Ghana OCTP Development Project, FPSO

EPC for Module MM1 & MM2


Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
333 13-Mar-15 08-Apr-16
0 TC2A - Manifolding Topsides Modules-(baseline)
0.D.26 Process System 333 13-Mar-15 08-Apr-16
0.D.26.0000 Sub System Code Level 333 13-Mar-15 08-Apr-16
0.D.26.0000.MM1 MM1-Manifold and Pigging 333 13-Mar-15 08-Apr-16
0.D.26.0000.MM1.A Milestone 333 13-Mar-15 08-Apr-16
MM1-10010 Effective date (LOI) 0 13-Mar-15* Effective date (LOI)
MM1-101000 Commence Basic & Detail Engineering Modules MM1 0 13-Mar-15* Commence Basic & Detail Engineering Modules MM1
MM1-101040 HAZID Review Workshop 0 23-Mar-15* HAZID Review Workshop
MM1-101060 HAZOP Review Workshop 0 27-Apr-15* HAZOP Review Workshop
MM1-101080 Commence Fab Modules MM1 0 17-Sep-15 Commence Fab Modules MM1
MM1-101020 Completion Basic & Detail Engineering Modules MM1 0 23-Sep-15* Completion Basic & Detail Engineering Modules MM1
MM1-10070 MCD for MM1 0 24-Mar-16* MCD for MM1
MM1-10090 Commence Load-out Modules MM1 0 26-Mar-16* Commence Load-out Modu
MM1-101100 Modules MM1 available at Singapore Yard 0 08-Apr-16* Modules MM1 available
0.D.26.0000.MM1.B Engineering 327 13-Mar-15 01-Apr-16
0.D.26.0000.MM1.B.0 General 321 13-Mar-15 01-Apr-16
0.D.26.0000.MM1.B.0.92 PTSC 321 13-Mar-15 01-Apr-16
MM1-10130 General for PMT (Meeting, Project Management, Project Coordination, Engineering
321 13-Mar-15
review, etc) 01-Apr-16
MM1-1305-PT-00-A-TB-00001
MM1 & MM2 - Detailed Engineering Execution Plan 40 13-Mar-15 29-Apr-15
MM1-1305-PT-00-A-TB-00001-1
MM1 & MM2 - Detailed Engineering Execution Plan-IDC 8 13-Mar-15* 21-Mar-15
MM1-1305-PT-00-A-TB-00001-2
MM1 & MM2 - Detailed Engineering Execution Plan-IFR 6 23-Mar-15 28-Mar-15
MM1-1305-PT-00-A-TB-00001-3
MM1 & MM2 - Detailed Engineering Execution Plan-IFD 11 30-Mar-15 10-Apr-15
MM1-1305-PT-00-A-TB-00001-4
MM1 & MM2 - Detailed Engineering Execution Plan-IFC 15 11-Apr-15 29-Apr-15
MM1-1305-PT-00-A-KA-00001
MM1 & MM2 - Detailed Engineering Coordination Procedure 31 13-Mar-15 17-Apr-15
MM1-1305-PT-00-A-KA-00001-1
MM1 & MM2 - Detailed Engineering Coordination Procedure-IDC 8 13-Mar-15* 21-Mar-15
MM1-1305-PT-00-A-KA-00001-2
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFR 6 23-Mar-15 28-Mar-15
MM1-1305-PT-00-A-KA-00001-3
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFD 0 30-Mar-15 30-Mar-15
MM1-1305-PT-00-A-KA-00001-4
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFC 17 30-Mar-15 17-Apr-15
0.D.26.0000.MM1.B.9 3D Modelling 65 12-May-15 25-Jul-15
0.D.26.0000.MM1.B.9.92 PTSC 65 12-May-15 25-Jul-15
MM1-1305-PT-00-L-RA-00001
MM1 & MM2 - PDMS 30% model review report 17 12-May-15 30-May-15
MM1-1305-PT-00-L-RA-00001-1
MM1 & MM2 - PDMS 30% model review report-IDC 7 12-May-15* 19-May-15
MM1-1305-PT-00-L-RA-00001-2
MM1 & MM2 - PDMS 30% model review report-IFR 4 20-May-15 23-May-15
MM1-1305-PT-00-L-RA-00001-3
MM1 & MM2 - PDMS 30% model review report-IFD 0 25-May-15 25-May-15
MM1-1305-PT-00-L-RA-00001-4
MM1 & MM2 - PDMS 30% model review report-IFC 6 25-May-15 30-May-15
MM1-1305-PT-00-L-RA-00002
MM1 & MM2 - PDMS 60% model review report 17 09-Jun-15 27-Jun-15
MM1-1305-PT-00-L-RA-00002-1
MM1 & MM2 - PDMS 60% model review report-IDC 7 09-Jun-15* 16-Jun-15
MM1-1305-PT-00-L-RA-00002-2
MM1 & MM2 - PDMS 60% model review report-IFR 4 17-Jun-15 20-Jun-15
MM1-1305-PT-00-L-RA-00002-3
MM1 & MM2 - PDMS 60% model review report-IFD 0 22-Jun-15 22-Jun-15
MM1-1305-PT-00-L-RA-00002-4
MM1 & MM2 - PDMS 60% model review report-IFC 6 22-Jun-15 27-Jun-15
MM1-1305-PT-00-L-RA-00003
MM1 & MM2 - PDMS 90% model review report 17 07-Jul-15 25-Jul-15
MM1-1305-PT-00-L-RA-00003-1
MM1 & MM2 - PDMS 90% model review report -IDC 7 07-Jul-15* 14-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 1 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-L-RA-00003-2
MM1 & MM2 - PDMS 90% model review report -IFR 4 15-Jul-15 18-Jul-15
MM1-1305-PT-00-L-RA-00003-3
MM1 & MM2 - PDMS 90% model review report -IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-00-L-RA-00003-4
MM1 & MM2 - PDMS 90% model review report -IFC 6 20-Jul-15 25-Jul-15
0.D.26.0000.MM1.B.S Process & Systems 79 13-Mar-15 16-Jun-15
0.D.26.0000.MM1.B.S.92 PTSC 79 13-Mar-15 16-Jun-15
MM1-1305-PT-30-P-FD-00001
MM1 & MM2 - Basic Design Data 47 13-Mar-15 09-May-15
MM1-1305-PT-30-P-FD-00001-1
MM1 & MM2 - Basic Design Data-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-30-P-FD-00001-2
MM1 & MM2 - Basic Design Data-IFR 7 24-Mar-15 31-Mar-15
MM1-1305-PT-30-P-FD-00001-3
MM1 & MM2 - Basic Design Data-IFD 13 01-Apr-15 15-Apr-15
MM1-1305-PT-30-P-FD-00001-4
MM1 & MM2 - Basic Design Data-IFC 18 16-Apr-15 09-May-15
MM1-1305-PT-30-P-RA-00001
MM1 & MM2 - Report - HYSYS Simulation 48 13-Mar-15 11-May-15
MM1-1305-PT-30-P-RA-00001-1
MM1 & MM2 - Report - HYSYS Simulation-IDC 1 13-Mar-15* 13-Mar-15
MM1-1305-PT-30-P-RA-00001-2
MM1 & MM2 - Report - HYSYS Simulation-IFR 17 14-Mar-15 02-Apr-15
MM1-1305-PT-30-P-RA-00001-3
MM1 & MM2 - Report - HYSYS Simulation-IFD 13 03-Apr-15 17-Apr-15
MM1-1305-PT-30-P-RA-00001-4
MM1 & MM2 - Report - HYSYS Simulation-IFC 17 18-Apr-15 11-May-15
MM1-1305-PT-30-P-RA-00002
MM1 & MM2 - Report - Line Sizing 55 03-Apr-15 09-Jun-15
MM1-1305-PT-30-P-RA-00002-1
MM1 & MM2 - Report - Line Sizing-IDC 1 03-Apr-15* 03-Apr-15
MM1-1305-PT-30-P-RA-00002-2
MM1 & MM2 - Report - Line Sizing-IFR 21 04-Apr-15 29-Apr-15
MM1-1305-PT-30-P-RA-00002-3
MM1 & MM2 - Report - Line Sizing-IFD 13 02-May-15 16-May-15
MM1-1305-PT-30-P-RA-00002-4
MM1 & MM2 - Report - Line Sizing-IFC 20 18-May-15 09-Jun-15
MM1-1305-PT-30-P-RA-00003
MM1 & MM2 - Report - Utility Summary 40 22-Apr-15 10-Jun-15
MM1-1305-PT-30-P-RA-00003-1
MM1 & MM2 - Report - Utility Summary-IDC 1 22-Apr-15* 22-Apr-15
MM1-1305-PT-30-P-RA-00003-2
MM1 & MM2 - Report - Utility Summary-IFR 6 23-Apr-15 02-May-15
MM1-1305-PT-30-P-RA-00003-3
MM1 & MM2 - Report - Utility Summary-IFD 12 04-May-15 16-May-15
MM1-1305-PT-30-P-RA-00003-4
MM1 & MM2 - Report - Utility Summary-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-CA-00001
MM1 & MM2 - Calculation Note - Depressuring 44 23-Mar-15 15-May-15
MM1-1305-PT-30-P-CA-00001-1
MM1 & MM2 - Calculation Note - Depressuring -IDC 1 23-Mar-15* 23-Mar-15
MM1-1305-PT-30-P-CA-00001-2
MM1 & MM2 - Calculation Note - Depressuring -IFR 12 24-Mar-15 06-Apr-15
MM1-1305-PT-30-P-CA-00001-3
MM1 & MM2 - Calculation Note - Depressuring -IFD 13 07-Apr-15 21-Apr-15
MM1-1305-PT-30-P-CA-00001-4
MM1 & MM2 - Calculation Note - Depressuring -IFC 18 22-Apr-15 15-May-15
MM1-1305-PT-30-P-CA-00002
MM1 & MM2 - Calculation Note - PSV Sizing 44 07-Apr-15 30-May-15
MM1-1305-PT-30-P-CA-00002-1
MM1 & MM2 - Calculation Note - PSV Sizing -IDC 1 07-Apr-15* 07-Apr-15
MM1-1305-PT-30-P-CA-00002-2
MM1 & MM2 - Calculation Note - PSV Sizing -IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-CA-00002-3
MM1 & MM2 - Calculation Note - PSV Sizing -IFD 10 22-Apr-15 06-May-15
MM1-1305-PT-30-P-CA-00002-4
MM1 & MM2 - Calculation Note - PSV Sizing -IFC 21 07-May-15 30-May-15
MM1-1305-PT-30-P-XA-00001
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00001-1
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XA-00001-2
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00001-3
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00001-4
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XA-00002
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00002-1
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 2 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-30-P-XA-00002-2
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00002-3
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00002-4
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XA-00003
MM1 & MM2 - Material Selection Diagrams (3 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00003-1
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XA-00003-2
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00003-3
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00003-4
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00001
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00001-1
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00001-2
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00001-3
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00001-4
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00002
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00002-1
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00002-2
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00002-3
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00002-4
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00003
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00003-1
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00003-2
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00003-3
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00003-4
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00004
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00004-1
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00004-2
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00004-3
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00004-4
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00005
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00005-1
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00005-2
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00005-3
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00005-4
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00006
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00006-1
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00006-2
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00006-3
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00006-4
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00007
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00007-1
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00007-2
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00007-3
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 3 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-30-P-XB-00007-4
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00008
MM1 & MM2 - P&ID HP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00008-1
MM1 & MM2 - P&ID HP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00008-2
MM1 & MM2 - P&ID HP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00008-3
MM1 & MM2 - P&ID HP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00008-4
MM1 & MM2 - P&ID HP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00009
MM1 & MM2 - P&ID HHP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00009-1
MM1 & MM2 - P&ID HHP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00009-2
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00009-3
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00009-4
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00010
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00010-1
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00010-2
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00010-3
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00010-4
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00011
MM1 & MM2 - P&ID Test Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00011-1
MM1 & MM2 - P&ID Test Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00011-2
MM1 & MM2 - P&ID Test Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00011-3
MM1 & MM2 - P&ID Test Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00011-4
MM1 & MM2 - P&ID Test Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00012
MM1 & MM2 - P&ID Gas Injection Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00012-1
MM1 & MM2 - P&ID Gas Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00012-2
MM1 & MM2 - P&ID Gas Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00012-3
MM1 & MM2 - P&ID Gas Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00012-4
MM1 & MM2 - P&ID Gas Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00013
MM1 & MM2 - P&ID Water Injection Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00013-1
MM1 & MM2 - P&ID Water Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00013-2
MM1 & MM2 - P&ID Water Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00013-3
MM1 & MM2 - P&ID Water Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00013-4
MM1 & MM2 - P&ID Water Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00014
MM1 & MM2 - P&ID Gas Export Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00014-1
MM1 & MM2 - P&ID Gas Export Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00014-2
MM1 & MM2 - P&ID Gas Export Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00014-3
MM1 & MM2 - P&ID Gas Export Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00014-4
MM1 & MM2 - P&ID Gas Export Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00015
MM1 & MM2 - P&ID Gas Lift Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00015-1
MM1 & MM2 - P&ID Gas Lift Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00015-2
MM1 & MM2 - P&ID Gas Lift Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00015-3
MM1 & MM2 - P&ID Gas Lift Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00015-4
MM1 & MM2 - P&ID Gas Lift Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00016
MM1 & MM2 - P&ID Diesel Manifold 69 13-Mar-15 04-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 4 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-30-P-XB-00016-1
MM1 & MM2 - P&ID Diesel Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00016-2
MM1 & MM2 - P&ID Diesel Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00016-3
MM1 & MM2 - P&ID Diesel Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00016-4
MM1 & MM2 - P&ID Diesel Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-LA-00001
MM1 & MM2 - Line List 56 09-Apr-15 16-Jun-15
MM1-1305-PT-30-P-LA-00001-1
MM1 & MM2 - Line List-IDC 14 09-Apr-15* 24-Apr-15
MM1-1305-PT-30-P-LA-00001-2
MM1 & MM2 - Line List-IFR 10 25-Apr-15 09-May-15
MM1-1305-PT-30-P-LA-00001-3
MM1 & MM2 - Line List-IFD 14 11-May-15 26-May-15
MM1-1305-PT-30-P-LA-00001-4
MM1 & MM2 - Line List-IFC 18 27-May-15 16-Jun-15
MM1-1305-PT-30-P-XM-00001
MM1 & MM2 - Safe Chart 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-XM-00001-1
MM1 & MM2 - Safe Chart-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-XM-00001-2
MM1 & MM2 - Safe Chart-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-XM-00001-3
MM1 & MM2 - Safe Chart-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-XM-00001-4
MM1 & MM2 - Safe Chart-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-XL-00001
MM1 & MM2 - ESD Logic Diagram 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-XL-00001-1
MM1 & MM2 - ESD Logic Diagram-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-XL-00001-2
MM1 & MM2 - ESD Logic Diagram-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-XL-00001-3
MM1 & MM2 - ESD Logic Diagram-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-XL-00001-4
MM1 & MM2 - ESD Logic Diagram-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-LA-00002
MM1 & MM2 - Alarm / Trip Schedule 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-LA-00002-1
MM1 & MM2 - Alarm / Trip Schedule-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-LA-00002-2
MM1 & MM2 - Alarm / Trip Schedule-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-LA-00002-3
MM1 & MM2 - Alarm / Trip Schedule-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-LA-00002-4
MM1 & MM2 - Alarm / Trip Schedule-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-X-CA-00001
MM1 & MM2 - Calculation Note - Deluge System 53 08-Apr-15 11-Jun-15
MM1-1305-PT-30-X-CA-00001-1
MM1 & MM2 - Calculation Note - Deluge System-IDC 1 08-Apr-15* 08-Apr-15
MM1-1305-PT-30-X-CA-00001-2
MM1 & MM2 - Calculation Note - Deluge System-IFR 17 09-Apr-15 29-Apr-15
MM1-1305-PT-30-X-CA-00001-3
MM1 & MM2 - Calculation Note - Deluge System-IFD 14 02-May-15 18-May-15
MM1-1305-PT-30-X-CA-00001-4
MM1 & MM2 - Calculation Note - Deluge System-IFC 21 19-May-15 11-Jun-15
MM1-1305-PT-30-X-CA-00002
MM1 & MM2 - Steady State Analysis for Deluge System 51 15-Apr-15 16-Jun-15
MM1-1305-PT-30-X-CA-00002-1
MM1 & MM2 - Steady State Analysis for Deluge System-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-30-X-CA-00002-2
MM1 & MM2 - Steady State Analysis for Deluge System-IFR 15 16-Apr-15 06-May-15
MM1-1305-PT-30-X-CA-00002-3
MM1 & MM2 - Steady State Analysis for Deluge System-IFD 15 07-May-15 23-May-15
MM1-1305-PT-30-X-CA-00002-4
MM1 & MM2 - Steady State Analysis for Deluge System-IFC 20 25-May-15 16-Jun-15
MM1-1305-PT-30-X-XE-10001
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
59 26-Mar-15
Equipment Layout
05-Jun-15
Plan
MM1-1305-PT-30-X-XE-10001-1
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
13 26-Mar-15*
Equipment Layout
09-Apr-15
Plan-IDC
MM1-1305-PT-30-X-XE-10001-2
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
12 10-Apr-15
Equipment Layout
23-Apr-15
Plan-IFR
MM1-1305-PT-30-X-XE-10001-3
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
11 24-Apr-15
Equipment Layout
09-May-15
Plan-IFD
MM1-1305-PT-30-X-XE-10001-4
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
23 11-May-15
Equipment Layout
05-Jun-15
Plan-IFC
MM1-1305-PT-30-X-XE-10002
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
59 Equipment
26-Mar-15 Layout
05-Jun-15
Plan
MM1-1305-PT-30-X-XE-10002-1
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
13 Equipment
26-Mar-15*Layout
09-Apr-15
Plan-IDC
MM1-1305-PT-30-X-XE-10002-2
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
12 Equipment
10-Apr-15 Layout
23-Apr-15
Plan-IFR

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 5 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-30-X-XE-10002-3
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
11 Equipment
24-Apr-15 Layout
09-May-15
Plan-IFD
MM1-1305-PT-30-X-XE-10002-4
MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
23 Equipment
11-May-15Layout
05-Jun-15
Plan-IFC
MM1-1305-PT-30-X-XB-10001
MM1 - P&ID Firewater Deluge System 56 08-Apr-15 15-Jun-15
MM1-1305-PT-30-X-XB-10001-1
MM1 - P&ID Firewater Deluge System-IDC 10 08-Apr-15* 18-Apr-15
MM1-1305-PT-30-X-XB-10001-2
MM1 - P&ID Firewater Deluge System-IFR 11 20-Apr-15 05-May-15
MM1-1305-PT-30-X-XB-10001-3
MM1 - P&ID Firewater Deluge System-IFD 15 06-May-15 22-May-15
MM1-1305-PT-30-X-XB-10001-4
MM1 - P&ID Firewater Deluge System-IFC 20 23-May-15 15-Jun-15
0.D.26.0000.MM1.B.N Structural 315 16-Mar-15 21-Mar-16
0.D.26.0000.MM1.B.N.92 PTSC 315 16-Mar-15 21-Mar-16
MM1-1305-PT-95-N-RA-10001
MM1 - In-place Analysis Report 82 16-Mar-15 22-Jun-15
MM1-1305-PT-95-N-RA-10001-1
MM1 - In-place Analysis Report-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-RA-10001-2
MM1 - In-place Analysis Report-IFR 55 16-Mar-15 21-May-15
MM1-1305-PT-95-N-RA-10001-3
MM1 - In-place Analysis Report-IFD 12 22-May-15 04-Jun-15
MM1-1305-PT-95-N-RA-10001-4
MM1 - In-place Analysis Report-IFC 15 05-Jun-15 22-Jun-15
MM1-1305-PT-95-N-RA-10002
MM1 - Preservice Analysis Report 85 16-Mar-15 25-Jun-15
MM1-1305-PT-95-N-RA-10002-1
MM1 - Preservice Analysis Report-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-RA-10002-2
MM1 - Preservice Analysis Report-IFR 57 16-Mar-15 23-May-15
MM1-1305-PT-95-N-RA-10002-3
MM1 - Preservice Analysis Report-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-RA-10002-4
MM1 - Preservice Analysis Report-IFC 16 08-Jun-15 25-Jun-15
MM1-1305-PT-95-N-RA-10003
MM1 - Structural Miscellaneous design 45 06-Jun-15 28-Jul-15
MM1-1305-PT-95-N-RA-10003-1
MM1 - Structural Miscellaneous design-IDC 1 06-Jun-15* 06-Jun-15
MM1-1305-PT-95-N-RA-10003-2
MM1 - Structural Miscellaneous design-IFR 17 08-Jun-15 26-Jun-15
MM1-1305-PT-95-N-RA-10003-3
MM1 - Structural Miscellaneous design-IFD 12 27-Jun-15 10-Jul-15
MM1-1305-PT-95-N-RA-10003-4
MM1 - Structural Miscellaneous design-IFC 15 11-Jul-15 28-Jul-15
MM1-1305-PT-95-N-RA-10005
MM1 - Weight Control Report 74 28-Mar-15 25-Jun-15
MM1-1305-PT-95-N-RA-10005-1
MM1 - Weight Control Report-IDC 33 28-Mar-15* 08-May-15
MM1-1305-PT-95-N-RA-10005-2
MM1 - Weight Control Report-IFR 13 09-May-15 23-May-15
MM1-1305-PT-95-N-RA-10005-3
MM1 - Weight Control Report-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-RA-10005-4
MM1 - Weight Control Report-IFC 16 08-Jun-15 25-Jun-15
MM1-1305-PT-95-N-RA-10006
MM1 - Seafastening Report 50 30-Jun-15 26-Aug-15
MM1-1305-PT-95-N-RA-10006-1
MM1 - Seafastening Report-IDC 1 30-Jun-15* 30-Jun-15
MM1-1305-PT-95-N-RA-10006-2
MM1 - Seafastening Report-IFR 16 01-Jul-15 18-Jul-15
MM1-1305-PT-95-N-RA-10006-3
MM1 - Seafastening Report-IFD 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-RA-10006-4
MM1 - Seafastening Report-IFC 21 03-Aug-15 26-Aug-15
MM1-1305-PT-95-N-LA-00001
MM1 & MM2 - Structural Primary & secondary steel MTOs 61 16-Mar-15 28-May-15
MM1-1305-PT-95-N-LA-00001-1
MM1 & MM2 - Structural Primary & secondary steel MTOs-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-LA-00001-2
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFR 24 16-Mar-15 11-Apr-15
MM1-1305-PT-95-N-LA-00001-3
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFD 0 13-Apr-15 13-Apr-15
MM1-1305-PT-95-N-LA-00001-4
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFC 37 13-Apr-15 28-May-15
MM1-1305-PT-95-N-LA-00002
MM1 & MM2 - Structural Tertiary Steel MTOs 67 04-May-15 20-Jul-15
MM1-1305-PT-95-N-LA-00002-1
MM1 & MM2 - Structural Tertiary Steel MTOs-IDC 1 04-May-15* 04-May-15
MM1-1305-PT-95-N-LA-00002-2
MM1 & MM2 - Structural Tertiary Steel MTOs-IFR 25 05-May-15 02-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 6 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-LA-00002-3
MM1 & MM2 - Structural Tertiary Steel MTOs-IFD 0 03-Jun-15 03-Jun-15
MM1-1305-PT-95-N-LA-00002-4
MM1 & MM2 - Structural Tertiary Steel MTOs-IFC 41 03-Jun-15 20-Jul-15
MM1-1305-PT-95-N-LA-00003
MM1 & MM2 - Structural Miscellaneous MTOs 68 22-Jun-15 09-Sep-15
MM1-1305-PT-95-N-LA-00003-1
MM1 & MM2 - Structural Miscellaneous MTOs-IDC 0 22-Jun-15* 22-Jun-15
MM1-1305-PT-95-N-LA-00003-2
MM1 & MM2 - Structural Miscellaneous MTOs-IFR 24 22-Jun-15 18-Jul-15
MM1-1305-PT-95-N-LA-00003-3
MM1 & MM2 - Structural Miscellaneous MTOs-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-LA-00003-4
MM1 & MM2 - Structural Miscellaneous MTOs-IFC 44 20-Jul-15 09-Sep-15
MM1-1305-PT-95-N-LA-00004
MM1 & MM2 - Structural Grating MTOs 71 23-Jun-15 14-Sep-15
MM1-1305-PT-95-N-LA-00004-1
MM1 & MM2 - Structural Grating MTOs-IDC 1 23-Jun-15* 23-Jun-15
MM1-1305-PT-95-N-LA-00004-2
MM1 & MM2 - Structural Grating MTOs-IFR 25 24-Jun-15 22-Jul-15
MM1-1305-PT-95-N-LA-00004-3
MM1 & MM2 - Structural Grating MTOs-IFD 0 23-Jul-15 23-Jul-15
MM1-1305-PT-95-N-LA-00004-4
MM1 & MM2 - Structural Grating MTOs-IFC 45 23-Jul-15 14-Sep-15
MM1-1305-PT-95-N-XG-01001
MM1 & MM2 - Structural General Notes 47 24-Mar-15 20-May-15
MM1-1305-PT-95-N-XG-01001-1
MM1 & MM2 - Structural General Notes-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-01001-2
MM1 & MM2 - Structural General Notes-IFR 18 25-Mar-15 14-Apr-15
MM1-1305-PT-95-N-XG-01001-3
MM1 & MM2 - Structural General Notes-IFD 11 15-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-01001-4
MM1 & MM2 - Structural General Notes-IFC 17 29-Apr-15 20-May-15
MM1-1305-PT-95-N-XG-01002
MM1 & MM2 - Typical Weld Details 49 24-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01002-1
MM1 & MM2 - Typical Weld Details-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-01002-2
MM1 & MM2 - Typical Weld Details-IFR 20 25-Mar-15 16-Apr-15
MM1-1305-PT-95-N-XG-01002-3
MM1 & MM2 - Typical Weld Details-IFD 10 17-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01002-4
MM1 & MM2 - Typical Weld Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01003
MM1 & MM2 - Typical Connection Details 48 02-Apr-15 30-May-15
MM1-1305-PT-95-N-XG-01003-1
MM1 & MM2 - Typical Connection Details-IDC 1 02-Apr-15* 02-Apr-15
MM1-1305-PT-95-N-XG-01003-2
MM1 & MM2 - Typical Connection Details-IFR 20 03-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-01003-3
MM1 & MM2 - Typical Connection Details-IFD 9 27-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-01003-4
MM1 & MM2 - Typical Connection Details-IFC 18 11-May-15 30-May-15
MM1-1305-PT-95-N-XG-01004
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01004-1
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01004-2
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01004-3
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01004-4
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01005
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01005-1
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01005-2
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01005-3
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01005-4
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01006
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01006-1
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01006-2
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01006-3
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01006-4
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFC 18 02-May-15 22-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 7 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-01007
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01007-1
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01007-2
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01007-3
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01007-4
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01008
MM1 & MM2 - Typical Plating & Grating Arrangement & Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01008-1
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01008-2
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01008-3
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01008-4
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01009
MM1 & MM2 - Typical Handrail Arrangement & Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01009-1
MM1 & MM2 - Typical Handrail Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01009-2
MM1 & MM2 - Typical Handrail Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01009-3
MM1 & MM2 - Typical Handrail Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01009-4
MM1 & MM2 - Typical Handrail Arrangement & Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01010
MM1 & MM2 - Typical Drain Outlet Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01010-1
MM1 & MM2 - Typical Drain Outlet Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01010-2
MM1 & MM2 - Typical Drain Outlet Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01010-3
MM1 & MM2 - Typical Drain Outlet Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01010-4
MM1 & MM2 - Typical Drain Outlet Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-12001
MM1 - Drawing Index 64 24-Mar-15 09-Jun-15
MM1-1305-PT-95-N-XG-12001-1
MM1 - Drawing Index-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-12001-2
MM1 - Drawing Index-IFR 27 25-Mar-15 24-Apr-15
MM1-1305-PT-95-N-XG-12001-3
MM1 - Drawing Index-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12001-4
MM1 - Drawing Index-IFC 36 25-Apr-15 09-Jun-15
MM1-1305-PT-95-N-XG-12002
MM1 - Structural Perspective View 52 29-Apr-15 30-Jun-15
MM1-1305-PT-95-N-XG-12002-1
MM1 - Structural Perspective View-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12002-2
MM1 - Structural Perspective View-IFR 24 29-Apr-15 28-May-15
MM1-1305-PT-95-N-XG-12002-3
MM1 - Structural Perspective View-IFD 0 29-May-15 29-May-15
MM1-1305-PT-95-N-XG-12002-4
MM1 - Structural Perspective View-IFC 28 29-May-15 30-Jun-15
MM1-1305-PT-95-N-XG-12003
MM1 - Deck Load Plan 32 29-Apr-15 06-Jun-15
MM1-1305-PT-95-N-XG-12003-1
MM1 - Deck Load Plan-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12003-2
MM1 - Deck Load Plan-IFR 20 29-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12003-3
MM1 - Deck Load Plan-IFD 0 25-May-15 25-May-15
MM1-1305-PT-95-N-XG-12003-4
MM1 - Deck Load Plan-IFC 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-XG-12004
MM1 - Upper Deck Primary Framing Plan 36 02-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12004-1
MM1 - Upper Deck Primary Framing Plan-IDC 19 02-Apr-15* 23-Apr-15
MM1-1305-PT-95-N-XG-12004-2
MM1 - Upper Deck Primary Framing Plan-IFR 4 24-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12004-3
MM1 - Upper Deck Primary Framing Plan-IFD 0 02-May-15 02-May-15
MM1-1305-PT-95-N-XG-12004-4
MM1 - Upper Deck Primary Framing Plan-IFC 13 02-May-15 16-May-15
MM1-1305-PT-95-N-XG-12005
MM1 - Mezzanine Deck Primary Framing Plan 36 31-Mar-15 14-May-15
MM1-1305-PT-95-N-XG-12005-1
MM1 - Mezzanine Deck Primary Framing Plan-IDC 19 31-Mar-15* 21-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 8 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12005-2
MM1 - Mezzanine Deck Primary Framing Plan-IFR 5 22-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12005-3
MM1 - Mezzanine Deck Primary Framing Plan-IFD 0 29-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12005-4
MM1 - Mezzanine Deck Primary Framing Plan-IFC 12 29-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12006
MM1 - Main Deck Primary Framing Plan 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12006-1
MM1 - Main Deck Primary Framing Plan-IDC 19 28-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12006-2
MM1 - Main Deck Primary Framing Plan-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12006-3
MM1 - Main Deck Primary Framing Plan-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12006-4
MM1 - Main Deck Primary Framing Plan-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12007
MM1 - Truss Row 89 & Row 90 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12007-1
MM1 - Truss Row 89 & Row 90-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12007-2
MM1 - Truss Row 89 & Row 90-IFR 6 18-Apr-15 24-Apr-15
MM1-1305-PT-95-N-XG-12007-3
MM1 - Truss Row 89 & Row 90-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12007-4
MM1 - Truss Row 89 & Row 90-IFC 12 25-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12008
MM1 - Truss Row 91 & Row 92 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12008-1
MM1 - Truss Row 91 & Row 92-IDC 19 28-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12008-2
MM1 - Truss Row 91 & Row 92-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12008-3
MM1 - Truss Row 91 & Row 92-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12008-4
MM1 - Truss Row 91 & Row 92-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12009
MM1 - Truss Row 93 & Row 94 34 02-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12009-1
MM1 - Truss Row 93 & Row 94-IDC 17 02-Apr-15* 21-Apr-15
MM1-1305-PT-95-N-XG-12009-2
MM1 - Truss Row 93 & Row 94-IFR 6 22-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12009-3
MM1 - Truss Row 93 & Row 94-IFD 0 02-May-15 02-May-15
MM1-1305-PT-95-N-XG-12009-4
MM1 - Truss Row 93 & Row 94-IFC 11 02-May-15 14-May-15
MM1-1305-PT-95-N-XG-12010
MM1 - Truss Row 1A 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12010-1
MM1 - Truss Row 1A-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12010-2
MM1 - Truss Row 1A-IFR 6 18-Apr-15 24-Apr-15
MM1-1305-PT-95-N-XG-12010-3
MM1 - Truss Row 1A-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12010-4
MM1 - Truss Row 1A-IFC 12 25-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12011
MM1 - Truss Row 1B 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12011-1
MM1 - Truss Row 1B-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12011-2
MM1 - Truss Row 1B-IFR 7 18-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12011-3
MM1 - Truss Row 1B-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12011-4
MM1 - Truss Row 1B-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12012
MM1 - Truss Row 1C 35 31-Mar-15 13-May-15
MM1-1305-PT-95-N-XG-12012-1
MM1 - Truss Row 1C-IDC 17 31-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12012-2
MM1 - Truss Row 1C-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12012-3
MM1 - Truss Row 1C-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12012-4
MM1 - Truss Row 1C-IFC 12 27-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12013
MM1 - Upper Deck Joint Details Sheet 1 27 17-Apr-15 21-May-15
MM1-1305-PT-95-N-XG-12013-1
MM1 - Upper Deck Joint Details Sheet 1-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12013-2
MM1 - Upper Deck Joint Details Sheet 1-IFR 20 18-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12013-3
MM1 - Upper Deck Joint Details Sheet 1-IFD 0 15-May-15 15-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 9 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12013-4
MM1 - Upper Deck Joint Details Sheet 1-IFC 6 15-May-15 21-May-15
MM1-1305-PT-95-N-XG-12014
MM1 - Upper Deck Joint Details Sheet 2 27 17-Apr-15 21-May-15
MM1-1305-PT-95-N-XG-12014-1
MM1 - Upper Deck Joint Details Sheet 2-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12014-2
MM1 - Upper Deck Joint Details Sheet 2-IFR 20 18-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12014-3
MM1 - Upper Deck Joint Details Sheet 2-IFD 0 15-May-15 15-May-15
MM1-1305-PT-95-N-XG-12014-4
MM1 - Upper Deck Joint Details Sheet 2-IFC 6 15-May-15 21-May-15
MM1-1305-PT-95-N-XG-12015
MM1 - Upper Deck Joint Details Sheet 3 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12015-1
MM1 - Upper Deck Joint Details Sheet 3-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12015-2
MM1 - Upper Deck Joint Details Sheet 3-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12015-3
MM1 - Upper Deck Joint Details Sheet 3-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12015-4
MM1 - Upper Deck Joint Details Sheet 3-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12016
MM1 - Upper Deck Joint Details sheet 4 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12016-1
MM1 - Upper Deck Joint Details sheet 4-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12016-2
MM1 - Upper Deck Joint Details sheet 4-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12016-3
MM1 - Upper Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12016-4
MM1 - Upper Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12017
MM1 - Upper Deck Joint Details sheet 5 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12017-1
MM1 - Upper Deck Joint Details sheet 5-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12017-2
MM1 - Upper Deck Joint Details sheet 5-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12017-3
MM1 - Upper Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12017-4
MM1 - Upper Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12018
MM1 - Mezzanine Deck Joint Details sheet 1 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12018-1
MM1 - Mezzanine Deck Joint Details sheet 1-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12018-2
MM1 - Mezzanine Deck Joint Details sheet 1-IFR 22 15-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12018-3
MM1 - Mezzanine Deck Joint Details sheet 1-IFD 0 14-May-15 14-May-15
MM1-1305-PT-95-N-XG-12018-4
MM1 - Mezzanine Deck Joint Details sheet 1-IFC 11 14-May-15 26-May-15
MM1-1305-PT-95-N-XG-12019
MM1 - Mezzanine Deck Joint Details sheet 2 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12019-1
MM1 - Mezzanine Deck Joint Details sheet 2-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12019-2
MM1 - Mezzanine Deck Joint Details sheet 2-IFR 22 15-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12019-3
MM1 - Mezzanine Deck Joint Details sheet 2-IFD 0 14-May-15 14-May-15
MM1-1305-PT-95-N-XG-12019-4
MM1 - Mezzanine Deck Joint Details sheet 2-IFC 11 14-May-15 26-May-15
MM1-1305-PT-95-N-XG-12020
MM1 - Mezzanine Deck Joint Details sheet 3 33 15-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12020-1
MM1 - Mezzanine Deck Joint Details sheet 3-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12020-2
MM1 - Mezzanine Deck Joint Details sheet 3-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12020-3
MM1 - Mezzanine Deck Joint Details sheet 3-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12020-4
MM1 - Mezzanine Deck Joint Details sheet 3-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12021
MM1 - Mezzanine Deck Joint Details sheet 4 33 15-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12021-1
MM1 - Mezzanine Deck Joint Details sheet 4-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12021-2
MM1 - Mezzanine Deck Joint Details sheet 4-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12021-3
MM1 - Mezzanine Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12021-4
MM1 - Mezzanine Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12022
MM1 - Mezzanine Deck Joint Details sheet 5 33 15-Apr-15 26-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 10 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12022-1
MM1 - Mezzanine Deck Joint Details sheet 5-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12022-2
MM1 - Mezzanine Deck Joint Details sheet 5-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12022-3
MM1 - Mezzanine Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12022-4
MM1 - Mezzanine Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12023
MM1 - Main Deck Joint Details Sheet 1 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12023-1
MM1 - Main Deck Joint Details Sheet 1-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12023-2
MM1 - Main Deck Joint Details Sheet 1-IFR 19 15-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-12023-3
MM1 - Main Deck Joint Details Sheet 1-IFD 0 11-May-15 11-May-15
MM1-1305-PT-95-N-XG-12023-4
MM1 - Main Deck Joint Details Sheet 1-IFC 14 11-May-15 26-May-15
MM1-1305-PT-95-N-XG-12024
MM1 - Main Deck Joint Details Sheet 2 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12024-1
MM1 - Main Deck Joint Details Sheet 2-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12024-2
MM1 - Main Deck Joint Details Sheet 2-IFR 19 15-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-12024-3
MM1 - Main Deck Joint Details Sheet 2-IFD 0 11-May-15 11-May-15
MM1-1305-PT-95-N-XG-12024-4
MM1 - Main Deck Joint Details Sheet 2-IFC 14 11-May-15 26-May-15
MM1-1305-PT-95-N-XG-12025
MM1 - Main Deck Joint Details Sheet 3 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12025-1
MM1 - Main Deck Joint Details Sheet 3-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12025-2
MM1 - Main Deck Joint Details Sheet 3-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12025-3
MM1 - Main Deck Joint Details Sheet 3-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12025-4
MM1 - Main Deck Joint Details Sheet 3-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12026
MM1 - Main Deck Joint Details Sheet 4 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12026-1
MM1 - Main Deck Joint Details Sheet 4-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12026-2
MM1 - Main Deck Joint Details Sheet 4-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12026-3
MM1 - Main Deck Joint Details Sheet 4-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12026-4
MM1 - Main Deck Joint Details Sheet 4-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12027
MM1 - Main Deck Joint Details Sheet 5 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12027-1
MM1 - Main Deck Joint Details Sheet 5-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12027-2
MM1 - Main Deck Joint Details Sheet 5-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12027-3
MM1 - Main Deck Joint Details Sheet 5-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12027-4
MM1 - Main Deck Joint Details Sheet 5-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12028
MM1 - Upper Deck Secondary Framing Plan 29 20-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12028-1
MM1 - Upper Deck Secondary Framing Plan-IDC 15 20-Apr-15* 09-May-15
MM1-1305-PT-95-N-XG-12028-2
MM1 - Upper Deck Secondary Framing Plan-IFR 6 11-May-15 16-May-15
