You are on page 1of 24

HOJA RESUMEN DE VALORIZACION N°12

( AL 25 DE ABRIL DEL 2018)


CODIGO : 993462-CS20-G-AD-VAL-1016 - REV0
Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS Plazo Contractual : 150 días calendarios
Obra: OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION) Fecha de Inicio de Plazo : 4/20/2017
Cliente: SHOUGANG HIERRO PERU Ampliacion de Plazo : -
Contratista: CCCC DEL PERU Fecha de Termino de Plazo : 9/16/2017
Ubicación: MARCONA Gerente de Proyecto : ING. HAN XIU FENG
Fecha: 4/20/2018

PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS SEGÚN CONTRATO : PASHP-CS20-2017

FECHA CORRESPONDIENTE: ( AL 25 DE ABRIL DEL 2018) DEL 21 DE MARZO AL 20 DE ABRIL DEL 2018

PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS 1,603,993.36

Sub Total de Valorizacion ($) 2,066,556.12

AMORTIZACION ADELANTO DIRECTO ($) 517,931.59

SUB TOTAL DE VALORIZACION ($) 1,548,624.53

I.G.V. 18% 278,752.42

TOTAL A FACTURAR ($) 1,827,376.95

TOTAL VALORIZACION N°12 $ 1,827,376.95

ING. ENGELBERT CHAVEZ ING. HAN XIU FENG


COORDINADOR DE PROYECTO GERENTE DE PROYECTO
SHOUGANG HIERRO PERU CCCC DEL PERU
HOJA RESUMEN DE VALORIZACION N°12
( AL 25 DE ABRIL DEL 2018)
CODIGO : 993462-CS20-G-AD-VAL-1016

Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS Plazo Contractual : 150 días calendarios
Obra: OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION) Fecha de Inicio de Plazo : 4/20/2017
Cliente: SHOUGANG HIERRO PERU Ampliacion de Plazo : -
Contratista: CCCC DEL PERU Fecha de Termino de Plazo : 9/16/2017
Ubicación: MARCONA Gerente de Proyecto : ING. HAN XIU FENG
Fecha: 4/20/2018

ACUMULADO - ANTERIOR AVANCE ACTUAL (Monto Valorizado) ACUMULADO - ACTUAL SALDO


ITEM VALORIZACION MONTO CONTRACTUAL

% TOTAL % TOTAL % TOTAL % TOTAL

OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA,


01 10,478,259.00 80.16% 8,399,201.56 15.31% 1,603,993.36 95.47% 10,003,194.92 4.53% 475,064.08
SEPARADORES MAGNETICOS Y FLOTACION)

0.00

COSTO DIRECTO TOTAL 10,478,259.00 80.16% 8,399,201.56 15.31% 1,603,993.36 95.47% 10,003,194.92 4.53% 475,064.08

Gastos Generales 0.24838197 2,602,610.64 2,086,210.25 398,403.03 2,484,613.28 117,997.36

Utilidad 0.04 419,130.36 335,968.06 64,159.73 400,127.79 19,002.57

Sub Total 13,500,000.00 10,821,379.87 2,066,556.12 12,887,935.99 612,064.01

Amortizacion del Adelanto 0.2000 2,700,000.00 2,164,275.97 517,931.59 2,682,207.56 17,792.44

Sub Total 10,800,000.00 8,657,103.90 1,548,624.53 10,205,728.43 594,271.57

IGV (18%) 1,944,000.00 1,558,278.70 278,752.42 1,837,031.12 106,968.88

TOTAL NETO VALORIZADO 12,744,000.00 80.16% 10,215,382.59 14.34% 1,827,376.95 94.50% 12,042,759.54 5.50% 701,240.46
TOTAL NETO A COBRAR $ 10,215,382.59 1,827,376.95 12,042,759.54 701,240.46
RESUMEN GENERAL DE VALORIZACIONES
CODIGO : 993462-CS20-G-AD-VAL-1016

Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS Plazo Contractual : 150 días calendarios

Obra: OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION) Fecha de Inicio de Plazo : 4/20/2017

Cliente: SHOUGANG HIERRO PERU Ampliacion de Plazo : -


Contratista: CCCC DEL PERU Fecha de termino de Plazo : 9/16/2017
Ubicación: MARCONA Gerente de Proyecto : ING. HAN XIU FENG
Fecha: 4/20/2018

Amortizacion del SUB TOTAL I.G.V. IMPORTE NETO IMPORTE NETO


ITEM DESCRIPCIÒN FECHA Sub Total
Adelanto Directo (Sin IGV) 0.18 A FACTURAR A PAGAR ( $ )

01 Valorizacion N° 01 20-05-17 191,194.48 0.00 191,194.48 34,415.01 225,609.49 225,609.49

02 Valorizacion N° 02 20-06-17 536,091.90 0.00 536,091.90 96,496.54 632,588.44 632,588.44

03 Valorizacion N° 03 20-07-17 937,486.01 332,954.47 749,988.81 134,997.99 884,986.80 884,986.80

04 Valorizacion N° 04 20-08-17 3,062,495.57 612,499.11 2,449,996.46 440,999.36 2,890,995.82 2,890,995.82

05 Valorizacion N° 05 20-09-17 1,110,395.47 222,079.09 888,316.38 159,896.95 1,048,213.33 1,048,213.33

06 Valorizacion N° 06 20-10-17 1,609,639.73 321,927.95 1,287,711.78 231,788.12 1,519,499.90 1,519,499.90

07 Valorizacion N° 07 20-11-17 1,115,434.51 223,086.90 892,347.61 160,622.57 1,052,970.18 1,052,970.18

08 Valorizacion N° 08 20-12-17 1,254,699.72 252,882.24 1,001,817.48 180,327.15 1,182,144.63 1,182,144.63

09 Valorizacion N° 09 20-01-18 191,155.08 38,231.02 152,924.06 27,526.33 180,450.39 180,450.39

10 Valorizacion N° 10 20-02-18 56,428.01 11,285.60 45,142.41 8,125.63 53,268.04 53,268.04

11 Valorizacion N° 11 20-03-18 845,321.60 169,064.32 676,257.28 121,726.31 797,983.59 797,983.59

11 Valorizacion N° 12 20-04-18 2,066,556.12 517,931.59 1,548,624.53 278,752.42 1,827,376.95 1,827,376.95

TOTAL $ 13,202,516.58 2,701,942.29 10,420,413.18 1,875,674.38 12,296,087.56 12,296,087.56

ING. ENGELBERT CHAVEZ ING. HAN XIU FENG


COORDINADOR DE PROYECTO RESIDENTE DE OBRA
SHOUGANG HIERRO PERU CCCC DEL PERU
VALORIZACION N°12
( AL 25 DE ABRIL DEL 2018)

Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS


Obra: OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION)
Cliente: SHOUGANG HIERRO PERU
Contratista: CCCC DEL PERU
Ubicación: MARCONA
Fecha: 4/20/2018

PRESUPUESTO AVANCE ANTERIOR


Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
01.01 PARTIDAS COMUNES
01.01.01 CONSTRUCCIONES PROVISIONALES 115,494.93 0.00 109,720.19
01.01.01.01 Construcción de oficinas provisionales glb 1.00 97,331.66 97,331.66 0.95 92,465.08
01.01.01.02 Construcción de almacén, taller u otros glb 1.00 18,163.27 18,163.27 0.95 17,255.11
01.01.02 TRABAJOS PRELIMINARES 352,524.81 0.00 330,726.17
01.01.02.01 Traslado de maquinarias, equipos, herramientas y materiales a/d obra glb 1.00 119477.40 119,477.40 0.95 113,503.53
01.01.02.02 Trazo, niveles y replanteo (topografía permanente) glb 1.00 127770.87 127,770.87 0.95 121,382.33
01.01.02.03 Desquinche de taludes temporales de ser requerido m2 2,400.00 1.83 4,392.00 0.00 -

01.01.02.04 Mantenimiento de accesos principales, secundarios y temporales para la construcción (inc 1.00 100,884.54 100,884.54 0.95 95,840.31
mitigación de polvo) glb
01.01.03 OTROS 680,160.00 0.00 -
01.01.03.01 Tratamiento de Consolidación de macizo rocoso RQD<60% L - 6.37 - 0.00

6,500.00 104.64 680,160.00 0.00 -


Subcimiento concreto fc=100 kg/cm2 cemento tipo V de acuerdo a la especificación tecnica m3
02.01 MOVIMIENTO DE TIERRAS 0.00 -
02.01.01 Edificio Principal Molienda- Separavión Magnética - Celdas de Flotación 472,818.02 0.00 410,422.30
02.01.01.01 Excavación roca sana o fragmentada con equipo (-0.30m) m3 4,000.00 8.86 35,440.00 1,520.83 13,474.55
Excavación de terreno residual y aluvial m3 6,500.00 5.16 33,540.00 0.00 -
02.01.01.02 Relleno estructural de acuerdo a las especificaciones técnicas m3 24,068.00 15.14 364,389.52 25,816.80 390,866.35
02.01.01.03 Eliminación de material excedente c/equipo 1.7km aprox. m3 13,650.00 2.89 39,448.50 2,104.29 6,081.40
03.01 OBRAS DE CONCRETO 0.00 -

03.01.00.00 Planta Principal 8,244,008.35 0.00 7,222,439.61


5740;5750;5760
03.01.01.00 Solado m³ 615.00 104.64 64,353.60 593.97 62,152.98
03.01.02.00 Cimiento independiente m³ 1,364.00 158.72 216,494.08 1,718.98 272,836.51
03.01.02.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 84,568.00 1.40 118,395.20 547,848.70 766,988.18
03.01.02.02 Encofrado m2 10,912.00 21.77 237,554.24 2,266.00 49,330.82
03.01.03.00 Cimiento Platea m³ 4,100.00 158.72 650,752.00 5,084.54 807,018.19
03.01.03.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 278,800.00 1.40 390,320.00 0.00 -
03.01.03.02 Encofrado m2 32,800.00 21.77 714,056.00 1,630.33 35,492.28
03.01.04.00 Base de Molino m³ 12,180.00 158.72 1,933,209.60 11,551.11 1,833,392.18

Página 4
PRESUPUESTO AVANCE ANTERIOR
Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
03.01.04.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 962,220.00 1.40 1,347,108.00 1,374,841.45 1,924,778.03
03.01.04.02 Encofrado m2 8,000.00 18.35 146,800.00 4,919.44 90,271.72
03.01.05.00 Zanja m³ 797.00 158.72 126,499.84 0.00 -
03.01.05.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 100,422.00 1.40 140,590.80 0.00 -
03.01.05.02 Encofrado m2 3,188.00 21.77 69,402.76 0.00 -
03.01.06.00 Piso m³ 1,650.00 158.72 261,888.00 0.00 -
03.01.06.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 171,600.00 1.40 240,240.00 52,682.20 73,755.08
03.01.06.02 Encofrado m2 6,600.00 21.77 143,682.00 0.00 -
03.01.07.00 Pedestal m³ 931.00 158.72 147,768.32 497.30 78,931.46
03.01.07.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 259,749.00 1.40 363,648.60 286,947.75 401,726.85
03.01.07.02 Encofrado m2 5,586.00 21.77 121,607.22 1,174.94 25,578.44
03.01.08.00 Placa de muro de contención m³ 245.00 158.72 38,886.40 299.61 47,554.10
03.01.08.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 54,145.00 1.40 75,803.00 57,148.18 80,007.45
03.01.08.02 Encofrado m2 1,470.00 21.77 32,001.90 1,622.97 35,332.06
03.01.09.00 Contrafuerte de muro de contención m³ 236.00 158.72 37,457.92 243.50 38,648.32
03.01.09.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 43,660.00 1.40 61,124.00 118,379.36 165,731.10
03.01.09.02 Encofrado m2 1,888.00 21.77 41,101.76 1,356.34 29,527.52

03.01.10.00 Suministro e instalación de Pernos de anclaje base de columna (Galvanización por inmersión en 22.00 9,917.74 218,190.28 35.05 347,577.12
caliente) t
03.01.11.00 17.00 4,381.44 74,484.48 0.00 -
Instalación de pernos de anclaje de equipo( (Galvanización por inmersión en caliente) t
03.01.12.00 Provisión, Fabricación e instalación Pieza embedida t 15.00 3,725.81 55,887.15 0.31 1,136.37
03.01.13.00 Pared de concreto de espesor 200 m³ 28.00 158.72 4,444.16 0.00 -

