International Journal of Scientific and Technological Research (IJSTER)

ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018


www.oircjournals.org

Monitoring Intensity and


Procurement Performance; Empirical
Evidence from Elgeyo Marakwet
County, Kenya.
Lonah Kandie Tallam & Kibet Yusuf
Jomo Kenyatta University of Agriculture and Technology

Type of the Paper: Research Paper.


Type of Review: Peer Reviewed.
Indexed in: worldwide web.
Google Scholar Citation: AIJMR

How to Cite this Paper:


Tallam, L. K. and Kibet, Y., (2018). Monitoring Intensity and Procurement Performance.
Empirical Evidence from Elgeyo Marakwet County, Kenya. International Journal of Scientific
and Technological Research (IJSTER), 1 (1) 97-108.

Africa International Journal of Multidisciplinary Research (AIJMR)


A Refereed International Journal of OIRC JOURNALS.

© OIRC JOURNALS.

This work is licensed under a Creative Commons Attribution-Non Commercial 4.0


International License subject to proper citation to the publication source of the work.
Disclaimer: The scholarly papers as reviewed and published by the OIRC JOURNALS, are
the views and opinions of their respective authors and are not the views or opinions of the
OIRC.

97 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

Monitoring Intensity and Procurement Performance.


Empirical Evidence from Elgeyo Marakwet County,
Kenya.
Lonah Kandie Tallam & Kibet Yusuf
Jomo Kenyatta University of Agriculture and Technology

ARTICLE INFO Abstract


Contract management practice is a vital aspect
in any organization that intends to gain a
Received 1 October, 2018
st
competitive advantage and value for money. In
Received in Revised Form 29th October, 2018 public organizations, every year a major
Accepted 1st November, 2018 portion of budget allocation is given for
procurement of goods and services for various
Published online 2nd November 2018 kinds of projects to be done. The study focused
Key words: Monitoring Intensity, procurement on the effect of monitoring intensity on
procurement performance of public
performance, Contract Management organizations in Elgeyo Marakwet County.
The study was guided by relational contract theory and principal-agent theory. It adopted a descriptive study
design utilizing questionnaires as the primary data collection tool. The staff from finance and procurement
departments in the County government formed the study’s unit of analysis. The sample for the study was
procurement officers and finance officers. It also adopted census sampling on all the target respondents. A pilot
study was done in Uasin Gishu County Government. The computer programme Statistical Package for Social
Sciences (SPSS) version 22.0 aided in data analysis. Data was analyzed using Quantitative data analysis with
both descriptive and inferential statistics. Descriptive statistics like frequencies, percentages, means and cross
tabulation will be used while multiple regressions will be used to test the hypothesis. Presentation of finding done
using questionnaires which was coded, organized, analyzed and presented using frequency tables, and
percentages. The study found that the organization was able to practice monitoring intensity with the view to
enhance procurement performance. The results established a positive but weak correlation between the variables
(P= 0.288, r=.057). The strength of association was weak. The study concluded that monitoring intensity was a
factor that influences procurement performance in organizations. However it was noted that other factors were
needed to support this practice. It was recommended that contractors should be allocated with the right amount
of resources to complete the projects assigned to them.
Introduction wide contracts with the goal of minimizing costs and
Contract management is the process that ensures risks, maximizing revenues, streamlining
both parties to a contract fully meet their respective operations, and improving compliance with policies,
obligations as efficiently and effectively as possible, procedures, regulations, and negotiated terms and
in order to deliver the business and operational conditions (Saxena, 2008).
objectives required from the contract and in Procurement performance has been described as the
particular to provide value for money. As a result degree of achievement of certain effort or
developing and managing contracts is a skill undertaking. It relates to the prescribed goals or
required by public sector entities in the management objectives which form the project parameters
of the majority, if not all, programmes. However, (Chitkara, 2015). In order to achieve optimum
contract management is not an end in itself and it is procurement performance, procuring entities
important that all contracting decisions and actions through the existing legal framework are required
focus on the outcomes that entities are seeking to to firstly consolidate departmental procurement
achieve (Kakwezi, 2012). plans to provide the entity’s corporate procurement
In the public sector there is huge variety of contracts, plan which before its implementation must get the
with different types of contracts needing different accounting officer’s approval. Industry Manual,
types of contract management. On the other hand (2008) indicates that a procurement plan is an
agency contract management is the process of instrument for implementation of the budget and
managing all stages in the lifecycle of enterprise- should be prepared by the user departments with

