ID Description Dur Dur Start Finish Float
Milestones
Contract Milestones
Pre-construction
Pre-construction Meetings
DBA Insurance
Design
10% Design Submittal
Procurement
Civil/Structural
Concrete Reinforecement
Architectural
Joint Sealant
Electrical
Generator
Mechanical
Plumbing
Water and Sewer Pipes
Construction
Mobilization
Sitework
Site Demolition/Grading
Volleyball Fields
1st Field
RPS-0030 Layout Volleyball Fields 1 0 100 12MAY12A 12MAY12A
RPS-0031 Excavation Volleyball Fields 10 0 100 20MAY12A 16JUL12A
RPS-0032 Backfiling / Compaction Volleyball Fields 10 0 100 03JUL12A 16JUL12A
RPS-0033 Sand for Volleyball Fields 10 0 100 22JUL12A 26AUG12A
RPS-0034 Test & Completion Volleyball Fields 1 1 0 01APR13 01APR13 85
2nd Field
RPS-0035 Layout Volleyball Fields 1 0 100 12MAY12A 12MAY12A
RPS-0036 Excavation Volleyball Fields 12 0 100 16MAY12A 24JUL12A
RPS-0037 Backfiling / Compaction Volleyball Fields 12 0 100 04JUN12A 26AUG12A
RPS-0038 Sand for Volleyball Fields 12 0 100 18NOV12A 01DEC12A
RPS-0039 Test & Completion Volleyball Fields 1 1 0 01APR13 01APR13 85
Force Protection
Personnel Bunker
BUNKER #1,2,3
FPR-0001 Layout for Bunker #1,2,3 1 0 100 18NOV12A 18NOV12A
FPR-0002 Casting for Bunker #1,2,3 8 0 100 19NOV12A 27NOV12A
FPR-0003 Construct Bunker #1,2,3 4 0 100 21NOV12A 09JAN13A
FPR-0004 Cmplt Sandbag & T. Barriers of B. #1,2,3 6 6 70 10DEC12A 07APR13 79
FPR-0005 Test & Completion of Bunker # 1,2,3 1 1 0 08APR13 08APR13 79
BUNKER #4,5,6
FPR-0006 Layout for Bunker #4,5,6 1 0 100 02DEC12A 02DEC12A
FPR-0007 Casting for Bunker #4,5,6 8 0 100 03DEC12A 17DEC12A
FPR-0008 Construct Bunker #4,5,6 4 0 100 18DEC12A 09JAN13A
FPR-0009 Cmplt Sandbag & T. Barriers of B. #4,5,6 6 6 70 10FEB13A 07APR13 78
FPR-0010 Test & Completion of Bunker #4,5,6 1 1 0 08APR13 08APR13 78
BUNKER #7,8,9
FPR-0012 Casting Bunker #7,8,9 8 0 100 18DEC12A 26DEC12A
FPR-0011 Layout for Bunker #7,8,9 1 0 96 18DEC12A 31MAR13 85
FPR-0013 Construct Bunker #7,8,9 4 0 100 20DEC12A 14JAN13A
FPR-0014 Cmplt Sandbag & T. Barriers of B. #7,8,9 6 6 25 10JAN13A 07APR13 79
FPR-0015 Test & Completion of Bunker #7,8,9 1 1 0 09APR13 09APR13 78
BUNKER #10,11,12,13
FPR-0016 Layout for Bunker #10,11,12,13 1 0 100 31DEC12A 31DEC12A
FPR-0017 Casting for Bunker #10,11,12,13 10 0 100 31DEC12A 03JAN13A
FPR-0018 Construct Bunker #10,11,12,13 4 0 100 06JAN13A 14JAN13A
FPR-0019 Cmplt Sandbag & T.Barriers of B.#10,11,12,13 6 6 25 18MAR13A 07APR13 78
FPR-0020 Test & Completion of Bunker#10,11,12,13 1 1 0 08APR13 08APR13 78
BUNKER #14,15,16,17
FPR-0021 Layout for Bunker #14,15,16,17 1 0 100 31DEC12A 31DEC12A
FPR-0022 Casting for Bunker #14,15,16,17 10 0 100 31DEC12A 06JAN13A
Utilities
Water Supply and Distribution System