MM1-1305-PT-95-N-XG-12028-3
MM1 - Upper Deck Secondary Framing Plan-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12028-4
MM1 - Upper Deck Secondary Framing Plan-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12029
MM1 - Mezzanine Deck Secondary Framing Plan 28 18-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12029-1
MM1 - Mezzanine Deck Secondary Framing Plan-IDC 15 18-Apr-15* 08-May-15
MM1-1305-PT-95-N-XG-12029-2
MM1 - Mezzanine Deck Secondary Framing Plan-IFR 6 09-May-15 15-May-15
MM1-1305-PT-95-N-XG-12029-3
MM1 - Mezzanine Deck Secondary Framing Plan-IFD 0 16-May-15 16-May-15
MM1-1305-PT-95-N-XG-12029-4
MM1 - Mezzanine Deck Secondary Framing Plan-IFC 7 16-May-15 23-May-15
MM1-1305-PT-95-N-XG-12030
MM1 - Main Deck Secondary Framing plan 28 18-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12030-1
MM1 - Main Deck Secondary Framing plan-IDC 15 18-Apr-15* 08-May-15
MM1-1305-PT-95-N-XG-12030-2
MM1 - Main Deck Secondary Framing plan-IFR 6 09-May-15 15-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 11 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12030-3
MM1 - Main Deck Secondary Framing plan-IFD 0 16-May-15 16-May-15
MM1-1305-PT-95-N-XG-12030-4
MM1 - Main Deck Secondary Framing plan-IFC 7 16-May-15 23-May-15
MM1-1305-PT-95-N-XG-12031
MM1 - Upper Deck Flooring & Handrail Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12031-1
MM1 - Upper Deck Flooring & Handrail Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12031-2
MM1 - Upper Deck Flooring & Handrail Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12031-3
MM1 - Upper Deck Flooring & Handrail Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12031-4
MM1 - Upper Deck Flooring & Handrail Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12032
MM1 - Mezzanine Deck Flooring & Handrail Layout 53 23-Apr-15 26-Jun-15
MM1-1305-PT-95-N-XG-12032-1
MM1 - Mezzanine Deck Flooring & Handrail Layout-IDC 35 23-Apr-15* 05-Jun-15
MM1-1305-PT-95-N-XG-12032-2
MM1 - Mezzanine Deck Flooring & Handrail Layout-IFR 6 06-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12032-3
MM1 - Mezzanine Deck Flooring & Handrail Layout-IFD 0 13-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12032-4
MM1 - Mezzanine Deck Flooring & Handrail Layout-IFC 12 13-Jun-15 26-Jun-15
MM1-1305-PT-95-N-XG-12033
MM1 - Main Deck Flooring & Handrail Layout 54 23-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12033-1
MM1 - Main Deck Flooring & Handrail Layout-IDC 36 23-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12033-2
MM1 - Main Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12033-3
MM1 - Main Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12033-4
MM1 - Main Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12034
MM1 - Upper Deck Penetration Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12034-1
MM1 - Upper Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12034-2
MM1 - Upper Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12034-3
MM1 - Upper Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12034-4
MM1 - Upper Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12035
MM1 - Mezzanine Deck Penetration Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12035-1
MM1 - Mezzanine Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12035-2
MM1 - Mezzanine Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12035-3
MM1 - Mezzanine Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12035-4
MM1 - Mezzanine Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12036
MM1 - Main Deck Penetration Layout 51 27-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12036-1
MM1 - Main Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12036-2
MM1 - Main Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12036-3
MM1 - Main Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12036-4
MM1 - Main Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12037
MM1 - Lifting Padeye Arrangement & Details Sheet 1 47 29-Apr-15 24-Jun-15
MM1-1305-PT-95-N-XG-12037-1
MM1 - Lifting Padeye Arrangement & Details Sheet 1-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12037-2
MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFR 31 29-Apr-15 05-Jun-15
MM1-1305-PT-95-N-XG-12037-3
MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFD 0 06-Jun-15 06-Jun-15
MM1-1305-PT-95-N-XG-12037-4
MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFC 16 06-Jun-15 24-Jun-15
MM1-1305-PT-95-N-XG-12038
MM1 - Lifting Padeye Arrangement & Details Sheet 2 47 29-Apr-15 24-Jun-15
MM1-1305-PT-95-N-XG-12038-1
MM1 - Lifting Padeye Arrangement & Details Sheet 2-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12038-2
MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFR 31 29-Apr-15 05-Jun-15
MM1-1305-PT-95-N-XG-12038-3
MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFD 0 06-Jun-15 06-Jun-15
MM1-1305-PT-95-N-XG-12038-4
MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFC 16 06-Jun-15 24-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 12 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12039
MM1 - Stair Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12039-1
MM1 - Stair Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12039-2
MM1 - Stair Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12039-3
MM1 - Stair Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12039-4
MM1 - Stair Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12040
MM1 - Stair Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12040-1
MM1 - Stair Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12040-2
MM1 - Stair Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12040-3
MM1 - Stair Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12040-4
MM1 - Stair Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12041
MM1 - Ladder Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12041-1
MM1 - Ladder Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12041-2
MM1 - Ladder Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12041-3
MM1 - Ladder Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12041-4
MM1 - Ladder Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12042
MM1 - Ladder Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12042-1
MM1 - Ladder Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12042-2
MM1 - Ladder Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12042-3
MM1 - Ladder Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12042-4
MM1 - Ladder Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12043
MM1 - Mechanical Handling For Main Deck Equipment - sheet 1 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12043-1
MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12043-2
MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12043-3
MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12043-4
MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12044
MM1 - Mechanical Handling For Main Deck Equipment - sheet 2 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12044-1
MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12044-2
MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12044-3
MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12044-4
MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12045
MM1 - Mechanical Handling For Main Deck Equipment - sheet 3 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12045-1
MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12045-2
MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12045-3
MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12045-4
MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12046
MM1 - Mechanical Handling For Main Deck Equipment - sheet 4 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12046-1
MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12046-2
MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12046-3
MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12046-4
MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12047
MM1 - Mechanical Handling For Main Deck Equipment - sheet 5 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12047-1
MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IDC 11 01-Jun-15* 12-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 13 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-95-N-XG-12047-2
MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12047-3
MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12047-4
MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12048
MM1 - Equipment Support- Sheet 1 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12048-1
MM1 - Equipment Support- Sheet 1-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12048-2
MM1 - Equipment Support- Sheet 1-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12048-3
MM1 - Equipment Support- Sheet 1-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12048-4
MM1 - Equipment Support- Sheet 1-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12049
MM1 - Equipment Support- Sheet 2 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12049-1
MM1 - Equipment Support- Sheet 2-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12049-2
MM1 - Equipment Support- Sheet 2-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12049-3
MM1 - Equipment Support- Sheet 2-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12049-4
MM1 - Equipment Support- Sheet 2-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12050
MM1 - Equipment Support- Sheet 3 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12050-1
MM1 - Equipment Support- Sheet 3-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12050-2
MM1 - Equipment Support- Sheet 3-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12050-3
MM1 - Equipment Support- Sheet 3-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12050-4
MM1 - Equipment Support- Sheet 3-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12051
MM1 - Seafastening On Barge Arrangment & Details - Sheet 1 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12051-1
MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12051-2
MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12051-3
MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12051-4
MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFC 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-XG-12052
MM1 - Seafastening On Barge Arrangment & Details - Sheet 2 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12052-1
MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12052-2
MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12052-3
MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12052-4
MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFC 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-XG-12053
MM1 - Seafastening On Barge Arrangment & Details - Sheet 3 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12053-1
MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12053-2
MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12053-3
MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12053-4
MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFC 12 20-Jul-15 01-Aug-15
MM1-10150 TR/MTO for Primary & Secondary Steel 1 07-Apr-15 07-Apr-15
MM1-10170 TR/MTO for Tertiary Steel 1 09-Jun-15 09-Jun-15
MM1-10190 TR/MTO for Structural Miscellaneous 1 28-Jul-15 28-Jul-15
MM1-10210 TR/MTO for Gratings (including Hilti clip and cartridge) 1 09-Aug-15 09-Aug-15
MM1-1000 TR/MTO for SF and Grillage Material 1 10-Oct-15 10-Oct-15
MM1-1100 Prepare / Submit/ Approve Structural Shop Drawings 185 11-Aug-15 21-Mar-16
0.D.26.0000.MM1.B.L Piping 312 14-Mar-15 16-Mar-16
0.D.26.0000.MM1.B.L.92 PTSC 312 14-Mar-15 16-Mar-16
MM1-1305-PT-00-L-CA-00001
MM1 & MM2 - Stress Analysis Report 50 01-Jun-15 28-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 14 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-L-CA-00001-1
MM1 & MM2 - Stress Analysis Report-IDC 20 01-Jun-15* 23-Jun-15
MM1-1305-PT-00-L-CA-00001-2
MM1 & MM2 - Stress Analysis Report-IFR 6 24-Jun-15 30-Jun-15
MM1-1305-PT-00-L-CA-00001-3
MM1 & MM2 - Stress Analysis Report-IFD 12 01-Jul-15 14-Jul-15
MM1-1305-PT-00-L-CA-00001-4
MM1 & MM2 - Stress Analysis Report-IFC 12 15-Jul-15 28-Jul-15
MM1-1305-PT-00-L-LA-00001
MM1 & MM2 - Special Piping Item List 47 12-May-15 04-Jul-15
MM1-1305-PT-00-L-LA-00001-1
MM1 & MM2 - Special Piping Item List-IDC 7 12-May-15* 19-May-15
MM1-1305-PT-00-L-LA-00001-2
MM1 & MM2 - Special Piping Item List-IFR 4 20-May-15 23-May-15
MM1-1305-PT-00-L-LA-00001-3
MM1 & MM2 - Special Piping Item List-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-00-L-LA-00001-4
MM1 & MM2 - Special Piping Item List-IFC 24 08-Jun-15 04-Jul-15
MM1-1305-PT-00-L-LA-00002
MM1 & MM2 - TIE-IN Schedule 56 26-May-15 29-Jul-15
MM1-1305-PT-00-L-LA-00002-1
MM1 & MM2 - TIE-IN Schedule-IDC 25 26-May-15* 23-Jun-15
MM1-1305-PT-00-L-LA-00002-2
MM1 & MM2 - TIE-IN Schedule-IFR 7 24-Jun-15 01-Jul-15
MM1-1305-PT-00-L-LA-00002-3
MM1 & MM2 - TIE-IN Schedule-IFD 12 02-Jul-15 15-Jul-15
MM1-1305-PT-00-L-LA-00002-4
MM1 & MM2 - TIE-IN Schedule-IFC 12 16-Jul-15 29-Jul-15
MM1-1305-PT-00-L-LA-00003
MM1 & MM2 - Manual valve list 49 17-Apr-15 16-Jun-15
MM1-1305-PT-00-L-LA-00003-1
MM1 & MM2 - Manual valve list-IDC 7 17-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-LA-00003-2
MM1 & MM2 - Manual valve list-IFR 2 25-Apr-15 27-Apr-15
MM1-1305-PT-00-L-LA-00003-3
MM1 & MM2 - Manual valve list-IFD 10 29-Apr-15 12-May-15
MM1-1305-PT-00-L-LA-00003-4
MM1 & MM2 - Manual valve list-IFC 30 13-May-15 16-Jun-15
MM1-1305-PT-00-L-SA-00001
MM1 & MM2 - Addional piping class 46 14-Mar-15 09-May-15
MM1-1305-PT-00-L-SA-00001-1
MM1 & MM2 - Addional piping class -IDC 1 14-Mar-15* 14-Mar-15
MM1-1305-PT-00-L-SA-00001-2
MM1 & MM2 - Addional piping class -IFR 24 16-Mar-15 11-Apr-15
MM1-1305-PT-00-L-SA-00001-3
MM1 & MM2 - Addional piping class -IFD 12 13-Apr-15 25-Apr-15
MM1-1305-PT-00-L-SA-00001-4
MM1 & MM2 - Addional piping class -IFC 9 27-Apr-15 09-May-15
MM1-1305-PT-00-L-SA-00002
MM1 & MM2 - Pipe support standard 46 06-Apr-15 01-Jun-15
MM1-1305-PT-00-L-SA-00002-1
MM1 & MM2 - Pipe support standard -IDC 1 06-Apr-15* 06-Apr-15
MM1-1305-PT-00-L-SA-00002-2
MM1 & MM2 - Pipe support standard -IFR 21 07-Apr-15 04-May-15
MM1-1305-PT-00-L-SA-00002-3
MM1 & MM2 - Pipe support standard -IFD 12 05-May-15 18-May-15
MM1-1305-PT-00-L-SA-00002-4
MM1 & MM2 - Pipe support standard -IFC 12 19-May-15 01-Jun-15
MM1-1305-PT-00-L-DS-00001
MM1 & MM2 - Ball valve Data sheets 34 03-Apr-15 15-May-15
MM1-1305-PT-00-L-DS-00001-1
MM1 & MM2 - Ball valve Data sheets-IDC 1 03-Apr-15* 03-Apr-15
MM1-1305-PT-00-L-DS-00001-2
MM1 & MM2 - Ball valve Data sheets-IFR 12 04-Apr-15 17-Apr-15
MM1-1305-PT-00-L-DS-00001-3
MM1 & MM2 - Ball valve Data sheets-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-00-L-DS-00001-4
MM1 & MM2 - Ball valve Data sheets-IFC 12 02-May-15 15-May-15
MM1-1305-PT-00-L-DS-00002
MM1 & MM2 - Globe Valve Data sheets 33 06-Apr-15 16-May-15
MM1-1305-PT-00-L-DS-00002-1
MM1 & MM2 - Globe Valve Data sheets-IDC 0 06-Apr-15* 06-Apr-15
MM1-1305-PT-00-L-DS-00002-2
MM1 & MM2 - Globe Valve Data sheets-IFR 12 06-Apr-15 18-Apr-15
MM1-1305-PT-00-L-DS-00002-3
MM1 & MM2 - Globe Valve Data sheets-IFD 9 20-Apr-15 02-May-15
MM1-1305-PT-00-L-DS-00002-4
MM1 & MM2 - Globe Valve Data sheets-IFC 12 04-May-15 16-May-15
MM1-1305-PT-00-L-DS-00003
MM1 & MM2 - Check Data sheets 34 07-Apr-15 19-May-15
MM1-1305-PT-00-L-DS-00003-1
MM1 & MM2 - Check Data sheets-IDC 1 07-Apr-15* 07-Apr-15
MM1-1305-PT-00-L-DS-00003-2
MM1 & MM2 - Check Data sheets-IFR 12 08-Apr-15 21-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 15 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-L-DS-00003-3
MM1 & MM2 - Check Data sheets-IFD 9 22-Apr-15 05-May-15
MM1-1305-PT-00-L-DS-00003-4
MM1 & MM2 - Check Data sheets-IFC 12 06-May-15 19-May-15
MM1-1305-PT-00-L-DS-00004
MM1 & MM2 - DBB valve sheets 58 10-Apr-15 19-Jun-15
MM1-1305-PT-00-L-DS-00004-1
MM1 & MM2 - DBB valve sheets-IDC 1 10-Apr-15* 10-Apr-15
MM1-1305-PT-00-L-DS-00004-2
MM1 & MM2 - DBB valve sheets-IFR 12 11-Apr-15 24-Apr-15
MM1-1305-PT-00-L-DS-00004-3
MM1 & MM2 - DBB valve sheets-IFD 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00004-4
MM1 & MM2 - DBB valve sheets-IFC 36 09-May-15 19-Jun-15
MM1-1305-PT-00-L-DS-00005
MM1 & MM2 - SP Item Data Sheet -Valve Interlock 61 12-May-15 21-Jul-15
MM1-1305-PT-00-L-DS-00005-1
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IDC 1 12-May-15* 12-May-15
MM1-1305-PT-00-L-DS-00005-2
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFR 12 13-May-15 26-May-15
MM1-1305-PT-00-L-DS-00005-3
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFD 12 27-May-15 09-Jun-15
MM1-1305-PT-00-L-DS-00005-4
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFC 36 10-Jun-15 21-Jul-15
MM1-1305-PT-00-L-DS-00006
MM1 & MM2 - SP Item Data Sheet - Barred Tee 52 10-Apr-15 12-Jun-15
MM1-1305-PT-00-L-DS-00006-1
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IDC 1 10-Apr-15* 10-Apr-15
MM1-1305-PT-00-L-DS-00006-2
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFR 12 11-Apr-15 24-Apr-15
MM1-1305-PT-00-L-DS-00006-3
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFD 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00006-4
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFC 30 09-May-15 12-Jun-15
MM1-1305-PT-00-L-DS-00007
MM1 & MM2 - SP Item Data Sheet - Bends 70 24-Apr-15 17-Jul-15
MM1-1305-PT-00-L-DS-00007-1
MM1 & MM2 - SP Item Data Sheet - Bends-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00007-2
MM1 & MM2 - SP Item Data Sheet - Bends-IFR 15 25-Apr-15 15-May-15
MM1-1305-PT-00-L-DS-00007-3
MM1 & MM2 - SP Item Data Sheet - Bends-IFD 12 16-May-15 29-May-15
MM1-1305-PT-00-L-DS-00007-4
MM1 & MM2 - SP Item Data Sheet - Bends-IFC 42 30-May-15 17-Jul-15
MM1-1305-PT-00-L-DS-00008
MM1 & MM2 - SP Item Data Sheets for Sample connection 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00008-1
MM1 & MM2 - SP Item Data Sheets for Sample connection -IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00008-2
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00008-3
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00008-4
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00009
MM1 & MM2 - SP Item Data Sheet - Chemcial injection 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00009-1
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00009-2
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00009-3
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00009-4
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00010
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00010-1
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00010-2
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00010-3
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00010-4
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00011
MM1 & MM2 - SP Item Data Sheet - Sand probe 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00011-1
MM1 & MM2 - SP Item Data Sheet - Sand probe-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00011-2
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00011-3
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00011-4
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFC 36 23-May-15 03-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 16 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-L-DS-00012
MM1 & MM2 - SP Item Data Sheet - Quick coupling 70 05-Jun-15 25-Aug-15
MM1-1305-PT-00-L-DS-00012-1
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IDC 1 05-Jun-15* 05-Jun-15
MM1-1305-PT-00-L-DS-00012-2
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFR 12 06-Jun-15 19-Jun-15
MM1-1305-PT-00-L-DS-00012-3
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFD 12 20-Jun-15 03-Jul-15
MM1-1305-PT-00-L-DS-00012-4
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFC 45 04-Jul-15 25-Aug-15
MM1-1305-PT-00-L-DS-00013
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR 70 05-Jun-15 25-Aug-15
MM1-1305-PT-00-L-DS-00013-1
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IDC 1 05-Jun-15* 05-Jun-15
MM1-1305-PT-00-L-DS-00013-2
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFR 12 06-Jun-15 19-Jun-15
MM1-1305-PT-00-L-DS-00013-3
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFD 12 20-Jun-15 03-Jul-15
MM1-1305-PT-00-L-DS-00013-4
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFC 45 04-Jul-15 25-Aug-15
MM1-1305-PT-00-L-XE-10001
MM1 - Equipment Layout 40 24-Apr-15 12-Jun-15
MM1-1305-PT-00-L-XE-10001-1
MM1 - Equipment Layout-IDC 10 24-Apr-15* 08-May-15
MM1-1305-PT-00-L-XE-10001-2
MM1 - Equipment Layout-IFR 6 09-May-15 15-May-15
MM1-1305-PT-00-L-XE-10001-3
MM1 - Equipment Layout-IFD 12 16-May-15 29-May-15
MM1-1305-PT-00-L-XE-10001-4
MM1 - Equipment Layout-IFC 12 30-May-15 12-Jun-15
MM1-1305-PT-00-L-XE-10002
MM1 - Piping layout 43 30-May-15 18-Jul-15
MM1-1305-PT-00-L-XE-10002-1
MM1 - Piping layout-IDC 13 30-May-15* 13-Jun-15
MM1-1305-PT-00-L-XE-10002-2
MM1 - Piping layout-IFR 6 15-Jun-15 20-Jun-15
MM1-1305-PT-00-L-XE-10002-3
MM1 - Piping layout-IFD 12 22-Jun-15 04-Jul-15
MM1-1305-PT-00-L-XE-10002-4
MM1 - Piping layout-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-00-L-XF-10003
MM1 - Pipe support location plan 43 20-Jun-15 08-Aug-15
MM1-1305-PT-00-L-XF-10003-1
MM1 - Pipe support location plan-IDC 13 20-Jun-15* 04-Jul-15
MM1-1305-PT-00-L-XF-10003-2
MM1 - Pipe support location plan-IFR 6 06-Jul-15 11-Jul-15
MM1-1305-PT-00-L-XF-10003-3
MM1 - Pipe support location plan-IFD 0 13-Jul-15 13-Jul-15
MM1-1305-PT-00-L-XF-10003-4
MM1 - Pipe support location plan-IFC 24 13-Jul-15 08-Aug-15
MM1-1305-PT-00-L-XN-10001
MM1 - Isometric drawings (n Sheets) 59 16-May-15 23-Jul-15
MM1-1305-PT-00-L-XN-10001-1
MM1 - Isometric drawings (n Sheets)-IDC 13 16-May-15* 30-May-15
MM1-1305-PT-00-L-XN-10001-2
MM1 - Isometric drawings (n Sheets)-IFR 12 01-Jun-15 13-Jun-15
MM1-1305-PT-00-L-XN-10001-3
MM1 - Isometric drawings (n Sheets)-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-00-L-XN-10001-4
MM1 - Isometric drawings (n Sheets)-IFC 34 15-Jun-15 23-Jul-15
MM1-1305-PT-00-L-XO-10001
MM1 - Pipe support detail drawings 59 16-May-15 23-Jul-15
MM1-1305-PT-00-L-XO-10001-1
MM1 - Pipe support detail drawings-IDC 13 16-May-15* 30-May-15
MM1-1305-PT-00-L-XO-10001-2
MM1 - Pipe support detail drawings-IFR 12 01-Jun-15 13-Jun-15
MM1-1305-PT-00-L-XO-10001-3
MM1 - Pipe support detail drawings-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-00-L-XO-10001-4
MM1 - Pipe support detail drawings-IFC 34 15-Jun-15 23-Jul-15
MM1-1305-PT-00-L-LA-00004
MM1 & MM2 - Material take-off for Manual Valves 45 23-Apr-15 17-Jun-15
MM1-1305-PT-00-L-LA-00004-1
MM1 & MM2 - Material take-off for Manual Valves-IDC 1 23-Apr-15* 23-Apr-15
MM1-1305-PT-00-L-LA-00004-2
MM1 & MM2 - Material take-off for Manual Valves-IFR 4 24-Apr-15 29-Apr-15
MM1-1305-PT-00-L-LA-00004-3
MM1 & MM2 - Material take-off for Manual Valves-IFD 0 02-May-15 02-May-15
MM1-1305-PT-00-L-LA-00004-4
MM1 & MM2 - Material take-off for Manual Valves-IFC 40 02-May-15 17-Jun-15
MM1-1305-PT-00-L-LA-00005
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket 54 26-Jun-15 27-Aug-15
MM1-1305-PT-00-L-LA-00005-1
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IDC 1 26-Jun-15* 26-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 17 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-L-LA-00005-2
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFR 5 27-Jun-15 02-Jul-15
MM1-1305-PT-00-L-LA-00005-3
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFD 0 03-Jul-15 03-Jul-15
MM1-1305-PT-00-L-LA-00005-4
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFC 48 03-Jul-15 27-Aug-15
MM1-1305-PT-00-L-LA-00006
MM1 & MM2 - Material take-off for Pipe Support (Raw Material) 53 30-May-15 30-Jul-15
MM1-1305-PT-00-L-LA-00006-1
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IDC 1 30-May-15* 30-May-15
MM1-1305-PT-00-L-LA-00006-2
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFR 6 01-Jun-15 06-Jun-15
MM1-1305-PT-00-L-LA-00006-3
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-L-LA-00006-4
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFC 46 08-Jun-15 30-Jul-15
MM1-1305-PT-00-L-LA-00007
MM1 & MM2 - Material take-off - Hub Connector 70 11-Jun-15 31-Aug-15
MM1-1305-PT-00-L-LA-00007-1
MM1 & MM2 - Material take-off - Hub Connector-IDC 1 11-Jun-15* 11-Jun-15
MM1-1305-PT-00-L-LA-00007-2
MM1 & MM2 - Material take-off - Hub Connector-IFR 12 12-Jun-15 25-Jun-15
MM1-1305-PT-00-L-LA-00007-3
MM1 & MM2 - Material take-off - Hub Connector-IFD 0 26-Jun-15 26-Jun-15
MM1-1305-PT-00-L-LA-00007-4
MM1 & MM2 - Material take-off - Hub Connector-IFC 57 26-Jun-15 31-Aug-15
MM1-10250 TR/MTO for Piping Bulk 1 10-Apr-15 10-Apr-15
MM1-10270 TR/MTO for Manual valves 1 29-Apr-15 29-Apr-15
MM1-10290 TR/MTO for Barred Tee 1 29-Apr-15 29-Apr-15
MM1-10310 TR/MTO for Cuni fittings 1 08-May-15 08-May-15
MM1-10330 TR/MTO for Corrosion, sand probe, sample connection, chemical connection 1 18-May-15 18-May-15
MM1-10350 TR/MTO for 3D Bend (free bare pipe to bending contractor) 1 30-May-15 30-May-15
MM1-10370 TR/MTO for Pipe Supports 1 06-Jun-15 06-Jun-15
MM1-10410 TR/MTO for Piping insulation 1 04-Jul-15 04-Jul-15
MM1-10430 TR/MTO for Bolt nut, gasket and other 1 06-Jul-15 06-Jul-15
MM1-10390 TR/MTO for Quick Coupling 1 09-Jul-15 09-Jul-15
MM1-10450 TR/MTO for Valve Inter-locks 1 16-Sep-15 16-Sep-15
MM1-10470 Prepare / Submit/ Approve Piping Shop Drawings 151 16-Sep-15 16-Mar-16
0.D.26.0000.MM1.B.1 E&I 313 13-Mar-15 16-Mar-16
0.D.26.0000.MM1.B.1.92 PTSC 313 13-Mar-15 16-Mar-16
MM1-1305-PT-82-E-CA-00001
MM1 & MM2 - Electrical Load List 57 04-May-15 08-Jul-15
MM1-1305-PT-82-E-CA-00001-1
MM1 & MM2 - Electrical Load List-IDC 10 04-May-15* 14-May-15
MM1-1305-PT-82-E-CA-00001-2
MM1 & MM2 - Electrical Load List-IFR 13 15-May-15 29-May-15
MM1-1305-PT-82-E-CA-00001-3
MM1 & MM2 - Electrical Load List-IFD 13 30-May-15 13-Jun-15
MM1-1305-PT-82-E-CA-00001-4
MM1 & MM2 - Electrical Load List-IFC 21 15-Jun-15 08-Jul-15
MM1-1305-PT-82-E-CA-00002
MM1 & MM2 - Electrical Lighting Calculation 32 20-Mar-15 25-Apr-15
MM1-1305-PT-82-E-CA-00002-1
MM1 & MM2 - Electrical Lighting Calculation-IDC 9 20-Mar-15* 30-Mar-15
MM1-1305-PT-82-E-CA-00002-2
MM1 & MM2 - Electrical Lighting Calculation-IFR 6 31-Mar-15 06-Apr-15
MM1-1305-PT-82-E-CA-00002-3
MM1 & MM2 - Electrical Lighting Calculation-IFD 13 07-Apr-15 21-Apr-15
MM1-1305-PT-82-E-CA-00002-4
MM1 & MM2 - Electrical Lighting Calculation-IFC 4 22-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XX-00001
MM1 & MM2 - Electrical General Drawing and Document Index 36 23-Mar-15 06-May-15
MM1-1305-PT-82-E-XX-00001-1
MM1 & MM2 - Electrical General Drawing and Document Index-IDC 9 23-Mar-15* 01-Apr-15
MM1-1305-PT-82-E-XX-00001-2
MM1 & MM2 - Electrical General Drawing and Document Index-IFR 13 02-Apr-15 16-Apr-15
MM1-1305-PT-82-E-XX-00001-3
MM1 & MM2 - Electrical General Drawing and Document Index-IFD 0 17-Apr-15 17-Apr-15
MM1-1305-PT-82-E-XX-00001-4
MM1 & MM2 - Electrical General Drawing and Document Index-IFC 14 17-Apr-15 06-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 18 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-82-E-XX-00002
MM1 & MM2 - Electrical Typical Installation Details 48 13-Mar-15 11-May-15
MM1-1305-PT-82-E-XX-00002-1
MM1 & MM2 - Electrical Typical Installation Details-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XX-00002-2
MM1 & MM2 - Electrical Typical Installation Details-IFR 13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XX-00002-3
MM1 & MM2 - Electrical Typical Installation Details-IFD 13 08-Apr-15 22-Apr-15
MM1-1305-PT-82-E-XX-00002-4
MM1 & MM2 - Electrical Typical Installation Details-IFC 13 23-Apr-15 11-May-15
MM1-1305-PT-82-E-DS-00001
MM1 & MM2 - Electrical Datasheet 30 02-Apr-15 09-May-15
MM1-1305-PT-82-E-DS-00001-1
MM1 & MM2 - Electrical Datasheet-IDC 9 02-Apr-15* 11-Apr-15
MM1-1305-PT-82-E-DS-00001-2
MM1 & MM2 - Electrical Datasheet-IFR 6 13-Apr-15 18-Apr-15
MM1-1305-PT-82-E-DS-00001-3
MM1 & MM2 - Electrical Datasheet-IFD 10 20-Apr-15 04-May-15
MM1-1305-PT-82-E-DS-00001-4
MM1 & MM2 - Electrical Datasheet-IFC 5 05-May-15 09-May-15
MM1-1305-PT-82-E-XX-10001
MM1 - Electrical Drawing Index 37 23-Mar-15 07-May-15
MM1-1305-PT-82-E-XX-10001-1
MM1 - Electrical Drawing Index -IDC 10 23-Mar-15* 02-Apr-15
MM1-1305-PT-82-E-XX-10001-2
MM1 - Electrical Drawing Index -IFR 13 03-Apr-15 17-Apr-15
MM1-1305-PT-82-E-XX-10001-3
MM1 - Electrical Drawing Index -IFD 0 18-Apr-15 18-Apr-15
MM1-1305-PT-82-E-XX-10001-4
MM1 - Electrical Drawing Index -IFC 14 18-Apr-15 07-May-15
MM1-1305-PT-82-E-XX-10002
MM1 - Electrical Cable Ladder Support 39 08-May-15 22-Jun-15
MM1-1305-PT-82-E-XX-10002-1
MM1 - Electrical Cable Ladder Support-IDC 9 08-May-15* 18-May-15
MM1-1305-PT-82-E-XX-10002-2
MM1 - Electrical Cable Ladder Support-IFR 13 19-May-15 02-Jun-15
MM1-1305-PT-82-E-XX-10002-3
MM1 - Electrical Cable Ladder Support-IFD 0 03-Jun-15 03-Jun-15
MM1-1305-PT-82-E-XX-10002-4
MM1 - Electrical Cable Ladder Support-IFC 17 03-Jun-15 22-Jun-15
MM1-1305-PT-82-E-XJ-10001
MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001 39 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10001-1
MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10001-2
MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFR 13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10001-3
MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFD 0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10001-4
MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFC 17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10002
MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002
39 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10002-1
MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IDC
9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10002-2
MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFR
13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10002-3
MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFD
0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10002-4
MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFC
17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10003
MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003
39 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10003-1
MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IDC
9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10003-2
MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFR
13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10003-3
MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFD
0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10003-4
MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFC
17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10004
MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel39
82EL004
13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10004-1
MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IDC
9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10004-2
MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel13
82EL004-IFR
24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10004-3
MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFD
0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10004-4
MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel17
82EL004-IFC
08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10005
MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005
39 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10005-1
MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IDC
9 13-Mar-15* 23-Mar-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 19 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-82-E-XJ-10005-2
MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFR
13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10005-3
MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFD
0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10005-4
MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFC
17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-TA-10001
MM1 - Electrical Cable Schedule 51 10-Apr-15 11-Jun-15
MM1-1305-PT-82-E-TA-10001-1
MM1 - Electrical Cable Schedule -IDC 13 10-Apr-15* 24-Apr-15
MM1-1305-PT-82-E-TA-10001-2
MM1 - Electrical Cable Schedule -IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-82-E-TA-10001-3
MM1 - Electrical Cable Schedule -IFD 13 09-May-15 23-May-15
MM1-1305-PT-82-E-TA-10001-4
MM1 - Electrical Cable Schedule -IFC 16 25-May-15 11-Jun-15
MM1-1305-PT-82-E-XT-10001
MM1 - Electrical Heat Tracing Interconnection Diagram 39 21-May-15 04-Jul-15
MM1-1305-PT-82-E-XT-10001-1
MM1 - Electrical Heat Tracing Interconnection Diagram-IDC 9 21-May-15* 30-May-15
MM1-1305-PT-82-E-XT-10001-2
MM1 - Electrical Heat Tracing Interconnection Diagram-IFR 13 01-Jun-15 15-Jun-15
MM1-1305-PT-82-E-XT-10001-3
MM1 - Electrical Heat Tracing Interconnection Diagram-IFD 0 16-Jun-15 16-Jun-15
MM1-1305-PT-82-E-XT-10001-4
MM1 - Electrical Heat Tracing Interconnection Diagram-IFC 17 16-Jun-15 04-Jul-15
MM1-1305-PT-82-E-XI-10001
MM1 - Electrical Heat Tracing Block Diagram 58 25-Apr-15 04-Jul-15
MM1-1305-PT-82-E-XI-10001-1
MM1 - Electrical Heat Tracing Block Diagram-IDC 6 25-Apr-15* 05-May-15
MM1-1305-PT-82-E-XI-10001-2
MM1 - Electrical Heat Tracing Block Diagram-IFR 13 06-May-15 20-May-15
MM1-1305-PT-82-E-XI-10001-3
MM1 - Electrical Heat Tracing Block Diagram-IFD 0 21-May-15 21-May-15
MM1-1305-PT-82-E-XI-10001-4
MM1 - Electrical Heat Tracing Block Diagram-IFC 39 21-May-15 04-Jul-15
MM1-1305-PT-82-E-XI-10002
MM1 - Electrical Lighting Interconnection Diagram 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XI-10002-1
MM1 - Electrical Lighting Interconnection Diagram-IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XI-10002-2
MM1 - Electrical Lighting Interconnection Diagram-IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XI-10002-3
MM1 - Electrical Lighting Interconnection Diagram-IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XI-10002-4
MM1 - Electrical Lighting Interconnection Diagram-IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10001
MM1 - Electrical Lighting And Small Power Layout - Main Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10001-1
MM1 - Electrical Lighting And Small Power Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10001-2
MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10001-3
MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10001-4
MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10002
MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10002-1
MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10002-2
MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10002-3
MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10002-4
MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10003
MM1 - Electrical Lighting And Small Power Layout - Upper Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10003-1
MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10003-2
MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10003-3
MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10003-4
MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-11001
MM1 - Electrical Earthing Layout - Main Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11001-1
MM1 - Electrical Earthing Layout - Main Deck -IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11001-2
MM1 - Electrical Earthing Layout - Main Deck -IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11001-3
MM1 - Electrical Earthing Layout - Main Deck -IFD 0 27-Apr-15 27-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 20 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-82-E-XE-11001-4
MM1 - Electrical Earthing Layout - Main Deck -IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11002
MM1 - Electrical Earthing Layout - Mezzanine Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11002-1
MM1 - Electrical Earthing Layout - Mezzanine Deck-IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11002-2
MM1 - Electrical Earthing Layout - Mezzanine Deck-IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11002-3
MM1 - Electrical Earthing Layout - Mezzanine Deck-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XE-11002-4
MM1 - Electrical Earthing Layout - Mezzanine Deck-IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11003
MM1 - Electrical Earthing Layout - Upper Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11003-1
MM1 - Electrical Earthing Layout - Upper Deck -IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11003-2
MM1 - Electrical Earthing Layout - Upper Deck -IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11003-3
MM1 - Electrical Earthing Layout - Upper Deck -IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XE-11003-4
MM1 - Electrical Earthing Layout - Upper Deck -IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-12001
MM1 - Electrical Cable Ladder And Support Layout - Main Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12001-1
MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12001-2
MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12001-3
MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12001-4
MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-12002
MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12002-1
MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12002-2
MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12002-3
MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12002-4
MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-12003
MM1 - Electrical Cable Ladder And Support Layout - Upper Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12003-1
MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12003-2
MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12003-3
MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12003-4
MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-13001
MM1 - Electrical Cable Routing Layout - Main Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13001-1
MM1 - Electrical Cable Routing Layout - Main Deck-IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13001-2
MM1 - Electrical Cable Routing Layout - Main Deck-IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13001-3
MM1 - Electrical Cable Routing Layout - Main Deck-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13001-4
MM1 - Electrical Cable Routing Layout - Main Deck-IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-XE-13002
MM1 - Electrical Cable Routing Layout - Mezzanine Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13002-1
MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13002-2
MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13002-3
MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13002-4
MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-XE-13003
MM1 - Electrical Cable Routing Layout - Upper Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13003-1
MM1 - Electrical Cable Routing Layout - Upper Deck-IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13003-2
MM1 - Electrical Cable Routing Layout - Upper Deck-IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13003-3
MM1 - Electrical Cable Routing Layout - Upper Deck-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13003-4
MM1 - Electrical Cable Routing Layout - Upper Deck-IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-LA-00001
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures 80 05-May-15 05-Aug-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 21 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-82-E-LA-00001-1
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IDC 7 05-May-15* 12-May-15
MM1-1305-PT-82-E-LA-00001-2
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFR 24 13-May-15 09-Jun-15
MM1-1305-PT-82-E-LA-00001-3
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFD 0 10-Jun-15 10-Jun-15
MM1-1305-PT-82-E-LA-00001-4
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFC 49 10-Jun-15 05-Aug-15