98 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

a view to avoiding or minimizing excess votes in in both public and private organizations are endemic
the entities’ budgets and to ensure that procurements in any contractual relationship due to lack of
do not proceed unless there are funds to pay for transparency and poor record keeping. Successful
them. This implies that all procurement plans must contract management and completion is often
be well integrated into the budget process based on defined, as procurement of the right item, in the right
the indicative budget as appropriate and in quantity, for the right price, at the right time, with
compliance with the procurement law. the right quality, from the right source (Thai, 2005).
Globally, today governments all over the world have Prager (1994) contends that proper and effective
received a great deal of attention as providers of management and monitoring of contracts helps
essential services such as health, education, defense improve the quality of goods and services and
and security, and infrastructure (OECD, 2000). So reduces procurement cost thus achieving three broad
as to be able to meet the demand of all these services, goals: quality products and services, timely delivery
governments procure goods, works and services of products and services, and cost effectiveness
from supply markets. That means public sector (within budget).
procurement has both economic and political Currently, Kenya loses billions of taxpayers’ money
implications. There is no doubt amongst policy to improper procurement process, specifically poor
makers, managers, professionals and academicians contract management practices. This commonly
about the role of public sector procurement in happens in the country’s state corporations due to
facilitating government operations towards issues, such as, corruption, litigations, contract
economic growth, poverty reduction and good cancellations and substandard service or product
governance through provision of quality services to delivery. This calls for the pressing need to make
the citizens. The performance of public procurement appropriate policies and decisions to save the
markets has significant implications for the situation. Since the state requires to realize its value
effectiveness of governance in both developed and for money in the process of the serving its people,
developing countries. There are strategic decisions every state corporation is required to account for its
to be made that will affect the nature of contract expenses (Contract Monitoring Kenya Network,
management role. For example, one might contract 2012). Therefore, contract management is a valuable
out a whole requirement leaving one a relatively step in public procurement as it ensures that service
straightforward contract management task (OECD, or products delivery is undertaken as per the
2005). contractual terms and conditions.
In Africa, South Africa in particular, the Common
Market for East and Southern Africa Statement of the Problem
(COMESA,2011) guidelines observes that neither In County Governments, every year a major portion
the COMESA Procurement Directive, nor the of budget allocation is given for procurement of
UNCITRAL Model Law, specifically address the goods and services for various kinds of projects to
subject of contract management. Despite the be done. However in some organizations,
importance of contract management researchers are procurement has not been done the right way.
unable to empirically and systematically pinpoint Proponents argue that contracting can reduce costs
the determinants and constraints by using objective and improve flexibility and customer satisfaction.
‘hard data’ (Jiang & Qureshi, 2006). In several Critics point to a growing number of failed
countries, few articles have rigorously analyzed and contracts, arguing there are numerous pitfalls
empirically tested the factors that actually affect a associated with contracting. The problem arisen due
government agency’s decision to manage contracts. to poor contract management leading to failure to
Within the relatively scarce empirical evidence on procure the right quality goods, in the right time at
contracting decisions and management (Boyne, the right price. It was reported that 80 to 90% of the
1998; Ferris & Graddy, 1986), there is yet little goods are not managed properly. Therefore there
information on the effectiveness of contract was loss of government money which is not properly
management specific to public procurement. addressed and many projects are not completed
In East Africa, Uganda for example, contract (Kakwezi & Nyeko, 2010).
management has become a megatrend in many Despite efforts by public organizations being
public entities especially as result of social transparent and accountable on what they procure,
accountability and increased demand of service the issue of poor performance is still felt. The county
delivery by citizens (World Bank Institute, 2011; governments still lose billions of taxpayers’ money
Schiel, 2007; Swinnery & Netssins, 2007). to improper procurement process, specifically poor
However, Dew (2008); Thai (2005) and Bolton contract management practices.
(2006) observe that contract management challenges