Water Distribution
Buildings
Arms Storage Buildings #100
Foundations
GFC-0025 Nrth Prt Ele PVC Conduits & Fittings & Boxes 5 5 80 01DEC12A 06APR13 66
GFC-0026 Nrth Prt Electrical Wiring Works 5 5 80 01JAN13A 06APR13 66
GFC-0028 Nrth Prt Duplex and switch installation 18 10 70 03JAN13A 11APR13 58
GFC-0027 Nrth Prt Lighting Fix. & Cover Plates Insta 2 2 0 13APR13 14APR13 61
GFC-0041 Nrth Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -21
GFC-0032 Nrth Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 44
GFC-0034 Nrth Prt Toilet & Misc.Accessories 4 4 0 18APR13 22APR13 44
GFC-0033 Nrth Prt Toilet Sanitry Fixture Installation 15 15 0 23APR13 09MAY13 44
Fire Protection System
GFC-0037 Nrth Prt Telephone and Data wall recepticle Inst 15 15 35 02JAN13A 17APR13 63
Inspections, Punchlists
GFC-0066 West Prt Elec PVC Conduits & Fittings & Boxes 5 0 100 01JAN13A 23MAR13A
GFC-0068 West Prt Duplex and switch installation 10 10 45 03JAN13A 11APR13 68
GFC-0067 West Prt Electrical Wiring Works 5 5 50 10JAN13A 06APR13 65
GFC-0069 West Prt Lighting Fix. & Cover Plates Inst 2 2 0 22APR13 23APR13 50
GFC-0070 West Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -23
Mechanical
GFC-0074 West Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 55
GFC-0075 West Prt Kitchen & Misc.Accessories 5 5 0 18APR13 23APR13 57
GFC-0076 West Prt Kithen Fixture Installation 8 8 0 18APR13 27APR13 55
Fire Protection System
GFC-0079 West Prt Tele and Data wall receptacle Insta 15 15 40 02JAN13A 17APR13 63
GFC-0115 Sout Prt Ele PVC Conduits & Fittings & Boxes 5 5 90 01FEB13A 07APR13 65
GFC-0116 Sout Prt Electrical Wiring Works 5 5 40 21FEB13A 07APR13 65
GFC-0118 Sout Prt Duplex and switch installation 10 10 20 28FEB13A 11APR13 77
GFC-0117 Sout Prt Lighting Fix. & Cover Plates Inst 2 2 0 13APR13 14APR13 61
GFC-0119 Sout Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -21
Mechanical
GFC-0122 Sout Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 53
GFC-0124 Sout Prt Toilet Sanitry Fixture Installation 3 3 0 18APR13 21APR13 55
GFC-0123 Sout Prt Toilet & Misc.Accessories 5 5 0 18APR13 23APR13 53
Fire Protection System
GFC-0127 Sout Prt Telephone and Data wall recepticle Inst 3 3 38 01MAR13A 23JUN13 6
Inspections, Punchlists
KAN-0008 KHQ - Inst of Steel Bar for Stem Wall 10 0 100 25JUL12A 12AUG12A
ADM-0008 ADB 109 - Inst. of Steel Bar for Stem Walls 4 0 100 01JUL12A 04JUL12A
ADM-0009 ADB 109 - Concrete for Stem Walls 7 0 100 02JUL12A 20SEP12A
ADM-0010 ADB 109 - Installation of K Span 13 0 100 01OCT12A 09OCT12A
Architectural - Exterior
ADM-0014 ADB 109 - Plaster Work for steam Walls 8 0 100 10OCT12A 18OCT12A
ADM-0015 ADB 109 - Spray Insulation 7 7 70 10DEC12A 08APR13 37