MM1-1305-PT-82-E-LA-00002
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories
77 11-May-15 07-Aug-15
MM1-1305-PT-82-E-LA-00002-1
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IDC
7 11-May-15* 18-May-15
MM1-1305-PT-82-E-LA-00002-2
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFR
23 19-May-15 13-Jun-15
MM1-1305-PT-82-E-LA-00002-3
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFD
0 15-Jun-15 15-Jun-15
MM1-1305-PT-82-E-LA-00002-4
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFC
47 15-Jun-15 07-Aug-15
MM1-1305-PT-82-E-LA-00003
MM1 & MM2 - Electrical Material Take-Off - Cables 62 18-May-15 28-Jul-15
MM1-1305-PT-82-E-LA-00003-1
MM1 & MM2 - Electrical Material Take-Off - Cables-IDC 7 18-May-15* 25-May-15
MM1-1305-PT-82-E-LA-00003-2
MM1 & MM2 - Electrical Material Take-Off - Cables-IFR 8 26-May-15 03-Jun-15
MM1-1305-PT-82-E-LA-00003-3
MM1 & MM2 - Electrical Material Take-Off - Cables-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-LA-00003-4
MM1 & MM2 - Electrical Material Take-Off - Cables-IFC 47 04-Jun-15 28-Jul-15
MM1-1305-PT-82-E-LA-00004
MM1 & MM2 - Electrical Material Take-Off - Cable Glands 77 21-May-15 18-Aug-15
MM1-1305-PT-82-E-LA-00004-1
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IDC 7 21-May-15* 28-May-15
MM1-1305-PT-82-E-LA-00004-2
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFR 22 29-May-15 23-Jun-15
MM1-1305-PT-82-E-LA-00004-3
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFD 0 24-Jun-15 24-Jun-15
MM1-1305-PT-82-E-LA-00004-4
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFC 48 24-Jun-15 18-Aug-15
MM1-1305-PT-82-E-LA-00005
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes 83 02-May-15 06-Aug-15
MM1-1305-PT-82-E-LA-00005-1
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IDC 6 02-May-15* 08-May-15
MM1-1305-PT-82-E-LA-00005-2
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFR 31 09-May-15 13-Jun-15
MM1-1305-PT-82-E-LA-00005-3
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-82-E-LA-00005-4
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFC 46 15-Jun-15 06-Aug-15
MM1-1305-PT-82-E-LA-00006
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials 94 21-May-15 08-Sep-15
MM1-1305-PT-82-E-LA-00006-1
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IDC 7 21-May-15* 28-May-15
MM1-1305-PT-82-E-LA-00006-2
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFR 38 29-May-15 11-Jul-15
MM1-1305-PT-82-E-LA-00006-3
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFD 0 13-Jul-15 13-Jul-15
MM1-1305-PT-82-E-LA-00006-4
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFC 49 13-Jul-15 08-Sep-15
MM1-1305-PT-82-E-LA-00007
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials 52 15-May-15 14-Jul-15
MM1-1305-PT-82-E-LA-00007-1
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IDC 7 15-May-15* 22-May-15
MM1-1305-PT-82-E-LA-00007-2
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFR 10 23-May-15 03-Jun-15
MM1-1305-PT-82-E-LA-00007-3
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-LA-00007-4
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFC 35 04-Jun-15 14-Jul-15
MM1-1305-PT-00-I-LA-00009
MM1 & MM2 - Ex Equipment Register 68 11-Jun-15 28-Aug-15
MM1-1305-PT-00-I-LA-00009-1
MM1 & MM2 - Ex Equipment Register-IDC 27 11-Jun-15* 11-Jul-15
MM1-1305-PT-00-I-LA-00009-2
MM1 & MM2 - Ex Equipment Register-IFR 12 13-Jul-15 25-Jul-15
MM1-1305-PT-00-I-LA-00009-3
MM1 & MM2 - Ex Equipment Register-IFD 12 27-Jul-15 08-Aug-15
MM1-1305-PT-00-I-LA-00009-4
MM1 & MM2 - Ex Equipment Register-IFC 17 10-Aug-15 28-Aug-15
MM1-1305-PT-00-I-SA-00001
MM1 & MM2 - Instrument Control and Shutdown Philosophy 64 10-Jun-15 22-Aug-15
MM1-1305-PT-00-I-SA-00001-1
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IDC 27 10-Jun-15* 10-Jul-15
MM1-1305-PT-00-I-SA-00001-2
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFR 8 11-Jul-15 20-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 22 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-I-SA-00001-3
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFD 13 21-Jul-15 04-Aug-15
MM1-1305-PT-00-I-SA-00001-4
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFC 16 05-Aug-15 22-Aug-15
MM1-1305-PT-00-I-XR-00001
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix 68 15-Jun-15 01-Sep-15
MM1-1305-PT-00-I-XR-00001-1
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IDC 27 15-Jun-15* 15-Jul-15
MM1-1305-PT-00-I-XR-00001-2
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFR 13 16-Jul-15 30-Jul-15
MM1-1305-PT-00-I-XR-00001-3
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFD 13 31-Jul-15 14-Aug-15
MM1-1305-PT-00-I-XR-00001-4
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFC 15 15-Aug-15 01-Sep-15
MM1-1305-PT-00-I-XT-00001
M1 & MM2 - Instrument Cable Block Diagram 44 13-Apr-15 05-Jun-15
MM1-1305-PT-00-I-XT-00001-1
M1 & MM2 - Instrument Cable Block Diagram-IDC 20 13-Apr-15* 08-May-15
MM1-1305-PT-00-I-XT-00001-2
M1 & MM2 - Instrument Cable Block Diagram-IFR 6 09-May-15 15-May-15
MM1-1305-PT-00-I-XT-00001-3
M1 & MM2 - Instrument Cable Block Diagram-IFD 0 16-May-15 16-May-15
MM1-1305-PT-00-I-XT-00001-4
M1 & MM2 - Instrument Cable Block Diagram-IFC 18 16-May-15 05-Jun-15
MM1-1305-PT-00-I-XT-00002
MM1 - Instrument Interconnection Wiring diagram 49 13-Apr-15 11-Jun-15
MM1-1305-PT-00-I-XT-00002-1
MM1 - Instrument Interconnection Wiring diagram -IDC 20 13-Apr-15* 08-May-15
MM1-1305-PT-00-I-XT-00002-2
MM1 - Instrument Interconnection Wiring diagram -IFR 12 09-May-15 22-May-15
MM1-1305-PT-00-I-XT-00002-3
MM1 - Instrument Interconnection Wiring diagram -IFD 0 23-May-15 23-May-15
MM1-1305-PT-00-I-XT-00002-4
MM1 - Instrument Interconnection Wiring diagram -IFC 17 23-May-15 11-Jun-15
MM1-1305-PT-00-I-XQ-00001
MM1- Instrument Hookup Drawing 47 06-Apr-15 02-Jun-15
MM1-1305-PT-00-I-XQ-00001-1
MM1- Instrument Hookup Drawing-IDC 14 06-Apr-15* 21-Apr-15
MM1-1305-PT-00-I-XQ-00001-2
MM1- Instrument Hookup Drawing-IFR 15 22-Apr-15 12-May-15
MM1-1305-PT-00-I-XQ-00001-3
MM1- Instrument Hookup Drawing-IFD 0 13-May-15 13-May-15
MM1-1305-PT-00-I-XQ-00001-4
MM1- Instrument Hookup Drawing-IFC 18 13-May-15 02-Jun-15
MM1-1305-PT-00-I-XX-00001
MM1- Instrument Support Details 41 04-May-15 19-Jun-15
MM1-1305-PT-00-I-XX-00001-1
MM1- Instrument Support Details-IDC 13 04-May-15* 18-May-15
MM1-1305-PT-00-I-XX-00001-2
MM1- Instrument Support Details-IFR 12 19-May-15 01-Jun-15
MM1-1305-PT-00-I-XX-00001-3
MM1- Instrument Support Details-IFD 0 02-Jun-15 02-Jun-15
MM1-1305-PT-00-I-XX-00001-4
MM1- Instrument Support Details-IFC 16 02-Jun-15 19-Jun-15
MM1-1305-PT-00-I-XX-00003
MM1 - Instrument Cable Tray Ladder Support Details 36 20-May-15 30-Jun-15
MM1-1305-PT-00-I-XX-00003-1
MM1 - Instrument Cable Tray Ladder Support Details-IDC 13 20-May-15* 03-Jun-15
MM1-1305-PT-00-I-XX-00003-2
MM1 - Instrument Cable Tray Ladder Support Details-IFR 6 04-Jun-15 10-Jun-15
MM1-1305-PT-00-I-XX-00003-3
MM1 - Instrument Cable Tray Ladder Support Details-IFD 0 11-Jun-15 11-Jun-15
MM1-1305-PT-00-I-XX-00003-4
MM1 - Instrument Cable Tray Ladder Support Details-IFC 17 11-Jun-15 30-Jun-15
MM1-1305-PT-00-I-XE-00001
MM1 - Instrument cable and cable tray/ ladder routing layout 59 04-May-15 10-Jul-15
MM1-1305-PT-00-I-XE-00001-1
MM1 - Instrument cable and cable tray/ ladder routing layout-IDC 12 04-May-15* 16-May-15
MM1-1305-PT-00-I-XE-00001-2
MM1 - Instrument cable and cable tray/ ladder routing layout-IFR 12 18-May-15 30-May-15
MM1-1305-PT-00-I-XE-00001-3
MM1 - Instrument cable and cable tray/ ladder routing layout-IFD 0 01-Jun-15 01-Jun-15
MM1-1305-PT-00-I-XE-00001-4
MM1 - Instrument cable and cable tray/ ladder routing layout-IFC 35 01-Jun-15 10-Jul-15
MM1-1305-PT-00-I-XE-00003
MM1 - Instrument tubing and tubing tray routing layout 53 02-May-15 02-Jul-15
MM1-1305-PT-00-I-XE-00003-1
MM1 - Instrument tubing and tubing tray routing layout-IDC 13 02-May-15* 16-May-15
MM1-1305-PT-00-I-XE-00003-2
MM1 - Instrument tubing and tubing tray routing layout-IFR 6 18-May-15 23-May-15
MM1-1305-PT-00-I-XE-00003-3
MM1 - Instrument tubing and tubing tray routing layout-IFD 0 25-May-15 25-May-15
MM1-1305-PT-00-I-XE-00003-4
MM1 - Instrument tubing and tubing tray routing layout-IFC 34 25-May-15 02-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 23 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-I-XE-00005
MM1- Instrument and JB location layout 43 20-Apr-15 11-Jun-15
MM1-1305-PT-00-I-XE-00005-1
MM1- Instrument and JB location layout-IDC 24 20-Apr-15* 20-May-15
MM1-1305-PT-00-I-XE-00005-2
MM1- Instrument and JB location layout-IFR 6 21-May-15 27-May-15
MM1-1305-PT-00-I-XE-00005-3
MM1- Instrument and JB location layout-IFD 0 28-May-15 28-May-15
MM1-1305-PT-00-I-XE-00005-4
MM1- Instrument and JB location layout-IFC 13 28-May-15 11-Jun-15
MM1-1305-PT-00-I-XE-00007
MM1- Fire & Gas layout 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-I-XE-00007-1
MM1- Fire & Gas layout-IDC 16 13-Mar-15* 31-Mar-15
MM1-1305-PT-00-I-XE-00007-2
MM1- Fire & Gas layout-IFR 49 01-Apr-15 30-May-15
MM1-1305-PT-00-I-XE-00007-3
MM1- Fire & Gas layout-IFD 0 01-Jun-15 01-Jun-15
MM1-1305-PT-00-I-XE-00007-4
MM1- Fire & Gas layout-IFC 17 01-Jun-15 19-Jun-15
MM1-1305-PT-00-I-XE-00009
MM1 - PAGA Equipment Location Layout 101 13-Mar-15 11-Jul-15
MM1-1305-PT-00-I-XE-00009-1
MM1 - PAGA Equipment Location Layout-IDC 35 13-Mar-15* 22-Apr-15
MM1-1305-PT-00-I-XE-00009-2
MM1 - PAGA Equipment Location Layout-IFR 48 23-Apr-15 20-Jun-15
MM1-1305-PT-00-I-XE-00009-3
MM1 - PAGA Equipment Location Layout-IFD 0 22-Jun-15 22-Jun-15
MM1-1305-PT-00-I-XE-00009-4
MM1 - PAGA Equipment Location Layout-IFC 18 22-Jun-15 11-Jul-15
MM1-1305-PT-00-I-LA-00001
MM1 - Instrument I/O LIST 51 20-Apr-15 20-Jun-15
MM1-1305-PT-00-I-LA-00001-1
MM1 - Instrument I/O LIST-IDC 16 20-Apr-15* 11-May-15
MM1-1305-PT-00-I-LA-00001-2
MM1 - Instrument I/O LIST-IFR 6 12-May-15 18-May-15
MM1-1305-PT-00-I-LA-00001-3
MM1 - Instrument I/O LIST-IFD 13 19-May-15 02-Jun-15
MM1-1305-PT-00-I-LA-00001-4
MM1 - Instrument I/O LIST-IFC 16 03-Jun-15 20-Jun-15
MM1-1305-PT-00-I-LA-00003
MM1 - Instrument INDEX 51 20-Apr-15 20-Jun-15
MM1-1305-PT-00-I-LA-00003-1
MM1 - Instrument INDEX-IDC 16 20-Apr-15* 11-May-15
MM1-1305-PT-00-I-LA-00003-2
MM1 - Instrument INDEX-IFR 6 12-May-15 18-May-15
MM1-1305-PT-00-I-LA-00003-3
MM1 - Instrument INDEX-IFD 13 19-May-15 02-Jun-15
MM1-1305-PT-00-I-LA-00003-4
MM1 - Instrument INDEX-IFC 16 03-Jun-15 20-Jun-15
MM1-1305-PT-00-I-LA-00005
MM1 - Instrument CABLE SCHEDULE 40 21-Apr-15 09-Jun-15
MM1-1305-PT-00-I-LA-00005-1
MM1 - Instrument CABLE SCHEDULE-IDC 10 21-Apr-15* 05-May-15
MM1-1305-PT-00-I-LA-00005-2
MM1 - Instrument CABLE SCHEDULE-IFR 6 06-May-15 12-May-15
MM1-1305-PT-00-I-LA-00005-3
MM1 - Instrument CABLE SCHEDULE-IFD 0 13-May-15 13-May-15
MM1-1305-PT-00-I-LA-00005-4
MM1 - Instrument CABLE SCHEDULE-IFC 24 13-May-15 09-Jun-15
MM1-1305-PT-00-I-LA-00007
MM1 - Instrument TUBING SCHEDULE 58 22-Apr-15 01-Jul-15
MM1-1305-PT-00-I-LA-00007-1
MM1 - Instrument TUBING SCHEDULE-IDC 22 22-Apr-15* 20-May-15
MM1-1305-PT-00-I-LA-00007-2
MM1 - Instrument TUBING SCHEDULE-IFR 12 21-May-15 03-Jun-15
MM1-1305-PT-00-I-LA-00007-3
MM1 - Instrument TUBING SCHEDULE-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-00-I-LA-00007-4
MM1 - Instrument TUBING SCHEDULE-IFC 24 04-Jun-15 01-Jul-15
MM1-1305-PT-00-I-RA-00001
MM1 & MM2 - PSV Sizing Calculation Report 45 22-Apr-15 16-Jun-15
MM1-1305-PT-00-I-RA-00001-1
MM1 & MM2 - PSV Sizing Calculation Report-IDC 10 22-Apr-15* 06-May-15
MM1-1305-PT-00-I-RA-00001-2
MM1 & MM2 - PSV Sizing Calculation Report-IFR 6 07-May-15 13-May-15
MM1-1305-PT-00-I-RA-00001-3
MM1 & MM2 - PSV Sizing Calculation Report-IFD 13 14-May-15 28-May-15
MM1-1305-PT-00-I-RA-00001-4
MM1 & MM2 - PSV Sizing Calculation Report-IFC 16 29-May-15 16-Jun-15
MM1-1305-PT-00-I-RA-00002
MM1 & MM2 - Choke Valve Sizing Calculation Report 45 23-Apr-15 17-Jun-15
MM1-1305-PT-00-I-RA-00002-1
MM1 & MM2 - Choke Valve Sizing Calculation Report-IDC 10 23-Apr-15* 07-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 24 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-I-RA-00002-2
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFR 6 08-May-15 14-May-15
MM1-1305-PT-00-I-RA-00002-3
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFD 13 15-May-15 29-May-15
MM1-1305-PT-00-I-RA-00002-4
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFC 16 30-May-15 17-Jun-15
MM1-1305-PT-00-I-RA-00003
MM1 & MM2 - FE/RO Sizing Calculation Report 45 24-Apr-15 18-Jun-15
MM1-1305-PT-00-I-RA-00003-1
MM1 & MM2 - FE/RO Sizing Calculation Report-IDC 10 24-Apr-15* 08-May-15
MM1-1305-PT-00-I-RA-00003-2
MM1 & MM2 - FE/RO Sizing Calculation Report-IFR 6 09-May-15 15-May-15
MM1-1305-PT-00-I-RA-00003-3
MM1 & MM2 - FE/RO Sizing Calculation Report-IFD 13 16-May-15 30-May-15
MM1-1305-PT-00-I-RA-00003-4
MM1 & MM2 - FE/RO Sizing Calculation Report-IFC 16 01-Jun-15 18-Jun-15
MM1-1305-PT-00-I-RA-00004
MM1 & MM2 - Instrument utility/ power consumption calculation report 60 25-May-15 01-Aug-15
MM1-1305-PT-00-I-RA-00004-1
MM1 & MM2 - Instrument utility/ power consumption calculation report-IDC 25 25-May-15* 22-Jun-15
MM1-1305-PT-00-I-RA-00004-2
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFR 6 23-Jun-15 29-Jun-15
MM1-1305-PT-00-I-RA-00004-3
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFD 13 30-Jun-15 14-Jul-15
MM1-1305-PT-00-I-RA-00004-4
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFC 16 15-Jul-15 01-Aug-15
MM1-1305-PT-00-I-DS-00001
MM1 & MM2 - Instrument Datasheet for On-Off valves 75 13-Mar-15 11-Jun-15
MM1-1305-PT-00-I-DS-00001-1
MM1 & MM2 - Instrument Datasheet for On-Off valves-IDC 20 13-Mar-15* 04-Apr-15
MM1-1305-PT-00-I-DS-00001-2
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFR 6 06-Apr-15 11-Apr-15
MM1-1305-PT-00-I-DS-00001-3
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFD 0 13-Apr-15 13-Apr-15
MM1-1305-PT-00-I-DS-00001-4
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFC 49 13-Apr-15 11-Jun-15
MM1-1305-PT-00-I-DS-00002
MM1 & MM2 - Instrument Datasheet for Motor Operated valves 69 13-Mar-15 04-Jun-15
MM1-1305-PT-00-I-DS-00002-1
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IDC 20 13-Mar-15* 04-Apr-15
MM1-1305-PT-00-I-DS-00002-2
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFR 2 06-Apr-15 07-Apr-15
MM1-1305-PT-00-I-DS-00002-3
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFD 0 08-Apr-15 08-Apr-15
MM1-1305-PT-00-I-DS-00002-4
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFC 47 08-Apr-15 04-Jun-15
MM1-1305-PT-00-I-DS-00003
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves 87 13-Mar-15 25-Jun-15
MM1-1305-PT-00-I-DS-00003-1
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IDC 20 13-Mar-15* 04-Apr-15
MM1-1305-PT-00-I-DS-00003-2
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFR 18 06-Apr-15 25-Apr-15
MM1-1305-PT-00-I-DS-00003-3
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-I-DS-00003-4
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFC 49 27-Apr-15 25-Jun-15
MM1-1305-PT-00-I-DS-00004
MM1 & MM2 - Instrument Datasheet for Choke valve 89 13-Mar-15 27-Jun-15
MM1-1305-PT-00-I-DS-00004-1
MM1 & MM2 - Instrument Datasheet for Choke valve-IDC 20 13-Mar-15* 04-Apr-15
MM1-1305-PT-00-I-DS-00004-2
MM1 & MM2 - Instrument Datasheet for Choke valve-IFR 19 06-Apr-15 27-Apr-15
MM1-1305-PT-00-I-DS-00004-3
MM1 & MM2 - Instrument Datasheet for Choke valve-IFD 0 29-Apr-15 29-Apr-15
MM1-1305-PT-00-I-DS-00004-4
MM1 & MM2 - Instrument Datasheet for Choke valve-IFC 50 29-Apr-15 27-Jun-15
MM1-1305-PT-00-I-DS-00005
MM1 & MM2 - Instrument Datasheet for H2S Analyser 89 13-Mar-15 27-Jun-15
MM1-1305-PT-00-I-DS-00005-1
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-00-I-DS-00005-2
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-00-I-DS-00005-3
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFD 0 22-Apr-15 22-Apr-15
MM1-1305-PT-00-I-DS-00005-4
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFC 55 22-Apr-15 27-Jun-15
MM1-1305-PT-00-I-DS-00006
MM1 & MM2 - Instrument Datasheet for Pig Signaller 105 13-Mar-15 16-Jul-15
MM1-1305-PT-00-I-DS-00006-1
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IDC 47 13-Mar-15* 09-May-15
MM1-1305-PT-00-I-DS-00006-2
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFR 12 11-May-15 23-May-15
MM1-1305-PT-00-I-DS-00006-3
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFD 0 25-May-15 25-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 25 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-I-DS-00006-4
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFC 46 25-May-15 16-Jul-15
MM1-1305-PT-00-I-DS-00007
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter 125 13-Mar-15 08-Aug-15
MM1-1305-PT-00-I-DS-00007-1
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IDC 59 13-Mar-15* 23-May-15
MM1-1305-PT-00-I-DS-00007-2
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFR 12 25-May-15 06-Jun-15
MM1-1305-PT-00-I-DS-00007-3
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-I-DS-00007-4
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM1-1305-PT-00-I-DS-00008
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter 125 13-Mar-15 08-Aug-15
MM1-1305-PT-00-I-DS-00008-1
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IDC 59 13-Mar-15* 23-May-15
MM1-1305-PT-00-I-DS-00008-2
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFR 12 25-May-15 06-Jun-15
MM1-1305-PT-00-I-DS-00008-3
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-I-DS-00008-4
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM1-1305-PT-00-I-DS-00009
MM1 & MM2 - Instrument Datasheet for Flow Transmitter 125 13-Mar-15 08-Aug-15
MM1-1305-PT-00-I-DS-00009-1
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IDC 59 13-Mar-15* 23-May-15
MM1-1305-PT-00-I-DS-00009-2
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFR 12 25-May-15 06-Jun-15
MM1-1305-PT-00-I-DS-00009-3
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-I-DS-00009-4
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM1-1305-PT-00-I-DS-00010
MM1 & MM2 - Instrument Datasheet for Pressure Gauge 111 13-Mar-15 23-Jul-15
MM1-1305-PT-00-I-DS-00010-1
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IDC 51 13-Mar-15* 14-May-15
MM1-1305-PT-00-I-DS-00010-2
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFR 12 15-May-15 28-May-15
MM1-1305-PT-00-I-DS-00010-3
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFD 0 29-May-15 29-May-15
MM1-1305-PT-00-I-DS-00010-4
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFC 48 29-May-15 23-Jul-15
MM1-1305-PT-00-I-DS-00011
MM1 & MM2 - Instrument Datasheet for Temperature Gauge 111 13-Mar-15 23-Jul-15
MM1-1305-PT-00-I-DS-00011-1
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IDC 51 13-Mar-15* 14-May-15
MM1-1305-PT-00-I-DS-00011-2
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFR 12 15-May-15 28-May-15
MM1-1305-PT-00-I-DS-00011-3
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFD 0 29-May-15 29-May-15
MM1-1305-PT-00-I-DS-00011-4
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFC 48 29-May-15 23-Jul-15
MM1-1305-PT-00-I-DS-00012
MM1 & MM2 - Instrument Datasheet for Restriction Orifice 123 13-Mar-15 06-Aug-15
MM1-1305-PT-00-I-DS-00012-1
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IDC 57 13-Mar-15* 21-May-15
MM1-1305-PT-00-I-DS-00012-2
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFR 12 22-May-15 04-Jun-15
MM1-1305-PT-00-I-DS-00012-3
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFD 0 05-Jun-15 05-Jun-15
MM1-1305-PT-00-I-DS-00012-4
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFC 54 05-Jun-15 06-Aug-15
MM1-1305-PT-00-I-DS-00013
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges 123 13-Mar-15 06-Aug-15
MM1-1305-PT-00-I-DS-00013-1
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IDC 57 13-Mar-15* 21-May-15
MM1-1305-PT-00-I-DS-00013-2
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFR 12 22-May-15 04-Jun-15
MM1-1305-PT-00-I-DS-00013-3
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFD 0 05-Jun-15 05-Jun-15
MM1-1305-PT-00-I-DS-00013-4
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFC 54 05-Jun-15 06-Aug-15
MM1-1305-PT-00-I-DS-00014
MM1 & MM2 - Instrument Datasheet for Junction Box 116 20-Mar-15 05-Aug-15
MM1-1305-PT-00-I-DS-00014-1
MM1 & MM2 - Instrument Datasheet for Junction Box-IDC 53 20-Mar-15* 23-May-15
MM1-1305-PT-00-I-DS-00014-2
MM1 & MM2 - Instrument Datasheet for Junction Box-IFR 12 25-May-15 06-Jun-15
MM1-1305-PT-00-I-DS-00014-3
MM1 & MM2 - Instrument Datasheet for Junction Box-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-I-DS-00014-4
MM1 & MM2 - Instrument Datasheet for Junction Box-IFC 51 08-Jun-15 05-Aug-15
MM1-1305-PT-00-I-LA-00015
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves 113 20-Mar-15 01-Aug-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 26 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-I-LA-00015-1
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IDC 53 20-Mar-15* 23-May-15
MM1-1305-PT-00-I-LA-00015-2
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFR 12 25-May-15 06-Jun-15
MM1-1305-PT-00-I-LA-00015-3
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-I-LA-00015-4
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFC 48 08-Jun-15 01-Aug-15
MM1-1305-PT-00-I-LA-00016
MM1 & MM2 - Instrument MTO for Instrument Steel Support 97 20-Mar-15 14-Jul-15
MM1-1305-PT-00-I-LA-00016-1
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IDC 55 20-Mar-15* 26-May-15
MM1-1305-PT-00-I-LA-00016-2
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFR 12 27-May-15 09-Jun-15
MM1-1305-PT-00-I-LA-00016-3
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFD 0 10-Jun-15 10-Jun-15
MM1-1305-PT-00-I-LA-00016-4
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFC 30 10-Jun-15 14-Jul-15
MM1-1305-PT-00-I-LA-00017
MM1 & MM2 - Instrument MTO for Cable 67 12-May-15 28-Jul-15
MM1-1305-PT-00-I-LA-00017-1
MM1 & MM2 - Instrument MTO for Cable-IDC 14 12-May-15* 27-May-15
MM1-1305-PT-00-I-LA-00017-2
MM1 & MM2 - Instrument MTO for Cable-IFR 12 28-May-15 10-Jun-15
MM1-1305-PT-00-I-LA-00017-3
MM1 & MM2 - Instrument MTO for Cable-IFD 0 11-Jun-15 11-Jun-15
MM1-1305-PT-00-I-LA-00017-4
MM1 & MM2 - Instrument MTO for Cable-IFC 41 11-Jun-15 28-Jul-15
MM1-1305-PT-00-I-LA-00018
MM1 & MM2 - Instrument MTO for Cable Gland 84 13-May-15 18-Aug-15
MM1-1305-PT-00-I-LA-00018-1
MM1 & MM2 - Instrument MTO for Cable Gland-IDC 14 13-May-15* 28-May-15
MM1-1305-PT-00-I-LA-00018-2
MM1 & MM2 - Instrument MTO for Cable Gland-IFR 12 29-May-15 11-Jun-15
MM1-1305-PT-00-I-LA-00018-3
MM1 & MM2 - Instrument MTO for Cable Gland-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-00-I-LA-00018-4
MM1 & MM2 - Instrument MTO for Cable Gland-IFC 58 12-Jun-15 18-Aug-15
MM1-1305-PT-00-I-LA-00019
MM1 & MM2 - Instrument MTO for Miscellaneous Materials 76 11-Jun-15 08-Sep-15
MM1-1305-PT-00-I-LA-00019-1
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IDC 9 11-Jun-15* 20-Jun-15
MM1-1305-PT-00-I-LA-00019-2
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFR 12 22-Jun-15 04-Jul-15
MM1-1305-PT-00-I-LA-00019-3
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-00-I-LA-00019-4
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFC 55 06-Jul-15 08-Sep-15
MM1-1305-PT-00-I-LA-00020
MM1 & MM2 - Instrument MTO for Cable Tray/ladder 60 01-Jun-15 08-Aug-15
MM1-1305-PT-00-I-LA-00020-1
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IDC 6 01-Jun-15* 06-Jun-15
MM1-1305-PT-00-I-LA-00020-2
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFR 12 08-Jun-15 20-Jun-15
MM1-1305-PT-00-I-LA-00020-3
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFD 0 22-Jun-15 22-Jun-15
MM1-1305-PT-00-I-LA-00020-4
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFC 42 22-Jun-15 08-Aug-15
MM1-10570 TR/MTO for Motor Operated Valve 1 07-Apr-15 07-Apr-15
MM1-10530 TR/MTO for ON-OFF Valve 1 11-Apr-15 11-Apr-15
MM1-10550 TR/MTO for Choke Valve 1 16-Apr-15 16-Apr-15
MM1-10630 TR/MTO for Pressure Safety valves 1 27-Apr-15 27-Apr-15
MM1-10710 TR/MTO for H2S analyzer 1 29-Apr-15 29-Apr-15
MM1-10590 TR/MTO for Pig Signaller 1 18-May-15 18-May-15
MM1-10670 TR/MTO for Gauges (PG/TG/LG) 1 05-Jun-15 05-Jun-15
MM1-10610 TR/MTO for Tubing & Fitting 1 10-Jun-15 10-Jun-15
MM1-10790 TR/MTO for E&I Cable Tray & Ladder 1 10-Jun-15 10-Jun-15
MM1-10830 TR/MTO for E&I Steel Support 1 10-Jun-15 10-Jun-15
MM1-10750 TR/MTO for E&I Cable 1 12-Jun-15 12-Jun-15
MM1-10650 TR/MTO for ElectronicTransmitter (PT/TT/LT/FT) 1 16-Jun-15 16-Jun-15
MM1-10810 TR/MTO for Lighting Fixtures 1 19-Jun-15 19-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 27 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-10870 TR/MTO for Heat Tracing system 1 19-Jun-15 19-Jun-15
MM1-10890 TR/MTO for MOV & Lighting distribution panel 1 19-Jun-15 19-Jun-15
MM1-10690 TR/MTO for Orifice Plate/Restriction Orifice 1 20-Jun-15 20-Jun-15
MM1-10730 TR/MTO for Junction Box 1 21-Jun-15 21-Jun-15
MM1-10770 TR/MTO for E&I Cable Gland 1 02-Jul-15 02-Jul-15
MM1-10850 TR/MTO for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 1 19-Jul-15 19-Jul-15
MM1-10910 Prepare / Submit/ Approve E&I Shop Drawings 116 27-Oct-15 16-Mar-16
0.D.26.0000.MM1.B.R Mechanical/ Material Handling 261 13-Mar-15 15-Jan-16
0.D.26.0000.MM1.B.R.92 PTSC 261 13-Mar-15 15-Jan-16
MM1-1305-PT-00-R-RA-00001
MM1 & MM2 - Material Handling Study Report 44 27-Apr-15 19-Jun-15
MM1-1305-PT-00-R-RA-00001-1
MM1 & MM2 - Material Handling Study Report-IDC 7 27-Apr-15* 07-May-15
MM1-1305-PT-00-R-RA-00001-2
MM1 & MM2 - Material Handling Study Report-IFR 7 08-May-15 15-May-15
MM1-1305-PT-00-R-RA-00001-3
MM1 & MM2 - Material Handling Study Report-IFD 7 16-May-15 23-May-15
MM1-1305-PT-00-R-RA-00001-4
MM1 & MM2 - Material Handling Study Report-IFC 23 25-May-15 19-Jun-15
MM1-1305-PT-00-R-LA-00002
MM1 & MM2 - Equipment List 53 13-Mar-15 16-May-15
MM1-1305-PT-00-R-LA-00002-1
MM1 & MM2 - Equipment List-IDC 19 13-Mar-15* 03-Apr-15
MM1-1305-PT-00-R-LA-00002-2
MM1 & MM2 - Equipment List-IFR 7 04-Apr-15 11-Apr-15
MM1-1305-PT-00-R-LA-00002-3
MM1 & MM2 - Equipment List-IFD 7 13-Apr-15 20-Apr-15
MM1-1305-PT-00-R-LA-00002-4
MM1 & MM2 - Equipment List-IFC 20 21-Apr-15 16-May-15
MM1-1305-PT-00-R-DS-00001
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001 58 13-Mar-15 22-May-15
MM1-1305-PT-00-R-DS-00001-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IDC
25 13-Mar-15* 10-Apr-15
MM1-1305-PT-00-R-DS-00001-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFR6 11-Apr-15 17-Apr-15
MM1-1305-PT-00-R-DS-00001-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFD7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-DS-00001-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFC
20 27-Apr-15 22-May-15
MM1-1305-PT-00-R-DS-00002
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002 60 13-Mar-15 25-May-15
MM1-1305-PT-00-R-DS-00002-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IDC
27 13-Mar-15* 13-Apr-15
MM1-1305-PT-00-R-DS-00002-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFR6 14-Apr-15 20-Apr-15
MM1-1305-PT-00-R-DS-00002-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFD7 21-Apr-15 29-Apr-15
MM1-1305-PT-00-R-DS-00002-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFC
20 02-May-15 25-May-15
MM1-1305-PT-00-R-DS-00003
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003 58 13-Mar-15 22-May-15
MM1-1305-PT-00-R-DS-00003-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IDC
25 13-Mar-15* 10-Apr-15
MM1-1305-PT-00-R-DS-00003-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFR6 11-Apr-15 17-Apr-15
MM1-1305-PT-00-R-DS-00003-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFD7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-DS-00003-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFC
20 27-Apr-15 22-May-15
MM1-1305-PT-00-R-DS-00004
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004 60 13-Mar-15 25-May-15
MM1-1305-PT-00-R-DS-00004-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IDC
27 13-Mar-15* 13-Apr-15
MM1-1305-PT-00-R-DS-00004-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFR6 14-Apr-15 20-Apr-15
MM1-1305-PT-00-R-DS-00004-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFD7 21-Apr-15 29-Apr-15
MM1-1305-PT-00-R-DS-00004-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFC
20 02-May-15 25-May-15
MM1-1305-PT-00-R-DS-00005
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005 58 13-Mar-15 22-May-15
MM1-1305-PT-00-R-DS-00005-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IDC
25 13-Mar-15* 10-Apr-15
MM1-1305-PT-00-R-DS-00005-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFR6 11-Apr-15 17-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 28 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-R-DS-00005-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFD7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-DS-00005-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFC
20 27-Apr-15 22-May-15
MM1-1305-PT-00-R-DS-00006
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007 60 13-Mar-15 25-May-15
MM1-1305-PT-00-R-DS-00006-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IDC
27 13-Mar-15* 13-Apr-15
MM1-1305-PT-00-R-DS-00006-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFR6 14-Apr-15 20-Apr-15
MM1-1305-PT-00-R-DS-00006-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFD7 21-Apr-15 29-Apr-15
MM1-1305-PT-00-R-DS-00006-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFC
20 02-May-15 25-May-15
MM1-1305-PT-00-R-XD-00001
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00001-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00001-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00001-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00001-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XD-00002
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00002-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00002-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00002-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00002-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XD-00003
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00003-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00003-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00003-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00003-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XD-00004
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00004-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00004-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00004-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00004-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XD-00005
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00005-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00005-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00005-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00005-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XD-00006
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007 82 13-Mar-15 19-Jun-15
MM1-1305-PT-00-R-XD-00006-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IDC
46 13-Mar-15* 08-May-15
MM1-1305-PT-00-R-XD-00006-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFR
6 09-May-15 15-May-15
MM1-1305-PT-00-R-XD-00006-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFD
0 16-May-15 16-May-15
MM1-1305-PT-00-R-XD-00006-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFC
30 16-May-15 19-Jun-15
MM1-1305-PT-00-R-XS-00001
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00001-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00001-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00001-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00001-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFC
30 25-May-15 27-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 29 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-R-XS-00002
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00002-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00002-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00002-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00002-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFC
30 25-May-15 27-Jun-15
MM1-1305-PT-00-R-XS-00003
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00003-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00003-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00003-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00003-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFC
30 25-May-15 27-Jun-15
MM1-1305-PT-00-R-XS-00004
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00004-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00004-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00004-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00004-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFC
30 25-May-15 27-Jun-15
MM1-1305-PT-00-R-XS-00005
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00005-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00005-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00005-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00005-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFC
30 25-May-15 27-Jun-15
MM1-1305-PT-00-R-XS-00006
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007 71 03-Apr-15 27-Jun-15
MM1-1305-PT-00-R-XS-00006-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IDC
34 03-Apr-15* 15-May-15
MM1-1305-PT-00-R-XS-00006-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFR7 16-May-15 23-May-15
MM1-1305-PT-00-R-XS-00006-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFD0 25-May-15 25-May-15
MM1-1305-PT-00-R-XS-00006-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFC
30 25-May-15 27-Jun-15
MM1-1305-PT-00-R-CA-00001
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00001-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IDC
25 20-Mar-15* 17-Apr-15
MM1-1305-PT-00-R-CA-00001-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00001-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00001-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-CA-00002
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00002-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IDC
25 20-Mar-15* 17-Apr-15
MM1-1305-PT-00-R-CA-00002-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00002-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00002-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-CA-00003
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00003-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IDC
25 20-Mar-15* 17-Apr-15
MM1-1305-PT-00-R-CA-00003-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00003-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00003-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-CA-00004
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00004-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IDC
25 20-Mar-15* 17-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 30 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-1305-PT-00-R-CA-00004-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00004-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00004-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-CA-00005
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00005-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IDC
25 20-Mar-15* 17-Apr-15
MM1-1305-PT-00-R-CA-00005-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00005-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00005-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-CA-00006
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007
59 20-Mar-15 30-May-15
MM1-1305-PT-00-R-CA-00006-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IDC
25 20-Mar-15* 17-Apr-15
MM1-1305-PT-00-R-CA-00006-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFR
7 18-Apr-15 25-Apr-15
MM1-1305-PT-00-R-CA-00006-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFD
0 27-Apr-15 27-Apr-15
MM1-1305-PT-00-R-CA-00006-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFC
27 27-Apr-15 30-May-15
MM1-1305-PT-00-R-SA-00001
MM1 & MM2 - Technical Requisition for QOC 45 13-Apr-15 06-Jun-15
MM1-1305-PT-00-R-SA-00001-1
MM1 & MM2 - Technical Requisition for QOC-IDC 16 13-Apr-15* 04-May-15
MM1-1305-PT-00-R-SA-00001-2
MM1 & MM2 - Technical Requisition for QOC-IFR 4 05-May-15 08-May-15
MM1-1305-PT-00-R-SA-00001-3
MM1 & MM2 - Technical Requisition for QOC-IFD 0 09-May-15 09-May-15
MM1-1305-PT-00-R-SA-00001-4
MM1 & MM2 - Technical Requisition for QOC-IFC 25 09-May-15 06-Jun-15
MM1-10490 TR/MTO for Pig Receivers (Q.O.C) 1 07-May-15 07-May-15
MM1-10510 Prepare / Submit/ Approve Mechanical Shop Drawings 84 09-Oct-15 15-Jan-16
0.D.26.0000.MM1.C Procurement 314 08-Apr-15 15-Feb-16
0.D.26.0000.MM1.C.N Structural 293 08-Apr-15 25-Jan-16
0.D.26.0000.MM1.C.N.92 PTSC 293 08-Apr-15 25-Jan-16
MM1-10000 RFQ/TBE/CBE/PO for Primary & Secondary Steel 39 08-Apr-15 16-May-15
MM1-11100 Delivery for Primary & Secondary Steel 119 17-May-15 12-Sep-15
MM1-11900 RFQ/TBE/CBE/PO for Tertiary Steel 35 10-Jun-15 14-Jul-15
MM1-14400 Delivery for Tertiary Steel 91 15-Jul-15 13-Oct-15
MM1-15100 RFQ/TBE/CBE/PO for Structural Miscellaneous 37 29-Jul-15 03-Sep-15
MM1-16600 Delivery for Structural Miscellaneous 77 04-Sep-15 19-Nov-15
MM1-15800 RFQ/TBE/CBE/PO for Gratings 37 10-Aug-15 15-Sep-15
MM1-16800 Delivery for Gratings 91 16-Sep-15 15-Dec-15
MM1-18700 RFQ/TBE/CBE/PO for SF and Grillage Material 37 11-Oct-15 16-Nov-15
MM1-21900 Delivery for SF and Grillage Material 70 17-Nov-15 25-Jan-16
0.D.26.0000.MM1.C.1 E&I 296 08-Apr-15 28-Jan-16
0.D.26.0000.MM1.C.1.91 Yinson 0 04-Jan-16 04-Jan-16
MM1-25400 ROS for ICSS RIO panels 0 04-Jan-16 ROS for ICSS RIO panels
MM1-25500 ROS for F&G detectors 0 04-Jan-16 ROS for F&G detectors
MM1-25600 ROS for PA Systems 0 04-Jan-16 ROS for PA Systems
0.D.26.0000.MM1.C.1.92 PTSC 296 08-Apr-15 28-Jan-16
MM1-10100 RFQ/TBE/CBE/PO for Motor Operated Valve 58 08-Apr-15 04-Jun-15
MM1-11600 Delivery for Motor Operated Valve 238 05-Jun-15 28-Jan-16
MM1-10300 RFQ/TBE/CBE/PO for ON-OFF Valve 61 12-Apr-15 11-Jun-15
MM1-12300 Delivery for ON-OFF Valve 231 12-Jun-15 28-Jan-16
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 31 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-10800 RFQ/TBE/CBE/PO for H2S analyzer 52 30-Apr-15 20-Jun-15
MM1-13100 Delivery for H2S analyzer 189 21-Jun-15 26-Dec-15
MM1-12800 RFQ/TBE/CBE/PO for Lighting Fixtures 48 20-Jun-15 06-Aug-15
MM1-15500 Delivery for Lighting Fixtures 133 07-Aug-15 17-Dec-15
MM1-10500 RFQ/TBE/CBE/PO for Pressure Safety valves 59 28-Apr-15 25-Jun-15
MM1-13500 Delivery for Pressure Safety valves 217 26-Jun-15 28-Jan-16
MM1-12000 RFQ/TBE/CBE/PO for E&I Cable Tray & Ladder 48 11-Jun-15 28-Jul-15
MM1-15200 Delivery for E&I Cable Tray & Ladder 106 29-Jul-15 11-Nov-15
MM1-10400 RFQ/TBE/CBE/PO for Choke Valve 58 17-Apr-15 13-Jun-15
MM1-12500 Delivery for Choke Valve 229 14-Jun-15 28-Jan-16
MM1-13300 RFQ/TBE/CBE/PO for Junction Box 59 22-Jun-15 19-Aug-15
MM1-16200 Delivery for Junction Box 105 20-Aug-15 02-Dec-15
MM1-11300 RFQ/TBE/CBE/PO for Pig Signaller 53 19-May-15 10-Jul-15
MM1-14300 Delivery for Pig Signaller 167 11-Jul-15 24-Dec-15
MM1-12100 RFQ/TBE/CBE/PO for E&I Steel Support 35 11-Jun-15 15-Jul-15
MM1-14600 Delivery for E&I Steel Support 77 16-Jul-15 30-Sep-15
MM1-12700 RFQ/TBE/CBE/PO for ElectronicTransmitter (PT/TT/LT/FT) 48 17-Jun-15 03-Aug-15
MM1-15300 Delivery for ElectronicTransmitter (PT/TT/LT/FT) 147 04-Aug-15 28-Dec-15
MM1-12400 RFQ/TBE/CBE/PO for E&I Cable 62 13-Jun-15 13-Aug-15
MM1-15900 Delivery for E&I Cable 111 14-Aug-15 02-Dec-15
MM1-11700 RFQ/TBE/CBE/PO for Gauges (PG/TG/LG) 41 06-Jun-15 16-Jul-15
MM1-14700 Delivery for Gauges (PG/TG/LG) 161 17-Jul-15 24-Dec-15
MM1-13900 RFQ/TBE/CBE/PO for E&I Cable Gland 48 03-Jul-15 19-Aug-15
MM1-16100 Delivery for E&I Cable Gland 105 20-Aug-15 02-Dec-15
MM1-15000 RFQ/TBE/CBE/PO for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.)