99 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

Numerous studies have been done on contract overemphasis on the existence of collaborative
management but little has been done in Kenya and relationships and social control mechanisms and
specifically in County Governments of Kenya. is a reflection of the observation that, even where a
Outside Kenya, Holtand Graves (2001) conducted a written contract exists, frequently companies seek
study on benchmarking UK public procurement to avoid the use of legal action against their
performance, Bassioni, Price and Hassan (2004) suppliers and or customers. Yet, empirical
dwelt on the performance measurement in investigations reveal the existence of detailed
construction industry. Moreover, Jeanette (2008) contracts that firms use to manage their firm
conducted a study on the benchmarking and its relationships. Indeed, empirical research into
importance on procurement performance. It is manufacturer retailer networks as well as into
therefore against this problem and gap that the study manufacturer to manufacturer relationships shows
seeks to assess contract management practices and that companies attempt to simplify and facilitate
procurement performance in County Governments the complex process of a business interaction by
of Kenya, a case of Elgeyo Marakwet County. embracing a new form of contract described as
umbrella agreements. It informs the study variables
Research Objective of monitoring intensity practice and risk
To determine the effect of monitoring intensity on management practices as it emphasizes on planning
procurement performance of Elgeyo Marakwet and the management of contracts in organizations.
County, Kenya. Macneil’s theoretical criticism of this view of
Research Hypothesis contract is that it does not take into account the
H01. There is no significant effect of monitoring co-operative, relational phenomena to which he
intensity on procurement performance Elgeyo draws the attention. As well as taking up the
Marakwet, County. social philosophical issues involved in this, he
Literature Review makes this point in respect of many contract
Theoretical Review doctrines, such as the regulation of penalty
The study was guided by relational contract theory. clauses (1981b) and (other) standard terms
Relational Contract Theory (Macneil, 1984), the adjustment of formally strict
Relational Contracts Theory is a theory mainly liabilities (Macneil 1983b) and the nature of
developed by Ian MacNeil in U.S.A. in 1980. breach. The last of these is particularly instructive,
According to relational contracts theory, relations for it does not turn on any welfares considerations
are governed by a set of common characteristics but solely on “economic efficiency.”
(norms) that play an important role, regarding the
content of the relation, the formation of parties’ Effect of Monitoring Intensity and Procurement
obligations and the actual operation of the contracts. Performance
These norms are based on a set of internal values and Brown and Hyer (2010), describe monitoring as the
the broad context social and economic factors, tracking aimed at identifying variances from the
related to the relation. According to MacNeil, there original plan using simple checklist to sophisticated
are ten norms common for all kinds of contracts: role dashboard style approaches. According to Meredith
integrity, reciprocity, implementation of planning, and Mantel (2012), cost (budget) and scope
effectuation of consent, flexibility, and contractual (performance) and time (schedule), are important
solidarity, the ‘linking norms’ (restitution, reliance things to be considered during planning, and should
and expectation interests), creation and restraint of therefore be monitored and controlled effectively.
power, propriety of means and harmonization with Until the project is complete the cycle of planning,
the social matrix. There are also five norms monitoring and exercising control should be made a
(additional or the same as these of common routine. The organization structure should construct
contracts), responding in an intensive way to the process as an integral part ensuring that it does
contracts with a highly relational character than not cause any conflicts. The organization should
conventional contracts: role integrity, preservation clearly outline the aspects for monitoring and
of the relation (expansion of contractual solidarity), control bearing in consideration the scope,
harmonization of the relational conflict, boundaries, time and cost. During the life of a
supracontract norms and propriety of means. project the team in charge of monitoring should
This theory is applicable in the study variables as develop appropriate approach for monitoring the
contracts in the county government need integrity, Key Performance Indicators (KPI’s). According to
reciprocity, planning, flexibility among other norms Brown and Hyer (2010) the concept of project
to be successful, hence enhance procurement control is a combination of decisions, procedures,
performance. This may be a result of an decisions and actions included in coping with the

