DOC Description Date to Date from Duration Status
Trade Rev # Consult. Consult. D1 D2 APP ANN Resubmit Rejected

MAR M001 UPVC PIPES 0 10/28/2017 11/9/2017 12 X

M002 Pressure PVC pipes PN 10 0 10/28/2017 11/9/2017 12 X

M003 Drainage fittings and accessories 0 10/28/2017 11/9/2017 12 X

M004 Galvanized steel and black steel accessories 0 10/28/2017 11/9/2017 12 X

M005 Supports and anchors 0 10/28/2017 11/9/2017 12 X


M005 Supports and anchors 1 11/15/2017 12/5/2017 20 X

M006 Black Steel Pipe 0 10/28/2017 11/9/2017 12 X

M007 Galvanized Steel Pipe 0 10/28/2017 11/9/2017 12 X

M008 PPR Pipes 0 10/28/2017 11/9/2017 12 X


M008 PPR Pipes 1 11/15/2017 12/5/2017 20 X

M009 Hot Water Tank 0 10/28/2017 11/9/2017 12 X


M009 Hot Water Tank 1 11/15/2017 12/5/2017 20 X

M010 PVC pressure Fittings 0 11/15/2017 12/5/2017 20 X

M011 Two Hour Fire Rated Insulation Section (15890) 0 11/15/2017 12/5/2017 20 X

M012 Roof Vent Cap 0 11/15/2017 12/5/2017 20 X

M013 Solvent, Adhesive and Cleaner 0 11/15/2017 12/5/2017 20 X

M014 Galvanized Seamless Pipe 0 11/29/2017 12/12/2017 13 X

M015 VALVES 0 11/29/2017 12/12/2017 13 X

M016 GROOVED FITTINGS 0 11/29/2017 12/12/2017 13 X

M017 DOUBLE SEAL MANHOLE COVER 0 12/9/2017 12/22/2017 13 X

M018 GUTTER 0 12/9/2017 12/22/2017 13 X


Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING

Document
Material Submittal [MAR]-"E" ELECTRICAL
Updated 10/7/2018
DOC Description Date to Date from Duration Status
Trade Rev # Consult. Consult. D1 D2 APP ANN Resubmit Rejected

MAR E001 Wires and Cables - Liban Cable 0 10/28/2017 11/9/2017 12 X

E002 Disconnect Switch - Katco 0 10/28/2017 11/9/2017 12 X

E003 PVC Conduits - Decoduct 0 10/28/2017 11/9/2017 12 X

E004 Polyethylene Conduits - Machco 0 10/28/2017 11/9/2017 12 X

E005 Fire Alarm Cable-Ramcro 0 10/28/2017 11/9/2017 12 X

E006 Earthing & Lightning - Wallis/France Paratonnerres 0 10/28/2017 11/9/2017 12 X

E007 Wall Boxes - Beticino 0 10/28/2017 11/9/2017 12 X

E008 Cable Tray - Fimi 0 10/28/2017 11/9/2017 12 X

E009 Data Cable - Le Grand 0 10/28/2017 11/9/2017 12 X


E009 Data Cable - Le Grand 1 11/29/2017 12/5/2017 6 X

E010 Wiring Devices - Arteor (White) 0 11/29/2017 12/5/2017 6 X

E011 Panel Boards & Breakers - Eaton 0 11/29/2017 12/5/2017 6 X


Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING

Document
Documents Transmittal [DT] - "E" Electrical
Updated 10/7/2018
Description Date to Date from Duration Status
DOC Trade Rev # Consult. Consult. D1 D2 APP ANN Resubmit Rejected

DT
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING

Document Documents Transmittal [DT] - "M"


Mechanical
Updated 10/7/2018
Description Date to Date from Duration Status
DOC Trade Rev # Consult. Consult. D1 D2 APP ANN Resubmit Rejected

DT
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING

Document
Shop Drawings Submittals [SDS] - "M" Mehcanical
Updated 10/7/2018
Description Date to Date from Duration Status
Rev
DOC Trade Dwg # Consult. Consult. D1 D2 APP ANN Resubmit Rejected
#

SDS M01 Underground Drainage Layout 0


M001 Underground Drainage Layout 0 10/19/2017 10/28/2017 9 X

M01 Underground Drainage Layout 1


M-401 6TH BASEMENT RAFT DRAINAGE LAYOUT 1 11/6/2017 11/9/2017 3 X
M-B01 BUILDER'S WORK 1 11/6/2017 11/9/2017 3 X

M02 Basement 6 Mechanical Layout 0


WS-01 SPEARS 1788-B6- WATER SUPPLY LAYOUT 0 12/6/2017 12/20/2017 14 X
VAC-01 SPEARS 1788-B6-HVAC LAYOUT 0 12/6/2017 12/20/2017 14 X
FF-01 SPEARS 1788-B6- FIRE FIGHTING LAYOUT 0 12/6/2017 12/20/2017 14 X
CO-01 SPEARS 1788-B6- COMPOSITE LAYOUT 0 12/6/2017 12/20/2017 14 X
DT-01 SPEARS 1788-B6- DETAIL LAYOUT 0 12/6/2017 12/20/2017 14 X