52 20-Jul-15 09-Sep-15
MM1-16700 Delivery for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 84 10-Sep-15 02-Dec-15
MM1-13000 RFQ/TBE/CBE/PO for MOV & Lighting distribution panel 48 20-Jun-15 06-Aug-15
MM1-15700 Delivery for MOV & Lighting distribution panel 126 07-Aug-15 10-Dec-15
MM1-13200 RFQ/TBE/CBE/PO for Orifice Plate/Restriction Orifice 47 21-Jun-15 06-Aug-15
MM1-15400 Delivery for Orifice Plate/Restriction Orifice 140 07-Aug-15 24-Dec-15
MM1-12200 RFQ/TBE/CBE/PO for Tubing & Fitting 39 11-Jun-15 19-Jul-15
MM1-14900 Delivery for Tubing & Fitting 140 20-Jul-15 06-Dec-15
MM1-12900 RFQ/TBE/CBE/PO for Heat Tracing system 48 20-Jun-15 06-Aug-15
MM1-15600 Delivery for Heat Tracing system 126 07-Aug-15 10-Dec-15
0.D.26.0000.MM1.C.R Mechanical/ Material Handling 251 08-May-15 13-Jan-16
0.D.26.0000.MM1.C.R.91 Yinson 5 08-Jan-16 13-Jan-16
MM1-26200 ROS for Material Handling Equipment 0 08-Jan-16 ROS for Material Handling Equipment
MM1-26500 ROS for Safety equipment 0 13-Jan-16 ROS for Safety equipment
0.D.26.0000.MM1.C.R.92 PTSC 197 08-May-15 20-Nov-15
MM1-10900 RFQ/TBE/CBE/PO for Pig Receivers (Q.O.C) 48 08-May-15 24-Jun-15
MM1-13400 Delivery Pig Receivers (Q.O.C) 149 25-Jun-15 20-Nov-15
0.D.26.0000.MM1.C.L Piping 311 11-Apr-15 15-Feb-16
0.D.26.0000.MM1.C.L.92 PTSC 311 11-Apr-15 15-Feb-16
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 32 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-10200 RFQ/TBE/CBE/PO for Piping Bulk 46 11-Apr-15 26-May-15
MM1-11400 Delivery for Piping Bulk 127 27-May-15 30-Sep-15
MM1-10700 RFQ/TBE/CBE/PO for Manual valves 58 30-Apr-15 26-Jun-15
MM1-13600 Delivery for Manual valves 182 27-Jun-15 25-Dec-15
MM1-10600 RFQ/TBE/CBE/PO for Barred Tee 47 29-Apr-15 14-Jun-15
MM1-12600 Delivery for Barred Tee 176 15-Jun-15 07-Dec-15
MM1-11000 RFQ/TBE/CBE/PO for Cuni fittings 53 09-May-15 30-Jun-15
MM1-13800 Delivery for Cuni fittings 108 01-Jul-15 16-Oct-15
MM1-11200 RFQ/TBE/CBE/PO for Corrosion, sand probe, sample connection, chemical connection…
41 19-May-15I 28-Jun-15
MM1-13700 Delivery for Corrosion, sand probe, sample connection, chemical connection131 29-Jun-15 06-Nov-15
MM1-11500 RFQ/TBE/CBE/PO for 3D Bend (free bare pipe to bending contractor) 48 31-May-15 17-Jul-15
MM1-14800 Delivery for 3D Bend (free bare pipe to bending contractor) 213 18-Jul-15 15-Feb-16
MM1-11800 RFQ/TBE/CBE/PO for Pipe Supports 39 07-Jun-15 15-Jul-15
MM1-14500 Delivery for Pipe Supports 85 16-Jul-15 08-Oct-15
MM1-14200 RFQ/TBE/CBE/PO for Quick Coupling 52 10-Jul-15 30-Aug-15
MM1-16500 Delivery for Quick Coupling 98 31-Aug-15 06-Dec-15
MM1-14000 RFQ/TBE/CBE/PO for Piping insulation 55 05-Jul-15 28-Aug-15
MM1-16300 Delivery for Piping insulation 99 29-Aug-15 05-Dec-15
MM1-14100 RFQ/TBE/CBE/PO for Bolt nut, gasket and other 53 07-Jul-15 28-Aug-15
MM1-16400 Delivery for Bolt nut, gasket and other 71 29-Aug-15 07-Nov-15
MM1-17100 RFQ/TBE/CBE/PO for Valve Inter-locks 56 17-Sep-15 11-Nov-15
MM1-21500 Delivery for Valve Inter-locks 70 12-Nov-15 20-Jan-16
0.D.26.0000.MM1.D Construction 194 18-Aug-15 01-Apr-16
0.D.26.0000.MM1.D.N Structural 182 18-Aug-15 24-Mar-16
0.D.26.0000.MM1.D.N.20 Blasting & Painting 154 21-Sep-15 24-Mar-16
MM1-17200 Blast, primer, tie coat for primary beam of Main Deck 10 21-Sep-15 01-Oct-15
MM1-17600 Blast, primer, tie coat for primary beam of Mezz deck 10 26-Sep-15 07-Oct-15
MM1-18400 Blast, primer, tie coat for secondary beam of main deck 10 08-Oct-15 19-Oct-15
MM1-18600 Blast, primer, tie coat for primary beam of upper deck 10 10-Oct-15 21-Oct-15
MM1-18900 Blast, primer, tie coat for secondary beam of Mezz deck 10 13-Oct-15 23-Oct-15
MM1-19400 Blast, primer, tie coat for deck plate of main deck 10 17-Oct-15 28-Oct-15
MM1-19500 Blast, primer, tie coat for secondary beam of upper deck 10 17-Oct-15 28-Oct-15
MM1-20200 Blast, primer, tie coat for deck plate of Mezz deck 10 22-Oct-15 02-Nov-15
MM1-20700 Blast, primer, tie coat for Legs and Braces for MD & Mezz Deck 14 26-Oct-15 10-Nov-15
MM1-21000 Blast, primer, tie coat for deck plate of upper deck 10 04-Nov-15 14-Nov-15
MM1-22100 Third coat for Mezz deck 10 20-Nov-15 01-Dec-15
MM1-22200 Third coat for main deck 10 21-Nov-15 02-Dec-15
MM1-23400 Third coat for upper deck 10 09-Dec-15 19-Dec-15
MM1-24200 Sweep blast and painting for handrail 10 16-Dec-15 26-Dec-15
MM1-24700 Blast to galvanizing hand rail 14 28-Dec-15 13-Jan-16
MM1-26600 Touch up for column and bracing 14 18-Jan-16 02-Feb-16
MM1-28000 Touch up for deck plate 14 03-Feb-16 24-Feb-16

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 33 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-29200 Final and touch up for main deck 14 02-Mar-16 17-Mar-16
MM1-29300 Final and touch up painting for upper deck 14 02-Mar-16 17-Mar-16
MM1-29400 Final and touch up painting for Mezz deck 14 02-Mar-16 17-Mar-16
MM1-29600 Cleaning and hand over MM1 14 09-Mar-16 24-Mar-16
0.D.26.0000.MM1.D.N.05 Pre-Fabrication 30 18-Aug-15 22-Sep-15
MM1-16000 Pre-fab & Assembly for LOSF 30 18-Aug-15 22-Sep-15
0.D.26.0000.MM1.D.N.10 Fabrication 134 17-Sep-15 26-Feb-16
0.D.26.0000.MM1.D.N.10.1 Main Deck 122 17-Sep-15 12-Feb-16
MM1-16900 Cut & prep Main Deck Primary Beams 10 17-Sep-15 28-Sep-15
MM1-17000 Fab Main Deck nodes & Joints 10 17-Sep-15 28-Sep-15
MM1-18100 Cut & prep Main Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15
MM1-19100 Fab Main Deck Plates 10 14-Oct-15 24-Oct-15
MM1-19300 Fab column and bracing 14 17-Oct-15 02-Nov-15
MM1-22700 Fab Handrail, landing & Sockets... 60 28-Nov-15 12-Feb-16
0.D.26.0000.MM1.D.N.10.2 Mezz Deck 126 21-Sep-15 20-Feb-16
MM1-17300 Cut & prep Mezz Deck Primary Beams 10 21-Sep-15 01-Oct-15
MM1-17400 Fab Mezz Deck nodes & Joints 10 21-Sep-15 01-Oct-15
MM1-18200 Cut & prep Mezz Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15
MM1-19800 Fab column and bracing 14 17-Oct-15 02-Nov-15
MM1-20000 Fab Mezz Deck Plates 10 19-Oct-15 29-Oct-15
MM1-23300 Fab Handrail, landing & Sockets... 60 07-Dec-15 20-Feb-16
0.D.26.0000.MM1.D.N.10.3 Upper Deck 120 03-Oct-15 26-Feb-16
MM1-17800 Cut & prep Upper Deck Primary Beams 10 03-Oct-15 14-Oct-15
MM1-17900 Fab Upper Deck nodes & Joints 10 03-Oct-15 14-Oct-15
MM1-18500 Cut & prep Upper Deck Secondary Beams & Stiffeners 10 09-Oct-15 20-Oct-15
MM1-20600 Fab Upper Deck Plates 14 26-Oct-15 10-Nov-15
MM1-24000 Fab Handrail, landing & Sockets... 60 12-Dec-15 26-Feb-16
0.D.26.0000.MM1.D.N.25 Installation 137 24-Sep-15 08-Mar-16
0.D.26.0000.MM1.D.N.25.1 Main Deck 133 24-Sep-15 03-Mar-16
MM1-17500 Assembly Main Deck Primary Beams & Deck nodes above LOSF 30 24-Sep-15 28-Oct-15
MM1-19700 Assembly Main Deck Secondary Beams & Stiffemers above LOSF 14 17-Oct-15 02-Nov-15
MM1-20900 Installation Main Deck Plate 16 03-Nov-15 20-Nov-15
MM1-21300 Installation Columns onto Main Deck (for Mezz Deck) 10 10-Nov-15 20-Nov-15
MM1-23800 Installation Bracings onto Main Deck 24 11-Dec-15 08-Jan-16
MM1-24100 Installation Remaining Legs onto Main Deck 8 12-Dec-15 21-Dec-15
MM1-25000 Installation Handrail, landing & Sockets, Gratings... 50 30-Dec-15 03-Mar-16
MM1-28900 Weighting for MM1 1 24-Feb-16 24-Feb-16
0.D.26.0000.MM1.D.N.25.2 Mezz Deck 127 01-Oct-15 03-Mar-16
MM1-17700 Assembly Mezz Deck Primary Beams & Deck nodes 21 01-Oct-15 24-Oct-15
MM1-20100 Assembly Mezz Deck Secondary Beams & Stiffemers 14 21-Oct-15 05-Nov-15
MM1-21200 Installation Mezz Deck Plate 12 06-Nov-15 19-Nov-15
MM1-22800 Install Mezz Deck onto Main Deck 6 03-Dec-15 09-Dec-15
MM1-23900 Installation Columns onto Mezz Deck 8 12-Dec-15 21-Dec-15
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 34 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-25200 Installation Bracings onto Mezz Deck 10 31-Dec-15 12-Jan-16
MM1-26000 Installation Handrail, landing & Sockets, Gratings... 45 06-Jan-16 03-Mar-16
0.D.26.0000.MM1.D.N.25.3 Upper Deck 117 17-Oct-15 08-Mar-16
MM1-19600 Assembly Upper Deck Primary Beams & Deck nodes 30 17-Oct-15 20-Nov-15
MM1-21100 Assembly Upper Deck Secondary Beams & Stiffemers 14 04-Nov-15 19-Nov-15
MM1-22000 Installation Upper Deck Plate 16 20-Nov-15 08-Dec-15
MM1-24400 Install Upper Deck onto Main Deck & Mezz Deck 6 22-Dec-15 28-Dec-15
MM1-25800 Installation Handrail, landing & Sockets, Gratings... 50 05-Jan-16 08-Mar-16
0.D.26.0000.MM1.D.R Mechanical/ Material Handling 112 26-Oct-15 10-Mar-16
0.D.26.0000.MM1.D.R.20 Blasting & Painting Equipment support 93 17-Nov-15 10-Mar-16
MM1-21800 Blast, primer for equipment support 21 17-Nov-15 10-Dec-15
MM1-28700 Touch up for equipment support and final coat 14 24-Feb-16 10-Mar-16
0.D.26.0000.MM1.D.R.25 Installation 40 26-Oct-15 10-Dec-15
MM1-20500 Fabrication and installation euipment support 40 26-Oct-15 10-Dec-15
0.D.26.0000.MM1.D.R.80 Equipment Securing 74 07-Dec-15 08-Mar-16
MM1-22900 Installation ROP3 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM1-23000 Installation ROP4 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM1-23100 Installation ROP5 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM1-23200 Installation ROP7 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM1-27900 Installation safty sign and safety equipment 25 03-Feb-16 08-Mar-16
0.D.26.0000.MM1.D.L Piping 135 05-Oct-15 16-Mar-16
0.D.26.0000.MM1.D.L.20 Blasting & Painting 126 15-Oct-15 16-Mar-16
MM1-19900 Blast & Paint for piping spool, SS 60 19-Oct-15 26-Dec-15
MM1-19200 Blast & Paint for piping spool, Duplex SS & Cladding 60 15-Oct-15 23-Dec-15
MM1-20300 Blast & Paint for Pipe support 55 24-Oct-15 26-Dec-15
MM1-20800 Blast & Paint for piping spool CS 90 30-Oct-15 18-Feb-16
MM1-26300 Touch up painting for piping 50 13-Jan-16 16-Mar-16
MM1-28100 Touch up for piping support 14 12-Feb-16 27-Feb-16
MM1-28400 Touch up painting for valve 14 16-Feb-16 02-Mar-16
0.D.26.0000.MM1.D.L.10 Fabrication 107 05-Oct-15 12-Feb-16
MM1-18000 Fabrication Carbon steel piping spool work 107 05-Oct-15 12-Feb-16
MM1-18800 Fabrication Stainless steel piping spool work 60 13-Oct-15 21-Dec-15
MM1-18300 Fabrication Duplex SS & Cladding piping spool work 60 07-Oct-15 15-Dec-15
MM1-19000 Fabrication Pipe support 60 14-Oct-15 22-Dec-15
MM1-20400 Fabrication CUNI piping spool work 35 26-Oct-15 04-Dec-15
0.D.26.0000.MM1.D.L.25 Installation 84 11-Nov-15 23-Feb-16
MM1-21400 Pipe support installation 60 11-Nov-15 20-Jan-16
MM1-22300 Installation Carbon steel piping spool work 56 25-Nov-15 29-Jan-16
MM1-22400 Installation Stainless steel piping spool work 55 26-Nov-15 29-Jan-16
MM1-22500 Installation Duplex SS & Cladding piping spool work 55 26-Nov-15 29-Jan-16
MM1-25300 Installation Manual valve 30 02-Jan-16 05-Feb-16
MM1-25700 Installation CUNI piping spool work 22 05-Jan-16 29-Jan-16
MM1-27400 Installation MOV valve 15 30-Jan-16 22-Feb-16

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 35 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-27500 Installation Choke valve 15 30-Jan-16 22-Feb-16
MM1-27600 Installation On-off valve 15 01-Feb-16 23-Feb-16
0.D.26.0000.MM1.D.L.40 Testing 42 31-Dec-15 24-Feb-16
MM1-25100 Flushing and hydro test 30 31-Dec-15 04-Feb-16
MM1-26100 Flangemanagement & reinstatement 37 07-Jan-16 24-Feb-16
0.D.26.0000.MM1.D.1 E&I 101 13-Nov-15 16-Mar-16
0.D.26.0000.MM1.D.1.20 Blasting & Painting 88 28-Nov-15 16-Mar-16
MM1-22600 Blast & Paint E&I support 40 28-Nov-15 14-Jan-16
MM1-29100 Touch up for E&I support 14 01-Mar-16 16-Mar-16
0.D.26.0000.MM1.D.1.10 Fabrication 50 13-Nov-15 11-Jan-16
MM1-21600 Fabrication Electrical Support 50 13-Nov-15 11-Jan-16
MM1-21700 Fabrication Instrument Support 50 13-Nov-15 11-Jan-16
0.D.26.0000.MM1.D.1.25 Installation 70 10-Dec-15 07-Mar-16
MM1-23500 Installation Electrical Support 48 10-Dec-15 04-Feb-16
MM1-24300 Installation of Instrument Support 41 18-Dec-15 04-Feb-16
MM1-24500 Installation Electrical cable Ladder/Tray 35 26-Dec-15 05-Feb-16
MM1-24900 Installation Instrument cable and Tubing Ladder/Tray 35 29-Dec-15 13-Feb-16
MM1-27000 Installation Instrument equipments 30 27-Jan-16 07-Mar-16
MM1-26900 Installation Electrical Equipments 30 26-Jan-16 05-Mar-16
MM1-27200 Installation Tubing 28 29-Jan-16 07-Mar-16
MM1-26800 Install Heat tracing 25 25-Jan-16 27-Feb-16
0.D.26.0000.MM1.D.1.40 Testing 48 11-Dec-15 05-Feb-16
MM1-23600 Testing Electrical Cable 40 11-Dec-15 27-Jan-16
MM1-23700 Testing Instrument Cable 40 11-Dec-15 27-Jan-16
MM1-24600 Calibration of instrument equipments 25 28-Dec-15 26-Jan-16
MM1-27300 Function test/ Leak test (Choke Valve, On-off Valve) 7 29-Jan-16 05-Feb-16
0.D.26.0000.MM1.D.1.30 Cabling & Termination 55 06-Jan-16 15-Mar-16
MM1-25900 Pulling Electrical Cable 35 06-Jan-16 20-Feb-16
MM1-26400 Pulling Instrument Cable 30 13-Jan-16 22-Feb-16
MM1-27100 Glanding and Termination Electrical 35 28-Jan-16 14-Mar-16
MM1-27800 Glanding and Termination Instrument 32 02-Feb-16 15-Mar-16
0.D.26.0000.MM1.D.4 Insulation 35 01-Feb-16 17-Mar-16
0.D.26.0000.MM1.D.4.25 Installation 35 01-Feb-16 17-Mar-16
MM1-27700 Insulation for Mechanical equipment & Piping 35 01-Feb-16 17-Mar-16
0.D.26.0000.MM1.D.5 Mechanical Completion ("A" Scope) 48 23-Jan-16 24-Mar-16
0.D.26.0000.MM1.D.5.60 Finishing 43 23-Jan-16 18-Mar-16
MM1-26700 ITR checksheet for Piping 40 23-Jan-16 15-Mar-16
MM1-28300 ITR checksheet for Instrument 30 13-Feb-16 18-Mar-16
MM1-28200 ITR checksheet for Electrical 30 12-Feb-16 17-Mar-16
0.D.26.0000.MM1.D.5.70 Pre-commissioning 33 16-Feb-16 24-Mar-16
MM1-28500 Pre-com for Modules MM1 ( Leak Test, Heatracing...) 33 16-Feb-16 24-Mar-16
MM1-29000 Disciplines Acceptance Certificate (DAC) 20 27-Feb-16 21-Mar-16
MM1-29500 Loop Test from Instrument devices to RIO panels 16 04-Mar-16 22-Mar-16

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 36 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM1-28800 Full power up of the module lighting 4 24-Feb-16 27-Feb-16
MM1-29700 Mechanical & Pre-com Completion date for MM1 0 24-Mar-16 Mechanical & Pre-com Com
0.D.26.0000.MM1.D.6 Finishing/ Load-Out 33 24-Feb-16 01-Apr-16
0.D.26.0000.MM1.D.6.1 Load-Out 33 24-Feb-16 01-Apr-16
MM1-28600 Fab Seafastening & Install Grillage on Barge for MM1 20 24-Feb-16 17-Mar-16
MM1-29800 Load-Out for Modules MM1 7 26-Mar-16 01-Apr-16
0.D.26.0000.MM1.T Transportation (Optional) 7 02-Apr-16 08-Apr-16
0.D.26.0000.MM1.T.7 Delivery 7 02-Apr-16 08-Apr-16
0.D.26.0000.MM1.T.7.70 Delivery 7 02-Apr-16 08-Apr-16
MM1-29900 Transportation Modules MM1 to Singapore Yard 7 02-Apr-16 08-Apr-16
0.D.26.0000.MM2 MM2-Manifold and Pigging 333 13-Mar-15 08-Apr-16
0.D.26.0000.MM2.A Milestone 333 13-Mar-15 08-Apr-16
MM2-11020 Effective date (LOI) 0 13-Mar-15* Effective date (LOI)
MM2-101000 Commence Basic & Detail Engineering Modules MM2 0 13-Mar-15* Commence Basic & Detail Engineering Modules MM2
MM2-101040 HAZID Review Workshop 0 23-Mar-15* HAZID Review Workshop
MM2-101060 HAZOP Review Workshop 0 27-Apr-15* HAZOP Review Workshop
MM2-101080 Commence Fab Modules MM2 0 17-Sep-15 Commence Fab Modules MM2
MM2-101020 Completion Basic & Detail Engineering Modules MM2 0 23-Sep-15* Completion Basic & Detail Engineering Modules MM2
MM2-11800 MCD for MM2 0 24-Mar-16* MCD for MM2
MM2-12040 Commence Load-out Modules MM2 0 26-Mar-16* Commence Load-out Modu
MM2-101100 Modules MM2 available at Singapore Yard 0 08-Apr-16* Modules MM2 available
0.D.26.0000.MM2.B Engineering 327 13-Mar-15 01-Apr-16
0.D.26.0000.MM2.B.0 General 321 13-Mar-15 01-Apr-16
0.D.26.0000.MM2.B.0.92 PTSC 321 13-Mar-15 01-Apr-16
MM2-12260 General for PMT (Meeting, Project Management, Project Coordination, Engineering
321 13-Mar-15
review, etc) 01-Apr-16
MM2-1305-PT-00-A-TB-00001
MM1 & MM2 - Detailed Engineering Execution Plan 40 13-Mar-15 29-Apr-15
MM2-1305-PT-00-A-TB-00001-1
MM1 & MM2 - Detailed Engineering Execution Plan-IDC 8 13-Mar-15* 21-Mar-15
MM2-1305-PT-00-A-TB-00001-2
MM1 & MM2 - Detailed Engineering Execution Plan-IFR 6 23-Mar-15 28-Mar-15
MM2-1305-PT-00-A-TB-00001-3
MM1 & MM2 - Detailed Engineering Execution Plan-IFD 11 30-Mar-15 10-Apr-15
MM2-1305-PT-00-A-TB-00001-4
MM1 & MM2 - Detailed Engineering Execution Plan-IFC 15 11-Apr-15 29-Apr-15
MM2-1305-PT-00-A-KA-00001
MM1 & MM2 - Detailed Engineering Coordination Procedure 31 13-Mar-15 17-Apr-15
MM2-1305-PT-00-A-KA-00001-1
MM1 & MM2 - Detailed Engineering Coordination Procedure-IDC 8 13-Mar-15* 21-Mar-15
MM2-1305-PT-00-A-KA-00001-2
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFR 6 23-Mar-15 28-Mar-15
MM2-1305-PT-00-A-KA-00001-3
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFD 0 30-Mar-15 30-Mar-15
MM2-1305-PT-00-A-KA-00001-4
MM1 & MM2 - Detailed Engineering Coordination Procedure-IFC 17 30-Mar-15 17-Apr-15
0.D.26.0000.MM2.B.9 3D Modelling 65 12-May-15 25-Jul-15
0.D.26.0000.MM2.B.9.92 PTSC 65 12-May-15 25-Jul-15
MM2-1305-PT-00-L-RA-00001
MM1 & MM2 - PDMS 30% model review report 17 12-May-15 30-May-15
MM2-1305-PT-00-L-RA-00001-1
MM1 & MM2 - PDMS 30% model review report-IDC 7 12-May-15* 19-May-15
MM2-1305-PT-00-L-RA-00001-2
MM1 & MM2 - PDMS 30% model review report-IFR 4 20-May-15 23-May-15
MM2-1305-PT-00-L-RA-00001-3
MM1 & MM2 - PDMS 30% model review report-IFD 0 25-May-15 25-May-15
MM2-1305-PT-00-L-RA-00001-4
MM1 & MM2 - PDMS 30% model review report-IFC 6 25-May-15 30-May-15
MM2-1305-PT-00-L-RA-00002
MM1 & MM2 - PDMS 60% model review report 17 09-Jun-15 27-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 37 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-L-RA-00002-1
MM1 & MM2 - PDMS 60% model review report-IDC 7 09-Jun-15* 16-Jun-15
MM2-1305-PT-00-L-RA-00002-2
MM1 & MM2 - PDMS 60% model review report-IFR 4 17-Jun-15 20-Jun-15
MM2-1305-PT-00-L-RA-00002-3
MM1 & MM2 - PDMS 60% model review report-IFD 0 22-Jun-15 22-Jun-15
MM2-1305-PT-00-L-RA-00002-4
MM1 & MM2 - PDMS 60% model review report-IFC 6 22-Jun-15 27-Jun-15
MM2-1305-PT-00-L-RA-00003
MM1 & MM2 - PDMS 90% model review report 17 07-Jul-15 25-Jul-15
MM2-1305-PT-00-L-RA-00003-1
MM1 & MM2 - PDMS 90% model review report -IDC 7 07-Jul-15* 14-Jul-15
MM2-1305-PT-00-L-RA-00003-2
MM1 & MM2 - PDMS 90% model review report -IFR 4 15-Jul-15 18-Jul-15
MM2-1305-PT-00-L-RA-00003-3
MM1 & MM2 - PDMS 90% model review report -IFD 0 20-Jul-15 20-Jul-15
MM2-1305-PT-00-L-RA-00003-4
MM1 & MM2 - PDMS 90% model review report -IFC 6 20-Jul-15 25-Jul-15
0.D.26.0000.MM2.B.S Process & Systems 79 13-Mar-15 16-Jun-15
0.D.26.0000.MM2.B.S.92 PTSC 79 13-Mar-15 16-Jun-15
MM2-1305-PT-30-P-FD-00001
MM1 & MM2 - Basic Design Data 47 13-Mar-15 09-May-15
MM2-1305-PT-30-P-FD-00001-1
MM1 & MM2 - Basic Design Data-IDC 9 13-Mar-15* 23-Mar-15
MM2-1305-PT-30-P-FD-00001-2
MM1 & MM2 - Basic Design Data-IFR 7 24-Mar-15 31-Mar-15
MM2-1305-PT-30-P-FD-00001-3
MM1 & MM2 - Basic Design Data-IFD 13 01-Apr-15 15-Apr-15
MM2-1305-PT-30-P-FD-00001-4
MM1 & MM2 - Basic Design Data-IFC 18 16-Apr-15 09-May-15
MM2-1305-PT-30-P-RA-00001
MM1 & MM2 - Report - HYSYS Simulation 48 13-Mar-15 11-May-15
MM2-1305-PT-30-P-RA-00001-1
MM1 & MM2 - Report - HYSYS Simulation-IDC 1 13-Mar-15* 13-Mar-15
MM2-1305-PT-30-P-RA-00001-2
MM1 & MM2 - Report - HYSYS Simulation-IFR 17 14-Mar-15 02-Apr-15
MM2-1305-PT-30-P-RA-00001-3
MM1 & MM2 - Report - HYSYS Simulation-IFD 13 03-Apr-15 17-Apr-15
MM2-1305-PT-30-P-RA-00001-4
MM1 & MM2 - Report - HYSYS Simulation-IFC 17 18-Apr-15 11-May-15
MM2-1305-PT-30-P-RA-00002
MM1 & MM2 - Report - Line Sizing 55 03-Apr-15 09-Jun-15
MM2-1305-PT-30-P-RA-00002-1
MM1 & MM2 - Report - Line Sizing-IDC 1 03-Apr-15* 03-Apr-15
MM2-1305-PT-30-P-RA-00002-2
MM1 & MM2 - Report - Line Sizing-IFR 21 04-Apr-15 29-Apr-15
MM2-1305-PT-30-P-RA-00002-3
MM1 & MM2 - Report - Line Sizing-IFD 13 02-May-15 16-May-15
MM2-1305-PT-30-P-RA-00002-4
MM1 & MM2 - Report - Line Sizing-IFC 20 18-May-15 09-Jun-15
MM2-1305-PT-30-P-RA-00003
MM1 & MM2 - Report - Utility Summary 40 22-Apr-15 10-Jun-15
MM2-1305-PT-30-P-RA-00003-1
MM1 & MM2 - Report - Utility Summary-IDC 1 22-Apr-15* 22-Apr-15
MM2-1305-PT-30-P-RA-00003-2
MM1 & MM2 - Report - Utility Summary-IFR 6 23-Apr-15 02-May-15
MM2-1305-PT-30-P-RA-00003-3
MM1 & MM2 - Report - Utility Summary-IFD 12 04-May-15 16-May-15
MM2-1305-PT-30-P-RA-00003-4
MM1 & MM2 - Report - Utility Summary-IFC 21 18-May-15 10-Jun-15
MM2-1305-PT-30-P-CA-00001
MM1 & MM2 - Calculation Note - Depressuring 44 23-Mar-15 15-May-15
MM2-1305-PT-30-P-CA-00001-1
MM1 & MM2 - Calculation Note - Depressuring -IDC 1 23-Mar-15* 23-Mar-15
MM2-1305-PT-30-P-CA-00001-2
MM1 & MM2 - Calculation Note - Depressuring -IFR 12 24-Mar-15 06-Apr-15
MM2-1305-PT-30-P-CA-00001-3
MM1 & MM2 - Calculation Note - Depressuring -IFD 13 07-Apr-15 21-Apr-15
MM2-1305-PT-30-P-CA-00001-4
MM1 & MM2 - Calculation Note - Depressuring -IFC 18 22-Apr-15 15-May-15
MM2-1305-PT-30-P-CA-00002
MM1 & MM2 - Calculation Note - PSV Sizing 44 07-Apr-15 30-May-15
MM2-1305-PT-30-P-CA-00002-1
MM1 & MM2 - Calculation Note - PSV Sizing -IDC 1 07-Apr-15* 07-Apr-15
MM2-1305-PT-30-P-CA-00002-2
MM1 & MM2 - Calculation Note - PSV Sizing -IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-CA-00002-3
MM1 & MM2 - Calculation Note - PSV Sizing -IFD 10 22-Apr-15 06-May-15
MM2-1305-PT-30-P-CA-00002-4
MM1 & MM2 - Calculation Note - PSV Sizing -IFC 21 07-May-15 30-May-15
MM2-1305-PT-30-P-XA-00001
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets) 69 13-Mar-15 04-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 38 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-30-P-XA-00001-1
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XA-00001-2
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XA-00001-3
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XA-00001-4
MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XA-00002
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets) 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XA-00002-1
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XA-00002-2
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XA-00002-3
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XA-00002-4
MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XA-00003
MM1 & MM2 - Material Selection Diagrams (3 Sheets) 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XA-00003-1
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XA-00003-2
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XA-00003-3
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XA-00003-4
MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00001
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00001-1
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00001-2
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00001-3
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00001-4
MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00002
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00002-1
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00002-2
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00002-3
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00002-4
MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00003
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00003-1
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00003-2
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00003-3
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00003-4
MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00004
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00004-1
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00004-2
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00004-3
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00004-4
MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00005
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00005-1
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00005-2
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00005-3
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00005-4
MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00006
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00006-1
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00006-2
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 39 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-30-P-XB-00006-3
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00006-4
MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00007
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00007-1
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00007-2
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00007-3
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00007-4
MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00008
MM1 & MM2 - P&ID HP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00008-1
MM1 & MM2 - P&ID HP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00008-2
MM1 & MM2 - P&ID HP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00008-3
MM1 & MM2 - P&ID HP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00008-4
MM1 & MM2 - P&ID HP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00009
MM1 & MM2 - P&ID HHP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00009-1
MM1 & MM2 - P&ID HHP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00009-2
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00009-3
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00009-4
MM1 & MM2 - P&ID HHP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00010
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets) 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00010-1
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00010-2
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00010-3
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00010-4
MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00011
MM1 & MM2 - P&ID Test Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00011-1
MM1 & MM2 - P&ID Test Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00011-2
MM1 & MM2 - P&ID Test Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00011-3
MM1 & MM2 - P&ID Test Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00011-4
MM1 & MM2 - P&ID Test Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00012
MM1 & MM2 - P&ID Gas Injection Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00012-1
MM1 & MM2 - P&ID Gas Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00012-2
MM1 & MM2 - P&ID Gas Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00012-3
MM1 & MM2 - P&ID Gas Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00012-4
MM1 & MM2 - P&ID Gas Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00013
MM1 & MM2 - P&ID Water Injection Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00013-1
MM1 & MM2 - P&ID Water Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00013-2
MM1 & MM2 - P&ID Water Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00013-3
MM1 & MM2 - P&ID Water Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00013-4
MM1 & MM2 - P&ID Water Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00014
MM1 & MM2 - P&ID Gas Export Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00014-1
MM1 & MM2 - P&ID Gas Export Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00014-2
MM1 & MM2 - P&ID Gas Export Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00014-3
MM1 & MM2 - P&ID Gas Export Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00014-4
MM1 & MM2 - P&ID Gas Export Manifold-IFC 21 12-May-15 04-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 40 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-30-P-XB-00015
MM1 & MM2 - P&ID Gas Lift Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00015-1
MM1 & MM2 - P&ID Gas Lift Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00015-2
MM1 & MM2 - P&ID Gas Lift Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00015-3
MM1 & MM2 - P&ID Gas Lift Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00015-4
MM1 & MM2 - P&ID Gas Lift Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-XB-00016
MM1 & MM2 - P&ID Diesel Manifold 69 13-Mar-15 04-Jun-15
MM2-1305-PT-30-P-XB-00016-1
MM1 & MM2 - P&ID Diesel Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-30-P-XB-00016-2
MM1 & MM2 - P&ID Diesel Manifold-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-30-P-XB-00016-3
MM1 & MM2 - P&ID Diesel Manifold-IFD 14 22-Apr-15 11-May-15
MM2-1305-PT-30-P-XB-00016-4
MM1 & MM2 - P&ID Diesel Manifold-IFC 21 12-May-15 04-Jun-15
MM2-1305-PT-30-P-LA-00001
MM1 & MM2 - Line List 56 09-Apr-15 16-Jun-15
MM2-1305-PT-30-P-LA-00001-1
MM1 & MM2 - Line List-IDC 14 09-Apr-15* 24-Apr-15
MM2-1305-PT-30-P-LA-00001-2
MM1 & MM2 - Line List-IFR 10 25-Apr-15 09-May-15
MM2-1305-PT-30-P-LA-00001-3
MM1 & MM2 - Line List-IFD 14 11-May-15 26-May-15
MM2-1305-PT-30-P-LA-00001-4
MM1 & MM2 - Line List-IFC 18 27-May-15 16-Jun-15
MM2-1305-PT-30-P-XM-00001
MM1 & MM2 - Safe Chart 52 08-Apr-15 10-Jun-15
MM2-1305-PT-30-P-XM-00001-1
MM1 & MM2 - Safe Chart-IDC 7 08-Apr-15* 15-Apr-15
MM2-1305-PT-30-P-XM-00001-2
MM1 & MM2 - Safe Chart-IFR 6 16-Apr-15 22-Apr-15
MM2-1305-PT-30-P-XM-00001-3
MM1 & MM2 - Safe Chart-IFD 18 23-Apr-15 16-May-15
MM2-1305-PT-30-P-XM-00001-4
MM1 & MM2 - Safe Chart-IFC 21 18-May-15 10-Jun-15
MM2-1305-PT-30-P-XL-00001
MM1 & MM2 - ESD Logic Diagram 52 08-Apr-15 10-Jun-15
MM2-1305-PT-30-P-XL-00001-1
MM1 & MM2 - ESD Logic Diagram-IDC 7 08-Apr-15* 15-Apr-15
MM2-1305-PT-30-P-XL-00001-2
MM1 & MM2 - ESD Logic Diagram-IFR 6 16-Apr-15 22-Apr-15
MM2-1305-PT-30-P-XL-00001-3
MM1 & MM2 - ESD Logic Diagram-IFD 18 23-Apr-15 16-May-15
MM2-1305-PT-30-P-XL-00001-4
MM1 & MM2 - ESD Logic Diagram-IFC 21 18-May-15 10-Jun-15
MM2-1305-PT-30-P-LA-00002
MM1 & MM2 - Alarm / Trip Schedule 52 08-Apr-15 10-Jun-15
MM2-1305-PT-30-P-LA-00002-1
MM1 & MM2 - Alarm / Trip Schedule-IDC 7 08-Apr-15* 15-Apr-15
MM2-1305-PT-30-P-LA-00002-2
MM1 & MM2 - Alarm / Trip Schedule-IFR 6 16-Apr-15 22-Apr-15
MM2-1305-PT-30-P-LA-00002-3
MM1 & MM2 - Alarm / Trip Schedule-IFD 18 23-Apr-15 16-May-15
MM2-1305-PT-30-P-LA-00002-4
MM1 & MM2 - Alarm / Trip Schedule-IFC 21 18-May-15 10-Jun-15
MM2-1305-PT-30-X-CA-00001
MM1 & MM2 - Calculation Note - Deluge System 53 08-Apr-15 11-Jun-15
MM2-1305-PT-30-X-CA-00001-1
MM1 & MM2 - Calculation Note - Deluge System-IDC 1 08-Apr-15* 08-Apr-15
MM2-1305-PT-30-X-CA-00001-2
MM1 & MM2 - Calculation Note - Deluge System-IFR 17 09-Apr-15 29-Apr-15
MM2-1305-PT-30-X-CA-00001-3
MM1 & MM2 - Calculation Note - Deluge System-IFD 14 02-May-15 18-May-15
MM2-1305-PT-30-X-CA-00001-4
MM1 & MM2 - Calculation Note - Deluge System-IFC 21 19-May-15 11-Jun-15
MM2-1305-PT-30-X-CA-00002
MM1 & MM2 - Steady State Analysis for Deluge System 51 15-Apr-15 16-Jun-15
MM2-1305-PT-30-X-CA-00002-1
