Annex- I

RENOVATION, MODERNISATION & UPRATING OF


HYDRO ELECTRIC POWER PROJECTS

BACKGROUND

For optimization of resources and to tide over the shortage of electricity in the country, Renovation &
Modernisation, Uprating and Life Extension (RMU&LE) of the existing old hydro electric power
projects is considered a cost effective option to ensure efficiency, better availability and also to
augment capacity addition

VIII Plan to XII Plan

The R&M works at 103 (21 in Central and 82 in State Sector) hydro projects (13 upto the VIII Plan,
20 in the IX Plan, 32 in the X Plan, 18 in the XI Plan & 21 in the XII Plan) with an aggregate installed
capacity of 19472 MW have been completed by the end of the XII Plan (i.e by 31 st March 2017). A
benefit of 3635 MW through Life Extension, Uprating and Restoration has been accrued.

During the XII Plan, 21 schemes (2 in central sector & 19 in state sector) with an installed capacity
of 4150 MW have been completed till March, 2017 and accrued a benefit of 549 MW through Life
Extension, Uprating and Restoration.

Programmed for 2017-22

During 2017-22, an aggregate capacity of 9239.80 MW at 49 Hydro Electric Power Station (7 in


Central Sector and 42 in State Sector) is programmed for R&M which will accrue benefit of about
4755.35 MW through Life Extension, Uprating and Restoration. Out of the 49 schemes expected
for completion during 2017-22, 2 schemes in Central Sector with an aggregate capacity of about
213.4 MW have been completed till December, 2017 and have accrued a benefit of 48.4 MW
through Life Extension.

Programmed for 2022-27

During 2022-27, an aggregate capacity of 1956 MW at 17 Hydro Electric Power Station (1 in


Central Sector and 16 in State Sector) is programmed for R&M.
Summary of R&M of Hydro Electric Projects
(As on 31.12.2017)
I Hydro R&M schemes completed up to XII Plan

Sl. Plan Period No. of Projects Installed Actual Benefit


No. Capacity Expenditure (MW)
Central State Total (MW) (Rs. in Crs)
Sector Sector
1. VIII Plan 2 11 13 1282.00 127.37 429.00
Schemes [39.00(U) +
completed 336.00
(Res.)
+54.00(LE)]
2. IX Plan 8 12 20 4892.10 570.16 1093.03
Schemes [339.00(U) +
completed 331.03(Res.) +
423.00(LE)]
3. X \Plan 5 27 32 4336.60 1029.24 829.08
Schemes [123.40(U) +
completed 701.25 (LE) +
4.43(Res.)]
4. XI Plan 4 14 18 5841.20 294.84 735
Schemes [12 (U) +
completed 15 (Res.) +
708 (LE)]
5. XII Plan 2 19 21 4149.60 1116 549.40
Schemes [58 (U)+
completed 476.40
(LE)+15(Res.)]

II Hydro R&M schemes Programmed for completion during 2017-22

Sl. Category No. of Projects Capacity Estimated Cost Benefit


No. (MW) (Rs. in Crs.) (MW)
Central State Total covered
Sector Sector under
R&M
1. Programmed 7 42 49 9239.8 6415.65 4755.35
[149.7(U) +
4605.65(LE)]

2. Under 3 21 24 4691.10 3012.80 2111.50


Implementation [116.20 (U)+
1995.30 (LE)]

3. Under Tendering 1 14 15 2624.10 2322.28 878.25


[27.5 (U) +
850.75 (LE)]
4. Under DPR 1 7 8 1711.20 1046.51 1717.20
Preparation/Finalis [6 (U) +
ation/Approval 1711.20 (LE)]

5. Completed 2 0 2 213.4 25.34 48.4 (LE)


(Actual Cost)

Abbreviations:
MW – Mega Watt;
Res. – Restoration;
U – Uprating;
LE – Life Extension

III Hydro R&M schemes Programmed for completion beyond 2022

Sl. Category No. of Projects Capacity Estimated Benefit


No. (MW) Cost (MW)
Central State Total covered (Rs. in Crs.)
Sector Sector under
R&M
1. Programmed 1 16 17 1956 1120.50 752
[31(U) +
721(LE)]

2. Under Tendering 0 1 1 36 67.05 42


[6 (U) +
36 (LE))

3. Under DPR 1 5 6 685 1053.50 710


Preparation/Finalis [25(U) + 685
ation/Approval (LE)]

4. Under RLA Studies - 10 10 1235.00 - -

Abbreviations:
MW – Mega Watt;
Res. – Restoration;
U – Uprating;
LE – Life Extension
The Projects for which design & engineering services are rendered by HE&RM Division during
2017-18 are as given below: -

S.No Project State/Executing Agency Capacity


(MW/MVA)
Northern Region
1. Lakhwar MPP Uttarakhand / UJVNL 3x100
Neighbouring Countries
2. Punatsangchhu St.I Bhutan/ PHPA-I 6x200
3. Punatsangchhu St.II Bhutan/ PHPA-II 6x170
4. 400 kV Jigmeling Bhutan/ BPC 500 MVA*
Substation
Total 2520MW/
500MVA
*500 MVA capacity is a 400 kV GIS substation and not a Hydro Power Station.