100 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

project variances. Project control therefore acts as a anticipated and would be costly.(iii) Pareto’s
guide to the firm and influences the decisions on principle; which states that 80% of project’s
when to make changes or focus on the project limitations and postponement are caused by 20% of
course. project actions. Red tape in organizations may lead
According to Brown and Hyer (2010) in their view to delays intake-off of projects. (iv) Increase of
to monitor and control contracts assert that several Commitment principle which holds that, people
issues interfere with project execution causing the persist in engaging in failing course of action even
actual/real performance to deviate from the at the state of fallacy intent. Therefore a procurement
budgeted performance. The issues are: (i) Scope service level agreement monitoring initiative can
Creep; which basically refers to a situation where the have a strong influence on decisions to escalate or
project grows beyond its initial size. This may be de-escalate commitment
caused by new government rates that will influence
way leaves causing the customers’ needs to inflate 2.4 Conceptual Framework
the budget (ii) Murphy’s Rule; which asserts that The study was guided by the following conceptual
you cannot be accurate and anticipate all risks. The framework. The dependent variable is procurement
government may decide to construct new roads performance while the independent variables are the
where already there is an existing fiber cableen contract management practices.
trenched; the relocation of such a network was not

Monitoring intensity practice Procurement performance


- Quality projects
 Compliance to specifications
- Lead time management
 Complaints management
- Efficiency and effectiveness
 Utilization of resources
- Delivery of goods

Independent variables Dependent variable


Figure 2.1: Conceptual Framework
Population
Research Methodology According to Kumar (2008), populations are all the
Research Design items in the field of inquiry. The population of the
This study used descriptive case study design. study comprised of all the employees of the finance
According to Sekaran & Bougie (2011) descriptive and procurement departments of the County
study is undertaken in order to ascertain and be able Government of Elgeyo Marakwet. According to the
to describe the characteristics of the variable of County’s 2018 records there are 31 procurement
interest in a situation. Descriptive studies are employees and 29 finance employees. This formed
essential in many situations especially when using the target population of the study. This is distributed
qualitative and quantitative data in understanding as shown in Table 3.1
the phenomena.
Table 3.1: Population
Department Population
Finance department 29
Procurement department 31
Total 60

Sample and Sampling Technique is an attempt to gather information about every


The study was stratified the population to their individual in a population. Census sampling is
departments. It then used census sampling to select normally used when the population is small and
the respondents who participated in the study in this manageable. The sample size therefore was 60
case all the population under the study participated respondents.
in the study. According to Rosseau (2012), a census
Table 3.2: Sample Frame
Department Population Sample size
Finance department 29 29
Procurement department 31 31
Total 60 60
101 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

Data Collection Method employing the pre-testing method. Content validity


The study used questionnaires to collect primary on the other hand refers to the capacity of the
data. The questionnaires were semi structured instrument to provide adequate coverage of the
questionnaire. The open ended questions were used topic. Adequate preparation of the instruments under
in order to allow respondents to provide information the guidance of the experts and pre-testing of open
which they may deem relevant for the study. Closed ended questions helped in establishing content. The
ended questions were used in order to standardize questionnaire was assessed by the supervisor in
the responses and save on the respondents’ time order to make sure the information in the instrument
taken to fill in the questionnaire. The researcher will was valid.
exercise care and control to ensure all questionnaires Data Processing and Analysis
issued to the respondents are received. After data collection, the researcher coded the items
ready for analysis. The computer programme
Data Collection Procedure Statistical Package for Social Sciences (SPSS)
The researcher acquired a permit from Jomo version 22.0 aided in data analysis. Data was
Kenyatta University of Agriculture and Technology; analyzed using quantitative data analysis with both
the researcher sought permission from the County descriptive and inferential statistics. Descriptive
Government to conduct the research. A research statistics like frequencies, percentages and means,
permit from the Ministry of Education, Science and cross tabulation were used.
Technology (NACOSTI) was then sought. After Pearson moment of correlation was used to find the
getting all the requirements the researcher embarked correlation between the variables. Multiple
on the journey of collecting data starting from regression analysis with ANOVA technique was
familiarizing herself with the target population to used to determine the effect of independent variables
issuing of the questionnaires and collecting them at on the dependent variable, it was used to measure
an agreed later date. Follow ups were made to ensure the relative influence of each independent variable
that all the questionnaires are filled and returned. based on its covariance dependent variable and was
useful in forecasting. Usually, it is most appropriate
Pilot Test when both the independent and dependent variables
The researcher conducted a pilot study to ascertain are interval, though some social scientists also use
the reliability of the instruments before the study regression on ordinal data. Like correlation,
was done. A pilot study was done in Uasin Gishu regression analysis assumes that the relationship
County government which had similar between variables is linear. In its simplest form
characteristics as the area of study. Reliability is the multiple regression analysis involves finding the
degree to which tests agree with itself and free from best straight-line relationship to explain how the
random errors which normally occur through variation in an outcome (or dependent) variable, Y,
chance. As random error in the data decreases, depends on the variation in a predictor (or
reliability of the data increases (Mugenda, 2008). In independent or explanatory) variable, X. Once the
order to ascertain the reliability of the research relationship is estimated, it is possible to use the
instruments, the results from the pilot study were equation:
subjected to Cronbach Coefficient Alpha. The
reliability coefficient reflects the extent to which Y = b0 + b1X1 + ɛ
items measure the same characteristics. Coefficient
Alpha is calculated using the variance of the total Where:
test score and the variance of the individual item X1 Represents monitoring intensity
scores. Correlations achieved here would be Y Represents The Dependent variable
expected to be above 0.7 to signify a high reliability. (Procurement performance)
A reliability index of 0.7 was appropriate as b Represents Independent Variable
Mugenda & Mugenda (2009) stated that a Coefficients
correlation coefficient tells the researcher the ɛ Represents Error term (sum of the deviations
magnitude of the relationship between the two within the regression line)
variables, the bigger the coefficient, the stronger the
association between the two variables.
Validity of the Research Instruments will also be
tested. Face and content validity of the questionnaire Research Findings and Discussion
was tested whereby face validity is in relation to the Response Rate
misunderstanding or misinterpretation of the A total of 60 questionnaires were sent out to the
questions in the questionnaire. This was checked by respondents to fill. Of these questionnaires, 52 were
102 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