Página 5
PRESUPUESTO AVANCE ANTERIOR
Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
03.01.13.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 2,912.00 1.40 4,076.80 2,912.00 4,076.80
03.01.13.02 Encofrado m2 224.00 21.77 4,876.48 0.00 -
03.01.14.00 Viga de cimiento m³ 202.00 158.72 32,061.44 177.49 28,171.21
03.01.14.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 29,896.00 1.40 41,854.40 0.00 -
03.01.14.02 Encofrado m2 1,616.00 21.77 35,180.32 1,030.08 22,424.84

03.01.16.00 35.00 16.16 565.60 0.00 -


Provisión e instalación de Water Stop (Cinta de goma impermeable (espesor 10mm, ancho 400mm) m
03.01.17.00 Juntas de Aislamiento m - 9.59 - 0.00 -
03.01.18.00 Juntas de Contracción m - 13.11 - 0.00 -
03.01.19.00 Pared vertical de sótano m³ - 158.72 - 0.00 -
03.01.19.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - 1.40 - 0.00 -
03.01.19.02 Encofrado m2 - 21.77 - 0.00 -
03.01.20.00 Otros m³ 100.00 158.72 15,872.00 0.00 -
03.01.20.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 10,000.00 1.40 14,000.00 0.00 -
03.01.20.02 Encofrado m2 1,000.00 21.77 21,770.00 0.00 -
04.01 PLANTA PRINCIPAL-MOLIENDA-FLOTACION-SEPARACION MAGNETICA 0.00
04.01.01 SISTEMA DE TIERRA PROFUNDA 613,252.89 0.00 325,893.29

Suministro y montaje de cable de cobre desnudo temple blando de120 m2, para sistema de malla a
04.01.01.01 tierra profunda se debera lograr una resistencia final de 5 ohm. (ver estandar N° 962100-000-STD-E- 6,200.00 20.99 130,138.00 2,743.70 57,590.26
DWG-0116) m
04.01.01.02 Suministro y montaje de cable de cobre aislado color verde 120 m2, para conexiones externas 600.00 62.19 37,314.00 421.80 26,231.74
(mechas). N° 962100-000-STD-E-DWG-0142 m
04.01.01.03 Suministro y montaje de cable de cobre desnudo temple blando de 70 m2, para conexiones 3,600.00 20.99 75,564.00 684.20 14,361.36
externas (mechas). N° 962100-000-STD-E-DWG-0142 m
04.01.01.04 Suministro e instalacion de Soldadura Exotermica 120mm2 a 120mm2. und 800.00 59.25 47,400.00 512.00 30,336.00
04.01.01.05 Suministro e instalacion de Soldadura Exotermica 120mm2 a 70mm2. und 350.00 54.11 18,938.50 174.00 9,415.14

04.01.01.06 Suministro e instalacion de Pozos a tierra con caja de registro (varilla, conectores, cajas de registro, 60.00 705.29 42,317.40 4.00 2,821.16
cemento conductivo, bentonita, tierra de cultivo) unid
04.01.01.07 Suministro e instalacion de Pozos a tierra sin caja de registro (varilla, conectores, cemento 50.00 675.01 33,750.50 31.50 21,262.82
conductivo, bentonita, tierra de cultivo) unid

04.01.01.08 Suministro e instalacion de tuberia conduit de PVC. SCHD 80 Ø 1", debera considerarse conectores, 750.00 4.34 3,255.00 817.50 3,547.95
grapas y el sellado (ver estandar N° 962100-000-STD-E-DWG-0142 m

04.01.01.09 Suministro de Tierra de cultivo, bentonita y cemento conductivo para lograr 5 Ohm de resistencia 1.00 189,695.72 189,695.72 0.75 142,271.79
en la malla a tierra de acuerdo a estandar constructivo N° 962100-000-STD-E-DWG-0116 glb
04.01.01.10 Ejecución de Excavación para malla a tierra. De acuerdo a estandar constructivo N° 962100-000- 2,650.00 8.86 23,479.00 997.21 8,835.28
STD-E-DWG-0116 m3

04.01.01.11 Suministro e instalacion de tuberias PVC SCHD 40 Ø1" para cruce en concreto. Incluye el sellado en 1.00 1,416.77 1,416.77 0.87 1,232.59
donde se requiera de acuerdo a estandar 962100-000-STD-E-DWG-0179 glb
04.01.01.12 A prueba de rayos y puesta a tierra t 2.00 4,992.00 9,984.00 1.60 7,987.20

COSTO DIRECTO A 10,478,259.00 8,399,201.56


GASTOS GENERALES A 0.24838 2,602,610.64 2,086,210.25
UTILIDAD A 0.0400 419,130.36 335,968.06

Página 6
PRESUPUESTO AVANCE ANTERIOR
Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
TOTAL PRESUPUESTO A 13,500,000.00 10,821,379.87

ORDEN DE CAMBIO N°1 TRABAJOS DE APOYO

PRESUPUESTO AVANCE ANTERIOR


Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
01.. TRABAJOS DE APOYO
01.01. TRABAJOS DE APOYO glb 1.00 205.44 205.44 1.00 205.44

COSTO DIRECTO B 205.44 205.44


GASTOS GENERALES B -
UTILIDAD B 0.0400 8.22 8.22
TOTAL PRESUPUESTO B 213.66 213.66

ORDEN DE CAMBIO N°2 TRABAJOS DE COLOCACION DE ANCLAJES EN CAJUELAS DEL MOTOR

PRESUPUESTO AVANCE ANTERIOR


Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
01.. TRABAJOS ADICIONALES
01.01. Traslado de Materiales glb 1.00 564.50 564.50 1.00 564.50
01.02. Trabajos de colocacion de anclajes en cajuelas del motor (tubos) und 72.00 119.00 8,568.00 72.00 8,568.00

COSTO DIRECTO C 9,132.50 9,132.50


GASTOS GENERALES C -
UTILIDAD C 0.0400 365.30 365.30
TOTAL PRESUPUESTO C 9,497.80 9,497.80

ORDEN DE CAMBIO N°4 PARTIDAS ADICIONALES DE INSTALACION DE MEMBRANA IMPERMEABLE

PRESUPUESTO AVANCE ANTERIOR


Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
01.. TRABAJOS ADICIONALES
01.01. Suministro e instalación de geomembrana impermeable en Molienda m2 4,078.65 7.76 31,650.32 4,078.65 31,650.32
01.02. Suministro e instalación de geomembrana impermeable en Flotacion m2 2,163.16 7.76 16,786.12 2,163.16 16,786.12

