You are on page 1of 67

“I admit that this report is made by myself”

Signature: …………………………….

Name: NOORIYANA BINTI MISMAN

Date: ……………………………………

1|Page
ABSTRACT

This report describes the activities that I did during my industrial training period at Johor Port
Berhad, Pasir Gudang for 10 weeks. The company provided a comprehensive range of port
services to meet the individual needs to its customer.

The report also shows the details about background of the company and activities that I
carried out during the training period. It also contains recommendations for the organizations
and the university.

2|Page
ACKNOWLEDGEMENT

First, I would like to express my grateful to Almighty ALLAH s.w.t for blessing me
with good health and ideas in completing this industrial training successfully. I would like to
thanks Allah for His firm hands in guiding me during completing this report.

I would like to show my gratitude to Johor Port Berhad, Pasir Gudang for giving me
this opportunity to undergo industrial training for 10 weeks starting on 2nd July to 6th
September 2018. At the same time, I have completed my industrial training report
successfully as to fulfil the main condition in order complete my study in Bachelor of Civil
Engineering.

I would like to thank my supervisor, Mr Ahmad Zahry Iswandi bin Yunos and my
assistant general manager, Ir Shahrul Idzham bin Zainon Aznan for their guidance,
encouragement and advice during my industrial training. I also take this opportunity to thank
to my family, friends, engineers, technician and whoever involved directly or indirectly
helping me to learn new things and completing my training.

3|Page
INDEX

CHAPTER CONTENT PAGES

ADMISSION 1

ABSTRACT 2

ACKNOWLEDGEMENT 3

INDEX 4-5

LIST OF TABLES 6

LIST OF FIGURES 7-8

STUDENT BACKGROUND 9

1 INTRODUCTION 10-12

1.1. Preliminary
1.2. Objective of Industrial Training
1.3. Importance of Industrial Training

2 INDUSTRY BACKGROUND 13-23

2.1. About Johor Port


2.2. Johor Port’s Mission and Vision
2.3. Johor Port Core Values
2.4. Johor Port Facilities
2.5. JPB organization Chart
2.6. About Facility Development Department

4|Page
3 TRAINING SCOPE 24-63

3.1. Introduction of Training


3.2. Weekly Activity at Johor Port
3.3. Standard Operation Procedure (SOP)
3.4. Mode of Bidding Process
3.5. Project Involvement
3.6. Safety at Johor Port

4 CONCLUSION AND SUGGESTION 64-66

4.1. Comments

4.2. Suggestions

4.3. Conclusion

5 APPENDIXES 67

5|Page
LIST OF TABLES

NO TITLE PAGE

1 Weekly Activity 26-29

2 Bidding Type 37

6|Page
LIST OF FIGURES

NO TITLE PAGE

2.1 Johor Port Logo 13

2.2 Johor Port 14

2.3 Johor Port layout plan 15

2.4 Container Berth 17

2.5 Discharge Operation 18

2.6 Liquid Terminal 19

3.1 Layout of BT9 39

3.2 Column hacking 40

3.3 Cleaning work 41

3.4 Layout of BT2 41

3.5 Layout of Wharf 5 and Wharf 6 42

3.6 Location Wharf 5 and Wharf 6 43

3.7 Hacked slab 43

3.8 Inspection of reinforcement and formwork before

Concreting process 44

3.9 Slump test 45

3.10 Concreting works 45

3.11 Wharf mark 46

3.12 Process installation fender 49

3.13 Before fender installation 49

3.14 Slab inspection 50

3.15 Wall inspection 51

3.16 Elevator testing 51

7|Page
3.17 Foldaway door inspection 52

3.18 Louvers 53

3.19 Blowers 53

3.20 Exhaust fan 54

3.21 Flow of firefighting system 54

3.22 Pressure meter 55

3.23 Pump control switch 56

3.24 Pump 56

3.25 Main fire alarm panel and SPKA 57

3.26 Main pipe 58

3.27 Sample of entry pass 60

3.28 Example of complete PPE 61

3.29 Life jacket and safety helmet 61

3.30 Parking lot at Wisma Kontena 63

3.31 5S Concept 63

8|Page
STUDENT BACKGROUND

NAME: NOORLIYANA BINTI MISMAN

MATRIC NO: AF 150165

COURSE: BACHELOR OF CIVIL ENGINEERING (BFF)

COMPANY’s NAME: JOHOR PORT BERHAD (Facility Development Department)

COMPANY’s ADDRESS: JOHOR PORT BERHAD, P.O BOX 151, WISMA KONTENA,
81707, PASIR GUDANG, JOHOR.

