2014 2015 2016 2017

Line Name Duration Start Finish


July August September October November December January February March April May June July August September October November December January February March April May June July August September October November December January February March April May
28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29
-140 -138 -136 -134 -132 -130 -128 -126 -124 -122 -120 -118 -116 -114 -112 -110 -108 -106 -104 -102 -100 -98 -96 -94 -92 -90 -88 -86 -84 -82 -80 -78 -76 -74 -72 -70 -68 -66 -64 -62 -60 -58 -56 -54 -52 -50 -48 -46 -44 -42 -40 -38 -36 -34 -32 -30 -28 -26 -24 -22 -20 -18 -16 -14 -12 -10 -8 -6 -4 -2 1 3 5 7 9
1 DESIGN STAGES 255d 28/07/14 07/08/15 1

2 Stage 0 - Strategic Definition 20d 28/07/14 22/08/14 2

3 Commence 28/07/14 28/07/14 3


4 Business Case 2w 28/07/14 08/08/14 4
5 Strategic Brief 1w 11/08/14 15/08/14 5

6 Site survey information 1w 11/08/14 15/08/14 6

7 Establish Project Programme 2w 11/08/14 22/08/14 7

8 Stage 1 - Preparation & Brief 34d 18/08/14 03/10/14 8

9 Sustainability Aspirations 1w 18/08/14 22/08/14 9

10 Project Objectives 1w 4d 18/08/14 29/08/14 10

11 Quality Objectives 1w 4d 18/08/14 29/08/14 11

12 Project Outcomes 1w 4d 18/08/14 29/08/14 12

13 Project Budget 2w 01/09/14 12/09/14 13

14 Initial Project Brief 2w 01/09/14 12/09/14 14

15 Feasibility Studies 3w 15/09/14 03/10/14 15

16 Site Information Review 1w 15/09/14 19/09/14 16

17 Stage 2 - Concept Design 30d 06/10/14 14/11/14 17

18 Concept Design 3w 06/10/14 24/10/14 18

19 Consultation with Planning Officer 5w 06/10/14 07/11/14 19

20 Cost Information 2w 13/10/14 24/10/14 20

21 Project Strategies 1w 27/10/14 31/10/14 21

22 Design Programme 1w 27/10/14 31/10/14 22

23 Final Project Brief 2w 03/11/14 14/11/14 23

24 Submit planning application 1w 10/11/14 14/11/14 24

25 Stage 3 - Developed Design 117d 17/11/14 15/05/15 25

26 Develop Design 6w 17/11/14 09/01/15 26

27 Building Regulation Compliance 6w 17/11/14 09/01/15 27

28 Cost Information 3w 08/12/14 09/01/15 28

29 Project Strategies Review 1w 12/01/15 16/01/15 29

30 Issue Party Wall notices 08/12/14 08/12/14 30 4w

31 PWS liason with design team 5w 19/01/15 20/02/15 31 7w 3d

32 Submit detailed proposals to neighbours 20/04/15 20/04/15 32

33 Complete party wall award 20/04/15 20/04/15 33

34 Principle Contractor Tender & Appointment 82d 19/01/15 15/05/15 34

35 Prepare Tender Documents and Contract 4w 19/01/15 13/02/15 35

36 Principle Contractor Tender Period 1m 3.54w 16/02/15 10/04/15 36

37 Mid tender Q&A 16/03/15 16/03/15 37

38 Tender returns 13/04/15 13/04/15 38 5d

39 Interview Principle Contractor 20/04/15 20/04/15 39

40 Client Review 2w 20/04/15 01/05/15 40

41 Award Contract to Priciple Contractor 05/05/15 05/05/15 41

42 Mobilise principle contractor team 1w 4d 05/05/15 15/05/15 42

43 Stage 4 - Technical Design 68d 05/05/15 07/08/15 43+ +


44 SUB-CONTRACTOR APPOINTMENT 294d 10/08/15 14/10/16 44
5d
45 Window Installer 11w 4d 10/08/15 06/11/15 45
5d
46 Scaffolding 10w 4d 10/08/15 30/10/15 46
5d
47 Temporary Services 6w 4d 17/08/15 12/10/15 47
5d
48 Temporary Accomodation 5w 4d 24/08/15 09/10/15 48
5d
49 General Attendance 5w 28/08/15 09/10/15 49
5d
50 Sub-structure 12w 07/09/15 04/12/15 50
5d
51 Carpentry & Joinery 12w 07/09/15 04/12/15 51
5d
52 Architectural Metalwork 12w 14/09/15 11/12/15 52
5d
53 General Builder 12w 02/11/15 12/02/16 53
5d
54 Soft Strip 9w 02/11/15 22/01/16 54
5d
55 Mechanical & Electrical Services 12w 23/11/15 04/03/16 55
5d
56 Kitchen Fit Out 11w 30/11/15 04/03/16 56
5d
57 Roof works 11w 2d 29/02/16 27/05/16 57
5d
58 Landscaping 12w 1d 07/03/16 10/06/16 58
4d
59 Stone & Tiling 10w 3d 29/03/16 17/06/16 59
5d
60 Hardwood Floors 8w 3d 25/04/16 01/07/16 60
4d
61 Audio & Visual 11w 31/05/16 19/08/16 61
5d
62 Painting & Decorating 11w 06/06/16 26/08/16 62
5d
63 Floor Finishes 7w 4d 25/07/16 23/09/16 63
5d
64 Builder Clean 6w 4d 22/08/16 14/10/16 64