01.03. 2,964.76 7.76 23,006.54 2,964.76 23,006.54


Suministro e instalación de geomembrana impermeable Separacion Magnetica m2

Página 7
PRESUPUESTO AVANCE ANTERIOR
Item Descripción
Und. Metrado Unit Parcial Metrado Parcial

COSTO DIRECTO D 71,442.98 71,442.98


GASTOS GENERALES D 4,950.01 4,950.01
UTILIDAD D 0.0400 2,857.72 2,857.72
TOTAL PRESUPUESTO D 79,250.72 79,250.71

COSTO TOTAL DE LA PRESENTE VALORIZACION

PRESUPUESTO AVANCE ANTERIOR


Item Descripción
Und. Metrado Unit Parcial Metrado Parcial
COSTO DIRECTO A+B+C+D 10,478,259.00 8,479,982.48
GASTOS GENERALES A+B+C+D 2,602,610.64 2,091,160.26
UTILIDAD A+B+C+D 0.0400 419,130.36 339,199.30
TOTAL PRESUPUESTO A+B+C+D 13,500,000.00 10,910,342.04
AMORTIZACIÓN DE ADELANTO 0.2000 2,700,000.00 2,182,068.41
TOTAL PRESUPUESTO (SIN. IGV) 10,800,000.00 8,728,273.63
IGV 0.180 1,944,000.00 1,571,089.25
TOTAL PRESUPUESTO (INC. IGV) 12,744,000.00 10,299,362.88

Página 8
ZACION N°12
E ABRIL DEL 2018)
CODIGO : 993462-CS20-G-AD-VAL-1016
Plazo Contractual : 150 días calendarios
Fecha de Inicio de Plazo : 4/20/2017
Ampliacion de Plazo : -
Fecha de termino de Plazo : 9/16/2017
Gerente de Proyecto : ING. HAN XIU FENG

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
0.00
95.00% 0.00 5,774.74 5.00% 0.00 115,494.93 100.00% - - 0.00%
95.00% 0.05 4,866.58 5.00% 1.00 97,331.66 100.00% - - 0.00%
95.00% 0.05 908.16 5.00% 1.00 18,163.27 100.00% - - 0.00%
93.82% 0.00 17,406.64 4.94% 0.00 348,132.81 98.75% - 4,392.00 1.25%
95.00% 0.05 5,973.87 5.00% 1.00 119,477.40 100.00% - - 0.00%
95.00% 0.05 6,388.54 5.00% 1.00 127,770.87 100.00% - - 0.00%
0.00% 0.00 - 0.00% 0.00 - 0.00% 2,400.00 4,392.00 100.00%

95.00% 0.05 5,044.23 5.00% 1.00 100,884.54 100.00% - - 0.00%

0.00% 0.00 - 0.00% 0.00 - 0.00% - 680,160.00 100.00%


0.00 - 0.00 - - -

0.00% 0.00 - 0.00% 0.00 - 0.00% 6,500.00 680,160.00 100.00%

0.00 - 0.00 - - -
86.80% 0.00 29,636.10 6.27% 0.00 440,058.40 93.07% - 32,759.62 6.93%
38.02% 2,515.98 22,291.58 62.90% 4,036.81 35,766.13 100.92% -36.81 -326.13 -0.92%
0.00% 0.00 - 0.00% 0.00 - 0.00% 6,500.00 33,540.00 100.00%
107.27% 1.00 15.14 0.00% 25,817.80 390,881.49 107.27% -1,749.80 -26,491.97 -7.27%
15.42% 2,536.12 7,329.38 18.58% 4,640.41 13,410.78 34.00% 9,009.59 26,037.72 66.00%
0.00 - 0.00 - - -

87.61% 0.00 1,778,496.00 21.57% 0.00 9,000,935.61 109.18% - -756,927.26 -9.18%

96.58% 990.80 103,677.35 161.11% 1,584.77 165,830.33 257.69% -969.77 -101,476.73 -157.69%
126.02% 0.00 - 0.00% 1,718.98 272,836.51 126.02% -354.98 -56,342.43 -26.02%
647.82% 0.00 - 0.00% 547,848.70 766,988.18 647.82% -463,280.70 -648,592.98 -547.82%
20.77% 194.62 4,236.88 1.78% 2,460.62 53,567.70 22.55% 8,451.38 183,986.54 77.45%
124.01% 67.40 10,697.73 1.64% 5,151.94 817,715.92 125.66% -1,051.94 -166,963.92 -25.66%
0.00% 0.00 - 0.00% 0.00 - 0.00% 278,800.00 390,320.00 100.00%
4.97% 6.49 141.29 0.02% 1,636.82 35,633.57 4.99% 31,163.18 678,422.43 95.01%
94.84% 241.32 38,302.31 1.98% 11,792.43 1,871,694.49 96.82% 387.57 61,515.11 3.18%

Página 9
AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR
% Metrado Parcial % Metrado Parcial % Metrado Parcial %
142.88% 262,220.00 367,108.00 27.25% 1,637,061.45 2,291,886.03 170.13% -674,841.45 -944,778.03 -70.13%
61.49% 103.26 1,894.82 1.29% 5,022.70 92,166.54 62.78% 2,977.30 54,633.46 37.22%
0.00% 488.17 77,482.34 61.25% 488.17 77,482.34 61.25% 308.83 49,017.50 38.75%
0.00% 84,729.08 118,620.71 84.37% 84,729.08 118,620.71 84.37% 15,692.92 21,970.09 15.63%
0.00% 2,248.54 48,950.72 70.53% 2,248.54 48,950.72 70.53% 939.46 20,452.04 29.47%
0.00% 1,748.92 277,588.58 106.00% 1,748.92 277,588.58 106.00% -98.92 -15,700.58 -6.00%
30.70% 156,102.13 218,542.98 90.97% 208,784.33 292,298.06 121.67% -37,184.33 -52,058.06 -21.67%
0.00% 685.55 14,924.42 10.39% 685.55 14,924.42 10.39% 5,914.45 128,757.58 89.61%
53.42% 90.41 14,349.88 9.71% 587.71 93,281.34 63.13% 343.29 54,486.98 36.87%
110.47% 35,426.13 49,596.58 13.64% 322,373.88 451,323.43 124.11% -62,624.88 -87,674.83 -24.11%
21.03% 429.47 9,349.56 7.69% 1,604.41 34,928.00 28.72% 3,981.59 86,679.22 71.28%
122.29% 118.54 18,814.67 48.38% 418.15 66,368.77 170.67% -173.15 -27,482.37 -70.67%
105.55% 27,157.71 38,020.79 50.16% 84,305.89 118,028.24 155.70% -30,160.89 -42,225.24 -55.70%
110.41% 661.29 14,396.28 44.99% 2,284.26 49,728.34 155.39% -814.26 -17,726.44 -55.39%
103.18% 0.00 - 0.00% 243.50 38,648.32 103.18% -7.50 -1,190.40 -3.18%
271.14% (59,944.33) -83,922.06 -137.30% 58,435.03 81,809.04 133.84% -14,775.03 -20,685.04 -33.84%
71.84% 0.00 - 0.00% 1,356.34 29,527.52 71.84% 531.66 11,574.24 28.16%