SUPERVISOR: EN AHMAD ZAHRY ISWANDI BIN YUNOS

9|Page
CHAPTER 1

INTRODUCTION

1.1 Preliminary

Industrial training is the main requirements to be taken, completed dan pass by every
student of the Universiti Tun Hussien Onn Malaysia (UTHM) for completing bachelor’s
in civil engineer to qualify themselves to receive the award at by the end of study. During
the period of industrial training, students can gather knowledge as well as experience and
expertise of various work performed. Student can also relate all the theory that have been
learned in to practical form during training. In addition, this training aimed to relate the
theories learned in classroom or lab with actual working environment and give early
exposure to students of work situation. It also helps students to enhancing their
communication skills, experience, and expand the student experience thus, it will inspire
the spirit of productive work and good relationship with workers.

10 | P a g e
1.2 Objective of Industrial Training

Generally, this industry training program is to achieve the following objectives:

 Provide initial exposure and directly to the profession and the application in a real
job
 To provide an opportunity to communicate and work together with professionals
from various fields
 Experience working in a professional organization
 Help build creativity, technical skills, interpersonal, communication and ability
for work together in resolving problems with colleagues.
 Nurture themselves for more confident and responsible as well as to build and
strengthen relationships with professional outside the campus.

Therefore, the industrial training is seen to provide many positive effects expected from
students at the end of the training. At the same time, it could help in improving the
quality of Educational performance for each educational institution itself.

11 | P a g e
1.3 Importance of Industrial Training

Industrial training serves to give students the opportunity to understand more about the real
work environment. Students are given the opening to practice knowledge acquired during the
theoretical to the practical learning. Theory and practice are two different things that are
equally important to adapt.

Those are the importance of industrial training are:

i. Discipline the students to produce disciplined workers


ii. Students can practice real-life work situations in the future
iii. Students can practice safety regulations in industry
iv. Students can add experience in the field
v. Increase confidence by communicating with workers in the organization
vi. Students can identify problems and can solve problems arise.

12 | P a g e
CHAPTER 2

INDUSTRY BACKGROUND

2.1 Company Background

Figure 2.1: Johor Port Logo

13 | P a g e
Johor Port Berhad (Johor Port), a Member of MMC Group commenced operation in
1977 as the Southern Gateway Multi-Purpose Port in Malaysia and is also the first port in
Malaysia to be accorded with Free Zone status. Located at the southern tip of Peninsula
Malaysia, Johor Port is strategically positioned at the heart of the sprawling 8,000 acres
Pasir Gudang Industrial Estate and just across the Causeway from Singapore.

Figure 2.2: Johor Port

Johor Port operates a total area of 1,000 acres, 660 acres of which are designated as
Free Zone. With 24 berths and a total berthing length of 4.75 km, the services and
facilities within Johor Port include the Break Bulk Terminal, Dry Bulk Terminal, Liquid
Terminal, Container Terminal, Container Storage Yard, Inland Container Depot and
Warehousing Facilities. In addition, Johor Port is the appointed Free Zone Authority for
the management of its Free Zone area.

Johor Port is the largest palm oil terminal in the world and was designated as an
approved London Metal Exchange (LME) location in 2004. As one of the largest in the
region for the hubbing of Non-Ferrous Metals for clients such as Pacorini, Henry Bath
B.V. and Metro International, Johor Port is currently ranked No. 6 out of 35 in the world
for LME Cargo. Johor Port is also one of the largest discharging points for rice and cocoa
in Malaysia as well as being one of the biggest terminals in Malaysia for fertilizer and
cement. Multi-national clients at the Port include companies such as Shell, Chevron,
Holcim/LaFarge, BASF and FJB.

14 | P a g e
Figure 2.3: Johor Port layout plan

2.2 Johor Port Mission and Vision

Mission

“We are committed to providing customer-friendly solutions and cost-effective services to


our customers”

Vision

“To become the most efficient and integrated multi-purpose port in the region”

15 | P a g e
2.3 Johor Port Core Values

 Operative Efficiency
- Ensuring efficiency in running day-to-day operations in the port to guarantee
safety and ease for both employees and customers alike.
 People Involvement
- Making contributions and working collaboratively to accomplish organization's
goals by developing people and helping to improve the community.
 Uncompromising Integrity
- Upholding ethical standards, honesty and sincerity while demonstrating mutual
respect and trust for each other.
 Sustainable Development
- Aiming to meet every human need by preserving the environment to promote a
healthier and safer environment for both present and future generations.
 Customer Excellence
- Delivering commitments and dedicating our services to meet both external and
internal customer's expectations.

