Professional Documents
Culture Documents
680
the construction. Above technically challenging issues takes around 15 to 20 days from Kolkata to the bridge
are some of the main reason why bridge at Gurupriya Site. In case of any breakdown/regular maintenance; wire
site could not happen since long, rope and all spares to be brought from Kolkata. Pontoons
The bridge site near Janbai on Chitrokonda-Janbai- were fabricated in workshop at Raipur, Chhattisgarh and
Papermetla road is in a remote location touching the shifted in pieces over Trailer and assembled at site. High
border zone of Orissa-Andhra Pradesh and Chhattisgarh Capacity crane was moved from Latehar of Jharkhand
and very much affected by Naxal threats. Very poor state. Crane was moved on its wheel and its counter
accessibility for movement of man and machineries weight was sent through Trailer. A team of 4 members
for construction purpose due to hilly terrain & narrow was sent along with the crane to reach the site safely. It
inaccessible roads from both approaching ends i.e either took about 5 days to reach the site.
from Jeypore side (i.e through state of Odisha) OR from Due to Naxal threats, no material supplier was ready
Visakhapatnam side (i.e from state of Andhra Pradesh). to supply materials at site. District Administration did
The accessibility to Janbai site approach of the bridge not permit to run crusher due to pollution and green
are either through Jeypore-Baipariguda-Govindali- belt issue at Malkangiri, which hampered supply of
Balimela-Chitrkonda route from state of Odisha OR aggregates. No transport facilities are available at site,
through Visakhapatnam-Tahllipelam-Narsingpatnam- therefore, for sending even for small parts/spares also,
Chintapalli-Gudem-Darkonda-Chitrokonda from state of an individual vehicle had to be arranged. Prestressing
Andhra Pradesh. Road conditions were extremely poor wire rope was procured from M/s Usha Martin from their
from Chitrokonda to Janbai. Similarly the only route Ranchi production unit. Each lot took about 15 days to
available to come to Papermetla side approach of the reach the site. Prestressing Jacks and other materials
bridge is from Visakhapatnam of Andhra Pradesh through were procured from Dynamic Prestressing system from
Visakhapatnam-Tahllipelam-Narsingpatnam-Chintapall- Nasik and 30 days lead time was required to reach
Paderu-Muchingiput-umuda-Gandiguda-Jantapai- the materials at site. Steel Girders for the six spans of
Papermetla-Badapada. The road from Muchingput to the bridge were fabricated in workshop at Raipur and
Badapada is earthen kachha road. Besides above, the individual segments were transported through trailer
surrounding areas all along the above three routes are through the Ghat Roads to the bridge site which used to
affected by regular maoist activities and with almost nil/ take 8 to 10 days time. HSFG bolts were procured from
very poor tele network connectivity till today. Ludhiana and dispatched after inspection from the shops
and each lot took about 20 days to reach the site.
3. SITE STRATGIC ISSUES & DIFFICULTIES IN
MOBILIZING MATERIALS, MACHINARY & Similar difficulties were faced during mobilization
HUMAN RESOURCE of manpower: The 17 Km long existing road between
Chitrokonda (i.e the block head quarter) to Janbai
Three challenges that was originally predicted were;
approach of the bridge site is full of jungle and barren
access to reach the bridge site, availability of limited
areas with no tele communication facilities. Due to
working period of only four to five months a year that again
Naxal threat, no staffs were ready to work at bridge site.
only during day time as evening work was considered
Subsequently, the project site office including labour
highly unsafe & risky due to naxalite problems. The
camp were established just adjacent to BSF base camp
amenities like electricity and communication were very
on A1 side approach of Janbai and officials camp near
poor. Though a fair access to the site was made partially
Chitrokonda BSF premise for safety purpose. There
ready around June 2013 after start of construction
is no direct rail/road route from metro like Kolkata to
work for Chitrokonda-Janbai road, there was need for
the project site. Pilling gangs were arranged from West
appropriate planning to mobilize material, plants &
Bengal. Labour was sent to Kolkata from their native
machineries and labour to complete the task considering
place, Kolkata to Vizag via train, then Vizag to Selur via
the natural and man made hinderances.
bus and Selur to Site through Jeep. It took around 36 hrs.
As the area was affected/defamed due to Naxal threats, no for labours to reach the site from their native place.
agency was ready to supply any machinery/equipment to
the site. The area was cut-off from transmission/ mobile 4. TECHNICAL CHALLENGES DURING
network, and thus no operator was ready to work in the CONSTRUCTION OF FOUNDATIONS
Gurupriya bridge site. Piling machineries were shifted The Full Reservoir Level (FRL) of Balimela reservoir
from Kolkata through Bhubaneswar to Janbai via Jeypore is R.L.462 m. Considering vertical clearance to the
route. This route passes through narrow Ghat road. It superstructure, the formation level of bridge has been
Photo 1 Bridge Site in September 2014 The foundation for the bridge are executed with large
After Award of the Work diameter piles (1200 mm & 1500 mm diameter) anchored
Photograph shown at Photo 1 presents the view of inside hard rock. Average depth of pile foundation
the bridge site during September 2014 after award of is about 20 m below ground level with 3.5 m to 7 m
the work to the EPC contractor. The field water level embedment inside hard rock. The piling work in shallow
as witnessed by the department has gone beyond RL water depth zone was done by making local earthen
460 m during 2014, 2015 and 2016 construction period.