65 LONG LEAD ITEMS 240d 09/11/15 28/10/16 65

66 Windows 17w 09/11/15 18/03/16 66

67 Frames & Doors 15w 3d 07/12/15 08/04/16 67

68 Metal Stairs 21w 2d 14/12/15 27/05/16 68

69 Special bricks 12w 14/12/15 18/03/16 69

70 Slates 13w 2d 22/02/16 27/05/16 70

71 Timber Stairs 17w 01/03/16 01/07/16 71

72 Boilers 9w 2d 07/03/16 13/05/16 72

73 Fire Alarm Panel 9w 2d 07/03/16 13/05/16 73

74 Security Panel 9w 2d 07/03/16 13/05/16 74

75 Kitchen 18w 1d 07/03/16 15/07/16 75

76 Sanitaryware Schedule 16w 1d 13/04/16 05/08/16 76

77 Stone worktop 9w 4d 09/05/16 15/07/16 77

78 Lights - Type A 11w 4d 16/05/16 05/08/16 78

79 Special radiators 11w 4d 16/05/16 05/08/16 79

80 Fire place 11w 4d 16/05/16 05/08/16 80

81 Cupboards 14w 3d 23/05/16 02/09/16 81

82 Vanity Units 14w 3d 23/05/16 02/09/16 82

83 Stone floor - Type A 13w 4d 20/06/16 23/09/16 83

84 Timber floor 11w 4d 04/07/16 23/09/16 84

85 LED TV's 9w 4d 22/08/16 28/10/16 85

86 CONSTRUCTION 378d 12/10/15 02/05/17 86

87 Enabling works 40d 12/10/15 07/12/15 87

88 Commence Pre-Construction 12/10/15 12/10/15 88

89 Set up site office and welfare 3w 4d 12/10/15 05/11/15 89

90 Asbestos, drainage, trial pit surveys 2w 19/10/15 30/10/15 90

91 Protect neighbours wall 3w 19/10/15 06/11/15 91

92 Protect trees 1w 19/10/15 23/10/15 92

93 Erect hoarding and gates 2w 4d 26/10/15 12/11/15 93

94 Hoarding and scaffold 5w 02/11/15 04/12/15 94

95 Grid lines and datums 2w 4d 09/11/15 26/11/15 95

96 Install turstile 1w 09/11/15 13/11/15 96

97 Complete Pre-construction 07/12/15 07/12/15 97

98 New build houses & apartments 265d 07/12/15 16/01/17 98

99 Sub-Structure 65d 07/12/15 18/03/16 99

100 Commence New Build 07/12/15 07/12/15 100

101 Clear oversite and reduce levels 1w 07/12/15 11/12/15 101

102 Excavate foundations and drain runs 3w 14/12/15 15/01/16 102

103 Lay drains, test, inspect, backfill 2w 18/01/16 29/01/16 103

104 Reinforcement, formwork and cast foundations 4w 01/02/16 26/02/16 104

105 Block & brick to DPC 3w 29/02/16 18/03/16 105

106 Install beams and block 2w 29/02/16 11/03/16 106

107 Super-Structure 200d 21/03/16 16/01/17 107

108 External walls and steel 25w 21/03/16 16/09/16 108

109 Hollow concrete floor planks 8w 1d 13/04/16 10/06/16 109

110 Trusses 3w 09/05/16 27/05/16 110

111 Roof & gutter 5w 4d 31/05/16 08/07/16 111

112 Windows and external doors 5w 3d 13/06/16 20/07/16 112

113 Internal walls and board 1 side 5w 3d 13/06/16 20/07/16 113

114 1st fix services 8w 20/06/16 12/08/16 114

115 Terrace decking 4w 20/06/16 15/07/16 115

116 Cladding 4w 20/06/16 15/07/16 116

117 Balcony railings 2w 20/06/16 01/07/16 117

118 Stairs 6w 04/07/16 12/08/16 118

119 Close up walls 5w 4d 01/08/16 09/09/16 119

120 Plastering & mist coat 10w 15/08/16 24/10/16 120

121 Internal frames and doors 6w 30/08/16 10/10/16 121

122 2nd fix carpentry 8w 05/09/16 28/10/16 122

123 Install kitchen 6w 12/09/16 21/10/16 123

124 Install Sanitaryware and connect 6w 26/09/16 04/11/16 124

125 2nd fix services 6w 26/09/16 04/11/16 125