MM1 & MM2 - Steady State Analysis for Deluge System-IDC 1 15-Apr-15* 15-Apr-15
MM2-1305-PT-30-X-CA-00002-2
MM1 & MM2 - Steady State Analysis for Deluge System-IFR 15 16-Apr-15 06-May-15
MM2-1305-PT-30-X-CA-00002-3
MM1 & MM2 - Steady State Analysis for Deluge System-IFD 15 07-May-15 23-May-15
MM2-1305-PT-30-X-CA-00002-4
MM1 & MM2 - Steady State Analysis for Deluge System-IFC 20 25-May-15 16-Jun-15
MM2-1305-PT-30-X-XE-20001
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
59 26-Mar-15
Equipment Layout
05-Jun-15
Plan
MM2-1305-PT-30-X-XE-20001-1
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
13 26-Mar-15*
Equipment Layout
09-Apr-15
Plan-IDC

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 41 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-30-X-XE-20001-2
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
12 10-Apr-15
Equipment Layout
23-Apr-15
Plan-IFR
MM2-1305-PT-30-X-XE-20001-3
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
11 24-Apr-15
Equipment Layout
09-May-15
Plan-IFD
MM2-1305-PT-30-X-XE-20001-4
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck
23 11-May-15
Equipment Layout
05-Jun-15
Plan-IFC
MM2-1305-PT-30-X-XE-20002
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
59 Equipment
26-Mar-15 Layout
05-Jun-15
Plan
MM2-1305-PT-30-X-XE-20002-1
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
13 Equipment
26-Mar-15*Layout
09-Apr-15
Plan-IDC
MM2-1305-PT-30-X-XE-20002-2
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
12 Equipment
10-Apr-15 Layout
23-Apr-15
Plan-IFR
MM2-1305-PT-30-X-XE-20002-3
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
11 Equipment
24-Apr-15 Layout
09-May-15
Plan-IFD
MM2-1305-PT-30-X-XE-20002-4
MM2 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck
23 Equipment
11-May-15Layout
05-Jun-15
Plan-IFC
MM2-1305-PT-30-X-XB-20001
MM2 - P&ID Firewater Deluge System 56 08-Apr-15 15-Jun-15
MM2-1305-PT-30-X-XB-20001-1
MM2 - P&ID Firewater Deluge System-IDC 10 08-Apr-15* 18-Apr-15
MM2-1305-PT-30-X-XB-20001-2
MM2 - P&ID Firewater Deluge System-IFR 11 20-Apr-15 05-May-15
MM2-1305-PT-30-X-XB-20001-3
MM2 - P&ID Firewater Deluge System-IFD 15 06-May-15 22-May-15
MM2-1305-PT-30-X-XB-20001-4
MM2 - P&ID Firewater Deluge System-IFC 20 23-May-15 15-Jun-15
0.D.26.0000.MM2.B.N Structural 315 16-Mar-15 21-Mar-16
0.D.26.0000.MM2.B.N.92 PTSC 315 16-Mar-15 21-Mar-16
MM2-1305-PT-95-N-RA-20001
MM2 - In-place Analysis Report 75 28-Mar-15 26-Jun-15
MM2-1305-PT-95-N-RA-20001-1
MM2 - In-place Analysis Report-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-RA-20001-2
MM2 - In-place Analysis Report-IFR 43 30-Mar-15 21-May-15
MM2-1305-PT-95-N-RA-20001-3
MM2 - In-place Analysis Report-IFD 12 22-May-15 04-Jun-15
MM2-1305-PT-95-N-RA-20001-4
MM2 - In-place Analysis Report-IFC 19 05-Jun-15 26-Jun-15
MM2-1305-PT-95-N-RA-20002
MM2 - Preservice Analysis Report 75 31-Mar-15 29-Jun-15
MM2-1305-PT-95-N-RA-20002-1
MM2 - Preservice Analysis Report-IDC 1 31-Mar-15* 31-Mar-15
MM2-1305-PT-95-N-RA-20002-2
MM2 - Preservice Analysis Report-IFR 43 01-Apr-15 23-May-15
MM2-1305-PT-95-N-RA-20002-3
MM2 - Preservice Analysis Report-IFD 12 25-May-15 06-Jun-15
MM2-1305-PT-95-N-RA-20002-4
MM2 - Preservice Analysis Report-IFC 19 08-Jun-15 29-Jun-15
MM2-1305-PT-95-N-RA-20003
MM2 - Structural Miscellaneous design 49 19-Jun-15 14-Aug-15
MM2-1305-PT-95-N-RA-20003-1
MM2 - Structural Miscellaneous design-IDC 1 19-Jun-15* 19-Jun-15
MM2-1305-PT-95-N-RA-20003-2
MM2 - Structural Miscellaneous design-IFR 17 20-Jun-15 09-Jul-15
MM2-1305-PT-95-N-RA-20003-3
MM2 - Structural Miscellaneous design-IFD 12 10-Jul-15 23-Jul-15
MM2-1305-PT-95-N-RA-20003-4
MM2 - Structural Miscellaneous design-IFC 19 24-Jul-15 14-Aug-15
MM2-1305-PT-95-N-RA-20005
MM2 - Weight Control Report 73 02-Apr-15 29-Jun-15
MM2-1305-PT-95-N-RA-20005-1
MM2 - Weight Control Report-IDC 33 02-Apr-15* 13-May-15
MM2-1305-PT-95-N-RA-20005-2
MM2 - Weight Control Report-IFR 9 14-May-15 23-May-15
MM2-1305-PT-95-N-RA-20005-3
MM2 - Weight Control Report-IFD 12 25-May-15 06-Jun-15
MM2-1305-PT-95-N-RA-20005-4
MM2 - Weight Control Report-IFC 19 08-Jun-15 29-Jun-15
MM2-1305-PT-95-N-RA-20006
MM2 - Seafastening Report 49 19-Jun-15 14-Aug-15
MM2-1305-PT-95-N-RA-20006-1
MM2 - Seafastening Report-IDC 1 19-Jun-15* 19-Jun-15
MM2-1305-PT-95-N-RA-20006-2
MM2 - Seafastening Report-IFR 17 20-Jun-15 09-Jul-15
MM2-1305-PT-95-N-RA-20006-3
MM2 - Seafastening Report-IFD 12 10-Jul-15 23-Jul-15
MM2-1305-PT-95-N-RA-20006-4
MM2 - Seafastening Report-IFC 19 24-Jul-15 14-Aug-15
MM2-1305-PT-95-N-LA-00001
MM1 & MM2 - Structural Primary & secondary steel MTOs 61 16-Mar-15 28-May-15
MM2-1305-PT-95-N-LA-00001-1
MM1 & MM2 - Structural Primary & secondary steel MTOs-IDC 0 16-Mar-15* 16-Mar-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 42 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-LA-00001-2
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFR 24 16-Mar-15 11-Apr-15
MM2-1305-PT-95-N-LA-00001-3
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFD 0 13-Apr-15 13-Apr-15
MM2-1305-PT-95-N-LA-00001-4
MM1 & MM2 - Structural Primary & secondary steel MTOs-IFC 37 13-Apr-15 28-May-15
MM2-1305-PT-95-N-LA-00002
MM1 & MM2 - Structural Tertiary Steel MTOs 67 04-May-15 20-Jul-15
MM2-1305-PT-95-N-LA-00002-1
MM1 & MM2 - Structural Tertiary Steel MTOs-IDC 1 04-May-15* 04-May-15
MM2-1305-PT-95-N-LA-00002-2
MM1 & MM2 - Structural Tertiary Steel MTOs-IFR 25 05-May-15 02-Jun-15
MM2-1305-PT-95-N-LA-00002-3
MM1 & MM2 - Structural Tertiary Steel MTOs-IFD 0 03-Jun-15 03-Jun-15
MM2-1305-PT-95-N-LA-00002-4
MM1 & MM2 - Structural Tertiary Steel MTOs-IFC 41 03-Jun-15 20-Jul-15
MM2-1305-PT-95-N-LA-00003
MM1 & MM2 - Structural Miscellaneous MTOs 68 22-Jun-15 09-Sep-15
MM2-1305-PT-95-N-LA-00003-1
MM1 & MM2 - Structural Miscellaneous MTOs-IDC 0 22-Jun-15* 22-Jun-15
MM2-1305-PT-95-N-LA-00003-2
MM1 & MM2 - Structural Miscellaneous MTOs-IFR 24 22-Jun-15 18-Jul-15
MM2-1305-PT-95-N-LA-00003-3
MM1 & MM2 - Structural Miscellaneous MTOs-IFD 0 20-Jul-15 20-Jul-15
MM2-1305-PT-95-N-LA-00003-4
MM1 & MM2 - Structural Miscellaneous MTOs-IFC 44 20-Jul-15 09-Sep-15
MM2-1305-PT-95-N-LA-00004
MM1 & MM2 - Structural Grating MTOs 71 23-Jun-15 14-Sep-15
MM2-1305-PT-95-N-LA-00004-1
MM1 & MM2 - Structural Grating MTOs-IDC 1 23-Jun-15* 23-Jun-15
MM2-1305-PT-95-N-LA-00004-2
MM1 & MM2 - Structural Grating MTOs-IFR 25 24-Jun-15 22-Jul-15
MM2-1305-PT-95-N-LA-00004-3
MM1 & MM2 - Structural Grating MTOs-IFD 0 23-Jul-15 23-Jul-15
MM2-1305-PT-95-N-LA-00004-4
MM1 & MM2 - Structural Grating MTOs-IFC 45 23-Jul-15 14-Sep-15
MM2-1305-PT-95-N-XG-01001
MM1 & MM2 - Structural General Notes 47 24-Mar-15 20-May-15
MM2-1305-PT-95-N-XG-01001-1
MM1 & MM2 - Structural General Notes-IDC 1 24-Mar-15* 24-Mar-15
MM2-1305-PT-95-N-XG-01001-2
MM1 & MM2 - Structural General Notes-IFR 18 25-Mar-15 14-Apr-15
MM2-1305-PT-95-N-XG-01001-3
MM1 & MM2 - Structural General Notes-IFD 11 15-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-01001-4
MM1 & MM2 - Structural General Notes-IFC 17 29-Apr-15 20-May-15
MM2-1305-PT-95-N-XG-01002
MM1 & MM2 - Typical Weld Details 49 24-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01002-1
MM1 & MM2 - Typical Weld Details-IDC 1 24-Mar-15* 24-Mar-15
MM2-1305-PT-95-N-XG-01002-2
MM1 & MM2 - Typical Weld Details-IFR 20 25-Mar-15 16-Apr-15
MM2-1305-PT-95-N-XG-01002-3
MM1 & MM2 - Typical Weld Details-IFD 10 17-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01002-4
MM1 & MM2 - Typical Weld Details-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01003
MM1 & MM2 - Typical Connection Details 48 02-Apr-15 30-May-15
MM2-1305-PT-95-N-XG-01003-1
MM1 & MM2 - Typical Connection Details-IDC 1 02-Apr-15* 02-Apr-15
MM2-1305-PT-95-N-XG-01003-2
MM1 & MM2 - Typical Connection Details-IFR 20 03-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-01003-3
MM1 & MM2 - Typical Connection Details-IFD 9 27-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-01003-4
MM1 & MM2 - Typical Connection Details-IFC 18 11-May-15 30-May-15
MM2-1305-PT-95-N-XG-01004
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01004-1
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01004-2
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01004-3
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01004-4
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01005
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01005-1
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01005-2
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01005-3
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFD 9 18-Apr-15 29-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 43 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-01005-4
MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01006
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01006-1
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01006-2
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01006-3
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01006-4
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01007
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01007-1
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01007-2
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01007-3
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01007-4
MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01008
MM1 & MM2 - Typical Plating & Grating Arrangement & Details 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01008-1
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01008-2
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01008-3
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01008-4
MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01009
MM1 & MM2 - Typical Handrail Arrangement & Details 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01009-1
MM1 & MM2 - Typical Handrail Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01009-2
MM1 & MM2 - Typical Handrail Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01009-3
MM1 & MM2 - Typical Handrail Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01009-4
MM1 & MM2 - Typical Handrail Arrangement & Details-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-01010
MM1 & MM2 - Typical Drain Outlet Details 45 28-Mar-15 22-May-15
MM2-1305-PT-95-N-XG-01010-1
MM1 & MM2 - Typical Drain Outlet Details-IDC 1 28-Mar-15* 28-Mar-15
MM2-1305-PT-95-N-XG-01010-2
MM1 & MM2 - Typical Drain Outlet Details-IFR 17 30-Mar-15 17-Apr-15
MM2-1305-PT-95-N-XG-01010-3
MM1 & MM2 - Typical Drain Outlet Details-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-01010-4
MM1 & MM2 - Typical Drain Outlet Details-IFC 18 02-May-15 22-May-15
MM2-1305-PT-95-N-XG-22001
MM2 - Drawing Index 64 24-Mar-15 09-Jun-15
MM2-1305-PT-95-N-XG-22001-1
MM2 - Drawing Index-IDC 1 24-Mar-15* 24-Mar-15
MM2-1305-PT-95-N-XG-22001-2
MM2 - Drawing Index-IFR 27 25-Mar-15 24-Apr-15
MM2-1305-PT-95-N-XG-22001-3
MM2 - Drawing Index-IFD 0 25-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-22001-4
MM2 - Drawing Index-IFC 36 25-Apr-15 09-Jun-15
MM2-1305-PT-95-N-XG-22002
MM2 - Structural Perspective View 51 29-Apr-15 29-Jun-15
MM2-1305-PT-95-N-XG-22002-1
MM2 - Structural Perspective View-IDC 0 29-Apr-15* 29-Apr-15
MM2-1305-PT-95-N-XG-22002-2
MM2 - Structural Perspective View-IFR 24 29-Apr-15 28-May-15
MM2-1305-PT-95-N-XG-22002-3
MM2 - Structural Perspective View-IFD 0 29-May-15 29-May-15
MM2-1305-PT-95-N-XG-22002-4
MM2 - Structural Perspective View-IFC 27 29-May-15 29-Jun-15
MM2-1305-PT-95-N-XG-22003
MM2 - Deck Load Plan 32 29-Apr-15 06-Jun-15
MM2-1305-PT-95-N-XG-22003-1
MM2 - Deck Load Plan-IDC 0 29-Apr-15* 29-Apr-15
MM2-1305-PT-95-N-XG-22003-2
MM2 - Deck Load Plan-IFR 20 29-Apr-15 23-May-15
MM2-1305-PT-95-N-XG-22003-3
MM2 - Deck Load Plan-IFD 0 25-May-15 25-May-15
MM2-1305-PT-95-N-XG-22003-4
MM2 - Deck Load Plan-IFC 12 25-May-15 06-Jun-15
MM2-1305-PT-95-N-XG-22004
MM2 - Upper Deck Primary Framing Plan 39 28-Mar-15 15-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 44 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22004-1
MM2 - Upper Deck Primary Framing Plan-IDC 21 28-Mar-15* 21-Apr-15
MM2-1305-PT-95-N-XG-22004-2
MM2 - Upper Deck Primary Framing Plan-IFR 5 22-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-22004-3
MM2 - Upper Deck Primary Framing Plan-IFD 0 29-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-22004-4
MM2 - Upper Deck Primary Framing Plan-IFC 13 29-Apr-15 15-May-15
MM2-1305-PT-95-N-XG-22005
MM2 - Mezzanine Deck Primary Framing Plan 37 28-Mar-15 13-May-15
MM2-1305-PT-95-N-XG-22005-1
MM2 - Mezzanine Deck Primary Framing Plan-IDC 19 28-Mar-15* 18-Apr-15
MM2-1305-PT-95-N-XG-22005-2
MM2 - Mezzanine Deck Primary Framing Plan-IFR 6 20-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-22005-3
MM2 - Mezzanine Deck Primary Framing Plan-IFD 0 27-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-22005-4
MM2 - Mezzanine Deck Primary Framing Plan-IFC 12 27-Apr-15 13-May-15
MM2-1305-PT-95-N-XG-22006
MM2 - Main Deck Primary Framing Plan 37 28-Mar-15 13-May-15
MM2-1305-PT-95-N-XG-22006-1
MM2 - Main Deck Primary Framing Plan-IDC 19 28-Mar-15* 18-Apr-15
MM2-1305-PT-95-N-XG-22006-2
MM2 - Main Deck Primary Framing Plan-IFR 6 20-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-22006-3
MM2 - Main Deck Primary Framing Plan-IFD 0 27-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-22006-4
MM2 - Main Deck Primary Framing Plan-IFC 12 27-Apr-15 13-May-15
MM2-1305-PT-95-N-XG-22007
MM2 - Truss Row 89 & Row 91 37 28-Mar-15 13-May-15
MM2-1305-PT-95-N-XG-22007-1
MM2 - Truss Row 89 & Row 91-IDC 19 28-Mar-15* 18-Apr-15
MM2-1305-PT-95-N-XG-22007-2
MM2 - Truss Row 89 & Row 91-IFR 6 20-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-22007-3
MM2 - Truss Row 89 & Row 91-IFD 0 27-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-22007-4
MM2 - Truss Row 89 & Row 91-IFC 12 27-Apr-15 13-May-15
MM2-1305-PT-95-N-XG-22008
MM2 - Truss Row 93 & Row 94 37 28-Mar-15 13-May-15
MM2-1305-PT-95-N-XG-22008-1
MM2 - Truss Row 93 & Row 94-IDC 19 28-Mar-15* 18-Apr-15
MM2-1305-PT-95-N-XG-22008-2
MM2 - Truss Row 93 & Row 94-IFR 6 20-Apr-15 25-Apr-15
MM2-1305-PT-95-N-XG-22008-3
MM2 - Truss Row 93 & Row 94-IFD 0 27-Apr-15 27-Apr-15
MM2-1305-PT-95-N-XG-22008-4
MM2 - Truss Row 93 & Row 94-IFC 12 27-Apr-15 13-May-15
MM2-1305-PT-95-N-XG-22009
MM2 - Truss Row 2A 37 01-Apr-15 16-May-15
MM2-1305-PT-95-N-XG-22009-1
MM2 - Truss Row 2A-IDC 19 01-Apr-15* 22-Apr-15
MM2-1305-PT-95-N-XG-22009-2
MM2 - Truss Row 2A-IFR 5 23-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-22009-3
MM2 - Truss Row 2A-IFD 0 02-May-15 02-May-15
MM2-1305-PT-95-N-XG-22009-4
MM2 - Truss Row 2A-IFC 13 02-May-15 16-May-15
MM2-1305-PT-95-N-XG-22010
MM2 - Truss Row 2B 37 01-Apr-15 16-May-15
MM2-1305-PT-95-N-XG-22010-1
MM2 - Truss Row 2B-IDC 19 01-Apr-15* 22-Apr-15
MM2-1305-PT-95-N-XG-22010-2
MM2 - Truss Row 2B-IFR 5 23-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-22010-3
MM2 - Truss Row 2B-IFD 0 02-May-15 02-May-15
MM2-1305-PT-95-N-XG-22010-4
MM2 - Truss Row 2B-IFC 13 02-May-15 16-May-15
MM2-1305-PT-95-N-XG-22011
MM2 - Truss Row 2C 37 01-Apr-15 16-May-15
MM2-1305-PT-95-N-XG-22011-1
MM2 - Truss Row 2C-IDC 19 01-Apr-15* 22-Apr-15
MM2-1305-PT-95-N-XG-22011-2
MM2 - Truss Row 2C-IFR 5 23-Apr-15 29-Apr-15
MM2-1305-PT-95-N-XG-22011-3
MM2 - Truss Row 2C-IFD 0 02-May-15 02-May-15
MM2-1305-PT-95-N-XG-22011-4
MM2 - Truss Row 2C-IFC 13 02-May-15 16-May-15
MM2-1305-PT-95-N-XG-22012
MM2 - Truss Row 2D 37 01-Apr-15 16-May-15
MM2-1305-PT-95-N-XG-22012-1
MM2 - Truss Row 2D-IDC 19 01-Apr-15* 22-Apr-15
MM2-1305-PT-95-N-XG-22012-2
MM2 - Truss Row 2D-IFR 5 23-Apr-15 29-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 45 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22012-3
MM2 - Truss Row 2D-IFD 0 02-May-15 02-May-15
MM2-1305-PT-95-N-XG-22012-4
MM2 - Truss Row 2D-IFC 13 02-May-15 16-May-15
MM2-1305-PT-95-N-XG-22013
MM2 - Upper Deck Joint Details Sheet 1 34 14-Apr-15 26-May-15
MM2-1305-PT-95-N-XG-22013-1
MM2 - Upper Deck Joint Details Sheet 1-IDC 1 14-Apr-15* 14-Apr-15
MM2-1305-PT-95-N-XG-22013-2
MM2 - Upper Deck Joint Details Sheet 1-IFR 21 15-Apr-15 12-May-15
MM2-1305-PT-95-N-XG-22013-3
MM2 - Upper Deck Joint Details Sheet 1-IFD 0 13-May-15 13-May-15
MM2-1305-PT-95-N-XG-22013-4
MM2 - Upper Deck Joint Details Sheet 1-IFC 12 13-May-15 26-May-15
MM2-1305-PT-95-N-XG-22014
MM2 - Upper Deck Joint Details Sheet 2 34 14-Apr-15 26-May-15
MM2-1305-PT-95-N-XG-22014-1
MM2 - Upper Deck Joint Details Sheet 2-IDC 1 14-Apr-15* 14-Apr-15
MM2-1305-PT-95-N-XG-22014-2
MM2 - Upper Deck Joint Details Sheet 2-IFR 21 15-Apr-15 12-May-15
MM2-1305-PT-95-N-XG-22014-3
MM2 - Upper Deck Joint Details Sheet 2-IFD 0 13-May-15 13-May-15
MM2-1305-PT-95-N-XG-22014-4
MM2 - Upper Deck Joint Details Sheet 2-IFC 12 13-May-15 26-May-15
MM2-1305-PT-95-N-XG-22015
MM2 - Upper Deck Joint Details Sheet 3 34 14-Apr-15 26-May-15
MM2-1305-PT-95-N-XG-22015-1
MM2 - Upper Deck Joint Details Sheet 3-IDC 1 14-Apr-15* 14-Apr-15
MM2-1305-PT-95-N-XG-22015-2
MM2 - Upper Deck Joint Details Sheet 3-IFR 21 15-Apr-15 12-May-15
MM2-1305-PT-95-N-XG-22015-3
MM2 - Upper Deck Joint Details Sheet 3-IFD 0 13-May-15 13-May-15
MM2-1305-PT-95-N-XG-22015-4
MM2 - Upper Deck Joint Details Sheet 3-IFC 12 13-May-15 26-May-15
MM2-1305-PT-95-N-XG-22016
MM2 - Upper Deck Joint Details sheet 4 34 14-Apr-15 26-May-15
MM2-1305-PT-95-N-XG-22016-1
MM2 - Upper Deck Joint Details sheet 4-IDC 1 14-Apr-15* 14-Apr-15
MM2-1305-PT-95-N-XG-22016-2
MM2 - Upper Deck Joint Details sheet 4-IFR 21 15-Apr-15 12-May-15
MM2-1305-PT-95-N-XG-22016-3
MM2 - Upper Deck Joint Details sheet 4-IFD 0 13-May-15 13-May-15
MM2-1305-PT-95-N-XG-22016-4
MM2 - Upper Deck Joint Details sheet 4-IFC 12 13-May-15 26-May-15
MM2-1305-PT-95-N-XG-22017
MM2 - Upper Deck Joint Details sheet 5 34 14-Apr-15 26-May-15
MM2-1305-PT-95-N-XG-22017-1
MM2 - Upper Deck Joint Details sheet 5-IDC 1 14-Apr-15* 14-Apr-15
MM2-1305-PT-95-N-XG-22017-2
MM2 - Upper Deck Joint Details sheet 5-IFR 21 15-Apr-15 12-May-15
MM2-1305-PT-95-N-XG-22017-3
MM2 - Upper Deck Joint Details sheet 5-IFD 0 13-May-15 13-May-15
MM2-1305-PT-95-N-XG-22017-4
MM2 - Upper Deck Joint Details sheet 5-IFC 12 13-May-15 26-May-15
MM2-1305-PT-95-N-XG-22018
MM2 - Mezzanine Deck Joint Details sheet 1 31 13-Apr-15 21-May-15
MM2-1305-PT-95-N-XG-22018-1
MM2 - Mezzanine Deck Joint Details sheet 1-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22018-2
MM2 - Mezzanine Deck Joint Details sheet 1-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22018-3
MM2 - Mezzanine Deck Joint Details sheet 1-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22018-4
MM2 - Mezzanine Deck Joint Details sheet 1-IFC 10 11-May-15 21-May-15
MM2-1305-PT-95-N-XG-22019
MM2 - Mezzanine Deck Joint Details sheet 2 32 13-Apr-15 22-May-15
MM2-1305-PT-95-N-XG-22019-1
MM2 - Mezzanine Deck Joint Details sheet 2-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22019-2
MM2 - Mezzanine Deck Joint Details sheet 2-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22019-3
MM2 - Mezzanine Deck Joint Details sheet 2-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22019-4
MM2 - Mezzanine Deck Joint Details sheet 2-IFC 11 11-May-15 22-May-15
MM2-1305-PT-95-N-XG-22020
MM2 - Mezzanine Deck Joint Details sheet 3 32 13-Apr-15 22-May-15
MM2-1305-PT-95-N-XG-22020-1
MM2 - Mezzanine Deck Joint Details sheet 3-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22020-2
MM2 - Mezzanine Deck Joint Details sheet 3-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22020-3
MM2 - Mezzanine Deck Joint Details sheet 3-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22020-4
MM2 - Mezzanine Deck Joint Details sheet 3-IFC 11 11-May-15 22-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 46 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22021
MM2 - Main Deck Joint Details Sheet 1 31 13-Apr-15 21-May-15
MM2-1305-PT-95-N-XG-22021-1
MM2 - Main Deck Joint Details Sheet 1-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22021-2
MM2 - Main Deck Joint Details Sheet 1-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22021-3
MM2 - Main Deck Joint Details Sheet 1-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22021-4
MM2 - Main Deck Joint Details Sheet 1-IFC 10 11-May-15 21-May-15
MM2-1305-PT-95-N-XG-22022
MM2 - Main Deck Joint Details Sheet 2 31 13-Apr-15 21-May-15
MM2-1305-PT-95-N-XG-22022-1
MM2 - Main Deck Joint Details Sheet 2-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22022-2
MM2 - Main Deck Joint Details Sheet 2-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22022-3
MM2 - Main Deck Joint Details Sheet 2-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22022-4
MM2 - Main Deck Joint Details Sheet 2-IFC 10 11-May-15 21-May-15
MM2-1305-PT-95-N-XG-22023
MM2 - Main Deck Joint Details Sheet 3 32 13-Apr-15 22-May-15
MM2-1305-PT-95-N-XG-22023-1
MM2 - Main Deck Joint Details Sheet 3-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22023-2
MM2 - Main Deck Joint Details Sheet 3-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22023-3
MM2 - Main Deck Joint Details Sheet 3-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22023-4
MM2 - Main Deck Joint Details Sheet 3-IFC 11 11-May-15 22-May-15
MM2-1305-PT-95-N-XG-22024
MM2 - Main Deck Joint Details Sheet 4 32 13-Apr-15 22-May-15
MM2-1305-PT-95-N-XG-22024-1
MM2 - Main Deck Joint Details Sheet 4-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22024-2
MM2 - Main Deck Joint Details Sheet 4-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22024-3
MM2 - Main Deck Joint Details Sheet 4-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22024-4
MM2 - Main Deck Joint Details Sheet 4-IFC 11 11-May-15 22-May-15
MM2-1305-PT-95-N-XG-22025
MM2 - Main Deck Joint Details Sheet 5 32 13-Apr-15 22-May-15
MM2-1305-PT-95-N-XG-22025-1
MM2 - Main Deck Joint Details Sheet 5-IDC 0 13-Apr-15* 13-Apr-15
MM2-1305-PT-95-N-XG-22025-2
MM2 - Main Deck Joint Details Sheet 5-IFR 21 13-Apr-15 09-May-15
MM2-1305-PT-95-N-XG-22025-3
MM2 - Main Deck Joint Details Sheet 5-IFD 0 11-May-15 11-May-15
MM2-1305-PT-95-N-XG-22025-4
MM2 - Main Deck Joint Details Sheet 5-IFC 11 11-May-15 22-May-15
MM2-1305-PT-95-N-XG-22026
MM2 - Upper Deck Secondary Framing Plan 34 18-Apr-15 30-May-15
MM2-1305-PT-95-N-XG-22026-1
MM2 - Upper Deck Secondary Framing Plan-IDC 20 18-Apr-15* 14-May-15
MM2-1305-PT-95-N-XG-22026-2
MM2 - Upper Deck Secondary Framing Plan-IFR 7 15-May-15 22-May-15
MM2-1305-PT-95-N-XG-22026-3
MM2 - Upper Deck Secondary Framing Plan-IFD 0 23-May-15 23-May-15
MM2-1305-PT-95-N-XG-22026-4
MM2 - Upper Deck Secondary Framing Plan-IFC 7 23-May-15 30-May-15
MM2-1305-PT-95-N-XG-22027
MM2 - Mezzanine Deck Secondary Framing Plan 34 18-Apr-15 30-May-15
MM2-1305-PT-95-N-XG-22027-1
MM2 - Mezzanine Deck Secondary Framing Plan-IDC 18 18-Apr-15* 12-May-15
MM2-1305-PT-95-N-XG-22027-2
MM2 - Mezzanine Deck Secondary Framing Plan-IFR 7 13-May-15 20-May-15
MM2-1305-PT-95-N-XG-22027-3
MM2 - Mezzanine Deck Secondary Framing Plan-IFD 0 21-May-15 21-May-15
MM2-1305-PT-95-N-XG-22027-4
MM2 - Mezzanine Deck Secondary Framing Plan-IFC 9 21-May-15 30-May-15
MM2-1305-PT-95-N-XG-22028
MM2 - Main Deck Secondary Framing plan 34 18-Apr-15 30-May-15
MM2-1305-PT-95-N-XG-22028-1
MM2 - Main Deck Secondary Framing plan-IDC 18 18-Apr-15* 12-May-15
MM2-1305-PT-95-N-XG-22028-2
MM2 - Main Deck Secondary Framing plan-IFR 7 13-May-15 20-May-15
MM2-1305-PT-95-N-XG-22028-3
MM2 - Main Deck Secondary Framing plan-IFD 0 21-May-15 21-May-15
MM2-1305-PT-95-N-XG-22028-4
MM2 - Main Deck Secondary Framing plan-IFC 9 21-May-15 30-May-15
MM2-1305-PT-95-N-XG-22029
MM2 - Upper Deck Flooring & Handrail Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22029-1
MM2 - Upper Deck Flooring & Handrail Layout-IDC 33 27-Apr-15* 06-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 47 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22029-2
MM2 - Upper Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22029-3
MM2 - Upper Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22029-4
MM2 - Upper Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22030
MM2 - Mezzanine Deck Flooring & Handrail Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22030-1
MM2 - Mezzanine Deck Flooring & Handrail Layout-IDC 33 27-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22030-2
MM2 - Mezzanine Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22030-3
MM2 - Mezzanine Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22030-4
MM2 - Mezzanine Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22031
MM2 - Main Deck Flooring & Handrail Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22031-1
MM2 - Main Deck Flooring & Handrail Layout-IDC 33 27-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22031-2
MM2 - Main Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22031-3
MM2 - Main Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22031-4
MM2 - Main Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22032
MM2 - Upper Deck Penetration Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22032-1
MM2 - Upper Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22032-2
MM2 - Upper Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22032-3
MM2 - Upper Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22032-4
MM2 - Upper Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22033
MM2 - Mezzanine Deck Penetration Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22033-1
MM2 - Mezzanine Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22033-2
MM2 - Mezzanine Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22033-3
MM2 - Mezzanine Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22033-4
MM2 - Mezzanine Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22034
MM2 - Main Deck Penetration Layout 51 27-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22034-1
MM2 - Main Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22034-2
MM2 - Main Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22034-3
MM2 - Main Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22034-4
MM2 - Main Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22035
MM2 - Lifting Padeye Arrangement & Details Sheet 1 47 29-Apr-15 24-Jun-15
MM2-1305-PT-95-N-XG-22035-1
MM2 - Lifting Padeye Arrangement & Details Sheet 1-IDC 0 29-Apr-15* 29-Apr-15
MM2-1305-PT-95-N-XG-22035-2
MM2 - Lifting Padeye Arrangement & Details Sheet 1-IFR 31 29-Apr-15 05-Jun-15
MM2-1305-PT-95-N-XG-22035-3
MM2 - Lifting Padeye Arrangement & Details Sheet 1-IFD 0 06-Jun-15 06-Jun-15
MM2-1305-PT-95-N-XG-22035-4
MM2 - Lifting Padeye Arrangement & Details Sheet 1-IFC 16 06-Jun-15 24-Jun-15
MM2-1305-PT-95-N-XG-22036
MM2 - Lifting Padeye Arrangement & Details Sheet 2 47 29-Apr-15 24-Jun-15
MM2-1305-PT-95-N-XG-22036-1
MM2 - Lifting Padeye Arrangement & Details Sheet 2-IDC 0 29-Apr-15* 29-Apr-15
MM2-1305-PT-95-N-XG-22036-2
MM2 - Lifting Padeye Arrangement & Details Sheet 2-IFR 31 29-Apr-15 05-Jun-15
MM2-1305-PT-95-N-XG-22036-3
MM2 - Lifting Padeye Arrangement & Details Sheet 2-IFD 0 06-Jun-15 06-Jun-15
MM2-1305-PT-95-N-XG-22036-4
MM2 - Lifting Padeye Arrangement & Details Sheet 2-IFC 16 06-Jun-15 24-Jun-15
MM2-1305-PT-95-N-XG-22037
MM2 - Stair Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22037-1
MM2 - Stair Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22037-2
MM2 - Stair Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22037-3
MM2 - Stair Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 48 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22037-4
MM2 - Stair Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22038
MM2 - Stair Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22038-1
MM2 - Stair Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22038-2
MM2 - Stair Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22038-3
MM2 - Stair Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22038-4
MM2 - Stair Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22039
MM2 - Ladder Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22039-1
MM2 - Ladder Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22039-2
MM2 - Ladder Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22039-3
MM2 - Ladder Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22039-4
MM2 - Ladder Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22040
MM2 - Ladder Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM2-1305-PT-95-N-XG-22040-1
MM2 - Ladder Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM2-1305-PT-95-N-XG-22040-2
MM2 - Ladder Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM2-1305-PT-95-N-XG-22040-3
MM2 - Ladder Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-95-N-XG-22040-4
MM2 - Ladder Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM2-1305-PT-95-N-XG-22041
MM2 - Mechanical Handling For Main Deck Equipment - sheet 1 29 01-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22041-1
MM2 - Mechanical Handling For Main Deck Equipment - sheet 1-IDC 11 01-Jun-15* 12-Jun-15
MM2-1305-PT-95-N-XG-22041-2
MM2 - Mechanical Handling For Main Deck Equipment - sheet 1-IFR 6 13-Jun-15 19-Jun-15
MM2-1305-PT-95-N-XG-22041-3
MM2 - Mechanical Handling For Main Deck Equipment - sheet 1-IFD 0 20-Jun-15 20-Jun-15
MM2-1305-PT-95-N-XG-22041-4
MM2 - Mechanical Handling For Main Deck Equipment - sheet 1-IFC 12 20-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22042
MM2 - Mechanical Handling For Main Deck Equipment - sheet 2 29 01-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22042-1
MM2 - Mechanical Handling For Main Deck Equipment - sheet 2-IDC 11 01-Jun-15* 12-Jun-15
MM2-1305-PT-95-N-XG-22042-2
MM2 - Mechanical Handling For Main Deck Equipment - sheet 2-IFR 6 13-Jun-15 19-Jun-15
MM2-1305-PT-95-N-XG-22042-3
MM2 - Mechanical Handling For Main Deck Equipment - sheet 2-IFD 0 20-Jun-15 20-Jun-15
MM2-1305-PT-95-N-XG-22042-4
MM2 - Mechanical Handling For Main Deck Equipment - sheet 2-IFC 12 20-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22043
MM2 - Mechanical Handling For Main Deck Equipment - sheet 3 29 01-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22043-1
MM2 - Mechanical Handling For Main Deck Equipment - sheet 3-IDC 11 01-Jun-15* 12-Jun-15
MM2-1305-PT-95-N-XG-22043-2
MM2 - Mechanical Handling For Main Deck Equipment - sheet 3-IFR 6 13-Jun-15 19-Jun-15
MM2-1305-PT-95-N-XG-22043-3
MM2 - Mechanical Handling For Main Deck Equipment - sheet 3-IFD 0 20-Jun-15 20-Jun-15
MM2-1305-PT-95-N-XG-22043-4
MM2 - Mechanical Handling For Main Deck Equipment - sheet 3-IFC 12 20-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22044
