Professional Documents
Culture Documents
A. GENERAL
Mechanical units are commonly placed upon the roofs of buildings and are referred
to as ROOF TOP UNITS (RTU). These units are often supported on the building
roof by a metal roof curb which is in turn supported by:
• Curb sub-framing
• Framed opening
• Structural primary and secondary members.
• Magnitude of Loads: Determine the maximum loads of the RTU. The RTU loads is to
be devided by the number of supports. The support load is the load that will be applied
to the individual WBTP membersThe loads from a RTU do not normally include the
weight of the roof curb. This roof curb load will also need to be determined and added
to the toal design loads.
• RTU Footprint: The location and size of the RTU are critical. So the exact dimensions
of the unit and the direction of those dimensions are required. The locations of these
dimentions and whether the unit penetrates below the roof surface will have a major
impact on the design.
• Type and Number of Supports: Determine the type, locations, support loads and
number of supports for the RTU unit.
Compare the RTU loads to the WBTP allowable load groups listed below to
determine the next course of action. (The RTU loads are the individual loads
actually applied to each WBTP and all loads must be reported to the VP
Building designers.)
• Loads < 50 lbs may be located anywhere along the chord without additional vertical
web members.
• Loads > 50 lbs < 500 lbs must be located within 6” of a panel point or a vertical web
member. Otherwise, vertical web members can be field added per the Standard
Erection Details.
• Loads > 500 lbs must be reported so that special provisions for their support can be
included in the design and detail of the WideBay members.
In some situations, the RTU loads are minor and can be supported using a support
beam with short columns (NBVP) that can be located on the top of WBTP chords.
0.25” plate
5/16”
Holes
RTU Footprint
• Provide additional WBTPs under the RTU footprint to reduce the applied RTU
load to each WBTP. These WBTPs can be added in VPCommand to have them
properly designed and detailed.
In the actual design of WBTPs for RTU units, consider the possible lateral in-plane
loads from snow build-up and overturning from the wind and seismic loading.
On some buildings, the exact location of the RTUs can not be determined. When
that occurs, a loading zone will need to be determined and all WBTPs in that
loading zone will be designed with the worst case load application in that zone.
This method is not preferred, it is not cost efficient because of the overall
higher cost to design WBTPs for loads that may not be applied. The location and
size of the loading zone must be shown on the erection drawings.
o These header assemblies, will carry the RTU loads as well as the reactions
from any WBTPs required be cut out of the roof penetration area.
o The headers can be supported on the WBTPs if the loaded WBTPs can carry
the loads.
• The WBTPs adjacent to the framed opening will not be automatically designed
or detailed in VPCommand, unless the following steps are taken:
• Use the VP Command workaround procedure.
• Deduct the full length WBTPs that will be replaced.
• Determine the WBTP lengths on either side of the framed opening. The
program will identify the WBTPLeft and WBTPRight .
• If the lengths are over 11’-0”, a WBTP can be designed and detailed in
VPCommand as explained in the VP Command work around procedure.
WBTP Left
WBTP Right
• This different panel spacing in the individual WBTPs will create a problem
when sprinkler lines and ductwork go through this area.
• Because the minimum WBTP length is a factor of the WBTP depth, if a
specific depth must be held, the minimum WBTP length will be as shown in
the following table.
WideBay Depth
18 20 22 24 26 28 30 32 34 36 38 40
Minimum Bay Spacing 11’ 12’ 13’ 14’ 15’ 16’ 17’ 18’ 19’ 20’ 21’ 22’
• When the WBTPs must be supplied with lengths less than 11’-0” (Minimum
WBTP length limit for 18” depth), a WideBay Replacement member must be
made as shown below.
• These WideBay Replacement members consist of a chord member with two
WBTP seats and will be supplied with the WBTPs. The chord member sizing
criteria is in the MEMBER AND CONNECTION DESIGN section later in this
document.
Bay E .
