You are on page 1of 8

QATAR CHARITY

Construction activities in vulunerable schools of Shorkot

Construction of twin set latrines in schools (per unit)

Abstract of Cost

Sr # Description Total Cost

1 Toilets + Hand washing facility 238,207

2 Septic Tank and soakage pit 52,097.40

3 Sanitry & Electric Work 95,538

Total Cost 385,843

Sr # Description of Item Length

Latrine work
1 Excavation
1.1 Excavation of bath rooms foundation long wall 17.75
1.2 Excavation of bath rooms foundation short wall 4.25
Net quantity
2 Backfilling
2.1 Backfilling of Latrine structure 14.00
Net quantity
4 PCC 1:4:8 in foundation 3" thick
4.1 PCC in long wall 17.75
4.2 PCC in short wall 4.25
Net quantity
5 Brick masnary (1:5)
5.1 1st step long wall 17.38
5.2 1s tstep short wall 4.63
5.3 2nd step long wall 17.00
5.4 2nd step short wall 5.00
5.5 Brick masnory super structure long wall 17.00
5.6 Brick masnory super structure short wall 5.00
5.7 Brick masnory in abolution area back side 6.00
5.8 Brick masonary parapet wall overall 1 length 46.00
Total Brick Masonary
Deduction Doors 2.00
Open area in Ablution area front side 6.00
Ventilator (1'x1') 1no on back side each latrine 1.00
Net Brick Masonary
6 DPC (1:2:4)
6.1 Long wall 17.00
6.2 short wall 5.00
Total quantity D.P.C
7 Plaster Work
7.1 3/4" Plaster (1:4) inside wall 49.00
7.2 1/2" Plaster (1:4) outside wall 47.00
7.3 1/2" Plaster (1:4) parapet wall overall length & 46.00
Total quantityPalaster
Deductions
Deductions of doors 2.00
Deductions of Abolution area front wall 6.00
Net Quantity Palaster
8 Flooring
8.1 Compacted Brick Ballast 3"thick in 2 latrines f 5.00
8.2 Compacted Brick Ballast 3"thick in Abolution 6.00
Net quantity
8.3 PCC 3" thick 1:2:4 in wash room 5.00
8.4 PCC 3" thick 1:2:4 in Abolution area 6.00
Net quantity
9 Roof
9.1 Girder 3"x 6.5" with 1 coat of red oxide & 2
coats paint Vivid blue color 7.50
9.2 T iron ( 100 x 100 ) with 1 coat of red oxide & 2
coats paint Vivid blue color 17.00
9.3 Bricks tiles 17.00
9.4 Polythene sheet 17.00
9.5 PCC 2" thick 1:2:4 in wash room roof 16.00
9.6 Grouting of bricks tiles both sides (up and
down) 17.00
10 Abolution place and Latrine Steps
10.1 Brick Masonary for steps 17.00
10.2 Plaster Work for steps riser & threads 17.00
10.3 Plaster Work for steps sides 3.00
Lintal for door and aboulation area 9"X4"
complete with all respect 13.00
Coping 1;2;4 6.00
10.4 PCC 1"2"4 In abulation area Drain sides and
bed with Plaster finish 6.00
10.5 Brick Masonary Sitting place 1'x 1' x 9" 1.00
10.6 Palaster Sitting place 1'x 1' x 9" 1.00
11 Doors and ventilator
11.1 Doors 2.00
11.2 Door Ventilator 2.00
11.3 Ventilator 1.00
Total quantity
12 White washing

Distemper on all Inner Side and weather shield


12.1 on all outer sides of the structure 3 coats each
Oil pint for 3' hight in aboulation area and
12.2 wash room border
12.3 Paint on Doors 3 coats on double side 2.00
13 Installatin of Marbel plate
Total cost of Toilet and handwashing facility

Sr # Description of Item Length

1 Septic Tank
1.1 Excavation 7.5
1.2 PCC 1:4:8 in bed 2" thick 7.5
2 Brick masnary (1:5)
2.1 long wall 7.5
2.2 short wall 4
2.3 Baffle wall 4
3 Plaster (1:4) 1/2" thick
3.1 Plaster (1:4) long wall 6
3.2 Plaster (1:4) short wall 4
3.3 PCC 1:2:4 for 3"thick slab 5.5
4 Steel 1/2" dia for RCC Slab
4.1 Main bars 8# 1/2" dia @ 9"c/c with 1.5" cc.
4.2 Distribution bars 4# 1/2" dia @ 9"c/c with 1.5" cc.
Binding wire
(B) Soakage pit
1.1 Excavation 25.9540625
1.2 PCC 1:4:8 in bed 4" thick at walls only 25.95

1 Brick masnary (1:5) .complete in all


respect.
1.1 wall icludind deuction of honey combing of (qt 25.95
1.2 PCC(1:2:4 ) for 3" thick slabs, 25.9540625
2 Steel 1/2" dia for RCC slab
2.1 Main bars 7# 1/2" dia @ 9"c/c with 1.5" cc.
2.2 Distribution bars 4# 1/2" dia @ 9"c/c with 1.5" cc.
2.3 Binding wire
2.4 Filter material Brick Ballast or Course Gravel of average size 2"
TOTAL QUANTITY