MM2 - Mechanical Handling For Main Deck Equipment - sheet 4 29 01-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22044-1
MM2 - Mechanical Handling For Main Deck Equipment - sheet 4-IDC 11 01-Jun-15* 12-Jun-15
MM2-1305-PT-95-N-XG-22044-2
MM2 - Mechanical Handling For Main Deck Equipment - sheet 4-IFR 6 13-Jun-15 19-Jun-15
MM2-1305-PT-95-N-XG-22044-3
MM2 - Mechanical Handling For Main Deck Equipment - sheet 4-IFD 0 20-Jun-15 20-Jun-15
MM2-1305-PT-95-N-XG-22044-4
MM2 - Mechanical Handling For Main Deck Equipment - sheet 4-IFC 12 20-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22045
MM2 - Mechanical Handling For Main Deck Equipment - sheet 5 29 01-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22045-1
MM2 - Mechanical Handling For Main Deck Equipment - sheet 5-IDC 11 01-Jun-15* 12-Jun-15
MM2-1305-PT-95-N-XG-22045-2
MM2 - Mechanical Handling For Main Deck Equipment - sheet 5-IFR 6 13-Jun-15 19-Jun-15
MM2-1305-PT-95-N-XG-22045-3
MM2 - Mechanical Handling For Main Deck Equipment - sheet 5-IFD 0 20-Jun-15 20-Jun-15
MM2-1305-PT-95-N-XG-22045-4
MM2 - Mechanical Handling For Main Deck Equipment - sheet 5-IFC 12 20-Jun-15 03-Jul-15
MM2-1305-PT-95-N-XG-22046
MM2 - Equipment Support - sheet 1 29 16-Jun-15 18-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 49 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-95-N-XG-22046-1
MM2 - Equipment Support - sheet 1-IDC 11 16-Jun-15* 27-Jun-15
MM2-1305-PT-95-N-XG-22046-2
MM2 - Equipment Support - sheet 1-IFR 6 29-Jun-15 04-Jul-15
MM2-1305-PT-95-N-XG-22046-3
MM2 - Equipment Support - sheet 1-IFD 0 06-Jul-15 06-Jul-15
MM2-1305-PT-95-N-XG-22046-4
MM2 - Equipment Support - sheet 1-IFC 12 06-Jul-15 18-Jul-15
MM2-1305-PT-95-N-XG-22047
MM2 - Equipment Support - sheet 2 29 16-Jun-15 18-Jul-15
MM2-1305-PT-95-N-XG-22047-1
MM2 - Equipment Support - sheet 2-IDC 11 16-Jun-15* 27-Jun-15
MM2-1305-PT-95-N-XG-22047-2
MM2 - Equipment Support - sheet 2-IFR 6 29-Jun-15 04-Jul-15
MM2-1305-PT-95-N-XG-22047-3
MM2 - Equipment Support - sheet 2-IFD 0 06-Jul-15 06-Jul-15
MM2-1305-PT-95-N-XG-22047-4
MM2 - Equipment Support - sheet 2-IFC 12 06-Jul-15 18-Jul-15
MM2-1305-PT-95-N-XG-22048
MM2 - Equipment Support - sheet 3 29 16-Jun-15 18-Jul-15
MM2-1305-PT-95-N-XG-22048-1
MM2 - Equipment Support - sheet 3-IDC 11 16-Jun-15* 27-Jun-15
MM2-1305-PT-95-N-XG-22048-2
MM2 - Equipment Support - sheet 3-IFR 6 29-Jun-15 04-Jul-15
MM2-1305-PT-95-N-XG-22048-3
MM2 - Equipment Support - sheet 3-IFD 0 06-Jul-15 06-Jul-15
MM2-1305-PT-95-N-XG-22048-4
MM2 - Equipment Support - sheet 3-IFC 12 06-Jul-15 18-Jul-15
MM2-1305-PT-95-N-XG-22049
MM2 - Seafastening On Barge Arrangment & Details - Sheet 1 30 29-Jun-15 01-Aug-15
MM2-1305-PT-95-N-XG-22049-1
MM2 - Seafastening On Barge Arrangment & Details - Sheet 1-IDC 0 29-Jun-15* 29-Jun-15
MM2-1305-PT-95-N-XG-22049-2
MM2 - Seafastening On Barge Arrangment & Details - Sheet 1-IFR 18 29-Jun-15 18-Jul-15
MM2-1305-PT-95-N-XG-22049-3
MM2 - Seafastening On Barge Arrangment & Details - Sheet 1-IFD 0 20-Jul-15 20-Jul-15
MM2-1305-PT-95-N-XG-22049-4
MM2 - Seafastening On Barge Arrangment & Details - Sheet 1-IFC 12 20-Jul-15 01-Aug-15
MM2-1305-PT-95-N-XG-22050
MM2 - Seafastening On Barge Arrangment & Details - Sheet 2 30 29-Jun-15 01-Aug-15
MM2-1305-PT-95-N-XG-22050-1
MM2 - Seafastening On Barge Arrangment & Details - Sheet 2-IDC 0 29-Jun-15* 29-Jun-15
MM2-1305-PT-95-N-XG-22050-2
MM2 - Seafastening On Barge Arrangment & Details - Sheet 2-IFR 18 29-Jun-15 18-Jul-15
MM2-1305-PT-95-N-XG-22050-3
MM2 - Seafastening On Barge Arrangment & Details - Sheet 2-IFD 0 20-Jul-15 20-Jul-15
MM2-1305-PT-95-N-XG-22050-4
MM2 - Seafastening On Barge Arrangment & Details - Sheet 2-IFC 12 20-Jul-15 01-Aug-15
MM2-1305-PT-95-N-XG-22051
MM2 - Seafastening On Barge Arrangment & Details - Sheet 3 30 29-Jun-15 01-Aug-15
MM2-1305-PT-95-N-XG-22051-1
MM2 - Seafastening On Barge Arrangment & Details - Sheet 3-IDC 0 29-Jun-15* 29-Jun-15
MM2-1305-PT-95-N-XG-22051-2
MM2 - Seafastening On Barge Arrangment & Details - Sheet 3-IFR 18 29-Jun-15 18-Jul-15
MM2-1305-PT-95-N-XG-22051-3
MM2 - Seafastening On Barge Arrangment & Details - Sheet 3-IFD 0 20-Jul-15 20-Jul-15
MM2-1305-PT-95-N-XG-22051-4
MM2 - Seafastening On Barge Arrangment & Details - Sheet 3-IFC 12 20-Jul-15 01-Aug-15
MM2-14100 TR/MTO for Primary & Secondary Steel 1 07-Apr-15 07-Apr-15
MM2-14120 TR/MTO for Tertiary Steel 1 09-Jun-15 09-Jun-15
MM2-14140 TR/MTO for Structural Miscellaneous 1 28-Jul-15 28-Jul-15
MM2-14160 TR/MTO for Gratings (including Hilti clip and cartridge) 1 09-Aug-15 09-Aug-15
MM2-1000 TR/MTO for SF and Grillage Material 1 10-Oct-15 10-Oct-15
MM2-1100 Prepare / Submit/ Approve Structural Shop Drawings 185 11-Aug-15 21-Mar-16
0.D.26.0000.MM2.B.L Piping 312 14-Mar-15 16-Mar-16
0.D.26.0000.MM2.B.L.92 PTSC 312 14-Mar-15 16-Mar-16
MM2-1305-PT-00-L-CA-00001
MM1 & MM2 - Stress Analysis Report 50 01-Jun-15 28-Jul-15
MM2-1305-PT-00-L-CA-00001-1
MM1 & MM2 - Stress Analysis Report-IDC 20 01-Jun-15* 23-Jun-15
MM2-1305-PT-00-L-CA-00001-2
MM1 & MM2 - Stress Analysis Report-IFR 6 24-Jun-15 30-Jun-15
MM2-1305-PT-00-L-CA-00001-3
MM1 & MM2 - Stress Analysis Report-IFD 12 01-Jul-15 14-Jul-15
MM2-1305-PT-00-L-CA-00001-4
MM1 & MM2 - Stress Analysis Report-IFC 12 15-Jul-15 28-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 50 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-L-LA-00001
MM1 & MM2 - Special Piping Item List 47 12-May-15 04-Jul-15
MM2-1305-PT-00-L-LA-00001-1
MM1 & MM2 - Special Piping Item List-IDC 7 12-May-15* 19-May-15
MM2-1305-PT-00-L-LA-00001-2
MM1 & MM2 - Special Piping Item List-IFR 4 20-May-15 23-May-15
MM2-1305-PT-00-L-LA-00001-3
MM1 & MM2 - Special Piping Item List-IFD 12 25-May-15 06-Jun-15
MM2-1305-PT-00-L-LA-00001-4
MM1 & MM2 - Special Piping Item List-IFC 24 08-Jun-15 04-Jul-15
MM2-1305-PT-00-L-LA-00002
MM1 & MM2 - TIE-IN Schedule 56 26-May-15 29-Jul-15
MM2-1305-PT-00-L-LA-00002-1
MM1 & MM2 - TIE-IN Schedule-IDC 25 26-May-15* 23-Jun-15
MM2-1305-PT-00-L-LA-00002-2
MM1 & MM2 - TIE-IN Schedule-IFR 7 24-Jun-15 01-Jul-15
MM2-1305-PT-00-L-LA-00002-3
MM1 & MM2 - TIE-IN Schedule-IFD 12 02-Jul-15 15-Jul-15
MM2-1305-PT-00-L-LA-00002-4
MM1 & MM2 - TIE-IN Schedule-IFC 12 16-Jul-15 29-Jul-15
MM2-1305-PT-00-L-LA-00003
MM1 & MM2 - Manual valve list 49 17-Apr-15 16-Jun-15
MM2-1305-PT-00-L-LA-00003-1
MM1 & MM2 - Manual valve list-IDC 7 17-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-LA-00003-2
MM1 & MM2 - Manual valve list-IFR 2 25-Apr-15 27-Apr-15
MM2-1305-PT-00-L-LA-00003-3
MM1 & MM2 - Manual valve list-IFD 10 29-Apr-15 12-May-15
MM2-1305-PT-00-L-LA-00003-4
MM1 & MM2 - Manual valve list-IFC 30 13-May-15 16-Jun-15
MM2-1305-PT-00-L-SA-00001
MM1 & MM2 - Addional piping class 46 14-Mar-15 09-May-15
MM2-1305-PT-00-L-SA-00001-1
MM1 & MM2 - Addional piping class -IDC 1 14-Mar-15* 14-Mar-15
MM2-1305-PT-00-L-SA-00001-2
MM1 & MM2 - Addional piping class -IFR 24 16-Mar-15 11-Apr-15
MM2-1305-PT-00-L-SA-00001-3
MM1 & MM2 - Addional piping class -IFD 12 13-Apr-15 25-Apr-15
MM2-1305-PT-00-L-SA-00001-4
MM1 & MM2 - Addional piping class -IFC 9 27-Apr-15 09-May-15
MM2-1305-PT-00-L-SA-00002
MM1 & MM2 - Pipe support standard 46 06-Apr-15 01-Jun-15
MM2-1305-PT-00-L-SA-00002-1
MM1 & MM2 - Pipe support standard -IDC 1 06-Apr-15* 06-Apr-15
MM2-1305-PT-00-L-SA-00002-2
MM1 & MM2 - Pipe support standard -IFR 21 07-Apr-15 04-May-15
MM2-1305-PT-00-L-SA-00002-3
MM1 & MM2 - Pipe support standard -IFD 12 05-May-15 18-May-15
MM2-1305-PT-00-L-SA-00002-4
MM1 & MM2 - Pipe support standard -IFC 12 19-May-15 01-Jun-15
MM2-1305-PT-00-L-DS-00001
MM1 & MM2 - Ball valve Data sheets 34 03-Apr-15 15-May-15
MM2-1305-PT-00-L-DS-00001-1
MM1 & MM2 - Ball valve Data sheets-IDC 1 03-Apr-15* 03-Apr-15
MM2-1305-PT-00-L-DS-00001-2
MM1 & MM2 - Ball valve Data sheets-IFR 12 04-Apr-15 17-Apr-15
MM2-1305-PT-00-L-DS-00001-3
MM1 & MM2 - Ball valve Data sheets-IFD 9 18-Apr-15 29-Apr-15
MM2-1305-PT-00-L-DS-00001-4
MM1 & MM2 - Ball valve Data sheets-IFC 12 02-May-15 15-May-15
MM2-1305-PT-00-L-DS-00002
MM1 & MM2 - Globe Valve Data sheets 33 06-Apr-15 16-May-15
MM2-1305-PT-00-L-DS-00002-1
MM1 & MM2 - Globe Valve Data sheets-IDC 0 06-Apr-15* 06-Apr-15
MM2-1305-PT-00-L-DS-00002-2
MM1 & MM2 - Globe Valve Data sheets-IFR 12 06-Apr-15 18-Apr-15
MM2-1305-PT-00-L-DS-00002-3
MM1 & MM2 - Globe Valve Data sheets-IFD 9 20-Apr-15 02-May-15
MM2-1305-PT-00-L-DS-00002-4
MM1 & MM2 - Globe Valve Data sheets-IFC 12 04-May-15 16-May-15
MM2-1305-PT-00-L-DS-00003
MM1 & MM2 - Check Data sheets 34 07-Apr-15 19-May-15
MM2-1305-PT-00-L-DS-00003-1
MM1 & MM2 - Check Data sheets-IDC 1 07-Apr-15* 07-Apr-15
MM2-1305-PT-00-L-DS-00003-2
MM1 & MM2 - Check Data sheets-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-00-L-DS-00003-3
MM1 & MM2 - Check Data sheets-IFD 9 22-Apr-15 05-May-15
MM2-1305-PT-00-L-DS-00003-4
MM1 & MM2 - Check Data sheets-IFC 12 06-May-15 19-May-15
MM2-1305-PT-00-L-DS-00004
MM1 & MM2 - DBB valve sheets 58 10-Apr-15 19-Jun-15
MM2-1305-PT-00-L-DS-00004-1
MM1 & MM2 - DBB valve sheets-IDC 1 10-Apr-15* 10-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 51 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-L-DS-00004-2
MM1 & MM2 - DBB valve sheets-IFR 12 11-Apr-15 24-Apr-15
MM2-1305-PT-00-L-DS-00004-3
MM1 & MM2 - DBB valve sheets-IFD 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00004-4
MM1 & MM2 - DBB valve sheets-IFC 36 09-May-15 19-Jun-15
MM2-1305-PT-00-L-DS-00005
MM1 & MM2 - SP Item Data Sheet -Valve Interlock 61 12-May-15 21-Jul-15
MM2-1305-PT-00-L-DS-00005-1
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IDC 1 12-May-15* 12-May-15
MM2-1305-PT-00-L-DS-00005-2
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFR 12 13-May-15 26-May-15
MM2-1305-PT-00-L-DS-00005-3
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFD 12 27-May-15 09-Jun-15
MM2-1305-PT-00-L-DS-00005-4
MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFC 36 10-Jun-15 21-Jul-15
MM2-1305-PT-00-L-DS-00006
MM1 & MM2 - SP Item Data Sheet - Barred Tee 52 10-Apr-15 12-Jun-15
MM2-1305-PT-00-L-DS-00006-1
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IDC 1 10-Apr-15* 10-Apr-15
MM2-1305-PT-00-L-DS-00006-2
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFR 12 11-Apr-15 24-Apr-15
MM2-1305-PT-00-L-DS-00006-3
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFD 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00006-4
MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFC 30 09-May-15 12-Jun-15
MM2-1305-PT-00-L-DS-00007
MM1 & MM2 - SP Item Data Sheet - Bends 70 24-Apr-15 17-Jul-15
MM2-1305-PT-00-L-DS-00007-1
MM1 & MM2 - SP Item Data Sheet - Bends-IDC 1 24-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-DS-00007-2
MM1 & MM2 - SP Item Data Sheet - Bends-IFR 15 25-Apr-15 15-May-15
MM2-1305-PT-00-L-DS-00007-3
MM1 & MM2 - SP Item Data Sheet - Bends-IFD 12 16-May-15 29-May-15
MM2-1305-PT-00-L-DS-00007-4
MM1 & MM2 - SP Item Data Sheet - Bends-IFC 42 30-May-15 17-Jul-15
MM2-1305-PT-00-L-DS-00008
MM1 & MM2 - SP Item Data Sheets for Sample connection 58 24-Apr-15 03-Jul-15
MM2-1305-PT-00-L-DS-00008-1
MM1 & MM2 - SP Item Data Sheets for Sample connection -IDC 1 24-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-DS-00008-2
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFR 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00008-3
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFD 12 09-May-15 22-May-15
MM2-1305-PT-00-L-DS-00008-4
MM1 & MM2 - SP Item Data Sheets for Sample connection -IFC 36 23-May-15 03-Jul-15
MM2-1305-PT-00-L-DS-00009
MM1 & MM2 - SP Item Data Sheet - Chemcial injection 58 24-Apr-15 03-Jul-15
MM2-1305-PT-00-L-DS-00009-1
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IDC 1 24-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-DS-00009-2
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFR 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00009-3
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFD 12 09-May-15 22-May-15
MM2-1305-PT-00-L-DS-00009-4
MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFC 36 23-May-15 03-Jul-15
MM2-1305-PT-00-L-DS-00010
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon 58 24-Apr-15 03-Jul-15
MM2-1305-PT-00-L-DS-00010-1
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IDC 1 24-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-DS-00010-2
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFR 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00010-3
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFD 12 09-May-15 22-May-15
MM2-1305-PT-00-L-DS-00010-4
MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFC 36 23-May-15 03-Jul-15
MM2-1305-PT-00-L-DS-00011
MM1 & MM2 - SP Item Data Sheet - Sand probe 58 24-Apr-15 03-Jul-15
MM2-1305-PT-00-L-DS-00011-1
MM1 & MM2 - SP Item Data Sheet - Sand probe-IDC 1 24-Apr-15* 24-Apr-15
MM2-1305-PT-00-L-DS-00011-2
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFR 9 25-Apr-15 08-May-15
MM2-1305-PT-00-L-DS-00011-3
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFD 12 09-May-15 22-May-15
MM2-1305-PT-00-L-DS-00011-4
MM1 & MM2 - SP Item Data Sheet - Sand probe-IFC 36 23-May-15 03-Jul-15
MM2-1305-PT-00-L-DS-00012
MM1 & MM2 - SP Item Data Sheet - Quick coupling 70 05-Jun-15 25-Aug-15
MM2-1305-PT-00-L-DS-00012-1
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IDC 1 05-Jun-15* 05-Jun-15
MM2-1305-PT-00-L-DS-00012-2
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFR 12 06-Jun-15 19-Jun-15
MM2-1305-PT-00-L-DS-00012-3
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFD 12 20-Jun-15 03-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 52 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-L-DS-00012-4
MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFC 45 04-Jul-15 25-Aug-15
MM2-1305-PT-00-L-DS-00013
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR 70 05-Jun-15 25-Aug-15
MM2-1305-PT-00-L-DS-00013-1
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IDC 1 05-Jun-15* 05-Jun-15
MM2-1305-PT-00-L-DS-00013-2
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFR 12 06-Jun-15 19-Jun-15
MM2-1305-PT-00-L-DS-00013-3
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFD 12 20-Jun-15 03-Jul-15
MM2-1305-PT-00-L-DS-00013-4
MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFC 45 04-Jul-15 25-Aug-15
MM2-1305-PT-00-L-XE-20001
MM2 - Equipment Layout 40 24-Apr-15 12-Jun-15
MM2-1305-PT-00-L-XE-20001-1
MM2 - Equipment Layout-IDC 10 24-Apr-15* 08-May-15
MM2-1305-PT-00-L-XE-20001-2
MM2 - Equipment Layout-IFR 6 09-May-15 15-May-15
MM2-1305-PT-00-L-XE-20001-3
MM2 - Equipment Layout-IFD 12 16-May-15 29-May-15
MM2-1305-PT-00-L-XE-20001-4
MM2 - Equipment Layout-IFC 12 30-May-15 12-Jun-15
MM2-1305-PT-00-L-XE-20002
MM2 - Piping layout 43 30-May-15 18-Jul-15
MM2-1305-PT-00-L-XE-20002-1
MM2 - Piping layout-IDC 13 30-May-15* 13-Jun-15
MM2-1305-PT-00-L-XE-20002-2
MM2 - Piping layout-IFR 6 15-Jun-15 20-Jun-15
MM2-1305-PT-00-L-XE-20002-3
MM2 - Piping layout-IFD 12 22-Jun-15 04-Jul-15
MM2-1305-PT-00-L-XE-20002-4
MM2 - Piping layout-IFC 12 06-Jul-15 18-Jul-15
MM2-1305-PT-00-L-XF-20003
MM2 - Pipe support location plan 43 20-Jun-15 08-Aug-15
MM2-1305-PT-00-L-XF-20003-1
MM2 - Pipe support location plan-IDC 13 20-Jun-15* 04-Jul-15
MM2-1305-PT-00-L-XF-20003-2
MM2 - Pipe support location plan-IFR 6 06-Jul-15 11-Jul-15
MM2-1305-PT-00-L-XF-20003-3
MM2 - Pipe support location plan-IFD 0 13-Jul-15 13-Jul-15
MM2-1305-PT-00-L-XF-20003-4
MM2 - Pipe support location plan-IFC 24 13-Jul-15 08-Aug-15
MM2-1305-PT-00-L-XN-20001
MM2 - Isometric drawings (n Sheets) 59 16-May-15 23-Jul-15
MM2-1305-PT-00-L-XN-20001-1
MM2 - Isometric drawings (n Sheets)-IDC 13 16-May-15* 30-May-15
MM2-1305-PT-00-L-XN-20001-2
MM2 - Isometric drawings (n Sheets)-IFR 12 01-Jun-15 13-Jun-15
MM2-1305-PT-00-L-XN-20001-3
MM2 - Isometric drawings (n Sheets)-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-00-L-XN-20001-4
MM2 - Isometric drawings (n Sheets)-IFC 34 15-Jun-15 23-Jul-15
MM2-1305-PT-00-L-XO-20001
MM2 - Pipe support detail drawings 59 16-May-15 23-Jul-15
MM2-1305-PT-00-L-XO-20001-1
MM2 - Pipe support detail drawings-IDC 13 16-May-15* 30-May-15
MM2-1305-PT-00-L-XO-20001-2
MM2 - Pipe support detail drawings-IFR 12 01-Jun-15 13-Jun-15
MM2-1305-PT-00-L-XO-20001-3
MM2 - Pipe support detail drawings-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-00-L-XO-20001-4
MM2 - Pipe support detail drawings-IFC 34 15-Jun-15 23-Jul-15
MM2-1305-PT-00-L-LA-00004
MM1 & MM2 - Material take-off for Manual Valves 45 23-Apr-15 17-Jun-15
MM2-1305-PT-00-L-LA-00004-1
MM1 & MM2 - Material take-off for Manual Valves-IDC 1 23-Apr-15* 23-Apr-15
MM2-1305-PT-00-L-LA-00004-2
MM1 & MM2 - Material take-off for Manual Valves-IFR 4 24-Apr-15 29-Apr-15
MM2-1305-PT-00-L-LA-00004-3
MM1 & MM2 - Material take-off for Manual Valves-IFD 0 02-May-15 02-May-15
MM2-1305-PT-00-L-LA-00004-4
MM1 & MM2 - Material take-off for Manual Valves-IFC 40 02-May-15 17-Jun-15
MM2-1305-PT-00-L-LA-00005
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket 54 26-Jun-15 27-Aug-15
MM2-1305-PT-00-L-LA-00005-1
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IDC 1 26-Jun-15* 26-Jun-15
MM2-1305-PT-00-L-LA-00005-2
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFR 5 27-Jun-15 02-Jul-15
MM2-1305-PT-00-L-LA-00005-3
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFD 0 03-Jul-15 03-Jul-15
MM2-1305-PT-00-L-LA-00005-4
MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFC 48 03-Jul-15 27-Aug-15
MM2-1305-PT-00-L-LA-00006
MM1 & MM2 - Material take-off for Pipe Support (Raw Material) 53 30-May-15 30-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 53 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-L-LA-00006-1
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IDC 1 30-May-15* 30-May-15
MM2-1305-PT-00-L-LA-00006-2
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFR 6 01-Jun-15 06-Jun-15
MM2-1305-PT-00-L-LA-00006-3
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-L-LA-00006-4
MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFC 46 08-Jun-15 30-Jul-15
MM2-1305-PT-00-L-LA-00007
MM1 & MM2 - Material take-off - Hub Connector 70 11-Jun-15 31-Aug-15
MM2-1305-PT-00-L-LA-00007-1
MM1 & MM2 - Material take-off - Hub Connector-IDC 1 11-Jun-15* 11-Jun-15
MM2-1305-PT-00-L-LA-00007-2
MM1 & MM2 - Material take-off - Hub Connector-IFR 12 12-Jun-15 25-Jun-15
MM2-1305-PT-00-L-LA-00007-3
MM1 & MM2 - Material take-off - Hub Connector-IFD 0 26-Jun-15 26-Jun-15
MM2-1305-PT-00-L-LA-00007-4
MM1 & MM2 - Material take-off - Hub Connector-IFC 57 26-Jun-15 31-Aug-15
MM2-14200 TR/MTO for Piping Bulk 1 10-Apr-15 10-Apr-15
MM2-14220 TR/MTO for Manual valves 1 29-Apr-15 29-Apr-15
MM2-14240 TR/MTO for Barred Tee 1 29-Apr-15 29-Apr-15
MM2-14260 TR/MTO for Cuni fittings 1 08-May-15 08-May-15
MM2-14280 TR/MTO for Corrosion, sand probe, sample connection, chemical connection 1 18-May-15 18-May-15
MM2-14300 TR/MTO for 3D Bend (free bare pipe to bending contractor) 1 30-May-15 30-May-15
MM2-14320 TR/MTO for Pipe Supports 1 06-Jun-15 06-Jun-15
MM2-14340 TR/MTO for Quick Coupling 1 09-Jul-15 09-Jul-15
MM2-14360 TR/MTO for Piping insulation 1 04-Jul-15 04-Jul-15
MM2-14380 TR/MTO for Bolt nut, gasket and other 1 06-Jul-15 06-Jul-15
MM2-14400 TR/MTO for Valve Inter-locks 1 16-Sep-15 16-Sep-15
MM2-14420 Prepare / Submit/ Approve Piping Shop Drawings 151 16-Sep-15 16-Mar-16
0.D.26.0000.MM2.B.1 E&I 313 13-Mar-15 16-Mar-16
0.D.26.0000.MM2.B.1.92 PTSC 313 13-Mar-15 16-Mar-16
MM2-1305-PT-82-E-CA-00001
MM1 & MM2 - Electrical Load List 57 04-May-15 08-Jul-15
MM2-1305-PT-82-E-CA-00001-1
MM1 & MM2 - Electrical Load List-IDC 10 04-May-15* 14-May-15
MM2-1305-PT-82-E-CA-00001-2
MM1 & MM2 - Electrical Load List-IFR 13 15-May-15 29-May-15
MM2-1305-PT-82-E-CA-00001-3
MM1 & MM2 - Electrical Load List-IFD 13 30-May-15 13-Jun-15
MM2-1305-PT-82-E-CA-00001-4
MM1 & MM2 - Electrical Load List-IFC 21 15-Jun-15 08-Jul-15
MM2-1305-PT-82-E-CA-00002
MM1 & MM2 - Electrical Lighting Calculation 32 20-Mar-15 25-Apr-15
MM2-1305-PT-82-E-CA-00002-1
MM1 & MM2 - Electrical Lighting Calculation-IDC 9 20-Mar-15* 30-Mar-15
MM2-1305-PT-82-E-CA-00002-2
MM1 & MM2 - Electrical Lighting Calculation-IFR 6 31-Mar-15 06-Apr-15
MM2-1305-PT-82-E-CA-00002-3
MM1 & MM2 - Electrical Lighting Calculation-IFD 13 07-Apr-15 21-Apr-15
MM2-1305-PT-82-E-CA-00002-4
MM1 & MM2 - Electrical Lighting Calculation-IFC 4 22-Apr-15 25-Apr-15
MM2-1305-PT-82-E-XX-00001
MM1 & MM2 - Electrical General Drawing and Document Index 36 23-Mar-15 06-May-15
MM2-1305-PT-82-E-XX-00001-1
MM1 & MM2 - Electrical General Drawing and Document Index-IDC 9 23-Mar-15* 01-Apr-15
MM2-1305-PT-82-E-XX-00001-2
MM1 & MM2 - Electrical General Drawing and Document Index-IFR 13 02-Apr-15 16-Apr-15
MM2-1305-PT-82-E-XX-00001-3
MM1 & MM2 - Electrical General Drawing and Document Index-IFD 0 17-Apr-15 17-Apr-15
MM2-1305-PT-82-E-XX-00001-4
MM1 & MM2 - Electrical General Drawing and Document Index-IFC 14 17-Apr-15 06-May-15
MM2-1305-PT-82-E-XX-00002
MM1 & MM2 - Electrical Typical Installation Details 48 13-Mar-15 11-May-15
MM2-1305-PT-82-E-XX-00002-1
MM1 & MM2 - Electrical Typical Installation Details-IDC 9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XX-00002-2
MM1 & MM2 - Electrical Typical Installation Details-IFR 13 24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XX-00002-3
MM1 & MM2 - Electrical Typical Installation Details-IFD 13 08-Apr-15 22-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 54 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-82-E-XX-00002-4
MM1 & MM2 - Electrical Typical Installation Details-IFC 13 23-Apr-15 11-May-15
MM2-1305-PT-82-E-DS-00001
MM1 & MM2 - Electrical Datasheet 30 02-Apr-15 09-May-15
MM2-1305-PT-82-E-DS-00001-1
MM1 & MM2 - Electrical Datasheet-IDC 9 02-Apr-15* 11-Apr-15
MM2-1305-PT-82-E-DS-00001-2
MM1 & MM2 - Electrical Datasheet-IFR 6 13-Apr-15 18-Apr-15
MM2-1305-PT-82-E-DS-00001-3
MM1 & MM2 - Electrical Datasheet-IFD 10 20-Apr-15 04-May-15
MM2-1305-PT-82-E-DS-00001-4
MM1 & MM2 - Electrical Datasheet-IFC 5 05-May-15 09-May-15
MM2-1305-PT-82-E-XX-20001
MM2 - Electrical Drawing Index 36 23-Mar-15 06-May-15
MM2-1305-PT-82-E-XX-20001-1
MM2 - Electrical Drawing Index-IDC 9 23-Mar-15* 01-Apr-15
MM2-1305-PT-82-E-XX-20001-2
MM2 - Electrical Drawing Index-IFR 13 02-Apr-15 16-Apr-15
MM2-1305-PT-82-E-XX-20001-3
MM2 - Electrical Drawing Index-IFD 0 17-Apr-15 17-Apr-15
MM2-1305-PT-82-E-XX-20001-4
MM2 - Electrical Drawing Index-IFC 14 17-Apr-15 06-May-15
MM2-1305-PT-82-E-XX-20002
MM2 - Electrical Cable Ladder Support 39 07-May-15 20-Jun-15
MM2-1305-PT-82-E-XX-20002-1
MM2 - Electrical Cable Ladder Support-IDC 9 07-May-15* 16-May-15
MM2-1305-PT-82-E-XX-20002-2
MM2 - Electrical Cable Ladder Support-IFR 13 18-May-15 01-Jun-15
MM2-1305-PT-82-E-XX-20002-3
MM2 - Electrical Cable Ladder Support-IFD 0 02-Jun-15 02-Jun-15
MM2-1305-PT-82-E-XX-20002-4
MM2 - Electrical Cable Ladder Support-IFC 17 02-Jun-15 20-Jun-15
MM2-1305-PT-82-E-XJ-20001
MM2 - Electrical Single Line Diagram - MOV Distribution Panel 82EL101 39 13-Mar-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20001-1
MM2 - Electrical Single Line Diagram - MOV Distribution Panel 82EL101-IDC 9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XJ-20001-2
MM2 - Electrical Single Line Diagram - MOV Distribution Panel 82EL101-IFR 13 24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XJ-20001-3
MM2 - Electrical Single Line Diagram - MOV Distribution Panel 82EL101-IFD 0 08-Apr-15 08-Apr-15
MM2-1305-PT-82-E-XJ-20001-4
MM2 - Electrical Single Line Diagram - MOV Distribution Panel 82EL101-IFC 17 08-Apr-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20002
MM2 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL102
39 13-Mar-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20002-1
MM2 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL102-IDC
9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XJ-20002-2
MM2 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL102-IFR
13 24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XJ-20002-3
MM2 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL102-IFD
0 08-Apr-15 08-Apr-15
MM2-1305-PT-82-E-XJ-20002-4
MM2 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL102-IFC
17 08-Apr-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20003
MM2 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL103
39 13-Mar-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20003-1
MM2 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL103-IDC
9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XJ-20003-2
MM2 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL103-IFR
13 24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XJ-20003-3
MM2 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL103-IFD
0 08-Apr-15 08-Apr-15
MM2-1305-PT-82-E-XJ-20003-4
MM2 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL103-IFC
17 08-Apr-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20004
MM2 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel39
82EL104
13-Mar-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20004-1
MM2 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL104-IDC
9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XJ-20004-2
MM2 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel13
82EL104-IFR
24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XJ-20004-3
MM2 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL104-IFD
0 08-Apr-15 08-Apr-15
MM2-1305-PT-82-E-XJ-20004-4
MM2 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel17
82EL104-IFC
08-Apr-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20005
MM2 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL105
39 13-Mar-15 27-Apr-15
MM2-1305-PT-82-E-XJ-20005-1
MM2 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL105-IDC
9 13-Mar-15* 23-Mar-15
MM2-1305-PT-82-E-XJ-20005-2
MM2 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL105-IFR
13 24-Mar-15 07-Apr-15
MM2-1305-PT-82-E-XJ-20005-3
MM2 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL105-IFD
0 08-Apr-15 08-Apr-15
MM2-1305-PT-82-E-XJ-20005-4
MM2 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL105-IFC
17 08-Apr-15 27-Apr-15
MM2-1305-PT-82-E-TA-20001
MM2 - Electrical Cable Schedule 51 10-Apr-15 11-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 55 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-82-E-TA-20001-1
MM2 - Electrical Cable Schedule -IDC 13 10-Apr-15* 24-Apr-15
MM2-1305-PT-82-E-TA-20001-2
MM2 - Electrical Cable Schedule -IFR 9 25-Apr-15 08-May-15
MM2-1305-PT-82-E-TA-20001-3
MM2 - Electrical Cable Schedule -IFD 13 09-May-15 23-May-15
MM2-1305-PT-82-E-TA-20001-4
MM2 - Electrical Cable Schedule -IFC 16 25-May-15 11-Jun-15
MM2-1305-PT-82-E-XT-20001
MM2 - Electrical Heat Tracing Interconnection Diagram 40 20-May-15 04-Jul-15
MM2-1305-PT-82-E-XT-20001-1
MM2 - Electrical Heat Tracing Interconnection Diagram-IDC 10 20-May-15* 30-May-15
MM2-1305-PT-82-E-XT-20001-2
MM2 - Electrical Heat Tracing Interconnection Diagram-IFR 12 01-Jun-15 13-Jun-15
MM2-1305-PT-82-E-XT-20001-3
MM2 - Electrical Heat Tracing Interconnection Diagram-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-82-E-XT-20001-4
MM2 - Electrical Heat Tracing Interconnection Diagram-IFC 18 15-Jun-15 04-Jul-15
MM2-1305-PT-82-E-XI-20001
MM2 - Electrical Heat Tracing Block Diagram 59 24-Apr-15 04-Jul-15
MM2-1305-PT-82-E-XI-20001-1
MM2 - Electrical Heat Tracing Block Diagram-IDC 6 24-Apr-15* 04-May-15
MM2-1305-PT-82-E-XI-20001-2
MM2 - Electrical Heat Tracing Block Diagram-IFR 13 05-May-15 19-May-15
MM2-1305-PT-82-E-XI-20001-3
MM2 - Electrical Heat Tracing Block Diagram-IFD 0 20-May-15 20-May-15
MM2-1305-PT-82-E-XI-20001-4
MM2 - Electrical Heat Tracing Block Diagram-IFC 40 20-May-15 04-Jul-15
MM2-1305-PT-82-E-XI-20002
MM2 - Electrical Lighting Interconnection Diagram 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XI-20002-1
MM2 - Electrical Lighting Interconnection Diagram-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XI-20002-2
MM2 - Electrical Lighting Interconnection Diagram-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XI-20002-3
MM2 - Electrical Lighting Interconnection Diagram-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XI-20002-4
MM2 - Electrical Lighting Interconnection Diagram-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-20001
MM2 - Electrical Lighting And Small Power Layout - Main Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-20001-1
MM2 - Electrical Lighting And Small Power Layout - Main Deck-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-20001-2
MM2 - Electrical Lighting And Small Power Layout - Main Deck-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-20001-3
MM2 - Electrical Lighting And Small Power Layout - Main Deck-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-20001-4
MM2 - Electrical Lighting And Small Power Layout - Main Deck-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-20002
MM2 - Electrical Lighting And Small Power Layout - Mezzanine Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-20002-1
MM2 - Electrical Lighting And Small Power Layout - Mezzanine Deck-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-20002-2
MM2 - Electrical Lighting And Small Power Layout - Mezzanine Deck-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-20002-3
MM2 - Electrical Lighting And Small Power Layout - Mezzanine Deck-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-20002-4
MM2 - Electrical Lighting And Small Power Layout - Mezzanine Deck-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-20003
MM2 - Electrical Lighting And Small Power Layout - Upper Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-20003-1
MM2 - Electrical Lighting And Small Power Layout - Upper Deck-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-20003-2
MM2 - Electrical Lighting And Small Power Layout - Upper Deck-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-20003-3
MM2 - Electrical Lighting And Small Power Layout - Upper Deck-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-20003-4
MM2 - Electrical Lighting And Small Power Layout - Upper Deck-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-21001
MM2 - Electrical Earthing Layout - Main Deck 35 01-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-21001-1
MM2 - Electrical Earthing Layout - Main Deck -IDC 8 01-Apr-15* 09-Apr-15
MM2-1305-PT-82-E-XE-21001-2
MM2 - Electrical Earthing Layout - Main Deck -IFR 13 10-Apr-15 24-Apr-15