Photographs shown at Photo 2 and 3 explains how islands as shown in Photo 4.
transportation of heavy construction machineries and The piling work in deep channel zones are done over
construction materials were made over floating pontoons floating pontoons with the help of steel liner, which were
during the construction period.
provided through the standing water to the starting of
The construction activities for foundation work were rock zone. This is one of the critical activities of the
carefully planned as per the gradual water spread and
corresponding water depth at any particular location by project which had consumed lot of time due to difficulties
segregating the construction activities for shallow water in maintaining balance over the floating pontoon while
zone and deep channel zone. driving the chisels as shown in Photo 5.
Fig 3 Shuttering Arrangement with Sacrificial Base for Deep Water Pile Cap
Above proposals alongwith supported design and In situ casting and subsequent stressing of PSC girders
methodology were examined & reviewed critically and for the spans close to the deep water zone were made
proved to be acceptable for construction considering the from a staging platform placed on a designed truss
site condition . The earth filled island for any particular system over pile caps.. As shown in the construction
span in the shallow zones over an area of 40 m X 9 m photograph Photo 11 for the span P17-P18, there were
was stabilised by driving wooden piles with proper three inter connected plane truss over which tubular
compaction as shown in Photo 8 to support the induced staging were erected to facilitate required casting height.
dead load of concrete girders before stressing. Other The segments and joints of the trusses were made with
slope strengthening measures using sand bags as pitching typical splice plate connected with high tensile nut &
elements to the temporary earthen islands was also made bolt system so that the segments can be opened for re-use
besides laying of 150 thick PCC bed over the compacted in another span. This type of staging was first attempted
bullah pile system to avoid any failure of the temporary over span P17-P18 and the work was successfully carried
out. However, the arrangement took considerable amount in-house fabrication factory and transported to the bridge
of time for erection of the truss over the pile cap and the site.
tubular staging over the truss system . Removal of such
truss system segment wise & re-fixation in another span
inside deep water zone also took considerable amount of
time, which compelled to look after other alternatives.
facilitating lifting by typical winch-pulley-roller system. than 14 m were erected over temporary earthen island
Photo 12 to 15 explains the sequential activities starting with design staging platform. The temporary earthfill
from site assembly of steel girders with connection of island at this location was strengthened by combination
their flange & web splice plates, tightening of HSFG of bullah piles and steel piles driven deep inside the bed
bolts by mechanical torque wrench of required capacity, level besides sacrificial concrete capping arrangement to
placement of assembled girder over floating pontoons prevent any collapse of the tall towers due to underneath
by mechanical crane, transportation of girder on floating seepage failure. Assembling of the individual box
pontoons by tug boats to the required location and finally segments were made at the bearing level over temporary
lifting of girders from floating pontoons with help of steel towers after matching the splice holes for the
designed pulley & roller system. HSFG bolts. Thereafter the fully assembled box girders
were laterally moved one by one with help of designed
41 m Long Steel Girder errection in deep channel rollers from down stream side pedestal to up stream side
zone from floating pontoon-I, November 2018 pedestal followed by fixation of cross girders The site
photographs showing launching of box-type steel girders
of 60 m length over the last span on P12A-P14 is shown
in Photo 12. The compulsion to change the execution
methodology due to unexpected abnormal drawn down
of reservoir water level has resulted some delay in the
work for this last span of the bridge.
7. QUALITY ASSURANCE & DUE DELIGENCE safety of the bridge. As a part of audit by CRRI, two
THIRD PARTY TESTS representative span of the bridge namely span P2-P3
Various quality assurance tests were performed during (PSC girder with RC deck superstructure) and P12-P12A
the construction phase after finalizing the methodology (Steel composite super structure) were load tested under
and schedule in advance. All tests after completion of the full design load test. Before load test visual inspection
project were conducted for issue of completion certificate of full span had been done properly. Expansion
to the contractor as per the EPC agreement condition. joints checked to insure for their proper functioning.
Finally a third-party quality audit was also conducted Scaffolding erected for fixing the instruments such
by the Bridge and Structures Division of Central Road as displacement transducers, temperature and strain
Research Institute (CRRI) who has certified the structural gauges.
Check for Deflection at various points due to test vehicle
Fig. 4 Discretization of Girder System Showing Critical Nodes and Sequential Loading Pattern of the Test Vehicles.