returned for analysis. The returned 52 questionnaires Mugenda, 2013) and therefore a response rate of
accounted for 86.6% response rate. A response rate 86.6% was acceptable for data analysis. Table 4.1
of 70% and above is adequate (Mugenda and shows the response rate.

Table 4.1: Response Rate


Category Frequency Percentage
Administered 60 100.0 %
Returned 52 86.6%

Reliability Test Results instruments. Data was subjected into cronbach alpha
Before the actual study, the researcher did a pilot test coefficient and the findings were generated in
to ascertain the reliability of the research relation to each variables (see Table 4.2).
Table 4.2 Reliability Statistics
Variable Cronbach Alpha Coefficient Test item
Monitoring intensity .866 5
Risk management .857 6
Evaluation .866 6
Dispute Resolution .734 7

According to the reliability statistics indicated the academic level and work experience. These
results shows that the research instrument is reliable. variables were considered to have an influence on
A Cronbach alpha coefficient of >0.7 is deemed the performance of procurement operations in
excellent reliability (Rousson, Gasser & Seifer, organizations.
2010).
Gender of the Respondents
Demographic Characteristics of the An inquiry was made on the gender of the
Respondents respondents. Table 4.3 showed that 55.8% (29) were
An inquiry was made on the ages of the female while 44.2% (23) were male. It was
demographics of the respondents, among the established that majority of the respondents were
demographic information sought were; gender, age, female as illustrated in Table 4.3

Table 4.3 Gender of the Respondents


Gender Frequency Percentage
Male 23 44.2
Female 29 55.8
Total 52 100

Age of the Respondents 21.2% (11) were between 26 to 30 years, another


The study assessed the age of the respondents. Age 21.2% (11) were between 36 to 40 years, 15.4% (8)
was further categorized into different groups. The were 41 to 45 years and 9.6% (5) were over 46 years.
study established that majority 32.7% (17) of the The results therefore are illustrated in Table 4.4;
respondents were between the ages 31 to 35 years,
Table 4.4 Age of the Respondents
Age Frequency Percentage
26-30 Years 11 21.20
31-35 Years 17 32.7
36-40 Years 11 21.2
41-45 Years 8 15.4
Over 46 years 5 9.6
Total 52 100

Level of Education had diverse levels of education, majority had a


The level of education of the respondents was also masters level of education 36.5% (19), 32.7% had a
sought; the findings indicated that the respondents degree level of education 32.7% (17), 26.9% (14)
103 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

had a diploma level and the least of 3.8% (2) had a masters’ levels followed by degree level and
technical certificate. The study shows a high therefore they were learned and well versed on the
percentage of the respondents had completed their study. Table 4.5 illustrates the findings.

