Professional Documents
Culture Documents
and Safety
S. ZARDYNEZHAD, Contributing Writer,
Calgary, Alberta, Canada
the vents are equipped with environmental controls and flame This design is most common in EFRTs, based on the au-
arresters/diverters to capture emissions. thor’s experience. To weld the outside angle between the deck
An EFRT comprises vertical steel cylinders with a roof that plate and the outer ring plate (FIG. 5), the design of the angle
floats on the surface of the liquid in the tank. It is open to the should be modified, as shown in FIG. 6. Basically, the outer ring
atmosphere above; i.e., there is no fixed roof above the floating plate of the pontoon is extended vertically to make a 90° angle
roof. The risk of a fire in this type of tank is very high and prob- with the deck plate. This will allow the welder to weld the angle
able because the wetted shells are open to atmosphere when the from below the deck when the deck sits on supports. In FIG. 3,
floating roof travels downward. In addition, any leak could re- the deck plate is extended horizontally rather than the outer
sult in stock on the deck, which can cause a fire. Pontoon failure ring plate extending vertically, as shown in FIG. 6. The details
of the EFRT is another source of accident and can be caused by shown in FIGS. 3 and 5 may cause leakage of the liquid to the
several factors, including an incorrect selection of weld design. pontoon and sink the roof accordingly, causing many problems
FIG. 2 shows welding inside the pontoon, which is normally in- (even during hydrostatic test operations).
complete in length. Welding outside the pontoon (FIG. 3) can- Rim-seal fires are the main cause of a large majority of EFRT
not be done due to limited access and space between the tank fires, and can occur in IFRTs, as well. Lightning is the primary
shell and outer ring of the pontoon, which is 300 mm–400 mm. source of ignition for rim fires for EFRTs, and an induced electri-
This clearance will not provide suitable access to weld the outer cal charge may also spark ignition.
ring plate to the deck plate, as shown in FIG. 4. In addition to manual semi-fixed or fully-fixed, rim-seal fire
FIG. 2. Welding inside the pontoon is normally incomplete FIG. 3. Limited access between the tank shell and outer ring of the
in length. pontoon prohibits welding.
TABLE 1. Inputs, tools and techniques, and outputs of risk-identification processes for AAST design activities
Inputs Tools and techniques Outputs
Equipment criticality table Expert judgment Risk register
Technical document and drawing Design review
Decision criteria Information gathering techniques
FMEA for each tank Group creativity techniques
Hidden failure study Analytic hierarchy process (AHP)
Mean-time between failures (MTBF) Assumption validity analysis
Causes of accidents/lessons learned Diagnostic techniques
Technical deviations
Prototype design identification
Plant layout
Plant hazard identification/HAZOP
Plant safety philosophy
Stockholder register and analysis
Community/neighborhood study
Codes, standards and regulations
78 OCTOBER 2017 | HydrocarbonProcessing.com
Environment and Safety
protection systems, an automatic foam injection system mount- welded to the tank surfaces (FIG. 9). At the very least, the num-
ed on the floating roof deck in different locations should be con- ber of fixed cooling piping rings should cover from the top to
sidered to cover 360° and quickly inject foam to the rim seal. near the middle of the tank surface.
Rim-seal fires for IFRTs are more difficult to combat compared
to EFRTs—particularly when semi-fixed or fully-fixed systems Tank height. Careful selection of tank height is important, as
are not considered by the designer—because the only access for it affects firefighting operations and productivity. Designers
fire extinguishing is through the vents or access covers on the prefer to reduce AAST diameter and increase the height for the
fixed roof (FIG. 7). following reasons:
• To provide positive head for unloading pumps
Layout. One key aspect of AAST design is determining the best [The AAST must always remain filled above the
location (for cost minimization, required safety, etc.) for the “low pump-out” level (LPO) during operation,
AAST during the preparation of the plant plot plan. If a plant which is a fixed distance above the bottom of the tank]
is on a slope and must be designed over several terraces, design- • The cost of a floating roof is proportionally higher
ers sometimes install the feed and intermediate products of than that of a shell for a given tank capacity
the AAST upstream of the process plant to minimize costs and • To reduce the bottom surface area, shorten the maximum
pumping power requirements. However, if the large-feed AAST
collapses due to fire, then the fire and hydrocarbon liquid may Outer ring plate Welding is not possible
reach the plant and create a dangerous and out-of-control situa-
tion. It is better to install the tanks downstream of the plant on Inner ring plate
the slope—the overall plant layout should be carefully studied
on a case-by-case basis. Shell plate
The surrounding areas and a suitable number of access routes
to the tank’s location have significant impacts on firefighting
Pontoon 300 mm–400 mm
activities and success. Safe distances from other process equip-
ment must be calculated. The layout and distance of the hydrant FIG. 5. A method of pontoon welding design.