159.30% 25.09 248,875.77 114.06% 60.14 596,452.89 273.36% -38.14 -378,262.61 -173.36%

0.00% 0.00 - 0.00% 0.00 - 0.00% 17.00 74,484.48 100.00%

2.03% 18.28 68,089.18 121.83% 18.58 69,225.55 123.87% -3.58 -13,338.40 -23.87%
0.00% 0.00 - 0.00% 0.00 - 0.00% 28.00 4,444.16 100.00%

Página 10
AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR
% Metrado Parcial % Metrado Parcial % Metrado Parcial %
100.00% (2,912.00) -4,076.80 -100.00% 0.00 - 0.00% 2,912.00 4,076.80 100.00%
0.00% 0.00 - 0.00% 0.00 - 0.00% 224.00 4,876.48 100.00%
87.87% 0.00 - 0.00% 177.49 28,171.21 87.87% 24.51 3,890.23 12.13%
0.00% 40,947.64 57,326.70 136.97% 40,947.64 57,326.70 136.97% -11,051.64 -15,472.30 -36.97%
63.74% 45.12 982.26 2.79% 1,075.20 23,407.10 66.53% 540.80 11,773.22 33.47%

0.00% 87.30 1,410.77 249.43% 87.30 1,410.77 249.43% -52.30 -845.17 -149.43%

0.00 - 0.00 - - -
4,814.21 63,114.29 4,814.21 63,114.29 -4,814.21 -63,114.29
0.00 - 0.00 - - -
0.00 - 0.00 - - -
0.00 - 0.00 - - -
0.00% 0.00 - 0.00% 0.00 - 0.00% 100.00 15,872.00 100.00%
0.00% 0.00 - 0.00% 0.00 - 0.00% 10,000.00 14,000.00 100.00%
0.00% 0.00 - 0.00% 0.00 - 0.00% 1,000.00 21,770.00 100.00%
0.00 - 0.00 - - -
53.14% 0.00 -227,320.12 -37.07% 0.00 98,573.17 16.07% - 514,679.72 83.93%

44.25% (2,333.70) -48,984.36 -37.64% 410.00 8,605.90 6.61% 5,790.00 121,532.10 93.39%

70.30% (341.80) -21,256.54 -56.97% 80.00 4,975.20 13.33% 520.00 32,338.80 86.67%

19.01% (654.20) -13,731.66 -18.17% 30.00 629.70 0.83% 3,570.00 74,934.30 99.17%

64.00% (424.00) -25,122.00 -53.00% 88.00 5,214.00 11.00% 712.00 42,186.00 89.00%
49.71% (148.00) -8,008.28 -42.29% 26.00 1,406.86 7.43% 324.00 17,531.64 92.57%

6.67% (2.00) -1,410.58 -3.33% 2.00 1,410.58 3.33% 58.00 40,906.82 96.67%

63.00% (23.00) -15,525.23 -46.00% 8.50 5,737.59 17.00% 41.50 28,012.91 83.00%

109.00% (787.50) -3,417.75 -105.00% 30.00 130.20 4.00% 720.00 3,124.80 96.00%

75.00% (0.41) -77,775.25 -41.00% 0.34 64,496.54 34.00% 0.66 125,199.18 66.00%

37.63% (887.21) -7,860.68 -33.48% 110.00 974.60 4.15% 2,540.00 22,504.40 95.85%

87.00% (0.87) -1,232.59 -87.00% 0.00 - 0.00% 1.00 1,416.77 100.00%

80.00% (0.60) -2,995.20 -30.00% 1.00 4,992.00 50.00% 1.00 4,992.00 50.00%

80.16% 1,603,993.36 15.31% 10,003,194.92 95.47% 475,064.08 4.53%


398,403.03 2,484,613.29 117,997.35
64,159.73 400,127.80 19,002.56

Página 11
AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR
% Metrado Parcial % Metrado Parcial % Metrado Parcial %
2,066,556.12 12,887,936.01 612,063.99

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% - 0.00% 1.00 205.44 100.00% - - 0.00%

100.00% - 0.00% 205.44 100.00% - 0.00%


- - -
- 8.22 -
- 213.66 -

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% - 0.00% 1.00 564.50 100.00% - - 0.00%


100.00% - 0.00% 72.00 8,568.00 100.00% - - 0.00%

100.00% - 0.00% 9,132.50 100.00% - 0.00%


- - -
- 365.30 -
- 9,497.80 -

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR


% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% - 0.00% 4,078.65 31,650.32 100.00% - 0.00 0.00%


100.00% - 0.00% 2,163.16 16,786.12 100.00% - 0.00 0.00%

100.00% - 0.00% 2,964.76 23,006.54 100.00% - -0.00 0.00%

Página 12
AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR
% Metrado Parcial % Metrado Parcial % Metrado Parcial %

100.00% - 0.00% 71,442.98 100.00% 0.00 0.00%


- 4,950.01 -
- 2,857.72 -
- 79,250.71 -

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A COBRAR


% Metrado Parcial % Metrado Parcial % Metrado Parcial %
80.93% 1,603,993.36 15.31% 10,083,975.84 96.24% 394,283.16 3.76%
398,403.03 2,489,563.30 113,047.34
64,159.73 403,359.04 15,771.32
2,066,556.12 12,976,898.18 523,101.82
517,931.59 2,700,000.00 -
1,548,624.53 10,276,898.16 523,101.84
278,752.42 1,849,841.67 94,158.33
80.82% 1,827,376.95 14.34% 12,126,739.83 95.16% 617,260.17 4.84%