Table 4.5 Level of Education


Level of education Frequency Percentage
Technical certificate 2 3.8
Diploma level 14 26.9
Degree level 17 32.7
Masters level 19 36.5
Total 52 100

Work Experience of the Respondents who had worked for between 2 to 5 years and 11
The study sought to establish the level of work years and above respectively, the least 5.8% (3) had
experience of the respondents. The results showed worked for less than 1 year. The findings are
that majority 36.5% (19) of the respondents had illustrated in Table 4.6;
worked for 5 to 10 years, followed by 28.8% (15)
Table 4.6 Work Experience of the Respondents
Work experience Frequency Percentage
Less than a year 3 5.8
Between 2-5 years 15 28.8
Between 5-10 years 19 36.5
11 Years and above 15 28.8
Total 52 100

Descriptive Statistics the level of agreement on a five point Likert scale of


In this section descriptive analysis of the objective the variable performance (Table 4.7).
of the study was done. A scale of 1 to 5 was used to
show the extent to which the respondents agreed to
the statements of effects of monitoring intensity, risk
management, evaluation practices and dispute
resolution practices on procurement performance.

Effects of Monitoring Intensity Practice on


Procurement Performance
For analysis of objective one, correlation was the
preferred statistic. This statistic helped to find out
the relationship between variables. The analysis
therefore opens with the descriptive statistics
(frequency, percentage and mean distribution) for

104 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

Table 4.7 Monitoring Intensity and Procurement Performance


Monitoring Intensity SA A U D SD MEAN
i The contractors follow the standards F 15 30 2 4 1 4.039
required for the their methods of
contracting % 28.8 57.7 3.8 7.7 1.9
ii The contractors always do the right F 17 28 0 3 4 3.981
amount of work within the
approximated time % 32.7 53.8 0 5.8 7.7
iii The contractors always use the right F 4 36 5 4 3 3.654
amount of resources to complete the
projects assigned to them % 7.7 69.2 9.6 7.7 5.8
iv The supervisors carry out their duties F 16 27 3 4 2 3.981
to make sure that the contracts given
% 30.8 51.9 5.8 7.7 3.8
out are successful
v Funds allocated are well utilized for F 25 18 5 2 2 4.192
only the intended projects
% 48.1 34.6 9.6 3.8 3.8
vi Formal monthly inspections are being F 22 21 6 3 0 4.192
done on the projects
% 42.3 40.4 11.5 5.8 0
vii The contractors always comply with F 10 35 0 0 7 3.789
the service quality levels which has
been specified in the bidding % 19.2 67.3 0 0 13.5
document

The responses on monitoring intensity revealed that duties to make sure that the contracts given out are
the contractors follow the standards required for the successful, this was spread at 3.9808.
their methods of contracting where 57.7% agreed on The findings also indicated that funds allocated are
this and 28.5% strongly agreed giving an average well utilized for only the intended projects with
mean of 4.03. On the response that the contractors majority 48.1% of the respondents strongly agreeing
always do the right amount of work within the on this and 34.6% agreed. The mean was spread at
approximated time, the study established a high 4.1923. Further findings on the fact that formal
percentage of agreement on this 53.8% agreed while monthly inspections are being done on the projects
32.7% strongly agreed with a mean of 3.98. indicated a majority of the respondents being in
Further results showed that a majority 69.2% agreed agreement with this. This was denoted by 42.3%
and 7.7% strongly agreed that the contractors always strongly agreed while 40.4% agreed with a mean of
use the right amount of resources to complete the 4.1923.
projects assigned to them. The mean was labeled at Lastly, the findings showed that majority of 67.3%
3.6538. In addition, the study established that of the respondents and 19.2% agreed and strongly
majority of the respondents agreed 51.9%, 30.8% agreed respectively on the idea that the contractors
strongly agreed that the supervisors carry out their always comply with the service quality levels which

105 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

has been specified in the bidding document. The


mean was spread at 3.7885.

