You are on page 1of 38

Activity Activity Orig Rem % Early Early Total 2011 2012 2013

J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

W5J9JR-10-D-0005-0006 ANA Gardez


Total 773 158 68 26JUL11A 05SEP13 -32

Milestones
Contract Milestones

KEY-0001 Notice to Proceed (NTP) 0 0 100 26JUL11A


KEY-0002 Project Duration 773* 158* 0 26JUL11A 05SEP13 -32
KEY-0003 End Date of Project 0 0 0 05SEP13 -32
Project Milestones

KEY-0004 Start Work on Project 0 0 100 27JUL11A


KEY-0005 Release Partial Letter for CON 1 0 100 09MAY12A 09MAY12A
KEY-0006 Release Letter for Full CON 1 1 0 01APR13 01APR13 -7

Pre-construction
Pre-construction Meetings

KEY-0007 Provide Documents for Pre-CON 6 0 100 27JUL11A 01AUG11A


KEY-0008 Hold Pre-CON Meeting 1 0 100 02AUG11A 02AUG11A
Pre-construction Submittals

KEY-0009 Submit ActivityHazard Analysis 1 0 100 02AUG11A 02AUG11A


KEY-0010 Submit Baseline Schedule 1 0 100 02AUG11A 02AUG11A
KEY-0011 Submit Accidend PreventionPlan 1 0 100 02AUG11A 02AUG11A
KEY-0012 Submit Quality Control Plan 1 0 100 02AUG11A 02AUG11A
KEY-0013 Submit Security Plan 1 0 100 02AUG11A 02AUG11A
KEY-0014 Approve Activity Hazard Analysis 14 0 100 03AUG11A 16AUG11A
KEY-0015 Approve Baseline Schedule 14 0 100 03AUG11A 16AUG11A
KEY-0016 Approve AccidentPreventionPlan 14 0 100 03AUG11A 16AUG11A
KEY-0017 Approve QC Plan by USACE 14 0 100 03AUG11A 16AUG11A
KEY-0018 Approved Security Plan by AED 14 0 100 03AUG11A 16AUG11A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 1 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

DBA Insurance

KEY-0019 DBA Insurance 1 0 100 26JUL11A 26AUG11A

Design
10% Design Submittal

DES-0001 Site Survey 22 0 100 10AUG11A 05SEP11A


DES-0003 10% Site Design Submittal 13 0 100 10OCT11A 25OCT11A
DES-0002 Geotechnical Report 12 0 100 26OCT11A 06NOV11A
DES-0004 10% Site Design Conference / Approval 14 0 100 26OCT11A 08NOV11A
DES-0014 Pay Request 10% Desgin 1 0 100 09NOV11A 09NOV11A

65% Design Submittal

DES-0005 65% Design Submittal 4 0 100 24MAR12A 27MAR12A


DES-0016 65% Design Conference / Approval 14 0 100 29MAR12A 08APR12A
DES-0006 Pay Request 65% Design 1 0 100 05JUN12A 05JUN12A

100% Design Submittall

DES-0009 100% Design Submittal 10 0 100 10OCT12A 24OCT12A


DES-0010 100% Design Conference / Approval 14 0 100 25OCT12A 31OCT12A
DES-0020 Pay Request 100% Design 1 0 100 01NOV12A 01NOV12A

Procurement
Civil/Structural
Concrete Reinforecement

PRO-0001 Submit Reinforcement Steel 5 0 100 13NOV11A 17NOV11A


PRO-0002 Approved Reinforcement Steel 14 0 100 18NOV11A 01DEC11A
PRO-0003 Issue Parchase Order for SS 2 0 100 17DEC11A 19DEC11A
PRO-0004 Delivery of SS to Jobsite 5 0 100 08MAY12A 11MAY12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 2 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
PRO-0064 Production of Concrete 10 0 100 12MAY12A 21MAY12A
3D Panel

PRO-0009 Submit 3D Data Sheet 5 0 100 21APR12A 25APR12A


PRO-0010 Approve 3D Data 14 0 100 25APR12A 05MAY12A
PRO-0011 Issue Purchase Order for 3D 5 0 100 05MAY12A 09MAY12A
PRO-0072 Production of 3D for Project 10 0 100 10MAY12A 20MAY12A
PRO-0012 Deliver of 3D to Jobsite 5 0 100 21MAY12A 25MAY12A
K Span

PRO-0060 Submit K Span 5 0 100 21APR12A 25APR12A


PRO-0061 Approve K Span 14 0 100 25APR12A 08MAY12A
PRO-0062 Manufacturing of K Span 10 0 100 09MAY12A 19MAY12A
PRO-0063 Deliver of K Span to Jobsite 5 0 100 19MAY12A 23MAY12A

Architectural
Joint Sealant

PRO-0005 Submit Joint Sealants 5 0 100 15APR12A 19MAY12A


PRO-0006 Approved Joint Sealants 14 0 100 20APR12A 03MAY12A
PRO-0007 Issue Purchase Order for SJS 5 0 100 05MAY12A 09MAY12A
PRO-0068 Material's Production for Project 15 0 100 09MAY12A 23MAY12A
PRO-0008 Delivery of SJS at Jobsite 5 0 100 23MAY12A 27MAY12A
Doors & Frames

PRO-0013 Submit Doors & Frames 5 0 100 02OCT11A 11OCT11A


PRO-0014 Approved Doors & Frames 14 0 100 12OCT11A 25OCT11A
PRO-0015 Issue Purchase Order for DR 2 0 100 29OCT11A 30OCT11A
PRO-0016 Manufacturing of Doors 10 0 100 12MAY12A 21MAY12A
PRO-0017 Delivery of Doors to Jobsite 5 0 100 22JUN12A 01JUL12A
Windows and Frames

PRO-0018 Submit Windows & Frames 5 0 100 18SEP11A 27SEP11A


PRO-0019 Approved Windows & Frames 14 0 100 12MAY12A 25MAY12A
PRO-0020 Issue Pruchase Order for WDW 2 0 100 25MAY12A 26MAY12A
PRO-0021 Manufacturing of Windows 10 0 100 10NOV12A 19NOV12A
PRO-0022 Delivery of Windows to Jobsite 5 0 100 20NOV12A 01JAN13A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 3 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Stucco & Paint

PRO-0023 Sumbit Stucco, Paint&Coating 5 0 100 20APR12A 24APR12A


PRO-0024 Approve Stucco, Paint&Coating 14 0 100 24APR12A 07MAY12A
PRO-0025 Purchase Order for Stucco & P 2 0 100 07MAY12A 08MAY12A
PRO-0066 Material's Manufacturing for Project 18 0 100 01OCT12A 07OCT12A
PRO-0026 Deliver Stucco & P at Jobsite 6 0 100 07OCT12A 14OCT12A

Electrical
Generator

PRO-0027 Submit Generator Product Data 10 0 100 31MAR12A 09APR12A


PRO-0028 Approve Generator Product Data 14 0 100 09APR12A 16APR12A
PRO-0029 Purchase Order for Generator 2 0 100 21APR12A 22APR12A
PRO-0030 Manufacturing the Generators 30 30 0 01APR13 30APR13 7
PRO-0031 Shipment of Generator 20 20 0 01MAY13 20MAY13 7
PRO-0032 Deliver of Generator at site 15 15 0 21MAY13 04JUN13 7
Lighting System

PRO-0033 Submit Lighting System 10 0 100 03SEP11A 13SEP11A


PRO-0034 Approve Lighting System 14 0 100 17SEP11A 30SEP11A
PRO-0035 Purchase Order for LTG SYS 2 0 100 01OCT11A 02OCT11A
PRO-0036 Shipment Lighting System 20 0 100 01DEC12A 01JAN13A
PRO-0037 Deliver of LTG SYS Material 8 0 100 01JAN13A 28FEB13A
Pannel Board and Transfer Switch

PRO-0038 Submit EP & TRANS Switch 1 0 100 29AUG11A 29AUG11A


PRO-0039 Approve EP & TRANS Switch 14 0 100 29AUG11A 03SEP11A
PRO-0040 Purchase Order for EP/TRANS SW 2 0 100 10SEP11A 11SEP11A
PRO-0041 Manufacture EP/TRANS Switch 60 60 0 01APR13 30MAY13 -31
PRO-0042 Shipment of EP & TRANS Switch 40 40 0 31MAY13 09JUL13 -31
PRO-0043 Delivere EP & TRANS SW at Site 10 10 0 10JUL13 19JUL13 -31
Electrical Distribution System

PRO-0044 Submit ELECT Distribution MAT 1 0 100 08SEP11A 08SEP11A


PRO-0045 Approve ELECT Distribution MAT 14 0 100 08SEP11A 13SEP11A
PRO-0046 PurchaseOrder forELEC Material 1 0 100 15SEP11A 15SEP11A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 4 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
PRO-0048 Shipment of ELECT Material 6 3 50 23APR12A 03APR13 41
PRO-0049 Deliver ELECT Material at site 3 1 50 28APR12A 01APR13 41
PRO-0047 Manufacturing of ELEC Material 5 0 100 25MAY12A 05JUN12A

Mechanical

PRO-0055 Submit Mechcanical Matrials 1 1 0 02APR13 02APR13 -7


PRO-0056 Approve Mechcanical Matrials 14 14 0 03APR13 16APR13 -7
PRO-0057 Purchase Order Mechcanical Matrials 2 2 0 17APR13 18APR13 -7
PRO-0058 Shipment of Mechcanical Matrials 45 45 0 19APR13 02JUN13 -7
PRO-0059 Deliver Mechcanical Matrials to the site 15 15 0 03JUN13 17JUN13 -7

Plumbing
Water and Sewer Pipes

PRO-0050 Submit Water & Sewer Pipes 30 0 100 17SEP11A 22SEP11A


PRO-0051 Approve Water & Sewer Pipes 14 0 100 23SEP11A 05OCT11A
PRO-0052 Purchase Order-W & Sewer Pipes 2 0 100 08OCT11A 09OCT11A
PRO-0053 Shipment of W & Sewer Pipes 35 0 100 16APR12A 21MAY12A
PRO-0054 Deliver W & Sewer Pipe at site 35 0 100 22APR12A 26MAY12A

Construction
Mobilization

MOB-0001 Grading/Leveling the Area 19 0 100 10SEP11A 29SEP11A


MOB-0002 Install. of Fence around Camp Area 20 0 100 30SEP11A 15OCT11A
MOB-0012 Installation of Conexes 10 0 100 16OCT11A 26OCT11A
MOB-0022 Construction of Buildings 20 0 100 27OCT11A 08DEC11A

Sitework
Site Demolition/Grading

SDG-0001 Grubbing of Site 10 0 100 01APR12A 05JUN12A


SDG-0002 Grading & Demolising 9 0 100 04APR12A 20OCT12A
SDG-0003 Removing Materials from site 12 0 100 10APR12A 23OCT12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 5 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Soccer Field Irrigation System

STO-0001 Layout for Irrigation Pipes 10 10 0 01APR13 11APR13 27


STO-0002 Excavation/leveling/Lay Pipes 20 20 0 13APR13 05MAY13 27
STO-0003 Backfilling/Compaction 20 20 0 06MAY13 28MAY13 27
STO-0004 Punchlist Correction 8 8 0 29MAY13 06JUN13 27
STO-0005 Finish & Handover 1 1 0 08JUN13 08JUN13 27
Road Network, Walkways, Parking
Roads

RPS-0007 Road Layout 2 0 100 01MAY12A 15MAY12A


RPS-0008 Road Sub-Grade 15 0 100 07MAY12A 23MAY12A
RPS-0009 Compact Sub-Grade of Road 15 0 100 12MAY12A 03JUN12A
RPS-0010 Road Base Course 14 0 100 17MAY12A 22MAY12A
RPS-0011 Compact Base-Course of Road 10 0 100 24MAY12A 15SEP12A
RPS-0012 Asphalt pavement 10 0 100 12SEP12A 23SEP12A
RPS-0024 Soil Ditch 10 0 100 18SEP12A 29SEP12A
RPS-0013 Test & Completion 2 2 0 01APR13 02APR13 35
Crush Around Building

RPS-0014 Layout/Level of Crush 1 1 0 13APR13 13APR13 57


RPS-0015 Sub Grade for Crush 10 10 0 14APR13 24APR13 57
RPS-0017 Compaction of Crush all arround Building 15 15 0 16APR13 02MAY13 57
RPS-0018 Test & Completion for Crush 1 1 0 04MAY13 04MAY13 57
Concrete walkways

RPS-0019 Layout for Sidewalks 2 2 0 03APR13 04APR13 35


RPS-0020 Sub Base for Sidewalks 15 15 0 06APR13 22APR13 35
RPS-0021 Base Course for Sidewalks 15 15 0 23APR13 09MAY13 35
RPS-0022 Pour Concrete for Sidewalks 15 15 0 11MAY13 27MAY13 35
RPS-0023 Test & Completion of Sidewalks 2 2 0 28MAY13 29MAY13 35
Athletic Field & Track
Field & Track

RPS-0025 Layout Athletic Field & Track 1 0 100 12MAY12A 12MAY12A


RPS-0026 Excavation Athletic Field & Track 10 0 100 15MAY12A 26MAY12A
RPS-0027 Backfiling/Compaction Athletic Field & Track 14 0 100 21MAY12A 18JUL12A
RPS-0028 Grass/Cursh for Athletic 10 10 0 01APR13 11APR13 75
RPS-0029 Test & Completion of Field & Track 1 1 0 13APR13 13APR13 75