Página 13
HOJA DE METRADOS
( AL 25 DE ABRIL DEL 2018)

Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS


Obra: OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1 (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION)
Cliente: SHOUGANG HIERRO PERU
Contratista: CCCC DEL PERU
Ubicación: MARCONA
Fecha: 4/20/2018

Metrado Metrado
ITEM DESCRIPCION Und
Contractual Val. 01
01.01 PARTIDAS COMUNES
01.01.01 CONSTRUCCIONES PROVISIONALES
01.01.01.01 Construcción de oficinas provisionales glb 1.00 0.77
01.01.01.02 Construcción de almacén, taller u otros glb 1.00 0.76
01.01.02 TRABAJOS PRELIMINARES -
01.01.02.01 Traslado de maquinarias, equipos, herramientas y materiales a/d obra glb 1.00 0.22
01.01.02.02 Trazo, niveles y replanteo (topografía permanente) glb 1.00 0.20
01.01.02.03 Desquinche de taludes temporales de ser requerido m2 2,400.00 -
01.01.02.04 Mantenimiento de accesos principales, secundarios y temporales para la construc glb 1.00 -
01.01.03 OTROS -
01.01.03.01 Tratamiento de Consolidación de macizo rocoso RQD<60% L - -
Subcimiento concreto fc=100 kg/cm2 cemento tipo V de acuerdo a la especificaci m3 6,500.00 -
02.01 MOVIMIENTO DE TIERRAS -

Página 14
Metrado Metrado
ITEM DESCRIPCION Und
Contractual Val. 01
02.01.01 Edificio Principal Molienda- Separavión Magnética - Celdas de Flotación -
02.01.01.01 Excavación roca sana o fragmentada con equipo (-0.30m) m3 4,000.00 136.84
Excavación de terreno residual y aluvial m3 6,500.00 -
02.01.01.02 Relleno estructural de acuerdo a las especificaciones técnicas m3 24,068.00 -
02.01.01.03 Eliminación de material excedente c/equipo 1.7km aprox. m3 13,650.00 177.89
03.01 OBRAS DE CONCRETO -
Planta Principal ???
03.01.00.00 -
5740;5750;5760
03.01.01.00 Solado m³ 615.00 58.14
03.01.02.00 Cimiento independiente m³ 1,364.00 -
03.01.02.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 84,568.00 -
03.01.02.02 Encofrado m2 10,912.00 -
03.01.03.00 Cimiento Platea m³ 4,100.00 -
03.01.03.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 278,800.00 -
03.01.03.02 Encofrado m2 32,800.00 -
03.01.04.00 Base de Molino m³ 12,180.00 -
03.01.04.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 962,220.00 -
03.01.04.02 Encofrado m2 8,000.00 -
03.01.05.00 Zanja m³ 797.00 -
03.01.05.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 100,422.00 -
03.01.05.02 Encofrado m2 3,188.00 -
03.01.06.00 Piso m³ 1,650.00 -
03.01.06.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 171,600.00 -
03.01.06.02 Encofrado m2 6,600.00 -
03.01.07.00 Pedestal m³ 931.00 -
03.01.07.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 259,749.00 -
03.01.07.02 Encofrado m2 5,586.00 -
03.01.08.00 Placa de muro de contención m³ 245.00 -

Página 15
Metrado Metrado
ITEM DESCRIPCION Und
Contractual Val. 01
03.01.08.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 54,145.00 -
03.01.08.02 Encofrado m2 1,470.00 -
03.01.09.00 Contrafuerte de muro de contención m³ 236.00 -
03.01.09.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 43,660.00 -
03.01.09.02 Encofrado m2 1,888.00 -
03.01.10.00 Suministro e instalación de Pernos de anclaje base de columna (Galvanización po t 22.00 -
03.01.11.00 Instalación de pernos de anclaje de equipo( (Galvanización por inmersión en cali t 17.00 -
03.01.12.00 Provisión, Fabricación e instalación Pieza embedida t 15.00 -
03.01.13.00 Pared de concreto de espesor 200 m³ 28.00 -
03.01.13.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 2,912.00 -
03.01.13.02 Encofrado m2 224.00 -
03.01.14.00 Viga de cimiento m³ 202.00 -
03.01.14.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 29,896.00 -
03.01.14.02 Encofrado m2 1,616.00 -
03.01.16.00 Provisión e instalación de Water Stop (Cinta de goma impermeable (espesor m 35.00 -
03.01.17.00 Juntas de Aislamiento m - -
03.01.18.00 Juntas de Contracción m - -
03.01.19.00 Pared vertical de sótano m³ - -
03.01.19.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - -
03.01.19.02 Encofrado m2 - -
03.01.20.00 Otros m³ 100.00 -
03.01.20.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 10,000.00 -
03.01.20.02 Encofrado m2 1,000.00 -
04.01 PLANTA PRINCIPAL-MOLIENDA-FLOTACION-SEPARACION MAGNETICA -
04.01.01 SISTEMA DE TIERRA PROFUNDA -
04.01.01.01 Suministro y montaje de cable de cobre desnudo temple blando de120 m2, para s m 6,200.00 -
04.01.01.02 Suministro y montaje de cable de cobre aislado color verde 120 m2, para co m 600.00 -

Página 16
Metrado Metrado
ITEM DESCRIPCION Und
Contractual Val. 01
04.01.01.03 Suministro y montaje de cable de cobre desnudo temple blando de 70 m2, pa m 3,600.00 -
04.01.01.04 Suministro e instalacion de Soldadura Exotermica 120mm2 a 120mm2. und 800.00 -
04.01.01.05 Suministro e instalacion de Soldadura Exotermica 120mm2 a 70mm2. und 350.00 -
04.01.01.06 Suministro e instalacion de Pozos a tierra con caja de registro (varilla, conectores unid 60.00 -
04.01.01.07 Suministro e instalacion de Pozos a tierra sin caja de registro (varilla, conectores unid 50.00 -
04.01.01.08 Suministro e instalacion de tuberia conduit de PVC. SCHD 80 Ø 1", debera con m 750.00 -
04.01.01.09 Suministro de Tierra de cultivo, bentonita y cemento conductivo para lograr 5 glb 1.00 -
04.01.01.10 Ejecución de Excavación para malla a tierra. De acuerdo a estandar construc m3 2,650.00 -
04.01.01.11 Suministro e instalacion de tuberias PVC SCHD 40 Ø1" para cruce en concreto glb 1.00 -
04.01.01.12 A prueba de rayos y puesta a tierra t 2.00 -