Inferential Statistics
Correlation analysis was used to determine the relationship between variables, while regression analysis was
used to test the hypothesis of the study.
Correlation Analysis on Monitoring Intensity and Procurement Performance
This was done using Pearson correlation statistical analysis. The correlation was measured at 0.05 significant level
(2-tailed). The findings are shown in table 4.8.

Table 4.8 Correlation Analysis Monitoring Intensity and Procurement Performance


Monitoring Intensity
Performance Pearson Correlation 0.057**
Sig. (2-tailed) .288
N 52
**. Correlation is significant at the 0.05 level (2-tailed).
Pearson's correlation was run to determine the From the Analysis report p = 0.288, which is more
relationship between the monitoring intensity and than 0.05, as such, there is no significant relationship
procurement performance of the organization. The between monitoring intensity and the procurement
results established a positive but weak correlation performance of the organization at Elgeyo
between the variables (P= 0.288, r=.057). The Marakwet County. Therefore, monitoring intensity
strength of association was weak. alone could not be associated with high procurement
performance of the organization.

Hypothesis testing using Regression Analysis


Table 4.9 Model Summary
Model Summary
Model R R Square Adjusted R Square Std. Error of the
Estimate
1 .923a .852 .849 .57938
a. Predictors: (Constant), d, a, b, c

This table provides the R and R2 values. The R value dependent variable, procurement performance, can
represents the simple correlation and is 0.923 (the be explained by the independent variable, contract
"R" Column), which indicates a high degree of management practices. In this case, it is 85.2%
correlation. The R2 value (the "R Square" column) which is very large.
indicates how much of the total variation in the

Table 4.10 ANOVA Summary for Regression Model


ANOVAa
Model Sum of Squares df Mean Square F Sig.
1 Regression 439.053 4 109.763 326.982 .000b
Residual 76.536 228 .336
Total 515.589 232
a. Dependent Variable: Procurement performance
b. Predictors: (Constant), d, a, b, c
The prediction of the variable p represented by 0.000 indicates that the regression model is statistically
significant.

Table 4.11 Model Summary


Coefficientsa
Model Unstandardized Coefficients Standardized t Sig.
Coefficients
B Std. Error Beta
(Constant) 1.944 .619 3.139 .002
106 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

Monitoring intensity -.017 .011 -.043 -1.559 .120

From the regression model computed in Table 4.11, was also run to determine the relationship between
the research hypotheses were tested using the the monitoring intensity and procurement
significance level of the coefficients. The research performance of the organization. The results
aimed to test the hypothesis with an aim of accepting established a positive but weak correlation between
or rejecting the relationship between contract the variables. The strength of association was weak.
management strategies and procurement Therefore, monitoring intensity alone could not be
performance. The research hypothesis for the study associated with high procurement performance of
included; the organization.
The regression results in this variable indicated that
There is no Significant Influence of Monitoring monitoring intensity does not have a direct effect on
Intensity on Procurement Performance. the procurement performance of the organization.
The regression results in Table 4.11 indicate that The study accepted the hypothesis. The findings
monitoring intensity does not have a direct effect on implied that concentrating on monitoring intensity
the procurement performance of the organization does not give the organizations any bases of
with a beta coefficient of -0.043 and significance of procurement performance.
(p=0.120). The study accepted the hypothesis. These
findings imply that concentrating on monitoring Conclusions
intensity does not give the organizations any bases The study concluded that monitoring intensity was a
of procurement performance. This may be true in factor that influences procurement performance in
that monitoring intensity should be incorporated organizations. However it was noted that other
with other factors so as to influence the performance factors were needed to support this practice. The
of procurement operations of an organization. county made sure that funds allocated are well
utilized for only the intended projects, they also did
Summary, Conclusions and Recommendations formal monthly inspections on the projects to ensure
Effects of Monitoring Intensity on Procurement progress and that the contractors followed the
Performance standards required for the their methods of
The first objective was to assess the effect of contracting.
monitoring intensity practice on procurement Recommendations
performance. The study found that the organization On monitoring intensity practice, it is recommended
was able to practice monitoring intensity with the that contractors should be allocated with the right
view to enhance procurement performance, for amount of resources to complete the projects
instance the organization made sure that funds assigned to them. On risk management practice, the
allocated are well utilized for only the intended study recommends that there should be regular
projects, they also did formal monthly inspections supply of material resources to be used in projects,
on the projects to ensure progress and that the this will allow them to manage the risks underway
contractors followed the standards required for the as they complete the projects.
their methods of contracting. Pearson's correlation
Reports. Florida, USA: CRC Press.
Chitkara V. (2015). Relationship between
References Innovativeness, Quality, Growth,
Bassioni, H., Price, A. & Hassan, T. (2004). Profitability and Market Value. Strategic
Performance Measurement in Management Journal, 26(6), 555-576.
Construction. J. Manage. Eng., 20(2), 42- COMESA Investment Report (2011) Common
50. Market for Eastern and Southern Africa
Bolton, M.L. (2006). Insights to Performance Contract Monitoring Kenya Network, CMKN
Excellence, 2009-2010: an inside look at (2012). Press Release. Launch of the
the 2009-2010 Baldrige Award criteria. Contract Monitoring Kenya Network and
Milwaukee: Asq. Quality Press. Baseline Report.
Boyne (1998). Human Resource Management: An Dew, C. (2008). Contractual Governance for
Experimental Approach, Academy of Sustainable Service. Qualitative Research
Management Journal, 38 (5), 673-703. in Accounting & Management, 2(1), 29 -
Brown, S.L., & Hyer, D.A. (2010). A Practical 53.
Guide to Understanding, Managing, and Ferris L., & Graddy, H.M. (1986). Public
Reviewing Environmental Risk Assessment Management in Global Perspective. New

