Architectural Work Sequence

1 2 3 4 5
BLOCKWALL DOOR FRAME AGW MEP CONCEAL
Setting Out Setting out Setting Out CONDUIT WALL PLASTER & PAINT
Inspection Reference Line Marking Reference Line Marking Setting out Surface preparation
DPC Laying Installation Frame Installation Frame Hacking Plaster Level Peg
Block Laying Grouting Inspection Conduit Installation Inspection
Lintol & Stiffener Inspection routing & water repellent Conceal Plastering Works
Inspection Installation Glass Inspection Inspection
Inspection
Protection

11 12 13 14 15
CEILING OFF-FORM CEILING MEP HORIZONTAL SMOKE CURTAIN ROLLER SHUTTER
PAINT FIBROUS GYPSUM Electrical Wiring
Surface Preparation Setting Out Aircond Ducting
Base Coat Ceiling Grid
Final Coat Installing Ceiling Board
Inpection Installing Stainless Steel
strip
Inspection

21 22
MEP FINAL FIX TESTING &
Installing M&E Equip. COMMISIONING
Inspection

TOILET
1 2 3 4 5
BLOCKWALL DOOR FRAME MEP CONCEAL WATERPROOFING FLOOR SCREEDING
Setting Out Setting out CONDUIT Surface Preparation Surface preparation
Inspection Reference Line Marking Setting out Angle Fillet Level pegs
DPC Laying Installation Frame Hacking Apply Waterproofing Screeding
Block Laying Grouting Conduit Installation Ponding Test Inspection
Lintol & Stiffener Inspection Conceal Inspection
Inspection Inspection Protection Screed

11 12 13 14 15
COUNTER TOP SANITARY FITTING DOOR PANEL PAINTING MEP FINAL FIX
Setting Out Basin INSTALLATION Surface Preparation Installing M&E Equip.
Installing Counter Top WC Installing Door Panel Base coat Inspection
Inspection Floor Trap Installing Iron Mongery Final Coat
Bidet Inspection Inspection
Water Tap

STAIRCASE

1 2 3 4 5
BLOCKWALL DOOR FRAME MEP CONCEAL WALL PLASTER & PAINT CEILING SKIMCOAT
Setting Out Setting out CONDUIT Surface preparation Surface Preparation
Inspection Reference Line Marking Setting out Plaster Level Peg Base Coat
DPC Laying Installation Frame Hacking Inspection Final Coat
Block Laying Grouting Conduit Installation Plastering Works Inspection
Lintol & Stiffener Inspection Conceal Inspection
Inspection Inspection
PAINTING MEP FINAL FIX TESTING &
Surface Preparation Installing M&E Equip. COMMISIONING
Base coat Inspection
Final Coat
Inspection
6 7 8 9 10
WATERPROOFING SKIMCOAT WALL CERAMIC TILES WALL GRANITE CEILING SKIMCOAT
Surface Preparation Surface Preparation Setting Out Setting out PAINT
Angle Fillet Base Coat Laying Tiles Laying Granite Surface Preparation
Apply Waterproofing Final Coat Grouting Grouting Base Coat
Ponding Test Inspection Inspection Final Coat
Inspection Inspection
Protection Screed

16 17 18 19 20
FLOOR BASE CONCRETE FLOOR SCREEDING FLOOR HOMO. TILES DOOR PANEL PAINTING
Surface preparation Setting Out INSTALLATION Surface Preparation
Level pegs Laying Tiles Installing Door Panel Base coat
Screeding Skirting Installing Iron Mongery Final Coat
Inspection Grouting Inspection Inspection
6 7 8 9 10
WALL CERAMIC TILES FLOOR HOMO. TILES MEP HORIZONTALCEILING FIBROUS GYPSUM TOILET CUBICLE
Setting Out Setting Out Piping WATER RESISTANT Setting Out
Laying Tiles Laying Tiles Electrical Wiring & Setting Out Installing toilet cubicle
Grouting Skirting Fitting Ceiling Grid Inspection
Grouting Inspection Install Ceiling Board
Inspection

16
TESTING &
COMMISIONING

6 7 8 9 10
STEEL HANDRAIL FLOOR NOSING TILES FLOOR SCREEDING FLOOR HOMO. TILES DOOR PANEL
Setting Out Setting Out Surface preparation (STAIRCASE LOBBY) INSTALLATION
Installing Handrail Installing Nosing Tiles Level pegs Setting Out Installing Door Panel
Inspection Screeding Tiles laying Installing Iron Mongery
Trowel Finish(staircase) Skirting Inspection
Inspection Grouting
Inspection