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 6 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Volleyball Fields

1st Field
RPS-0030 Layout Volleyball Fields 1 0 100 12MAY12A 12MAY12A
RPS-0031 Excavation Volleyball Fields 10 0 100 20MAY12A 16JUL12A
RPS-0032 Backfiling / Compaction Volleyball Fields 10 0 100 03JUL12A 16JUL12A
RPS-0033 Sand for Volleyball Fields 10 0 100 22JUL12A 26AUG12A
RPS-0034 Test & Completion Volleyball Fields 1 1 0 01APR13 01APR13 85
2nd Field
RPS-0035 Layout Volleyball Fields 1 0 100 12MAY12A 12MAY12A
RPS-0036 Excavation Volleyball Fields 12 0 100 16MAY12A 24JUL12A
RPS-0037 Backfiling / Compaction Volleyball Fields 12 0 100 04JUN12A 26AUG12A
RPS-0038 Sand for Volleyball Fields 12 0 100 18NOV12A 01DEC12A
RPS-0039 Test & Completion Volleyball Fields 1 1 0 01APR13 01APR13 85
Force Protection
Personnel Bunker
BUNKER #1,2,3
FPR-0001 Layout for Bunker #1,2,3 1 0 100 18NOV12A 18NOV12A
FPR-0002 Casting for Bunker #1,2,3 8 0 100 19NOV12A 27NOV12A
FPR-0003 Construct Bunker #1,2,3 4 0 100 21NOV12A 09JAN13A
FPR-0004 Cmplt Sandbag & T. Barriers of B. #1,2,3 6 6 70 10DEC12A 07APR13 79
FPR-0005 Test & Completion of Bunker # 1,2,3 1 1 0 08APR13 08APR13 79
BUNKER #4,5,6
FPR-0006 Layout for Bunker #4,5,6 1 0 100 02DEC12A 02DEC12A
FPR-0007 Casting for Bunker #4,5,6 8 0 100 03DEC12A 17DEC12A
FPR-0008 Construct Bunker #4,5,6 4 0 100 18DEC12A 09JAN13A
FPR-0009 Cmplt Sandbag & T. Barriers of B. #4,5,6 6 6 70 10FEB13A 07APR13 78
FPR-0010 Test & Completion of Bunker #4,5,6 1 1 0 08APR13 08APR13 78
BUNKER #7,8,9
FPR-0012 Casting Bunker #7,8,9 8 0 100 18DEC12A 26DEC12A
FPR-0011 Layout for Bunker #7,8,9 1 0 96 18DEC12A 31MAR13 85
FPR-0013 Construct Bunker #7,8,9 4 0 100 20DEC12A 14JAN13A
FPR-0014 Cmplt Sandbag & T. Barriers of B. #7,8,9 6 6 25 10JAN13A 07APR13 79
FPR-0015 Test & Completion of Bunker #7,8,9 1 1 0 09APR13 09APR13 78
BUNKER #10,11,12,13
FPR-0016 Layout for Bunker #10,11,12,13 1 0 100 31DEC12A 31DEC12A
FPR-0017 Casting for Bunker #10,11,12,13 10 0 100 31DEC12A 03JAN13A
FPR-0018 Construct Bunker #10,11,12,13 4 0 100 06JAN13A 14JAN13A
FPR-0019 Cmplt Sandbag & T.Barriers of B.#10,11,12,13 6 6 25 18MAR13A 07APR13 78
FPR-0020 Test & Completion of Bunker#10,11,12,13 1 1 0 08APR13 08APR13 78
BUNKER #14,15,16,17
FPR-0021 Layout for Bunker #14,15,16,17 1 0 100 31DEC12A 31DEC12A
FPR-0022 Casting for Bunker #14,15,16,17 10 0 100 31DEC12A 06JAN13A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 7 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
FPR-0023 Construct Bunker #14,15,16,17 4 0 100 06JAN13A 14JAN13A
FPR-0024 Cmplt Sandbag & T.Barriers of B. #14,15,16,17 6 6 0 01APR13 07APR13 79
FPR-0025 Test & Completion of Bunker #14,15,16,17 1 1 0 09APR13 09APR13 78

FPR-0026 Layout for Bunker #18,19,20,21 1 0 100 10DEC12A 11DEC12A


FPR-0027 Casting for Bunker #18,19,20,21 10 0 100 12DEC12A 22DEC12A
FPR-0028 Construct Bunker #18,19,20,21 4 0 100 23DEC12A 14JAN13A
FPR-0029 Cmplt Sandbag & T.Barriers of B.#18,19,20,21 6 6 25 18MAR13A 07APR13 79
FPR-0030 Test & Completion of Bunker#18,19,20,21 1 1 0 08APR13 08APR13 79

FPR-0031 Layout for Bunker #22,23,24,25 1 0 100 10DEC12A 11DEC12A


FPR-0032 Casting for Bunker #22,23,24,25 10 0 100 12DEC12A 23DEC12A
FPR-0033 Construct Bunker #22,23,24,25 4 0 100 24DEC12A 14JAN13A
FPR-0034 Cmplt Sandbag & T.Barriers of B.#22,23,24,25 6 6 25 18MAR13A 07APR13 79
FPR-0035 Test & Completion of Bunker#22,23,24,25 1 1 0 08APR13 08APR13 79

FPR-0036 Area Layout for ECP 1 0 100 12MAY12A 12MAY12A


FPR-0044 ECP Construct Main Drop Gate 7 0 100 19MAY12A 25MAY12A
FPR-0037 ECP FDN Works 8 0 100 02JUN12A 09JUN12A
FPR-0038 Slab on Grade Work for ECP 12 0 100 12AUG12A 28AUG12A
FPR-0039 CMU Wall&Slab Work for ECP 14 0 100 15AUG12A 28AUG12A
FPR-0040 ECP Plaster & Insulation 15 0 100 10NOV12A 17MAR13A
FPR-0042 ECP Internal & External Paint 10 10 50 14JAN13A 10APR13 86
FPR-0041 ECP Install Doors & Windows 4 4 0 01APR13 04APR13 82
FPR-0043 ECP Install Barriers 12 12 0 05APR13 16APR13 82
FPR-0045 Test & Completion for ECP 2 2 0 17APR13 18APR13 82

FPR-0046 Area Layout for Wall 1 0 100 01APR12A 12MAY12A


FPR-0047 Excavation for Wall 8 0 100 03APR12A 12MAY12A
FPR-0048 Wall Backfilling/Compaction 7 0 95 12APR12A 31MAR13 69
FPR-0049 Wall PCC Works 5 0 100 14MAY12A 12SEP12A
FPR-0050 Wall Masonary Work 18 18 96 14MAY12A 18APR13 80
FPR-0051 Wall Copping 18 0 100 13SEP12A 31MAR13A
FPR-0052 Wall-Install Concertina Wire 15 15 75 10NOV12A 15APR13 80
FPR-0053 Wall-Test & Completion 5 5 0 16APR13 20APR13 80

FPR-0054 FPs Layout 1 0 100 12MAY12A 12MAY12A


FPR-0055 FPs Excavation 4 0 100 13MAY12A 13JAN13A
FPR-0057 FPs HESCO Installation 14 0 100 28MAY12A 09JAN13A
FPR-0056 FPs Backfilling & Compaction 5 0 100 11SEP12A 14JAN13A
FPR-0058 FPs Sand Bag 9 9 0 01APR13 09APR13 89
Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 8 of 38
Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
FPR-0059 FPs Test & Completion 2 2 0 10APR13 11APR13 89
Guard Tower

FPR-0060 GT - Layout 1 0 100 08APR12A 10MAY12A


FPR-0061 GT - Excavation 4 0 100 12MAY12A 15MAY12A
FPR-0063 GT - Foundation & Ring Beam Works 10 0 100 12MAY12A 22MAY12A
FPR-0062 GT - Watering, Backfilling & Compaction 5 0 100 14MAY12A 19MAY12A
FPR-0064 GT - Formwork & RFT for Slab on Grade 15 0 100 18JUN12A 05JUL12A
FPR-0065 GT - Concrete Works for Slab on Grade 7 0 100 23JUN12A 02JUL12A
FPR-0066 GT - Installation of CMU Wall&Slab 10 0 100 13SEP12A 20DEC12A
FPR-0067 GT - Plaster and Insulation 15 15 65 10FEB13A 17APR13 63
FPR-0068 GT - Electrical Works 8 8 80 18FEB13A 09APR13 63
FPR-0070 GT - Internal & External Painting 10 10 70 27FEB13A 11APR13 67
FPR-0069 GT - Bitumens&Corregated Sheets Inst. 6 6 0 10APR13 16APR13 63
FPR-0071 GT - Door&Windows Installation 4 4 0 17APR13 21APR13 63
FPR-0072 GT - Test & Commissioning 1 1 0 22APR13 22APR13 63
FPR-0073 GT - Punch list Correction 4 4 0 23APR13 27APR13 63
Trash Collection Point
Trash Collection Point #1,2,3,4,5

TCP-0001 TPT#1 - Construct 14 14 80 06MAY12A 16APR13 67


TCP-0002 TPT#1 - Install Fence 4 4 0 17APR13 21APR13 67
TCP-0003 TPT#1 - Inspection 1 1 0 22APR13 22APR13 67
Trash Collection Point #6,7,8,9

TCP-0004 TPT#2 - Construct 14 14 80 07MAY12A 16APR13 67


TCP-0005 TPT#2 - Install Fence 4 4 0 17APR13 21APR13 67
TCP-0006 TPT#2 - Inspection 1 1 0 22APR13 22APR13 67
Trash Collection Point #10,11,12

TCP-0007 TPT#3 - Construct 14 14 80 08MAY12A 16APR13 67


TCP-0008 TPT#3 - InstalI Fence 4 4 0 17APR13 21APR13 67
TCP-0009 TPT#3 - Inspection 1 1 0 22APR13 22APR13 67
Trash Collection Point #13,14,15

TCP-0010 TPT#4 - Construct 14 14 80 08MAY12A 16APR13 67


TCP-0011 TPT#4 - Install Fence 4 4 0 17APR13 21APR13 67
TCP-0012 TPT#4 - Inspection 1 1 0 22APR13 22APR13 67
Cover Walkway for Corps Headquarters
Foundations

CWW-0001 CW- Layout 1 0 100 12MAY12A 12MAY12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 9 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
CWW-0002 CW- Excavation 7 0 100 13MAY12A 03OCT12A
CWW-0003 CW- Watering, Backfilling & Compaction 4 4 25 20MAY12A 04APR13 36
CWW-0004 CW- Graveling 7 7 0 06APR13 13APR13 36
CWW-0005 CW- Foundation & Ring Beam 10 10 0 14APR13 24APR13 36
Superstructure & Close-in

CWW-0008 CW- Column Installation 10 10 0 25APR13 06MAY13 36


Architectural - Exterior

CWW-0009 CW- Corregated Sheet Inst. 8 8 0 07MAY13 15MAY13 36


Inspections, Punchlists

CWW-0010 CW- Test & Commission 2 2 0 16MAY13 18MAY13 36


CWW-0011 CW- Punchlist Correction 8 8 0 19MAY13 27MAY13 36
CWW-0012 CW- Finish and Handover 1 1 0 28MAY13 28MAY13 36
Bleacher Enclosures
Bleacher #1

OTH-0001 Bleacher #1- Layout 1 0 100 14MAY12A 14MAY12A


OTH-0002 Bleacher #1 - Construct FDN 15 0 100 15MAY12A 18JUL12A
OTH-0004 Bleacher #1- Construct COL 12 0 100 03JUN12A 18JUL12A
OTH-0005 Bleacher #1-Construct Stairs 12 0 100 07JUN12A 18JUL12A
OTH-0006 Bleacher #1- Install CORR Sheet 12 0 100 14AUG12A 30AUG12A
OTH-0003 Bleacher #1- Slab on Grade 18 2 90 18NOV12A 02APR13 76
OTH-0010 Bleacher #1 Test & Commission 2 2 0 03APR13 04APR13 76
OTH-0011 Bleacher #1 Punchlist Correction 5 5 0 06APR13 10APR13 76
OTH-0012 Bleacher #1 Finish and Handover 1 1 0 11APR13 11APR13 76
Bleacher #2

OTH-0013 Bleacher #2- Layout 1 0 100 14MAY12A 25JUN12A


OTH-0014 Bleacher #2 - Construct FDN 15 0 100 26JUN12A 17JUL12A
OTH-0015 Bleacher #2- Slab on Grade 18 18 0 01APR13 21APR13 48
OTH-0016 Bleacher #2- Construct COL 12 12 0 10APR13 23APR13 48
OTH-0017 Bleacher #2-Construct Stairs 12 12 0 17APR13 30APR13 48
OTH-0018 Bleacher #2- Install CORR Sheet 12 12 0 22APR13 05MAY13 48
OTH-0019 Bleacher #2 Test & Commission 2 2 0 06MAY13 07MAY13 48
OTH-0020 Bleacher #2 Punchlist Correction 5 5 0 08MAY13 13MAY13 48
OTH-0021 Bleacher #2 Finish and Handover 1 1 0 14MAY13 14MAY13 48

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 10 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Utilities
Water Supply and Distribution System
Water Distribution