Página 17
TRADOS
BRIL DEL 2018)
CODIGO : 993462-CS20-G-AD-VAL-1002
Plazo Contractual : 150 días calendarios
COS Y FLOTACION) Fecha de Inicio de Plazo : 4/20/2017
Ampliacion de Plazo : -
Fecha de termino de Plazo : 9/16/2017
Gerente de Proyecto : ING. HAN XIU FENG

Metrado Metrado Metrado Val. Metrado Metrado


Metrado Total
Val. 02 Val. 03 04 Val. 05 Val. 06

-
0.05 0.82
0.05 0.81
- -
0.05 0.27
0.05 0.25
- -
0.05 0.05
- -
- -
- -
- -

Página 18
Metrado Metrado Metrado Val. Metrado Metrado
Metrado Total
Val. 02 Val. 03 04 Val. 05 Val. 06
- -
2,515.98 2,652.82
- -
1.00 1.00
2,536.12 2,714.01
- -
- -
990.80 1,048.94
- -
- -
194.62 194.62
67.40 67.40
- -
6.49 6.49
241.32 241.32
262,220.00 262,220.00
103.26 103.26
488.17 488.17
84,729.08 84,729.08
2,248.54 2,248.54
1,748.92 1,748.92
156,102.13 156,102.13
685.55 685.55
90.41 90.41
35,426.13 35,426.13
429.47 429.47
118.54 118.54

Página 19
Metrado Metrado Metrado Val. Metrado Metrado
Metrado Total
Val. 02 Val. 03 04 Val. 05 Val. 06
27,157.71 27,157.71
661.29 661.29
- -
-59,944.33 -59,944.33
- -
25.09 25.09
- -
18.28 18.28
- -
-2,912.00 -2,912.00
- -
- -
40,947.64 40,947.64
45.12 45.12
87.30 87.30
- -
4,814.21 4,814.21
- -
- -
- -
- -
- -
- -
- -
- -
-2,333.70 -2,333.70
-341.80 -341.80

Página 20
Metrado Metrado Metrado Val. Metrado Metrado
Metrado Total
Val. 02 Val. 03 04 Val. 05 Val. 06
-654.20 -654.20
-424.00 -424.00
-148.00 -148.00
-2.00 -2.00
-23.00 -23.00
-787.50 -787.50
-0.41 -0.41
-887.21 -887.21
-0.87 -0.87
-0.60 -0.60

Página 21
PLANILLA DE METRADOS EJECUTADOS
CODIGO : 993462-CS20-G-AD-VAL-1016
Proyecto: PTA BENEFICIO DOS LINEAS DE PRODUCCION PRIMARIOS Plazo Contractual : 150 días calendarios
OBRAS CIVILES PARA LA NUEVA PLANTA DE BENEFICIO - AREA 1
Obra: (MOLIENDA, SEPARADORES MAGNETICOS Y FLOTACION) Fecha de Inicio de Plazo : 4/20/2017

Cliente: SHOUGANG HIERRO PERU Ampliacion de Plazo : -


Contratista: CCCC DEL PERU Fecha de termino de Plazo : 9/16/2017
Ubicación: MARCONA Gerente de Proyecto : ING. HAN XIU FENG
Fecha: 4/20/2018

METRADOS
METRADOS
Item Descripción Und. ACUMULADO VAL TOTAL (B-A) PARCIAL
CONSILIADOS
ANTERIOR

01.01 PARTIDAS COMUNES -


01.01.01 CONSTRUCCIONES PROVISIONALES - -
01.01.01.01 Construcción de oficinas provisionales glb 1.00 0.95 0.05 0.05
01.01.01.02 Construcción de almacén, taller u otros glb 1.00 0.95 0.05 0.05
01.01.02 TRABAJOS PRELIMINARES - - -
01.01.02.01 Traslado de maquinarias, equipos, herramientas y materiales a/d obra glb 1.00 0.95 0.05 0.05
01.01.02.02 Trazo, niveles y replanteo (topografía permanente) glb 1.00 0.95 0.05 0.05
01.01.02.03 Desquinche de taludes temporales de ser requerido m2 - - - -
Mantenimiento de accesos principales, secundarios y temporales para la
01.01.02.04 glb 1.00 0.95 0.05 0.05
construcción (inc mitigación de polvo)
01.01.03 OTROS - - - -
01.01.03.01 Tratamiento de Consolidación de macizo rocoso RQD<60% L - - - -
Subcimiento concreto fc=100 kg/cm2 cemento tipo V de acuerdo a la
m3 - - - -
especificación tecnica
02.01 MOVIMIENTO DE TIERRAS - - -
02.01.01 Edificio Principal Molienda- Separavión Magnética - Celdas de Flotación - - -
02.01.01.01 Excavación roca sana o fragmentada con equipo (-0.30m) m3 4,036.81 1,520.83 2,515.98 2,515.98
Excavación de terreno residual y aluvial m3 - - - -
02.01.01.02 Relleno estructural de acuerdo a las especificaciones técnicas m3 25,817.80 25,816.80 1.00 1.00
02.01.01.03 Eliminación de material excedente c/equipo 1.7km aprox. m3 4,640.41 2,104.29 2,536.12 2,536.12
03.01 OBRAS DE CONCRETO - - -
Planta Principal ???
03.01.00.00 - - -
5740;5750;5760
03.01.01.00 Solado m³ 1,584.77 593.97 990.80 990.80
03.01.02.00 Cimiento independiente m³ 1,718.98 1,718.98 - -
03.01.02.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 547,848.70 547,848.70 - -
03.01.02.02 Encofrado m2 2,460.62 2,266.00 194.62 194.62
03.01.03.00 Cimiento Platea m³ 5,151.94 5,084.54 67.40 67.40
03.01.03.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - - -
03.01.03.02 Encofrado m2 1,636.82 1,630.33 6.49 6.49

