (1 per 3 cal yr/39 months)                
.491 .483/.485 Remedial: Replaced or Repaired Pipe; coated and protected; corrosion evaluation and actions                

Comments:
     

Form 2 Standard Inspection Report of a Gas Distribution Operator (Rev. 03/17/06 through Amdt. 192-102). La. Revised: 5/06 15

You might also like