Fig. 4 explains the discretization of girder system in to and strain value continued for next 24 hours at an
finite elements and nodes. The sequential positioning of interval of one hour. After completion of 24 hours the
test vehicle loading pattern in longitudinal and transverse above procedure was repeated for unloading of load and
axis for analytical evaluation of deflection under test deflection, temperature and strain values were recorded.
load as per equivalent absolute maximum bending Afresh. Total 27 numbers of LVDT and 9 numbers of strain
moment concept and the corresponding deflection at gauges were fixed at the critical locations of the girders as
critical nodes are shown in Fig. 5. The load was applied shown in the Fig. 7 to record & measure the displacements
by adding loaded trucks of known weight. The test load and rotations in the three girder integral system.
is applied in stages of 55T, 85T and 115T (100% design Fig. 8 shows the schematic arrangement of test load and
equivalent load) as shown in Fig. 6. Fig. 9 demonstrates the load deflection graphs as per the
The deflections are measured at every stage of loading data recorded through four numbers of LVDTs placed near
and after one hour of loading. The recording of deflection the mid span, The test spans were constantly monitored
Fig. 5 Sequential Loading Along Longitudinal Axis with Fig. 6 Theoretical Deflection Values at Critical Nodes for the
Transverse Critical Position Outer and Inner Girder
for any structural distress at every stage of loading. From spans satisfy the required recovery of deflection
the load test results it is clear that both the representative more than 85% as per IRC:SP:51-2015 specification.
Fig. 7 Location of LVDTs & Strain Gauges for Load Testing of Full Span
Fig. 9 Load Deflection Curve for the LVDTs Placed at Mid Span of Girders
Photo 18 Completion Photograph Of Gurupriya Bridge with Water at Full Reservoir Level of 462 m During September 2018
8. CONCLUSION
the estimate considering the ground realities. In a
The planning for construction of the high level bridge competitive bidding process, M/s Royal Infraconstru
near Balimela reservoir was started in 1982, but it could Ltd from Kolkatta was awarded with the work, who
not take off due to technical challenges, remote location could finally complete the bridge within a span of three
and inaccessibility, and foremost, the menace of naxals/ and half years under BSF protection. Two companies of
left wing extremism. After several attempts, the State BSF were deployed on each side of the bridge to provide
Government could finally start the work in 2014 and security cover to the personnel and machineries during
the bridge was constructed within a short span of three the construction. The BSF security arrangement will
and half years due to dedicated micro managemet at remain in place for some more days near the bridge site.
each stage of work . The bridge has become a landmark The entire bridge has been illuminated and brought under
engineering feat in the State considering the natural CCTV surveillance to detect any attempt of sabotage by
features and technical challenges posed by the site. The naxals. The bridge will bring all-round transformation
present bridge structure as shown in the completion in the worst LWE-affected region by facilitating fast-
photograph Photo 18 inside Balimela reservoir basin paced development through improved connectivity,
has 22 spans standing on the water depth of an average health, education, electrification and access to public
20 m with the deep channel zone extending to a depth of services. It will boost economic activities and create
around 28 m. better livelihood opportunities for the people.
At the time of the beginning of construction of the One of the lesson learned in this project is to assess the
Gurupriya bridge, there were many skeptics who constructability issues that may arise from time to time
believed it was impossible to try and build a bridge due to fluctuating water depth, which practically guides
that can span across the Balimela reservoir. One of the the execution methodology and provide the basis for
nation’s leading engineering firms Gammon India tried actual construction time period in such a remotely located
their efforts during 2006-2008 but could not progress naxal disturbing zone. All items of works including the
due to remote site condition with naxal threats besides required machineries and associated logistics that can be
abnormal fluctuation in water depth for three consecutive safely deployed in such site scenario should be worked
years. State Govt’s initiative for making the bridge out at the planning stage and cost estimate as per ground
with help of Garden Reach Ship Builders, Kolkatta realities should be prepared.
and Bharat Earth Movers Ltd, Bangalore also could
not materialised Subsequently the project was included 9. ACKNOWLEDGEMENT
under the LWE (Left Wing Extremism) scheme of The authors wish to record their appreciation and sincere
Govt of India. During 2010. However multiple bidding thanks to the team of Scientists from Bridge and Structure
attempts made on behalf of Government of India could Division of Central Road Research Institute (CRRI) New
not yield any success ill 2013. As the State Govt. was Delhi for their suggestions during 3rd party quality audit
desperate for giving all-weather connectivity to the in documenting the work as a case study example. Special
remote and un connected 151 habitations for bringing thanks are extended to the Authority Engineer team from
the people to the main stream and also to free the area ARCHITECHNO Consultant Pvt Ltd, Bhubaneswar led
from LWE activists, it was finally decided to initiate by Er. Rajesh Roy Choudhury, Managing Director and
fresh bidding attempt with Engineering, Procurement Er Ashok Basa, Director Technical for their technical
and Construction (EPC) contract provisions by recasting guidance during supervision of the project.
ABSTRACT
Premature pavement distresses primarily in terms of moderate to severe fatigue cracking were observed on
a four-laning, 50-km national highway project. This paper describes in detail the systematic sampling and
testing plan which was executed to determine the specific cause(s) of the premature pavement distresses.
In general, good construction quality control and quality assurance of various pavement courses was not
exercised, which led generally to the development of premature “bottom up” fatigue cracking on the project.
Remedial measures to rehabilitate this distressed national highway project have been described in detail based
on the category, severity, and extent of the distresses. General recommendations have also been made to avoid
such pitfalls on other major highway projects.