16 | P a g e
2.4 Johor Port Facilities

2.4.1 Container Terminal

 The Johor Port Container Terminal (JCT) hosts a total of 700m berthing length
which is designed to handle up to 1.2 million TEUs annually.
 Equipped with 8 Quay Cranes, 19 RTGs, 9 Stackers and 50 Prime Movers, the
Container Terminal can accommodate up to 3 vessels at any one time with
maximum depth of 13.5m.
 Equipped with a 250,000 m² of container yard and 11,000 m² CFS facilities
and supported by a web-based Johor Port Container Terminal System (JCTS)
which can facilitate real-time, integrated, paperless transactions for optimal
commercial and operational efficiency.
 Container Terminal also has its own dedicated rail depot with scheduled rail
services to PTP and as well as being linked to the national rail grid and
onward to neighbouring countries.
 JCT currently serves various international main line operators including
Pacific International Line, Wan Hai Lines, Evergreen Marine Corporation,
CTP Line, K Line Maritime, TS Line and MSC Shipping Corporation.

Figure 2.4: Container berth

17 | P a g e
Figure 2.5: Discharge operation

2.4.2 Bulk and Break Bulk Terminal

 Johor Port Bulk and Break Bulk Terminal (BBT) currently operate 8 berths
with maximum depth of 13.5m. The Bulk and Break Bulk Terminal currently
offers around 73,364 sqm of open yard area and over 230,000m² of storage
facility.
 It handles various cargoes of any type and size, including both edible and non-
edible dry bulk, break bulk, general cargo, project cargo, heavy lift and gas-
related cargoes. Equipped with 7 Shore Cranes, 23 forklifts, 3 conveyor belt
and rail-mounted quay cranes, the Bulk and Break Bulk Terminal’s operation
is supported by an on-line Multi-Purpose Terminal System (MPTS).

2.4.3 Liquid Terminal

 Johor Port Liquid Bulk Terminal provides specialised facilities to cater for
both edible liquid and petrochemicals cargoes and is equipped with a network
of pipelines with multiple high capacity loading arms to allow the liquid bulk
cargo to be piped directly to tank farms at high transfer rates.
 Johor Port is also the largest Edible Liquid Terminal in the world with
terminal tank farm capacity of almost 500,000 cubic metres.

18 | P a g e
Figure 2.6: Liquid Terminal

2.4.4 Warehouse Facilities

 Johor Port provides more than 2,000,000 sq ft of warehousing space and


approximately 600,000 sq ft open yard allocated for LME cargo and Break
Bulk cargo.
 In addition, there is also more than 300,000 sq ft of warehousing space for
value-added and distribution activities and more than 250,000 sq ft of
warehousing space for grain storage.

2.4.5 Johor Port Free Zone

 Johor Port is appointed as the Free Zone Authority and directly manages its
own Free Zone.
 The Johor Port Free Zone area covers about two-thirds of the port area,
providing ample space for companies wishing to engage in industrial and
commercial activities within a Free Zone environment

19 | P a g e
2.4.6 Offshore Inspection, Maintenance and Repairs (OIMR) Centre

 The OIMR Centre offers a comprehensive scope of services and facilities to


the Oil & Gas industries ranging from lay-up facilities, manpower
mobilization, maintenance and repair works as well as providing an integrated
suite of logistics solutions via its One Stop Centre

20 | P a g e
2.5 Johor Port Group Organizational Structure

21 | P a g e
2.6 Facility Development Department Organization Chart

22 | P a g e
2.6.1 Facility Development Department Responsible and Jurisdiction

Since Facility Development Department more incline to project development, the main
responsibilities can divide and describes as follow:

Civil Structure

 Wharf and Jetties


 Building (e.g: warehouse, operation building)
 Infrastructure (e.g: road, drainage, pipelines and operation terminal)

Mechanical and Electrical

 Sub-station and electrical power distribution system (e.g: switch gear,


generator set)
 Firefighting system
 Weight bridge
 Quick release hook
 Passenger and good lifts
 Sewage system
 Gas detector
 Container reefers

Administration and Contract Management

 Contract management / Agreement


 Standard operation procedure (SOP)
 Risk management
 Budget
 Human resources admin station
 Project reports / MCM / MMC, EXCO / BOD, etc

23 | P a g e
CHAPTER 3

TRAINING SCOPE

3.1 Introduction of Training

During my industrial training, I was exposed to the real working environment. I


learned a lot about the sciences related to the field what I learned and what I need to know
when I enter the workforce. I also learn how to manage a project form start until the end of
the project.