Sr # Description of Item Unit

1 Indian wc 20"size No
2 HDPE water supply pipe 3/4" Ø (25mm) super a Rf
3 GI pipe IIL 1.5" Ø Rf
4 GI elbow 1.5" Ø No
5 Pipe nipple 1.5" Ø No
6 Pipe nipple 3/4" Ø No
7 Pipe nipple 1.5"x1/2" Ø No
8 Handle valve 3/4"Ø No
9 Stoper 1.5" No
10 GI elbow 3/4" Ø No
11 GI union 3/4" Ø No
12 GI tee 3/4" Ø No
13 GI valve socket 3/4" No
14 GI socket 1/2" Ø for bib cock No
15 Bib cock (super asia) No
16 UPVC pipe 4" Ø (Pak arab, golden) Rf
17 UPVC pipe 2" Ø (Pak arab, golden) Rf
18 Vent pipe Cap No
19 UPVC Tee 4" Ø No
20 UPVC Elbow 4" Ø No
21 P-trap (Master)4" No
22 Cotton thread No
23 Clip for pipe fixing No
24 AGM solution No

Electric motor 1 HP Master/ Pakistan/Super


25 asia with conection and board etc complete
wioth all respect No

Bore 2.5" for clean water Depth 70 rf


26 inculding conection pipe and complete with
all respect Rf

27 Water Tank double ply/super tuff with


complete accessiories (Master) (250 Gal) No

Total cost of Sanitary &


electric work
Width H/D No Unit Quantity Unit Price Total Price

1.50 1.50 2.00 cf 79.88 10


1.50 1.50 4.00 cf 38.25 10
118.13 10 1181.25

5.00 2.00 1.00 cf 140.00 8


140.00 8 1120.00

1.50 0.25 2.00 cf 13.31 220


1.50 0.25 4.00 cf 6.38 220
19.69 220 4331.25

1.13 0.50 2.00 cf 19.55 222


1.13 0.50 4.00 cf 10.41 222
0.75 2.08 2.00 cf 53.04 222
0.75 2.08 4.00 cf 31.20 222
0.75 8.25 2.00 cf 210.38 222
0.75 8.25 4.00 cf 123.75 222
0.38 3.50 1.00 cf 7.88 222
0.75 0.50 1.00 cf 17.25 222
473.44 222
0.75 8.00 2.00 24.00
0.75 8.00 2.00 72.00
0.75 1.00 2.00 1.50
375.94 222 83459.37

0.75 0.17 2.00 cf 4.25 320


0.75 0.17 4.00 cf 2.50 320
6.75 320 2160.43

8.00 1.00 sf 392.00 27


10.00 1.00 sf 470.00 27
1.50 1.00 sf 69.00 27
931.00 27 25137.00

8.00 4.00 sf 64.00


8.50 1.00 sf 51.00
816.00 27 22032.00

4.00 0.25 2.00 cf 10.00 48


6.00 0.25 1.00 cf 9.00 48
19.00 48 912.00
4.00 0.25 2.00 cf 10.00 320
6.00 0.25 1.00 cf 9.00 320
19.00 320 6080.00

2.00 Rf 15.00 379 5685.00

5.00 Rf 85.00 285 24225.00


6.50 sf 110.50 38 4199.00
6.50 sf 110.50 8 884.00
5.50 0.17 1.00 cf 14.96 320 4787.20

6.50 0.02 1.00 cf 2.21 250 552.50

1.00 0.50 3.00 cf 25.50 230 5865.00


1.50 3.00 sf 76.50 28 2142.00
1.00 6.00 sf 18.00 28 504.00

0.75 0.33 1.00 Cf 3.22 450 1447.88


0.75 0.17 1.00 Cf 0.77 320 244.80
4.00 0.33 1.00 cf 7.92 300 2376.00
1.00 0.75 3.00 cf 2.25 230 517.50
1.00 15.00 sf 15.00 28 420.00

6.50 2.00 sf 26.00 450


1.50 2.00 sf 6.00 450
1.00 2.00 sf 2.00 450
34.00 450 15300.00

1.00 sf 816.00 20 16320.00

1.00 Sf 138.00 28 3864.00


8.00 2.00 sf 32.00 30 960.00
1 No 1 1500 1500.00
ndwashing facility 238207

Width H/D No Unit Quantity Unit Price Total Price

5.5 5 1 cf 206.25 10.00 2062.50


5.5 0.166 1 cf 6.8475 220.00 1506.45

0.75 4.75 2 cf 53.4375 222.00 11863.13


0.75 4.75 2 cf 28.5 222.00 6327.00
0.375 2.5 1 cf 3.75 222.00 832.50

4.5 2 sf 54 28.00 1512.00


4.5 2 sf 36 28.00 1008.00
2.5 0.25 3 cf 10.3125 320.00 3300.00

Kg 16.2 150 2430.00


Kg 18.9 150 2835.00
Kg 0.5 150 75.00

6 1 cf 155.7244 10 1557.24
0.5 0.333 1 cf 4.320675 220 950.55

0.375 6 1 cf 38.9275 222 8641.91


0.25 1 cf 6.488516 320 2076.33
Kg 9 150 1350.00
Kg 11 150 1650.00
Kg 0.5 150 75.00
Cf 42.6 48 2044.80
TITY 52097.40

Unit
Quantity Total Price
Price
2 4500 9000.00
100 90 9000.00
10 250 2500.00
1 75 75.00
1 50 50.00
3 45 135.00
1 85 85.00
1 335 335.00
1 38 38.00
6 70 420.00
1 85 85.00
4 65 260.00
2 80 160.00
5 65 325.00
5 825 4125.00
39 330 12870.00
20 250 5000.00
2 100 200.00
3 450 1350.00
2 450 900.00
2 350 700.00
10 40 400.00
12 35 420.00
1 200 200.00

1 18795 18795.00

19460.00
70 278

1 8650 8650.00

95538.00