Interior Bay 0”
End Bay 4 ½”
End Bay 10 ¼”
Maximum Length = 11’-0”
E
Figure 8 WideBay Replacement
WBTP Left
WBTP Right
Support
Headers
• The framed opening will included support header assemblies which will impose
concentrated loads on the adjacent WBTP members supporting loads. The
support header assembly carries the loads of the RTUs as well as the seat loads
from any WBTPs required adjacent to the roof penetration area.
o A support header assembly is similar to the following detail. It will consist of
a header beam, with two header clips welded to the beam
5”
o The header assembly’s use will be limited by the adjacent WBTPs load
carrying capacity to carry the RTU and WBTP seat loads from the support
header with the header clip (WBHC1) assembly.
o Header assemblies are to be used on both sides of the framed openings.
o The design of this assembly is discussed in the MEMBER AND
CONNECTION DESIGN section later in this document
o The following detail shows an in-place assembly for this support header
assembly shown follows.
o If the opening penetration is less than 2 support spacing wide, two more
WideBay Replacement members can be used to frame the smaller opening.
Figure 13
• The use of double WBTPs can be done when a single WBTP is not able to carry
the header loads.
o When double WBTPs are required, add a WBTP 5” from the adjacent
existing WBTP on the Supports screen in the Spaces folder in the Secondary
Folder in VPCommand.
o To apply the RTU loads in VPCommand, split the RTU load and apply the
reduced load to each WBTP in the double WBTP condition.
• Structural beams spanning between the main frames are used when:
When the RTU Extends Below the Roof Line and the Support
Header Loads Can Not Be Supported By The WBTPs
Support Beams
WBTP Left
WBTP Right
Support
Headers
Support Beams
o If only one side header assembly can be used but the other side header
requires a support beam off the main framing, use the support beams for both
headers.
o The total applied RTU loads and the WBTP seat reaction loads exceed the
load carrying capacity of the adjacent WBTPs.
o The total header clip load exceeds the header clip capacity.
o This framing system is used when a larger number of WBTPs are cut in
length or when the adjacent WBTP members are too heavily loaded to be
able to support the additional loads.
o The 3-plate beams are laterally braced on one side to the WideBay bridging
system in the adjacent WBTP as shown in the following detail.
Bay E .
Interior Bay 0”
End Bay 4 ½”
End Bay 10 ¼”
Maximum Length = 11’-0”
E
Figure 18 WideBay Replacement
2.33” 2.33”
For Example:
10” Wide by 0.25” thick. (Single WBTP) 50ksi
Mallow = (b t2/6 )(.75 Fy) = 3.91 kip-in
Mallow = (2.33”)( Pallow)
Pallow = Mallow /2.33 =3.91 /2.33
Pallow = 1.67 kips
o Check the weld holding the 3-plate beam on the header clip.
Weld capacity = 0.928 x (Length of Weld on the web)x(Weld Fillet in 16ths )
Length of weld = (18”) one side Weld
Weld Fillet = 3/16”
Weld capacity = 0.928 x (18) x (3 ) = 50 kips < 3.35 kips OK
o Because these header clips will have to be attached to WBTP top chords,
they will have 5/16” holes shop drilled in them for a screw attachment of the
header clip to the WBTP chord. (No field welding is allowed with the
WBTPs.)
o The following charts show the possible header clip loads from loading
combinations on the header assemblies from the possible seat reaction on
the header assembly in the previous chart (Spacing is assumed to be 5’-0”
on center.
The following tables give the beam capacities for different point loads
- Load on Header Clip = 1/2 x Sum of Seat Reactions
- Beam size is based upon the maximum header clip capacity for a beam of
that length with the number of reactions described.
10" Wide header Clip 6” by 0.1875” 20" Wide Header Clip 6” by 0.3125”
6” by 0 .1875” 6” by 0.3125”
5” by 0.1875” 6” by 0.25”
6” by 0.25”
H. BRIDGING:
• When the RTU does not extend into the building and is above the roofline, extra
diagonal bridging should be used to stabilize the RTU area when the RTU
weight exceeds 1000 lbs.
• When the RTU extends into the building and prevents the installation of the
WBTP bridging rows, the bridging members have to be properly anchored on
either side of the RTU. When sub-framing WBTPs and a framed opening are
used, consideration is required to properly support and anchor the bridging
members.
No Bridging
required for
WRM_ parts
• When support beams are used, the beams can be laterally braced to the
adjacent WBTP members using diagonal bridging. This bridging is to be located
at the WBTP bridging runs as shown in the following drawing.
No Bridging
required for
WRM_ parts
• No bridging will be required when the WideBay Replacement members are used.