4. MEASURES BEFORE START-UP ....................................................................... 2
4.1 General inspection at the boiler plant .................................................................... 2
4.2 Preparations for the start-up of the feedwater system ........................................... 5
4.2.1 Preparation for chemical dosing station................................................................. 5
4.2.2 Filling of feedwater tank......................................................................................... 5
4.2.3 Filling of feedwater line .......................................................................................... 7
4.3 Start-up preparations of boiler water and steam system........................................ 9
4.3.1 Boiler water filling................................................................................................... 9
4.3.2 Preparations at sample station ............................................................................ 11
4.4 Start-up preparations of flue gas system ............................................................. 12
4.5 Start-up preparations of the air system................................................................ 14
4.5.1 Loop seal air compressors................................................................................... 15
4.5.2 Secondary air fans............................................................................................... 15
4.5.3 Primary air fans.................................................................................................... 15
4.6 Oil pumping and heating station .......................................................................... 16
4.6.1 Heavy fuel oil ....................................................................................................... 16
4.6.2 Diesel oil .............................................................................................................. 16
4.7 Start-up preparations of the oil burners ............................................................... 17
4.8 Start-up preparations of solid fuel system............................................................ 19
4.9 Start-up preparations of the fluidized bed combustion system ............................ 20
4.9.1 Sand handling system ......................................................................................... 20
4.9.2 Limestone handling system ................................................................................. 20
4.9.3 Fluidized bed combustion .................................................................................... 21
4.10 Start-up preparations of ash handling system ..................................................... 22
4.10.1 Fly ash equipment............................................................................................ 22
4.10.2 Bottom ash handling equipment....................................................................... 23
4.11 Start-up preparations of the sootblowing system ................................................. 23
4.12 Walk around at the boiler plant ............................................................................ 24
• Make sure that the valves and instruments at the boiler operate
properly.
• Check that particularly the feedwater and main steam lines are
ready for operation
− allowances for thermal expansion
− supports and insulation
− function of the valves
− blow-off pipes of safety valves
− drain pipes
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Check that the dampers and gate valves can move freely.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Check that all necessary dosing chemicals are available and dosing
pumps are ready for operation. See also supplier’s separate
instructions for dosing equipment.
Make-up water for the boiler comes from the water treatment plant.
Condensate from the mill process and turbine is returned through
the deaerator into the feedwater tank.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
When the tank level rises to level 3.68 m (80 %), the level switch
gives the upper limit alarm. When the level rises to 4.14 m (90 %),
the overflow valve is totally open controlled by the level
measurement. The manual valve in the overflow pipe must be open
during a normal situation.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
The safety valve in the feedwater tank opens if the pressure in the
tank exceeds 6.5 bar(e).
Before feedwater pumps are started, feedwater pipe and boiler are
filled as much as possible by means of static pressure and
feedwater tank overpressure. Then note the following things:
Feedwater pumps
• Check that cooling water manual valves for pumps and hydraulic
couplings are open. Set manually right cooling water flow to the
feedwater pump bearings (abt. 20 l/min). Cooling water flow to
the hydraulic couplings is remote controlled.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Feedwater piping
• Check that the shut-off valves in the chemical feeding lines are
open.
• Check that the valves in pressure and flow measurement pipes
are open.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Check that the root valve in the spray water line is open and
drain valves are closed.
• Check that the shut-off valves before and after spray water
control valves are open and bypass valves closed. Spray water
control valves must be closed.
• Check that manual valves in blow-out tank cooling water line are
open and put tank temperature control loop to automatic, set
value about 60°C.
• Check that the main steam valve and its bypass valve are
closed.
• Check that vent and drain valves of the superheaters are open.
When starting boiler filling with water the situation may be one of the
follows:
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
1. Empty boiler
When the boiler is empty, start water filling carefully first with a water
flow of abt. 5 - 7 kg/s. Water flow is regulated suitable by means of
the motor valve 1 (or manual valves in bypass line). Now and then
filling can be interrupted to wait until drum temperature stabilizes.
The boiler operator must follow up filling often enough beside the
boiler. Water flow can be added to 7-12 kg/s later. Check drum water
level from local water glasses always before heating is started. With
cold boiler water level can remain at abt. –200 mm due to thermal
expansion allowance (lower interlock limit is -250 mm).
In this case the boiler (also drum and superheaters) is filled with
water (more chemicals have possibly been added) and excess water
must be drained off through bottom drains - using motor operating
valve. On the basis of laboratory analyses, water change, if any,
must be decided on.