During my training session, I was attached at Facility Development Department


(FDD) in Civil Engineering section. This department are more focus on major engineering
project and Johor Port’s (JPB) implementation plan for infrastructure and facilities.

24 | P a g e
In addition, FDD also provide major services in engineering management and
consultation for support in Strategic Business Units (SBUs). This is to increase throughout
customer satisfaction, revenue and productivity.

3.2 Weekly Activity at Johor Port Berhad

Table 1: Weekly activity

Week Activity
Week 1  Induction program: -
 Briefing about Johor Port background, Safety Health and
Environment Awareness and Work Etiquette
 Site visit to ongoing project
 Tender No: JPB/46/2016 – Construction and Completion of
the rehabilitation of Jetty BT9, BT2, Wharf 5, Wharf 6 and
other associated work at Johor Port
 Learn and monitor on rehabilitation of wharf surface
 Join safety walkabout at BT2 and checking on
 Hazard
 House keeping
 Safety
 Handling on fire extinguisher
 Introduction of air supply for the diver

Week 2  Fender installation process


 Learn and monitor installation of fender
 Learn on how to identify of water tide and vessel schedules to
organize and plan fender installation work
 Know the basic terminology of vessel such as; bow (front), stark
board side (right), port side (left) and stern (back)

25 | P a g e
 Mooring line;
o Head line
o Spring line
o Stern line
 Learn on how the tugboat manuever vessel process
 Monitor the process of vessel anchored
 Bollard
 Learn the function of bollard, type and its capacity that it can
bear at one time
 Learn on how the installation process of bollard
 Learn on how the tender process by referring “Tender and Contact
Award Manual for Johor Port and Its Subsidiary” and “MMC Group
Procurement Policy”

Week 3  Learn the function of tender document and payment method claimed
by contractor.
 Learn on how to check the Work Programme with the Letter
of Acceptance
 Learn all the term in tender.
E.g: Defect Liability Period (DLP), Performance Security,
Extension of Time (EOT)
 Joined LOTO (Lock Out Tag Out System) – BT2
 Inspection work quality (eg: reinforcement, formwork, etc) at
Wharf 5 before the concreting work.
 Slump test process (eg: 20mm±30mm; pass)
 Cube test
 Identify the type and capacity of bollard existing on wharf 7,8,9,10
and 11.

Week 4  Make a list and classified type of bollard with capacity and type of
fender at every wharf mark for wharf 7,8,9,10 and 11.
 Site visit to BT3 and BT4 (Dangerous Cargo Jetty)
 Know the type and function of pipe depends on its colour.

26 | P a g e
 Know the function of emergency shower and how to use
 Site visit Zone 12C
 Monitoring the road construction and culvert installation
 Learn on work flow of procurement
 Divided by three section
i. Purchasing (Central Store) – up to RM15,000
ii. Quotation – RM15,001 to RM 100,000
iii. Tender – RM100,000 and above

Week 5  Explanation from Madam Asmariah about the Johor Port tender
process.
 Site diary – to record the progress of work, work site condition and
weather.
 Site visit warehouse 3E.
 Learn and monitor installation process of interlocking
 Slide preparation for tender briefing (JPB/27/2018) – Improvement
and repair existing interlocking pavement along Gate C and
Warehouse 6C and ancillary works in Johor Port.
 Site visit Zone 12C
 Monitoring the culvert installation and electric cable pipe

Week 6  Join Tender Briefing for (JPB/27/2018)


 Site visit – explanation to the contractor about the current
condition at site and location of the work site.
 Site visit to Rail Yard
 Site visit Wharf 8 and Wharf 9
 Checking on the fender condition
(before and after the vessel alongside)
 Site visit Warehouse 3E
 Checking on the progress of work of interlocking
 Site visit Wharf 4

27 | P a g e
 Learn and monitor on how the AGT (Authorised Gas Tester)
checking on the condition of pontoon surface after the fender
installation work finished.
 This is to ensure the surface are not affected due to the heat
penetration from the welding works.