and monitors around/to each tank should be carefully studied,
and decisions should be based on the number of tanks in each
area, wind direction, migration of fire risk to adjacent tanks, etc. Outer ring plate
Water supply. A large volume of water is critical during AAST Inner ring plate
firefighting operations for cooling and extinguishing purposes.
If the plant is located near the sea, connecting the main fire-wa- Shell plate
ter piping system to the seawater in case of emergency is highly
recommended. Also, during the design phase, consider suitable Pontoon
portable or fixed monitors around the tank to cool it evenly. Un- 300 mm–400 mm
even cooling of the AAST will allow the tank shell to soften and
ultimately fail where the uneven cooling was applied (FIG. 8). Welding is now possible from under the deck
The fixed cooling piping rings and associated supports in-
stalled around the tank perimeter are suitable for working under FIG. 6. Recommended method of pontoon welding design.
high-temperature conditions as a result of fire, and are carefully
FIG. 4. The limited space between the tank shell and the outer ring
of the pontoon. FIG. 7. Automatic foam injection-deck mounted.
distance to sump and minimize the formation of ing AAST operations: slop-over, froth-over, boil-over and py-
“bird baths” rophoric ignitions.
• To reduce vapor space in fixed-roof tanks
• To reduce the cost of foundation, cathodic protection, Dike designs. Dikes around the AAST serve two main purposes:
earth work, etc. • Provide a physical barrier to prevent the spread of
The recommended height of an AAST is a maximum of 15 tank contents if the tank overflows, or if the tank
m, depending on land acquisition and cost limitations. It is im- structure fails due to corrosion or other causes
portant that the fire-water stream’s trajectory can reach to the • Segregate and group tanks according to their
top of the tank. During a fire, obstructed full liquid surface content classifications.
fires can occur in a fixed roof, EFRT and IFRT. The roof or pan Dike types and materials (i.e., compacted earth, concrete or
blocks access to the burning surface, and this becomes more dif- other material) are carefully selected and designed. The dike’s di-
ficult when the tank’s height is increased. If the tank height can- mensions (height, perimeter, etc.) are functions of the volume of
not be limited at 15 m, then an elevated monitor tower should the tanks enclosed within a particular dike area. Dike design must
be considered to allow fire water or foam to reach the top of the consider containment of the tank’s total contents, and it should be
tank for firefighting and cooling. designed according to the volume of the largest tank, plus an ad-
ditional percentage as a safety margin (FIG. 10). The dike’s waste
Open flames. Hot particles can ignite flammable vapors around and rainwater drain piping system should be furnished with a
an AAST. The risk of explosion of process equipment, such as suitable gate valve located safely outside the dike area: that valve
large process towers, should be considered during plant layout, should be normally closed with a proper locking device. Equip-
and a safe distance should be determined following risk and other ment, lighting towers, transformers, etc., should also be installed
required studies. In a fire case at a mega petrochemical plant, a outside the dike area, and all openings on the dike walls should be
large process tower, with a height that exceeded 120 m, exploded carefully and completely sealed by proper materials.