WSD-0004 Layout for Water Pipes 1 0 100 07APR12A 10JAN13A


WSD-0005 Excavation for Water Pipes 8 8 96 25JUN12A 09APR13 66
WSD-0006 Lay Site Water Pipes 10 10 90 04JUL12A 11APR13 66
WSD-0008 Construction of Water Manholes 12 12 70 09JUL12A 14APR13 66
WSD-0009 Test & Completion for W Pipes 10 10 60 05OCT12A 11APR13 70
WSD-0007 Check W Pipes & Backfill 2 2 80 02DEC12A 16APR13 66
WSD-0010 Punchlist Correction - W Pipes 5 5 0 17APR13 22APR13 66
WSD-0011 Finish and Handover - W Pipes 1 1 0 23APR13 23APR13 66
Sanitary Sewer System
Sewage Collection

SSS-0001 Layout for Sewer Pipes 1 0 100 04APR12A 21JUN12A


SSS-0002 Excavation for Sewer Pipe 8 8 97 07APR12A 09APR13 62
SSS-0003 Install Sewer Pipes 10 10 96 13MAY12A 11APR13 62
SSS-0004 Checking & Backfill Sewer Pipe 10 10 96 18JUN12A 11APR13 62
SSS-0005 Construction of Sewer Manholes 18 18 83 27JUN12A 21APR13 62
SSS-0006 Test & Completion - Sewer Pipe 18 18 75 05OCT12A 21APR13 62
SSS-0007 Correct Punchlist - Sewer Pipe 5 5 0 22APR13 27APR13 62
SSS-0008 Finish & Handover - Sewer Pipe 1 1 0 28APR13 28APR13 62
Site Electrical Distribution Network
Power Distribution

ELE-0015 Layout for ELECT Pipes 2 0 100 07APR12A 16MAY12A


ELE-0016 Excavation for ELECT Pipes 6 6 96 09APR12A 07APR13 35
ELE-0018 Lay Electrical Pipes 10 10 80 06MAY12A 11APR13 35
ELE-0019 Concrete Work for Duct Bank 12 12 91 18JUN12A 14APR13 35
ELE-0024 Checking & Backfill Elect Pipes 10 10 93 20JUN12A 11APR13 42
ELE-0017 Electrical Manholes 20 20 90 23JUN12A 23APR13 42
ELE-0020 Electrical Cable Pulling 15 15 0 15APR13 01MAY13 35
ELE-0021 Test & Commission 4 4 0 02MAY13 06MAY13 47
ELE-0022 Puchlist Correction 5 5 0 07MAY13 12MAY13 49
ELE-0023 Finish and Handover 1 1 0 13MAY13 13MAY13 49
Power Generation
Emergency Generator for Headquarter
ELE-0009 Install Emergncy Generator 9 9 0 05JUN13 15JUN13 6
ELE-0010 Install Control Panel for Generator 12 12 0 10JUN13 23JUN13 6
ELE-0011 Test & Commission 2 2 0 24JUN13 25JUN13 6
ELE-0012 Puchlist Correction 5 5 0 26JUN13 01JUL13 6

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 11 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
ELE-0013 Finishing & Handover 1 1 0 02JUL13 02JUL13 6
Site Communication System

COM-0001 Layout for Communication SYS 1 0 100 13MAY12A 15MAY12A


COM-0002 Excavation for Conduits 7 5 90 16MAY12A 06APR13 62
COM-0005 Construct Communication Manholes 17 17 80 20JUN12A 20APR13 62
COM-0003 Install Counduits 9 5 80 11OCT12A 06APR13 74
COM-0004 Backfilling & Compaction 3 5 75 18OCT12A 06APR13 74
COM-0006 Testing & Completion - Com Sys 2 2 0 21APR13 22APR13 62
COM-0007 Punchlist Correction - Com Sys 4 4 0 23APR13 27APR13 62
COM-0008 Finish & Handover - Com Sys 1 1 0 28APR13 28APR13 62

Buildings
Arms Storage Buildings #100
Foundations

AB1-0001 100 S.ASB - Layout 1 0 100 01JAN12A 02JAN12A


AB1-0002 100 S.ASB - Excavation Work 6 0 100 03JAN12A 12JAN12A
AB1-0003 100 S.ASB - Concrete Work for Footings 9 0 100 05JUN12A 14JUN12A
AB1-0004 100 S.ASB - Under Ground Electrical Works 6 0 100 09JUN12A 17JUN12A
AB1-0005 100 S.ASB - Backfilling/Capillary Water Barrier 3 0 100 16JUN12A 14JUL12A
AB1-0006 100 S.ASB - Slab on Grade 6 0 100 13SEP12A 19SEP12A
Superstructure & Close-in

AB1-0008 100 S.ASB - Construction of Shear walls 10 0 100 15OCT12A 25OCT12A


AB1-0007 100 S.ASB - Construction of CMU Walls 10 0 100 10NOV12A 20NOV12A
AB1-0012 100 S.ASB - Steel Joists, Welding Plate& Purlins 6 6 0 01APR13 07APR13 52
Architectural - Exterior

AB1-0010 100 S.ASB - Exterior Door Installation 2 2 90 10FEB13A 02APR13 67


AB1-0014 100 S.ASB - Roof insullation 8 0 100 20MAR13A 28MAR13A
AB1-0015 100 S.ASB - External Paint 12 4 60 27MAR13A 04APR13 65
AB1-0013 100 S.ASB - Seam Metal Roof (Corr. Sheet) 6 6 0 14APR13 20APR13 52
Architectural - Interior

AB1-0016 100 S.ASB - Plastering 10 0 100 29NOV12A 30NOV12A


AB1-0017 100 S.ASB - Internal Painting 10 4 80 27FEB13A 04APR13 65
Electrical

AB1-0018 100 S.ASB - Conduits & Fittings 10 4 90 01DEC12A 04APR13 63


AB1-0019 100 S.ASB - Electrical Wiring Works 10 4 50 28MAR13A 04APR13 63
AB1-0020 100 S.ASB - Lighting Fix ,Cover Plates Inst. 1 1 0 06APR13 06APR13 63
Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 12 of 38
Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
AB1-0022 100 S.ASB - Panel Boards 5 5 0 20JUL13 24JUL13 -25
Mechanical

AB1-0024 100 S.ASB - Electric Heater Install 4 4 80 28MAR13A 04APR13 65


AB1-0021 100 S.ASB - Exhaust Fans install 1 1 0 07APR13 07APR13 63
Inspections, Punchlists

AB1-0023 100 S.ASB - Test & Commission 2 2 0 25JUL13 27JUL13 -25


AB1-0025 100 S.ASB - Punchlist Works 5 5 0 28JUL13 03AUG13 -25
AB1-0026 100 S.ASB - Finishing & Handover 1 1 0 04AUG13 04AUG13 -25
Arms Storage Buildings #101
Foundations

AB2-0001 101 S.ASB - Layout 1 0 100 04APR12A 07APR12A


AB2-0002 101 S.ASB - Excavation Work 4 0 100 05APR12A 09APR12A
AB2-0003 101 S.ASB - Concrete Work for Footings 9 0 100 21APR12A 02MAY12A
AB2-0004 101 S.ASB - Backfilling/Capillary Water Barrier 6 0 100 14MAY12A 20MAY12A
AB2-0006 101 S.ASB - Slab On Grade 6 0 100 23MAY12A 02JUL12A
AB2-0005 101 S.ASB - Under Ground Electrical Works 6 0 100 21JUN12A 16JUL12A
Superstructure & Close-in

AB2-0007 101 S.ASB - Construction of CMU Walls 10 0 100 03JUL12A 17JUL12A


AB2-0008 101 S.ASB - Construction of Shear walls 10 0 100 05JUL12A 17JUL12A
AB2-0009 101 S.ASB - Steel Joists, Welding Plate& Purlins 7 7 90 18MAR13A 08APR13 61
Architectural - Exterior

AB2-0012 101 S.ASB - External Paint 12 0 100 15OCT12A 23JAN13A


AB2-0010 101 S.ASB - Roof insulation 10 7 75 09MAR13A 08APR13 61
AB2-0011 101 S.ASB - Seam Metal Roof (Corr. Sheet) 7 7 85 28MAR13A 08APR13 61
AB2-0013 101 S.ASB - Ext Door Installation 8 8 0 01APR13 09APR13 61
Architectural - Interior

AB2-0014 101 S.ASB - Plastering 10 0 100 30SEP12A 09OCT12A


AB2-0015 101 S.ASB - Internal Painting 10 7 90 01NOV12A 08APR13 61
Electrical

AB2-0016 101 S.ASB - Conduits & Fittings 10 7 95 01DEC12A 08APR13 61


AB2-0017 101 S.ASB - Electrical Wiring Works 10 7 95 01JAN13A 08APR13 61
AB2-0018 101 S.ASB - Lighting Fix ,Cover Plates Inst 7 7 10 05FEB13A 08APR13 61
AB2-0019 101 S.ASB - Panel Boards 9 9 0 20JUL13 29JUL13 -25

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 13 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Mechanical

AB2-0021 101 S.ASB - Exhaust Fans inst 10 7 60 03JAN13A 08APR13 62


AB2-0020 101 S.ASB - Electric Heater Inst 1 1 0 09APR13 09APR13 61
Inspections, Punchlists

AB2-0022 101 S.ASB - Test & Commission 2 2 0 30JUL13 31JUL13 -25


AB2-0023 101 S.ASB - Punchlist Works 5 5 0 01AUG13 06AUG13 -25
AB2-0024 101 S.ASB - Finishing & Handover 1 1 0 07AUG13 07AUG13 -25
Arms Storage Buildings #102
Foundations

AB3-0001 102 S.ASB - Layout 2 0 100 01JAN12A 02JAN12A


AB3-0002 102 S.ASB - Excavation Work 6 0 100 03JAN12A 09JAN12A
AB3-0003 102 S.ASB - Concrete Work for Footings 9 0 100 12MAY12A 21MAY12A
AB3-0004 102 S.ASB - Backfilling/Capillary Water Barrier 6 0 100 04JUN12A 21JUN12A
AB3-0005 102 S.ASB - Under Ground Electrical Works 6 0 100 07JUN12A 21JUN12A
AB3-0006 102 S.ASB - Slab on Grade 6 0 100 09JUN12A 23JUN12A
Superstructure & Close-in

AB3-0007 102 S.ASB - Construction of CMU Walls 10 0 100 24JUN12A 04JUL12A


AB3-0008 102 S.ASB - Construction of Shear walls 10 0 100 05JUL12A 16JUL12A
AB3-0009 102 S.ASB - Steel Joists, Welding Plate& Purlins 7 7 0 01APR13 08APR13 57
Architectural - Exterior

AB3-0012 102 S.ASB - External Paint 18 0 100 01JAN13A 30JAN13A


AB3-0013 102 S.ASB - Ext Door Instalation 10 10 90 20FEB13A 16APR13 57
AB3-0010 102 S.ASB - Roof Insulation 12 0 100 27MAR13A 29MAR13A
AB3-0011 102 S.ASB - Seam Metal Roof (Corr. Sheet) 8 8 0 09APR13 17APR13 57
Architectural - Interior

AB3-0014 102 S.ASB - Plastering 10 0 100 28OCT12A 20NOV12A


AB3-0015 102 S.ASB - Internal Painting 10 10 90 10DEC12A 11APR13 57
Electrical

AB3-0016 102 S.ASB - Conduits & Fittings 4 4 90 10NOV12A 04APR13 67


AB3-0017 102 S.ASB - Electrical Wiring Works 8 4 90 20FEB13A 04APR13 67
AB3-0018 102 S.ASB - Lighting Fix ,Cover Plates Inst 1 1 0 04APR13 04APR13 67
AB3-0019 102 S.ASB - Panel Boards 2 2 0 19JUN13 20JUN13 4
Mechanical

AB3-0021 102 S.ASB - Exhaust Fans Inst 1 1 0 17APR13 17APR13 57

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 14 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
AB3-0020 102 S.ASB - Electric Heater Inst 1 1 0 18JUN13 18JUN13 4
Inspections, Punchlists

AB3-0022 102 S.ASB - Test & Commission 2 2 0 22JUN13 23JUN13 4


AB3-0023 102 S.ASB - Punchlist Works 5 5 0 24JUN13 29JUN13 4
AB3-0024 102 S.ASB - Finishing & Handover 1 1 0 30JUN13 30JUN13 4
Arms Storage Buildings #103
Foundations

AB4-0001 103 S.ASB - Layout 1 0 100 02JAN12A 02JAN12A


AB4-0002 103 S.ASB - Excavation Work 6 0 100 03JAN12A 09JAN12A
AB4-0003 103 S.ASB - Concrete Work for Footings 4 0 100 14JAN12A 20MAY12A
AB4-0004 103 S.ASB - Backfilling/Capillary Water Barrier 6 0 100 03JUN12A 23JUN12A
AB4-0005 103 S.ASB - Under Ground Electrical Works 6 0 100 06JUN12A 23JUN12A
AB4-0006 103 S.ASB - Slab on Grade 6 0 100 12JUN12A 23JUN12A
Superstructure & Close-in

AB4-0007 103 S.ASB - Construction of CMU Walls 15 0 100 24JUN12A 10JUL12A


AB4-0008 103 S.ASB - Construction of Shear walls 18 0 100 11JUL12A 30JUL12A
AB4-0009 103 S.ASB - Steel Joists, Welding Plate& Purlins 10 10 0 01APR13 11APR13 50
Architectural - Exterior

AB4-0012 103 S.ASB - External Paint 10 2 95 18NOV12A 02APR13 60


AB4-0013 103 S.ASB - Ext Door Installation 5 5 90 21FEB13A 06APR13 57
AB4-0010 103 S.ASB - Roof insullation 10 10 90 27MAR13A 11APR13 49
AB4-0011 103 S.ASB - Seam Metal Roof (Corr. Sheet) 5 5 0 13APR13 17APR13 50
Architectural - Interior