MM2-1305-PT-82-E-XE-21001-3
MM2 - Electrical Earthing Layout - Main Deck -IFD 0 25-Apr-15 25-Apr-15
MM2-1305-PT-82-E-XE-21001-4
MM2 - Electrical Earthing Layout - Main Deck -IFC 14 25-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-21002
MM2 - Electrical Earthing Layout - Mezzanine Deck 35 01-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-21002-1
MM2 - Electrical Earthing Layout - Mezzanine Deck-IDC 8 01-Apr-15* 09-Apr-15
MM2-1305-PT-82-E-XE-21002-2
MM2 - Electrical Earthing Layout - Mezzanine Deck-IFR 13 10-Apr-15 24-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 56 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-82-E-XE-21002-3
MM2 - Electrical Earthing Layout - Mezzanine Deck-IFD 0 25-Apr-15 25-Apr-15
MM2-1305-PT-82-E-XE-21002-4
MM2 - Electrical Earthing Layout - Mezzanine Deck-IFC 14 25-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-21003
MM2 - Electrical Earthing Layout - Upper Deck 35 01-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-21003-1
MM2 - Electrical Earthing Layout - Upper Deck -IDC 8 01-Apr-15* 09-Apr-15
MM2-1305-PT-82-E-XE-21003-2
MM2 - Electrical Earthing Layout - Upper Deck -IFR 13 10-Apr-15 24-Apr-15
MM2-1305-PT-82-E-XE-21003-3
MM2 - Electrical Earthing Layout - Upper Deck -IFD 0 25-Apr-15 25-Apr-15
MM2-1305-PT-82-E-XE-21003-4
MM2 - Electrical Earthing Layout - Upper Deck -IFC 14 25-Apr-15 14-May-15
MM2-1305-PT-82-E-XE-22001
MM2 - Electrical Cable Ladder And Support Layout - Main Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-22001-1
MM2 - Electrical Cable Ladder And Support Layout - Main Deck -IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-22001-2
MM2 - Electrical Cable Ladder And Support Layout - Main Deck -IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-22001-3
MM2 - Electrical Cable Ladder And Support Layout - Main Deck -IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-22001-4
MM2 - Electrical Cable Ladder And Support Layout - Main Deck -IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-22002
MM2 - Electrical Cable Ladder And Support Layout - Mezzanine Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-22002-1
MM2 - Electrical Cable Ladder And Support Layout - Mezzanine Deck-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-22002-2
MM2 - Electrical Cable Ladder And Support Layout - Mezzanine Deck-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-22002-3
MM2 - Electrical Cable Ladder And Support Layout - Mezzanine Deck-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-22002-4
MM2 - Electrical Cable Ladder And Support Layout - Mezzanine Deck-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-22003
MM2 - Electrical Cable Ladder And Support Layout - Upper Deck 36 23-Apr-15 06-Jun-15
MM2-1305-PT-82-E-XE-22003-1
MM2 - Electrical Cable Ladder And Support Layout - Upper Deck-IDC 6 23-Apr-15* 02-May-15
MM2-1305-PT-82-E-XE-22003-2
MM2 - Electrical Cable Ladder And Support Layout - Upper Deck-IFR 13 04-May-15 18-May-15
MM2-1305-PT-82-E-XE-22003-3
MM2 - Electrical Cable Ladder And Support Layout - Upper Deck-IFD 0 19-May-15 19-May-15
MM2-1305-PT-82-E-XE-22003-4
MM2 - Electrical Cable Ladder And Support Layout - Upper Deck-IFC 17 19-May-15 06-Jun-15
MM2-1305-PT-82-E-XE-23001
MM2 - Electrical Cable Routing Layout - Main Deck 39 08-May-15 22-Jun-15
MM2-1305-PT-82-E-XE-23001-1
MM2 - Electrical Cable Routing Layout - Main Deck-IDC 9 08-May-15* 18-May-15
MM2-1305-PT-82-E-XE-23001-2
MM2 - Electrical Cable Routing Layout - Main Deck-IFR 13 19-May-15 02-Jun-15
MM2-1305-PT-82-E-XE-23001-3
MM2 - Electrical Cable Routing Layout - Main Deck-IFD 0 03-Jun-15 03-Jun-15
MM2-1305-PT-82-E-XE-23001-4
MM2 - Electrical Cable Routing Layout - Main Deck-IFC 17 03-Jun-15 22-Jun-15
MM2-1305-PT-82-E-XE-23002
MM2 - Electrical Cable Routing Layout - Mezzanine Deck 39 08-May-15 22-Jun-15
MM2-1305-PT-82-E-XE-23002-1
MM2 - Electrical Cable Routing Layout - Mezzanine Deck-IDC 9 08-May-15* 18-May-15
MM2-1305-PT-82-E-XE-23002-2
MM2 - Electrical Cable Routing Layout - Mezzanine Deck-IFR 13 19-May-15 02-Jun-15
MM2-1305-PT-82-E-XE-23002-3
MM2 - Electrical Cable Routing Layout - Mezzanine Deck-IFD 0 03-Jun-15 03-Jun-15
MM2-1305-PT-82-E-XE-23002-4
MM2 - Electrical Cable Routing Layout - Mezzanine Deck-IFC 17 03-Jun-15 22-Jun-15
MM2-1305-PT-82-E-XE-23003
MM2 - Electrical Cable Routing Layout - Upper Deck 39 08-May-15 22-Jun-15
MM2-1305-PT-82-E-XE-23003-1
MM2 - Electrical Cable Routing Layout - Upper Deck-IDC 9 08-May-15* 18-May-15
MM2-1305-PT-82-E-XE-23003-2
MM2 - Electrical Cable Routing Layout - Upper Deck-IFR 13 19-May-15 02-Jun-15
MM2-1305-PT-82-E-XE-23003-3
MM2 - Electrical Cable Routing Layout - Upper Deck-IFD 0 03-Jun-15 03-Jun-15
MM2-1305-PT-82-E-XE-23003-4
MM2 - Electrical Cable Routing Layout - Upper Deck-IFC 17 03-Jun-15 22-Jun-15
MM2-1305-PT-82-E-LA-00001
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures 80 05-May-15 05-Aug-15
MM2-1305-PT-82-E-LA-00001-1
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IDC 7 05-May-15* 12-May-15
MM2-1305-PT-82-E-LA-00001-2
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFR 24 13-May-15 09-Jun-15
MM2-1305-PT-82-E-LA-00001-3
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFD 0 10-Jun-15 10-Jun-15
MM2-1305-PT-82-E-LA-00001-4
MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFC 49 10-Jun-15 05-Aug-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 57 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-82-E-LA-00002
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories
77 11-May-15 07-Aug-15
MM2-1305-PT-82-E-LA-00002-1
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IDC
7 11-May-15* 18-May-15
MM2-1305-PT-82-E-LA-00002-2
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFR
23 19-May-15 13-Jun-15
MM2-1305-PT-82-E-LA-00002-3
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFD
0 15-Jun-15 15-Jun-15
MM2-1305-PT-82-E-LA-00002-4
MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFC
47 15-Jun-15 07-Aug-15
MM2-1305-PT-82-E-LA-00003
MM1 & MM2 - Electrical Material Take-Off - Cables 62 18-May-15 28-Jul-15
MM2-1305-PT-82-E-LA-00003-1
MM1 & MM2 - Electrical Material Take-Off - Cables-IDC 7 18-May-15* 25-May-15
MM2-1305-PT-82-E-LA-00003-2
MM1 & MM2 - Electrical Material Take-Off - Cables-IFR 8 26-May-15 03-Jun-15
MM2-1305-PT-82-E-LA-00003-3
MM1 & MM2 - Electrical Material Take-Off - Cables-IFD 0 04-Jun-15 04-Jun-15
MM2-1305-PT-82-E-LA-00003-4
MM1 & MM2 - Electrical Material Take-Off - Cables-IFC 47 04-Jun-15 28-Jul-15
MM2-1305-PT-82-E-LA-00004
MM1 & MM2 - Electrical Material Take-Off - Cable Glands 77 21-May-15 18-Aug-15
MM2-1305-PT-82-E-LA-00004-1
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IDC 7 21-May-15* 28-May-15
MM2-1305-PT-82-E-LA-00004-2
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFR 22 29-May-15 23-Jun-15
MM2-1305-PT-82-E-LA-00004-3
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFD 0 24-Jun-15 24-Jun-15
MM2-1305-PT-82-E-LA-00004-4
MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFC 48 24-Jun-15 18-Aug-15
MM2-1305-PT-82-E-LA-00005
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes 83 02-May-15 06-Aug-15
MM2-1305-PT-82-E-LA-00005-1
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IDC 6 02-May-15* 08-May-15
MM2-1305-PT-82-E-LA-00005-2
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFR 31 09-May-15 13-Jun-15
MM2-1305-PT-82-E-LA-00005-3
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFD 0 15-Jun-15 15-Jun-15
MM2-1305-PT-82-E-LA-00005-4
MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFC 46 15-Jun-15 06-Aug-15
MM2-1305-PT-82-E-LA-00006
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials 94 21-May-15 08-Sep-15
MM2-1305-PT-82-E-LA-00006-1
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IDC 7 21-May-15* 28-May-15
MM2-1305-PT-82-E-LA-00006-2
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFR 38 29-May-15 11-Jul-15
MM2-1305-PT-82-E-LA-00006-3
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFD 0 13-Jul-15 13-Jul-15
MM2-1305-PT-82-E-LA-00006-4
MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFC 49 13-Jul-15 08-Sep-15
MM2-1305-PT-82-E-LA-00007
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials 52 15-May-15 14-Jul-15
MM2-1305-PT-82-E-LA-00007-1
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IDC 7 15-May-15* 22-May-15
MM2-1305-PT-82-E-LA-00007-2
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFR 10 23-May-15 03-Jun-15
MM2-1305-PT-82-E-LA-00007-3
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFD 0 04-Jun-15 04-Jun-15
MM2-1305-PT-82-E-LA-00007-4
MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFC 35 04-Jun-15 14-Jul-15
MM2-1305-PT-00-I-LA-00009
MM1 & MM2 - Ex Equipment Register 68 11-Jun-15 28-Aug-15
MM2-1305-PT-00-I-LA-00009-1
MM1 & MM2 - Ex Equipment Register-IDC 27 11-Jun-15* 11-Jul-15
MM2-1305-PT-00-I-LA-00009-2
MM1 & MM2 - Ex Equipment Register-IFR 12 13-Jul-15 25-Jul-15
MM2-1305-PT-00-I-LA-00009-3
MM1 & MM2 - Ex Equipment Register-IFD 12 27-Jul-15 08-Aug-15
MM2-1305-PT-00-I-LA-00009-4
MM1 & MM2 - Ex Equipment Register-IFC 17 10-Aug-15 28-Aug-15
MM2-1305-PT-00-I-SA-00001
MM1 & MM2 - Instrument Control and Shutdown Philosophy 64 10-Jun-15 22-Aug-15
MM2-1305-PT-00-I-SA-00001-1
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IDC 27 10-Jun-15* 10-Jul-15
MM2-1305-PT-00-I-SA-00001-2
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFR 8 11-Jul-15 20-Jul-15
MM2-1305-PT-00-I-SA-00001-3
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFD 13 21-Jul-15 04-Aug-15
MM2-1305-PT-00-I-SA-00001-4
MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFC 16 05-Aug-15 22-Aug-15
MM2-1305-PT-00-I-XR-00001
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix 68 15-Jun-15 01-Sep-15
MM2-1305-PT-00-I-XR-00001-1
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IDC 27 15-Jun-15* 15-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 58 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-I-XR-00001-2
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFR 13 16-Jul-15 30-Jul-15
MM2-1305-PT-00-I-XR-00001-3
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFD 13 31-Jul-15 14-Aug-15
MM2-1305-PT-00-I-XR-00001-4
MM1 & MM2 - Alarm & Shutdown Cause & Effect Matrix -IFC 15 15-Aug-15 01-Sep-15
MM2-1305-PT-00-I-XT-00001
MM1 & MM2 - Instrument Cable Block Diagram 44 13-Apr-15 05-Jun-15
MM2-1305-PT-00-I-XT-00001-1
MM1 & MM2 - Instrument Cable Block Diagram-IDC 20 13-Apr-15* 08-May-15
MM2-1305-PT-00-I-XT-00001-2
MM1 & MM2 - Instrument Cable Block Diagram-IFR 6 09-May-15 15-May-15
MM2-1305-PT-00-I-XT-00001-3
MM1 & MM2 - Instrument Cable Block Diagram-IFD 0 16-May-15 16-May-15
MM2-1305-PT-00-I-XT-00001-4
MM1 & MM2 - Instrument Cable Block Diagram-IFC 18 16-May-15 05-Jun-15
MM2-1305-PT-00-I-XT-00003
MM2 - Instrument Interconnection Wiring diagram 49 13-Apr-15 11-Jun-15
MM2-1305-PT-00-I-XT-00003-1
MM2 - Instrument Interconnection Wiring diagram -IDC 20 13-Apr-15* 08-May-15
MM2-1305-PT-00-I-XT-00003-2
MM2 - Instrument Interconnection Wiring diagram -IFR 12 09-May-15 22-May-15
MM2-1305-PT-00-I-XT-00003-3
MM2 - Instrument Interconnection Wiring diagram -IFD 0 23-May-15 23-May-15
MM2-1305-PT-00-I-XT-00003-4
MM2 - Instrument Interconnection Wiring diagram -IFC 17 23-May-15 11-Jun-15
MM2-1305-PT-00-I-XQ-00002
MM2- Instrument Hookup Drawing 47 06-Apr-15 02-Jun-15
MM2-1305-PT-00-I-XQ-00002-1
MM2- Instrument Hookup Drawing-IDC 14 06-Apr-15* 21-Apr-15
MM2-1305-PT-00-I-XQ-00002-2
MM2- Instrument Hookup Drawing-IFR 15 22-Apr-15 12-May-15
MM2-1305-PT-00-I-XQ-00002-3
MM2- Instrument Hookup Drawing-IFD 0 13-May-15 13-May-15
MM2-1305-PT-00-I-XQ-00002-4
MM2- Instrument Hookup Drawing-IFC 18 13-May-15 02-Jun-15
MM2-1305-PT-00-I-XX-00002
MM2- Instrument Support Details 41 04-May-15 19-Jun-15
MM2-1305-PT-00-I-XX-00002-1
MM2- Instrument Support Details-IDC 13 04-May-15* 18-May-15
MM2-1305-PT-00-I-XX-00002-2
MM2- Instrument Support Details-IFR 12 19-May-15 01-Jun-15
MM2-1305-PT-00-I-XX-00002-3
MM2- Instrument Support Details-IFD 0 02-Jun-15 02-Jun-15
MM2-1305-PT-00-I-XX-00002-4
MM2- Instrument Support Details-IFC 16 02-Jun-15 19-Jun-15
MM2-1305-PT-00-I-XX-00004
MM2 - Instrument Cable Tray Ladder Support Details 36 20-May-15 30-Jun-15
MM2-1305-PT-00-I-XX-00004-1
MM2 - Instrument Cable Tray Ladder Support Details-IDC 13 20-May-15* 03-Jun-15
MM2-1305-PT-00-I-XX-00004-2
MM2 - Instrument Cable Tray Ladder Support Details-IFR 6 04-Jun-15 10-Jun-15
MM2-1305-PT-00-I-XX-00004-3
MM2 - Instrument Cable Tray Ladder Support Details-IFD 0 11-Jun-15 11-Jun-15
MM2-1305-PT-00-I-XX-00004-4
MM2 - Instrument Cable Tray Ladder Support Details-IFC 17 11-Jun-15 30-Jun-15
MM2-1305-PT-00-I-XE-00002
MM2 - Instrument cable and cable tray/ ladder routing layout 59 04-May-15 10-Jul-15
MM2-1305-PT-00-I-XE-00002-1
MM2 - Instrument cable and cable tray/ ladder routing layout-IDC 12 04-May-15* 16-May-15
MM2-1305-PT-00-I-XE-00002-2
MM2 - Instrument cable and cable tray/ ladder routing layout-IFR 12 18-May-15 30-May-15
MM2-1305-PT-00-I-XE-00002-3
MM2 - Instrument cable and cable tray/ ladder routing layout-IFD 0 01-Jun-15 01-Jun-15
MM2-1305-PT-00-I-XE-00002-4
MM2 - Instrument cable and cable tray/ ladder routing layout-IFC 35 01-Jun-15 10-Jul-15
MM2-1305-PT-00-I-XE-00004
MM2 - Instrument tubing and tubing tray routing layout 53 02-May-15 02-Jul-15
MM2-1305-PT-00-I-XE-00004-1
MM2 - Instrument tubing and tubing tray routing layout-IDC 13 02-May-15* 16-May-15
MM2-1305-PT-00-I-XE-00004-2
MM2 - Instrument tubing and tubing tray routing layout-IFR 6 18-May-15 23-May-15
MM2-1305-PT-00-I-XE-00004-3
MM2 - Instrument tubing and tubing tray routing layout-IFD 0 25-May-15 25-May-15
MM2-1305-PT-00-I-XE-00004-4
MM2 - Instrument tubing and tubing tray routing layout-IFC 34 25-May-15 02-Jul-15
MM2-1305-PT-00-I-XE-00006
MM2- Instrument and JB location layout 43 20-Apr-15 11-Jun-15
MM2-1305-PT-00-I-XE-00006-1
MM2- Instrument and JB location layout-IDC 24 20-Apr-15* 20-May-15
MM2-1305-PT-00-I-XE-00006-2
MM2- Instrument and JB location layout-IFR 6 21-May-15 27-May-15
MM2-1305-PT-00-I-XE-00006-3
MM2- Instrument and JB location layout-IFD 0 28-May-15 28-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 59 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-I-XE-00006-4
MM2- Instrument and JB location layout-IFC 13 28-May-15 11-Jun-15
MM2-1305-PT-00-I-XE-00008
MM2- Fire & Gas layout 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-I-XE-00008-1
MM2- Fire & Gas layout-IDC 16 13-Mar-15* 31-Mar-15
MM2-1305-PT-00-I-XE-00008-2
MM2- Fire & Gas layout-IFR 49 01-Apr-15 30-May-15
MM2-1305-PT-00-I-XE-00008-3
MM2- Fire & Gas layout-IFD 0 01-Jun-15 01-Jun-15
MM2-1305-PT-00-I-XE-00008-4
MM2- Fire & Gas layout-IFC 17 01-Jun-15 19-Jun-15
MM2-1305-PT-00-I-XE-00010
MM2 - PAGA Equipment Location Layout 101 13-Mar-15 11-Jul-15
MM2-1305-PT-00-I-XE-00010-1
MM2 - PAGA Equipment Location Layout-IDC 35 13-Mar-15* 22-Apr-15
MM2-1305-PT-00-I-XE-00010-2
MM2 - PAGA Equipment Location Layout-IFR 48 23-Apr-15 20-Jun-15
MM2-1305-PT-00-I-XE-00010-3
MM2 - PAGA Equipment Location Layout-IFD 0 22-Jun-15 22-Jun-15
MM2-1305-PT-00-I-XE-00010-4
MM2 - PAGA Equipment Location Layout-IFC 18 22-Jun-15 11-Jul-15
MM2-1305-PT-00-I-LA-00002
MM2 - Instrument I/O LIST 51 20-Apr-15 20-Jun-15
MM2-1305-PT-00-I-LA-00002-1
MM2 - Instrument I/O LIST-IDC 16 20-Apr-15* 11-May-15
MM2-1305-PT-00-I-LA-00002-2
MM2 - Instrument I/O LIST-IFR 6 12-May-15 18-May-15
MM2-1305-PT-00-I-LA-00002-3
MM2 - Instrument I/O LIST-IFD 13 19-May-15 02-Jun-15
MM2-1305-PT-00-I-LA-00002-4
MM2 - Instrument I/O LIST-IFC 16 03-Jun-15 20-Jun-15
MM2-1305-PT-00-I-LA-00004
MM2 - Instrument INDEX 51 20-Apr-15 20-Jun-15
MM2-1305-PT-00-I-LA-00004-1
MM2 - Instrument INDEX-IDC 16 20-Apr-15* 11-May-15
MM2-1305-PT-00-I-LA-00004-2
MM2 - Instrument INDEX-IFR 6 12-May-15 18-May-15
MM2-1305-PT-00-I-LA-00004-3
MM2 - Instrument INDEX-IFD 13 19-May-15 02-Jun-15
MM2-1305-PT-00-I-LA-00004-4
MM2 - Instrument INDEX-IFC 16 03-Jun-15 20-Jun-15
MM2-1305-PT-00-I-LA-00006
MM2 - Instrument CABLE SCHEDULE 40 21-Apr-15 09-Jun-15
MM2-1305-PT-00-I-LA-00006-1
MM2 - Instrument CABLE SCHEDULE-IDC 10 21-Apr-15* 05-May-15
MM2-1305-PT-00-I-LA-00006-2
MM2 - Instrument CABLE SCHEDULE-IFR 6 06-May-15 12-May-15
MM2-1305-PT-00-I-LA-00006-3
MM2 - Instrument CABLE SCHEDULE-IFD 0 13-May-15 13-May-15
MM2-1305-PT-00-I-LA-00006-4
MM2 - Instrument CABLE SCHEDULE-IFC 24 13-May-15 09-Jun-15
MM2-1305-PT-00-I-LA-00008
MM2 - Instrument TUBING SCHEDULE 58 22-Apr-15 01-Jul-15
MM2-1305-PT-00-I-LA-00008-1
MM2 - Instrument TUBING SCHEDULE-IDC 22 22-Apr-15* 20-May-15
MM2-1305-PT-00-I-LA-00008-2
MM2 - Instrument TUBING SCHEDULE-IFR 12 21-May-15 03-Jun-15
MM2-1305-PT-00-I-LA-00008-3
MM2 - Instrument TUBING SCHEDULE-IFD 0 04-Jun-15 04-Jun-15
MM2-1305-PT-00-I-LA-00008-4
MM2 - Instrument TUBING SCHEDULE-IFC 24 04-Jun-15 01-Jul-15
MM2-1305-PT-00-I-RA-00001
MM1 & MM2 - PSV Sizing Calculation Report 45 22-Apr-15 16-Jun-15
MM2-1305-PT-00-I-RA-00001-1
MM1 & MM2 - PSV Sizing Calculation Report-IDC 10 22-Apr-15* 06-May-15
MM2-1305-PT-00-I-RA-00001-2
MM1 & MM2 - PSV Sizing Calculation Report-IFR 6 07-May-15 13-May-15
MM2-1305-PT-00-I-RA-00001-3
MM1 & MM2 - PSV Sizing Calculation Report-IFD 13 14-May-15 28-May-15
MM2-1305-PT-00-I-RA-00001-4
MM1 & MM2 - PSV Sizing Calculation Report-IFC 16 29-May-15 16-Jun-15
MM2-1305-PT-00-I-RA-00002
MM1 & MM2 - Choke Valve Sizing Calculation Report 45 23-Apr-15 17-Jun-15
MM2-1305-PT-00-I-RA-00002-1
MM1 & MM2 - Choke Valve Sizing Calculation Report-IDC 10 23-Apr-15* 07-May-15
MM2-1305-PT-00-I-RA-00002-2
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFR 6 08-May-15 14-May-15
MM2-1305-PT-00-I-RA-00002-3
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFD 13 15-May-15 29-May-15
MM2-1305-PT-00-I-RA-00002-4
MM1 & MM2 - Choke Valve Sizing Calculation Report-IFC 16 30-May-15 17-Jun-15
MM2-1305-PT-00-I-RA-00003
MM1 & MM2 - FE/RO Sizing Calculation Report 45 24-Apr-15 18-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 60 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-I-RA-00003-1
MM1 & MM2 - FE/RO Sizing Calculation Report-IDC 10 24-Apr-15* 08-May-15
MM2-1305-PT-00-I-RA-00003-2
MM1 & MM2 - FE/RO Sizing Calculation Report-IFR 6 09-May-15 15-May-15
MM2-1305-PT-00-I-RA-00003-3
MM1 & MM2 - FE/RO Sizing Calculation Report-IFD 13 16-May-15 30-May-15
MM2-1305-PT-00-I-RA-00003-4
MM1 & MM2 - FE/RO Sizing Calculation Report-IFC 16 01-Jun-15 18-Jun-15
MM2-1305-PT-00-I-RA-00004
MM1 & MM2 - Instrument utility/ power consumption calculation report 60 25-May-15 01-Aug-15
MM2-1305-PT-00-I-RA-00004-1
MM1 & MM2 - Instrument utility/ power consumption calculation report-IDC 25 25-May-15* 22-Jun-15
MM2-1305-PT-00-I-RA-00004-2
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFR 6 23-Jun-15 29-Jun-15
MM2-1305-PT-00-I-RA-00004-3
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFD 13 30-Jun-15 14-Jul-15
MM2-1305-PT-00-I-RA-00004-4
MM1 & MM2 - Instrument utility/ power consumption calculation report-IFC 16 15-Jul-15 01-Aug-15
MM2-1305-PT-00-I-DS-00001
MM1 & MM2 - Instrument Datasheet for On-Off valves 75 13-Mar-15 11-Jun-15
MM2-1305-PT-00-I-DS-00001-1
MM1 & MM2 - Instrument Datasheet for On-Off valves-IDC 20 13-Mar-15* 04-Apr-15
MM2-1305-PT-00-I-DS-00001-2
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFR 6 06-Apr-15 11-Apr-15
MM2-1305-PT-00-I-DS-00001-3
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFD 0 13-Apr-15 13-Apr-15
MM2-1305-PT-00-I-DS-00001-4
MM1 & MM2 - Instrument Datasheet for On-Off valves-IFC 49 13-Apr-15 11-Jun-15
MM2-1305-PT-00-I-DS-00002
MM1 & MM2 - Instrument Datasheet for Motor Operated valves 69 13-Mar-15 04-Jun-15
MM2-1305-PT-00-I-DS-00002-1
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IDC 20 13-Mar-15* 04-Apr-15
MM2-1305-PT-00-I-DS-00002-2
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFR 2 06-Apr-15 07-Apr-15
MM2-1305-PT-00-I-DS-00002-3
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFD 0 08-Apr-15 08-Apr-15
MM2-1305-PT-00-I-DS-00002-4
MM1 & MM2 - Instrument Datasheet for Motor Operated valves-IFC 47 08-Apr-15 04-Jun-15
MM2-1305-PT-00-I-DS-00003
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves 87 13-Mar-15 25-Jun-15
MM2-1305-PT-00-I-DS-00003-1
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IDC 20 13-Mar-15* 04-Apr-15
MM2-1305-PT-00-I-DS-00003-2
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFR 18 06-Apr-15 25-Apr-15
MM2-1305-PT-00-I-DS-00003-3
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFD 0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-I-DS-00003-4
MM1 & MM2 - Instrument Datasheet for Pressure Safety valves-IFC 49 27-Apr-15 25-Jun-15
MM2-1305-PT-00-I-DS-00004
MM1 & MM2 - Instrument Datasheet for Choke valve 89 13-Mar-15 27-Jun-15
MM2-1305-PT-00-I-DS-00004-1
MM1 & MM2 - Instrument Datasheet for Choke valve-IDC 20 13-Mar-15* 04-Apr-15
MM2-1305-PT-00-I-DS-00004-2
MM1 & MM2 - Instrument Datasheet for Choke valve-IFR 19 06-Apr-15 27-Apr-15
MM2-1305-PT-00-I-DS-00004-3
MM1 & MM2 - Instrument Datasheet for Choke valve-IFD 0 29-Apr-15 29-Apr-15
MM2-1305-PT-00-I-DS-00004-4
MM1 & MM2 - Instrument Datasheet for Choke valve-IFC 50 29-Apr-15 27-Jun-15
MM2-1305-PT-00-I-DS-00005
MM1 & MM2 - Instrument Datasheet for H2S Analyser 89 13-Mar-15 27-Jun-15
MM2-1305-PT-00-I-DS-00005-1
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IDC 22 13-Mar-15* 07-Apr-15
MM2-1305-PT-00-I-DS-00005-2
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFR 12 08-Apr-15 21-Apr-15
MM2-1305-PT-00-I-DS-00005-3
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFD 0 22-Apr-15 22-Apr-15
MM2-1305-PT-00-I-DS-00005-4
MM1 & MM2 - Instrument Datasheet for H2S Analyser-IFC 55 22-Apr-15 27-Jun-15
MM2-1305-PT-00-I-DS-00006
MM1 & MM2 - Instrument Datasheet for Pig Signaller 105 13-Mar-15 16-Jul-15
MM2-1305-PT-00-I-DS-00006-1
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IDC 47 13-Mar-15* 09-May-15
MM2-1305-PT-00-I-DS-00006-2
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFR 12 11-May-15 23-May-15
MM2-1305-PT-00-I-DS-00006-3
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFD 0 25-May-15 25-May-15
MM2-1305-PT-00-I-DS-00006-4
MM1 & MM2 - Instrument Datasheet for Pig Signaller-IFC 46 25-May-15 16-Jul-15
MM2-1305-PT-00-I-DS-00007
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter 125 13-Mar-15 08-Aug-15
MM2-1305-PT-00-I-DS-00007-1
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IDC 59 13-Mar-15* 23-May-15
MM2-1305-PT-00-I-DS-00007-2
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFR 12 25-May-15 06-Jun-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 61 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-I-DS-00007-3
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-I-DS-00007-4
MM1 & MM2 - Instrument Datasheet for Pressure Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM2-1305-PT-00-I-DS-00008
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter 125 13-Mar-15 08-Aug-15
MM2-1305-PT-00-I-DS-00008-1
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IDC 59 13-Mar-15* 23-May-15
MM2-1305-PT-00-I-DS-00008-2
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFR 12 25-May-15 06-Jun-15
MM2-1305-PT-00-I-DS-00008-3
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-I-DS-00008-4
MM1 & MM2 - Instrument Datasheet for Temperature Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM2-1305-PT-00-I-DS-00009
MM1 & MM2 - Instrument Datasheet for Flow Transmitter 125 13-Mar-15 08-Aug-15
MM2-1305-PT-00-I-DS-00009-1
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IDC 59 13-Mar-15* 23-May-15
MM2-1305-PT-00-I-DS-00009-2
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFR 12 25-May-15 06-Jun-15
MM2-1305-PT-00-I-DS-00009-3
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-I-DS-00009-4
MM1 & MM2 - Instrument Datasheet for Flow Transmitter-IFC 54 08-Jun-15 08-Aug-15
MM2-1305-PT-00-I-DS-00010
MM1 & MM2 - Instrument Datasheet for Pressure Gauge 111 13-Mar-15 23-Jul-15
MM2-1305-PT-00-I-DS-00010-1
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IDC 51 13-Mar-15* 14-May-15
MM2-1305-PT-00-I-DS-00010-2
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFR 12 15-May-15 28-May-15
MM2-1305-PT-00-I-DS-00010-3
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFD 0 29-May-15 29-May-15
MM2-1305-PT-00-I-DS-00010-4
MM1 & MM2 - Instrument Datasheet for Pressure Gauge-IFC 48 29-May-15 23-Jul-15
MM2-1305-PT-00-I-DS-00011
MM1 & MM2 - Instrument Datasheet for Temperature Gauge 111 13-Mar-15 23-Jul-15
MM2-1305-PT-00-I-DS-00011-1
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IDC 51 13-Mar-15* 14-May-15
MM2-1305-PT-00-I-DS-00011-2
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFR 12 15-May-15 28-May-15
MM2-1305-PT-00-I-DS-00011-3
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFD 0 29-May-15 29-May-15
MM2-1305-PT-00-I-DS-00011-4
MM1 & MM2 - Instrument Datasheet for Temperature Gauge-IFC 48 29-May-15 23-Jul-15
MM2-1305-PT-00-I-DS-00012
MM1 & MM2 - Instrument Datasheet for Restriction Orifice 123 13-Mar-15 06-Aug-15
MM2-1305-PT-00-I-DS-00012-1
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IDC 57 13-Mar-15* 21-May-15
MM2-1305-PT-00-I-DS-00012-2
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFR 12 22-May-15 04-Jun-15
MM2-1305-PT-00-I-DS-00012-3
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFD 0 05-Jun-15 05-Jun-15
MM2-1305-PT-00-I-DS-00012-4
MM1 & MM2 - Instrument Datasheet for Restriction Orifice-IFC 54 05-Jun-15 06-Aug-15
MM2-1305-PT-00-I-DS-00013
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges 123 13-Mar-15 06-Aug-15
MM2-1305-PT-00-I-DS-00013-1
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IDC 57 13-Mar-15* 21-May-15
MM2-1305-PT-00-I-DS-00013-2
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFR 12 22-May-15 04-Jun-15
MM2-1305-PT-00-I-DS-00013-3
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFD 0 05-Jun-15 05-Jun-15
MM2-1305-PT-00-I-DS-00013-4
MM1 & MM2 - Instrument Datasheet for Orifice and Flanges-IFC 54 05-Jun-15 06-Aug-15
MM2-1305-PT-00-I-DS-00014
MM1 & MM2 - Instrument Datasheet for Junction Box 116 20-Mar-15 05-Aug-15
MM2-1305-PT-00-I-DS-00014-1
MM1 & MM2 - Instrument Datasheet for Junction Box-IDC 53 20-Mar-15* 23-May-15
MM2-1305-PT-00-I-DS-00014-2
MM1 & MM2 - Instrument Datasheet for Junction Box-IFR 12 25-May-15 06-Jun-15
MM2-1305-PT-00-I-DS-00014-3
MM1 & MM2 - Instrument Datasheet for Junction Box-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-I-DS-00014-4
MM1 & MM2 - Instrument Datasheet for Junction Box-IFC 51 08-Jun-15 05-Aug-15
MM2-1305-PT-00-I-LA-00015
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves 113 20-Mar-15 01-Aug-15
MM2-1305-PT-00-I-LA-00015-1
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IDC 53 20-Mar-15* 23-May-15
MM2-1305-PT-00-I-LA-00015-2
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFR 12 25-May-15 06-Jun-15
MM2-1305-PT-00-I-LA-00015-3
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFD 0 08-Jun-15 08-Jun-15
MM2-1305-PT-00-I-LA-00015-4
MM1 & MM2 - Instrument MTO for Tubing, Fitting and Valves-IFC 48 08-Jun-15 01-Aug-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 62 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-I-LA-00016
MM1 & MM2 - Instrument MTO for Instrument Steel Support 97 20-Mar-15 14-Jul-15
MM2-1305-PT-00-I-LA-00016-1
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IDC 55 20-Mar-15* 26-May-15
MM2-1305-PT-00-I-LA-00016-2
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFR 12 27-May-15 09-Jun-15
MM2-1305-PT-00-I-LA-00016-3
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFD 0 10-Jun-15 10-Jun-15
MM2-1305-PT-00-I-LA-00016-4
MM1 & MM2 - Instrument MTO for Instrument Steel Support-IFC 30 10-Jun-15 14-Jul-15
MM2-1305-PT-00-I-LA-00017
MM1 & MM2 - Instrument MTO for Cable 67 12-May-15 28-Jul-15
MM2-1305-PT-00-I-LA-00017-1
MM1 & MM2 - Instrument MTO for Cable-IDC 14 12-May-15* 27-May-15
MM2-1305-PT-00-I-LA-00017-2
MM1 & MM2 - Instrument MTO for Cable-IFR 12 28-May-15 10-Jun-15
MM2-1305-PT-00-I-LA-00017-3
MM1 & MM2 - Instrument MTO for Cable-IFD 0 11-Jun-15 11-Jun-15
MM2-1305-PT-00-I-LA-00017-4
MM1 & MM2 - Instrument MTO for Cable-IFC 41 11-Jun-15 28-Jul-15
MM2-1305-PT-00-I-LA-00018
MM1 & MM2 - Instrument MTO for Cable Gland 84 13-May-15 18-Aug-15
MM2-1305-PT-00-I-LA-00018-1
MM1 & MM2 - Instrument MTO for Cable Gland-IDC 14 13-May-15* 28-May-15
MM2-1305-PT-00-I-LA-00018-2
MM1 & MM2 - Instrument MTO for Cable Gland-IFR 12 29-May-15 11-Jun-15
MM2-1305-PT-00-I-LA-00018-3
MM1 & MM2 - Instrument MTO for Cable Gland-IFD 0 12-Jun-15 12-Jun-15
MM2-1305-PT-00-I-LA-00018-4
MM1 & MM2 - Instrument MTO for Cable Gland-IFC 58 12-Jun-15 18-Aug-15
MM2-1305-PT-00-I-LA-00019
MM1 & MM2 - Instrument MTO for Miscellaneous Materials 76 11-Jun-15 08-Sep-15
MM2-1305-PT-00-I-LA-00019-1
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IDC 9 11-Jun-15* 20-Jun-15
MM2-1305-PT-00-I-LA-00019-2
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFR 12 22-Jun-15 04-Jul-15
MM2-1305-PT-00-I-LA-00019-3
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFD 0 06-Jul-15 06-Jul-15
MM2-1305-PT-00-I-LA-00019-4
MM1 & MM2 - Instrument MTO for Miscellaneous Materials-IFC 55 06-Jul-15 08-Sep-15
MM2-1305-PT-00-I-LA-00020
MM1 & MM2 - Instrument MTO for Cable Tray/ladder 60 01-Jun-15 08-Aug-15
MM2-1305-PT-00-I-LA-00020-1
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IDC 6 01-Jun-15* 06-Jun-15
MM2-1305-PT-00-I-LA-00020-2
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFR 12 08-Jun-15 20-Jun-15
MM2-1305-PT-00-I-LA-00020-3
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFD 0 22-Jun-15 22-Jun-15
MM2-1305-PT-00-I-LA-00020-4
MM1 & MM2 - Instrument MTO for Cable Tray/ladder-IFC 42 22-Jun-15 08-Aug-15
MM2-14480 TR/MTO for ON-OFF Valve 1 11-Apr-15 11-Apr-15
MM2-14500 TR/MTO for Choke Valve 1 16-Apr-15 16-Apr-15
MM2-14520 TR/MTO for Motor Operated Valve 1 07-Apr-15 07-Apr-15
MM2-14540 TR/MTO for Pig Signaller 1 18-May-15 18-May-15
MM2-14560 TR/MTO for Tubing & Fitting 1 10-Jun-15 10-Jun-15
MM2-14580 TR/MTO for Pressure Safety valves 1 27-Apr-15 27-Apr-15
MM2-14600 TR/MTO for ElectronicTransmitter (PT/TT/LT/FT) 1 16-Jun-15 16-Jun-15
MM2-14620 TR/MTO for Gauges (PG/TG/LG) 1 05-Jun-15 05-Jun-15
MM2-14640 TR/MTO for Orifice Plate/Restriction Orifice 1 20-Jun-15 20-Jun-15
MM2-14660 TR/MTO for H2S analyzer 1 29-Apr-15 29-Apr-15
MM2-14680 TR/MTO for Junction Box 1 21-Jun-15 21-Jun-15
MM2-14700 TR/MTO for E&I Cable 1 12-Jun-15 12-Jun-15
MM2-14720 TR/MTO for E&I Cable Gland 1 02-Jul-15 02-Jul-15
MM2-14740 TR/MTO for E&I Cable Tray & Ladder 1 10-Jun-15 10-Jun-15