Week 7  Differentiate between Repair Work Vs Maintenance


 Site Visit to Warehouse 12C (Bernas)
 Testing Generator set for preventive maintenance
 Went to M & R (Maintenance and Repair) - Workshop
 To check and charging batteries for Generator Set

Week 8  Preparing for slide presentation for Job Review and Book Review
 Site Visit to Warehouse 4FZ2
 Checking on damages on slab
– its happen due to overloading
 Job Review and Book Review Presentation at Human Resources
(HR) Department on 24th August 2018
 Preparing for final report draft

Week 9  Site visit to Warehouse JPL 2


 To identify defect and damages at the warehouse
o Loading ramp
o Steel grating
o Paving interlocking
o Elevation of ground (Ground Settlement)
o Platform failure due to heavy load
o Perimeter drain
 A visit from Dr Nurazuwa bt Mohd Noor
 Site visit to Warehouse Zone 12C (Bernas)
 Weekly preventive maintenance for Generator Set

28 | P a g e
 Joined Loto – BT2
 Vessel Name: MT Minerva Maya – Fuel Oil

Week 10  Safety Aweness – 10 Golden Rules S.H.E


 Site Visit Warehouse 12C (Bernas) – Genset Room
 Explanation from Mr Sofyan about the Fire Fighting devices
o Eg: Nozel – FM 200 (fire suppression)
o Fire curtain
o Heat detector
 Site Visit to Warehouse 3E
 Learn on the ventilation
o Natural – Lovers
o Mechanical – Exhaust fan, Blower and Air
conditioning
 Join Inspection Walkabout Warehouse 3E – Compartment 1 & 2
o Slab
o Column
o Finishing
o Painting
o Distribution box
o Cable
o Foldaway door
 Learn on fire fighting system at Warehouse 3E
 Tank – Pump house – Main Pipe

29 | P a g e
3.3 Standard Operating Procedure (SOP)

3.3.1 Project Management

Objective and Scope

This SOP is prepared to identify guidelines in executing activities related to project


planning and implementation in ensuring all steps / action are in-line with JPB
policies and advantageous to JPB as a whole.

This procedure shall apply to the following activities as follow:

i. Engineering project planning process including technical study, master


planning, approval, etc.
ii. Engineering project execution process including project implementation,
supervision, management, etc.
iii. Maintenance activity being carried after the project completion though-out
defect liability period in accordance to Contract Agreement.

30 | P a g e
Process Flow Diagram

a. Project, planning and Implementation

31 | P a g e
b. Defects during Defects Liability Period

32 | P a g e
c. Change Request (Variation)

33 | P a g e
d. Progress Payment

34 | P a g e
3.3.2 Document Management

Objective and Scope

This SOP is prepared to outline the document management practices within Facility
Development Department in order to achieve the following targets:

i. Ensuring all documents are properly managed and recorded for easy reference.
ii. Ensuring information delegation are properly attended and recorded in line
with JPB goals and objectives

This procedure applies to all administration activity relating to document control


including:

i. Letters and Memo


ii. Bills and Invoices
iii. Governing Certificates
iv. Job Order, Job Report, Checklist and Work Instruction
v. Quotations and tender documents
vi. Department files

35 | P a g e
Process Flow Diagram

36 | P a g e
3.4 Mode of Bidding Process

There are three (3) types of bidding process which are purchasing (central store),
quotation and tender. All this type is differentiate by the value of the of the price and
this process were handle by Procurement Department. Table below shows the value of
each type.

Table 2: Bidding type

Purchasing (Central Store) Value up to RM 15,000

Quotation RM 15,001 – RM 100,000

Tender RM 100,000 and more

During my internships period I more involved to tender type process. Tender is to


invite bids for a project, or to accept a formal offer such as takeover bid. Tender
usually refers to the process whereby governments and financial institutions invite
bids for large projects that must be submitted within a finite deadline. The term also
refers to the process whereby shareholders submit their shares or securities in
response to a takeover offer.

The following are tabulation of Johor Port Berhad tender cycle:

37 | P a g e
There are two volume of tender document which are:

Volume 1 – Technical component

i. Technical Proposals
ii. Company’s Profile
iii. Tender Deposit
iv. Audited Financial account

Volume 2 – Commercial compound

i. Commercial Proposal

38 | P a g e
3.5 Project Involvement

During my internship periods, I had been attached to Civil Engineering section which
is this section is divided into two part which are onshore and marine. Below is my
involvement project in Johor Port.