Página 22
METRADOS
METRADOS
Item Descripción Und. CONSILIADOS
ACUMULADO VAL TOTAL (B-A) PARCIAL
ANTERIOR

03.01.04.00 Base de Molino m³ 11,792.43 11,551.11 241.32 241.32


03.01.04.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 1,637,061.45 1,374,841.45 262,220.00 262,220.00
03.01.04.02 Encofrado m2 5,022.70 4,919.44 103.26 103.26
03.01.05.00 Zanja m³ 488.17 - 488.17 488.17
03.01.05.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 84,729.08 - 84,729.08 84,729.08
03.01.05.02 Encofrado m2 2,248.54 - 2,248.54 2,248.54
03.01.06.00 Piso m³ 1,748.92 - 1,748.92 1,748.92
03.01.06.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 208,784.33 52,682.20 156,102.13 156,102.13
03.01.06.02 Encofrado m2 685.55 - 685.55 685.55
03.01.07.00 Pedestal m³ 587.71 497.30 90.41 90.41
03.01.07.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 322,373.88 286,947.75 35,426.13 35,426.13
03.01.07.02 Encofrado m2 1,604.41 1,174.94 429.47 429.47
03.01.08.00 Placa de muro de contención m³ 418.15 299.61 118.54 118.54
03.01.08.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 84,305.89 57,148.18 27,157.71 27,157.71
03.01.08.02 Encofrado m2 2,284.26 1,622.97 661.29 661.29
03.01.09.00 Contrafuerte de muro de contención m³ 243.50 243.50 - -
03.01.09.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 58,435.03 118,379.36 -59,944.33 -59,944.33
03.01.09.02 Encofrado m2 1,356.34 1,356.34 - -
Suministro e instalación de Pernos de anclaje base de columna (Galvanización
03.01.10.00 t 60.14 35.05 25.09 25.09
por inmersión en caliente)
Instalación de pernos de anclaje de equipo( (Galvanización por inmersión en
03.01.11.00 t - - - -
caliente)
03.01.12.00 Provisión, Fabricación e instalación Pieza embedida t 18.58 0.31 18.28 18.28
03.01.13.00 Pared de concreto de espesor 200 m³ - - - -
03.01.13.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - 2,912.00 -2,912.00 -2,912.00
03.01.13.02 Encofrado m2 - - - -
03.01.14.00 Viga de cimiento m³ 177.49 177.49 - -
03.01.14.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg 40,947.64 - 40,947.64 40,947.64
03.01.14.02 Encofrado m2 1,075.20 1,030.08 45.12 45.12
Provisión e instalación de Water Stop (Cinta de goma impermeable (espesor
03.01.16.00 m 87.30 - 87.30 87.30
10mm, ancho 400mm)
03.01.17.00 Juntas de Aislamiento m - - - -
03.01.18.00 Juntas de Contracción m 4,814.21 - 4,814.21 4,814.21
03.01.19.00 Pared vertical de sótano m³ - - - -
03.01.19.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - - - -
03.01.19.02 Encofrado m2 - - - -
03.01.20.00 Otros m³ - - - -
03.01.20.01 Acero de refuerzo f'y = 4200 Kg/cm2 kg - - - -
03.01.20.02 Encofrado m2 - - - -
04.01 PLANTA PRINCIPAL-MOLIENDA-FLOTACION-SEPARACION MAGNETICA - - -
04.01.01 SISTEMA DE TIERRA PROFUNDA - - -

Suministro y montaje de cable de cobre desnudo temple blando de120 m2, para
04.01.01.01 sistema de malla a tierra profunda se debera lograr una resistencia final de 5 m 410.00 2,743.70 -2,333.70 -2,333.70
ohm. (ver estandar N° 962100-000-STD-E-DWG-0116)

Página 23
METRADOS
METRADOS
Item Descripción Und. CONSILIADOS
ACUMULADO VAL TOTAL (B-A) PARCIAL
ANTERIOR

Suministro y montaje de cable de cobre aislado color verde 120 m2, para
04.01.01.02 m 80.00 421.80 -341.80 -341.80
conexiones externas (mechas). N° 962100-000-STD-E-DWG-0142

Suministro y montaje de cable de cobre desnudo temple blando de 70 m2, para


04.01.01.03 m 30.00 684.20 -654.20 -654.20
conexiones externas (mechas). N° 962100-000-STD-E-DWG-0142

04.01.01.04 Suministro e instalacion de Soldadura Exotermica 120mm2 a 120mm2. und 88.00 512.00 -424.00 -424.00

04.01.01.05 Suministro e instalacion de Soldadura Exotermica 120mm2 a 70mm2. und 26.00 174.00 -148.00 -148.00

Suministro e instalacion de Pozos a tierra con caja de registro (varilla,


04.01.01.06 unid 2.00 4.00 -2.00 -2.00
conectores, cajas de registro, cemento conductivo, bentonita, tierra de cultivo)

Suministro e instalacion de Pozos a tierra sin caja de registro (varilla,


04.01.01.07 unid 8.50 31.50 -23.00 -23.00
conectores, cemento conductivo, bentonita, tierra de cultivo)

Suministro e instalacion de tuberia conduit de PVC. SCHD 80 Ø 1", debera


04.01.01.08 considerarse conectores, grapas y el sellado (ver estandar N° 962100-000-STD-E- m 30.00 817.50 -787.50 -787.50
DWG-0142
Suministro de Tierra de cultivo, bentonita y cemento conductivo para lograr 5
04.01.01.09 Ohm de resistencia en la malla a tierra de acuerdo a estandar constructivo N° glb 0.34 0.750 -0.41 -0.41
962100-000-STD-E-DWG-0116
Ejecución de Excavación para malla a tierra. De acuerdo a estandar constructivo
04.01.01.10 m3 110.00 997.21 -887.21 -887.21
N° 962100-000-STD-E-DWG-0116
Suministro e instalacion de tuberias PVC SCHD 40 Ø1" para cruce en concreto.
04.01.01.11 Incluye el sellado en donde se requiera de acuerdo a estandar 962100-000-STD- glb - 0.87 -0.87 -0.87
E-DWG-0179
04.01.01.12 A prueba de rayos y puesta a tierra t 1.00 1.60 -0.60 -0.60
- -

Página 24