ADM-0017 ADB 109 - Inst. of gypsum Board 8 8 10 18DEC12A 09APR13 37
ADM-0019 ADB 109 - Sealed Concrete for Floor 4 4 20 23MAR13A 04APR13 68
ADM-0018 ADB 109 - Interior Doors Instalation 5 5 0 10APR13 15APR13 39
ADM-0016 ADB 109 - Inst. of Suspended Ceiling 8 8 0 10APR13 18APR13 39
Electrical
ADM-0028 ADB 109 - Hot & Cold Water Piping 7 7 50 01DEC12A 08APR13 54
ADM-0029 ADB 109 - Toilet & Misc. Accessories 5 5 0 09APR13 14APR13 54
ADM-0030 ADB 109 - Toilet Sanitry Fixture Inst 6 6 0 09APR13 15APR13 54
Fire Protection System
LA1-0008 LTB 110- Inst. Steel Bar for Stem Walls 13 0 100 17JUN12A 02JUL12A
LA1-0009 LTB 110- Concrete for Stem Walls 15 0 100 19JUN12A 27OCT12A
LA1-0010 LTB 110- Installation of K Span 20 0 100 01OCT12A 09OCT12A
Architectural - Exterior
LA1-0014 LTB 110- Plaster Work for Steam Walls 12 0 100 18NOV12A 01DEC12A
LA1-0018 LTB 110- Int. Doors Installation 7 7 30 30DEC12A 08APR13 56
LA1-0015 LTB 110- Spray Insulation 7 7 0 01APR13 08APR13 36
LA1-0017 LTB 110- Inst of gypsum Board 12 12 0 09APR13 22APR13 36
LA1-0016 LTB 110- Inst. of gypsum Board Ceiling 12 12 0 23APR13 06MAY13 36
LA1-0019 LTB 110- Tiles for floor 10 10 0 04MAY13 14MAY13 36
LA1-0028 LTB 110- Hot & Cold Water Piping 7 7 50 01DEC12A 08APR13 64
LA1-0030 LTB 110- Toilet Sanitry Fixture Inst. 7 7 50 02FEB13A 08APR13 67
LA1-0029 LTB 110- Toilet & Misc. Accessories 5 5 0 09APR13 14APR13 64
Fire Protection System
LA2-0008 LTB 111- Inst of Steel Bar for Stem Walls 12 0 100 18JUN12A 03JUL12A
LA2-0009 LTB 111- Inst. of Concrete Stem Walls 15 0 100 04JUL12A 01OCT12A
LA2-0010 LTB 111- Installation of K Span 15 0 100 01OCT12A 09OCT12A
Architectural - Exterior
LA2-0014 LTB 111- Plaster for Steam Walls 7 0 100 18NOV12A 25NOV12A
LA2-0015 LTB 111- Spray Insulation 7 7 0 07APR13 14APR13 12
LA2-0016 LTB 111- Inst of gypsum Board Ceiling 6 6 0 15APR13 21APR13 39
LA2-0017 LTB 111- Inst. of gypsum Board 10 10 0 15APR13 25APR13 12
LA2-0018 LTB 111- Int. Doors Installation 7 7 0 27APR13 04MAY13 12
LA2-0019 LTB 111- Tiles for floor 15 15 0 24APR13 11MAY13 39
Electrical
LA2-0027 LTB 111- Hot & Cold Water Piping 7 7 25 01DEC12A 09APR13 60
LA2-0029 LTB 111- Toilet Sanitry Fixture Inst. 7 7 10 01MAR13A 09APR13 65
LA2-0028 LTB 111- Toilet & Misc. Accessories 4 4 0 10APR13 14APR13 60
Fire Protection System
LA3-0008 LTB 112- Inst. of Steel Bar for Stem Walls 12 0 100 25JUN12A 10JUL12A
LA3-0009 LTB 112- Concrete Stem Walls 12 0 100 11JUL12A 02OCT12A
LA3-0010 LTB 112- Installation of K Span 15 0 100 02OCT12A 09OCT12A
Architectural - Exterior
LA3-0014 LTB 112- Plaster for Steam Walls 10 0 100 10NOV12A 20NOV12A
LA3-0015 LTB 112- Spray Insulation 7 7 0 09APR13 15APR13 29