3.5.1 JPB / 46 / 2016 - CONSTRUCTION AND COMPLETION OF THE


REHABILITATION OF JETTY BT9, BT2, WHARF W5, W6 AND OTHER
ASSOCIATED WORKS AT JOHOR PORT

This project is more inclined to the construction and rehabilitation works of Jetty
BT9, BT2, Wharf 5 and Wharf 6 and other associate works at Johor Port, Pasir
Gudang for the purpose catering the operational needs. My involvement for this
project is more on learning and monitoring the process of the rehabilitation works at
the site work and learning on the documentation process for this project.

The scope of works for this project – as mentioned below:

BT9 – Protection and Repair Works

Figure 3.1: Layout of BT9

39 | P a g e
This is the scope of work on BT9 site:

1. Site surveying and cleaning


2. Install and weld semi-cylindrical pile
3. Install pile jacketing
4. Sand and concrete infill to pile
5. Rehabilitation of upper and lower column
- The rehabilitation of column/beams/stump is because of;
 Rebar is exposed or corroded
 Crack line or corrosion is present

The procedure rehabilitation of the column

i. Hack the concrete to expose steel bars and the corroded bar shall be
replaced with new bar of same size welded to existing non-rusting
portions of bar
ii. The replaced bars shall be fully covered by 2 coats approved
reinforcement corrosion protection coating
iii. Prior to the protection work with grout cover and coating the hacked-
out concrete shall be treated with bonding bridge and rehabilitated with
pressure grouted repair mortar
iv. Proper curing provided as it is the requirement of specification

Figure 3.2: Column hacking by contractor

40 | P a g e
Figure 3.3: Cleaning work – to remove barnacles

6. Rehabilitation of beam
7. Rehabilitation of deck and slab soffit
8. Rehabilitation of bollard

BT2 – Protection and Repair Works

Figure 3.4: Layout of BT2 (Repair work throughout BT2 jetty until the mooring
dolphin)

41 | P a g e
This is the scope of work on BT2 site:

1. Site surveying and cleaning


2. Install and weld semi-cylindrical pile
3. Install pipe jacketing
4. Sand and concrete infill to pile
5. Rehabilitation of beam
6. Rehabilitation of beam decks and slab soffit
7. Rehabilitation of bollard

Wharf 5 and Wharf 6 deck surface repair

Below the scope of work at Wharf 5 and Wharf 6:

Figure 3.5: Layout of Wharf 5 and Wharf 6

42 | P a g e
Figure 3.6: Location of wharf 5 and wharf

i. Removal of 100mm minimum thickness surfacing concrete and reconstruct


with G55 early strength of concrete levelled to fall drainage holes.

Figure 3.7: Hacked slab

43 | P a g e
ii. At spalled concrete area/steel reinforcement corroded area, remove existing
cast in situ concrete (approximately 260mm thick) to top of precast concrete
plank.
iii. Replace corroded rebars with new bars welded to non-rusting bars at both
ends. Reconstruct with G55 early strength concrete levelled to fall to drainage
hole.

Figure 3.8: Inspection of reinforcement and formwork


before the concreting process

44 | P a g e
Figure 3.9: Slump test with tolerance 200mm ± 30mm (pass)

Figure 3.10: Concreting works – concrete G55

iv. Cleaning of cable slot – clean out debris, dirt and all deposit.
v. Deck hole cleaning.

45 | P a g e
Wharf Marking

i. Supply and lay wharf marking using paint accordance to the requirement of
the specification and drawings.
ii. Wharf marking work carried out from berth BT9 to Wharf 11

Figure 3.11: Wharf mark

46 | P a g e
3.5.2 JPB/17/2017 – THE REPLACEMANT OF THE DAMAGED MARINE
FENDERS AT BBT WHARVES AND MAINTENANCE OF ALL MARINE
FENDER IN JOHOR PORT, PASIR GUDANG FOR JOHOR PORT
(the works)

This project is more inclined for the replacement of damaged fender at break bulk
terminal wharf and maintenance all fender in Johor Port, Pasir Gudang.