3. Stand-by
The boiler has a pressure of 2-10 bar and drum level is usually
above lower limit interlock, set the level to -200 mm if necessary.
Vent and drain valves of superheaters must be opened.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Open shut-off valves in sample station lines and make sure that
sample station lines are not blocked.
Make sure that the sample station is ready for operation and that
there is cooling water available.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
The flue gas system is the first of the different boiler systems to be
started. Filling of boiler water side, however, must be carried out
before this.
Before start-up of flue gas fans make sure that the auxiliary
equipment (fans, motors, dampers, oils, valves, and ducts) are in
proper condition (see separate operating instructions) and ready for
start-up.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Electrostatic precipitator
• Check that the insulation heating of the ESP has been switched
on.
• Check the oil level of the emitting system rapper gear motors.
• Check the oil level of the collecting system rapper gear motors.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Check that all the manual loop seal and windbox sand drain
valves are closed
• Before starting secondary air fans check that inverter set value is
in minimum.
Start-up conditions
• Main interlocks valid, secondary air fan, loop seal air compressor
and flue gas fan are running
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Check that manual valves in oil line are open to one suction filter,
to one pressure filter and to steam or electric heater. All the shut-
off valves in suction and discharge side around the pumps can
be open if the pumps are in working condition
NOTE! Be sure that the oil pumps are filled with oil
NOTE! Be sure the venting and drain valves are closed
• Check that manual valves in oil line are open to one suction filter.
All the shut-off valves in suction and discharge side around the
pumps can be open if the pumps are in working condition
NOTE! Be sure that the oil pumps are filled with oil
NOTE! Be sure the venting and drain valves are closed
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
For proper start-up and operation of oil burners, check the following
things before igniting the first burner:
• Check that valves are in the right position according to which oil
(diesel or heavy) is planned to be used
• If going to use heavy oil, start oil heating circulation and make
sure that the instruments function during this circulation cycle
(heating circulation abt. 0.15 kg/s/line).
• Check that the nozzles of the burners are in their proper places,
fit for operation and clean. Make sure that the nozzle is tightened
enough to prevent leaks.
• Check that primary air fans are in operation and flame scanner
and igniter are cooled (normal cooling air pressure about 30
mbar).
• Check that the switch on the local control box is in control room
position, if the burner is to be started from the system.
• Make sure that the manual valves in oil, atomizing steam/air and
ignition gas lines on burner level are open.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Before igniting the first burner make sure on the spot that the
following process values are met:
Normally when the boiler is cold, start of the boiler shall be done with
diesel oil. Heavy fuel oil firing can be started when bed temperature
has increased to about 250 °C and dry atomizing steam is available.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Before start-up of conveyors the operators must make sure that all
the equipment is in working order and start-up will not be hazardous
to other persons at the plant. Therefore during a field operators’
round it is recommended to check at least the following things:
NOTE! The boiler operators must always make sure that the
solid fuel to be burned and feed in to the silos is
according to the design data of the boiler and check
that all iron separating magnets, grates and crushers in
the fuel prehandling area are operate properly.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
The sand must be dried and screened into given size distribution
before it is transferred into the sand silo located inside the boiler
house.
Before the boiler is started, boiler sand filling has to be carried out
and the sand hopprt should be full. The sand is fed into the furnace
through one of the fuel feeding points).
The required sand amount for bed is about 110 m3 and in addition
three cyclone loop seals take about 15 m3 each - this means totally
155 m3 sand filling into the furnace before start-up.
The limestone must be dried and crushed into given size distribution
before it is transferred into limestone dosing silo.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
Make sure that the following things are in order regarding the
fluidized bed condition:
• ensure that there is enough sand in bed after the loop seal have
been filled with sand, proper bed depth is 500 - 550 mm
• If necessary, remove coarse sand from the whole bed area and
add new sand to keep the bed height right. The sand amount is
checked through sight glasses during oil firing when the bed is in
unfluidized condition.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Test the operation of the fly ash conveyors while the conveyors
are empty. If necessary, remove ash stuck on the conveyor
• Secure silo filling capacity by emptying the silo and cleaning the
discharge filter elements of the exhaust fan on the roof of the
silo, when the need arises.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
• Close the conveyor doors tightly, so that dry sand will not raise
dust into the boiler room.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005
Asiakirjan nimi - Name of Document Tunniste - Identification Rev.
This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project or
purpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.
© Kvaerner Power Oy, Tampere, Finland 2005