LA3-0016 LTB 112- Inst. of gypsum Board ceiling 7 7 0 16APR13 22APR13 29
LA3-0017 LTB 112- Inst. of gypsum Board 15 15 0 23APR13 07MAY13 29
LA3-0019 LTB 112- Tiles for floor 10 10 0 27APR13 07MAY13 42
LA3-0018 LTB 112- Interior Doors Inst. 12 12 0 08MAY13 21MAY13 25
Electrical
LA3-0027 LTB 112- Hot & Cold Water Piping 7 7 50 01DEC12A 09APR13 57
LA3-0029 LTB 112- Toilet Sanitry Fixture Inst. 7 7 10 01MAR13A 09APR13 62
LA3-0028 LTB 112- Toilet & Misc. Accessories 4 4 0 10APR13 14APR13 57
Fire Protection System
L4-0008 LTB 113- Inst. of Steel Bar for Steam Walls 10 0 100 30JUN12A 10JUL12A
L4-0009 LTB 113- Inst. of Concrete Steam Walls 12 0 100 11JUL12A 09DEC12A
L4-0010 LTB 113- Installation of K Span 15 0 100 02DEC12A 06DEC12A
Architectural - Exterior
L4-0014 LTB 113- Plaster Work for Steam Walls 7 7 20 10JAN13A 08APR13 19
L4-0015 LTB 113- Spray Insulation 7 7 0 09APR13 16APR13 19
L4-0016 LTB 113- Inst. of gypsum Board Ceiling 10 10 0 17APR13 28APR13 19
L4-0017 LTB 113- Inst. of gypsum Board 14 14 0 17APR13 02MAY13 35
L4-0019 LTB 113- Tiles for floor 10 10 0 01MAY13 12MAY13 19
L4-0018 LTB 113- Int. Doors Installation 15 15 0 04MAY13 20MAY13 35
Electrical
LA5-0008 LTB 114- Inst. Steel Bar for Stem Walls 4 0 100 16JUN12A 09SEP12A
LA5-0009 LTB 114- Concrete for Stem Walls 8 0 100 11JUL12A 18SEP12A
LA5-0010 LTB 114- Installation of K Span 15 0 100 15AUG12A 26SEP12A
Architectural - Exterior
LA5-0014 LTB 114- Plaster Work for Stem Walls 7 0 100 10OCT12A 17OCT12A
LA5-0015 LTB 114- Spray Insulation 7 7 0 18APR13 25APR13 8
LA5-0016 LTB 114- Inst. of gypsum Board Ceiling 6 6 0 27APR13 02MAY13 8
LA5-0017 LTB 114- Inst. of gypsum Board 15 15 0 27APR13 13MAY13 29
LA5-0018 LTB 114- Int. Doors Installation 10 10 0 18MAY13 28MAY13 26
LA5-0019 LTB 114- Tiles for Floor 15 15 0 12MAY13 28MAY13 8
LA6-0008 LTB 115- Inst. of Steel Bar for Stem Walls 4 0 100 20JUN12A 25JUN12A
LA6-0009 LTB 115- Concrete Stem Walls 8 0 100 26JUN12A 19JAN13A
LA6-0010 LTB 115- Installation of K Span 15 0 100 27NOV12A 05DEC12A
Architectural - Exterior
LA6-0014 LTB 115- Plaster for Stem Walls 7 0 100 18MAR13A 25MAR13A
LA6-0015 LTB 115- Spray Insulation 7 7 0 18APR13 25APR13 11
LA6-0016 LTB 115- Inst. of gypsum Board Ceiling 6 6 0 27APR13 02MAY13 11
LA6-0017 LTB 115- Inst. of gypsum Board 14 14 0 27APR13 12MAY13 23
LA6-0018 LTB 115- Int. Doors Installation 10 10 0 13MAY13 23MAY13 23
LA6-0019 LTB 115- Tiles for Floor 15 15 0 07MAY13 23MAY13 11
Electrical
LA6-0027 LTB 115- Hot & Cold Water Piping 7 7 0 25MAY13 01JUN13 11
LA6-0029 LTB 115- Toilet Sanitry Fixture Inst. 4 4 0 02JUN13 05JUN13 12
LA6-0028 LTB 115- Toilet & Misc. Accessories 5 5 0 02JUN13 06JUN13 11
Fire Protection System