From this project, my involvement is more to monitor and learn on how the process of
fender installation by considering:

a) Wharf mark
b) Lot Vessel (Vessel Schedule)
c) Mooring line
d) Water tide

Fender is the main type of marine equipment to absorb kinetic energy from boats,
vessels and ships against the berthing structure, wharves or dock. It is to prevent
damage to vessel and berthing structure in mooring process.

There are many types of fender which have emerged over the years. Below is the type
of fender used:

 Arch fender
 Cylindrical fender
 W fender
 Cell fender
 Solid rubber fender

47 | P a g e
Fender Component

Frontal Panel
Rubber Cell

Chains, bolt and nut

48 | P a g e
Below figure shows the process of fender installation at wharf mark 305 Container
Terminal, Johor Port Berhad.

Figure 3.12: Process installation

Figure 3.13: Before the installation (frontal panel, rubber cell and anchorage come in
separately)

49 | P a g e
3.5.3. JPB/ 20/ 2016 (R) – CONSTRUCTION AND COMPLETION OF TWO
STOREY WAREHOUSE AND ALL ANCILLARY WORKS AT JOHOR
PORT FOR JOHOR PORT BERHAD

This project is more inclined to the development of new multi – storey warehouse
within the vicinity of Johor Port, for the purpose of catering the operational needs.

The scope of work for this project:


i. Construction of the two storey Warehouse 3E including all the founding
works, superstructure works and all ancillary works
ii. Construction of all M&E facilities required for all the commissioning of
the warehouse.
iii. Construction of all the supporting external infrastructure eg: sewers,
drains, water supply, hydrants, road, etc.
iv. Demolition of existing building and facilities

For this project, my involvement is more to inspection to the structure, the


mechanical and electrical facilities at the warehouse after all the construction
done.
Example item that need to be inspect before handover to the client are slab,
finishing, beam, distribution box, cable, firefighting system, elevators, lamp (lux),
and etc. This is to make sure there is no complaint from client after the handover
of the warehouse.

50 | P a g e
Figure 3.14: Slab inspection

Figure 3.15: Wall inspection – cracking line

Figure 3.16: Elevators testing

51 | P a g e
Figure 3.17: Foldaway door inspection

From this project, I had learned about the mechanical and electrical system such
as ventilation and firefighting system.

Ventilation System

– Ventilation is the process by which clean air (normally outdoor air) is


intentionally provided to a space and stale air is removed.

There are two type of ventilation system at Warehouse 3E


a) Natural
b) Mechanical

52 | P a g e
For ground floor of the warehouse, the ventilation system is mechanical and
natural are apply while for the first floor only natural ventilation.

Figure 3.18: Louvers

Figure 3.19: Blowers

53 | P a g e
Figure 3.20: Exhaust Fan

Firefighting system

- Installed in building to help fire fighter quickly attack the fire. Essentially, a
hydrant system is a water reticulation system used to transport water to limit the
amount hose that firefighters have to lay, thus speeding up the firefighting
process.

Water tank
(Water supply from Pump House Main pipe
SAJ)

Figure 3.21: Flow of the firefighting system

54 | P a g e
The flow of the system started from the firefighting water tank. The water supply
from SAJ to the tank. Next, water is transferred to the pump house and it will be
divided into three type of pump based on the pressure drop from the main pipe. The
three type of pump are sprinkler duty pump, supply pump and jockey pump. All this
pump gets power supply from TNB and if the TNB power supply shut down, these
pumps generates power by using diesel.

Figure 3.22: Pressure Meter

This pressure meter determine which pump will generate first. Firstly, sprinkler duty
pump will generate first. Then if the pressure drops the supply pump will generate and
lastly if the pressure keeps decreasing, the supply pump together with jockey pump.

55 | P a g e
Figure 3.23: Pump control switch

Figure 3.24: Pump

56 | P a g e
For Warehouse 3E, they use SPKA (Automatic Fire Alarm Monitoring Control
System). Purpose of this system is to detect a fire in its early stages, notify the person
in charge and Bomba via SMS. Person in charge will give a confirmation to Bomba if
there is a fire occurs. This system uses Celcom network.

Figure 3.25: Main Fire Alarm Panel and SPKA

57 | P a g e
Figure 3.26: Main Pipe

58 | P a g e
3.6 Safety in Johor Port

Safety induction is a compulsory requirement that all the project’s employees and
general workers must attend safety induction host by MMCES. Those attended the
induction shall be given an identity pass and apply permit to work which is nature of
work such as hot work, diving, confine space and other to allow them to work inside the
project are.