1. INTRODUCTION (c) obtain samples of all pavement layers; (d) test all
After four-laning of a 50-km national highway was samples in an independent laboratory; (e) analyze the test
completed, premature pavement distresses were observed data and draw conclusions; and (f) recommend remedial
on it during the first monsoon. The following pavement measures considering the type, severity, and extent of
distresses were observed: open surface texture; raveling; specific pavement distress.
hungry surface; alligator cracks; and potholes. By far, 3. PROJECT DESCRIPTION AND DETAILS
fatigue cracking was the primary distress ranging from
3.1 Project Description
moderate cracking (one to two cracks in wheel path) to
severe cracking (alligator cracks in the wheel path or Four-laning of this project was completed on a Design,
block cracks across the lane). Build, Finance, Operate and Transfer (Toll) basis. The
concession period of this project is 20 years excluding
Further successive deterioration of pavement occurred the construction period.
during the second and third monsoons. Several areas of
severe alligator cracks also developed shallow and deep 3.2 Pavement Design
potholes which required extensive patching. The pavement design life adopted for bituminous layers
It was decided to investigate the specific cause(s) of was 10 years of stage construction option and the
premature pavement distresses on the entire project by underlying base and subbase layers were designed for
full operation period of 20 years. Both the bituminous
systematic sampling and testing so that suitable remedial
and granular layers design life period was adopted as per
measures could be recommended.
Indian Roads Congress IRC:37–2001, “Guidelines for
2. OBJECTIVE Designing Flexible Pavements”.
The objectives of this investigation were (a) prepare a For the entire project road (new construction and
systematic pavement evaluation plan for each section; reconstruction of existing lanes) flexible pavement
(b) conduct a visual inspection of the pavement surface; thickness was adopted in accordance with IRC:37-2001
1. Associate Director Emeritus, National Center for Asphalt Technology (NCAT), Auburn University, USA (currently at Jaipur)
Email: pkandhal@gmail.com
2. Professor of Civil Engineering, Indian Institute of Technology Madras, Chennai, Email: av@iitm.ac.in
and strengthening of the existing two-lane carriageway Bituminous Macadam (DBM) layers was considered as
flexible overlay thickness was adopted in accordance 1700 MPa and the Poisson’s ratio for BC and DBM layer
with IRC:81-1997. The four-lane pavement design was was considered 0.5. The statistical level of reliability
completed using the mechanistic method of pavement used in the design was 80 percent. Design CBR of 15%
design. was considered.
Vehicular movement on the project road indicated that The VDF values adopted in pavement design based on
the traffic pattern was significantly different along the traffic survey for two-axle, three-axle and multi-axle
length of the project. Therefore, this project road was tracks are 1.40, 2.57 and 3.27 respectively for the up
divided into two different homogenous sections as direction and these values were 2.30, 5.69 and 15.10 in
shown in Table 1. the down direction.
Table 1: Homogeneous Section-wise Cumulative Traffic The actual tensile strain values were calculated using in
the FPAVE program as per IRC:37-2001, and the actual
Homogeneous Design Chainage, 10 Year msa
strains were computed using various trial pavement
Section km
LHS RHS structural layer combinations. The tyre pressure used for
1 0+000 to 35+000 70 70 the analysis was 0.56 MPa and standard axle used was
dual type, having a mass of 8160 kg. This resulted in
2 35+000 to 50+000 68 95 consideration of single tyre load of 20,500 N.
The pavement temperature was considered as 35°C. In Pavement thicknesses adopted
accordance with IRC:37-2001, the resilient modulus Tables 2 and 3 show homogeneous section-wise adopted
(Mr) of the Bituminous Concrete (BC) and Dense MSA, CBR and pavement thickness values.
Table 2: Thickness of Pavement Layers (LHS Side)
The thickness of BC ranged from 40 to 50 mm whereas Specifications. The subgrade was constructed using
the DBM consisted of a single layer 100 mm thick. soils with 15% CBR from identified borrow areas. The
3.3 Pavement Construction and Quality Control pavement design was based on the 4-day soaked CBR
at maximum dry density. The construction and quality
General
control tests were carried out as per agreed Project
The pavement layers’ construction was carried out with Quality Plan.
the materials satisfying the “MORTH Specifications for
Granular Subbase (GSB)
Road and Bridge Works (4th Revision)”. The Project
Quality Plan (PQP) was submitted and approved by The construction of GSB was carried out as per Clause
Independent Engineer. The construction activities were 401 of MORTH Specifications (4th Revision). Grading
carried out as per the submitted PQP. The detailed I as per Table 400-1 was used. The construction and
description of various layers of construction is described quality control tests were carried out as per agreed
below: Project Quality Plan.
