Culture Documents
2. The __________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.
a) resource histogram
Ans: b Section Reference: 6.3 Human Resources: The RACI Matrix and Agile Projects
3. The success of the project launch meeting is dependent on the existence of __________.
a) a project charter
Ans: c Section Reference: 6.1 Initial Project Coordination and the Project Charter
4. This project plan element describes both the managerial and the technical approaches to the
work. The technical discussion describes the relationship of the project to available
technologies.
a) overview
1
MGO 634 F20 Quiz 6 of 10 Fall 2015
b) objectives
c) general approach
d) contractual aspects
Ans: a Section Reference: 6.1 Initial Project Coordination and the Project Charter
5. This project plan element should include profit and competitive goals as well as technical
goals.
a) overview
b) objectives
c) general approach
d) contractual aspects
Ans: b Section Reference: 6.1 Initial Project Coordination and the Project Charter
6. This project plan element lists all milestone events. It identifies the estimated time for
each task and is used to construct the master project schedule.
a) budget
b) schedule
c) personnel plan
d) evaluation methods
Ans: b Section Reference: 6.1 Initial Project Coordination and the Project Charter
7. This element of the project plan contains a brief description of the procedure to be
followed in monitoring, collecting, storing, and evaluating the history of the project.
a) schedule
b) resources
c) personnel
d) evaluation methods
Ans: d Section Reference: 6.1 Initial Project Coordination and the Project Charter
2
MGO 634 F20 Quiz 6 of 10 Fall 2015
8. One of the challenges project managers face is to ensure that managers do not mix
__________.
Ans: a Section Reference: 6.2 The WBS: A Key Element of the Project Plan
9. The process of coordinating the work and timing of the different groups working on
multidisciplinary teams is called __________.
a) procurement management
b) integration management
c) vertical management
d) matrix management
10. The __________ of a project includes the objectives of the project as well as the time
and cost required to complete the project to the customer’s satisfaction.
a) scope
b) change order
c) outcome
d) purpose