MWR-0008 MWR 105D- Inst. of Steel Bar for Stem Walls 6 0 100 09JUL12A 25SEP12A
MWR-0009 MWR 105D- Inst of Concrete Stem Walls 9 0 100 26SEP12A 19NOV12A
MWR-0010 MWR 105D- Installation of K Span 13 0 100 03OCT12A 24NOV12A
Architectural - Exterior
MWR-0014 MWR 105D- Plaster Work for Stem Walls 6 0 100 20NOV12A 26NOV12A
MWR-0015 MWR 105D- Spray Insulation 4 4 25 25NOV12A 04APR13 43
MWR-0016 MWR 105D- Fence Installation 9 9 0 06APR13 15APR13 47
DPW-0018 MWR 105D- Int. Doors Installation 6 6 0 24APR13 30APR13 43
MWR-0019 MWR 105D- Sealed Concrete for Floor 4 4 0 30APR13 04MAY13 46
Electrical
DPW-0008 DPW 116- Inst. of Steel Bar for Steam Walls 12 0 100 26JUN12A 08JUL12A
DPW-0009 DPW 116- Inst. of Concrete Steam Walls 12 0 100 10SEP12A 14JAN13A
DPW-0010 DPW 116- Installation of K Span 15 0 100 02OCT12A 26NOV12A
Architectural - Exterior
DPW-0028 DPW 116- Hot & Cold Water Piping 6 6 0 30APR13 06MAY13 35
DPW-0030 DPW 116- Toilet Sanitry Fixture Inst. 4 4 0 07MAY13 11MAY13 35
DPW-0029 DPW 116- Toilet & Misc. Accessories 5 5 0 07MAY13 12MAY13 35
Fire Protection System
LCR1-008 LCR 117A - Inst. of Steel Bar for Stem Walls 6 0 100 28JUN12A 04JUL12A
LCR1-009 LCR 117A - Concrete for Stem Walls 10 0 100 05JUL12A 02OCT12A
LCR1-010 LCR 117A - Installation of K Span 15 0 100 12AUG12A 08OCT12A
Architectural - Exterior
LCR1-014 LCR 117A - Plaster Work for Steam Walls 13 0 100 10OCT12A 24OCT12A
LCR1-015 LCR 117A - Spray Insulation 7 7 95 25NOV12A 08APR13 48
LCR1-017 LCR 117A - Int. Doors Installation 5 5 30 03MAR13A 06APR13 61
LCR1-016 LCR 117A - Fence Installation 10 10 0 09APR13 20APR13 48
LCR1-018 LCR 117A - Sealed Concrete for Floor 8 8 0 21APR13 29APR13 48
Electrical
LCR2-008 LCR 117B- Inst. of Steel Bar for Stem Walls 10 0 100 20JUN12A 02JUL12A
LCR2-009 LCR 117B- Concrete for Stem Walls 15 0 100 03JUL12A 02OCT12A
LCR2-010 LCR 117B- Installation of K Span 15 0 100 13AUG12A 08OCT12A
LCR2-014 LCR 117B- Plaster for Stem Walls 10 0 100 10OCT12A 09FEB13A
LCR2-015 LCR 117B- Spray Insulation 7 7 90 10DEC12A 08APR13 52
LCR2-017 LCR 117B- Int. Doors Installation 5 5 30 04MAR13A 06APR13 61
LCR2-016 LCR 117B- Fence Installation 10 10 0 09APR13 20APR13 52
LCR2-018 LCR 117B- Sealed Concrete for Floor 8 8 0 10APR13 18APR13 56
FSB-0014 FSB 118- Plaster for Stem Walls 10 0 100 10DEC12A 28MAR13A
FSB-0015 FSB 118- Spray Insulation 7 7 25 21FEB13A 07APR13 54
FSB-0017 FSB 118- Int. Doors Instalation 7 7 20 01MAR13A 08APR13 59
FSB-0016 FSB 118- Fence Installation 8 8 0 08APR13 15APR13 54
FSB-0018 FSB 118- Sealed Concrete for Floor 5 5 0 28APR13 02MAY13 46
Contract Close-out
Close-out Inspections
As-Built Drawings
Demobilization
CCO-0012 Demobilization of Site office & Con. Equipments 10 10 0 27AUG13 05SEP13 -32