Subgrade Wet Mix Macadam (WMM)
The construction of subgrade was carried out as per The construction of WMM Layer was carried out as per
the specifications of the clause 305 of the MORTH Clause 406 of MoRTH (4th Revision). The construction
and quality control tests were carried out as per agreed from this test pit. [This was later changed to an
Project Quality Plan. extra 150-mm diameter core because the pits were
Bituminous Layers taking too long. This extra core was brought to the
testing laboratory; warmed at 110 °C; and opened
The BC and DBM layers were constructed in the project to examine stripping, if any.]
as follows:
• Five (5) test pits along the edge of the pavement near
The BC layer was constructed with Polymer Modified shoulder to test the in-situ density of WMM, GSB,
Bitumen Grade PMB-40. The DBM layer was and subgrade and take samples of all three both
constructed with VG-30 Bitumen. The bituminous layers’ for determining in-situ moisture content, optimum
construction was carried out after duly applying the moisture content, optimum dry density; gradation
prime coat and tack coat as per MORTH specifications. and PI in the laboratory. Subgrade samples were
The construction of DBM and BC layers were carried out also used to determine the in-situ CBR values.
as per the clause 507 and 509 of MORTH Specifications. • Two (2) coring right on the crack to examine the
All aggregates met the MORTH requirements. depth of the crack within the pavement (only in
4 PAVEMENT EVALUATION PLAN distressed section).
The pavement evaluation plan consisted of the following Total number of samples to be collected from project
steps: site and pits to be dug in both poor and good sections:
4.1 Review of Mix Designs • 150-mm diameter cores = 6×2 = 12
• 150-mm diameter cores directly on cracks = 2 ×1 =
Hot mix asphalt mix designs of BC and DBM involved
2 (poor sections only)
in the construction of this project were studied in detail
• Edge pits for testing WMM, GSB, and subgrade =
before inspection of the projectroad to ensure Marshall
2×3×5 = 30
Mix Design data met the specifications.
4.2 Sampling Plan
It was proposed to locate a representative “distressed” or
poor section and a relatively “good” section on this project.
These sections were intended to be at least 500 m long;
cores to be obtained in the lane adjacent to the median,
which carries truck traffic; and cores to be obtained in
the wheel track near the median in that lane. This type of
approach for systematic pavement investigation has been
used successfully across the world by the first writer in
the past[1]. Comparison of the test data from relatively
good and poor areas is generally helpful in isolating the
cause(s) of poor performance. Moreover, it also gives the Fig.1. Sampling Plan
general range of pavement test properties on the project 4.3 Testing Plan
being investigated. This approach is highly successful if
only one primary distress type is being investigated, it Full depth cores of BC and DBM were brought to the
may be cracking; rutting; or raveling/potholes. laboratory and evaluated for poke marks (generally
indicate inadequate density) and stripping. Layer
Fig.1 shows the sampling plan for a typical “distressed” thicknesses were measured before sawing to separate
(poor) or “good” section which involves the following: BC and DBM layers. Also, the bond between the two
• Five (5) 150-mm diameter cores to comprise BC asphalt layers was evaluated before sawing. Bulk
and DBM layers (subjectively evaluate the adhesion specific gravity was obtained for BC and DBM layers.
between the two asphalt layers during coring). Cores were then warmed at 110°C or so to crumble them
• One (1) small test pit about 750 mm by 750 mm and evaluate % stripping in the mix, if any. Photograph
in the middle of the 500 m test section in line were taken of some typical stripped mixes. Extraction
with cores to visually examine the condition of test was then conducted on the loose, crumbled mix
in-situ BC and DBM (especially stripping). Also, to determine bitumen content and gradation. Gmm was
obtain samples of BC and DBM for determination measured on the loose mix of BC and DBM obtained
of maximum specific gravity (Gmm) of the mixes from the extra 150 mm diameter core. Gmm was measured
after heating and remixing the loose mix to ensure all with white fines from the WMM had oozed out of the full
aggregate particles are coated with bitumen. depth cracks in Fig. 3.
Total number of Tests Core taken directly on the crack (Fig. 5) showed the
• Measurement of thickness of each asphalt layer in bottom up crack traversing both DBM and BC. That is
full depth cores = 2×2 × 5 = 20 why; fines from the WMM were brought up to the road
• Bulk specific gravity of cores = 2×10 = 20 surface by moisture/water.
• Gmm of loose samples (BC and DBM) obtained from All core samples were brought to the testing
extra cores = 2 ×2 = 4 laboratory and tested. As mentioned earlier, in lieu
• Visual evaluation of stripping in 2 layers of all cores of excavating a 750 mm by 750 mm pit, an extra
= 2×10 = 20 150-mm diameter core was taken which was warmed
• Extractions (bitumen content and gradation) of BC in the laboratory at 110°C opened up, and both BC
and DBM=2×10 = 20 and DBM evaluated for stripping. Table 4 gives the
• WMM Tests (in-situ moisture content; in-situ details of thicknesses, condition of bond between
density; optimum dry density; optimum moisture DBM and BC, and observation of stripping within
content; gradation; and PI = 10 mixes for all cores.
• GSB Tests (in-situ moisture content; in-situ density;
optimum dry density; optimum moisture content;
gradation; and PI = 10
• Subgrade Tests: gradation; moisture content; LL;
PL; PI; in-situ density; and in-situ CBR = 10
4.4 Summary and Tabulation of Test Data
All necessary calculations such as % air voids and %
compaction of WMM and GSB were made. Then, all
test data were tabulated along with JMF values and
specification limits. Mean, standard deviation, and 95%
confidence limits (CL)were calculated for all 5-test data
each for relatively good and poor (distressed) sections and
reported on one sheet for comparison. The meaning of 95%
CL means: if 100 samples (not 5) are taken of the same
material, 95 samples would statistically have the property
within the CL or range. Thicknesses of bituminous courses
and bond between the DBM and BC (yes or no) were also Fig. 2. Typical Fatigue Cracking
reported on one sheet for each section.
