FOUNDTEST
INDEX
1.0 Introduction 1
2.0 Dynamic Pile Testing Equipment 2
3.0 Dynamic Load Test Preparation 2
4.0 Testing Procedures 3
5.0 Result Interpretation and Analysis 5
6.0 Final Reporting 6
FOUNDTEST (M) SDN BHD (647755-P)
1.0 Introduction
Dynamic pile testing technology had been introduced to the industry for more
than 30 years. This time and cost saving method of pile testing has been eventually
getting popular and is widely recognized nowadays. The American Society of Testing
and Materials has developed a standard (ASTM:D4945) for the performance of dynamic
load test. It is a very cost-efficient tool used to replace the time consuming conventional
static load test in determination of pile capacity.
1
FOUNDTEST (M) SDN BHD (647755-P)
High strain dynamic pile testing is perform by using PDI-PAX 8 series pile
driving analyzer and CAPWAP analysis program to determine the mobilized
capacity of a test pile.
PAX-8 series include:-
- Pile driving analyzer
- 2 strain transducers
- 2 accelerometers
- 1-4 cable
- 20m extension cable
The combination of the calibrated sensors and the latest analysis program
provides a high accuracy and reliable test results.
- Pile head must been explore at approximately 0.5m from the ground level. It
is to ensure that it has sufficient spacing to allocate the sensors and to avoid
any obstruction endangering the sensors or cable during testing (figure 1).
- An appropriate piling hammer is required for testing purpose until the final
result is obtained.
2
FOUNDTEST (M) SDN BHD (647755-P)
Figure 1 Figure 2
- Two strain transducers and two accelerometers will then attach on both sides
of the pile during initial driving or restrike testing (Figure 2). Stress wave
generated by hammer impact on pile top will be recorded in terms of force
(detect by transducers) and acceleration (detect by accelerometers).
3
FOUNDTEST (M) SDN BHD (647755-P)
R= HW x HDR x HEFF
SET + COMPt/2
- The signal captured will be presented in a graph as force curve and velocity
curve and is stored in the pile driving analyzer for later analysis purpose
(Figure 3).
Figure 3
4
FOUNDTEST (M) SDN BHD (647755-P)
By computation from the pile driving analyzer on force and velocity curve
recorded, a lot of useful information can be provided on site as preliminary results.
These results include:
- Pile capacity at the time of testing by CASE method. (RMX)
o Capacity predicted by assuming appropriate soil damping factor (Jc),
young modulus (Em) and wave speed (Ws).
5
FOUNDTEST (M) SDN BHD (647755-P)
The testing firm shall provide a full engineering report on the pile integrity test
performed, normally within ten days upon the completion of testing. The report
shall include the following:
- Project title
- Date of testing
- Report number
- Pile reference number or location
- Date of pile installation
- Pile size
- Total pile length at the time of testing
- Driven penetration at the time of testing
- Length below gauges
- Pile make up
- Working load and test load of pile
- Hammer type, weight and observed drop height at the time of testing
- Pile capacity by CASE method at the time of testing
- Pile integrity and location of damage (if any)
- Force and velocity vs. time curves
- Force and velocity matched curves
- Resistance distribution along the pile shaft and end bearing at the pile toe
- Estimated pile head settlement at working load and test load
- Field sheet with signature of test personnel and witness(es)
6
FOUNDTEST (M) SDN BHD (647755-P)
APPENDIX 1
7
FOUNDTEST (M) SDN BHD (647755-P)
Drop Hammer
Cushion
Test Pile
500mm
8
FOUNDTEST (M) SDN BHD (647755-P)
9
FOUNDTEST (M) SDN BHD (647755-P)
10
FOUNDTEST (M) SDN BHD (647755-P)
11
FOUNDTEST (M) SDN BHD (647755-P)
12
FOUNDTEST (M) SDN BHD (647755-P)
13
FOUNDTEST (M) SDN BHD (647755-P)
14