AB4-0014 103 S.ASB - Plastering 10 0 100 18SEP12A 28SEP12A


AB4-0015 103 S.ASB - Internal Painting 10 5 90 04DEC12A 06APR13 57
Electrical

AB4-0017 103 S.ASB - Electrical Wiring Works 12 12 95 03JAN13A 14APR13 47


AB4-0016 103 S.ASB - Conduits & Fittings 10 10 90 10JAN13A 11APR13 49
AB4-0018 103 S.ASB - Lighting Fix ,Cover Plates Inst 2 2 0 15APR13 16APR13 47
AB4-0019 103 S.ASB - Panel Boards 9 9 0 23JUN13 02JUL13 -6
Mechanical

AB4-0021 103 S.ASB - Exhaust Fans Inst 1 1 0 17APR13 17APR13 47


AB4-0020 103 S.ASB - Electric Heater Inst 1 1 0 18JUN13 18JUN13 -6

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 15 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Inspections, Punchlists

AB4-0022 103 S.ASB - Test & Commission 2 2 0 03JUL13 04JUL13 -6


AB4-0023 103 S.ASB - Punchlist Works 5 5 0 06JUL13 10JUL13 -6
AB4-0024 103 S.ASB - Finishing & Handover 1 1 0 11JUL13 11JUL13 -6
Arms Storage Buildings #104
Foundations

AB5-0001 104 S.ASB - Layout 1 0 100 01APR12A 01APR12A


AB5-0002 104 S.ASB - Excavation Work 5 0 100 02APR12A 07APR12A
AB5-0003 104 S.ASB - Concrete Work for Footings 12 0 100 14APR12A 20MAY12A
AB5-0004 104 S.ASB - Backfilling/Capillary Water Barrier 6 0 100 03JUN12A 27JUN12A
AB5-0006 104 S.ASB - Slab on Grade 10 0 100 05JUN12A 30JUN12A
AB5-0005 104 S.ASB - Under Ground Electrical Works 6 0 100 06JUN12A 26JUN12A
Superstructure & Close-in

AB5-0008 104 S.ASB - Construction of Shear walls 10 0 100 01JUL12A 12JUL12A


AB5-0007 104 S.ASB - Construction of CMU Walls 10 0 100 14AUG12A 27AUG12A
AB5-0009 104 S.ASB - Steel Joists, Welding Plate& Purlins 8 8 0 01APR13 09APR13 54
Architectural - Exterior

AB5-0012 104 S.ASB - External Paint 13 10 70 03FEB13A 11APR13 57


AB5-0013 104 S.ASB - Ext Door Installation 6 6 90 20FEB13A 07APR13 62
AB5-0010 104 S.ASB - Roof Insulation 12 10 90 27MAR13A 11APR13 57
AB5-0011 104 S.ASB - Seam Metal Roof (Corr. Sheet) 6 6 0 10APR13 16APR13 54
Architectural - Interior

AB5-0014 104 S.ASB - Plastering 15 0 100 26NOV12A 05DEC12A


AB5-0015 104 S.ASB - Internal Painting 15 6 90 10DEC12A 07APR13 62
Electrical

AB5-0016 104 S.ASB - Conduits & Fittings 10 0 100 10DEC12A 20FEB13A


AB5-0017 104 S.ASB - Electrical Wiring Works 10 10 95 21FEB13A 11APR13 57
AB5-0018 104 S.ASB - Lighting Fix ,Cover Plates Inst 10 10 95 22FEB13A 11APR13 57
AB5-0019 104 S.ASB - Panel Boards 6 6 0 19JUN13 25JUN13 0
Mechanical

AB5-0020 104 S.ASB - Electric Heater Inst 1 1 0 13APR13 13APR13 57


AB5-0021 104 S.ASB - Exhaust Fans inst 1 1 0 18JUN13 18JUN13 0
Inspections, Punchlists

AB5-0022 104 S.ASB - Test & Commission 2 2 0 26JUN13 27JUN13 0

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 16 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
AB5-0023 104 S.ASB - Punchlist Works 5 5 0 29JUN13 03JUL13 0
AB5-0024 104 S.ASB - Finishing & Handover 1 1 0 04JUL13 04JUL13 0
Corps Headquarters (North)
Foundations

GFC-0001 Nrth Prt GFCC Building Layout 1 0 100 07APR12A 07APR12A


GFC-0002 Nrth Prt GFCC Excavation 8 0 100 10MAY12A 10JUN12A
GFC-0003 Nrth Prt GFCC Watering, Backfilling & Compaction 5 0 100 15MAY12A 10JUN12A
GFC-0004 Nrth Prt GFCC Foundation & Ring Beam Works 15 0 100 11JUN12A 27JUN12A
GFC-0005 Nrth Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars 5 0 100 14JUN12A 27JUN12A
GFC-0006 Nrth Prt GFCC Formwork & RFT for Slab on Grade 14 0 100 18JUN12A 12JUL12A
GFC-0007 Nrth Prt San Sewer Piping under Slab on Grade 8 0 100 21JUN12A 12JUL12A
GFC-0008 Nrth Prt Concrete Works for Slab on Grade 6 0 100 25JUN12A 12JUL12A
Superstructure & Close-in

GFC-0009 Nrth Prt Installation of Shear Walls 12 0 100 14JUL12A 15AUG12A


GFC-0010 Nrth Prt Installation of 3D Panels Walls 15 0 100 18JUL12A 15AUG12A
GFC-0011 Nrth Prt Scaffolding for 3D Roof Slab 3 0 100 21JUL12A 20AUG12A
GFC-0012 Nrth Prt Instalaltion of 3D Panels Roof Slabs 12 0 100 23JUL12A 16AUG12A
GFC-0013 Nrth Prt Shotcreting for 3D Panels Roof & Walls 10 0 100 28JUL12A 12SEP12A
GFC-0014 Nrth Prt Pouring Concrete on Roof 8 0 100 04AUG12A 12SEP12A
Architectural - Exterior

GFC-0015 Nrth Prt Exterior Doors Installation 10 10 60 04AUG12A 11APR13 63


GFC-0018 Nrth Prt Cold Asphalt Damp Proofing 12 0 100 22OCT12A 20FEB13A
GFC-0016 Nrth Prt External Painting 12 8 90 01NOV12A 09APR13 70
GFC-0019 Nrth Prt Corregated Sheet Installation 10 10 85 24DEC12A 11APR13 63
GFC-0017 Nrth Prt Window Installation 8 0 100 01JAN13A 21JAN13A
Architectural - Interior

GFC-0024 Nrth Prt Interior Doors Installation 10 10 80 04AUG12A 11APR13 43


GFC-0021 Nrth Prt Plaster Works 18 0 100 01OCT12A 03JAN13A
GFC-0020 Nrth Prt Internal Painting 18 10 90 01DEC12A 11APR13 44
GFC-0022 Nrth Prt Sealed Concrete 10 10 20 25MAR13A 11APR13 68
GFC-0023 Nrth Prt Terrazzo Tiles 15 15 0 13APR13 29APR13 43
Electrical

GFC-0025 Nrth Prt Ele PVC Conduits & Fittings & Boxes 5 5 80 01DEC12A 06APR13 66
GFC-0026 Nrth Prt Electrical Wiring Works 5 5 80 01JAN13A 06APR13 66
GFC-0028 Nrth Prt Duplex and switch installation 18 10 70 03JAN13A 11APR13 58
GFC-0027 Nrth Prt Lighting Fix. & Cover Plates Insta 2 2 0 13APR13 14APR13 61
GFC-0041 Nrth Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -21

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 17 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Mechanical

GFC-0029 Nrth Prt Exhaust Fan Installation 10 10 40 27MAR13A 29JUN13 1


GFC-0030 Nrth Prt Unit Heater Installation 10 10 10 28MAR13A 29JUN13 1
GFC-0031 Nrth Prt AC Split Installation 10 10 0 30APR13 11MAY13 43
Plumbing

GFC-0032 Nrth Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 44
GFC-0034 Nrth Prt Toilet & Misc.Accessories 4 4 0 18APR13 22APR13 44
GFC-0033 Nrth Prt Toilet Sanitry Fixture Installation 15 15 0 23APR13 09MAY13 44
Fire Protection System

GFC-0035 Nrth Prt Smoke Detector Installation 1 1 10 29MAR13A 02APR13 83


GFC-0036 Nrth Prt Fire Extinguisher Installation 1 1 0 18JUN13 18JUN13 10
Communications

GFC-0037 Nrth Prt Telephone and Data wall recepticle Inst 15 15 35 02JAN13A 17APR13 63
Inspections, Punchlists

GFC-0038 Nrth Prt Test & Commission 2 2 0 25JUL13 27JUL13 -21


GFC-0039 Nrth Prt Punchlist Works 5 5 0 28JUL13 01AUG13 -21
GFC-0040 Nrth Prt Finishing & Handover 1 1 0 03AUG13 03AUG13 -21
Corps Headquarters (West)
Foundations

GFC-0042 West Prt GFCC Building Layout 1 0 100 07APR12A 07APR12A


GFC-0043 West Prt GFCC Excavation 4 0 100 14MAY12A 17MAY12A
GFC-0044 West Prt GFCC Watering, Backfilling & Compaction 5 0 100 20MAY12A 16JUN12A
GFC-0047 West Prt GFCC Formwork & RFT for Slab on Grade 14 0 100 18JUN12A 12JUL12A
GFC-0048 West Prt San Sewer Piping under Slab on Grade 5 0 100 21JUN12A 14AUG12A
GFC-0045 West Prt GFCC Foundation & Ring Beam Works 15 0 100 21JUN12A 12SEP12A
GFC-0046 West Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars 5 0 100 25JUN12A 12JUL12A
GFC-0049 West Prt Concrete Works for Slab on Grade 6 0 100 14JUL12A 15NOV12A
Superstructure & Close-in

GFC-0050 West Prt Installation of Shear Walls 8 0 100 17JUL12A 22SEP12A


GFC-0051 West Prt Installation of 3D Panels Walls 15 0 100 04AUG12A 12DEC12A
GFC-0052 West Prt Scaffolding for 3D Roof Slab 3 0 100 25SEP12A 12DEC12A
GFC-0053 West Prt Instalaltion of 3D Panels Roof Slabs 10 0 100 28SEP12A 12DEC12A
GFC-0054 West Prt Shotcreting for 3D Panels Roof & Walls 10 3 85 03OCT12A 03APR13 50
GFC-0055 West Prt Pouring Concrete on Roof 10 0 100 06OCT12A 13JAN13A
GFC-0073 West Prt Truss Installation 12 12 75 13DEC12A 14APR13 53

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 18 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Architectural - Exterior

GFC-0058 West Prt Exterior Doors Installation 10 10 40 01DEC12A 11APR13 68


GFC-0056 West Prt Cold Asphalt Damp Proofing 15 0 100 13DEC12A 27JAN13A
GFC-0057 West Prt Corregated Sheet Installation for 3D 12 10 67 13FEB13A 11APR13 68
GFC-0059 West Prt Window Installation 10 10 50 14FEB13A 11APR13 68
GFC-0060 West Prt External Painting 15 10 30 27FEB13A 11APR13 68
GFC-0085 West Prt Corregated Sheet Installation for Truss 12 12 50 27MAR13A 14APR13 53
Architectural - Interior

GFC-0062 West Prt Plaster Works 15 10 80 21NOV12A 11APR13 55


GFC-0063 West Prt Interior Doors Installation 10 10 36 28JAN13A 11APR13 60
GFC-0064 West Prt Internal Painting 15 10 55 01FEB13A 11APR13 60
GFC-0084 West Prt Glass Wool Insulation 12 12 70 28MAR13A 14APR13 53
GFC-0061 West Prt Terrazzo Tiles 15 15 0 04APR13 21APR13 50
GFC-0086 West Prt False Ceiling 15 15 0 01APR13 17APR13 53
GFC-0065 West Prt Sealed Concrete 7 7 0 20JUL13 27JUL13 -23
Electrical

GFC-0066 West Prt Elec PVC Conduits & Fittings & Boxes 5 0 100 01JAN13A 23MAR13A
GFC-0068 West Prt Duplex and switch installation 10 10 45 03JAN13A 11APR13 68
GFC-0067 West Prt Electrical Wiring Works 5 5 50 10JAN13A 06APR13 65
GFC-0069 West Prt Lighting Fix. & Cover Plates Inst 2 2 0 22APR13 23APR13 50
GFC-0070 West Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -23
Mechanical

GFC-0071 West Prt AC Split Installation 1 1 0 18JUN13 18JUN13 10


GFC-0072 West Prt Exhaust Fan Installation 1 1 0 18JUN13 18JUN13 10
Plumbing

GFC-0074 West Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 55
GFC-0075 West Prt Kitchen & Misc.Accessories 5 5 0 18APR13 23APR13 57
GFC-0076 West Prt Kithen Fixture Installation 8 8 0 18APR13 27APR13 55
Fire Protection System

GFC-0077 West Prt Smoke Detector Installation 1 1 0 23APR13 23APR13 58


GFC-0078 West Prt Fire Extinguisher Installation 1 1 0 18JUN13 18JUN13 10
Communications

GFC-0079 West Prt Tele and Data wall receptacle Insta 15 15 40 02JAN13A 17APR13 63

