1st Review (Engineer's Comment from NKDM) 2nd Submission 2nd Review (Engineer's Comment from NKDM) 3rd Submission 3rd Review (Engineer's Comment from NKDM)
Approval From NKDM Remarks
Sl No Drawing Description Drawing No Reference No Submissions Date Reference No Date Comment Reference No Re-Submission Date Reference No Date Comment Reference No Re-Submission Date Reference No Date Comment
Uttara RSS: Overall Equipment Layout Plan & NONOB Approved
1 Section O18161-E-IS-SY-EL-1002 Rev.A 07- PSY-DRW-0001-A 29thSept’18 07- PSY-DRW-0001-B 04th Oct’18 (With Drawing) 07- PSY-DRW-0001-C 15th Oct'18 07- PSY-DRW-0001-D 25th Oct’18 NONOB 07- PSY-DRW-0001-E 28th Oct'18 07- PSY-DRW-0001-F 28th Oct’18 NONOC with Comments Resubmission Required
Uttara RSS: GIS cum Control Building layout Plan NONOB NONOB
2 and Section O18161-E-IS-GB-EL-1003 Rev.A 07- PSY-DRW-0002-A 29thSept’18 07- PSY-DRW-0002-B 04th Oct’18 (With Drawing) 07- PSY-DRW-0002-C 15th Oct'18 07- PSY-DRW-0002-D 25th Oct’18 (With Drawing) 07- PSY-DRW-0002-E 28th Oct'18 07- PSY-DRW-0002-F 28th Oct’18 NONO Approved
8 Uttara RSS: 132kV RSS & 33kV AMS Single Line O18161-E-IS-SY-1L-1001 Rev.A 07- PSY-DRW-0008-A 07th Oct’18 07- PSY-DRW-0008-B 10th Oct'18 NONOC
Diagram (With Drawing)
NONOB
9 33kV Auxiliary Network Single Line Diagram O18161-E-IS-TC-1L-1004 Rev.A 07- PSY-DRW-0009-A 07th Oct’18 07- PSY-DRW-0009-B 23rd Oct’18 (With Drawing)
10 132/33kV RSS AT UTTARA SUBSTATION O18161-C-RE-SY-SR-6002 Rev.A 07-PSY-DRW-0010-A 08th Oct’18 07-PSY-DRW-0010-B 29th Oct'18 NOOA 07-PSY-DRW-0010-C 4th Novt’18
GEOTECHNICAL INTERPRETATIVE REPORT
DESIGN BASIS REPORT OF CIVIL & STRUCTURAL 07-PSY-DRW-0011-B 15th Oct'18 NONOB
FOR 132/33kV UTTARA AND MOTIJHEEL O18161-C-RE-SY-DB-6001 & & & Approved
11 Rev.A 07-PSY-DRW-0011-A 08th Oct’18 07-PSY-DRW-0011-C 28th Oct’18 PSY-DRW-0011-D 30th Oct'18 NONOC with Comments Resubmission Required
SUBSTATION 07-PSY-DRW-0011-B1 16th Oct'18 NOOA