M02 Basement 6 Mechanical Layout 1


WS-01 SPEARS 1788-B6- WATER SUPPLY LAYOUT 1 1/5/2018 1/18/2018 13 X
VAC-01 SPEARS 1788-B6-HVAC LAYOUT 1 1/5/2018 1/18/2018 13 X
FF-01 SPEARS 1788-B6- FIRE FIGHTING LAYOUT 1 1/5/2018 1/18/2018 13 X
C0-01 SPEARS 1788-B6- COMPOSITE LAYOUT 1 1/5/2018 1/18/2018 13 X
EMC SPEARS 1788-B6- EM COMPOSITE 1 1/5/2018 1/18/2018 13 X
DR-02 SPEARS 1788-B6- HIGH LEVEL DRAINAGE 0 1/5/2018 1/18/2018 13 X
BW-02 SPEARS 1788-B6- BUILDER'S WORK 0 1/5/2018 1/18/2018 13 X

M03 Water Tank 0


WS-01 SPEARS 1788-B6- WATER TANK DETAIL 0 12/22/2017 12/29/2017 7 X

M03 Water Tank 1


WS-01 SPEARS 1788-B6- WATER TANK DETAIL 1 1/3/2018 1/9/2018 6 X

M03 Water Tank 2


WS-01 SPEARS 1788-B6- WATER TANK DETAIL 2 1/9/2018 1/11/2018 2 X

M04 Basement 5 Mechanical Layout 1


WS-02 SPEARS 1788-B5- WATER SUPPLY LAYOUT 1 1/17/2018 10/7/2018 263
VAC-02 SPEARS 1788-B5-HVAC LAYOUT 1 1/17/2018 10/7/2018 263
FF-02 SPEARS 1788-B5- FIRE FIGHTING LAYOUT 1 1/17/2018 10/7/2018 263
C0-02 SPEARS 1788-B5- COMPOSITE LAYOUT 1 1/17/2018 10/7/2018 263
EMC-02 SPEARS 1788-B5- EM COMPOSITE 1 1/17/2018 10/7/2018 263
DR-02 SPEARS 1788-B5- HIGH LEVEL DRAINAGE 0 1/17/2018 10/7/2018 263
BW-02 SPEARS 1788-B5- BUILDER'S WORK 0 1/17/2018 10/7/2018 263
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING

Document
Shop Drawings Submittals [SDS] - "E" Electrical
Updated 10/7/2018
Description Date to Date from Duration Status
Rev
DOC Trade Dwg # Consult. Consult. D1 D2 APP ANN Resubmit Rejected
#

SDS E01 Basement 6 Electrical drawings 0


EAC-01 Basement 6 Outlet Boxes for AC Layout 0 10/28/2017 11/9/2017 12 X
EL-01 Basement 6 Lighting Layout 0 10/28/2017 11/9/2017 12 X
EP-01 Basement 6 Power Layout 0 10/28/2017 11/9/2017 12 X
EX-01 Basement 6 Extra Low Voltage Layout 0 10/28/2017 11/9/2017 12 X
ECC-01 Basement 6 Ceiling Composite Layout 0 10/28/2017 11/9/2017 12 X
EWC-01 Basement 6 Wall Composite Layout 0 10/28/2017 11/9/2017 12 X
EEMC-01 Basement 6 Electro-Mechanical Composite Layout 0 10/28/2017 11/9/2017 12 X

E01 Basement 6 Electrical drawings 1


EP-01 Basement 6 Power Layout 1 12/8/2017 12/20/2017 12 X
EEMC-01 Basement 6 Electro-Mechanical Composite Layout 1 12/8/2017 12/20/2017 12 X

E02 Basement 5 Electro-Mechanical Composite Layout 0


EEMC-02 Basement 5 Electro-Mechanical Composite Layout 0 12/12/2017 12/20/2017 8 X

E02 Basement 5 Electrical drawings 0


EAC-02 Basement 5 Outlet Boxes for AC Layout 0 1/17/2018 10/7/2018 263
EL-02 Basement 5 Lighting Layout 0 1/17/2018 10/7/2018 263
EP-02 Basement 5 Power Layout 0 1/17/2018 10/7/2018 263
EX-02 Basement 5 Extra Low Voltage Layout 0 1/17/2018 10/7/2018 263
ECC-02 Basement 5 Ceiling Composite Layout 0 1/17/2018 10/7/2018 263
EWC-02 Basement 5 Wall Composite Layout 0 1/17/2018 10/7/2018 263
EEMC-02 Basement 5 Electro-Mechanical Composite Layout 0 1/17/2018 10/7/2018 263
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING
Document
REQUEST FOR INFORMATION [RFI] - "E"
ELECTRICAL
Updated
10/7/2018
DOC Description Rev. # Date to Date from Duration
Trade
Consult. Consult. D1 D2
RFI
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING
Document
REQUEST FOR INFORMATION [RFI] - "M"
MECHANICAL
Updated
10/7/2018
DOC Description Rev. # Date to Date from Duration
Trade
Consult. Consult. D1 D2
RFI
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING
Document
REQUEST FOR INSPECTION [FIR] - "E"
ELECTRICAL
Updated
10/7/2018
DOC Description Rev. # Date to Date from Duration
Trade
Consult. Consult. D1 D2
FIR
Project: SPEARS 88
Project Manager: TRUSTHOLD DEVELOPMENT GROUP
Consultant: ASYA ARCHITECTS
Contractor: NATCON ENGINEERING AND CONTRACTING
Document
REQUEST FOR INSPECTION [FIR] - "M"
MECHANICAL
Updated
10/7/2018
DOC Description Rev. # Date to Date from Duration
Trade
Consult. Consult. D1 D2

M01 Drainage & rain water pipes laid in raft at level 40.44 0 12/11/2017 12/11/2017 0
FIR

M02 Drainage & rain water pipes laid in raft at level 41.3 0 12/15/2017 12/15/2017 0

M03 Water Tank reservations and sleeves 0 1/22/2018 1/22/2018 0