MM2-14760 TR/MTO for Lighting Fixtures 1 19-Jun-15 19-Jun-15
MM2-14780 TR/MTO for E&I Steel Support 1 10-Jun-15 10-Jun-15
MM2-14800 TR/MTO for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 1 19-Jul-15 19-Jul-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 63 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-14820 TR/MTO for Heat Tracing system 1 19-Jun-15 19-Jun-15
MM2-14840 TR/MTO for MOV & Lighting distribution panel 1 19-Jun-15 19-Jun-15
MM2-14860 Prepare / Submit/ Approve E&I Shop Drawings 116 27-Oct-15 16-Mar-16
0.D.26.0000.MM2.B.R Mechanical/ Material Handling 261 13-Mar-15 15-Jan-16
0.D.26.0000.MM2.B.R.92 PTSC 261 13-Mar-15 15-Jan-16
MM2-1305-PT-00-R-RA-00001
MM1 & MM2 - Material Handling Study Report 44 27-Apr-15 19-Jun-15
MM2-1305-PT-00-R-RA-00001-1
MM1 & MM2 - Material Handling Study Report-IDC 7 27-Apr-15* 07-May-15
MM2-1305-PT-00-R-RA-00001-2
MM1 & MM2 - Material Handling Study Report-IFR 7 08-May-15 15-May-15
MM2-1305-PT-00-R-RA-00001-3
MM1 & MM2 - Material Handling Study Report-IFD 7 16-May-15 23-May-15
MM2-1305-PT-00-R-RA-00001-4
MM1 & MM2 - Material Handling Study Report-IFC 23 25-May-15 19-Jun-15
MM2-1305-PT-00-R-LA-00002
MM1 & MM2 - Equipment List 53 13-Mar-15 16-May-15
MM2-1305-PT-00-R-LA-00002-1
MM1 & MM2 - Equipment List-IDC 19 13-Mar-15* 03-Apr-15
MM2-1305-PT-00-R-LA-00002-2
MM1 & MM2 - Equipment List-IFR 7 04-Apr-15 11-Apr-15
MM2-1305-PT-00-R-LA-00002-3
MM1 & MM2 - Equipment List-IFD 7 13-Apr-15 20-Apr-15
MM2-1305-PT-00-R-LA-00002-4
MM1 & MM2 - Equipment List-IFC 20 21-Apr-15 16-May-15
MM2-1305-PT-00-R-DS-00001
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001 58 13-Mar-15 22-May-15
MM2-1305-PT-00-R-DS-00001-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IDC
25 13-Mar-15* 10-Apr-15
MM2-1305-PT-00-R-DS-00001-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFR6 11-Apr-15 17-Apr-15
MM2-1305-PT-00-R-DS-00001-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFD7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-DS-00001-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL001-IFC
20 27-Apr-15 22-May-15
MM2-1305-PT-00-R-DS-00002
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002 60 13-Mar-15 25-May-15
MM2-1305-PT-00-R-DS-00002-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IDC
27 13-Mar-15* 13-Apr-15
MM2-1305-PT-00-R-DS-00002-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFR6 14-Apr-15 20-Apr-15
MM2-1305-PT-00-R-DS-00002-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFD7 21-Apr-15 29-Apr-15
MM2-1305-PT-00-R-DS-00002-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL002-IFC
20 02-May-15 25-May-15
MM2-1305-PT-00-R-DS-00003
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003 58 13-Mar-15 22-May-15
MM2-1305-PT-00-R-DS-00003-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IDC
25 13-Mar-15* 10-Apr-15
MM2-1305-PT-00-R-DS-00003-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFR6 11-Apr-15 17-Apr-15
MM2-1305-PT-00-R-DS-00003-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFD7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-DS-00003-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL003-IFC
20 27-Apr-15 22-May-15
MM2-1305-PT-00-R-DS-00004
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004 60 13-Mar-15 25-May-15
MM2-1305-PT-00-R-DS-00004-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IDC
27 13-Mar-15* 13-Apr-15
MM2-1305-PT-00-R-DS-00004-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFR6 14-Apr-15 20-Apr-15
MM2-1305-PT-00-R-DS-00004-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFD7 21-Apr-15 29-Apr-15
MM2-1305-PT-00-R-DS-00004-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL004-IFC
20 02-May-15 25-May-15
MM2-1305-PT-00-R-DS-00005
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005 58 13-Mar-15 22-May-15
MM2-1305-PT-00-R-DS-00005-1
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IDC
25 13-Mar-15* 10-Apr-15
MM2-1305-PT-00-R-DS-00005-2
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFR6 11-Apr-15 17-Apr-15
MM2-1305-PT-00-R-DS-00005-3
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFD7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-DS-00005-4
MM1 & MM2 - Mechanical Datasheet Pig Launcher/receiver - 001900VL005-IFC
20 27-Apr-15 22-May-15
MM2-1305-PT-00-R-DS-00006
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007 60 13-Mar-15 25-May-15
MM2-1305-PT-00-R-DS-00006-1
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IDC
27 13-Mar-15* 13-Apr-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 64 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-R-DS-00006-2
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFR6 14-Apr-15 20-Apr-15
MM2-1305-PT-00-R-DS-00006-3
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFD7 21-Apr-15 29-Apr-15
MM2-1305-PT-00-R-DS-00006-4
MM1 & MM2 - Mechanical Datasheet Pig launcher/receiver - 001900VL007-IFC
20 02-May-15 25-May-15
MM2-1305-PT-00-R-XD-00001
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00001-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00001-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00001-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00001-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL001-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XD-00002
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00002-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00002-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00002-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00002-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL002-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XD-00003
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00003-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00003-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00003-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00003-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL003-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XD-00004
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00004-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00004-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00004-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00004-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL004-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XD-00005
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00005-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00005-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00005-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00005-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL005-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XD-00006
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007 82 13-Mar-15 19-Jun-15
MM2-1305-PT-00-R-XD-00006-1
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IDC
46 13-Mar-15* 08-May-15
MM2-1305-PT-00-R-XD-00006-2
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFR
6 09-May-15 15-May-15
MM2-1305-PT-00-R-XD-00006-3
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFD
0 16-May-15 16-May-15
MM2-1305-PT-00-R-XD-00006-4
MM1 & MM2 - General drawing for Pig Launchers/Receivers - 001900VL007-IFC
30 16-May-15 19-Jun-15
MM2-1305-PT-00-R-XS-00001
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00001-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00001-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00001-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFD0 25-May-15 25-May-15
MM2-1305-PT-00-R-XS-00001-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL001-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-XS-00002
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00002-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00002-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00002-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFD0 25-May-15 25-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 65 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-R-XS-00002-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL002-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-XS-00003
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00003-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00003-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00003-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFD0 25-May-15 25-May-15
MM2-1305-PT-00-R-XS-00003-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL003-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-XS-00004
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00004-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00004-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00004-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFD0 25-May-15 25-May-15
MM2-1305-PT-00-R-XS-00004-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL004-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-XS-00005
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00005-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00005-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00005-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFD0 25-May-15 25-May-15
MM2-1305-PT-00-R-XS-00005-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL005-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-XS-00006
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007 71 03-Apr-15 27-Jun-15
MM2-1305-PT-00-R-XS-00006-1
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IDC
34 03-Apr-15* 15-May-15
MM2-1305-PT-00-R-XS-00006-2
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFR7 16-May-15 23-May-15
MM2-1305-PT-00-R-XS-00006-3
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFD0 25-May-15 25-May-15
MM2-1305-PT-00-R-XS-00006-4
MM1 & MM2 - Detail drawing for Pig Launchers/Receivers - 001900VL007-IFC
30 25-May-15 27-Jun-15
MM2-1305-PT-00-R-CA-00001
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001
59 20-Mar-15 30-May-15
MM2-1305-PT-00-R-CA-00001-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00001-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00001-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00001-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL001-IFC
27 27-Apr-15 30-May-15
MM2-1305-PT-00-R-CA-00002
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002
59 20-Mar-15 30-May-15
MM2-1305-PT-00-R-CA-00002-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00002-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00002-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00002-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL002-IFC
27 27-Apr-15 30-May-15
MM2-1305-PT-00-R-CA-00003
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003
59 20-Mar-15 30-May-15
MM2-1305-PT-00-R-CA-00003-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00003-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00003-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00003-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL003-IFC
27 27-Apr-15 30-May-15
MM2-1305-PT-00-R-CA-00004
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004
59 20-Mar-15 30-May-15
MM2-1305-PT-00-R-CA-00004-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00004-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00004-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00004-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL004-IFC
27 27-Apr-15 30-May-15
MM2-1305-PT-00-R-CA-00005
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005
59 20-Mar-15 30-May-15

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 66 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-1305-PT-00-R-CA-00005-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00005-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00005-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00005-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL005-IFC
27 27-Apr-15 30-May-15
MM2-1305-PT-00-R-CA-00006
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL00759 20-Mar-15 30-May-15
MM2-1305-PT-00-R-CA-00006-1
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IDC
25 20-Mar-15* 17-Apr-15
MM2-1305-PT-00-R-CA-00006-2
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFR
7 18-Apr-15 25-Apr-15
MM2-1305-PT-00-R-CA-00006-3
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFD
0 27-Apr-15 27-Apr-15
MM2-1305-PT-00-R-CA-00006-4
MM1 & MM2 - Mechanical Calculation for Pig Lauchers/Receivers - 001900VL007-IFC
27 27-Apr-15 30-May-15
MM2-14440 TR/MTO for Pig Receivers (Q.O.C) 1 07-May-15 07-May-15
MM2-14460 Prepare / Submit/ Approve Mechanical Shop Drawings 84 09-Oct-15 15-Jan-16
0.D.26.0000.MM2.C Procurement 314 08-Apr-15 15-Feb-16
0.D.26.0000.MM2.C.N Structural 293 08-Apr-15 25-Jan-16
0.D.26.0000.MM2.C.N.92 PTSC 293 08-Apr-15 25-Jan-16
MM2-11180 RFQ/TBE/CBE/PO for Primary & Secondary Steel 39 08-Apr-15 16-May-15
MM2-11440 Delivery for Primary & Secondary Steel 119 17-May-15 12-Sep-15
MM2-11720 RFQ/TBE/CBE/PO for Tertiary Steel 35 10-Jun-15 14-Jul-15
MM2-11960 Delivery for Tertiary Steel 91 15-Jul-15 13-Oct-15
MM2-12180 RFQ/TBE/CBE/PO for Structural Miscellaneous 37 29-Jul-15 03-Sep-15
MM2-12400 Delivery for Structural Miscellaneous 77 04-Sep-15 19-Nov-15
MM2-12540 RFQ/TBE/CBE/PO for Gratings 37 10-Aug-15 15-Sep-15
MM2-12640 Delivery for Gratings 91 16-Sep-15 15-Dec-15
MM2-12720 RFQ/TBE/CBE/PO for SF and Grillage Material 37 11-Oct-15 16-Nov-15
MM2-12800 Delivery for SF and Grillage Material 70 17-Nov-15 25-Jan-16
0.D.26.0000.MM2.C.L Piping 311 11-Apr-15 15-Feb-16
0.D.26.0000.MM2.C.L.92 PTSC 311 11-Apr-15 15-Feb-16
MM2-10700 RFQ/TBE/CBE/PO for Piping Bulk 46 11-Apr-15 26-May-15
MM2-10940 Delivery for Piping Bulk 127 27-May-15 30-Sep-15
MM2-11200 RFQ/TBE/CBE/PO for Manual valves 58 30-Apr-15 26-Jun-15
MM2-11460 Delivery for Manual valves 182 27-Jun-15 25-Dec-15
MM2-11740 RFQ/TBE/CBE/PO for Barred Tee 47 29-Apr-15 14-Jun-15
MM2-11980 Delivery for Barred Tee 176 15-Jun-15 07-Dec-15
MM2-12200 RFQ/TBE/CBE/PO for Cuni fittings 53 09-May-15 30-Jun-15
MM2-12420 Delivery for Cuni fittings 108 01-Jul-15 16-Oct-15
MM2-12560 RFQ/TBE/CBE/PO for Corrosion, sand probe, sample connection, chemical connection…
41 19-May-15I 28-Jun-15
MM2-12660 Delivery for Corrosion, sand probe, sample connection, chemical connection131 29-Jun-15 06-Nov-15
MM2-12740 RFQ/TBE/CBE/PO for 3D Bend (free bare pipe to bending contractor) 48 31-May-15 17-Jul-15
MM2-12820 Delivery for 3D Bend (free bare pipe to bending contractor) 213 18-Jul-15 15-Feb-16
MM2-12860 RFQ/TBE/CBE/PO for Pipe Supports 39 07-Jun-15 15-Jul-15
MM2-12920 Delivery for Pipe Supports 85 16-Jul-15 08-Oct-15
MM2-12960 RFQ/TBE/CBE/PO for Quick Coupling 52 10-Jul-15 30-Aug-15
MM2-12980 Delivery for Quick Coupling 98 31-Aug-15 06-Dec-15
MM2-13040 RFQ/TBE/CBE/PO for Piping insulation 55 05-Jul-15 28-Aug-15
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 67 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-13080 Delivery for Piping insulation 99 29-Aug-15 05-Dec-15
MM2-13100 RFQ/TBE/CBE/PO for Bolt nut, gasket and other 53 07-Jul-15 28-Aug-15
MM2-13160 Delivery for Bolt nut, gasket and other 71 29-Aug-15 07-Nov-15
MM2-13200 RFQ/TBE/CBE/PO for Valve Inter-locks 56 17-Sep-15 11-Nov-15
MM2-13240 Delivery for Valve Inter-locks 70 12-Nov-15 20-Jan-16
0.D.26.0000.MM2.C.R Mechanical/ Material Handling 251 08-May-15 13-Jan-16
0.D.26.0000.MM2.C.R.91 Yinson 5 08-Jan-16 13-Jan-16
MM2-11780 ROS for Material Handling Equipment 0 08-Jan-16 ROS for Material Handling Equipment
MM2-12020 ROS for Safety equipment 0 13-Jan-16 ROS for Safety equipment
0.D.26.0000.MM2.C.R.92 PTSC 197 08-May-15 20-Nov-15
MM2-11000 RFQ/TBE/CBE/PO for Pig Receivers (Q.O.C) 48 08-May-15 24-Jun-15
MM2-11240 Delivery Pig Receivers (Q.O.C) 149 25-Jun-15 20-Nov-15
0.D.26.0000.MM2.C.1 E&I 296 08-Apr-15 28-Jan-16
0.D.26.0000.MM2.C.1.91 Yinson 0 04-Jan-16 04-Jan-16
MM2-10980 ROS for ICSS RIO panels 0 04-Jan-16 ROS for ICSS RIO panels
MM2-11220 ROS for F&G detectors 0 04-Jan-16 ROS for F&G detectors
MM2-11500 ROS for PA Systems 0 04-Jan-16 ROS for PA Systems
0.D.26.0000.MM2.C.1.92 PTSC 296 08-Apr-15 28-Jan-16
MM2-10960 RFQ/TBE/CBE/PO for Motor Operated Valve 58 08-Apr-15 04-Jun-15
MM2-11480 Delivery for Motor Operated Valve 238 05-Jun-15 28-Jan-16
MM2-11760 RFQ/TBE/CBE/PO for ON-OFF Valve 61 12-Apr-15 11-Jun-15
MM2-12000 Delivery for ON-OFF Valve 231 12-Jun-15 28-Jan-16
MM2-12220 RFQ/TBE/CBE/PO for H2S analyzer 52 30-Apr-15 20-Jun-15
MM2-12440 Delivery for H2S analyzer 189 21-Jun-15 26-Dec-15
MM2-13220 RFQ/TBE/CBE/PO for Lighting Fixtures 48 20-Jun-15 06-Aug-15
MM2-13260 Delivery for Lighting Fixtures 133 07-Aug-15 17-Dec-15
MM2-13320 RFQ/TBE/CBE/PO for Pressure Safety valves 59 28-Apr-15 25-Jun-15
MM2-13360 Delivery for Pressure Safety valves 217 26-Jun-15 28-Jan-16
MM2-13400 RFQ/TBE/CBE/PO for E&I Cable Tray & Ladder 48 11-Jun-15 28-Jul-15
MM2-13440 Delivery for E&I Cable Tray & Ladder 106 29-Jul-15 11-Nov-15
MM2-13480 RFQ/TBE/CBE/PO for Choke Valve 58 17-Apr-15 13-Jun-15
MM2-13520 Delivery for Choke Valve 229 14-Jun-15 28-Jan-16
MM2-13560 RFQ/TBE/CBE/PO for Junction Box 59 22-Jun-15 19-Aug-15
MM2-13600 Delivery for Junction Box 105 20-Aug-15 02-Dec-15
MM2-13620 RFQ/TBE/CBE/PO for Pig Signaller 53 19-May-15 10-Jul-15
MM2-13680 Delivery for Pig Signaller 167 11-Jul-15 24-Dec-15
MM2-13700 RFQ/TBE/CBE/PO for E&I Steel Support 35 11-Jun-15 15-Jul-15
MM2-13720 Delivery for E&I Steel Support 77 16-Jul-15 30-Sep-15
MM2-13740 RFQ/TBE/CBE/PO for ElectronicTransmitter (PT/TT/LT/FT) 48 17-Jun-15 03-Aug-15
MM2-13760 Delivery for ElectronicTransmitter (PT/TT/LT/FT) 147 04-Aug-15 28-Dec-15
MM2-13780 RFQ/TBE/CBE/PO for E&I Cable 62 13-Jun-15 13-Aug-15
MM2-13800 Delivery for E&I Cable 111 14-Aug-15 02-Dec-15
MM2-13820 RFQ/TBE/CBE/PO for Gauges (PG/TG/LG) 41 06-Jun-15 16-Jul-15
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 68 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-13840 Delivery for Gauges (PG/TG/LG) 161 17-Jul-15 24-Dec-15
MM2-13860 RFQ/TBE/CBE/PO for E&I Cable Gland 48 03-Jul-15 19-Aug-15
MM2-13880 Delivery for E&I Cable Gland 105 20-Aug-15 02-Dec-15
MM2-13900 RFQ/TBE/CBE/PO for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.)
52 20-Jul-15 09-Sep-15
MM2-13920 Delivery for E&I Miscellaneous (Earthing Bosses, Lug, cable tie, etc.) 84 10-Sep-15 02-Dec-15
MM2-13940 RFQ/TBE/CBE/PO for MOV & Lighting distribution panel 48 20-Jun-15 06-Aug-15
MM2-13960 Delivery for MOV & Lighting distribution panel 126 07-Aug-15 10-Dec-15
MM2-13980 RFQ/TBE/CBE/PO for Orifice Plate/Restriction Orifice 47 21-Jun-15 06-Aug-15
MM2-14000 Delivery for Orifice Plate/Restriction Orifice 140 07-Aug-15 24-Dec-15
MM2-14020 RFQ/TBE/CBE/PO for Tubing & Fitting 39 11-Jun-15 19-Jul-15
MM2-14040 Delivery for Tubing & Fitting 140 20-Jul-15 06-Dec-15
MM2-14060 RFQ/TBE/CBE/PO for Heat Tracing system 48 20-Jun-15 06-Aug-15
MM2-14080 Delivery for Heat Tracing system 126 07-Aug-15 10-Dec-15
0.D.26.0000.MM2.D Construction 194 18-Aug-15 01-Apr-16
0.D.26.0000.MM2.D.N Structural 182 18-Aug-15 24-Mar-16
0.D.26.0000.MM2.D.N.20 Blasting & Painting 154 21-Sep-15 24-Mar-16
MM2-10880 Blast, primer, tie coat for primary beam of Main Deck 10 21-Sep-15 01-Oct-15
MM2-12880 Blast, primer, tie coat for primary beam of Mezz deck 10 26-Sep-15 07-Oct-15
MM2-12900 Blast, primer, tie coat for secondary beam of main deck 10 08-Oct-15 19-Oct-15
MM2-12940 Blast, primer, tie coat for primary beam of upper deck 10 10-Oct-15 21-Oct-15
MM2-13000 Blast, primer, tie coat for secondary beam of Mezz deck 10 13-Oct-15 23-Oct-15
MM2-13020 Blast, primer, tie coat for deck plate of main deck 10 17-Oct-15 28-Oct-15
MM2-13060 Blast, primer, tie coat for secondary beam of upper deck 10 17-Oct-15 28-Oct-15
MM2-13120 Blast, primer, tie coat for deck plate of Mezz deck 10 22-Oct-15 02-Nov-15
MM2-13140 Blast, primer, tie coat for Legs and Braces for MD & Mezz Deck 14 26-Oct-15 10-Nov-15
MM2-13180 Blast, primer, tie coat for deck plate of upper deck 10 04-Nov-15 14-Nov-15
MM2-13280 Third coat for Mezz deck 10 20-Nov-15 01-Dec-15
MM2-13300 Third coat for main deck 10 21-Nov-15 02-Dec-15
MM2-13340 Third coat for upper deck 10 09-Dec-15 19-Dec-15
MM2-13380 Sweep blast and painting for handrail 10 16-Dec-15 26-Dec-15
MM2-13420 Blast to galvanizing hand rail 14 28-Dec-15 13-Jan-16
MM2-13460 Touch up for column and bracing 14 18-Jan-16 02-Feb-16
MM2-13500 Touch up for deck plate 14 03-Feb-16 24-Feb-16
MM2-13540 Final and touch up for main deck 14 02-Mar-16 17-Mar-16
MM2-13580 Final and touch up painting for upper deck 14 02-Mar-16 17-Mar-16
MM2-13640 Final and touch up painting for Mezz deck 14 02-Mar-16 17-Mar-16
MM2-13660 Cleaning and hand over MM2 14 09-Mar-16 24-Mar-16
0.D.26.0000.MM2.D.N.05 Pre-Fabrication 30 18-Aug-15 22-Sep-15
MM2-10820 Pre-fab & Assembly for LOSF 30 18-Aug-15 22-Sep-15
0.D.26.0000.MM2.D.N.10 Fabrication 134 17-Sep-15 26-Feb-16
0.D.26.0000.MM2.D.N.10.1 Main Deck 122 17-Sep-15 12-Feb-16
MM2-10840 Cut & prep Main Deck Primary Beams 10 17-Sep-15 28-Sep-15
MM2-11120 Fab Main Deck nodes & Joints 10 17-Sep-15 28-Sep-15
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 69 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-11360 Cut & prep Main Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15
MM2-11640 Fab Main Deck Plates 10 14-Oct-15 24-Oct-15
MM2-11900 Fab column and bracing 14 17-Oct-15 02-Nov-15
MM2-12160 Fab Handrail, landing & Sockets... 60 28-Nov-15 12-Feb-16
0.D.26.0000.MM2.D.N.10.2 Mezz Deck 126 21-Sep-15 20-Feb-16
MM2-11040 Cut & prep Mezz Deck Primary Beams 10 21-Sep-15 01-Oct-15
MM2-11280 Fab Mezz Deck nodes & Joints 10 21-Sep-15 01-Oct-15
MM2-11540 Cut & prep Mezz Deck Secondary Beams & Stiffeners 10 05-Oct-15 15-Oct-15
MM2-11820 Fab column and bracing 14 17-Oct-15 02-Nov-15
MM2-12060 Fab Mezz Deck Plates 10 19-Oct-15 29-Oct-15
MM2-12280 Fab Handrail, landing & Sockets... 60 07-Dec-15 20-Feb-16
0.D.26.0000.MM2.D.N.10.3 Upper Deck 120 03-Oct-15 26-Feb-16
MM2-10860 Cut & prep Upper Deck Primary Beams 10 03-Oct-15 14-Oct-15
MM2-11380 Fab Upper Deck nodes & Joints 10 03-Oct-15 14-Oct-15
MM2-11660 Cut & prep Upper Deck Secondary Beams & Stiffeners 10 09-Oct-15 20-Oct-15
MM2-11920 Fab Upper Deck Plates 14 26-Oct-15 10-Nov-15
MM2-12320 Fab Handrail, landing & Sockets... 60 12-Dec-15 26-Feb-16
0.D.26.0000.MM2.D.N.25 Installation 137 24-Sep-15 08-Mar-16
0.D.26.0000.MM2.D.N.25.1 Main Deck 133 24-Sep-15 03-Mar-16
MM2-10920 Assembly Main Deck Primary Beams & Deck nodes above LOSF 30 24-Sep-15 28-Oct-15
MM2-11160 Assembly Main Deck Secondary Beams & Stiffemers above LOSF 14 17-Oct-15 02-Nov-15
MM2-11420 Installation Main Deck Plate 16 03-Nov-15 20-Nov-15
MM2-11700 Installation Columns onto Main Deck (for Mezz Deck) 10 10-Nov-15 20-Nov-15
MM2-11940 Installation Bracings onto Main Deck 24 11-Dec-15 08-Jan-16
MM2-12480 Installation Remaining Legs onto Main Deck 8 12-Dec-15 21-Dec-15
MM2-12520 Installation Handrail, landing & Sockets, Gratings... 50 30-Dec-15 03-Mar-16
MM2-12620 Weighting for MM2 1 24-Feb-16 24-Feb-16
0.D.26.0000.MM2.D.N.25.2 Mezz Deck 127 01-Oct-15 03-Mar-16
MM2-11060 Assembly Mezz Deck Primary Beams & Deck nodes 21 01-Oct-15 24-Oct-15
MM2-11300 Assembly Mezz Deck Secondary Beams & Stiffemers 14 21-Oct-15 05-Nov-15
MM2-11560 Installation Mezz Deck Plate 12 06-Nov-15 19-Nov-15
MM2-11840 Install Mezz Deck onto Main Deck 6 03-Dec-15 09-Dec-15
MM2-12080 Installation Columns onto Mezz Deck 8 12-Dec-15 21-Dec-15
MM2-12300 Installation Bracings onto Mezz Deck 10 31-Dec-15 12-Jan-16
MM2-12460 Installation Handrail, landing & Sockets, Gratings... 45 06-Jan-16 03-Mar-16
0.D.26.0000.MM2.D.N.25.3 Upper Deck 117 17-Oct-15 08-Mar-16
MM2-10900 Assembly Upper Deck Primary Beams & Deck nodes 30 17-Oct-15 20-Nov-15
MM2-11140 Assembly Upper Deck Secondary Beams & Stiffemers 14 04-Nov-15 19-Nov-15
MM2-11400 Installation Upper Deck Plate 16 20-Nov-15 08-Dec-15
MM2-11680 Install Upper Deck onto Main Deck & Mezz Deck 6 22-Dec-15 28-Dec-15
MM2-12340 Installation Handrail, landing & Sockets, Gratings... 50 05-Jan-16 08-Mar-16
0.D.26.0000.MM2.D.R Mechanical/ Material Handling 112 26-Oct-15 10-Mar-16
0.D.26.0000.MM2.D.R.20 Blasting & Painting Equipment support 93 17-Nov-15 10-Mar-16
Date Revision Checked Approved
Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 70 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MM2-10800 Blast, primer for equipment support 21 17-Nov-15 10-Dec-15
MM2-11620 Touch up for equipment support and final coat 14 24-Feb-16 10-Mar-16
0.D.26.0000.MM2.D.R.25 Installation 40 26-Oct-15 10-Dec-15
MM2-10780 Fabrication and installation euipment support 40 26-Oct-15 10-Dec-15
0.D.26.0000.MM2.D.R.80 Equipment Securing 74 07-Dec-15 08-Mar-16
MM2-10120 Installation ROP1 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM2-10420 Installation ROP2 - Oil Production Pig Launcher / Receiver 4 07-Dec-15 10-Dec-15
MM2-10540 Installation safty sign and safety equipment 25 03-Feb-16 08-Mar-16
0.D.26.0000.MM2.D.L Piping 135 05-Oct-15 16-Mar-16
0.D.26.0000.MM2.D.L.20 Blasting & Painting 126 15-Oct-15 16-Mar-16
MM2-12100 Blast & Paint for piping spool, SS 60 19-Oct-15 26-Dec-15
MM2-12360 Blast & Paint for piping spool, Duplex SS & Cladding 60 15-Oct-15 23-Dec-15
MM2-12500 Blast & Paint for Pipe support 55 24-Oct-15 26-Dec-15
MM2-12580 Blast & Paint for piping spool CS 90 30-Oct-15 18-Feb-16
MM2-12680 Touch up painting for piping 50 13-Jan-16 16-Mar-16
MM2-12760 Touch up for piping support 14 12-Feb-16 27-Feb-16
MM2-12840 Touch up painting for valve 14 16-Feb-16 02-Mar-16
0.D.26.0000.MM2.D.L.10 Fabrication 107 05-Oct-15 12-Feb-16
MM2-10720 Fabrication Carbon steel piping spool work 107 05-Oct-15 12-Feb-16
MM2-11100 Fabrication Stainless steel piping spool work 60 13-Oct-15 21-Dec-15
MM2-11320 Fabrication Duplex SS & Cladding piping spool work 60 07-Oct-15 15-Dec-15
MM2-11580 Fabrication Pipe support 60 14-Oct-15 22-Dec-15
MM2-11860 Fabrication CUNI piping spool work 35 26-Oct-15 04-Dec-15
0.D.26.0000.MM2.D.L.25 Installation 84 11-Nov-15 23-Feb-16
MM2-10740 Pipe support installation 60 11-Nov-15 20-Jan-16
MM2-11340 Installation Carbon steel piping spool work 56 25-Nov-15 29-Jan-16
MM2-11600 Installation Stainless steel piping spool work 55 26-Nov-15 29-Jan-16
MM2-11880 Installation Duplex SS & Cladding piping spool work 55 26-Nov-15 29-Jan-16
MM2-12120 Installation Manual valve 30 02-Jan-16 05-Feb-16
MM2-12380 Installation CUNI piping spool work 22 05-Jan-16 29-Jan-16
MM2-12600 Installation MOV valve 15 30-Jan-16 22-Feb-16
MM2-12700 Installation Choke valve 15 30-Jan-16 22-Feb-16
MM2-12780 Installation On-off valve 15 01-Feb-16 23-Feb-16
0.D.26.0000.MM2.D.L.40 Testing 42 31-Dec-15 24-Feb-16
MM2-10220 Flushing and hydro test 30 31-Dec-15 04-Feb-16
MM2-10300 Flangemanagement & reinstatement 37 07-Jan-16 24-Feb-16
0.D.26.0000.MM2.D.1 E&I 101 13-Nov-15 16-Mar-16
0.D.26.0000.MM2.D.1.20 Blasting & Painting 88 28-Nov-15 16-Mar-16
MM2-10760 Blast & Paint E&I support 40 28-Nov-15 14-Jan-16
MM2-12140 Touch up for E&I support 14 01-Mar-16 16-Mar-16
0.D.26.0000.MM2.D.1.10 Fabrication 50 13-Nov-15 11-Jan-16
MM2-10100 Fabrication Electrical Support 50 13-Nov-15 11-Jan-16
MM2-10280 Fabrication Instrument Support 50 13-Nov-15 11-Jan-16

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 71 of 72
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Activity ID Activity Name Original Start Finish 2015 2016
Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
0.D.26.0000.MM2.D.1.25 Installation 70 10-Dec-15 07-Mar-16
MM2-10060 Installation Electrical Support 48 10-Dec-15 04-Feb-16
MM2-10400 Installation of Instrument Support 41 18-Dec-15 04-Feb-16
MM2-10520 Installation Electrical cable Ladder/Tray 35 26-Dec-15 05-Feb-16
MM2-10580 Installation Instrument cable and Tubing Ladder/Tray 35 29-Dec-15 13-Feb-16
MM2-10620 Installation Instrument equipments 30 27-Jan-16 07-Mar-16
MM2-10660 Installation Electrical Equipments 30 26-Jan-16 05-Mar-16
MM2-10680 Installation Tubing 28 29-Jan-16 07-Mar-16
MM2-11080 Install Heat tracing 25 25-Jan-16 27-Feb-16
0.D.26.0000.MM2.D.1.40 Testing 48 11-Dec-15 05-Feb-16
MM2-10080 Testing Electrical Cable 40 11-Dec-15 27-Jan-16
MM2-10260 Testing Instrument Cable 40 11-Dec-15 27-Jan-16
MM2-10320 Calibration of instrument equipments 25 28-Dec-15 26-Jan-16
MM2-10480 Function test/ Leak test (Choke Valve, On-off Valve) 7 29-Jan-16 05-Feb-16
0.D.26.0000.MM2.D.1.30 Cabling & Termination 55 06-Jan-16 15-Mar-16
MM2-10040 Pulling Electrical Cable 35 06-Jan-16 20-Feb-16
MM2-10240 Pulling Instrument Cable 30 13-Jan-16 22-Feb-16
MM2-10380 Glanding and Termination Electrical 35 28-Jan-16 14-Mar-16
MM2-10500 Glanding and Termination Instrument 32 02-Feb-16 15-Mar-16
0.D.26.0000.MM2.D.4 Insulation 35 01-Feb-16 17-Mar-16
0.D.26.0000.MM2.D.4.25 Installation 35 01-Feb-16 17-Mar-16
MM2-10160 Insulation for Mechanical equipment & Piping 35 01-Feb-16 17-Mar-16
0.D.26.0000.MM2.D.5 Mechanical Completion ("A" Scope) 48 23-Jan-16 24-Mar-16
0.D.26.0000.MM2.D.5.60 Finishing 43 23-Jan-16 18-Mar-16
MM2-10140 ITR checksheet for Piping 40 23-Jan-16 15-Mar-16
MM2-10340 ITR checksheet for Instrument 30 13-Feb-16 18-Mar-16
MM2-10440 ITR checksheet for Electrical 30 12-Feb-16 17-Mar-16
0.D.26.0000.MM2.D.5.70 Pre-commissioning 33 16-Feb-16 24-Mar-16
MM2-10360 Pre-com for Modules MM1 ( Leak Test, Heatracing...) 33 16-Feb-16 24-Mar-16
MM2-10460 Disciplines Acceptance Certificate (DAC) 20 27-Feb-16 21-Mar-16
MM2-10560 Loop Test from Instrument devices to RIO panels 16 04-Mar-16 22-Mar-16
MM2-10600 Full power up of the module lighting 4 24-Feb-16 27-Feb-16
MM2-10640 Mechanical & Pre-com Completion date for MM2 0 24-Mar-16 Mechanical & Pre-com Com
0.D.26.0000.MM2.D.6 Finishing/ Load-Out 33 24-Feb-16 01-Apr-16
0.D.26.0000.MM2.D.6.1 Load-Out 33 24-Feb-16 01-Apr-16
MM2-10000 Fab Seafastening & Install Grillage on Barge for MM2 20 24-Feb-16 17-Mar-16
MM2-10200 Load-Out for Modules MM2 7 26-Mar-16 01-Apr-16
0.D.26.0000.MM2.T Transportation (Optional) 7 02-Apr-16 08-Apr-16
0.D.26.0000.MM2.T.7 Delivery 7 02-Apr-16 08-Apr-16
0.D.26.0000.MM2.T.7.70 Delivery 7 02-Apr-16 08-Apr-16
MM2-10180 Transportation Modules MM2 to Singapore Yard 7 02-Apr-16 08-Apr-16

Date Revision Checked Approved


Remaining Level of Effort Critical Remaining Work Schedule Level 3 28-Mar-15 Baseline Schedule Level 3
Actual Work Milestone
Remaining Work Summary Page 72 of 72

You might also like