5. VISUAL INSPECTION, TEST RESULTS,
CONCLUSIONS, AND RECOMMENDED
REMEDIAL MEASURES
Tentative selection of relatively good and poor areas
was made prior to the field inspection based on details
of distresses noted after the first monsoon since
construction. These areas were then finalized during this
inspection.
Both good and poor areas were selected on normal height
embankments. Although road surface appeared to be dry
and raveled at many places, the predominant distress
on this road is medium to high severity (alligator)
cracking mostly on the wheel tracks of the inside lane
(next to median). Fig. 2 shows typical fatigue cracking
(sometimes in form of block cracking) in the lane. Figs.3 Fig. 3. Close-up View of Fatigue Cracks also Showing White
and 4 show close-ups of the cracks. Note that water laden Stains of Fines Brought up from WMM
In-Situ Air Voids: At the present time, the mean air voids in Grading 1 is also prone to segregation and potholing
good and poor areas are 9.0 and 8.8 percent, respectively. which was also the case on this project[2].
This is unacceptable because at the time of construction
WMM (Table 7)
more than two years ago these values must have been
10% or even more. The DBM was also used by traffic Gradation: Although within the specified MORTH
before laying the BC, which causes some densification. range, the gradation of WMM both in good and poor
MORTH does not allow more than 8% air voids at the areas is on the fine side. The material passing 0.075
time of construction. As discussed in detail in BC above, mm should not exceed 8% as per MORTH. However,
high air voids cause the mix to be brittle (due to aging) it is excessive: 13.4% in good area and 13.7% in poor
and prone to raveling and cracking. Asphalt pavement area. According to Yoder[3], excessive fines interfere
with more than 8% air voids has interconnected voids with the interlocking of aggregate in the WMM and
which allow water intrusion into the pavement during therefore lower its structural strength. Once water gets
rains. That is why, such pavements develop problems into the WMM through cracks in the asphalt courses,
such as potholes during the monsoon. it becomes weaker and weaker and does not provide
As a rule, DBM Grading 1 which was used on in this adequate support to the overlying asphalt courses. Fines
section is generally more permeable than DBM Grading from the WMM have been brought to the road surface as
2 and therefore should not have been used at all. DBM mentioned earlier (Fig. 3).
Table 4. Condition of Cores
MORTH Good Area Poor Area
Spec. or
Test Property Location no. Std. Location no. Std. 95%
Project Mean 95% CL Mean
Spec. 1 2 3 4 5 Dev. 1 2 3 4 5 6 Dev. CL
109-
Thickness, mm 143 145 122 133 112 131 14 103-159 131 141 118 129 116 136 129 10
149
76-
DBM 100 101 102 79 92 75 90 12 66-114 104 97 83 89 86 102 94 9
112
BC 40 or 50 42 43 43 41 37 41 2 37-45 27 44 35 40 30 34 35 6 23-47
Bond between
Yes Yes Yes Yes Yes - - - Yes Yes Yes Yes Yes Yes - - -
DBM and BC
% Stripping in Mix
DBM None None
BC None None
Plasticity Index (PI): According to MORTH, PI of However, the mean density is 95% in the good area and
WMM should not exceed 6 percent. However, it is much lower, that is, 92% in the poor area. Both values
borderline (6) in the good area and exceeds (7) in the indicate inadequate compaction in the field, which
poor area. WMM with high PI, lose strength in presence further reduces the strength of the WMM.
of water. Granular Sub-Base (GSB) (Table 8)
In-Situ Density: The in-situ density of WMM should Gradation: The gradation of GSB in the poor area is
be at least 98% of optimum dry density (MORTH). finer all the way and is outside the range of MORTH
caused the premature distresses. This is rather unusual. iii. Intrusion of rainwater in the pavement system
Generally, one or two pavement courses are substandard from the surface including the full depth cracks is
in the poor area and therefore can be isolated as cause(s) causing serious problems in terms of disintegration
for premature distress. (potholes/loss of surface). The recommended
overlay system must ensure “complete sealing” of
Recommended Remedial Measures
the existing pavement.
This project experienced substantial distresses during the iv. The existing pavement has bottom up fatigue
first, second and third monsoons since it was constructed. cracking and therefore may not provide resistance
As immediate measure, all potholes should be repaired. to tensile strains. The new asphalt overlay must
The areas which show severe loss of road surface have its “own” reinforcement system to (a) resist
should be milled off and replaced with BC Grading 2 tensile strains at its bottom; (b) arrest cracking; and
(with gradation on the finer side of the JMF) containing (c) increase its fatigue life.
elastomeric PMB-40. [This work was carried out soon v. Despite its “own” reinforcement, the new asphalt
after this field evaluation.] These measures would ensure overlay would be subjected to extraordinary
the safety and comfort of the motoring public. stresses and strains due to inadequate support of
Then, pavement deflections should be measured on the the underlying courses. Therefore, the new asphalt
entire project using a falling weight deflectometer (FWD) overlay should be more flexible than BC Grading
which is more reliable and faster than the Benkelman 2; resistant to reflection cracking; and highly rut
Beam. Plot the results on a linear graph. Use IRC:81- resistant at the same time.