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 19 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Inspections, Punchlists

GFC-0080 West Prt Test & Commission 2 2 0 28JUL13 29JUL13 -23


GFC-0081 West Prt Punchlist Works 5 5 0 30JUL13 04AUG13 -23
GFC-0082 West Prt Finishing & Handover 1 1 0 05AUG13 05AUG13 -23
Corps Headquarters (South)
Foundations

GFC-0087 Sout Prt GFCC Building Layout 1 0 100 07APR12A 07APR12A


GFC-0088 Sout Prt GFCC Excavation 5 0 100 12MAY12A 16MAY12A
GFC-0089 Sout Prt GFCC Watering, Backfilling & Compaction 5 0 100 16MAY12A 16JUN12A
GFC-0092 Sout Prt GFCC Formwork & RFT for Slab on Grade 14 0 100 20JUN12A 10JUL12A
GFC-0091 Sout Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars 5 0 100 26JUN12A 18NOV12A
GFC-0093 Sout Prt San Sewer Piping under Slab on Grade 8 0 100 01JUL12A 11JUL12A
GFC-0090 Sout Prt GFCC Foundation & Ring Beam Works 15 0 100 14JUL12A 12SEP12A
GFC-0094 Sout Prt Concrete Works for Slab on Grade 6 0 100 16JUL12A 09JAN13A
Superstructure & Close-in

GFC-0095 Sout Prt Installation of Shear Walls 8 0 100 13AUG12A 22SEP12A


GFC-0096 Sout Prt Installation of 3D Panels Walls 15 0 100 13SEP12A 23JAN13A
GFC-0097 Sout Prt Scaffolding for 3D Roof Slab 3 0 100 25SEP12A 12DEC12A
GFC-0098 Sout Prt Instalaltion of 3D Panels Roof Slabs 12 0 100 28SEP12A 23DEC12A
GFC-0099 Sout Prt Shotcreting for 3D Panels Roof & Walls 15 12 87 13OCT12A 14APR13 49
GFC-0100 Sout Prt Pouring Concrete on roof 12 0 100 20OCT12A 23JAN13A
GFC-0101 Sout Prt Truss Installation 10 10 50 25MAR13A 11APR13 51
Architectural - Exterior

GFC-0105 Sout Prt Exterior Doors Installation 12 10 10 01DEC12A 11APR13 68


GFC-0102 Sout Prt Cold Asphalt Damp Proofing 10 10 60 24FEB13A 11APR13 57
GFC-0103 Sout Prt Corregated Sheet Installation for 3D 10 10 40 25FEB13A 11APR13 61
GFC-0107 Sout PrtExternal Painting 10 10 45 26FEB13A 11APR13 68
GFC-0104 Sout Prt Corregated Sheet Installation for Truss 10 10 10 27MAR13A 23APR13 51
GFC-0106 Sout PrtWindow Installation 12 12 0 01APR13 14APR13 61
Architectural - Interior

GFC-0111 Sout Prt Interior Doors Installation 10 10 30 01DEC12A 11APR13 53


GFC-0109 Sout Prt Plaster Works 15 15 85 03DEC12A 17APR13 53
GFC-0113 Sout Prt Internal Painting 10 10 60 27FEB13A 11APR13 61
GFC-0110 Sout Prt Glass Wool Insulation 10 10 40 27MAR13A 23APR13 51
GFC-0108 Sout Prt Terrazzo Tiles 12 12 0 15APR13 28APR13 49
GFC-0112 Sout Prt False Ceiling 2 2 0 24APR13 25APR13 51
GFC-0114 Sout Prt Sealed Concrete 5 5 0 23JUL13 28JUL13 -24

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 20 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Electrical

GFC-0115 Sout Prt Ele PVC Conduits & Fittings & Boxes 5 5 90 01FEB13A 07APR13 65
GFC-0116 Sout Prt Electrical Wiring Works 5 5 40 21FEB13A 07APR13 65
GFC-0118 Sout Prt Duplex and switch installation 10 10 20 28FEB13A 11APR13 77
GFC-0117 Sout Prt Lighting Fix. & Cover Plates Inst 2 2 0 13APR13 14APR13 61
GFC-0119 Sout Prt Panel Board Installation 5 5 0 20JUL13 24JUL13 -21
Mechanical

GFC-0120 Sout Prt AC Split Installation 1 1 0 01APR13 01APR13 77


GFC-0121 Sout Prt Exhaust Fan Installation 1 1 0 18JUN13 18JUN13 10
GFC-0131 Sout Prt Unit Heater Installation 1 1 0 18JUN13 18JUN13 10
Plumbing

GFC-0122 Sout Prt Hot & Cold Water Piping 15 15 25 01DEC12A 17APR13 53
GFC-0124 Sout Prt Toilet Sanitry Fixture Installation 3 3 0 18APR13 21APR13 55
GFC-0123 Sout Prt Toilet & Misc.Accessories 5 5 0 18APR13 23APR13 53
Fire Protection System

GFC-0125 Sout Prt Smoke Detector Installation 2 2 0 18JUN13 19JUN13 6


GFC-0126 Sout Prt Fire Extinguisher Installation 2 2 0 20JUN13 22JUN13 7
Communications

GFC-0127 Sout Prt Telephone and Data wall recepticle Inst 3 3 38 01MAR13A 23JUN13 6
Inspections, Punchlists

GFC-0128 Sout Prt Test & Commission 2 2 0 29JUL13 30JUL13 -24


GFC-0129 Sout Prt Punchlist Works 5 5 0 31JUL13 05AUG13 -24
GFC-0130 Sout PrtFinishing & Handover 1 1 0 06AUG13 06AUG13 -24
Kandak Headquarters
Foundations

KAN-0001 KHQ - Layout 1 0 100 08APR12A 16JUN12A


KAN-0002 KHQ - Excavation Work 4 0 100 09APR12A 20JUN12A
KAN-0003 KHQ - Watering, Backfilling & Compaction 5 0 100 17JUN12A 21JUN12A
KAN-0004 KHQ - Foundation & Ring Beam Works 7 0 100 23JUN12A 11JUL12A
KAN-0005 KHQ - BKFLNG, CMPCTN, CAP. & Vap. Barriers 7 0 100 10JUL12A 12AUG12A
KAN-0006 KHQ - Formwork & RFT for Slab on Grade 8 0 100 16JUL12A 12AUG12A
KAN-0007 KHQ - Concrete Works for Slab on Grade 2 0 100 11NOV12A 09JAN13A
Superstructure & Close-in

KAN-0008 KHQ - Inst of Steel Bar for Stem Wall 10 0 100 25JUL12A 12AUG12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 21 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
KAN-0009 KHQ - Concrete for Stem Walls 12 0 100 10SEP12A 09JAN13A
KAN-0010 KHQ - Installation of K Span 15 0 100 28OCT12A 26FEB13A
Architectural - Exterior

KAN-0013 KHQ - Windows Installation 8 8 50 05DEC12A 09APR13 45


KAN-0011 KHQ - Ext Door Instalation 8 8 40 05JAN13A 09APR13 45
KAN-0012 KHQ - Ext Painting of Stem Wall 7 7 75 01MAR13A 08APR13 46
Architectural - Interior

KAN-0014 KHQ - Plaster for Stem Wall 15 15 90 10NOV12A 17APR13 21


KAN-0015 KHQ - Spray Insulation 7 7 0 18APR13 25APR13 21
KAN-0017 KHQ - Inst. gypsum board 10 10 0 27APR13 07MAY13 21
KAN-0016 KHQ - Inst. Suspended Ceiling 15 15 0 27APR13 13MAY13 26
KAN-0018 KHQ - Interior Doors Inst 5 5 0 08MAY13 13MAY13 21
KAN-0019 KHQ - Sealed Concrete for floor 5 5 0 21MAY13 26MAY13 26
Electrical

KAN-0020 KHQ - Ele PVC Conduits/Fittings/Boxes 6 0 100 01MAR13A 08MAR13A


KAN-0021 KHQ - Electrical Wiring Works 7 7 0 01APR13 08APR13 56
KAN-0022 KHQ - Lighting Fix.&Cover Plates Inst 6 6 0 14MAY13 20MAY13 26
KAN-0023 KHQ - Duplex & Switch Inst 8 8 0 14MAY13 22MAY13 21
KAN-0024 KHQ - Panel Board Inst 3 3 0 20JUL13 22JUL13 -23
Mechanical

KAN-0026 KHQ - Exhaust Fan Inst. 2 2 0 18JUN13 19JUN13 2


KAN-0025 KHQ - AC Split Installation 3 3 0 18JUN13 20JUN13 -1
KAN-0027 KHQ - Unit Heater Inst. 2 2 0 22JUN13 23JUN13 -1
Plumbing

KAN-0028 KHQ - Hot&Cold Water Piping 9 9 50 05DEC12A 11APR13 51


KAN-0029 KHQ - Toilet & Misc. Accessories 5 5 0 13APR13 17APR13 54
KAN-0030 KHQ - Toilet Sanitry Fixture Inst. 8 8 0 13APR13 21APR13 51
Fire Protection System

KAN-0031 KHQ - Fire Extinguisher Inst. 3 3 0 20JUN13 23JUN13 2


Inspections, Punchlists

KAN-0032 KHQ - Test & Commission 2 2 0 23JUL13 24JUL13 -23


KAN-0033 KHQ - Punchlist Works 5 5 0 25JUL13 30JUL13 -23
KAN-0034 KHQ - Finishing & Handover 1 1 0 31JUL13 31JUL13 -23

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 22 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Administration Building #109


Foundations

ADM-0001 ADB 109 - Layout 2 0 100 09APR12A 10APR12A


ADM-0002 ADB 109 - Excavation Work 4 0 100 12APR12A 16APR12A
ADM-0003 ADB 109 - Watering, Backfilling & Compaction 4 0 100 16APR12A 22APR12A
ADM-0004 ADB 109 - Foundation & Ring Beam 10 0 100 10MAY12A 18NOV12A
ADM-0005 ADB 109 - BKFLNG, CMPCTN, CAP. & Vap. Barriers 8 0 100 16JUN12A 24JUN12A
ADM-0006 ADB 109 - Formwork & RFT for Slab on Grade 10 0 100 19JUN12A 30JUN12A
ADM-0007 ADB 109 - Concrete Works for Slab on Grade 4 0 100 26JUN12A 30JUN12A
Superstructure & Close-in

ADM-0008 ADB 109 - Inst. of Steel Bar for Stem Walls 4 0 100 01JUL12A 04JUL12A
ADM-0009 ADB 109 - Concrete for Stem Walls 7 0 100 02JUL12A 20SEP12A
ADM-0010 ADB 109 - Installation of K Span 13 0 100 01OCT12A 09OCT12A
Architectural - Exterior

ADM-0013 ADB 109 - Windows Inst 6 0 100 29NOV12A 16JAN13A


ADM-0012 ADB 109 - Ext. Painting of Stem Walls 13 13 15 18MAR13A 15APR13 39
ADM-0011 ADB 109 - Ext. Door Inst 5 5 0 09APR13 14APR13 57
Architectural - Interior

ADM-0014 ADB 109 - Plaster Work for steam Walls 8 0 100 10OCT12A 18OCT12A
ADM-0015 ADB 109 - Spray Insulation 7 7 70 10DEC12A 08APR13 37
ADM-0017 ADB 109 - Inst. of gypsum Board 8 8 10 18DEC12A 09APR13 37
ADM-0019 ADB 109 - Sealed Concrete for Floor 4 4 20 23MAR13A 04APR13 68
ADM-0018 ADB 109 - Interior Doors Instalation 5 5 0 10APR13 15APR13 39
ADM-0016 ADB 109 - Inst. of Suspended Ceiling 8 8 0 10APR13 18APR13 39
Electrical

ADM-0020 ADB 109 - Ele PVC Conduits/Fittings/Boxes 9 7 75 18FEB13A 08APR13 38


ADM-0023 ADB 109 - Duplex & Switch Inst 7 7 0 10APR13 17APR13 37
ADM-0021 ADB 109 - Electrical Wiring Works 6 6 0 18APR13 24APR13 37
ADM-0022 ADB 109 - Lighting Fix. & Cover Plates Inst. 7 7 0 22APR13 29APR13 37
ADM-0024 ADB 109 - Panel Board Inst. 3 3 0 20JUL13 22JUL13 -25
Mechanical

ADM-0026 ADB 109 - Exhaust Fan Installation 3 3 30 28MAR13A 20JUN13 -1


ADM-0025 ADB 109 - AC Split Installation 5 5 0 30APR13 05MAY13 37
ADM-0027 ADB 109 - Unit Heater Installation 2 2 0 06MAY13 07MAY13 37

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 23 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Plumbing

ADM-0028 ADB 109 - Hot & Cold Water Piping 7 7 50 01DEC12A 08APR13 54
ADM-0029 ADB 109 - Toilet & Misc. Accessories 5 5 0 09APR13 14APR13 54
ADM-0030 ADB 109 - Toilet Sanitry Fixture Inst 6 6 0 09APR13 15APR13 54
Fire Protection System

ADM-0031 ADB 109 - Fire Extinguisher Inst. 3 3 0 08MAY13 11MAY13 37


Inspections, Punchlists

ADM-0032 ADB 109 - Test & Commission 2 2 0 23JUL13 24JUL13 -25


ADM-0033 ADB 109 - Punchlist Works 7 7 0 25JUL13 01AUG13 -25
ADM-0034 ADB 109 - Finishing & Handover 1 1 0 03AUG13 03AUG13 -25
Large Latrine #110
Foundations

