Professional Documents
Culture Documents
ALECATEL BTS
Prepared by
Eng.\ Ahmed Elkhaiat
12/31/2008 AKHAIAT 1
Actual steps to make commissioning
Actual steps to make commissioning
1. Opening the terminal release.
2. Connection to BTS(off air) .
( ff )
3. Downloading Master and slave files(off air).
g ( )
4. Initializing all sectors(off air).
5
5. Measuring VSWR(off air)
Measuring VSWR(off air).
6. Making fans test(off air).
7. End commissioning(off air).
8
8. Putting Qmax address(on air)
Putting Qmax address(on air).
9. Putting time slot(o‐31)(on air).
12/31/2008 AKHAIAT 2
•Open BTS terminal release
•Open BTS terminal release
12/31/2008 AKHAIAT 3
Write the user name and password
•Write the user name and password
12/31/2008 AKHAIAT 4
Click on connection symbol
•Click on connection symbol
12/31/2008 AKHAIAT 5
12/31/2008 AKHAIAT 6
g
•Downloading files
12/31/2008 AKHAIAT 7
Don t put Qmax now so click NO
•Don’t put Qmax now so click NO
12/31/2008 AKHAIAT 8
•Determine the path for master and
slave files then click on download
l fl h l k d l d
12/31/2008 AKHAIAT 9
12/31/2008 AKHAIAT 10
12/31/2008 AKHAIAT 11
12/31/2008 AKHAIAT 12
Add the sectors according to DCR
Add the sectors according to DCR
12/31/2008 AKHAIAT 13
g
•Initializing all sectors
12/31/2008 AKHAIAT 14
12/31/2008 AKHAIAT 15
g
•Measuring VSWR
12/31/2008 AKHAIAT 16
•Select the sector to be measured then
click start
12/31/2008 AKHAIAT 17
•After measuring the sector click Stop
then select another sector and so on
12/31/2008 AKHAIAT 18
g
•Testing Fans
12/31/2008 AKHAIAT 19
12/31/2008 AKHAIAT 20
•Select the fan row to be measured
and press Execute
12/31/2008 AKHAIAT 21
gp
•After testing press Close
12/31/2008 AKHAIAT 22
•End commissioningg
12/31/2008 AKHAIAT 23
12/31/2008 AKHAIAT 24
•Put the Site Name and add the BTS
modules to be updated and submit
12/31/2008 AKHAIAT 25
12/31/2008 AKHAIAT 26
•Click yes
12/31/2008 AKHAIAT 27
• The previous steps were the off air steps.
The previous steps were the off air steps
• Now make the power off and connect E1 cable.
• Reconnect the power to the cabinet again.
• Then do the on air steps as the following
Then do the on air steps as the following.
12/31/2008 AKHAIAT 28
Putting the QMAX address
•Putting the QMAX address
12/31/2008 AKHAIAT 29
p g p g
•After putting data press Get Config
12/31/2008 AKHAIAT 30
12/31/2008 AKHAIAT 31
•Putting the time slots values and sum
functionality
12/31/2008 AKHAIAT 32
p g p g
•After putting data press Get Config
12/31/2008 AKHAIAT 33
12/31/2008 AKHAIAT 34