107 | P a g e
Tallam and Kibet (2018) www.oircjournals.org
International Journal of Scientific and Technological Research (IJSTER)
ISSN: 2617-6416 Vol. 1 (1) 97-108 November, 2018
www.oircjournals.org

York, NY: M.E. Sharpe. 24 (2), 235-256.


Industry Manual (2008) Benchmarking UK Sekaran, U. and Bougie, R. (2013) Research
Government Procurement Performance in Methods for Business: A Skill-Building
Construction Projects. Measuring Business Approach. 6th Edition, Wiley, New York.
Excellence, 5(4), 13-21. Swinnery, F. & Netsins, J. (2007). The Procurement
Jeanette R. (2008). Benchmarking in Public and Supply Manager's Desk Reference
Procurement. Benchmarking: An Hoboken, N.J.: Wiley.
International Journal, 15 (6), 782-793. Thai, R., (2005). Drug Procurement, the Global
Jiang, K. & Qureshi, Y. (2006). Operational Factors Fund and Misguided Competition Policies.
Affecting Strategic Partnering in UK social Malaria Journal, 8 (1), 305
housing. Engineering, Construction and
Architectural Management, 14(4), 334-
345.
Kakwezi P. (2012). Procurement Contract
Management in Public Procurement and
Disposal Entities (PDES). The
International Journal’s Research Journal
of Economics and Business Studies, 2(1),
230-240.
Kumar, N. (2008). Procurement performance in the
Public Universities in Kenya. University of
Nairobi. Pp. 1-50.
Lowe, D. (2013). Commercial Management Theory
and Practice. Chichester, West Sussex:
Wiley-Blackwell.
Macneil, I.R. (1980) 'Contracts: Adjustment of
Long-Term Economic Relations under
Classical, Neoclassical and Relational
Contract Law' (1978) 72. Northwestern
University Law Review
Meredith G. & Mantel, B. (2012). Core Concepts in
Data Analysis: Summarization,
Correlation and Visualization. London:
Springer.
Mugenda, O.M. and Mugenda, A.G. (2003)
Research Methods, Quantitative and
Qualitative Approaches. ACT, Nairobi
OECD. (2011).Contract Management. OECD
Publishing House
Prager C. (1994). Unbundled Government: A
Critical Analysis of the Global Trend to
Agencies, Quangos and
Contractualisation. New York, NY:
Routledge.
Project management Institute. (2007). Construction
Extension to the PMBOK Guide. 3rd ed.
Newtown square: Project Management
Institute
Saxena, A. (2008). Enterprise Contract
Management a Practical Guide to
Successfully Implementing an ECM
solution. McGraw Hill
Schiel, D. (2007). A Lifecycle Perspective on