LA1-0001 LTB 110- Layout 2 0 100 04APR12A 05APR12A


LA1-0002 LTB 110- Excavation Work 5 0 100 07APR12A 11APR12A
LA1-0003 LTB 110- Watering, Backfilling & Compaction 5 0 100 14APR12A 19APR12A
LA1-0004 LTB 110- Foundation & Ring Beam 12 0 100 21APR12A 11JUN12A
LA1-0005 LTB 110- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 12JUN12A 11JUL12A
LA1-0006 LTB 110- Formwork & RFT for Slab on Grade 12 0 100 14JUN12A 11JUL12A
LA1-0007 LTB 110- Concrete Works for Slab on Grade 4 0 100 25JUN12A 16SEP12A
Superstructure & Close-in

LA1-0008 LTB 110- Inst. Steel Bar for Stem Walls 13 0 100 17JUN12A 02JUL12A
LA1-0009 LTB 110- Concrete for Stem Walls 15 0 100 19JUN12A 27OCT12A
LA1-0010 LTB 110- Installation of K Span 20 0 100 01OCT12A 09OCT12A
Architectural - Exterior

LA1-0011 LTB 110- Exterior Door Installaion 6 6 45 18DEC12A 07APR13 56


LA1-0013 LTB 110- Windows Installation 7 0 100 20DEC12A 26JAN13A
LA1-0012 LTB 110- Ext. Painting of Stem Walls 10 7 90 18FEB13A 08APR13 56
Architectural - Interior

LA1-0014 LTB 110- Plaster Work for Steam Walls 12 0 100 18NOV12A 01DEC12A
LA1-0018 LTB 110- Int. Doors Installation 7 7 30 30DEC12A 08APR13 56
LA1-0015 LTB 110- Spray Insulation 7 7 0 01APR13 08APR13 36
LA1-0017 LTB 110- Inst of gypsum Board 12 12 0 09APR13 22APR13 36
LA1-0016 LTB 110- Inst. of gypsum Board Ceiling 12 12 0 23APR13 06MAY13 36
LA1-0019 LTB 110- Tiles for floor 10 10 0 04MAY13 14MAY13 36

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 24 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Electrical

LA1-0020 LTB 110- Ele PVC Conduits/Fittings/Boxes 5 0 100 18FEB13A 23FEB13A


LA1-0023 LTB 110- Duplex & Switch Inst. 5 5 0 23APR13 28APR13 40
LA1-0021 LTB 110- Electrical Wiring Works 3 3 0 06APR13 08APR13 56
LA1-0022 LTB 110- Lighting Fix. & Cover Plates Inst. 3 3 0 04MAY13 06MAY13 36
LA1-0024 LTB 110- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -24
Mechanical

LA1-0026 LTB 110- Exhaust Fan Inst. 1 1 90 01MAR13A 18JUN13 5


LA1-0027 LTB 110- Unit Heater Installation 1 1 0 18JUN13 18JUN13 6
Plumbing

LA1-0028 LTB 110- Hot & Cold Water Piping 7 7 50 01DEC12A 08APR13 64
LA1-0030 LTB 110- Toilet Sanitry Fixture Inst. 7 7 50 02FEB13A 08APR13 67
LA1-0029 LTB 110- Toilet & Misc. Accessories 5 5 0 09APR13 14APR13 64
Fire Protection System

LA1-0031 LTB 110- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5


Inspections, Punchlists

LA1-0032 LTB 110- Test & Commission 2 2 0 23JUL13 24JUL13 -23


LA1-0033 LTB 110- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
LA1-0034 LTB 110- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
Large Latrine #111
Foundations

LA2-0001 LTB 111- Layout 2 0 100 05APR12A 07APR12A


LA2-0002 LTB 111- Excavation Work 5 0 100 08APR12A 12APR12A
LA2-0003 LTB 111- Watering, Backfilling & Compaction 5 0 100 14APR12A 09OCT12A
LA2-0004 LTB 111- Foundation & Ring Beam Works 12 0 100 15MAY12A 28MAY12A
LA2-0005 LTB 111- BKFLNG, CMPCTN, CAP. & Vap. Barriers 2 0 100 05JUN12A 11JUN12A
LA2-0006 LTB 111- Formwork & RFT for Slab on Grade 12 0 100 12JUN12A 25JUN12A
LA2-0007 LTB 111- Concrete for Slab on Grade 7 0 100 14JUL12A 17SEP12A
Superstructure & Close-in

LA2-0008 LTB 111- Inst of Steel Bar for Stem Walls 12 0 100 18JUN12A 03JUL12A
LA2-0009 LTB 111- Inst. of Concrete Stem Walls 15 0 100 04JUL12A 01OCT12A
LA2-0010 LTB 111- Installation of K Span 15 0 100 01OCT12A 09OCT12A
Architectural - Exterior

LA2-0013 LTB 111- Windows Installation 7 0 100 24DEC12A 31JAN13A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 25 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LA2-0011 LTB 111- Ext. Door installaion 5 5 40 19JAN13A 06APR13 12
LA2-0012 LTB 111- Ext. Painting of Stem Walls 15 15 30 26MAR13A 17APR13 26
Architectural - Interior

LA2-0014 LTB 111- Plaster for Steam Walls 7 0 100 18NOV12A 25NOV12A
LA2-0015 LTB 111- Spray Insulation 7 7 0 07APR13 14APR13 12
LA2-0016 LTB 111- Inst of gypsum Board Ceiling 6 6 0 15APR13 21APR13 39
LA2-0017 LTB 111- Inst. of gypsum Board 10 10 0 15APR13 25APR13 12
LA2-0018 LTB 111- Int. Doors Installation 7 7 0 27APR13 04MAY13 12
LA2-0019 LTB 111- Tiles for floor 15 15 0 24APR13 11MAY13 39
Electrical

LA2-0020 LTB 111- Ele PVC Conduits/Fittings/Boxes 4 0 100 18FEB13A 21FEB13A


LA2-0021 LTB 111- Electrical Wiring Works 5 5 0 01APR13 06APR13 52
LA2-0022 LTB 111- Lighting Fix. & Cover Plates Inst. 2 2 0 22APR13 23APR13 39
LA2-0024 LTB 111- Panel Board Installation 6 6 0 20JUL13 25JUL13 -26
LA2-0023 LTB 111- Duplex & Switch Inst. 2 2 0 09JUN13 10JUN13 12
Mechanical

LA2-0025 LTB 111- Exhaust Fan Installation 1 1 90 01MAR13A 18JUN13 5


LA2-0026 LTB 111- Unit Heater Installation 1 1 0 19JUN13 19JUN13 5
Plumbing

LA2-0027 LTB 111- Hot & Cold Water Piping 7 7 25 01DEC12A 09APR13 60
LA2-0029 LTB 111- Toilet Sanitry Fixture Inst. 7 7 10 01MAR13A 09APR13 65
LA2-0028 LTB 111- Toilet & Misc. Accessories 4 4 0 10APR13 14APR13 60
Fire Protection System

LA2-0030 LTB 111- Fire Extinguisher Inst. 1 1 0 18JUN13 18JUN13 6


Inspections, Punchlists

LA2-0031 LTB 111- Test & Commission 2 2 0 27JUL13 28JUL13 -26


LA2-0032 LTB 111- Punchlist Works 5 5 0 29JUL13 03AUG13 -26
LA2-0033 LTB 111- Finishing & Handover 1 1 0 04AUG13 04AUG13 -26
Large Latrine #112
Foundations

LA3-0001 LTB 112- Layout 2 0 100 07APR12A 08APR12A


LA3-0002 LTB 112- Excavation Work 5 0 100 11APR12A 16APR12A
LA3-0003 LTB 112- Watering, Backfilling & Compaction 5 0 100 21APR12A 25APR12A
LA3-0004 LTB 112- Foundation & Ring Beam Works 15 0 100 12MAY12A 11JUN12A
LA3-0005 LTB 112- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 12JUN12A 21JUN12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 26 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LA3-0006 LTB 112- Formwork & RFT for Slab on Grade 12 0 100 23JUN12A 05JUL12A
LA3-0007 LTB 112- Concrete Works for Slab on Grade 8 0 100 07JUL12A 18SEP12A
Superstructure & Close-in

LA3-0008 LTB 112- Inst. of Steel Bar for Stem Walls 12 0 100 25JUN12A 10JUL12A
LA3-0009 LTB 112- Concrete Stem Walls 12 0 100 11JUL12A 02OCT12A
LA3-0010 LTB 112- Installation of K Span 15 0 100 02OCT12A 09OCT12A
Architectural - Exterior

LA3-0011 LTB 112- Ext. Door Installaion 8 8 50 17DEC12A 08APR13 29


LA3-0012 LTB 112- Ext. Painting of Stem Walls 15 15 60 17DEC12A 17APR13 29
LA3-0013 LTB 112- Windows Installation 9 0 100 25DEC12A 04FEB13A
Architectural - Interior

LA3-0014 LTB 112- Plaster for Steam Walls 10 0 100 10NOV12A 20NOV12A
LA3-0015 LTB 112- Spray Insulation 7 7 0 09APR13 15APR13 29
LA3-0016 LTB 112- Inst. of gypsum Board ceiling 7 7 0 16APR13 22APR13 29
LA3-0017 LTB 112- Inst. of gypsum Board 15 15 0 23APR13 07MAY13 29
LA3-0019 LTB 112- Tiles for floor 10 10 0 27APR13 07MAY13 42
LA3-0018 LTB 112- Interior Doors Inst. 12 12 0 08MAY13 21MAY13 25
Electrical

LA3-0020 LTB 112- Ele PVC Conduits/Fittings/Boxes 4 0 100 17FEB13A 20FEB13A


LA3-0021 LTB 112- Electrical Wiring Works 5 5 0 01APR13 06APR13 56
LA3-0022 LTB 112- Lighting Fix. & Cover Plates Inst. 3 3 0 23APR13 25APR13 42
LA3-0023 LTB 112- Duplex & Switch Inst. 2 2 0 22MAY13 23MAY13 25
LA3-0024 LTB 112- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -23
Mechanical

LA3-0025 LTB 112- Exhaust Fan Inst. 1 1 80 01MAR13A 18JUN13 2


LA3-0026 LTB 112- Unit Heater Inst. 1 1 0 19JUN13 19JUN13 2
Plumbing

LA3-0027 LTB 112- Hot & Cold Water Piping 7 7 50 01DEC12A 09APR13 57
LA3-0029 LTB 112- Toilet Sanitry Fixture Inst. 7 7 10 01MAR13A 09APR13 62
LA3-0028 LTB 112- Toilet & Misc. Accessories 4 4 0 10APR13 14APR13 57
Fire Protection System

LA3-0030 LTB 112- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5


Inspections, Punchlists

LA3-0031 LTB 112- Test & Commission 2 2 0 23JUL13 24JUL13 -23

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 27 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LA3-0032 LTB 112- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
LA3-0033 LTB 112- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
Large Latrine #113
Foundations

L4-0001 LTB 113- Layout 1 0 100 07APR12A 07APR12A


L4-0002 LTB 113- Excavation Work 5 0 100 11APR12A 16APR12A
L4-0003 LTB 113- Watering, Backfilling & Compaction 5 0 100 17APR12A 22APR12A
L4-0004 LTB 113- Foundation & Ring Beam Works 12 0 100 01MAY12A 20MAY12A
L4-0005 LTB 113- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 21MAY12A 02JUN12A
L4-0006 LTB 113- Formwork & RFT for Slab on Grade 12 0 100 03JUN12A 23JUN12A
L4-0007 LTB 113- Concrete for Slab on Grade 12 0 100 24JUN12A 08JUL12A
Superstructure & Close-in

L4-0008 LTB 113- Inst. of Steel Bar for Steam Walls 10 0 100 30JUN12A 10JUL12A
L4-0009 LTB 113- Inst. of Concrete Steam Walls 12 0 100 11JUL12A 09DEC12A
L4-0010 LTB 113- Installation of K Span 15 0 100 02DEC12A 06DEC12A
Architectural - Exterior

L4-0011 LTB 113- Exterior Door Inst. 6 6 40 26DEC12A 07APR13 64


L4-0013 LTB 113- Windows Installation 12 0 100 01JAN13A 09FEB13A
L4-0012 LTB 113- Ext. Painting of Stem Walls 14 14 60 20MAR13A 16APR13 49
Architectural - Interior

L4-0014 LTB 113- Plaster Work for Steam Walls 7 7 20 10JAN13A 08APR13 19
L4-0015 LTB 113- Spray Insulation 7 7 0 09APR13 16APR13 19
L4-0016 LTB 113- Inst. of gypsum Board Ceiling 10 10 0 17APR13 28APR13 19
L4-0017 LTB 113- Inst. of gypsum Board 14 14 0 17APR13 02MAY13 35
L4-0019 LTB 113- Tiles for floor 10 10 0 01MAY13 12MAY13 19
L4-0018 LTB 113- Int. Doors Installation 15 15 0 04MAY13 20MAY13 35
Electrical

L4-0020 LTB 113- Ele PVC Conduits/Fittings/Boxes 4 0 100 26FEB13A 02MAR13A


L4-0021 LTB 113- Electrical Wiring Works 5 5 0 01APR13 06APR13 39
L4-0022 LTB 113- Lighting Fix. & Cover Plates Inst 2 2 0 29APR13 30APR13 19
L4-0023 LTB 113- Duplex & Switch Inst. 5 5 0 04MAY13 08MAY13 35
L4-0024 LTB 113- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -24
Mechanical

