1-Sep-2018 Chemical Building Pipe treanch wall inner side 1st lift Grid (3-5)
Column concrete at Gellery H/11, H/12, H/13,
1-Sep-2018 RSF H/14, H/15
1-Sep-2018 Filter Annex Column concrete at
2-Sep-2018 Chemical Building Pipe treanch wall outer side 1st lift Grid (3-5)
8-Sep-2018 RSF Wall 3 Grid (D-E) 1st lift and Column B/3, B/8
12-Sep-2018 Chemical Building Screed concrete at floor slab at Grid (A-C)/(1-2) 1.6
12-Sep-2018 RSF Wall 12 with slope slab Grid (D-E) 2nd lift
14-Sep-2018 Chemical Building Screed concrete for tank Grid (1-3) 4.5
Centrifuge Building Column shaft 1st lift concrete at B1, C1, D1, E1,
22-Sep-2018 & E2
22-Sep-2018 Electrical Room-931 Plum concrete for footing at C5 & D5 2
23-Sep-2018
18 345.2
188
1.5
3.5
16.75
0.25
2.8
1.5
7.75
0.5
10.7
0.3
2
6.5
3.25
1.75
0.75
47
35
164
8.5
1.5
7.1
2
7.25
1.75
4.5
4.25
0.75
0.2
335
24.1
2.3
6.75
4.5
0.5
13.5
14
9
7.5
5.5
5.5
2.5
4.5
4.5
16
219
2.5
1.25
0.1
9
41.7 0 1384.4
Grade 35A
8418.545 CUM
For the September
Grade 15 Grade 20 Grade 25 Grade 30 Grade 35A TOTAL
18 345.2 41.7 0 1384.4 1789.3 CUM
Grand Total
Grade 15 Grade 20 Grade 25 Grade 30 Grade 35A
72.45 3734.15 210.15 285.9 4115.895 8418.545 CUM