JSW Steel – Group Companies
2
JSW : Process – Raw materials to finished steel
Non - coking coal
mp ore Iron ore Coking coal Fluxes
Lump orre
Lum
Pelletization
Sintering LCP
HMDS
3
HOT METAL STEEL
JSW Steel Products
4
Industrial management system
Entire Integrated Steel Operation certified
BENEFITS DERIVED:
DERIVED
¾Consistent quality and quantity of water .
¾Continuous improvements in quality.
¾Lower Operational & Maintenance costs.
¾Reliability of water for critical systems.
5
Water from Tunga Bhadra Reservoir (32 MGD)
2 Gas
2. G cleaning
l i & Fume
F flushing
fl hi
8
Water usage – Company “Policy”
1 Efficient use of available water
1.
Reduction of evaporation rate
• Maximize use of alternate sources rain water &
seepage.
• Reduction of fresh water in closed circuits by
higher COC.
• Reverse osmosis plant for recovering good
quality water.
2 Zero
2. Z Discharge
Di h
Cascading usage of water
• Use of blow down of one process
as make up water in other processes.
• Equalization of final blow down water quality
and its use in less critical applications.
pp
• Treated sewage for gardening.
9
Efficient Use of water
GCP
4.Consumptive Blow Down
use 3.
DCW
Blow Down
ft
11
Water Cascading – Corex Plant
Corex –DM
Water Circuit
Corex –ICW
C ICW Corex –Slurry
Water Circuit to PP
Blow down to
Ore
Beneficiation SLIME POND
12
Waste water discharge – ‘zero’
13
Water conservation – ‘total involvement’
Employee involvement A
Awareness
¾Water Help-Desk:
Help Desk: Call
Call-33457.
33457
¾Attend 15-20 calls per day.
¾Action taken within 6 hours. 14
Water – “Suggestion mela”
15
Water - MIS
Monitoringg system
y
Consumption:
¾Flow meters at TOP of Shops:165 Nos.
¾Daily readings at Production shops & Hourly reading readings at FFPHs.
Quality:
¾Hourly analysis of Raw water & Drinking water.
¾M hl water analysis
¾Monthly l i by
b externall chemical
h i l laboratories.
l b i
Reporting system
Reports:
¾Daily water consumption report (Enclosure3.xls).
¾Monthly water report (Enclosure-5.xls)
¾Monthly water cost (report)
Review:
¾Water consumption
p review in Daily
y HOD meeting.g
¾Weekly water conservation meeting (Enclosure4.xls).
¾DQEC meeting (MOM-May 2008.doc).
16
Specific water consumption
18
B. Cascading use of Water.
Invest.
Year of Annual Water Made Payback
Title of Water Saving
Sl No Implement Savings Period
project implemented
ation 3 (Months)
m Rs. Rs.
Lakhs Lakhs Lakhs
Utilization of blow down of
a GCP water of Corex, BF 1&2 2007-2008 7.58 3.79 10 32
for make up in ore
beneficiation plant
Conversion of open circuit ID
b fan cooling to closed circuit 2007-2008 2.73 13.65 15 14
cooling
Utilization of blow down water
c from CPP-2 for coke 2007-2008 6.57 32.85 6 3
quenching in to Coke oven-1,2
Collection of seepage water
d from MSDS cable tunnel and 2007-2008 4.97 24.82 10 5
use in scale pit, of BOF.
Recycling
R li off blow
bl down
d water
t
e 2007-2008 2.6 13 50 46
to slag quenching at BOF-CCP
19
Water usage - analysis
Cement Plant
LCP
Boilers
RMHS
Corex-1
utiltities
Sinter plant I
(25 TPH)
Pellet Plant & Corex-2 HSM FFPH
Benification BOC-1
plant.
BF-1 CPP-2 JSWEL
Corex
Coke Ovens I
& II
FFPH
FFPH.
BF-2
CRM BF-2 FFPH
CPP-1
JPOCL
HSM
Cokeoven
SMS-1
FFPH
Chart-1,4 MT Production units Chart-2, Fire fighting pump houses Chart-3, Power Plants
Turbidity Chart
Boilers utiltities
Water to
(80 TPH) Shankar Gudda
colony IST steel plant 12 NTU
WRM
New batching
SMS-2 VV Nagar
plant
T u r b i d i ty
Coke Ovens III Vaddu village 7 NTU
Crushing plant
Water supplied
to Township 7 MTPA Labour
Hort. Colony/Drinking
water For BF-3.
Water from
BF-3 Drinking water
Sinter plant II RWP to Lake
supplied to O NTU
Water to plant.
overhead tank
Hour
in Vidyanagar.
21
Evaloc is being mixed with water Solution is poured into a container
Water Consum ption - March 2007 Water Consumption - March 2008
Evaporation loss
17% Evaporation loss
13%
Others
Others
5%
4%
JSW
56% Ancillary units JSW
Ancillary units
20% 57%
19%
2.5
E vap o ratio n rate in cm
0
Jan Feb Mar Apr May June July Aug Sep
Month
Without Evaloc With Evaloc
23
Conservation projects - highlights
B Re use of seepage water & blow down water .
B.
24
¾ Cable Tunnel water is measured using
g Electromagnetic
g flow meter.
¾ Cable tunnel water is being pumped to consumer units.
¾About 150 to 200 m3/day water is being saved.
25
Conservation projects - highlights
C Use of Guard pond water .
C.
¾ Capacity
p y of Each Guard ppond is 55,000
, m3 .
¾There are two separate Guard ponds for 4 MT & 7 MT Stage.
26
Guard pond pipeline network
To 7MT ore
Beneficiation
plant
pump house
7 MT Guard
(1w+1s)
pond II Storage
Q= 300m3/hr
cap. 55000m3
o 7MT GP
s water
h ti lt
horticulture
Excess
30 m3/hr Plant
2.
Horticulture 20
m3/hr
300 m3 Vidya Nagar
200 m3 township /Air
port
Horticulture
Pump house (1w+1s) 2nd Boosting 50m3/hr
cap Q=250m3/hr
Each cap. 1st Boosting
g
station at station
t ti att
H=70mtr Air strip
RM Gate
Guard pond I
Storage cap.
25000 m3
27