1997 to determine the thickness of asphalt overlay to Ideally, all pavement courses which are substandard
bring deflections below the acceptable level or IRC:115- should be replaced. However, it is not practical nor
2014 should be used. economical. Therefore, the following remedial measures
Conduct a “broad” survey of the road surface in this are recommended for Type A Category:
section to identify the following three (3) road surface i. Mill off the existing BC Grading 2 exhibiting
categories: alligator cracks and/or block cracking and replace
Type A with BC Grading 2 (redesigned with finer gradation)
containing elastomeric PMB-40 from a reliable
Road surface showing “severe” fatigue cracks (alligator international supplier. Ensure good quality control
type) in the wheel tracks and/or block cracks in the entire in mix production and compaction.
lane. ii. Provide a composite (combination) of non-
Type B woven geotextile (GT) paving fabric (which is
Road surface showing “moderate” fatigue cracks (one or continuous and has polyester and glass fibers) and
two longitudinal cracks in the wheel track). This surface a glass fiber grid reinforcement. The quality of the
is likely to become Type A in the near future. composite GT should conform to IRC: SP:59-2002.
Application should consist of heavy tack coat of
Type C VG-30 bitumen (not emulsion) at a rate specified
Surface showing no fatigue cracks. There is no guarantee by the manufacturer of GT paving fabric. The
that fatigue cracks would not appear in the future given nonwoven geotextile together with heavy tack coat
the substandard quality of underlying pavement courses would ensure “complete sealing” of the existing
(even in the good areas) unless proven otherwise with pavement. The glass fiber geogrid would provide
additional explorations like this one. “reinforcement” to the overlying 50 mm asphalt
Type A Recommended Remedial Measures overlay to resist tensile stresses at its bottom. It
would also prevent lateral movement of the overlay
Any suggested remedial measures should take into asphalt mix.
consideration the following: iii. Provide 50 mm of Stone Matrix Asphalt (SMA)
i. All or most of the pavement courses are substandard in accordance with IRC:SP:79-2008 (drafted by
in quality. the first author) containing elastomeric PMB-40
ii. Alligatored BC cannot be kept within the pavement over the composite geotextile. A minimum asphalt
system because it is shattered and therefore likely overlay thickness of 50 mm is required over
to cause problems in future if overlaid without geotextile. Although SMA is preferred, BC Grading
removal from the distressed areas. 2 with highly modified asphalt binder HiMA can
also be considered. HiMA has about 7% SBS systematic sampling and testing so that suitable remedial
polymer compared to about 3% SBS in conventional measures could be recommended.
PMBs. Research at NCAT Test Track in the US has In general, good quality control of various pavement
shown it is highly resistant to rutting and fatigue courses was not exercised during construction, which
cracking. Due to its higher structural strength, 41 led generally to the development of “bottom up”
mm of BC with HiMA is approximately equivalent fatigue cracking on this project. The following general
to 50 mm of BC with conventional PMB. HiMA is deficiencies were noted on this project:
commercially available in India.
Subgrade: CBR values from the trial pits of 6 in good
iv. If the pavement deflection analyses show that
area and 4 in the poor area were less than the CBR value
asphalt overlay should be more than 50 mm, then
of 15 used in the structural design of this project. This
additional BC Grading 2 overlay should be provided
apart from inadequate compaction of the subgrade layer
prior to laying the geotextile.
resulted in an under designed pavement.
Type B Recommended Remedial Measures
Granular Subbase (GSB): Gradation; plasticity
Same as Type A above except that the existing BC need index (PI) and % compaction did not meet MORTH
not be milled off and replaced. However, all potholes and requirements. This results in poor subsurface drainage
surface deficiencies of existing BC should be corrected. and inadequate support to the overlying pavement
Cracks over 5 mm wide should be filled with hot asphalt- courses especially in presence of water.
rubber or hot VG-30 bitumen. Do not use emulsion
which would shrink when about 35% water contained in Wet Mix Macadam (WMM): Gradation; plasticity
it evaporates. index (PI) and % compaction did not meet MORTH
requirements. This results in weak WMM which provides
Type C Recommended Remedial Measures inadequate support to the overlying pavement courses
In case the deflection analysis does not require any especially in presence of water.
asphalt overlay, apply Microsurfacing Grade III (6 Dense Bituminous Macadam (DBM) Base Course:
to 8 mm) in accordance with IRC:SP:81-2008 to the DBM has excessive air voids (due to inadequate
existing road surface to seal it from moisture intrusion compaction) which allow water intrusion during rains
as a preventive maintenance. Then, it would be a matter causing potholes. High air voids also make the mix more
of “wait and watch”. If fatigue cracks start to develop, prone to cracking. Some DBM mixes contained soft,
use Type B remedial measures. In case, the deflection friable aggregate most likely from quarry overburden.
analysis requires an asphalt overlay, use 40 mm or 50 Also, traffic allowed on the DBM during construction
mm SMA rather than BC Grading 2 considering the before placing the BC can induce bottom up fatigue
substandard quality of underlying courses, unless proven cracking in it. These cracks then reflect though the BC
otherwise after explorations like this one. at a later date.
