Section 7.6 Assignment - Caisson - B of Q
Part 1 - Quantity Takeoff
20m Caisson 3.141593 PI
Excavation Diam Squared Depth Vol
21.3 453.69 10 3,563.0
Rebar Verti No. Diam Circum 9.5 Bars kg/m
0.5 41 20.5 64.40 41 389.50 3.64 1,418 kg
Rebar Hori No. Hoops Height 12 20.65 Bars kg/m
0.5 19 9.5 64.40 4 19.00 1,304.40 3.64 4,748 kg
Total 6,166 6.2
6.17 tonne
Formwork Internal Diam Circum Depth Area
20 62.8 1.0 62.8
Formwork External Diam Circum Depth Area
21 66.0 1.0 66.0
Total 129 m2
Concrete Internal Diam Squared Depth Vol
20 400 9.95 3,980.0
External Diam Squared Depth Vol
21 441 9.95 4,388.0
Shoe Diam Circum Area
20.4 416.16 0.17875 74.4
Total 482.3 m3
Crushed R Internal Diam Squared Depth Vol
20 400 1 314.2
Shoe Diam Circum Area
20.4 64.08849 0.17875 11.5
Total 325.6 m3
Cutting Edges 4
Shoe Diam Circum Length No.
20.4 64.09 4 16.02
Hand Trimming base
Diam Squared Area
21.2 449.44 1,412.0 m2
File Name:
Page 2 of 7 Date Printed: 11/21/2018
402528378.xlsCaisson Qty
HES5175_HES6175
Section 7.6 Assignment - Caisson - B of Q
Part 1 - Quantity Takeoff
File Name:
Page 3 of 7 Date Printed: 11/21/2018
402528378.xlsCaisson Qty
HES5175_HES6175
Section 7.6 Assignment - Caisson - B of Q
Part 1 - Quantity Takeoff
2 x 15m
File Name:
Page 4 of 7 Date Printed: 11/21/2018
402528378.xlsCaisson Qty
Section 7.6 Assignment - Caisson
HES5175_HES6175
Part 2 - Production Rates
Description Qty Unit Rate Hours Foreman Crane Operator No. Labourers FEL Operator Spotter Welders Totals m/hrs
20 m Caisson
Minimum No. of pours 15
Excavation 3,563 m3 15 237.5 20% 47.51 100% 237.5 2 475.1 760
FEL 3,563 m3 25 142.5 0.00 100% 142.5 143
Hand Trim Excavation 1,412 m2 5 282.4 0.00 5 282.4 282
Rebar 6.17 t 20 123.3 0.00 6 123.3 20.6 144
Formwork 129 m2 20 50% 4.30 20% 1.7 6 51.6 58
Concrete 482.34 m3 2 241.2 0.00 100% 40.2 6 241.2 281
Crushed Rock 325.62 m3 50 6.512 0.00 100% 6.5 1 6.5 13
Cutting Edge 4 80.11061 320
428.5 Subtotals 2,001
FEL 142.5
Crane Subtotal 286.0
15 m Caissons x 2
Minimum No. of pours 20
Excavation 4,173 m3 15 278.2 0.00 100% 278.2 2 556.5 835
FEL 4,173 m3 25 166.9 0.00 100% 166.9 167
Hand Trim Excavation 1,649 m2 5 329.8 0.00 5 329.8 330
Rebar 14.06 t 20 281.2 0.00 6 281.2 281
Formwork 195 m2 20 0.00 20% 2.6 6 77.9 81
Concrete 502 m3 2 250.9 0.00 100% 41.8 6 250.9 293
Crushed Rock 371 m3 50 7.415 0.00 100% 7.4 1 7.4 15
Cutting Edge 6 3,000.0 83.33 500
497.0 Subtotals 2,501
FEL 166.9
Crane Subtotal 330.1 TOTAL 4,502
Crane Total 616.0
2xA B ∑
Minimum No. of pours 20 15 35
Excavation time/lift 13.9 15.8 30
Rebar time/lift 2.3 1.4 4
Formwork time/lift 0.6 0.6 1
Concrete time per lift 2.1 2.7 5
Minimum time/lift 19.0 20.5 39
Total manhours 2,501 2,001 4,502
File Name: 402528378.xls Caisson Production Rates Page 5 of 7 Date Printed: 11/21/2018
Section 7.6 Assignment - Caisson
HES5175_HES6175
Part 2 - Production Rates
File Name: 402528378.xls Caisson Production Rates Page 6 of 7 Date Printed: 11/21/2018
Section 7.6 Assignment - Caisson
HES5175_HES6175
Part 2 - Production Rates
Duration
237.5
142.5 25m3/hr
56.5 1mhr/5m2 314
20.6 20MH/tonne
8.6 20m2/mday 20 6 120 1.075 Days
40.2 2MH/m3 2 6 12 40.19 hours
6.5 50m3/hr
320.4 20MH/join 20 16 320 80.11
832.8
278.2
166.9 25m3/hr
66.0 1mhr/5m2 353
46.9 20MH/tonne
13.0 20m2/mday 20 6 120 1.623 Days
41.8 2MH/m3 2 6 12 41.82 hours
7.4 50m3/hr
500.0 20MH/join 20 25 500 83.33
1,120.2
1,953
48.8