You are on page 1of 2

BILL OF QUANTITES FOR G+1 RESIDENTIAL BILDING

S.NO DESCRIPTION OR UNITS IN RUPEES TOTAL TOTAL


DESCRIPTION OR QUANTITY AMOUNT

1 CEMENT BAGS 310 900 279000


2 SAND TRUCK 8000 21 168000
3 AGGREGATE OF 40 MM SIZE TIPPER 4000 5 20000
4 AGGREGATE OF TIPPER 4700 10 47000
20MM SIZE 0
5 SHUTTERING M2 175 1500 262500
6 EXCAVTION M 3
300 386 115800
7 BACK FILLING M3 80 247 19760
8 BRICK NO'S 2.5 6000 15000
9 WALL PUTTY BAGS 125 10 1250
10 FALSE CEILING M2 325 74 24050
11 EMULSION PAINT (WATER-BOND) LTRS 70 155 10850
FOR INTERNAL AREA 0
12 EMULSION PAINT (WATER-BOND) LTRS 290 125 36250
FOR EXTERNAL AREA 0
13 ENAMEL PAINT(OIL PAINT) LTRS 165 20 3300
FOR DOORS & WINDOWS 0
14 MARBLE FLOORING & SKIRTING M2 270 170.52 46040.4
ARAEA 0
15 VITRIFIED TILES BOXES 155 14 2170
16 INTER LOCK TILES NO'S 30 3847 115410
17 CERAMIC TILES BOXES 170 102 17340
18 FRAMES FOR DOORS, AND WINDOWS 0
& VENTILATORS 0
19 DOORS & WINDOW PANEL OR SHUTTER 0
20 ACCESSORIES & FITTING FOR DOORS 0
& WINDOWS 0
21 WINDOW GRILL & GATE AREA M3 645 20 12900
22 OVER HEAD WATER TANK (PVC) LS 8000 1 8000
23 LABOUR CHARGES( MASON) LS 150 3504 525600
24 LABOUR CHARGES( CENTRING) LS 90 3504 315360
25 REINFORECEMENT - - 350000
26 ELECTRICAL MATERIAL & FITTING LS - 7% 200000
27 PLUMBING & SANITATION LS - 8% 210000
28 MISCELLIOUS ITEMS 100000
29 CONSULTANT FEE FOR DESIGING AND
30 EXECUTING PROJECT LS 50000
TOTAL 2955580.4

TOTAL COST OF PROJECT =2955580


REMARKS