due to an increase of internal pressure caused by overheating. Hot
flying particles reached an EFRT that was used to store naphtha, Emergency pumpouts. During firefighting, it is sometimes
igniting a large fire. If the tank had been an IFRT rather than an necessary to decrease the volume or level of flammable and com-
EFRT for this service, then the accident may not have happened. bustible liquid inside the tank as quickly as possible, particularly
for floating-roof tanks where decks or pans block access to the
Static electricity. Friction between two sliding or rolling parts burning surface. Eliminating combustible material greatly as-
made of different materials or substances generates static elec- sists firefighting efforts. Designers should check the capacity of
tricity. The electrical charges on the surface of the objects bal- tank unloading pumps—particularly large tanks—and consider
ance each other by the free flow of electrons. However, when proper margins that allow higher flowrates when needed, such
they are separated, each part is left with an extra or shortage of as using variable frequency drives (VFD) and parallel opera-
electrons, causing both parts to become electrically charged. tions. The temperature of the tank’s contents during a fire will be
When the produced charges lack a rout to the ground (e.g., increased, and designers should consider this when considering
by grounding probe or wire), the charges create static electricity, materials and pump seal selections, as well as the transfer of hot
which, if not eliminated from the system, will build up and change liquid to other tanks during the fire. However, when the prod-
to a spark to a grounded part or another less highly charged part. uct is removed from the tank that is on fire, air is drawn into the
If a flammable or combustible vapor or dust mixture exists, as vapor space as liquid is removed, creating a hazard and bringing
in a hydrocarbon AAST, the result can be a fire or an explosion. more oxygen into the tank. This must also be considered.
Static electricity can build up during liquid transfer and
through contact with other materials, such as when liquid is Roof plate joint designs. The details of fixed-roof AAST
pumped to a tank, agitated inside, stirred or transferred in pip- joints (including the fixed roof for an IFRT) are shown in
ing. Designers should consider suitable designs and materials In the author’s opinion, this joint design is unsuitable
FIG. 11.3
to eliminate the risk of fire due to static electricity. because the vapor inside the tank can be diffused and trapped
between the gap of two roof plates (e.g., A and B) and condensed
Special design considerations. Designers should remain by changing the ambient temperature or roof plate temperature.
aware of, and plan to prevent, the following phenomena dur- This configuration helps sever the corrosion condition that
can happen between the two plates when
the vapor contains a corrosive element
(e.g., the high sulfur content in gasoil).
As the author was inspecting a gasoil
tank in an oil refinery with a high sulfur
content run for 30 yr, part of the roof be-
neath his feet broke. A detailed root study
showed high corrosion in the gap between
the two plates. An alternative to prevent
trapped vapor in the gap is to install plate
FIG. 8. Steel tank softens and fails when FIG. 9. Cooling piping supports soften. A on plate B, and plate C below plate B,
heated. (Photo courtesy of Shana.) (Photo courtesy of Shana.) and so on. This configuration causes the
80 OCTOBER 2017 | HydrocarbonProcessing.com
Environment and Safety
condensed vapor to be drained from the gap between the roof level, different shell courses may have different corrosion allow-
plates. This is not in compliance with API 650 (11th Ed.) and ances. The corrosion allowances for removable parts, such as pipe
should not be used without API and designer approval. How- spools, and permanently welded parts, such as columns, should
ever, the author believes that this alternative supplements the be considered. The roof structure may also require a corrosion
standard design where highly corrosive vapor exists. allowance, particularly if the service and vapor are corrosive.
Frangible roof joint designs. Clause 5.10.2.6 of API 650 Column design. The following example illustrates the design
(11th Ed.) allows a frangible roof joint design for fixed-roof of columns. A project has two aboveground atmospheric AASTs
AASTs, after securing purchaser approval. This is not a man- with IFRTs, each with a diameter of 70 m and a height of 15 m.
datory requirement as per API 650, but rather a recommended Each AAST is being designed by a different engineer. One en-
practice for emergency venting. (This causes the roof-to-shell gineer considers a fixed dome roof with 130 columns of 6 in. to
joint of the tank to fail before the shell-to-bottom plate or an- 12 in., and the other is designing a dome roof without columns
nular plates in the event of excess internal pressure, preventing and with a self-supported roof. Both meet code requirements
tank collapse and catastrophic failure.) In this case, the design in terms of roof stability and strength. The fixed-roof columns
pressure is limited to the equivalent pressure of the dead weight pose the following disadvantages:
of the roof plates, including structural rafters. • They must penetrate into the floating roof/pan,
The designer should explain this API 650 requirement and causing vapor or liquid leakage from the opening and
its respective advantages to the purchaser. If the frangible joint requiring extra costs for sealing around the opening.