L4-0025 LTB 113- Exhaust Fan Inst. 2 2 90 27MAR13A 19JUN13 -1


L4-0026 LTB 113- Unit Heater Inst. 2 2 0 20JUN13 22JUN13 -1

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 28 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Plumbing

L4-0029 LTB 113- Toilet Sanitry Fixture Inst. 9 9 10 01MAR13A 10APR13 61


L4-0027 LTB 113- Hot & Cold Water Piping 7 7 0 13MAY13 20MAY13 19
L4-0028 LTB 113- Toilet & Misc. Accessories 4 4 0 21MAY13 25MAY13 19
Fire Protection System

L4-0030 LTB 113- Fire Extinguisher Inst. 2 2 0 23JUN13 24JUN13 1


Inspections, Punchlists

L4-0031 LTB 113- Test & Commission 2 2 0 23JUL13 24JUL13 -23


L4-0032 LTB 113- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
L4-0033 LTB 113- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
Large Latrine #114
Foundations

LA5-0001 LTB 114- Layout 1 0 100 08APR12A 08APR12A


LA5-0002 LTB 114- Excavation Work 5 0 100 14APR12A 19APR12A
LA5-0003 LTB 114- Watering, Backfilling & Compaction 5 0 100 21APR12A 26APR12A
LA5-0004 LTB 114- Foundation & Ring Beam Works 12 0 100 28APR12A 10MAY12A
LA5-0005 LTB 114- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 12MAY12A 21MAY12A
LA5-0006 LTB 114- Formwork & RFT for Slab on Grade 12 0 100 22MAY12A 05JUN12A
LA5-0007 LTB 114- Concrete for Slab on Grade 4 0 100 06JUN12A 11JUN12A
Superstructure & Close-in

LA5-0008 LTB 114- Inst. Steel Bar for Stem Walls 4 0 100 16JUN12A 09SEP12A
LA5-0009 LTB 114- Concrete for Stem Walls 8 0 100 11JUL12A 18SEP12A
LA5-0010 LTB 114- Installation of K Span 15 0 100 15AUG12A 26SEP12A
Architectural - Exterior

LA5-0011 LTB 114- Ext. Door Installaion 15 15 40 18DEC12A 17APR13 8


LA5-0013 LTB 114- Windows Installation 15 0 100 05JAN13A 09FEB13A
LA5-0012 LTB 114- Ext. Painting of Stem Walls 18 18 0 27APR13 16MAY13 26
Architectural - Interior

LA5-0014 LTB 114- Plaster Work for Stem Walls 7 0 100 10OCT12A 17OCT12A
LA5-0015 LTB 114- Spray Insulation 7 7 0 18APR13 25APR13 8
LA5-0016 LTB 114- Inst. of gypsum Board Ceiling 6 6 0 27APR13 02MAY13 8
LA5-0017 LTB 114- Inst. of gypsum Board 15 15 0 27APR13 13MAY13 29
LA5-0018 LTB 114- Int. Doors Installation 10 10 0 18MAY13 28MAY13 26
LA5-0019 LTB 114- Tiles for Floor 15 15 0 12MAY13 28MAY13 8

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 29 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:09 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Electrical

LA5-0020 LTB 114- Ele PVC Conduits/Fittings/Boxes 4 0 100 18FEB13A 21FEB13A


LA5-0021 LTB 114- Electrical Wiring Works 5 5 0 01APR13 06APR13 31
LA5-0022 LTB 114- Lighting Fix. & Cover Plates Inst. 3 3 0 04MAY13 06MAY13 8
LA5-0023 LTB 114- Duplex & Switch Inst. 5 5 0 20MAY13 25MAY13 26
LA5-0024 LTB 114- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -24
Mechanical

LA5-0025 LTB 114- Exhaust Fan Inst. 1 1 90 28MAR13A 18JUN13 2


LA5-0026 LTB 114- Unit Heater Inst. 1 1 0 18JUN13 18JUN13 2
Plumbing

LA5-0028 LTB 114- Toilet & Misc. Accessories 5 5 10 01MAR13A 06APR13 64


LA5-0027 LTB 114- Hot & Cold Water Piping 7 7 0 29MAY13 05JUN13 8
LA5-0029 LTB 114- Toilet Sanitry Fixture Inst. 4 4 0 06JUN13 10JUN13 8
Fire Protection System

LA5-0030 LTB 114- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5


Inspections, Punchlists

LA5-0031 LTB 114- Test & Commission 2 2 0 23JUL13 24JUL13 -23


LA5-0032 LTB 114- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
LA5-0033 LTB 114- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
Large Latrine #115
Foundations

LA6-0001 LTB 115- Layout 1 0 100 09APR12A 09APR12A


LA6-0002 LTB 115- Excavation Work 5 0 100 14APR12A 19APR12A
LA6-0003 LTB 115- Watering, Backfilling & Compaction 5 0 100 21APR12A 25APR12A
LA6-0004 LTB 115- Foundation & Ring Beam 12 0 100 26APR12A 10MAY12A
LA6-0005 LTB 115- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 12MAY12A 24MAY12A
LA6-0006 LTB 115- Formwork & RFT for Slab on Grade 12 0 100 26MAY12A 10JUN12A
LA6-0007 LTB 115- Concrete for Slab on Grade 4 0 100 11JUN12A 16JUN12A
Superstructure & Close-in

LA6-0008 LTB 115- Inst. of Steel Bar for Stem Walls 4 0 100 20JUN12A 25JUN12A
LA6-0009 LTB 115- Concrete Stem Walls 8 0 100 26JUN12A 19JAN13A
LA6-0010 LTB 115- Installation of K Span 15 0 100 27NOV12A 05DEC12A
Architectural - Exterior

LA6-0013 LTB 115- Windows Installation 10 0 100 05JAN13A 09FEB13A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 30 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LA6-0011 LTB 115- Ext. Door Installaion 15 15 40 05JAN13A 17APR13 11
LA6-0012 LTB 115- Ext. Painting of Steam Walls 15 15 20 21MAR13A 17APR13 27
Architectural - Interior

LA6-0014 LTB 115- Plaster for Stem Walls 7 0 100 18MAR13A 25MAR13A
LA6-0015 LTB 115- Spray Insulation 7 7 0 18APR13 25APR13 11
LA6-0016 LTB 115- Inst. of gypsum Board Ceiling 6 6 0 27APR13 02MAY13 11
LA6-0017 LTB 115- Inst. of gypsum Board 14 14 0 27APR13 12MAY13 23
LA6-0018 LTB 115- Int. Doors Installation 10 10 0 13MAY13 23MAY13 23
LA6-0019 LTB 115- Tiles for Floor 15 15 0 07MAY13 23MAY13 11
Electrical

LA6-0020 LTB 115- Ele PVC Conduits/Fittings/Boxes 4 0 100 26FEB13A 20MAR13A


LA6-0021 LTB 115- Electrical Wiring Works 5 5 0 01APR13 06APR13 34
LA6-0022 LTB 115- Lighting Fix. & Cover Plates Inst. 3 3 0 04MAY13 06MAY13 11
LA6-0023 LTB 115- Duplex & Switch Inst. 4 4 0 20MAY13 23MAY13 23
LA6-0024 LTB 115- Panel Board Installation 3 3 0 20JUL13 22JUL13 -24
Mechanical

LA6-0025 LTB 115- Exhaust Fan Installation 1 1 90 26MAR13A 18JUN13 2


LA6-0026 LTB 115- Unit Heater Installation 1 1 0 18JUN13 18JUN13 2
Plumbing

LA6-0027 LTB 115- Hot & Cold Water Piping 7 7 0 25MAY13 01JUN13 11
LA6-0029 LTB 115- Toilet Sanitry Fixture Inst. 4 4 0 02JUN13 05JUN13 12
LA6-0028 LTB 115- Toilet & Misc. Accessories 5 5 0 02JUN13 06JUN13 11
Fire Protection System

LA6-0030 LTB 115- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5


Inspections, Punchlists

LA6-0031 LTB 115- Test & Commission 2 2 0 23JUL13 24JUL13 -23


LA6-0032 LTB 115- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
LA6-0033 LTB 115- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
MWR Building #105D
Foundations

MWR-0001 MWR 105D- Layout 1 0 100 01APR12A 01APR12A


MWR-0002 MWR 105D- Excavation Work 3 0 100 02APR12A 04APR12A
MWR-0003 MWR 105D- Watering, Backfilling & Compaction 4 0 100 05APR12A 09APR12A
MWR-0004 MWR 105D- Foundation & Ring Beam 8 0 100 14APR12A 25APR12A
MWR-0005 MWR 105D- BKFLNG, CMPCTN, CAP. & Vap. Barriers 8 0 100 10JUN12A 18JUN12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 31 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
MWR-0006 MWR 105D- Formwork & RFT for Slab on Grade 10 0 100 19JUN12A 30JUN12A
MWR-0007 MWR 105D- Concrete for Slab on Grade 7 0 100 01JUL12A 08JUL12A
Superstructure & Close-in

MWR-0008 MWR 105D- Inst. of Steel Bar for Stem Walls 6 0 100 09JUL12A 25SEP12A
MWR-0009 MWR 105D- Inst of Concrete Stem Walls 9 0 100 26SEP12A 19NOV12A
MWR-0010 MWR 105D- Installation of K Span 13 0 100 03OCT12A 24NOV12A
Architectural - Exterior

MWR-0011 MWR 105D- Ext. Door Installation 9 9 90 14FEB13A 15APR13 44


MWR-0012 MWR 105D- Ext. Painting of Stem Walls 16 16 90 14FEB13A 23APR13 43
MWR-0013 MWR 105D- Windows Installation 6 6 50 25FEB13A 22APR13 44
Architectural - Interior

MWR-0014 MWR 105D- Plaster Work for Stem Walls 6 0 100 20NOV12A 26NOV12A
MWR-0015 MWR 105D- Spray Insulation 4 4 25 25NOV12A 04APR13 43
MWR-0016 MWR 105D- Fence Installation 9 9 0 06APR13 15APR13 47
DPW-0018 MWR 105D- Int. Doors Installation 6 6 0 24APR13 30APR13 43
MWR-0019 MWR 105D- Sealed Concrete for Floor 4 4 0 30APR13 04MAY13 46
Electrical

MWR-0020 MWR 105D- Ele PVC Conduits/Fittings/Boxes 8 0 100 14FEB13A 23FEB13A


MWR-0021 MWR 105D- Electrical Wiring Works 11 11 0 06APR13 17APR13 45
MWR-0022 MWR 105D- Lighting Fix. & Cover Plates Inst. 10 10 0 18APR13 29APR13 45
MWR-0023 MWR 105D- Duplex & Switch Inst. 6 6 0 01MAY13 07MAY13 43
MWR-0024 MWR 105D- Panel Board Inst. 5 5 0 20JUL13 24JUL13 -24
Mechanical

MWR-0026 MWR 105D- Exhaust Fan Inst. 2 2 0 18JUN13 19JUN13 2


MWR-0027 MWR 105D- Unit Heater Inst. 2 2 0 20JUN13 22JUN13 2
Fire Protection System

MWR-0031 MWR 105D- Fire Extinguisher Inst. 2 2 0 23JUN13 24JUN13 2


Inspections, Punchlists

MWR-0032 MWR 105D- Test & Commission 2 2 0 25JUL13 27JUL13 -24


MWR-0033 MWR 105D- Punchlist Works 4 4 0 28JUL13 31JUL13 -24
MWR-0034 MWR 105D- Finishing & Handover 1 1 0 01AUG13 01AUG13 -24
DPW Building #116
Foundations

DPW-0001 DPW 116- Layout 1 0 100 09APR12A 09APR12A

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 32 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
DPW-0002 DPW 116- Excavation Work 8 0 100 11APR12A 21APR12A
DPW-0003 DPW 116- Watering, Backfilling & Compaction 5 0 100 22APR12A 26APR12A
DPW-0004 DPW 116- Foundation & Ring Beam 16 0 100 22APR12A 09JAN13A
DPW-0005 DPW 116- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 20MAY12A 21JUN12A
DPW-0006 DPW 116- Formwork & RFT for Slab on Grade 15 0 100 25JUN12A 12AUG12A
DPW-0007 DPW 116- Concrete for Slab on Grade 10 0 100 13AUG12A 09SEP12A
Superstructure & Close-in

DPW-0008 DPW 116- Inst. of Steel Bar for Steam Walls 12 0 100 26JUN12A 08JUL12A
DPW-0009 DPW 116- Inst. of Concrete Steam Walls 12 0 100 10SEP12A 14JAN13A
DPW-0010 DPW 116- Installation of K Span 15 0 100 02OCT12A 26NOV12A
Architectural - Exterior

DPW-0013 DPW 116- Windows Installation 10 10 95 05DEC12A 11APR13 66


DPW-0011 DPW 116- Ext. Door Installaion 8 8 30 01JAN13A 09APR13 66
DPW-0012 DPW 116- Ext. Painting of Stem Walls 18 10 20 16FEB13A 11APR13 49
Architectural - Interior

DPW-0014 DPW 116- Plaster for Steam Walls 15 15 85 14NOV12A 17APR13 35


DPW-0015 DPW 116- Spray Insulation 15 10 60 10DEC12A 11APR13 40
DPW-0017 DPW 116- Inst. of gypsum Board 15 10 20 16FEB13A 11APR13 66
DPW-0016 DPW 116- Inst. of Suspended Ceiling 8 8 0 18APR13 27APR13 35
DPW-0019 DPW 116- Sealed Concrete for Floor 5 5 0 29APR13 04MAY13 35
Electrical