126 Decorations 8w 03/10/16 25/11/16 126

127 Tiling 6w 03/10/16 11/11/16 127

128 Carpet/Wooden and stone floor finishes 6w 17/10/16 25/11/16 128

129 Inspect, test and commission 6w 31/10/16 09/12/16 129

130 Air presure test 4w 07/11/16 02/12/16 130

131 Clean and snag 8w 07/11/16 13/01/17 131

132 Complete New build 16/01/17 16/01/17 132 14w 3d

133 Refurbished appartments 205d 25/01/16 14/11/16 133

134 Commence Retail Unit Flats 10,11,14 25/01/16 25/01/16 134

135 Soft strip 4w 25/01/16 19/02/16 135

136 Builder's work e.g. insulation 5w 4d 15/02/16 24/03/16 136

137 Install new windows 2w 3d 21/03/16 08/04/16 137

138 Internal walls & ceilings 5w 4d 11/04/16 20/05/16 138

139 1st fix services 2w 4d 16/05/16 03/06/16 139

140 Close up walls 2w 06/06/16 17/06/16 140

141 Plastering & mist coat 4w 20/06/16 15/07/16 141

142 Install bathroom sanitaryware 3w 18/07/16 05/08/16 142

143 Kitchen 3w 18/07/16 05/08/16 143

144 Frames & doors 3w 18/07/16 05/08/16 144

145 2nd fix services 3w 08/08/16 26/08/16 145

146 2nd fix carpentry 3w 08/08/16 26/08/16 146

147 Decorations 3w 4d 30/08/16 23/09/16 147

148 Tiling 2w 4d 30/08/16 16/09/16 148

149 Carpet/Wooden and stone floor 3w 26/09/16 14/10/16 149

150 Clean & Snag 3w 17/10/16 04/11/16 150

151 Testing and commissioning 1w 07/11/16 11/11/16 151

152 Air pressure test 1w 07/11/16 11/11/16 152

153 Final DS inspection 14/11/16 14/11/16 153 21w 3d

154 External works and common areas 226d 31/05/16 02/05/17 154

155 External stairs 1w 4d 31/05/16 10/06/16 155

156 Landscape back garden, bike store, fencing 6w 13/06/16 22/07/16 156

157 Refuse store 5w 25/07/16 26/08/16 157

158 Bike store 6w 4d 30/08/16 14/10/16 158

159 Court-Yard 6w 17/10/16 25/11/16 159

160 Terrace to units 12 & 13 6w 28/11/16 20/01/17 160

161 New build pedestrian path & planters 6w 28/11/16 20/01/17 161

162 Landscape carpark 6w 23/01/17 03/03/17 162

163 Retail terrace 6w 23/01/17 03/03/17 163

164 Clean and snag 7w 3d 06/03/17 28/04/17 164

165 Complete External works 02/05/17 02/05/17 165

Practical
Completion
166 PRACTICAL COMPLETION 02/05/17 02/05/17 166

Project Codes
RIBA Plan of work Client Representative Project Manager Cost Consultant Lead Designer Professional Team Party Wall Surveyor Principle Contractor Contractor Appointments Long Leads Groundworker Bricklaying Builder's Work Carpentry e.g. rafters & joists Roofing slate & tiles
Plumbing Joinery Electrical & Mechanical Architectural Metalwork Plastering Kitchen Decorations Ceramic tiling Floor finishes - carpet Services Consultant Commissioning Builder's Clean Trade Contractors Soft Strip Landscaping
Stage 0 - Strategic Definition Agree Tender List Review Design Stage 1 - Preparation & Brief Prepare Tender Documents Dwgs/TS/Samples Stage 2 - Concept Design Tender Issue samples/drawings for approval Stage 3 - Developed Design Evaluate Status sample/drawings Stage 4 - Technical Design
Approve Place order Mobilisation Manufacture Stage 5 - Construction Start Arrive on site

Planned by Asta Powerproject