Tool box talk shall also be implemented on a daily or weekly basis in the morning
before commencement of the works. This session shall give an opportunity to remind the
workers and allow for effective communication in ensuring safety practices to be fully
adhered too.

Health, Safety, Security, Environment and Monitored (HHSE) officer shall check to
ensure that all the workers have Construction Industry Development Board (CIDB)
green card for working in the project and comply with CIDB’s requirements.
Arrangement will be made to bring trainer and facilities the issuance of green card to
those who don’t have one.

Safety is the most important aspect that need to be alert especially in working area.
Safety is a priority in Johor Port, every worker needs to be adhere to the rules and
regulations stated for their own safety, to keep the quality of works and to keep the save
environment.

59 | P a g e
Below are the 10 golden S.H.E rules in Johor Port.

1. Johor Port Berhad Permit.


 Johor Port entry permit must be worn at all time during presence in
Johor Port.

Figure 3.27: Sample of entry pass

2. Personal Protective Equipment (PPE)


 PPE as safety shoes, safety helmet, safety vest, long pant, shirt is
mandatory when entering Johor Port operation areas such as
warehouse, jetties, wharves and vessels.

60 | P a g e
Safety helmet with
chin straps

Safety Jackets/Vest
with reflector

Long Pants

Safety Shoes

Figure 3.28: Example of complete PPE

Figure 3.29: Life jackets and safety helmet


(for working at wharves and jetty area)

61 | P a g e
3. Speed.
 Speeding is prohibited in Johor Port. 15km/h (max) at operation areas
and 45 km/h (max) at non-operation areas.

4. Work safely with manners and report on any unsafe action and unsafe
condition to the superior or PSSD

5. Smoking is prohibited in Johor Port except at designated area.

6. PTW is mandatory for construction work including maintenance activities.

7. Clam and obey instructions from work leader or PSSD during any emergency.

62 | P a g e
8. Parking.
 Reverse parking is mandatory in Johor Port except for certain
locations.

Figure 3.30: Parking lot at Wisma Kontena

9. Apply 5S concept
 Maintain proper housekeeping at all time

Figure 3.31: 5S concept

10. Drug and alcohol abuse are prohibited in Johor Port.

63 | P a g e
CHAPTER 4

CONCLUSSION & SUGESSTION

4.1 Comments

After my training period at Johor Port Berhad, I got many valuable experiences as a
student in Degree level. Here I guided and mentored to a range of knowledge during the
training session. I also have opportunity to explore and experience to learn new thing in other
civil engineering field such as in marine field since I was attached under marine section in
FDD. I also involved in Mechanical and Electrical field during this training this to expose me
to other engineering field too.

64 | P a g e
A lot of experience I gain during this training especially on project management. Here
I learn about how the project process from the documentation process until the end of the
project. For my knowledge and added value, I also learn about vessel and marine term during
my training. After the training periods, I realize that civil engineering is the wide field that I
need to explore more and gain more experience to added in my knowledge and for my future
working experience.

4.2 Suggestions

My suggestion for Johor Port management soon for the internship program, industrial
training at Johor Port Berhad can be improved by carefully planning the training that will
give to students and also give student more task for them to give the experience to handle the
problem.

In addition, I can recommended to the company to provide more opportunities to


student from university or college to training in this company so from here student can gain
more knowledge in the Engineering field.

4.3 Conclusion

Over the past 10 weeks during my industrial training, I gained a lot of experience and
knowledge, for example:

i. Apply 5S
ii. Knowing on how the project process
iii. Learning the documentation process
iv. Enhance communication skills

65 | P a g e
v. Expose to real working wold (eg: attend meeting, briefing to the client)
vi. Understand the purpose of the project
vii. Carry out task and responsibility assigned by the organization
viii. Solve problem encountered

As I can conclude throughout my industrial training at Facility Development


Department, Johor Port. A lot of experience and knowledge that I gained in Civil Engineering
field. Besides, this organization has awarded to myself with a golden opportunity of gaining
valuable knowledge (particularly theoretical) and experience in real working wold upon
completion of my studies.

Industrial training is the good exercise to student for encourage them towards
excellence and developing countries. Via this training I managed to explore and learn new
things such as handling equipment, involved in engineering drawing/plan, improving
communication skill through teamwork, and all this would be credit and plus point to
becoming a good employer.

66 | P a g e
CHAPTER 5

APPENDIX

67 | P a g e

You might also like