DPW-0020 DPW 116- Ele PVC Conduits/Fittings/Boxes 3 0 100 16FEB13A 18FEB13A


DPW-0023 DPW 116- Duplex & Switch Inst. 4 4 0 01APR13 04APR13 66
DPW-0021 DPW 116- Electrical Wiring Works 6 6 0 01APR13 07APR13 52
DPW-0022 DPW 116- Lighting Fix. & Cover Plates Inst. 2 2 0 28APR13 29APR13 35
DPW-0024 DPW 116- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -23
Mechanical

DPW-0025 DPW 116- AC Split Installation 1 1 0 06APR13 06APR13 66


DPW-0027 DPW 116- Unit Heater Installation 1 1 0 12MAY13 12MAY13 35
DPW-0026 DPW 116- Exhaust Fan Installation 1 1 0 18JUN13 18JUN13 3
Plumbing

DPW-0028 DPW 116- Hot & Cold Water Piping 6 6 0 30APR13 06MAY13 35
DPW-0030 DPW 116- Toilet Sanitry Fixture Inst. 4 4 0 07MAY13 11MAY13 35
DPW-0029 DPW 116- Toilet & Misc. Accessories 5 5 0 07MAY13 12MAY13 35
Fire Protection System

DPW-0031 DPW 116- Fire Extinguisher Inst. 1 1 0 30APR13 30APR13 48


Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 33 of 38
Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Inspections, Punchlists

DPW-0032 DPW 116- Test & Commission 2 2 0 23JUL13 24JUL13 -23


DPW-0033 DPW 116- Punchlist Works 5 5 0 25JUL13 30JUL13 -23
DPW-0034 DPW 116- Finishing & Handover 1 1 0 31JUL13 31JUL13 -23
Literacy Classroom #117A
Foundations

LCR1-001 LCR 117A - Layout 1 0 100 03APR12A 03APR12A


LCR1-002 LCR 117A - Excavation Work 3 0 100 04APR12A 07APR12A
LCR1-003 LCR 117A - Watering, Backfilling & Compaction 3 0 100 08APR12A 10APR12A
LCR1-004 LCR 117A - Foundation & Ring Beam 8 0 100 14APR12A 25APR12A
LCR1-005 LCR 117A - BKFLNG, CMPCTN, CAP. & Vap. Barriers 8 0 100 21MAY12A 05JUL12A
LCR1-007 LCR 117A - Concrete for Slab on Grade 5 0 100 25JUN12A 02JUL12A
LCR1-006 LCR 117A - Formwork & RFT for Slab on Grade 13 0 100 25JUN12A 08JUL12A
Superstructure & Close-in

LCR1-008 LCR 117A - Inst. of Steel Bar for Stem Walls 6 0 100 28JUN12A 04JUL12A
LCR1-009 LCR 117A - Concrete for Stem Walls 10 0 100 05JUL12A 02OCT12A
LCR1-010 LCR 117A - Installation of K Span 15 0 100 12AUG12A 08OCT12A
Architectural - Exterior

LCR1-013 LCR 117A - Windows Installation 5 0 100 01DEC12A 29JAN13A


LCR1-011 LCR 117A - Ext. Door Installaion 5 5 90 18DEC12A 06APR13 60
LCR1-012 LCR 117A - Ext. Painting of Stem Walls 11 0 100 18FEB13A 31MAR13A
Architectural - Interior

LCR1-014 LCR 117A - Plaster Work for Steam Walls 13 0 100 10OCT12A 24OCT12A
LCR1-015 LCR 117A - Spray Insulation 7 7 95 25NOV12A 08APR13 48
LCR1-017 LCR 117A - Int. Doors Installation 5 5 30 03MAR13A 06APR13 61
LCR1-016 LCR 117A - Fence Installation 10 10 0 09APR13 20APR13 48
LCR1-018 LCR 117A - Sealed Concrete for Floor 8 8 0 21APR13 29APR13 48
Electrical

LCR1-019 LCR 117A - Ele PVC Conduits/Fittings/Boxes 7 0 100 18FEB13A 25FEB13A


LCR1-020 LCR 117A - Electrical Wiring Works 6 5 30 26MAR13A 06APR13 60
LCR1-021 LCR 117A - Duplex & Switch Inst. 5 5 30 26MAR13A 06APR13 61
LCR1-022 LCR 117A - Lighting Fix. & Cover Plates Inst. 5 5 50 27MAR13A 20APR13 48
LCR1-023 LCR 117A - Panel Board Installation 3 3 0 20JUL13 22JUL13 -24
Mechanical

LCR1-024 LCR 117A - Exhaust Fan Installation 1 1 60 27MAR13A 18JUN13 2

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 34 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LCR1-025 LCR 117A - Unit Heater Installation 1 1 0 19JUN13 19JUN13 4

LCR1-026 LCR 117A - Fire Extinguisher Inst. 1 1 0 21APR13 21APR13 55

LCR1-027 LCR 117A - Test & Commission 2 2 0 23JUL13 24JUL13 -24


LCR1-028 LCR 117A - Punchlist Works 6 6 0 25JUL13 01AUG13 -24
LCR1-029 LCR 117A - Finishing & Handover 1 1 0 03AUG13 03AUG13 -24

LCR2-001 LCR 117B- Layout 1 0 100 04APR12A 04APR12A


LCR2-002 LCR 117B- Excavation Work 3 0 100 05APR12A 07APR12A
LCR2-003 LCR 117B- Watering, Backfilling & Compaction 3 0 100 08APR12A 10APR12A
LCR2-004 LCR 117B- Foundation & Ring Beam 10 0 100 11APR12A 23APR12A
LCR2-005 LCR 117B- BKFLNG, CMPCTN, CAP. & Vap. Barriers 9 0 100 12MAY12A 21MAY12A
LCR2-006 LCR 117B- Formwork & RFT for Slab on Grade 15 0 100 04JUN12A 26JUN12A
LCR2-007 LCR 117B- Concrete for Slab on Grade 12 0 100 20JUN12A 05JUL12A

LCR2-008 LCR 117B- Inst. of Steel Bar for Stem Walls 10 0 100 20JUN12A 02JUL12A
LCR2-009 LCR 117B- Concrete for Stem Walls 15 0 100 03JUL12A 02OCT12A
LCR2-010 LCR 117B- Installation of K Span 15 0 100 13AUG12A 08OCT12A

LCR2-013 LCR 117B- Windows Installation 8 0 100 01DEC12A 27JAN13A


LCR2-011 LCR 117B- Ext. Door Installation 8 8 90 18DEC12A 09APR13 56
LCR2-012 LCR 117B- Ext. Painting of Stem Walls 12 0 100 18FEB13A 31MAR13A

LCR2-014 LCR 117B- Plaster for Stem Walls 10 0 100 10OCT12A 09FEB13A
LCR2-015 LCR 117B- Spray Insulation 7 7 90 10DEC12A 08APR13 52
LCR2-017 LCR 117B- Int. Doors Installation 5 5 30 04MAR13A 06APR13 61
LCR2-016 LCR 117B- Fence Installation 10 10 0 09APR13 20APR13 52
LCR2-018 LCR 117B- Sealed Concrete for Floor 8 8 0 10APR13 18APR13 56

LCR2-019 LCR 117B- Ele PVC Conduits/Fittings/Boxes 6 0 100 18FEB13A 24FEB13A


LCR2-020 LCR 117B- Electrical Wiring Works 7 7 30 25FEB13A 08APR13 57
LCR2-021 LCR 117B- Duplex & Switch Inst. 7 7 30 27MAR13A 08APR13 61
LCR2-022 LCR 117B- Lighting Fix. & Cover Plates Inst. 7 7 60 27MAR13A 08APR13 57

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 35 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
LCR2-023 LCR 117B- Panel Board Inst. 3 3 0 20JUL13 22JUL13 -25
Mechanical

LCR2-024 LCR 117B- Exhaust Fan Inst. 1 1 60 27MAR13A 18JUN13 0


LCR2-025 LCR 117B- Unit Heater Inst. 1 1 0 19JUN13 19JUN13 0
Fire Protection System

LCR2-026 LCR 117B- Fire Extinguisher Inst. 1 1 0 10APR13 10APR13 63


Inspections, Punchlists

LCR2-027 LCR 117B- Test & Commission 2 2 0 23JUL13 24JUL13 -25


LCR2-028 LCR 117B- Punchlist Works 7 7 0 25JUL13 01AUG13 -25
LCR2-029 LCR 117B- Finishing & Handover 1 1 0 03AUG13 03AUG13 -25
Fire Station #118
Foundations

FSB-0001 FSB 118- Layout 1 0 100 06APR12A 07APR12A


FSB-0002 FSB 118- Excavation Work 3 0 100 07APR12A 09APR12A
FSB-0003 FSB 118- Watering, Backfilling & Compaction 3 0 100 14APR12A 19APR12A
FSB-0004 FSB 118- FDN & Ring Beam 8 0 100 21APR12A 03MAY12A
FSB-0005 FSB 118- BKFLNG, CMPCTN, CAP. & Vap. Barriers 7 0 100 12MAY12A 05JUL12A
FSB-0006 FSB 118- Formwork & RFT for Slab on Grade 5 0 100 07JUL12A 12JUL12A
FSB-0007 FSB 118- Concrete for Slab on Grade 1 0 100 14JUL12A 12AUG12A
Superstructure & Close-in

FSB-0010 FSB 118- Installation of K Span 13 0 100 12AUG12A 24NOV12A


FSB-0008 FSB 118- Inst. of Steel Bar for Stem Walls 12 0 100 13AUG12A 29AUG12A
FSB-0009 FSB 118- Concrete Stem Walls 10 0 100 03SEP12A 21JAN13A
Architectural - Exterior

FSB-0011 FSB 118- Ext. Door Installation 7 7 90 28DEC12A 07APR13 69


FSB-0013 FSB 118- Windows Installation 7 0 100 30DEC12A 17JAN13A
FSB-0012 FSB 118- Ext. Painting of Stem Walls 8 7 90 28FEB13A 08APR13 59
Architectural - Interior

FSB-0014 FSB 118- Plaster for Stem Walls 10 0 100 10DEC12A 28MAR13A
FSB-0015 FSB 118- Spray Insulation 7 7 25 21FEB13A 07APR13 54
FSB-0017 FSB 118- Int. Doors Instalation 7 7 20 01MAR13A 08APR13 59
FSB-0016 FSB 118- Fence Installation 8 8 0 08APR13 15APR13 54
FSB-0018 FSB 118- Sealed Concrete for Floor 5 5 0 28APR13 02MAY13 46

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 36 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float
Electrical

FSB-0019 FSB 118- Ele PVC Conduits/Fittings/Boxes 10 0 100 23FEB13A 01MAR13A


FSB-0020 FSB 118- Electrical Wiring Works 12 12 0 01APR13 14APR13 47
FSB-0021 FSB 118- Duplex & Switch Inst. 9 9 0 16APR13 25APR13 53
FSB-0022 FSB 118- Lighting Fix. & Cover Plates Inst. 10 10 0 16APR13 27APR13 46
FSB-0023 FSB 118- Panel Board Installation 5 5 0 20JUL13 24JUL13 -25
Mechanical

FSB-0024 FSB 118- Exhaust Fan Inst. 3 3 45 28MAR13A 20JUN13 -1


FSB-0025 FSB 118- Unit Heater Inst. 3 3 25 29MAR13A 20JUN13 -1
Fire Protection System

FSB-0026 FSB 118- Fire Extinguisher Inst. 5 5 0 22JUN13 26JUN13 -1


Inspections, Punchlists

FSB-0027 FSB 118- Test & Commission 2 2 0 25JUL13 27JUL13 -25


FSB-0028 FSB 118- Punchlist Works 5 5 0 28JUL13 01AUG13 -25
FSB-0029 FSB 118- Finishing & Handover 1 1 0 03AUG13 03AUG13 -25

Contract Close-out
Close-out Inspections

CCO-0001 Prefinal Inspection & Correction 10 10 0 11AUG13 21AUG13 -22


CCO-0002 Final Inspection 3 3 0 22AUG13 25AUG13 -22
CCO-0003 Final Acceptance & Handover 1 1 0 26AUG13 26AUG13 -22

As-Built Drawings

CCO-0004 Submit As-Built Drawings 6 6 0 04AUG13 09AUG13 -30


CCO-0005 Approved As-Built Drawing by AED 14 14 0 10AUG13 23AUG13 -30

O&M Manuals & Training

CCO-0006 Submit O&M Manual 7 7 0 04AUG13 10AUG13 -24


CCO-0007 Approved O&M Manual by AED 7 7 0 11AUG13 17AUG13 -24

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 37 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early Total 2011 2012 2013
J A S O N D J F M A M J J A S O N D J F M A M J J A SC
ID Description Dur Dur Start Finish Float

Demobilization

CCO-0012 Demobilization of Site office & Con. Equipments 10 10 0 27AUG13 05SEP13 -32

Start Date 26JUL11 PS19 FCEC UIProjects JV Sheet 38 of 38


Early Bar
Finish Date 05SEP13 Date Revision Checked Approved
Progress Bar W5J9JR-10-D-0005-0006 ANA Gardez
Data Date 01APR13
Run Date 13APR13 10:10 Critical Activity
Project Management Layout

© Primavera Systems, Inc.

You might also like