6. SUMMARY Bituminous Concrete (BC) Wearing Course: Deficient
On completion of the four-laning of this 50-km national bitumen content; gradation outside JMF tolerances
highway, premature pavement distresses were observed (generally coarser which allows intrusion of rainwater);
on it during the first monsoon. The following pavement and high air voids (due to poor compaction) made the mix
distresses were observed: open surface texture; raveling; more prone to cracking. Some BC mixes contained soft,
hungry surface; alligator cracks; and potholes. By far, friable aggregate most likely from quarry overburden. In
premature fatigue cracking was the primary distress most cases, BC did not provide an impermeable surface
ranging from moderate cracking (one to two cracks in for the pavement to prevent water intrusion.
wheel path) to severe cracking (alligator cracks in the Based on preceding deficiencies, all five pavement
wheel path or block cracks across the lane). Therefore, courses were substandard in quality. This resulted in a
this was the primary focus of this investigation. rather complex investigation, where the relatively good
Further successive deterioration of pavement occurred area also had serious deficiencies in case of some test
during the second and third monsoons. Several areas of parameters.
severe alligator cracks also developed shallow and deep It has been recommended that pavement deflections
potholes which required extensive patching. should be measured on the entire project using a falling
It was decided to investigate the specific causes of weight deflectometer (FWD). Plot the results on a linear
premature pavement distresses on the entire project by graph. Use IRC: 81-1997 or IRC:115-2014 to determine
the thickness of asphalt overlay to bring deflections asphalt (SMA). If two sets of extractions (bitumen
below the acceptable level, wherever needed. content and gradation) and Marshall tests are faithfully
Conduct a “broad” survey of the road surface on the done every day as per MORTH requirements, there is no
entire project to identify the following three (3) road reason as to how the quality can be compromised.
surface categories: 7. GENERAL RECOMMENDTIONS
Type A: Road surface showing “severe” fatigue cracks The following general recommendations are made so
(alligator type) in the wheel tracks and/or block cracks that major highways do not develop premature distresses
in the entire lane. as observed on this project:
Type B: Road surface showing “moderate” fatigue cracks (a) The pavement design life should not be based on
(one or two longitudinal cracks in the wheel track). This “stage construction” such as 10 years. Rather, it
surface is likely to become Type A in the near future. should be for the full operational period.
Type C: Surface showing no fatigue cracks. There is (b) Construction quality control (QC) needs to be
no guarantee that fatigue cracks would not appear in exercised by the contractor and quality assurance
the future given the substandard quality of underlying (QA) should be exercised by the concessionaire/
pavement courses (even in the good areas) unless proven Independent Engineer (IE) – both were lacking on
otherwise with additional explorations like this one. this project.
Type A Recommended Remedial Measures (c) DBM base course should not be used by traffic for
long periods of time; it should be overlaid with BC
Details are given in the body of this paper. Briefly, remedial
as soon as possible so that bottom-up fatigue cracks
measures consist of (a) mill off existing BC Grading 2
and replace with new BC Grading 2 with elastomeric do not develop in DBM due to reduced pavement
PMB-40 Bitumen; (b) provide a composite geotextile thickness.
paving fabric and glass fiber grid reinforcement; and (c) (d) Although not applicable to this project, the thickness
provide 50 mm of Stone Matrix Asphalt. of DBM should not be reduced when modified
binders are used. This is technically unwarranted
Type B Recommended Remedial Measures
and would further aggravate the problem of under
Same as Type A above except that the existing BC need designing the pavement structure.
not be milled off and replaced. However, all potholes and (e) If subgrade is constructed with high CBR soil from
surface deficiencies of existing BC should be corrected. identified borrow areas, it should be ensured that
Cracks over 5 mm wide should be filled with hot asphalt- local soil with low CBR value is not used.
rubber or hot VG-30 bitumen, not emulsion.
8. BIBLIOGRAPHY
Type C Recommended Remedial Measures
1. Kandhal, Prithvi Singh, “Bituminous Road
In case the deflection analysis does not require any Construction in India”. Textbook. Prentice Hall of
asphalt overlay, apply Micro surfacing Grade III (6 to 8 India, New Delhi, July 2016.
mm) in accordance with IRC:SP:81-2008 to the existing
2. Kandhal, P.S. and A. Veeraragavan, “Review of
road surface to seal it from moisture intrusion. Then, it
Practices for Improving Ride Quality and Periodical
would be a matter of “wait and watch
Renewal of Bituminous Pavements in India”. Paper
Quality Control No. 662. Journal of the Indian Roads Congress,
In all remedial measures, strict quality control need to Volume 77-3, October-December 2016.
be exercised during bituminous mix production and 3. Yoder, E.J., “Principles of Pavement Design”. John
compaction. It is especially important for stone matrix Wiley & Sons, New York, 1965.