is designed and fabricated carefully, the roof will only be sepa- • They occupy the volume of the tank.
rated, causing a “fish mouth” opening and not rocketing the roof • They require inspection during operation and extra cost
into the air. for scaffolding.
• Corrosion may occur on the surfaces of the columns.
Brittle fractures. Knowing the type and range of fluid, operat- • They need adjustment and added shims after a field
ing temperature, design life, geographic location and minimum hydrostatic test to prevent roof damage due to foundation
design metal temperature (MDMT) for the plates is important. settlement.
MDMT defines which grade of steel is necessary to prevent • They increase the cost of the project.
brittle fracture, and is the basis for establishing the required • They may obstruct future inspections of the bottom, roof
toughness for the selected steel. plates and respective welds.
The susceptibility of the material to brittle fracture—the It is recommended to minimize the number of columns for
tensile failure of a material showing little deformation or yield- the AAST and, preferably, design the tank without the column.
ing—is one of the most important material selection consider-
ations for an AAST. Literature provides evidence regarding tank Nozzle stress relief. API 650 (clauses 5.7.4.2 and 5.7.4.3) re-
failure due to brittle fracture, even during hydrostatic tests.4 quires post-weld heat treatment (PWHT) for all nozzle open-
The designer should be aware of two ways to ensure that se- ings of 12 in. and larger that are fabricated in a certain shell ma-
lected steel for an AAST has adequate toughness for the tank’s terial group. API requires that nozzle openings are prefabricated
MDMT. The first is to proof-test each plate by impact tough- into the shell plate or thickened insert plate, and that the pre-
ness testing samples at or below the MDMT (e.g., using the fabricated assembly is thermally stress relieved together prior
Charpy V-notch method). The second method is purchasing a to installation. In the author’s experience, most contractors and
material with adequate toughness (preferably one with a “tran- vendors prefer to install nozzles in the field, do local PWHT
sition temperature” that is below the MDMT), eliminating the and request a deviation to API 650, as they normally erect and
need for expensive impact testing, which can add 5%–10% to weld the shell plates onsite without the nozzles to accelerate
the cost of the plate. construction activity.
Older codes, along with some newer codes, do not have
toughness requirements, such as the API 12 series standards
and the Underwriters Laboratories (UL) tank standards. API
650 has clearly defined a basis for impact testing and toughness
requirements of the plates in clauses 4.2.8 and 4.2.9, as briefly
explained in FIG. 12 for plate material of A 283-C (Group 1) and
an MDMT of 14°F (–10°C).
The best practice for selecting steel for tank construction is
to use steel above its ductile-to-brittle transition temperature. FIG. 10. Common dike for several AASTs.
This helps ensure that the steel has adequate toughness for the
temperature conditions at the specified geographical location. Plate C
Plate B
Corrosion allowance. The designer should clearly define the Plate A No seal weld; vapor/gas can enter
corrosion allowance for AAST components to meet both eco- between plates and condense by
nomic and safety requirements. Normally, 1.5 mm is the mini- Roof-plate joint temperature change
mum thickness for the shell, and 0.75 mm for the roof. However,
FIG. 11. Roof-plate joint as per Figure 5-3A of API 650.
based on the water/corrosive elements content and the water
Hydrocarbon Processing | OCTOBER 2017 81
Environment and Safety
Average value of
3 nos test < 41 J Reject
Thk. > 9-mm Impact test Table 4-4
Figure 4-1 is required
A 283-C Average value of
MDMT = –10°C 3 nos test > = 41 J
Thk. < = 9-mm Impact test Table 4-4
Figure 4-1 is not required
82 OCTOBER 2017 | HydrocarbonProcessing.com